ML031700220
ML031700220 | |
Person / Time | |
---|---|
Site: | Big Rock Point File:Consumers Energy icon.png |
Issue date: | 06/18/2003 |
From: | Chris Miller NRC/RGN-III |
To: | Haas K Consumers Energy |
References | |
-RFPFR IR-03-002 | |
Download: ML031700220 (12) | |
See also: IR 05000155/2003002
Text
June 18, 2003
Mr. Kurt M. Haas
General Manager
Big Rock Point Nuclear Plant
Consumers Energy Company
10269 US 31 North
Charlevoix, MI 49720
SUBJECT: BIG ROCK POINT INSPECTION REPORT 05000155/2003-002(DNMS) &
INSPECTION REPORT 07200043/2003-002(DNMS)
Dear Mr. Haas:
On May 19, 2003, the NRC completed an inspection at the Big Rock Point Nuclear Plant. The
purpose of the inspection was to determine whether decommissioning activities were conducted
safely and in accordance with NRC requirements. Specifically, the inspectors evaluated
decommissioning support activities, spent fuel safety and radiological safety. At the conclusion
of on-site inspections on March 20 and April 24, 2003, the inspectors discussed the inspection
findings with you and members of your staff. An additional telephone exit interview was
conducted on May 19, 2003, to discuss the results of the NRCs independent soil sample
analyses.
This inspection consisted of an examination of decommissioning activities at the Big Rock
Point Nuclear Plant as they relate to safety and compliance with the Commissions rules and
regulations. Areas examined during the inspection are identified in the enclosed report.
Within these areas, the inspection consisted of a selective examination of procedures and
representative records, observations of activities in progress, and interviews with personnel.
Based on the results of this inspection, the NRC did not identify any violations. The
decommissioning activities reviewed were being conducted in accordance with applicable
regulations and license conditions.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter
and its enclosure will be made available electronically for public inspection in the NRC Public
Document Room or from the NRCs document system (ADAMS), accessible from the NRC
Web site at http://www.nrc.gov/reading-rm/adams.html.
K. Haas -2-
We will gladly discuss any questions you may have regarding this inspection.
Sincerely,
/RA/
Christopher G. Miller
Decommissioning Branch
Docket Nos. 05000155; 07200043
License No. DPR-6
Enclosures: Inspection Report 05000155/2003-002(DNMS) &
Inspection Report 07200043/2003-002(DNMS)
cc w/encl: R. A. Fenech, Senior Vice President,
Nuclear, Fossil, and Hydro Operations
Richard Whale, Michigan Public Service Commission
L. Shekter Smith, Michigan Department of
Environmental Quality
Chief, Nuclear Facilities Unit, Michigan
Department of Environmental Quality
Department of Attorney General (MI)
Emergency Management Division,
Michigan Department of State Police
Distribution:
Reading File
PUBLIC IE-01 w/encls
RIII PRR w/encls
M. Masnik, NRR w/encls
J. Shepherd, LPM, NMSS (e-mail)
J. L. Caldwell, RIII w/encls
M. L. Dapas, RIII w/encls
RIII Enf. Coordinator w/encls
DOCUMENT NAME: C:\ORPCheckout\FileNET\ML031700220.wpd
To receive a copy of this document, indicate in the box:"C" = Copy without enclosure "E"= Copy with enclosure"N"= No copy
OFFICE RIII E RIII RIII RIII E
NAME Snell:js Lee Landsman Miller
DATE 05/29/03 05/21/03 05/21/03 06/18/03
OFFICIAL RECORD COPY
U.S. NUCLEAR REGULATORY COMMISSION
REGION III
Docket No. 05000155; 07200043
License No. DPR-06
Report Nos. 05000155/2003-002(DNMS) &
07200043/2003-002(DNMS)
Licensee: Consumers Energy Company
Facility: Big Rock Point Nuclear Plant
Location: 10269 U.S. 31 North
Charlevoix, MI 49720
Dates: March 17 - May 19, 2003
Inspector: William Snell, Health Physics Manager
Peter Lee, Ph.D., CHP, Radiation Specialist
Ross Landsman, Ph.D., Project Engineer
G. Pirtle, Physical Security Inspector
Approved by: Christopher G. Miller, Chief
Decommissioning Branch
Division of Nuclear Materials Safety
EXECUTIVE SUMMARY
Big Rock Point Restoration Project
NRC Inspection Report 05000155/2003-002(DNMS)
& Inspection Report 07200043/2003002(DNMS)
This routine decommissioning inspection involved review of the licensees performance related
to decommissioning support activities, spent fuel safety and radiological safety. During this
assessment period, the licensee completed placing spent fuel into dry storage casks and
moving the casks to the Independent Spent Fuel Storage Installation (ISFSI). In addition, a
canister of greater than class C waste was placed on the ISFSI, and all the fuel racks were
removed from the Spent Fuel Pool. Overall, the licensees major decommissioning activities
were properly monitored and controlled.
