ML22339A174

From kanterella
Jump to navigation Jump to search
GE Hitachi Nuclear Energy NRC Inspection Report 05000018/2022002 05000070/2022002 and 05000183/2022002
ML22339A174
Person / Time
Site: Vallecitos Nuclear Center, Vallecitos
Issue date: 12/13/2022
From: Greg Warnick
NRC/RGN-IV/DRSS/DIOR
To: Pedley C
GE Hitachi Nuclear Energy
Anderson S
References
IR 2022002
Download: ML22339A174 (19)


See also: IR 05000018/2022002

Text

December 12, 2022

Mr. Charles Pedley, Site Manager

Vallecitos Nuclear Center

GE Hitachi Nuclear Energy

6705 Vallecitos Road

Sunol, CA 94586-8524

SUBJECT: GE HITACHI NUCLEAR ENERGY NRC INSPECTION REPORT 050-00018/2022-

002, 050-00070/2022-002, AND 050-00183/2022-002

Dear Mr. Pedley:

This letter refers to the U.S. Nuclear Regulatory Commission (NRC) inspection conducted on

November 7-9, 2022, at your Vallecitos Nuclear Center in Sunol, California. The inspection

covered the following shutdown reactors under the subject licenses, Vallecitos Boiling Water

Reactor (VBWR), General Electric Test Reactor (GETR), and Empire State Atomic Development

Associates Incorporated Vallecitos Experimental Superheat Reactor (EVESR). The NRC

inspectors discussed the results of this inspection with you and members of your staff on

November 9, 2022. The inspection results are documented in the enclosure to this letter.

During this inspection, the NRC inspectors examined activities conducted under your licenses

as they relate to public health and safety, the environment, and to confirm compliance with the

Commissions rules and regulations, as well as with the conditions of your license. Within these

areas, the inspection consisted of the examination of selected procedures and representative

records, tour of the reactors and supporting equipment, independent radiation surveys, and

interviews with personnel.

Based on the results of this inspection, the NRC has determined that one Severity Level IV

violation of NRC requirements occurred. The violation was evaluated in accordance with the

NRC Enforcement Policy. The current NRC Enforcement Policy is included on the NRCs

Web site at (https://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html).

The violation cited in the enclosed Notice of Violation (Notice) and the circumstances

surrounding it are described in detail in the subject inspection report. The violation is being cited

in the Notice because it was identified by the NRC and corrective actions had not been fully

articulated on the docket at the time of the final exit meeting. Therefore, you are required to

respond to this letter and should follow the instructions specified in the enclosed Notice when

preparing your response. If you have additional information that you believe the NRC should

consider, you may provide it in your response to the Notice. The NRC review of your response

to the Notice will also determine whether further enforcement action is necessary to ensure

compliance with regulatory requirements.

C. Pedley 2

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a

copy of this letter, its enclosure, and your response will be made available electronically for

public inspection in the NRC Public Document Room or from the NRCs Agencywide

Documents Access and Management System (ADAMS). ADAMS is accessible from the NRCs

Website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response

should not include any personal privacy or proprietary, information so that it can be made

available to the Public without redaction.

If you have any questions concerning this inspection report, please contact Stephanie Anderson

at 817-200-1213, or the undersigned at 817-200-1249.

Sincerely,

Signed by Warnick, Gregory

on 12/12/22

Gregory G. Warnick, Chief

Decommissioning, ISFSI, and Operating

Reactor Branch

Division of Radiological Safety and Security

Docket Nos. 050-00018; 050-00070;

050-00183

License Nos. DPR-1; TR-1; DR-10

Enclosures:

1. Notice of Violation

2. Inspection Report 050-00018/2022-002;

050-00070/2022-002; 050-00183/2022-002

ML22339A174

SUNSI Review ADAMS: Sensitive Non-Publicly Available Keyword

By: SGA Yes No Non-Sensitive Publicly Available NRC-002

OFFICE DRSS/DIOR DRSS/DIOR RI/DRSS/DIRHP NMSS/RDB

NAME SGAnderson RJEvans KRWarner JDParrott

SIGNATURE SGA RJE KRW JDP

DATE 12/06/2022 12/06/2022 12/06/2022 12/06/2022

OFFICE C:DIOR

NAME GGWarnick

SIGNATURE GGW

DATE 12/12/2022

NOTICE OF VIOLATION

GE Hitachi Nuclear Energy Docket Nos. 050-00018

Vallecitos Boiling Water Reactor 050-00070, 050-00183

GE Test Reactor License Nos. DPR-1; TR-1

ESADA Vallecitos Experimental Superheat Reactor DR-10

During an NRC inspection conducted on November 7-9, 2022, one violation of NRC

requirements of greater than minor significance was identified. In accordance with the NRC

Enforcement Policy, the violation is listed below:

10 CFR 20.1601(a) states, in part, The licensee shall ensure that each entrance or

access point to a high radiation area has one or more of the following features(3)

Entryways that are locked, except during periods when access to the areas is required,

with positive control over each individual entry.

