| title = IR 05000313-09-007, IR 05000368-09-007, for Arkansas One-Initial Information Request for NRC Triennial Baseline Component Design Bases Inspection
| title = IR 05000313-09-007, IR 05000368-09-007, for Arkansas One-Initial Information Request for NRC Triennial Baseline Component Design Bases Inspection
| author name = Farnholtz T R
| author name = Farnholtz T
| author affiliation = NRC/RGN-IV/DRS/EB-1
| author affiliation = NRC/RGN-IV/DRS/EB-1
| addressee name = Walsh K
| addressee name = Walsh K
Line 14: Line 14:
| page count = 9
| page count = 9
}}
}}
See also: [[followed by::IR 05000313/2009007]]
See also: [[see also::IR 05000313/2009007]]


=Text=
=Text=
{{#Wiki_filter:April 16, 2009  
{{#Wiki_filter:UNITED S TATE S
  Kevin Walsh, Vice President, Operations  
                                  N UCLE AR REGU LATORY COMMI SS ION
Entergy Operations, Inc. Arkansas Nuclear One 1448 S.R. 333 Russellville, AR 72802  
                                                    R E GI ON I V
                                          6 1 2 E. LAMAR BLVD. , SU ITE 4 00
SUBJECT: ARKANSAS NUCLEAR ONE - INITIAL INFORMATION REQUEST FOR NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION NRC INSPECTION REPORT 05000316; 05000368/2009007  
                                        AR LIN GTON , TEXAS 7 6 01 1- 4005
Dear Mr. Mitchell:  
                                              April 16, 2009
On June 15, 2009, the NRC will begin a triennial baseline Component Design Bases Inspection  
Kevin Walsh, Vice President, Operations
at the Arkansas Nuclear One. A six-person team will perform this inspection using NRC Inspection Procedure 71111.21, "Component Design Bases Inspection."
Entergy Operations, Inc.
The inspection focuses on components and operator actions that have high risk and low design margins. The samples reviewed during this inspection will be identified during an information  
Arkansas Nuclear One
gathering visit and during the subsequent in-office preparation week. In addition, a number of operating experience issues will also be selected for review.
1448 S.R. 333
The inspection will include an information gathering site visit by the team leader and a senior reactor analyst, and 3-weeks of onsite inspection by the team. The inspection will consist of  
Russellville, AR 72802
four NRC inspectors and two contractors, of which five will focus on engineering and one on operations. The current inspection schedule is as follows:  
SUBJECT:       ARKANSAS NUCLEAR ONE - INITIAL INFORMATION REQUEST FOR NRC
Onsite information gathering visit: Week of June 15, 2009 Preparation Week: June 29, 2009  
                TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION NRC
Onsite weeks: July 6 and July 20 thru July 31, 2009  
                INSPECTION REPORT 05000316; 05000368/2009007
The purpose of the information gathering visit is to meet with members of your staff to identify potential risk-significant components and operator actions. The lead inspector will also request a tour of the plant with members of your operations staff and probabilistic safety assessment  
Dear Mr. Mitchell:
staff. During the onsite weeks, several days of time will be needed on the plant-referenced simulator in order to facilitate the development of operator action-based scenarios. Additional information and documentation needed to support the inspection will be identified during the inspection, including interviews with engineering managers, engineers, and probabilistic safety assessment staff.
On June 15, 2009, the NRC will begin a triennial baseline Component Design Bases Inspection
UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 E. LAMAR BLVD., SUITE 400ARLINGTON, TEXAS 76011-4005
at the Arkansas Nuclear One. A six-person team will perform this inspection using NRC
Entergy Operations, Inc. - 2 -
Inspection Procedure 71111.21, Component Design Bases Inspection.
Our experience with these inspections has shown that they are extremely resource intensive, both for the NRC inspectors and the licensee staff.  In order to minimize the inspection impact on the site and to ensure a productive inspection, we have enclosed a request for information needed for the inspection.  The request has been divided into
The inspection focuses on components and operator actions that have high risk and low design
three groups.  The first group lists information necessary for the information gathering visit and for general preparation.  This information should be available to the regional office no later than May 26, 2009.  Insofar as possible, this information should be provided electronically to the lead inspector.  Since the inspection will be concentrated on high risk/low margin components, calculations associated with your list of high risk
margins. The samples reviewed during this inspection will be identified during an information
components should be available to review during the information gathering visit to assist in our selection of components based on available design margin. 
gathering visit and during the subsequent in-office preparation week. In addition, a number of
The second group of documents requested is those items that the team will need access to during the preparation week in order to finalize the samples to be inspected.  The third group lists information necessary to aid the inspection team in tracking issues identified as a result of the inspection.  It is requested that this information be provided to the lead
operating experience issues will also be selected for review.
inspector as the information is generated during the inspection.  Additional requests by inspectors will be made throughout all three onsite weeks for specific documents needed to complete the review of that component/selection.  It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. 
The inspection will include an information gathering site visit by the team leader and a senior
In order to facilitate the inspection, we request that a contact individual be assigned to each inspector to ensure information requests, questions, and concerns are addressed in a timely manner. 
reactor analyst, and 3-weeks of onsite inspection by the team. The inspection will consist of
The lead inspector for this inspection is Wayne Sifre.  We understand that our licensing
four NRC inspectors and two contractors, of which five will focus on engineering and one on
engineer contact for this inspection is Dick Scheide.  If there are any questions about the inspection or the requested materials, please contact the lead inspector at (817) 860-8193 or via e-mail at Wayne.Sifre@nrc.gov .  In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter
operations. The current inspection schedule is as follows:
will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
        Onsite information gathering visit: Week of June 15, 2009
        Preparation Week: June 29, 2009
      Sincerely,        /RA/  Thomas Farnholtz, Chief      Engineering Branch 1 Division of Reactor Safety
        Onsite weeks: July 6 and July 20 thru July 31, 2009
Dockets:  50-313; 50-368 Licenses:  DPR-51; NPF-6
The purpose of the information gathering visit is to meet with members of your staff to identify
Enclosure: 
potential risk-significant components and operator actions. The lead inspector will also request
Component Design Basis Inspection  Document Request 
a tour of the plant with members of your operations staff and probabilistic safety assessment
Entergy Operations, Inc. - 3 -
staff. During the onsite weeks, several days of time will be needed on the plant-referenced
  cc w/enclosure:
simulator in order to facilitate the development of operator action-based scenarios. Additional
Senior Vice President Entergy Operations, Inc. P.O. Box 31995
information and documentation needed to support the inspection will be identified during the
Jackson, MS  39286-1995
inspection, including interviews with engineering managers, engineers, and probabilistic safety
Senior Vice President  & Chief Operating Officer Entergy Operations, Inc.
assessment staff.
P.O. Box 31995 Jackson, MS  39286-1995
Vice President, Oversight Entergy Operations, Inc. P.O. Box 31995 Jackson, MS  39286-1995


