NRC POV Inspection (IP 71111.21N.02) Information Request Carman, Paul <Paul.Carman@nrc.gov>

Mon 3/1/2021 4:52 PM To: maria.s.groshner@dominionenergy.com <maria.s.groshner@dominionenergy.com>

Cc: Baptist, James <James.Baptist@nrc.gov>; Carman, Paul <Paul.Carman@nrc.gov>

2 attachments (1 MB) 2021 SUR - POV Inspection Information Request.pdf; Surry POV Data.docx; Good afternoon Maria, Thank you for working with me to get the POV inspection started. Attached is the initial document request and database file with the initial 30 valves for the POV inspection. PLEASE NOTE: the Access database is sent as a Word document in order to be able to transmit via email. You will need to change the file extension of the "Surry POV Data.docx" file from ".docx" to ".accdb" to convert it back into an Access file. Please provide as much of the requested information as possible, if it is readily available.

When filling out the database, you may have to enable content before using. This is only done once and shouldnt pop up again. It is understood that not all fields will be entered. Also, please note that when entering data into the various fields there is a text box at the bottom left of the data entry form that details to the person entering the data what needs to be entered. For example, when on the Docket field the text at the bottom will state Enter the Docket number last 3 digits. Also, when entering text in the comment field and it is desired to start a new line, it is necessary to hit control enter to start a new line.

Feel free to reach out to me with any questions regarding the inspection (inspection procedure, information request, database file, etc.). I appreciate all the support with this and I'm looking forward to the inspection.

Thanks, Paul Paul Carman Senior Reactor Inspector U. S. Nuclear Regulatory Commission - Region II 404-997-4471 (o)

Paul.Carman@nrc.gov

ML21061A029 Surry Power Station - Design Bases Assurance Inspection (Programs)

Initial Information Request Inspection Procedure: 71111.21N, Design Bases Assurance Inspection (Programs),

Attachment 21N.02, Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements, dated January 1, 2021 (ADAMS ML20220A667)

Inspection Dates: Information Gathering Visit: June 14-18, 2021 Preparation Week: June 28 - July 2, 2021 Onsite Week 1: July 12-16, 2021 Onsite Week 2: July 26-30, 2021 Inspection Report: 05000280/2021010 AND 05000281/2021010 (Standalone Inspection Report)

Inspectors: P. Carman (Lead/Mechanical), M. Riley (Electrical), and M.

Schwieg (Electrical)

The purpose of this letter is to notify you that three inspectors from Region II will conduct an inspection at your site in accordance with Inspection Procedure 71111.21N, Design Bases Assurance Inspection (Programs), Attachment 21N.02, Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements. This is not considered a team inspection. The inspection will evaluate the implementation of the programs regarding power operated valves (POVs) for compliance with 10 CFR 50.55a at the Surry Power Station. The inspectors will select samples of components that are risk significant and within the scope of the program.

On June 14, 2021, Mr. Paul Carman, a Senior Reactor Inspector from the NRCs Region II office, will begin the inspection with an information gathering visit to the site, if pandemic conditions allow. The purpose of the visit is to become familiar with your program and procedures which are supposed to ensure your compliance with 10 CFR 50.55a for POVs. This will require meetings with members of your staff to discuss aspects of the program including any specific applicable regulatory commitments made by the site and your use of regulatory guides or industry standards. Your processes for generating field instructions for POV switch settings and test acceptance criteria from design documents is also expected to be discussed. Plant walkdowns to observe the potential inspection sample are expected to occur during the information gathering visit, if a site visit is made.

The enclosure lists documents that are needed prior to the information gathering visit. Please provide the referenced information to the Region II Office by June 7, 2021. Additional documents may be requested during the information gathering visit. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for inspection preparation. The additional information should be provided to the Inspectors in the Region II office by June 25, 2021. During the information gathering visit, Mr. Carman will also discuss the following inspection support administrative details: (1) availability of knowledgeable plant engineering and licensing personnel to serve as points of contact during the inspection, (2) method of tracking inspector requests during the inspection, (3) computer access, (4) working space, (5) arrangements for site access, and (6) other applicable information.

INFORMATION REQUEST FOR SEQUOYAH NUCLEAR PLANT DESIGN BASES ASSURANCE INSPECTION (PROGRAMS)

(10 CFR 50.55a POWER OPERATED VALVE PROGRAMS IMPLEMENTATION)

Prior to the information gathering visit, please provide the information electronically in .pdf files, Excel, or other searchable format on CDROM (or FTP site, SharePoint, etc.). The CDROM (or website) should be indexed and hyperlinked to facilitate ease of use.