Decommissioning Support Activities
The inspectors determined that Revision 19 of the Defueled Security, Suitability,
Training, and Qualification Plan, submitted in accordance with 10 CFR 50.54(p) resulted
in no decrease in effectiveness to the security plan. (Section 1.1)
The licensee submitted Revision 38 to the Defueled Security Plan in accordance with
10 CFR 50.54(p). The security plan change does not relieve the licensee from
complying with applicable security advisories and orders issued by the NRC. The
inspectors determined that the changes to the Defueled Security Plan did not decrease
the effectiveness of the plan. (Section 1.2)
Spent Fuel Safety
Based on direct observations of the Horizontal Transfer System (HTS) test program and
reviews of the HTS procedures, the inspectors determined that the licensee personnel
could safely transfer a loaded canister between the transfer cask and a storage cask
without using the containment building crane. Procedures and administrative controls
had been established to ensure compliance with NRC requirements.
Radiological Safety
The inspectors determined that the licensees pre-demolition surface survey
program was capable of measuring the designed radiological survey criteria of
5000 disintegrations per minute per 100 square centimeters (dpm/100 cm2).
(Section 3.1)
The bulk material assay system was designed assuming a uniform spatial distribution of
contamination within a waste volume. In conjunction with the pre-demolition surface
survey program, the inspectors determined the system, as designed, will meet the
requirements of the licensees waste disposal criteria of 5 picocuries per gram.
(Section 3.2)
The licensees radioanalytical laboratory equipment, laboratory quality assurance
program, and analytical procedures were adequate. The program for laboratory
analyses was effectively implemented. (Section 3.3)
2
Licensee personnel performed soil surface scanning and sample collection at the site of
the Old Radwaste Building and its underground vault in accordance with the final status
survey program specified in the Big Rock Point Restoration Project License Termination
Plan (LTP), which the NRC has received for review and approval. Six of seven soil
samples sent to the Oak Ridge Institute for Science and Education (ORISE) for
independent analyses showed statistical agreement with the licensees results. The
ORISE personnel concluded that the statistical difference in the one sample was
probably due to a small particle of elevated activity in the sample. However, in all cases
the sample results were less than the Derived Concentration Guideline Levels (DCGLs).
(Section 3.4)
The inspectors did not identify any concerns regarding the licensees activities
associated with a radioactive waste shipment of contaminated concrete debris and a
spent fuel rack. (Section 3.5)
3
Report Details1
1.0 Decommissioning Support Activities
1.1 Safeguards Program Implementation (81700)
a. Inspection Scope
The inspectors reviewed Revision 19, dated October 8, 2002, to the Defueled Security
Suitability, Training, and Qualification Plan. The purpose of the review was to verify that
the change did not decrease the effectiveness of the security plan. The security plan
revision was submitted in accordance with 10 CFR 50.54(p).
b. Observations and Findings
The revision to the security plan was primarily administrative in nature and addressed
security measures for movement of spent fuel.
c. Conclusions
The inspectors determined that Revision 19 of the Defueled Security, Suitability,
Training, and Qualification Plan, submitted in accordance with 10 CFR 50.54(p) resulted
in no decrease in effectiveness to the security plan.
1.2 Safeguards Program Implementation (81700)
a. Inspection Scope
The inspector reviewed Revision 38, dated March 27, 2003, to the Defueled Security
Plan. The purpose of the review was to verify that the changes did not decrease the
effectiveness of the security plan.
b. Observations and Findings
The revision to the security plan was primarily administrative in nature and described
under what conditions the provisions of the defueled security plan would be applicable.