Manager, Licensing Entergy Operations, Inc. Arkansas Nuclear One 1448 SR 333
Entergy Operations, Inc.                     -2-
Russellville, AR  72802
Our experience with these inspections has shown that they are extremely resource
Associate General Counsel Entergy Nuclear Operations P.O. Box 31995
intensive, both for the NRC inspectors and the licensee staff. In order to minimize the
Jackson, MS  39286-1995
inspection impact on the site and to ensure a productive inspection, we have enclosed a
Senior Manager, Nuclear Safety & Licensing Entergy Operations, Inc. P.O. Box 31995
request for information needed for the inspection. The request has been divided into
Jackson, MS  39286-1995
three groups. The first group lists information necessary for the information gathering
Chief, Radiation Control Section Arkansas Department of Health 4815 West Markham Street, Slot 30
visit and for general preparation. This information should be available to the regional
Little Rock, AR  72205-3867
office no later than May 26, 2009. Insofar as possible, this information should be
Section Chief, Division of Health Emergency Management Section Arkansas Department of Health 4815 West Markham Street, Slot 30 Little Rock, AR  72205-3867
provided electronically to the lead inspector. Since the inspection will be concentrated
on high risk/low margin components, calculations associated with your list of high risk
components should be available to review during the information gathering visit to assist
in our selection of components based on available design margin.
The second group of documents requested is those items that the team will need access
to during the preparation week in order to finalize the samples to be inspected. The third
group lists information necessary to aid the inspection team in tracking issues identified
as a result of the inspection. It is requested that this information be provided to the lead
inspector as the information is generated during the inspection. Additional requests by
inspectors will be made throughout all three onsite weeks for specific documents needed
to complete the review of that component/selection. It is important that all of these
documents are up to date and complete in order to minimize the number of additional
documents requested during the preparation and/or the onsite portions of the inspection.
In order to facilitate the inspection, we request that a contact individual be assigned to
each inspector to ensure information requests, questions, and concerns are addressed
in a timely manner.
The lead inspector for this inspection is Wayne Sifre. We understand that our licensing
engineer contact for this inspection is Dick Scheide. If there are any questions about
the inspection or the requested materials, please contact the lead inspector at (817) 860-
8193 or via e-mail at Wayne.Sifre@nrc.gov .
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter
will be made available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document
system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
                                              Sincerely,
                                              /RA/
                                              Thomas Farnholtz, Chief
                                              Engineering Branch 1
                                              Division of Reactor Safety
Dockets: 50-313; 50-368
Licenses: DPR-51; NPF-6
Enclosure:
Component Design Basis Inspection
Document Request