Contact Information: Paul Carman (404) 997-4471 Paul.Carman@nrc.gov Information Gathering Visit: An information gathering visit is currently scheduled the week of June 14, 2021. During this visit, we would like to identify the component samples for this inspection. Wed like to meet with valve specialists to discuss the upcoming inspection and our sample selection process. Purposes of the site visit are to: (a) discuss the scope of the planned inspection; (b) obtain advance information to review in preparation for the inspection; (c) ensure that the information to be reviewed is available at the beginning of the inspection; and (d) verify that logistical issues (such as obtaining both site and computer system access and arranging the location of the inspection team working area) will be resolved prior to inspector arrival. Assuming that a site visit will be completed, please reserve a room during the scheduled inspection dates. We request the room have a telephone, wireless internet access, and a licensee computer with access to procedures, corrective action program documents, and a printer.

Logistics:

Information gathering visit: June 14-18, 2021 Onsite inspection weeks: July 12-16, 2021 and July 26-30, 2021 Please plan for an entrance meeting in the afternoon on Monday, July 12, 2021 (Time TBD during the information gathering visit, approximately 15 minutes). The date and time of the exit meeting will be discussed at a later date. In addition, Id like to have a daily debrief with your inspection support staff at a convenient time in the afternoons for both onsite inspection weeks (Time TBD, approximately 30 minutes).

We will need a conference room as workspace for the inspectors. We will also need an area available for conducting interviews. Please provide access to your document system (preferably at least one computer in our conference room), nearby printers, and Wi-Fi access.

During the information gathering visit, please provide info on (1) conference room location &

phone number, (2) cafeteria location/hours, and (3) engineering staff normal working hours.

Also, please let me know if there are any potential resource conflicts during our scheduled inspection weeks (Fridays off, EOP drills, management retreats) and well do our best to accommodate.

Team Members: Paul Carman (Inspection Lead, Mechanical)

Marcus Riley (Electrical)

Mark Schwieg (Electrical)

Please verify the status of access authorization and remaining requirements for unescorted access for each inspector. Please provide me with a list of exceptions, and I will take action to address them.

Info Request:

1. A word-searchable UFSAR. If not available in a single file per unit, please ensure a collective table of contents is provided.
2. Indicate if the NRC has granted a license amendment to categorize structures, systems, and components in accordance with 10 CFR 50.69, and if so, please provide the risk-informed safety category of the POVs important to safety at the site.
3. All NRC correspondence regarding the stations response to Generic Letter (GL) 89-10 and GL 96-05, including any NRC requests for additional information (RAIs) and any NRC Safety Evaluation Report(s) associated with your sites MOV program. Include any NRC inspection reports that were conducted to close out your GL responses.
4. Any NRC correspondence regarding the stations commitments for the AOV program (if any). Please include any AOV-related regulatory commitments that are currently being tracked in the stations regulatory commitment management program.
5. Site (and corporate if applicable) procedures associated with implementation of the inservice testing (IST) program required by 10 CFR 50.55a.
6. Site (and corporate if applicable) procedures associated with implementation of the MOV program required by 10 CFR 50.55a(b)(3)(ii) and/or ASME OM Code Mandatory Appendix III.
7. Site (and corporate if applicable) procedures associated with implementation of the AOV program.
8. List of corrective action documents related to the MOV and AOV programs since January 1, 2016.
9. List of modifications, repairs, or replacement of safety related power operated valves (motor, air, solenoid, hydraulic, and pyrotechnic operated) completed since January 1, 2016, including date completed.
10. Any self-assessments or QA assessments of the MOV/AOV programs (performed since January 1, 2016).
11. List of systems (system numbers/designators and corresponding names).
12. List of site contacts that will be associated with the inspection.
13. For the POVs listed on the accompanying database, please fill in as much of the indicated data as possible and provide the database back to the inspectors.

PAPERWORK REDUCTION ACT STATEMENT This letter contains voluntary information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB) approved these information collections (approval number 3150-0011). The burden to the public for these information collections is estimated to average 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> per response. Send comments regarding this information collection to the Information Services Branch, Office of the Chief Information Officer, Mail Stop: O-1F13, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and Budget, Washington, DC 20503.