The revision also showed changes in the security management organizational structure
and reporting responsibilities.
c. Conclusions
The licensee submitted Revision 38 to the Defueled Security Plan in accordance with
10 CFR 50.54(p). The security plan change does not relieve the licensee from
complying with applicable security advisories and orders issued by the NRC. The
inspectors determined that the changes to the Defueled Security Plan did not decrease
the effectiveness of the plan.
1
A list of acronyms used in the report is included at the end of the Report Details.
4
2.0 Spent Fuel Safety
2.1 Operation of an Independent Spent Fuel Storage Installation (ISFSI) (60855)
a. Inspection Scope
The inspector observed various portions of the licensees test program for the Horizontal
Transfer System (HTS) to determine whether the licensee was capable of safely
transferring a loaded canister between the transfer cask and a storage cask located on
the ISFSI storage pad. Prior to allowing the licensee to remove the containment
building crane, a successful demonstration of the licensees capability to transfer the
canister without the use of the containment building crane was required. The test
program was examined to ensure that all conditions and requirements of the Certificate
of Compliance, the Safety Analysis Report, Technical Specifications, and 10 CFR Part
72 requirements were met.
b. Observations
The inspectors reviewed licensee procedures and observed the implementation of those
procedures, which tested the licensees capability to safely transfer a loaded canister
between the transfer cask and a storage cask. The procedures were well developed
and complete. The licensee held pre-job briefings prior to the implementation of each
segment of the procedure. These pre-job meetings were conducted in a professional
manner, and the necessary issues to enhance safety (such as the need for three way
communication, pre-staging of equipment, and teamwork among work parties) were
discussed.
The inspectors observed various portions of implementing the transfer procedures.
Licensee personnel exercised good safety practices during heavy lifts and completed
the lifts in accordance with procedures. The inspectors observed proper work coverage
by health physics and security personnel on the ISFSI storage pad during work
activities. The inspector observed good communication and teamwork between
licensee personnel from various work groups.
c. Conclusions
Based on direct observations of the HTS test program and reviews of the HTS
procedures, the inspectors determined that the licensee personnel could safely transfer
a loaded canister between the transfer cask and a storage cask without using the
containment building crane. Procedures and administrative controls had been
established to ensure compliance with NRC requirements.
3.0 Radiological Safety
3.1 Pre-demolition Surface Contamination Surveys (83750)
a. Inspection Scope
The inspectors reviewed the licensees pre-demolition surface survey program. The
review included an evaluation of analytical procedures and the survey instruments
capability to meet the specified pre-demolition minimum detectable activity criteria.
5
b. Observations and Findings
The inspectors interviewed the licensees health physics technical personnel and
observed calibration and sensitivity tests of the radiological survey instruments that will
be used to conduct the pre-demolition final surface surveys. Prior to demolition, the
surveys will verify that building surface contamination levels are less than 5000
disintegrations per minute per 100 square centimeters (dpm/100 cm2). Based on the
observed verification of the instruments capabilities, the inspectors determined the
survey instruments were accurate, and would meet the specified minimum detectable
activity criteria based on the planned counting times. Use of the instruments would
allow the licensee to measure the designed survey criteria of 5000 dpm/100 cm2.
c. Conclusions
The inspectors determined that the licensees pre-demolition surface survey program
was capable of measuring the designed radiological survey criteria of 5000 dpm/
100 cm2.
3.2 Bulk Material Assay (86750)
a. Inspection Scope
Inspectors evaluated the bulk material assay program and the technical basis for
design, calibration, and operation of the bulk assay radiation detection system, to
determine whether the system would meet the requirements of the licensees waste
disposal criteria of 5 picocuries per gram (5 pCi/g).
b. Observations and Findings
By cover letter dated February 5, 2002, and in accordance with the provisions of
10 CFR 20.2002, the NRC approved the licensees proposal to dispose of demolition
debris in a State of Michigan landfill. The licensees proposal contained a commitment
that all demolition debris would be monitored by a bulk assay radiation detection system
with an alarm setpoint established at or below a 5 picocuries per gram (5 pCi/g) limit
prior to disposal. The inspectors reviewed procedures and documents regarding the
design, calibration and operation of the bulk assay radiation detection system. The
monitoring facilities and equipment were inspected and observed in operation, and
personnel knowledgeable of the system were interviewed.