David E. Maxwell, Director Arkansas Department of Emergency  Management, Bldg. 9501 Camp Joseph T. Robinson
Entergy Operations, Inc.               -3-
North Little Rock, AR 72199
cc w/enclosure:
 
Senior Vice President
Entergy Operations, Inc. - 4 -  
Entergy Operations, Inc.
  Pope County Judge
P.O. Box 31995
Pope County Courthouse 100 West Main Street Russellville, AR  72801 
Jackson, MS 39286-1995
Entergy Operations, Inc. - 5 -
Senior Vice President
  Electronic distribution by RIV:
& Chief Operating Officer
Regional Administrator (Elmo.Collins@nrc.gov ) Deputy Regional Administrator (Chuck.Casto@nrc.gov ) DRP Director (Dwight.Chamberlain@nrc.gov) DRP Deputy Director (Anton.Vegel@nrc.gov ) DRS Director (Roy.Caniano@nrc.gov ) DRS Deputy Director (Troy.Pruett@nrc.gov ) Senior Resident Inspector (Alfred.Sanchez@nrc.gov) Resident Inspector (Jeffrey.Josey@nrc.gov ) Branch Chief, DRP/E (Jeff.Clark@nrc.gov ) Senior Project Engineer, DRP/E (George.Replogle@nrc.gov) ANO Site Secretary (Vicki.High@nrc.gov ) Public Affairs Officer (Victor.Dricks@nrc.gov ) Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov ) RITS Coordinator (Marisa.Herrera@nrc.gov ) OEMail Resource
Entergy Operations, Inc.
Senior Enforcement Specialist (Mark.Haire@nrc.gov )   
P.O. Box 31995
   
Jackson, MS 39286-1995
   
Vice President, Oversight
   
Entergy Operations, Inc.
File located: R:REACTORS\ANO RFI - WCS    ML091060654  SUNSI Rev Compl.  Yes  No ADAMS  Yes  No Reviewer Initials WCS Publicly Avail  Yes  No Sensitive  Yes  No Sens. Type Initials  WCS EB 1    C:EB 1 W. Sifre    T. Farnholtz /RA/    /RA/ 4/15/09    4/16/09 OFFICIAL RECORD COPY  T=Telephone          E=E-mail        F=Fax
P.O. Box 31995
 
Jackson, MS 39286-1995
  - 1 - Enclosure  INFORMATION REQUEST FOR ARKANSAS NUCLEAR ONE COMPONENT DESIGN BASES (CDBI) INSPECTION
Manager, Licensing
    Inspection Report:    05000313; 05000368/2009007
Entergy Operations, Inc.
Information Gathering Dates: June 16-18, 2009
Arkansas Nuclear One
On-site Inspection Dates:  July 6-10 and July 20-31, 2009 Inspection Procedure:  IP 71111.21, "Component Design Bases Inspection"
1448 SR 333
Lead Inspector/Team Leader: Wayne C. Sifre      817-860-8193      Wayne.Sifre@nrc.gov
Russellville, AR 72802
 
Associate General Counsel
I. Information Requested Prior to the information Gathering Visit (June 16-18, 2009)  The following information (Section I of this enclosure) should be sent to the Region IV office in hard copy or electronic format (ims.certrec.com preferred), in
Entergy Nuclear Operations
care of Wayne C. Sifre, by May 26,2009 to facilitate the reduction in the items to be selected for a final list during the preparation week June 29, 2009. The inspection team will finalize the selected list during the prep week using the additional documents requested in Section II of this enclosure. The specific items selected from the lists shall be available and ready for review on the day
P.O. Box 31995
indicated in this request. *Please provide requested documentation electronically in "pdf" files, Excel, or other searchable formats, if possible. The information should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use.  Information in "lists" should contain enough information to be easily understood by someone who has knowledge of pressurized water reactor
Jackson, MS 39286-1995
technology.  If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection. 
Senior Manager, Nuclear Safety & Licensing
 
Entergy Operations, Inc.
1. An excel spreadsheet of equipment basic events (with definitions) including importance measures sorted by risk achievement worth (RAW) and Fussell-Vesely (FV) from your internal events probabilistic risk assessment (PRA). Include basic events with RAW value of 1.3 or greater. 
P.O. Box 31995
2. Provide a list of the top 500 cut-sets from your PRA. 
Jackson, MS 39286-1995
  3. Copies of PRA "system notebooks," and the latest PRA summary document.
Chief, Radiation Control Section
 