Licensee Procedures WI-27-105-01, Posting and Control of Radiological Areas,

revision 3, and WI-27-105-15, High Radiation Area Access Control, revision 2,

implements the positive control provision of the regulation as stated above. Procedure

WI-27-105-01, section 4.6.2, describes several ways to establish controls for a high

radiation area when one is unlocked. These include assigning an attendant at the

entrance to prevent unauthorized access or providing a control device with a

conspicuous visible or audible alarm neither of which were implemented. Procedure

WI-27-105-15, section 4.1.4, states If a guard will be used to control high radiation area

(HRA) access, then ensure the Guard has been briefed and understands the

responsibilities of a Guard per Attachment 3, Access Control Guard Responsibilities.

Attachment 3 requires, in part, that the guard maintains direct line-of-sight surveillance

of the access to the high radiation area until it is locked/secured and prevents

unauthorized entry into the high radiation area by verifying individuals seeking access to

the high radiation area are authorized on the radiation work permit.

Contrary to the above, on November 9, 2022, GE Hitachi Nuclear Energy failed to

establish positive controls over an entry to a posted high radiation area. Specifically,

during an NRC tour of the Waste Evaporator Plant (WEP) building, the licensee failed to

assign and brief an attendant per procedures WI-27-105-01 and WI-27-105-15, and as a

result, the licensee failed to maintain positive control over the posted high radiation area.

This is a Severity Level IV violation (Section 6.3).

Pursuant to the provisions of Title 10 Code of Federal Regulation (CFR) 2.201, GE Hitachi

Nuclear Energy is hereby required to submit a written statement or explanation to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001,

with a copy to the Regional Administrator, Region IV, 1600 E. Lamar Blvd., Arlington, TX 76011-

4511, within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This

reply should be clearly marked as a Reply to a Notice of Violation and should include for each

violation: (1) the reason for the violation, or if contested, the basis for disputing the violation or

severity level; (2) the corrective steps that have been taken and the results achieved; (3) the

corrective steps that will be taken; and (4) the date when full compliance will be achieved.

Your response may reference or include previously docketed correspondence, if the

correspondence adequately addresses the required response. If an adequate reply is not

received within the time specified in this Notice, an order or a Demand for Information may be

Enclosure 1

issued requiring information as to why the license should not be modified, suspended, or

revoked, or why such other action as may be proper should not be taken. Where good cause is

shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-001, with a copy to the Regional

Administrator, Region IV.

Your response will be made available electronically for public inspection in the NRC Public

Document Room or in the NRCs Agencywide Documents Access and Management System

(ADAMS), accessible from the NRC Web site at: http://www.nrc.gov/reading-rm/adams.html. To

the extent possible, your response should not include any personal privacy, proprietary or

safeguards information so that it can be made available to the public without redaction.

In accordance with 10 CFR 19.11, you may be required to post this Notice within two working

days of receipt.

Dated this 12 day of December 2022

2

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket Nos.: 050-00018; 050-00070; and 050-00183

License Nos.: DPR-1; TR-1; and DR-10

Report Nos.: 050-00018/2022-002; 050-00070/2022-002; and 050-00183/2022-002

Licensee: GE Hitachi Nuclear Energy

Facility: Vallecitos Boiling Water Reactor (VBWR)

GE Test Reactor (GETR)

ESADA Vallecitos Experimental Superheat Reactor (EVESR)

Location: 6705 Vallecitos Road

Sunol, California

Inspection Dates: November 7-9, 2022

Inspectors: Stephanie G. Anderson

Senior Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Robert J. Evans, PhD, CHP, PE

Senior Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Katherine R. Warner

Senior Health Physicist

Decommissioning, ISFSI, and Reactor HP Branch

Division of Radiological Safety and Security

Jack D. Parrott

Senior Project Manager

Reactor Decommissioning Branch

Office of Nuclear Materials Safety and Safeguards

Accompanied By: Eric S. McManus

Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Approved By: Gregory G. Warnick, Branch Chief

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Enclosure 2

EXECUTIVE SUMMARY

GE Hitachi Nuclear Energy

NRC Inspection Report 050-00018/2022-002; 050-00070/2022-002; and 050-00183/2022-002

This U.S. Nuclear Regulatory Commission (NRC) inspection was a routine, announced inspection

of licensed activities being conducted at the three permanently defueled reactors at the Vallecitos

Nuclear Center. In summary, the inspectors identified one Severity Level IV violation. Other than

the one identified violation, the licensee was conducting these activities in accordance with site

procedures, license requirements, and applicable NRC regulations.