The bulk assay radiation detection system consisted of two side by side trailers spaced
just far enough apart for a truck to drive between them. The demolition debris (which
was primarily concrete) was deposited into a large roll-off type container, which was
positioned on the truck. The truck was driven between the trailers. A scale was located
between the trailers so each load could be weighed. Four high-purity germanium
detectors were located inside the trailers, and two sodium iodide plastic scintillation
detectors were located on the outside of the trailers. The dimensions of the roll-off
containers were 670 cm (length) x 229 cm (width) x 107 cm (height) [263 x 90 x 42
inches]. The container was assayed by positioning the roll-off container with two
detectors on each side of the container, and with each detector centered to measure a
quadrant of the container, 350 cm x 115 cm x 107 cm.
6
The inspectors found that the bulk material assay system is designed only for a uniform
spatial distribution of contamination within a waste volume. To ensure the bulk material
assay system functions as designed, additional steps will be required to ensure a
uniform spatial distribution of contamination exists within a waste volume prior to the
assay. The licensee will ensure that the concrete waste to be monitored by the bulk
monitoring system is uniform and less than the 5pCi/gram limit by performing extensive
surface contamination surveys of the concrete walls and exposed surfaces prior to the
concrete being turned into rubble.
c. Conclusions
The bulk material assay system was designed assuming a uniform spatial distribution of
contamination within a waste volume. In conjunction with the pre-demolition surface
survey program, the inspectors determined the system, as designed, will meet the
requirements of the licensees waste disposal criteria of 5 pCi/g.
3.3 Quality Assurance/Quality Control (QA/QC) of Radioanalytical Laboratory (83750)
a. Inspection Scope
The inspectors evaluated the radioanalytical laboratory, including the Quality Assurance
and Quality Control program and pertinent analytical procedures, to ensure that sample
analyses were being performed in an acceptable manner and that the results were
accurate. The inspectors also reviewed portions of the licensee's program for laboratory
analyses, interviewed laboratory personnel, and reviewed gamma spectrum analyses of
a selection of previously analyzed archived samples.
b. Observations and Findings
The laboratory was equipped with high purity germanium detectors for soil sample
analyses. The inspectors conducted independent calibration and quality control checks.
The analytical results of soil samples previously analyzed were accurate. The
inspectors reviewed the results of the licensees radiochemistry cross check program,
and found the results were in agreement with the comparison.
c. Conclusions
The licensees radioanalytical laboratory equipment, laboratory quality assurance
program, and analytical procedures were adequate. The program for laboratory
analyses was effectively implemented.
3.4 Soil Sampling at Site of Old Radwaste Building (83801)
a. Inspection Scope
Inspectors evaluated licensee surface surveys and soil sampling for the unrestricted
release of the site where the Old Radwaste Building was located.
7
b. Observations and Findings
The licensee completed the demolition of the Old Radwaste Building and underground
vault that was located within the building, and had removed all demolition debris from
the area. Soil that been removed from around the vault during its demolition was
spread out on the ground in a layer of one meter or less in depth. The licensee had
previously collected soil samples from within the hole where the vault had been located,
and was collecting additional samples of the spread out dirt during the inspection. The
inspectors observed the licensee performing surface scanning of the soil and collecting
soil samples in accordance with the final status survey program specified in the Big
Rock Point Restoration Project License Termination Plan (LTP), which the NRC had
received for review and approval. After observing the licensees surface scanning and
soil collection and archiving techniques, the inspectors determined that the licensees
techniques were acceptable. The inspectors conducted independent scanning of some
of the same areas as the licensee, and obtained similar results.
The NRC sent seven of the soil samples collected and analyzed by the licensee to the
Oak Ridge Institute for Science and Education (ORISE) for independent analyses. In all
cases but one, ORISE obtained results similar to those of the licensee. In sample #6,
the radiological activity of the Cs-137 values were not within statistical agreement.