Arkansas Department of Health
  4. An excel spreadsheet of PRA human action basic events or risk ranking of operator actions from your site specific PSA sorted by RAW and FV.  Provide copies of your human reliability worksheets for these items. 
4815 West Markham Street, Slot 30
  5. If you have an external events or fire PSA model, provide the information requested in items 1-4 for external events and fire.
Little Rock, AR 72205-3867
  6.  Any pre-existing evaluation or list of components and associated calculations with low design margins, (i.e., pumps closest to the design limit for flow or pressure, diesel generator close to design required output, heat exchangers close to rated design heat removal, etc.).
Section Chief, Division of Health
  7. List of high risk maintenance rule systems/components and functions; based on engineering or expert panel judgment.  
Emergency Management Section
  8. A list of operating experience evaluations for the last 2 years. 
Arkansas Department of Health
  9.  A list of all time-critical operator actions in procedures.
4815 West Markham Street, Slot 30
Little Rock, AR 72205-3867
David E. Maxwell, Director
Arkansas Department of Emergency
  Management, Bldg. 9501
Camp Joseph T. Robinson
North Little Rock, AR 72199


  10. A list of permanent and temporary modifications sorted by component identified in Item 1. 
Entergy Operations, Inc. -4-
  11.  List of current "operator work arounds/burdens."
Pope County Judge
Pope County Courthouse
100 West Main Street
Russellville, AR 72801


  12. A list of the design calculations, which provide the design margin information for components included in Item 1. (Calculations should be available during the information gathering visit).
Entergy Operations, Inc.                  -5-
Electronic distribution by RIV:
13. List of root cause evaluations associated with component failures or design issues initiated/completed in the last 5 years.
Regional Administrator (Elmo.Collins@nrc.gov )
  14.   Current management and engineering organizational charts.
Deputy Regional Administrator (Chuck.Casto@nrc.gov )
DRP Director (Dwight.Chamberlain@nrc.gov)
15. Arkansas Nuclear One  IPEEE, if available electronically.  
DRP Deputy Director (Anton.Vegel@nrc.gov )
  16. Mechanical piping drawings for:  
DRS Director (Roy.Caniano@nrc.gov )
  Engineered safety features
DRS Deputy Director (Troy.Pruett@nrc.gov )
   Emergency core cooling systems   Emergency diesel generators
Senior Resident Inspector (Alfred.Sanchez@nrc.gov)
  17 Electrical one-line drawings for:  
Resident Inspector (Jeffrey.Josey@nrc.gov )
    Offsite power/switchyard supplies  Normal AC power systems  Emergency AC/DC power systems including    120VAC power, and    125VDC/24VDC safety class systems
Branch Chief, DRP/E (Jeff.Clark@nrc.gov )
Senior Project Engineer, DRP/E (George.Replogle@nrc.gov)
ANO Site Secretary (Vicki.High@nrc.gov )
Public Affairs Officer (Victor.Dricks@nrc.gov )
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov )
RITS Coordinator (Marisa.Herrera@nrc.gov )
OEMail Resource
Senior Enforcement Specialist (Mark.Haire@nrc.gov )
File located: R:REACTORS\ANO RFI - WCS                        ML091060654
SUNSI Rev Compl. ; Yes No              ADAMS    ; Yes  No  Reviewer          WCS
                                                                Initials
Publicly Avail          ; Yes      No  Sensitive   Yes ; No   Sens. Type        WCS
                                                                Initials
EB 1                                                                    C:EB 1
W. Sifre                                                                T. Farnholtz
/RA/                                                                    /RA/
4/15/09                                                                    4/16/09
OFFICIAL RECORD COPY                                T=Telephone        E=E-mail    F=Fax


  18. List of any common-cause failures of components in the last 3 years.  
INFORMATION REQUEST FOR ARKANSAS NUCLEAR ONE COMPONENT DESIGN
 
                                BASES (CDBI) INSPECTION
  19. An electronic copy of the Design Bases Documents.  
Inspection Report:                      05000313; 05000368/2009007
20. An electronic copy of the System Health notebooks.  
Information Gathering Dates:            June 16-18, 2009
  II.   Information Requested to be Available on First Day of Preparation Week (June 29, 2009)
On-site Inspection Dates:              July 6-10 and July 20-31, 2009
  1. List of condition reports (corrective action documents) associated with each of the selected components for the last 5 years.  
Inspection Procedure:                  IP 71111.21, Component Design Bases
                                        Inspection
2. The corrective maintenance history associated with each of the selected components for the last 2 years.
Lead Inspector/Team Leader:            Wayne C. Sifre
  3. Copies of calculations associated with each of the selected components (if not previously provided), excluding data files. Please review the calculations and also provide copies of reference material (such as drawings, engineering requests, and vendor letters).  
                                        817-860-8193
  4. Copies of operability evaluations associated with each of the selected components and plans for restoring operability, if applicable.
                                        Wayne.Sifre@nrc.gov
  5. Copies of selected operator work-around evaluations associated with each of the selected components and plans for resolution, if applicable.  
I.    Information Requested Prior to the information Gathering Visit (June 16-18,
  6. Copies of any open temporary modifications associated with each of the selected components, if applicable.  
      2009)
      The following information (Section I of this enclosure) should be sent to the
7. Trend data on the selected electrical/mechanical components' performance for last 3 years (for example, pumps' performance including in-service testing, other vibration monitoring, oil sample results, etc., as applicable).  
      Region IV office in hard copy or electronic format (ims.certrec.com preferred), in
      care of Wayne C. Sifre, by May 26,2009 to facilitate the reduction in the items to
8. A copy of any internal/external self-assessments and associated corrective action documents generated in preparation for the inspection.
      be selected for a final list during the preparation week June 29, 2009. The
  9. A copy of engineering/operations related audits completed in the last 2 years.   10. List of motor operated valves (MOVs) in the program, design margin and risk ranking.  
      inspection team will finalize the selected list during the prep week using the
  11. List of air operated valves (AOVs) in the valve program, design and risk ranking.
      additional documents requested in Section II of this enclosure. The specific items
12. Structure, system and components in the Maintenance Rule (a)(1) category.  
      selected from the lists shall be available and ready for review on the day
  13. Site top 10 issues list.  
      indicated in this request. *Please provide requested documentation electronically
 
