Change Letter to Tp Subsequent Renewed Licenses - March 17, 2022_Rev 1
ML22073A122
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/25/2022
From: Andrea Veil
NRC/NRR/DNRL/NLRP
To: Coffey B
Florida Power & Light Co
Thomas V
Shared Package
ML22073A121 List:
References
EPID L-2018-RNW-0002
Download: ML22073A122 (7)


Text

Mr. Bob Coffey Executive Vice President, Nuclear and Chief Nuclear Officer Florida Power & Light Company 700 Universe Boulevard Mail Stop EX/JB Juno Beach, FL 33408

SUBJECT:

TURKEY POINT NUCLEAR GENERATING, UNITS 3 AND 4MODIFICATION TO SUBSEQUENT RENEWED FACILITY OPERATING LICENSE NOS. DPR-31 AND DPR-41 IN CONJUNCTION WITH COMMISSION MEMORANDUM AND ORDER CLI-22-02 (EPID L-2018-RNW-0002)

Dear Mr. Coffey:

By letter dated December 4, 2019 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML19305C879), the U.S. Nuclear Regulatory Commission (NRC or the Commission) issued Subsequent Renewed Facility Operating License Nos. DPR-31 and DPR-41 to Florida Power & Light Company (FPL) for Turkey Point Nuclear Generating Unit Nos. 3 and 4 (Turkey Point, Units 3 and 4). Subsequent Renewed Facility Operating License Nos. DPR-31 and DPR-41 for Turkey Point, Units 3 and 4 were set to expire on July 19, 2052, and April 10, 2053, respectively.

Following the Commissions direction in the February 24, 2022, Memorandum and Order CLI-22-02 (ADAMS Accession No. ML22055A496), the NRC staff has modified the expiration dates for the subsequent renewed facility operating licenses to reflect the end dates of the previous renewed licenses. For Turkey Point, Units 3 and 4, the NRC staff has modified the subsequent renewed operating license expiration dates to July 19, 2032, and April 10, 2033, respectively. to this letter contains the modification to Subsequent Renewed Facility Operating License No. DPR-31 for Turkey Point, Unit 3. to this letter contains the modification to Subsequent Renewed Facility Operating License No. DPR-41 for Turkey Point, Unit 4.

March 25, 2022

B. Coffey Please contact your Licensing Project Manager or Mr. Vaughn Thomas, Subsequent and Renewed Facility Licenses Order Project Manager (301-415-5897), if you have any questions about this matter.

Sincerely, Andrea D. Veil, Director Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251

Enclosures:

1.

Page 8 of Turkey Point, Unit 3 Subsequent Renewed Facility Operating License No. DPR-31 2.

Page 8 of Turkey Point, Unit 4 Subsequent Renewed Facility Operating License No. DPR-41 cc: Listserv Signed by Veil, Andrea on 03/25/22 Page 8 of Turkey Point Nuclear Generating, Unit 3, Subsequent Renewed Facility Operating License No. DPR-31

spray piping headers (3A and 3B) at penetrations P-19A and P-19B to a minimum plant elevation of 65 feet inside containment. FPL shall notify the NRC in writing within 60 days following completion of the refueling outage during which the piping replacement is completed. The notification will confirm the elevation of the air-to-borated-water interface inside the piping and confirm that the installation of the stainless steel piping exceeds this elevation.

4.

This subsequent renewed license is effective as of the date of issuance, and shall expire at midnight July 19, 2032.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Ho K. Nieh, Director Office of Nuclear Reactor Regulation Attachments:

Appendix A - Technical Specifications for Unit 3 Appendix B - Environmental Protection Plan Date of Issuance: December 4, 2019 Page 8 of Turkey Point Nuclear Generating, Unit 4, Subsequent Renewed Facility Operating License No. DPR-41

the air-to-borated water interface inside the piping, and confirm that the installation of the stainless steel piping exceeds this elevation.

4.

This subsequent renewed license is effective as of the date of issuance, and shall expire at midnight April 10, 2033.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Ho K. Nieh, Director Office of Nuclear Reactor Regulation Attachments:

Appendix A - Technical Specifications for Unit 4 Appendix B - Environmental Protection Plan Date of Issuance: December 4, 2019

PKG ML22073A121

  • via e-mail NRR-106 OFFICE DNRL/ NLRP/PM DNRL/ NLRP/LA QTE*

DORL/LPLII-2/BC NAME VThomas YEdmonds JDougherty DWrona DATE 03/14/2022 03/15/2022 03/15/2022 03/16/2022 OFFICE DNRL/ NLRP/BC OGC (NLO)

NRR/DNRL/D NRR/D NAME LGibson STurk BSmith AVeil DATE 03/17/2022 03/17/2022 03/18/2022