Decommissioning Performance and Status Review at Permanently Shutdown Reactors and

Class III Research and Test Reactors

The licensee conducted annual inspections and audits of the three shutdown reactors in

accordance with regulatory, license, and procedure requirements. (Section 1.2)

Safety Reviews, Design Changes, and Modifications at Permanently Shutdown Reactors

The licensee implemented its safety review program in accordance with its procedures and

regulatory requirements. (Section 2.2)

Problem Identification and Resolution at Permanently Shutdown Reactors

The inspectors concluded that the licensee was adequately implementing its corrective

action program in accordance with regulatory requirements. (Section 3.2)

Fire Protection Program at Permanently Shutdown Reactors

The licensee had implemented a fire protection program that reasonably prevented fires

from occurring and was capable of rapidly extinguishing those fires that occurred.

(Section 4.2)

Occupational Radiation Exposure at Permanently Shutdown Reactors

The inspectors concluded that the licensee conducted its radiation control program in

accordance with license conditions and regulatory requirements, with one exception of more

than minor significance. The inspectors identified one Severity Level IV violation in the high

radiation area controls area of occupational radiation exposure. The licensee monitored

occupational exposures, and the results for 2021 - to date in 2022 were less than regulatory

limits. The licensee continued to conduct annual radiological surveys within each of the

shutdown reactor structures as required by the three licenses, and the licensee reported the

results to the NRC in an annual report. (Section 5.2)

Radioactive Waste Treatment, and Effluent and Environmental Monitoring

The licensee collected and analyzed all required effluent and environmental monitoring

samples, and no sample result exceeded the respective regulatory or procedural limits. Site

operations had a negligible effect on public doses during 2021. (Section 6.2)

2

Report Details

Summary of Plant Status

The GE Hitachi Nuclear Energy Americas, LLC (GEH or Licensee) transitioned the three

shutdown reactors, Vallecitos Boiling Water Reactor (VBWR), General Electric Test Reactor

(GETR), and Empire State Atomic Development Associates Incorporated Vallecitos Experimental

Superheat Reactor (EVESR) from a possession-only, safe storage (SAFSTOR) condition, with

no fuel remaining in the reactors or spent fuel pools to DECON status.

On December 15, 2015, the licensee submitted a request for license continuance under Title

10 to the Code of Federal Regulations (10 CFR) 50.51(b) for reactor licenses DR-10 and TR-1

(Agencywide Documents Access and Management System [ADAMS] Accession No.

ML15349A045). That request was approved by letter dated January 2, 2019 (ML18352A450).

The licensee also submitted a request on July 10, 2015 (ML15195A088), for an alternate

decommissioning schedule as described in 10 CFR 50.82(a)(3) and 50.82(b)(4)(i), using the

exemption criteria of 10 CFR 50.12.

On March 19, 2021 (ML19304B459), the NRC staff submitted a SECY paper to the

Commissioners, SECY-21-0033, Request for an exemption from the decommissioning schedule

requirements for shutdown reactors at GE Hitachi Vallecitos Nuclear Center. In the SECY

paper, there were two options for the Commissions consideration. Option 1 was to approve a 10 CFR 50.12 exemption from the applicable decommissioning schedule requirements of 10 CFR 50.82(a)(3) and 10 CFR 50.82(b)(4)(i) for the EVESR and GETR and delegate to the staff only

the authority to grant or deny such an exemption for the VBWR based on GEHs demonstration

of the VBWRs continued structural integrity. Option 2 was to deny the exemption request for all

three shutdown reactors at the Vallecitos Nuclear Center (VNC). The NRC staff recommend

approving Option 1, a 10 CFR 50.12 exemption from the applicable decommissioning schedule

requirements of 10 CFR 50.82(a)(3) and 10 CFR 50.82(b)(4)(i) for the EVESR and GETR and to

delegate to the staff the authority to grant or deny such an exemption for the VBWR based on

the licensees demonstration of the VBWRs continued structural integrity.

On August 6, 2021 (ML21218A110), the Commission disapproved the staffs recommendation to

grant GEH an exemption of 10 CFR 50.12, to extend the decommissioning schedule for EVESR,

GETR, and VBWR and instead approved a denial of the request under Option 2. On August 25,

2021 (ML21237A064), GEH requested to withdraw its exemption request for the shutdown

reactors from an alternate decommissioning schedule. By letter dated October 12, 2021

(ML21258A042), the NRC staff sent a letter to GEH accepting the withdraw of the exemption

request and reviewed the requirements from 10 CFR 50.82 that apply to the decommissioning of

the shutdown reactors at the VNC.

On September 21, 2022 (ML22264A325), GEH submitted their Limited Post-Shutdown

Decommissioning Activities Report (LPSDAR) to demonstrate compliance with 10 CFR 50.82(a)(4), 10 CFR 50.82(a)(6), and 10 CFR 50.82(a)(7). Although 10 CFR 50.82(a)(4)

requirements for content of the PSDAR do not apply to VBWR and EVESR, GEH agreed to

prepare the LPSDAR consistent with the description in 10 CFR 50.82(a)(4) and Regulatory

Guide 1.185, Standard Format and Content for Post-Shutdown Decommissioning Activities

Report.