      in pdf files, Excel, or other searchable formats, if possible. The information
  14. Procedures used to accomplish operator actions associated with the basic events in your PRA.  
      should contain descriptive names, and be indexed and hyperlinked to facilitate
  15. List of licensee contacts for the inspection team with pager or phone numbers.
      ease of use. Information in "lists" should contain enough information to be easily
III. Information Requested to be provided throughout the inspection.
      understood by someone who has knowledge of pressurized water reactor
  1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection.  
      technology. If requested documents are large and only hard copy formats are
  2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member).  
      available, please inform the inspector(s), and provide subject documentation
  3. Reference materials (available electronically and as needed during all onsite weeks):  
      during the first day of the onsite inspection.
  General set of plant drawings   IPE/PRA report   Procurement documents for components selected   Plant procedures (normal, abnormal, emergency, surveillance, etc.)  
      1.      An excel spreadsheet of equipment basic events (with definitions)
  Technical Specifications   Updated Final Safety Analysis Report   Vendor manuals  
                including importance measures sorted by risk achievement worth (RAW)
 
                and Fussell-Vesely (FV) from your internal events probabilistic risk
Inspector Contact Information
                assessment (PRA). Include basic events with RAW value of 1.3 or
Wayne C. Sifre Senior Reactor Inspector (817) 860-8193  
                greater.
      2.      Provide a list of the top 500 cut-sets from your PRA.
      3.      Copies of PRA system notebooks, and the latest PRA summary
                document.
                                              -1-                                Enclosure
 
4. An excel spreadsheet of PRA human action basic events or risk ranking
    of operator actions from your site specific PSA sorted by RAW and FV.
    Provide copies of your human reliability worksheets for these items.
5.  If you have an external events or fire PSA model, provide the information
    requested in items 1-4 for external events and fire.
6.  Any pre-existing evaluation or list of components and associated
    calculations with low design margins, (i.e., pumps closest to the design
    limit for flow or pressure, diesel generator close to design required output,
    heat exchangers close to rated design heat removal, etc.).
7.  List of high risk maintenance rule systems/components and functions;
    based on engineering or expert panel judgment.
8.  A list of operating experience evaluations for the last 2 years.
9.  A list of all time-critical operator actions in procedures.
10. A list of permanent and temporary modifications sorted by component
    identified in Item 1.
11. List of current operator work arounds/burdens.
12. A list of the design calculations, which provide the design margin
    information for components included in Item 1. (Calculations should be
    available during the information gathering visit).
13. List of root cause evaluations associated with component failures or
    design issues initiated/completed in the last 5 years.
14. Current management and engineering organizational charts.
15. Arkansas Nuclear One IPEEE, if available electronically.
16. Mechanical piping drawings for:
            Engineered safety features
            Emergency core cooling systems
            Emergency diesel generators
17  Electrical one-line drawings for:
            Offsite power/switchyard supplies
            Normal AC power systems
            Emergency AC/DC power systems including
            120VAC power, and
            125VDC/24VDC safety class systems
18. List of any common-cause failures of components in the last 3 years.
 