Since the sample size used by ORISE to analyze the sample was smaller than the
sample size used by Big Rock Point, ORISE personnel counted the remaining sample
material, recombined the soil, took two samples from the recombined soil, and counted
them. In none of the cases were the analytical results statistically equivalent. ORISE
personnel concluded that the statistical difference was probably due to a small particle
of elevated activity in the sample. However, since the results were in all cases less than
the Derived Concentration Guideline Levels (DCGLs), no further review was pursued.
The results of the analyses are listed in the following table.
8
Soil Sample Survey Results
Radwaste Building Demolition
Data in picoCuries per gram (pCi/g)
NRC (ORISE) Big Rock Point
Sample #
1 0.02 0.09 <MDAa 0.09
2 0.09 0.04 0.06 <MDA
3 0.02 0.02 <MDA 0.06
4 0.02 0.51 <MDA 0.37
5 0.12 0.47 0.13 0.43
6 0.11 2.28 0.12 1.62
7 0.80 3.02 0.73 3.45
a
Less than the minimum detectable activity (MDA).
c. Conclusions
Licensee personnel performed soil surface scanning and sample collection at the site of
the Old Radwaste Building and its underground vault in accordance with the final status
survey program specified in the Big Rock Point Restoration Project License Termination
Plan (LTP), which the NRC has received for review and approval. Six of seven soil
samples sent to the Oak Ridge Institute for Science and Education (ORISE) for
independent analyses showed statistical agreement with the licensees results. The
ORISE personnel concluded that the statistical difference in the one sample was
probably due to a small particle of elevated activity in the sample. However, in all cases
the sample results were less than the Derived Concentration Guideline Levels (DCGLs).
3.5 Transportation (86750)
a. Inspection Scope
The inspectors reviewed the licensees activities regarding a radioactive waste
shipment.
b. Observations and Findings
The inspectors observed activities and reviewed transportation documents associated
with a shipment of radioactive waste to GTS Duretek facilities in Tennessee. The
shipment contained a spent fuel rack in a sea-land container and contaminated concrete
debris in three B25 boxes. After reviewing all shipping documents and survey data from
the four containers and truck, the inspectors determined that the documents were
completed as required. The licensee informed the driver of who was to be notified in the
event of an incident, and the driver signed to indicate that he had examined the truck
and containers prior to departure. The inspectors did not identify any problems with the
shipment.
9
c. Conclusions
The inspectors did not identify any concerns regarding the licensees activities
associated with a radioactive waste shipment of contaminated concrete debris and a
spent fuel rack.
4.0 Exit Meetings
The inspectors presented preliminary inspection results to members of licensee management at
the conclusion of onsite inspections on March 20 and April 24, 2003, and in a telephone
discussion on May 19, 2003. The licensee acknowledged the findings presented. The licensee
did not identify any documents or processes reviewed by the inspectors as proprietary.
PARTIAL LIST OF PERSONS CONTACTED
Licensee
K. Haas, Plant General Manager
K. Pallagi, Radiation Protection & Environmental Services Manager
W. Trubilowicz, Dry Fuel Storage Manager
G. Withrow, Engineering, Operations & Licensing Manager
T. Petrosky, Public Relations
INSPECTION PROCEDURES USED
IP 60855 Operation of an Independent Spent Fuel Storage Installation
IP 81700 Safeguards Program Implementation
IP 83750 Occupational Radiation Exposure
IP 83801 Inspection of Final Surveys
IP 86750 Solid Radioactive Waste Management and Transportation
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened None
Closed None
Discussed None
LIST OF ACRONYMS USED
ALARA As-Low-As-Reasonably-Achievable
BRP Big Rock Point
DCGL Derived Concentration Guideline Levels
HTS Horizontal Transfer System
ISFSI Independent Spent Fuel Storage Installation
LTP License Termination Plan
MDA Minimum Detectable Activity
NRC Nuclear Regulatory Commission
ORISE Oak Ridge Institute for Science and Education
QA Quality Assurance
QC Quality Control
RP Radiation Protection
10
LICENSEE DOCUMENTS REVIEWED
Licensee documents reviewed and utilized during the course of this inspection are specifically
identified in the Report Details above.
11