PNO-I-87-104A:on 871108,normally Locked High Radiation Barrier Leading to Refueling Floor Was Found W/Locking Mechanism Taped Over.Info Serves as Update to PNO-I-87-104, Discussing Licensee Decision to Stop Work at Plant
ML20212E291
Person / Time
Site: Pilgrim
Issue date: 11/10/1987
From: Blough R, Lyash J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
References
PNO-I-87-104A, NUDOCS 9711030131
Download: ML20212E291 (1)


--

DCS No: 50293871109 6% Alt f( Date: November 10, 1987 k [^h PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE--PNO-I-87-104A 1 \ l V' This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by the Region I staff on this date.

Facility: Licensee Emergency Classification:

Boston Edison Company Notification of Unusual Event Pilgrim Nuclear Power Station Alert Plymouth, MA Site Area Emergency Docket No. 50-293 General Emergency X Not Applicable

Subject:

SITEWORKSTOPPAGE(UPDATE)

This updates PNO-1-87-104 issued on November 9, 1987, which discussed Boston Edison's decision to stop work at the Pilgrim facility to allow site management the opportunity to review the causes of v m 1 problems which occurred onsite since November 7, 1987.

Among other problems wi ich principally involved the adequacy of completed maintenance work, there were four radiological matters. In one instance, on November 8, the nonnally locked high radiation barrier gate leading to the refueling floor was found with its locking mechanism taped-over. Although there existed no actual radiological .

conditions warranting the establishment of a high radiation barrier, keeping the gate locked is a current site administrative requirement. In addition, there were several radioactive sp'.11s which occurred on November 8,1987 as an apparent result of 9 incomplete maintenance or modification work activities. The contamination levels resulting from the above spills were relatively low, however, about five people received clothing and/or skin contamination and four received shoe contamination which was easily renoved onsite. Further, on November 8, 1987, operator attempts to use water to clear a clogged transfer line resulted in a spill in an unoccupied area of the radwaste facility. This spill resulted in radiation levels of 500 mR/hr on contact on the floor. Finally, the licensee identified low level contamination in a corridor adjacent to the turbine building which resulted in 12-14 people with shoe contamination.

There has been significant media interest in the events leading up to the work stoppage.

CONTACT: J. Lyash R. Blough ' -

(Comm)617-747-0565 (FTS)488-1146 DISTRIBUTION:

H. St. MNBB Phillips E/W Willste Mail: ADM:DMB Chairman Zech EDO NRR NMSS 00T:Trans only Com. Roberts PA 01A RES Comm. Bernthal OGC AE0D NRC Ops Crt

< Comm. Carr Comm. Rogers ACRS Air Rights INP0----

SECY SP NSAC----

'PDR' Regional Offices TMI Resident Section RI Resident Office _

Licensee:

(ReactorLicensees)

(f Region I Form 83 9711030131 871110 C/R Distribu ion: Chm, Cmrs.

I -104A PDR S GC, CA, am, Historian, SECY, Records, a