    19.   An electronic copy of the Design Bases Documents.
    20.   An electronic copy of the System Health notebooks.
II. Information Requested to be Available on First Day of Preparation Week
    (June 29, 2009)
    1.     List of condition reports (corrective action documents) associated with
          each of the selected components for the last 5 years.
    2.     The corrective maintenance history associated with each of the selected
          components for the last 2 years.
    3.     Copies of calculations associated with each of the selected components
          (if not previously provided), excluding data files. Please review the
          calculations and also provide copies of reference material (such as
          drawings, engineering requests, and vendor letters).
    4.     Copies of operability evaluations associated with each of the selected
          components and plans for restoring operability, if applicable.
    5.     Copies of selected operator work-around evaluations associated with
          each of the selected components and plans for resolution, if applicable.
    6.     Copies of any open temporary modifications associated with each of the
          selected components, if applicable.
    7.     Trend data on the selected electrical/mechanical components
          performance for last 3 years (for example, pumps performance including
          in-service testing, other vibration monitoring, oil sample results, etc., as
          applicable).
    8.     A copy of any internal/external self-assessments and associated
          corrective action documents generated in preparation for the inspection.
    9.     A copy of engineering/operations related audits completed in the last 2
          years.
    10.   List of motor operated valves (MOVs) in the program, design margin and
          risk ranking.
    11.   List of air operated valves (AOVs) in the valve program, design and risk
          ranking.
    12.   Structure, system and components in the Maintenance Rule (a)(1)
          category.
    13.   Site top 10 issues list.
 
        14.   Procedures used to accomplish operator actions associated with the
              basic events in your PRA.
        15.   List of licensee contacts for the inspection team with pager or phone
              numbers.
III.   Information Requested to be provided throughout the inspection.
        1.     Copies of any corrective action documents generated as a result of the
              teams questions or queries during this inspection.
        2.     Copies of the list of questions submitted by the team members and the
              status/resolution of the information requested (provide daily during the
              inspection to each team member).
        3.     Reference materials (available electronically and as needed during all
              onsite weeks):
              General set of plant drawings
              IPE/PRA report
              Procurement documents for components selected
              Plant procedures (normal, abnormal, emergency, surveillance, etc.)
              Technical Specifications
              Updated Final Safety Analysis Report
              Vendor manuals
Inspector Contact Information:
Wayne C. Sifre
Senior Reactor Inspector
(817) 860-8193
Wayne.Sifre@nrc.gov
Wayne.Sifre@nrc.gov
  Mailing Address
Mailing Address:
: US NRC, Region IV Attn: Wayne C. Sifre  
US NRC, Region IV
612 East Lamar Blvd, Ste 400 Arlington, TX 76011
Attn: Wayne C. Sifre
612 East Lamar Blvd, Ste 400
Arlington, TX 76011
}}
}}

Latest revision as of 08:04, 14 November 2019

IR 05000313-09-007, IR 05000368-09-007, for Arkansas One-Initial Information Request for NRC Triennial Baseline Component Design Bases Inspection
ML091060654
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 04/16/2009
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Walsh K
Entergy Operations
References
IR-09-007
Download: ML091060654 (9)


See also: IR 05000313/2009007

Text

UNITED S TATE S

N UCLE AR REGU LATORY COMMI SS ION

R E GI ON I V

6 1 2 E. LAMAR BLVD. , SU ITE 4 00

AR LIN GTON , TEXAS 7 6 01 1- 4005

April 16, 2009

Kevin Walsh, Vice President, Operations

Entergy Operations, Inc.

Arkansas Nuclear One

1448 S.R. 333

Russellville, AR 72802

SUBJECT: ARKANSAS NUCLEAR ONE - INITIAL INFORMATION REQUEST FOR NRC

TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION NRC

INSPECTION REPORT 05000316; 05000368/2009007

Dear Mr. Mitchell:

On June 15, 2009, the NRC will begin a triennial baseline Component Design Bases Inspection

at the Arkansas Nuclear One. A six-person team will perform this inspection using NRC

Inspection Procedure 71111.21, Component Design Bases Inspection.

The inspection focuses on components and operator actions that have high risk and low design

margins. The samples reviewed during this inspection will be identified during an information

gathering visit and during the subsequent in-office preparation week. In addition, a number of

operating experience issues will also be selected for review.

The inspection will include an information gathering site visit by the team leader and a senior

reactor analyst, and 3-weeks of onsite inspection by the team. The inspection will consist of

four NRC inspectors and two contractors, of which five will focus on engineering and one on

operations. The current inspection schedule is as follows:

Onsite information gathering visit: Week of June 15, 2009

Preparation Week: June 29, 2009

Onsite weeks: July 6 and July 20 thru July 31, 2009

The purpose of the information gathering visit is to meet with members of your staff to identify

potential risk-significant components and operator actions. The lead inspector will also request

a tour of the plant with members of your operations staff and probabilistic safety assessment

staff. During the onsite weeks, several days of time will be needed on the plant-referenced

simulator in order to facilitate the development of operator action-based scenarios. Additional

information and documentation needed to support the inspection will be identified during the

inspection, including interviews with engineering managers, engineers, and probabilistic safety

assessment staff.

Entergy Operations, Inc. -2-

Our experience with these inspections has shown that they are extremely resource

intensive, both for the NRC inspectors and the licensee staff. In order to minimize the

inspection impact on the site and to ensure a productive inspection, we have enclosed a

request for information needed for the inspection. The request has been divided into

three groups. The first group lists information necessary for the information gathering

visit and for general preparation. This information should be available to the regional

office no later than May 26, 2009. Insofar as possible, this information should be

provided electronically to the lead inspector. Since the inspection will be concentrated

on high risk/low margin components, calculations associated with your list of high risk

components should be available to review during the information gathering visit to assist

in our selection of components based on available design margin.

