M220157 November 22, 2022 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555-001
Subject:
Vallecitos Nuclear Center Limited Post Shutdown Decommissioning Activities Report Update
References:
- 3) GEH Letter, Vallecitos Nuclear Center Decommissioning Limited Post Shutdown Decommissioning Activities Report, (ADAMS Accession No. ML22264A325), September 21, 2022 GE Hitachi Nuclear Energy, LLC (GEH) is providing the enclosed update to the activities included in the Vallecitos Nuclear Center Limited Post Shutdown Decommissioning Activities Report (Ref 3).
If there are any questions regarding this report or additional information required, please contact me at the number above.
Sincerely,
- GEH Affidavit : Changes to the Vallecitos Nuclear Center Limited Post Shutdown Decommissioning Activities Report cc: NRC Region IV Administrator S. Anderson, NRC RIV J. Parrott, NMSS/DUWP/RDB CM 22-006 GE Hitachi Nuclear Energy Carlos Martinez Site Manager, Vallecitos Nuclear Center 6705 Vallecitos Road Sunol, CA 94586 USA T 925-495-9173 Carlos1.Martinez@ge.com
Changes to the Vallecitos Nuclear Center Limited Post Shutdown Decommissioning Activities Report