For 2023 inspection activities, in accordance with Inspection Manual Chapter 2561,

Decommissioning Power Reactor Inspection Program, the direct inspection effort associated

3

with the implementation of the core inspection procedures will increase as the site transitions to

a Category 3 site as defined as Actively Decommissioning (DECON), no fuel in the spent fuel

pool.

1 Decommissioning Performance and Status Review at Permanently Shutdown

Reactors (71801) and Class III Research and Test Reactors (69002)

1.1 Inspection Scope

The inspectors reviewed the licensees control and oversight of the three shutdown

reactors.

1.2 Observations and Findings

a. Vallecitos Boiling Water Reactor

The VBWR is a possession-only reactor under License No. DPR-1, Amendment 21. It

was a 50-megawatt (MW) power reactor that achieved full power operations in 1957,

after receiving its Construction Permit No. CPPR-3 on May 14, 1956. It was shut down

on December 9, 1963, for an extended period of time and subsequently was

deactivated. All fuel has been removed from the facility.

The possession-only facility license DPR-1, License Condition 4 states in part, that

there should be an audible control device maintained on the doors to the containment

building. In addition, License Condition 5 authorizes GEH to dispose of component parts

or devices from the VBWR facility in accordance with the provisions of 10 CFR Part 20.

The licensee removed extensive components from the facility between October 2007

and November 2008. All reactor systems have been removed except for the reactor

vessel. The licensee does monitor the water level weekly in the reactor vessel and at the

time of the inspection, the manometer was not in service due to active work around the

reactor vessel to prepare the vessel for removal from the containment.

The inspectors toured the facility with licensee representatives. The inspectors

confirmed there was an audible control device functioning on the manual doors to the

containment building that provided an alarm at the 300-area alarm panel and at the

Central Alarm Station. The inspectors observed that the roll-up door was secured, which

was installed in place of the equipment hatch. The inspectors entered the basement

level to observe the condition and integrity of the retired facility. The inspectors identified

humidity and temperature sensors in the retired facility. The inspectors observed multiple

crack formation throughout the containment building. The cracks are being monitored by

the licensee to determine growth rate. During the inspection, the inspectors did not

identify any standing water on the floor of the basement. The sump pump was in

operation at the time of the inspection, and any water that is collected in the basement of

VBWR is pumped to the VBWR transfer tank, then ultimately transferred to the onsite

waste evaporator plant for processing.

b. ESADA Vallecitos Experimental Superheat Reactor

The ESADA Vallecitos Experimental Superheat Reactor (EVESR) is a possession-only

reactor under License No. DR-10, Amendment No. 7. The EVESR was a light water

moderated, steam cooled, superheat, experimental research reactor that used slightly

4

enriched uranium dioxide as fuel. It operated at a maximum of 17 MW thermal and was

initially licensed in 1963. It achieved full power operation in 1964, and was shut down on

February 1, 1967, and subsequently deactivated. All fuel and other special nuclear

material had been removed and shipped offsite. In addition, a significant amount of

equipment used to operate the reactor, such as nuclear instrumentation, piping, pumps,

and valves has been removed.

The inspectors toured the facility with licensee representatives. The inspectors

confirmed there was an audible control device functioning on the airlock door to the

containment building that provided an alarm at the 300 feet elevation area alarm panel

and at the Central Alarm Station. The licensee had a portable dehumidifier to remove

significant quantities of condensation that tended to buildup in the facility. The licensee

had lighting installed and it was operating sufficiently to ensure the passageways and

stairs were safely lit. The stack was no longer operational, and the licensee was using a

portable ventilation system.

c. General Electric Test Reactor

The GETR is a possession-only reactor under License No. TR-1, Amendment No. 17.

The reactor was a 50 MW thermal experimental test, development, and isotope

production reactor that utilized highly enriched plate fuel and was initially licensed to

operate in 1959. The reactor was shut down in 1977 and subsequently deactivated. All

fuel and isotope production targets containing special nuclear material have been

removed from the facility and shipped offsite. The reactor, systems and piping, and

spent fuel pool have been drained of water.

The inspectors toured the containment building, old control room, and tank farm. As

GETR has been shut down since 1977, there are no licensed operators nor a

requalification program, which is appropriate for the plant conditions. Staffing was

appropriate to meet the required weekly surveillance patrols, which were being

conducted in accordance with site procedures.

d. Other

The licenses for the three shutdown reactors require, in part, that activities involving

access to the facility area and use of any area shall be conducted under the direction of

a designated facility manager with functional responsibility and commensurate authority

to maintain the facility in a safe and secure condition at all times. The inspectors

reviewed the licensees organization and discussed the organizational structure with

members of the licensees organization. Based on discussions and observations, the

inspectors determined that the individual fulfilling the licensed responsibility as the facility

manager for the defueled reactors, adequately met the license condition requirements.

The licensee is managing the site as required by all regulatory and license requirements

including management of their decommissioning file as required by 10 CFR 50.75(g).

The inspectors evaluated the licensees decommissioning cost planning and

assessment, being an important part of the decommissioning process. The inspectors

determined that the licensees cost planning and assessment were inclusive of current

and planned major decommissioning activities as identified in the LPSDAR.

5

1.3 Conclusions

The licensee conducted annual inspections and audits of the three shutdown reactors in

accordance with regulatory, license, and procedure requirements.

2 Safety Reviews, Design Changes, and Modifications at Permanently Shutdown

Reactors (37801)

2.1 Inspection Scope

The inspectors reviewed the licensees control and oversight of the safety review

program to ensure design changes, tests, experiments and modifications were

effectively conducted, managed, and controlled during plant decommissioning.

2.2 Observations and Findings

There were three 10 CFR 50.59 modifications by the licensee related to the shutdown

reactors to review for 2022 to date. All three modifications were for the VBWR and

included the installation of a staircase in lieu of a ladder to the basement area,

radioactive characterization of the reactor vessel, and removal of shielding materials

around the vessel in preparation for vessel removal. The inspectors reviewed VSS 2.0,

Change Authorization, revision 24, and determined that the licensee had appropriately

followed the procedure to screen the changes. It was noted by the inspectors through

document review and interviews that cognizant licensee personnel were knowledgeable

and appeared to be appropriately trained.

2.3 Conclusions

The licensee implemented its safety review program in accordance with its procedures

and regulatory requirements.

3 Problem Identification and Resolution Action at Permanently Shutdown Reactors

(40801)

3.1 Inspection Scope

The inspectors reviewed the licensees corrective action program related to the oversight

of the three shutdown reactors.

3.2 Observations and Findings

At the time of the inspection the licensee was implementing its corrective action program

under procedures CP-16-108, Corrective Action Program, revision 13.4, WI-16-108-01,

Condition Review Process, revision 12.0, WI-20-106-06, Corrective Action Program

Qualifications, revision 7.0, and CP-16-202, Common Cause Analysis, revision 6.0.

These procedures apply to all the GE-Hitachi nuclear sites including the facilities at the

VNC. The inspectors reviewed the implementation of those procedures and a list of

corrective action condition reports on the shutdown reactors generated between August

2021 and the time of the inspection, including several specific condition reports (CRs)

6

related to the shutdown reactors (i.e., CRs 38035, 40513, 40514, and 40551) for

adherence to the corrective action procedure.

The inspectors also reviewed CR-39044, a three-year trend analysis of CR categories

specific to the VNC for trends and common causes for identified trends, the process and

results of GEHs Vallecitos specific trend analysis of CR categories based on key words,

the recent efforts by GEH to better specify trend categories specific to the activities done

on site and related to the shutdown reactors for better identification of issues, and how

these trending issues are reviewed by management. Also reviewed was the 2022

Vallecitos Radiation Survey Audit, the identification of opportunities for improvement,

and the capture of those issues in the corrective action system.

3.3 Conclusions

The inspectors concluded that the licensee was adequately implementing its corrective

action program in accordance with regulatory requirements.

4 Fire Protection Program at Permanently Shutdown Reactors (64704)

4.1 Inspection Scope

The inspectors evaluated the licensees fire protection program to support licensed

activities and regulatory requirements.

4.2 Observations and Findings

The licensee is required under 10 CFR 50.48(f) to maintain a fire protection program to:

(1) reasonably prevent fires from occurring; (2) rapidly detect, control, and extinguish

those fires that do occur and that could result in a radiological hazard; and (3) ensure

that the risk of fire-induced radiological hazards to the public, environment, and plant

personnel are minimized. The three shutdown reactors are required to have a fire

protection program; however, they are not required to maintain fire detection or

suppression equipment at their facilities because the majority of flammable materials

have been removed. The inspectors reviewed the fire protection program from an

emergency preparedness perspective to verify that the program can reasonably prevent

fires from occurring and rapidly extinguish those fires. The inspectors also reviewed the

fire drill report for 2022, fire extinguisher monthly surveillances, fire training, fire hoses

conditions, and the preventive maintenance monthly inspections.

4.3 Conclusions

The licensee had implemented a fire protection program that reasonably prevented fires

from occurring and was capable of rapidly extinguishing those fires that occurred.

5 Occupational Radiation Exposure at Permanently Shutdown Reactors (83750)

5.1 Inspection Scope

The inspectors reviewed occupational exposures and the results of the licensees

radiological surveys within the three shutdown reactors for compliance with license and

regulatory requirements.

7

5.2 Observations and Findings

The inspectors toured accessible areas within the site restricted areas, in part, to

observe radiological postings, area boundaries, and access controls. During site tours,

the inspectors conducted independent radiation measurements to ensure postings and

boundaries reflected actual radiological hazards. The inspectors independently

measured ambient gamma radiation levels using a Ludlum Model 2401-EC2 survey

meter (serial number 181580, calibration due date of 1/28/23, calibrated to cesium-137).

The inspectors toured the VBWR. The operating deck measured under 1 millirem per

hour. The basement area of the VBWR measured less than 5 millirem per hour, with the

sump area measuring around 3-4 millirem per hour. The general areas of the EVESR

and GETR measured under 5 millirem per hour, and areas that exceeded 5 millirem per

hour in GETR were properly posted as radiation areas as required by 10 CFR

20.1902(a). The inspectors also toured the onsite radiological count room and waste

evaporator plant. The count room and waste evaporator plant (WEP) measured less

than 5 millirem per hour with most areas at or near background levels.

The inspectors noted that the licensee performed several non-routine work activities in

the VBWR in 2022 as part of initial decommissioning activities. The inspectors reviewed

a sampling of documentation associated with these activities, including radiological

surveys and radiation work permits and did not identify any issues of more than minor

significance. The inspectors walked down the storage location of waste generated from

a recent activity involving removing shielding materials around the VBWR in preparation

for eventual shipment. The inspectors determined that the containers were appropriately

labeled, and the area was appropriately posted.

In the area of training, the inspectors reviewed procedure No. 1200, Qualification of

Radiation Monitoring Technicians, revision 0, and discussed its use with the radiation

safety officer. This new procedure provides a framework for the licensee to review the

qualifications of incoming radiation protection personnel and provide site-specific

training. The inspectors noted that the implementation of this process is timely given

increased use of radiation protection contractors for decommissioning work.

The occupational dose limits for adults are provided in 10 CFR 20.1201. The inspectors

reviewed the licensees occupational exposure records and discussed these records

with the radiation safety officer. The licensee divided the site staff into groups based on

major work activities. The groups included facilities management, nuclear test reactor,

and radiation protection. Worker exposures were primarily from external sources but

may include internal exposures based on air sample results.

During calendar year 2021, the onsite individual who received the highest total effective

dose equivalent exposure worked at the nuclear test reactor. This individual received

0.697 rem with a regulatory limit of 5 rem. The highest dose to a facilities worker was

0.424 rem, while the highest dose to a radiation protection worker was 0.330 rem. The

inspectors also reviewed the available occupational exposure records for calendar year

2022. At the time of the inspection, all doses were within the regulatory limit of 5 rem.

The licensee continued to monitor worker exposures using optically stimulated

dosimeters, electronic dosimeters, and air sampling as necessary based on the work

assignment.

8

The licenses for the three shutdown reactors include conditions, which state that a

general radiation survey shall be conducted at least annually, and the results of the

survey shall be submitted to the NRC on an annual basis. The radiological surveys of

the interiors of the three shutdown reactors were conducted in July and September

2021. The results of the surveys were submitted to the NRC by letter dated March 25,

2022 (ML22089A223). The radiological surveys included ambient and surface radiation

levels, removable contamination levels, and ambient air samples. The inspectors

reviewed the sample results for 2021. Although each building had variable levels of

contamination, according to the licensee, the overall radioactivity levels were found to

remain low. The licensee had completed their 2022 annual inspections and surveys of

the shutdown reactors, but at the time of this inspection, the report had not been issued.

The inspectors toured the WEP, in part, to observe radiological postings and access

controls. The licensee uses the WEP to process contaminated water from site facilities,

including the VBWR. The WEP is enclosed in one building, which is posted as a high

radiation area (HRA) and normally kept locked. As defined by 10 CFR 20.1003, a HRA is

an area, accessible to individuals, in which radiation levels from radiation sources

external to the body could result in an individual receiving a dose equivalent in excess of

0.1 rem (1 mSv) in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> at 30 centimeters from the radiation source or 30 centimeters

from any surface that the radiation penetrates. Within the WEP building, there are two

specific areas where radiation dose rates are expected to exceed high radiation dose

rate levels. One area is within the waste processing room and another under a holdup

tank. The waste processing room was verified to be locked. The area under the holdup

tank was accessible during the tour since the building was unlocked with access

available through a door and two roll up doors to the building. Recent surveys in July

and October 2022 both document a dose rate of 105 mrem/hour under the holdup tank,

which exceeded the HRA criteria stated above.

The inspectors identified one Severity Level IV notice of violation (NOV) of 10 CFR 20.1601(a) for the licensees failure to positively control an unlocked posted high

radiation area. 10 CFR 20.1601(a) states, in part, The licensee shall ensure that each

entrance or access point to a high radiation area has one or more of the following

features(3) Entryways that are locked, except during periods when access to the areas

is required, with positive control over each individual entry.

Licensee procedures WI-27-105-01, Posting and Control of Radiological Areas,

revision 3.0 and WI-27-105-15, High Radiation Area Access Control, revision 2.0

implements the positive control provision of the regulation as stated above. Procedure

WI-27-105-01, section 4.6.2, describes several ways to establish controls for a high

radiation area when one is unlocked. These include assigning an attendant at the

entrance to prevent unauthorized access or providing a control device with a

conspicuous visible or audible alarm neither of which were implemented. Procedure

WI-27-105-15, section 4.1.4, states, If a guard will be used to control HRA access, then

ensure the Guard has been briefed and understands the responsibilities of a Guard per

Attachment 3, Access Control Guard Responsibilities. Attachment 3 requires, in part,

that the guard maintains direct line-of-sight surveillance of the access to the HRA until

it is locked/secured and prevents unauthorized entry into the HRA by verifying

individuals seeking access to the HRA are authorized on the radiation work permit

(RWP).

9

Contrary to the above, on November 9, 2022, GE Hitachi Nuclear Energy failed to

establish positive controls over an entry to a posted HRA. Specifically, during the NRC

tour of the WEP building, the licensee failed to assign and brief an attendant per

procedures WI-27-105-01 and WI-27-105-15, and as a result the licensee failed to

maintain positive control over the posted HRA. (VIO 0500018/2022002-01)

The inspectors informed the significance determination using example 6.3.d.3 of the

NRC Enforcement Policy, dated January 14, 2022, regarding the failure to implement

procedures, where the failure has a low safety significance and the licensee

administrative requirement/limit issues example in the NRC Enforcement Manual,

Appendix E, Minor Violations - Examples, regarding the control of high radiation limits

where conditions exceed NRC regulatory limits. Additionally, the inspectors informed the

significance determination using the general screening criteria in section 6.0 of IMC 0612, Appendix E, Examples of Minor Issues, which describes the failure of one

radiological barrier to be of minor significance. The inspectors noted that this issue

involved a failure of multiple radiological barriers, including failure to follow procedures

WI-27-105-01 and WI-27-105-15, failure of radiation protection supervision oversight,

and failure to provide adequate instructions to workers of the area hazards, therefore the

issue is considered of more than minor significance.

The inspectors noted that while the building was posted as an HRA, the waste

processing room nor the area around the tank were posted or identified as having HRA

conditions. Further, until the inspectors queried the licensee, the higher dose areas were

not briefed. The inspectors were briefed to radiation work permit 2022-09 with a dose

rate limit of 100 mrem/hr. This RWP did not allow entry into HRA conditions. While no

actual entries to HRA conditions occurred, the inspectors noted that the above examples

are failures to provide adequate instructions to workers of radiological hazards.

5.3 Conclusions

The inspectors concluded that the licensee conducted its radiation control program in

accordance with license conditions and regulatory requirements, with one exception of

more than minor significance. The inspectors identified one Severity Level IV violation in

the HRA controls area of occupational radiation exposure.

The licensee monitored occupational exposures, and the results for 2021 - to date in

2022 were less than regulatory limits. The licensee continued to conduct annual

radiological surveys within each of the shutdown reactor structures as required by the

three licenses, and the licensee reported the results to the NRC in an annual report.

6 Radioactive Waste Treatment, and Effluent and Environmental Monitoring (84750)

6.1 Inspection Scope

The inspectors reviewed the licensees effluent and environmental monitoring program

for the facility. The objectives of this portion of the inspection effort were to ensure that

discharges of radioactive materials were adequately quantified and evaluated, and to

ensure that the radiological effluent and environmental program requirements were

effectively implemented.

6.2 Observations and Findings

10

a. Radioactive Waste Treatment

The WEP is designed to receive, transfer, store, process, and dispose of aqueous

radioactive waste liquids generated at the VNC. The evaporation process separates

radioactive products from the liquid by boiling the liquid in a closed tank. The steam

effluent is condensed in a separate chamber to relatively pure water while the

radioactive products remain in the evaporator to eventually be transferred to drums for

solidification and/or disposal. The inspectors conducted a walkdown of the waste

evaporator plant and compared system operations to applicable operating procedures.

The plant systems were not in service at the time of the inspection.

The inspectors observed the status of the equipment in the building. The 30,000-gallon

storage tank was out of service due to an annulus leak. The inspectors observed the

ozone/ultraviolet system where process liquids containing organics were processed. A

licensee representative indicated that this system was rarely used since the liquid

wastes did not normally contain organic material. The inspectors observed the locations

where the water was sampled prior to final evaporation and where the gaseous effluent

was monitored prior to release. Licensee representatives discussed how the evaporation

plant equipment worked and how air and water samples were collected.