The second group of documents requested is those items that the team will need access

to during the preparation week in order to finalize the samples to be inspected. The third

group lists information necessary to aid the inspection team in tracking issues identified

as a result of the inspection. It is requested that this information be provided to the lead

inspector as the information is generated during the inspection. Additional requests by

inspectors will be made throughout all three onsite weeks for specific documents needed

to complete the review of that component/selection. It is important that all of these

documents are up to date and complete in order to minimize the number of additional

documents requested during the preparation and/or the onsite portions of the inspection.

In order to facilitate the inspection, we request that a contact individual be assigned to

each inspector to ensure information requests, questions, and concerns are addressed

in a timely manner.

The lead inspector for this inspection is Wayne Sifre. We understand that our licensing

engineer contact for this inspection is Dick Scheide. If there are any questions about

the inspection or the requested materials, please contact the lead inspector at (817) 860-

8193 or via e-mail at Wayne.Sifre@nrc.gov .

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter

will be made available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document

system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Dockets: 50-313; 50-368

Licenses: DPR-51; NPF-6

Enclosure:

Component Design Basis Inspection

Document Request

Entergy Operations, Inc. -3-

cc w/enclosure:

Senior Vice President

Entergy Operations, Inc.

P.O. Box 31995

Jackson, MS 39286-1995

Senior Vice President

& Chief Operating Officer

Entergy Operations, Inc.

P.O. Box 31995

Jackson, MS 39286-1995

Vice President, Oversight

Entergy Operations, Inc.

P.O. Box 31995

Jackson, MS 39286-1995

Manager, Licensing

Entergy Operations, Inc.

Arkansas Nuclear One

1448 SR 333

Russellville, AR 72802

Associate General Counsel

Entergy Nuclear Operations

P.O. Box 31995

Jackson, MS 39286-1995

Senior Manager, Nuclear Safety & Licensing

Entergy Operations, Inc.

P.O. Box 31995

Jackson, MS 39286-1995

Chief, Radiation Control Section

Arkansas Department of Health

4815 West Markham Street, Slot 30

Little Rock, AR 72205-3867

Section Chief, Division of Health

Emergency Management Section

Arkansas Department of Health

4815 West Markham Street, Slot 30

Little Rock, AR 72205-3867

David E. Maxwell, Director

Arkansas Department of Emergency

Management, Bldg. 9501

Camp Joseph T. Robinson

North Little Rock, AR 72199

Entergy Operations, Inc. -4-

Pope County Judge

Pope County Courthouse

100 West Main Street

Russellville, AR 72801

Entergy Operations, Inc. -5-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov )

Deputy Regional Administrator (Chuck.Casto@nrc.gov )

DRP Director (Dwight.Chamberlain@nrc.gov)

DRP Deputy Director (Anton.Vegel@nrc.gov )

DRS Director (Roy.Caniano@nrc.gov )

DRS Deputy Director (Troy.Pruett@nrc.gov )

Senior Resident Inspector (Alfred.Sanchez@nrc.gov)

Resident Inspector (Jeffrey.Josey@nrc.gov )

Branch Chief, DRP/E (Jeff.Clark@nrc.gov )

Senior Project Engineer, DRP/E (George.Replogle@nrc.gov)

ANO Site Secretary (Vicki.High@nrc.gov )

Public Affairs Officer (Victor.Dricks@nrc.gov )

Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov )

RITS Coordinator (Marisa.Herrera@nrc.gov )

OEMail Resource

Senior Enforcement Specialist (Mark.Haire@nrc.gov )

File located: R:REACTORS\ANO RFI - WCS ML091060654

SUNSI Rev Compl. ; Yes No ADAMS  ; Yes No Reviewer WCS

Initials

Publicly Avail  ; Yes No Sensitive Yes ; No Sens. Type WCS

Initials

EB 1 C:EB 1

W. Sifre T. Farnholtz

/RA/ /RA/

4/15/09 4/16/09

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

INFORMATION REQUEST FOR ARKANSAS NUCLEAR ONE COMPONENT DESIGN

BASES (CDBI) INSPECTION

Inspection Report: 05000313; 05000368/2009007

Information Gathering Dates: June 16-18, 2009

On-site Inspection Dates: July 6-10 and July 20-31, 2009

Inspection Procedure: IP 71111.21, Component Design Bases

Inspection

Lead Inspector/Team Leader: Wayne C. Sifre

817-860-8193

Wayne.Sifre@nrc.gov

I. Information Requested Prior to the information Gathering Visit (June 16-18,

2009)

