| title = Mid-Cycle Performance Review and Inspection Plan - Kewaunee Power Station
| title = Mid-Cycle Performance Review and Inspection Plan - Kewaunee Power Station
| author name = Kunowski M A
| author name = Kunowski M
| author affiliation = NRC/RGN-III/DRP/B5
| author affiliation = NRC/RGN-III/DRP/B5
| addressee name = Heacock D A
| addressee name = Heacock D
| addressee affiliation = Dominion Energy Kewaunee, Inc
| addressee affiliation = Dominion Energy Kewaunee, Inc
| docket = 05000305
| docket = 05000305

Revision as of 05:36, 11 July 2019

Mid-Cycle Performance Review and Inspection Plan - Kewaunee Power Station
ML102440058
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 09/01/2010
From: Michael Kunowski
NRC/RGN-III/DRP/B5
To: Heacock D
Dominion Energy Kewaunee
References
Download: ML102440058 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 1, 2010

Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard

Glen Allen, VA 23060-6711

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - KEWAUNEE POWER STATION

Dear Mr. Heacock:

On August 4, 2010, the NRC staff completed its performance review of Kewaunee Power Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2009, through June 30, 2010. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information.

A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter at Kewaunee Power Station was within the Licensee Response column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2011. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

D. Heacock

In accordance with 10 CFR 2.390 of the NRC

=s A Rules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9618 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects

Docket No. 50-305 License No. DPR-43

Enclosure:

Kewaunee Power Station Inspection/Activity Plan

cc w/encl: Distribution via ListServ

D. Heacock

In accordance with 10 CFR 2.390 of the NRC

=s A Rules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9618 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects

Docket No. 50-305 License No. DPR-43

Enclosure:

Kewaunee Power Station Inspection/Activity Plan

cc w/encl: Distribution via ListServ DISTRIBUTION

See next page

DOCUMENT NAME: G:\Branch TSS\ALL MOC\midcycle 2010 to 2011\midcycle letters\Kewa 2010 MOC Letter.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME PCardona-Morales for Jandovitz:dtp:cs MKunowski DATE 08/26/10 08/26/10 OFFICIAL RECORD COPY

Letter to D. Heacock from M. Kunowski dated September 1, 2010

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - KEWAUNEE POWER STATION

DISTRIBUTION

Susan Bagley

RidsNrrDorlLpl3-1 RidsNrrPMKewaunee Resource RidsNrrDirsIpab Resource Steven Reynolds Steven Orth Jared Heck

Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource

Inspection / Activity Plan Page 1 of 2 08/26/2010 Report 22 09/01/2010

-12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Kewaunee IP71152-BIENNIAL PI&R INSPECTION 5 1 IP Identification and Resolution of Problems 71152B 08/16/2010 09/03/2010 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Radiological Environmental Monitoring Program 71124.07 10/18/2010 10/22/2010 1 IP Reactor Coolant System Activity 71151-BI01 10/18/2010 10/22/2010 1 IP Occupational Exposure Control Effectiveness 71151-OR01 10/18/2010 10/22/2010 1 IP RETS/ODCM Radiological Effluent 71151-PR01 10/18/2010 10/22/2010 BI EP-EP ROUTINE INSPECTION / PI VERIFICATION 2 1 IP A lert and Notification System Testing 7111402 11/01/2010 11/05/2010 1 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 11/01/2010 11/05/2010 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 11/01/2010 11/05/2010 1 IP Drill/Exercise Performance 71151-EP01 11/01/2010 11/05/2010 1 IP ERO Drill Participation 71151-EP02 11/01/2010 11/05/2010 1 IP A lert & Notification System 71151-EP03 11/01/2010 11/05/2010 BI OL-BIENNIAL REQUAL PROGRAM INSPECTION 2 1 IP Licensed Operator Requalification Program 7111111B 12/13/2010 12/17/2010 OL PREP-KEWAUNEE INIT PREP - 01/2011 3 1 OL - INITIAL EXAM - FEB 2011 - KEWA W90231 01/17/2011 01/21/2011 OL EXAM-KEWAUNEE INIT EXAM 02/2011 3 1 OL - INITIAL EXAM - FEB 2011 - KEWA W90231 02/07/2011 02/18/2011 BI ENG-INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - PWR 7111108P 02/26/2011 03/26/2011 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 02/28/2011 03/04/2011 1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 02/28/2011 03/04/2011 1 IP Occupational ALARA Planning and Controls 71124.02 02/28/2011 03/04/2011 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/06/2011 06/10/2011 1 IP Reactor Coolant System Activity 71151-BI01 06/06/2011 06/10/2011 1 IP Occupational Exposure Control Effectiveness 71151-OR01 06/06/2011 06/10/2011 1 IP RETS/ODCM Radiological Effluent 71151-PR01 06/06/2011 06/10/2011 ISFSI-ISFSI INSPECTION - SCHEDULE DEPENDENT 2 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 08/01/2011 08/31/2011 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Inspection / Activity Plan Page 2 of 2 08/26/2010 Report 22 09/01/2010

-12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Kewaunee BI ENG-TRIENNIAL FIRE PROTECTION INSPECTION 3 1 IP Fire Protection [Triennial]

7111105T 09/06/2011 10/07/2011 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/12/2011 09/16/2011 1 IP Occupational ALARA Planning and Controls 71124.02 09/12/2011 09/16/2011 1 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 09/12/2011 09/16/2011 1 IP Occupational Dose Assessment 71124.04 09/12/2011 09/16/2011 BI EP-EP EXERCISE INSPECTION / PI VERIFICATION 3 1 IP Exercise Evaluation 7111401 10/03/2011 10/07/2011 1 IP Drill/Exercise Performance 71151-EP01 10/03/2011 10/07/2011 1 IP ERO Drill Participation 71151-EP02 10/03/2011 10/07/2011 1 IP A lert & Notification System 71151-EP03 10/03/2011 10/07/2011 STRIKE-STRIKE CONTINGENCY - OPS/MAINT/RP 2 1 IP Licensee Strike Contingency Plans 92709 10/01/2011 11/11/2011 BI RP-RADIATION PROTECTION BASELINE INSPECTION 1 1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 12/05/2011 12/09/2011 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.