The inspectors reviewed recent water and air sample results collected from the waste

evaporator plants liquid and effluent release points and discussed the results with the

licensees staff. The air samples were collected from the outlet of the exhaust air filters,

while the water samples were collected from the monitor tanks prior to release to the

atmosphere as steam. The sample results were less than the procedural action levels.

b. Effluent and Environmental Monitoring

Licenses DR-10 and DPR-1 for the EVESR and VBWR, respectively, require the

licensee to maintain records showing the radioactivity released or discharged into the air

or water beyond the effective control of the licensee as measured at the point of such

release or discharge. At the time of the inspection, the licensee had established and

implemented effluent and environmental monitoring programs in accordance with the

instructions provide in the Environmental Monitoring Manual, revision 6, and procedure

7.2, Radioactive Effluent Control, revision 13. Section 3.1 of the Environmental

Monitoring Manual requires the licensee to submit the results from the previous year to

the NRC by May 1st of each calendar year. The inspectors reviewed the 2021 results

(ML22068A248) and discussed the results with licensee staff.

The licensees effluent monitoring program included gaseous and liquid effluents.

Airborne effluents were continuously monitored at four operating building discharge

stacks. Three other stacks remained idle during 2021. Liquid effluents included industrial

wastewater, sanitary wastewater, and stormwater runoff. The licensees records indicate

that all releases were within the action level limits established in the Environmental

Monitoring Manual and site procedures.

The licensees environmental monitoring program included groundwater monitoring,

stream sediment sampling, vegetation sampling, air sampling, and gamma radiation

monitoring. At the time of the inspection, the licensee was sampling 10 monitoring wells

on either a quarterly or annual basis. One sediment sample was collected from a local

11

stream downgradient from the industrial wastewater and sanitary wastewater retention

basins. Vegetation was measured at two locations at the site boundary. In addition,

environmental air sampling was conducted at four stations generally located in the four

quadrants around the site. Finally, gamma radiation monitoring was conducted at 20

locations around the site. The inspectors noted that the 2021 sample results were less

than the respective action levels as presented in the Environmental Monitoring Manual

and site procedures.

To demonstrate compliance with the dose limits specified in 10 CFR 20.1101(d) and

10 CFR 20.1301(a), the licensee calculated the public doses at the site boundary using

the COMPLY computer code as allowed by Regulatory Guide 4.20, Constraint on

Releases of Airborne Radioactive Materials to the Environment for Licensees Other

Than Power Reactors. The inspectors reviewed some of the licensees input parameters

into the COMPLY code. Based on the data collected during 2021, the dose at the

property line from all gaseous emissions was calculated to be 0.5 millirem per year, a

calculated dose that was well below the annual limit of 100 millirem per year specified in

10 CFR 20.1301(a).

The inspectors observed the operation of one of four environmental air sampling

stations. The air sampler at that station was in service during the tour. The licensees

representative described the operation and calibration requirements for the air sampler.

The inspectors provided the licensee with potential design enhancements to reduce the

potential of rain damage to the filter element.

6.3 Conclusions

The licensee collected and analyzed all required effluent and environmental monitoring

samples, and no sample result exceeded the regulatory or procedural limits. Site

operations had a negligible effect on public doses during 2021.

7 Exit Meeting Summary

On November 9, 2022, the NRC inspectors presented the final inspection results to Mr.

Charles Pedley, Site Manager, and other members of the licensees staff. The inspectors

asked the licensee whether any material examined during the inspection should be

considered proprietary information. No proprietary information was identified.

12

SUPPLEMENTAL INSPECTION INFORMATION

KEY POINTS OF CONTACT

Licensee

C. Pedley, VNC Site Manager

J. Smyly, Environmental Health and Safety Manager

D. Heckman, Regulatory Affairs and Licensing Lead

K. Zanotto, Facilities Manager

J. Ayala, Project Management

D. Demore, Interim Radiation Safety Officer

INSPECTION PROCEDURES

IP 71801 Decommissioning Performance and Status Review at Permanently Shutdown Reactors

IP 69002 Class III Research and Test Reactors

IP 37801 Safety Reviews, Design Changes, and Modifications at Permanently Shutdown Reactors

IP 40801 Problem Identification and Resolution at Permanently Shutdown Reactors

IP 64704 Fire Protection Program at Permanently Shutdown Reactors

IP 83750 Occupational Radiation Exposure at Permanently Shutdown Reactors

IP 84750 Radioactive Waste Treatment, and Effluent and Environmental Monitoring

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

0500018/2022002-01 VIO Failure to positively control an unlocked posted high

radiation area to demonstrate compliance with 10

CFR 20.1601(a).

Closed

None

Discussed

None

LIST OF ACRONYMS

ADAMS Agency Documents Access and Management Systems

CFR Code of Federal Regulations

CR Condition Report

EVESR Empire State Atomic Development Associates Incorporated Vallecitos

Experimental Superheat Reactor

GEH GE Hitachi Nuclear Energy Americas, LLC

GETR General Electric Test Reactor

HRA high radiation area

LPSDAR Limited Post-Shutdown Decommissioning Activities Report

MW megawatt

NRC U.S. Nuclear Regulatory Commission

NOV Notice of Violation

RWP Radiation Work Permit

Attachment

VBWR Vallecitos Boiling Water Reactor

VIO Violation

VNC Vallecitos Nuclear Center

WEP Waste Evaporator Plant

2