The following information (Section I of this enclosure) should be sent to the

Region IV office in hard copy or electronic format (ims.certrec.com preferred), in

care of Wayne C. Sifre, by May 26,2009 to facilitate the reduction in the items to

be selected for a final list during the preparation week June 29, 2009. The

inspection team will finalize the selected list during the prep week using the

additional documents requested in Section II of this enclosure. The specific items

selected from the lists shall be available and ready for review on the day

indicated in this request. *Please provide requested documentation electronically

in pdf files, Excel, or other searchable formats, if possible. The information

should contain descriptive names, and be indexed and hyperlinked to facilitate

ease of use. Information in "lists" should contain enough information to be easily

understood by someone who has knowledge of pressurized water reactor

technology. If requested documents are large and only hard copy formats are

available, please inform the inspector(s), and provide subject documentation

during the first day of the onsite inspection.

1. An excel spreadsheet of equipment basic events (with definitions)

including importance measures sorted by risk achievement worth (RAW)

and Fussell-Vesely (FV) from your internal events probabilistic risk

assessment (PRA). Include basic events with RAW value of 1.3 or

greater.

2. Provide a list of the top 500 cut-sets from your PRA.

3. Copies of PRA system notebooks, and the latest PRA summary

document.

-1- Enclosure

4. An excel spreadsheet of PRA human action basic events or risk ranking

of operator actions from your site specific PSA sorted by RAW and FV.

Provide copies of your human reliability worksheets for these items.

5. If you have an external events or fire PSA model, provide the information

requested in items 1-4 for external events and fire.

6. Any pre-existing evaluation or list of components and associated

calculations with low design margins, (i.e., pumps closest to the design

limit for flow or pressure, diesel generator close to design required output,

heat exchangers close to rated design heat removal, etc.).

7. List of high risk maintenance rule systems/components and functions;

based on engineering or expert panel judgment.

8. A list of operating experience evaluations for the last 2 years.

9. A list of all time-critical operator actions in procedures.

10. A list of permanent and temporary modifications sorted by component

identified in Item 1.

11. List of current operator work arounds/burdens.

12. A list of the design calculations, which provide the design margin

information for components included in Item 1. (Calculations should be

available during the information gathering visit).

13. List of root cause evaluations associated with component failures or

design issues initiated/completed in the last 5 years.

14. Current management and engineering organizational charts.

15. Arkansas Nuclear One IPEEE, if available electronically.

16. Mechanical piping drawings for:

Engineered safety features

Emergency core cooling systems

Emergency diesel generators

17 Electrical one-line drawings for:

Offsite power/switchyard supplies

Normal AC power systems

Emergency AC/DC power systems including

120VAC power, and

125VDC/24VDC safety class systems

18. List of any common-cause failures of components in the last 3 years.

19. An electronic copy of the Design Bases Documents.

20. An electronic copy of the System Health notebooks.

II. Information Requested to be Available on First Day of Preparation Week

(June 29, 2009)

1. List of condition reports (corrective action documents) associated with

each of the selected components for the last 5 years.

2. The corrective maintenance history associated with each of the selected

components for the last 2 years.

3. Copies of calculations associated with each of the selected components

(if not previously provided), excluding data files. Please review the

calculations and also provide copies of reference material (such as

drawings, engineering requests, and vendor letters).

4. Copies of operability evaluations associated with each of the selected

components and plans for restoring operability, if applicable.

5. Copies of selected operator work-around evaluations associated with

each of the selected components and plans for resolution, if applicable.

6. Copies of any open temporary modifications associated with each of the

selected components, if applicable.

7. Trend data on the selected electrical/mechanical components

performance for last 3 years (for example, pumps performance including

in-service testing, other vibration monitoring, oil sample results, etc., as

applicable).

8. A copy of any internal/external self-assessments and associated

corrective action documents generated in preparation for the inspection.

9. A copy of engineering/operations related audits completed in the last 2

years.

10. List of motor operated valves (MOVs) in the program, design margin and

risk ranking.

11. List of air operated valves (AOVs) in the valve program, design and risk

ranking.

12. Structure, system and components in the Maintenance Rule (a)(1)

category.

13. Site top 10 issues list.

14. Procedures used to accomplish operator actions associated with the

basic events in your PRA.

15. List of licensee contacts for the inspection team with pager or phone

numbers.

III. Information Requested to be provided throughout the inspection.

1. Copies of any corrective action documents generated as a result of the

teams questions or queries during this inspection.

2. Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily during the

inspection to each team member).

3. Reference materials (available electronically and as needed during all

onsite weeks):

General set of plant drawings

IPE/PRA report

Procurement documents for components selected

Plant procedures (normal, abnormal, emergency, surveillance, etc.)

Technical Specifications

Updated Final Safety Analysis Report

Vendor manuals

Inspector Contact Information: