ULNRC-03300, Monthly Operating Rept for Nov 1995 for Callaway Plant

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Nov 1995 for Callaway Plant
ML20095C657
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/30/1995
From: Affolter R, Holmes M
UNION ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
ULNRC-03300, ULNRC-3300, NUDOCS 9512120131
Download: ML20095C657 (6)


Text


- - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Ca!!away Plet e ^' Past G!!re 80> E20

--$ Fulton, fAssra.e E5251

, UVION ILLECTRIC December 6,1995

$3 U.S. Nuclear Regulatory Commission Document Control Desk

Washington, DC 20555 ULNRC-03300 Gentlemen

DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 FACILITY OPERATING LICENSE NPF-30 MONTIIIN OPERATING REPORT NOVEMBER 1995 Tlie enclosed Monthly Operating Report for November 1995 is submitted pursuant to Section 6.9.1.8 of the Callaway Unit 1 Technical Specifications.

t R. D fr Manager, Callaway Plant RDAgD All Enclosure ec: Distribution attached 120073 i

)b

~

9512120131 951130 ADOCK 050004B3

(

l PDR I .R , _.

PDR l -______ -

cc distribution for ULNRC-03300 with enclosures v Mr. L. Joe Callan l Regional Administrator U.S. Nuclear Regulatory Commission -

Region IV l 611 Ryan Plaza Drive

Suite 400 l Arlington,TX 76011 l

l Ms. Kristine M. Thomas (2 copies)

Licensing Project Manager

! Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 13-E-21 Washington, D.C. 20555 Manager, Electric Department Missouri Public Service Commission P. O. Box 360 Jefferson City, MO 65102 Mr. Thomas A. Baxter Shaw, Pittman, Potts & Trowbridge 2300 N. Street N.W.

Washington, D.C. 20037 NRC Resident Inspector

., u DOCKET NO.: 50-483 UNIT NAME: CALLAWAY UNIT 1 DATE: 12/6/95 COMPLETED BY: M. A. Ilolmes l TELEPIIONE: 314/676-8842 l FAX: 314/676-8562 l

PART A - OPERATIONS

SUMMARY

The plant operated at approximately 98.5% for the month of November due to steam generator low pressure limitations aften chemical cleaning. Also, on 11/02/95 at 13:45 CST, power was reduced to fix a problem with the loop 4 Reactor Trip System

! Instrumentation (Over-Power, Delta Temperature channel) per Technical Specification 3.3.1 & 3.3.2.

l PART B - PORV AND SAFETY VALVE

SUMMARY

None.

I Page1 of4

.. r' e

t PART C AVERAGE DAILY UNIT POWER LEVEL DOCKET NO: 50483 UNIT: Callaway Unit 1 DATE: 12/6/95 COMPLETED BY: M. A. Ilolmes i TELEPilONE: 314/676-8842 l

FAX: 314/676-8562

, MONTII NOVEMBER 1995 i

AVERAGE DAILY POWER AVERAGE DAILY POWER LEVEL LEVEL M (MWe-Net) M (MWe-Net) 1 1.149 17 1.160 2 1.159 18 1.163 3 1.163 19 1.158 1

4 1.165 20 1.158

=

5 1.164 21 1.164 6 1.159 22 1.163 7 1.165 23 1.165 f 8 1.166 24 1.166 ,

l 9 1.159 25 1.161 10 1.156 26 1.154 11 1.166 27 1.157 12 1.165 28 1.167 13 1.164 29 1.165 14 1.166 . . _ 30 1.150 15 1.164 31 0 16 1.162 Page 2 of 4

l

.,. .,- PART D  ;

,- OPERATING DATA REPORT i DOCKET NO.: 50-483 '!

UNIT NAME: CALLAWAY UNIT I DATE: 12/6/95 COMPLLTED BY: M, A. Ilolmes TELEPliONE: 314/676-8842  !

FAX: 314/676-8562 OPERATING STATUS:

(NOV) (YTD) (CUM)

1. REPORTING PERIOD:

GROSS liOURS IN REPORTING PERIOD: 720 8,016 95,941.5 '

2 CURRENTLY AUTilORIZED POWER LEVEL (MWt): 3565 MAX. DEPEND. CAPACITY (MWe-Net): 1125 DESIGN ELECTRICAL RATING (MWe-Net): 1171

3. POWER LEVEL TO WillCII RESTRICTED (IF ANY)(MWe-Net): 100 %

4.' REASONS FOR RESTRICTION (IF ANY):

THIS MONTH YR TO DATE CUMULATIVE

5. NLNBER OF llOURS REACTOR WAS CRITICAL 720 6,674.8 84,381.5
6. RT /CTOR RESERVE SilUTDOWN llOURS 0 0 0
7. IlOURS GENERATOR ON-LINE 720 6,615.6 82,897.4 r
8. UNIT RESERVE SliUTDOWN llOURS 0 0 0
9. GROSS T11ERMAL ENERGY GENERATED 2,440,443 22,689,518 280,246,281 t (MWil)
10. GROSS ELECTRICAL ENERGY GENERATED 874,936 7,759,814 95,611,582 (MWil)  ;

11, NET ELECTRICAL ENERGY GENERATEL 836,188 7,383,962 90,954,504 (MWil)

12. REACTOR SERVICE FACTOR 100 83.3 80 !

i

13. REACTOR AVAILABILITY FACTOR 100 83.3 88.0

-14. UNIT SERVICE FACTOR 100 82.5 86.4

15. UNIT AVAILABILITY FACTOR 100 82.5 86.4
16. UNIT CAPACITY FACTOR (Using MDC) 103.2 81.9 84.3
17. UNIT CAPACITY FACTOR (Using Design MWe) 99.2 81.9 84.3
18. UNIT FORCED OUTAGE RATE 0.0 3.67 2.36 t
19. SIIUTDOWNS SCIIEDULED OVER NEXT 6 MONTilS (TYPE, DATE AND DURATION OF EACli):

Refueling Date: 10/05/96 l Duration: 42 days

20. IF SilUT DOWN AT END OF REPORTING PERIOD, ESTIMATE DATE OF STARTUP:

Page 3 of 4

?.

s PART E i UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-483 UNITNAME: - CALLAWAY UNIT I DATE: 12/6/95 -

COMPLETED BY: M. A.!!olmes TELEPHONE: 314/676-8842 FAX: 314/676-8562 REPORT MONTH: NOVEMBER 1995 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR CORRECTIVE NQ. DATE S: SCHEDULED (HOURS) REASON REDUCING POWER ACTIONS / COMMENTS

SUMMARY

REASON METHOD A: EQUIPMENT FAILURE (EXPLAIN) 1: MANUAL B. MAINT.ORTEST 2: MANUAL SCRAM

- C: REFUELING 3: AUTOMATIC SCRAM D: REGULATORY RESTRICTION 4: OTHER(EXPLAIN)

E: OPERATOR TRAINING AND LICENSE EXAMINATION F: ADMINISTRATION G: OPERATIONAL ERROR (EXPLAIN)

H: OTHER(EXPLAIN)

~

Page 4 of 4