IR 05000280/2023004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000280/2023004 and 05000281/2023004
ML24043A079
Person / Time
Site: Surry  
Issue date: 02/09/2024
From: Matthew Fannon
NRC/RGN-II/DRP/RPB4
To: Carr E
Virginia Electric & Power Co (VEPCO)
References
IR 2023004
Download: ML24043A079 (16)


Text

SUBJECT:

SURRY POWER STATION - INTEGRATED INSPECTION REPORT 05000280/2023004 AND 05000281/2023004

Dear Eric S. Carr:

On December 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Surry Power Station. On January 24, 2024, the NRC inspectors discussed the results of this inspection with David Wilson, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Surry Power Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Surry Power Station.

February 9, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Matthew S. Fannon, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 05000280 and 05000281 License Nos. DPR-32 and DPR-37

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000280 and 05000281

License Numbers:

DPR-32 and DPR-37

Report Numbers:

05000280/2023004 and 05000281/2023004

Enterprise Identifier:

I-2023-004-0031

Licensee:

Virginia Electric and Power Company

Facility:

Surry Power Station

Location:

Surry, VA

Inspection Dates:

October 01, 2023 to December 31, 2023

Inspectors:

M. Donithan, Senior Operations Engineer

D. Jung, Resident Inspector

S. Kennedy, Senior Resident Inspector

M. Meeks, Senior Operations Engineer

M. Schwieg, Senior Reactor Inspector

Approved By:

Matthew S. Fannon, Chief

Reactor Projects Branch 4

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Surry Power Station, in accordance with

the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for

overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified

non-cited violation is documented in report section: 71152A.

List of Findings and Violations

Non-functional Fire Barrier associated with Unit 1 Cable Tray Room

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000280/2023004-01

Open/Closed

[H.1] -

Resources

71111.05

The inspectors identified a finding of very low safety significance (Green) and an associated

non-cited violation (NCV) of License Condition 3.I, Fire Protection, associated with the

licensee's failure to implement and maintain in effect, the provisions of the approved fire

protection program as described in the Updated Final Safety Analysis Report (UFSAR), which

resulted in non-functional fire penetrations in the Unit 1 cable tray room.

Failure to Effectively Monitor Maintenance Rule Scoped Components

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000280,05000281/2023004-02

Open/Closed

[P.2] -

Evaluation

71111.12

The inspectors identified a finding of very low safety significance (Green) and associated non-

cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) 50.65(a)(2) for

failure to demonstrate effective control of the performance of maintenance rule scoped

components through appropriate preventive maintenance. Specifically, the licensee failed to

monitor performance of the 96-inch circulating water expansion joint spray shields, in

accordance with their preventive maintenance program and did not implement (a)(1) goals

and corrective actions.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 operated at or near rated thermal power for the entire inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix DProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 2515,</br></br>Appendix D" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., Plant Status, observed risk significant activities, and completed on-site portions of

IPs. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel to assess licensee performance and compliance with Commission rules

and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated readiness for seasonal extreme weather conditions prior to

the onset of seasonal cold temperatures for the following systems:

refueling water storage tanks

emergency diesel generators (EDGs)

fire protection system

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1)

1-VS-E-4B, '4B' main control room chiller, following repair on November 27, 2023

(2)

Unit 1 auxiliary feedwater system following completion of 1-OPT-FW-003, Steam

Driven Auxiliary Feedwater Pump 1-FW-P-2 Performance Test, on November 29,

2023

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1)

Unit 1 cable tray room, fire zone 46, elevation 45 feet - 3 inches, on October 16,

2023

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1)

The licensee completed the annual requalification operating examinations required to

be administered to all licensed operators in accordance with Title 10 of the Code of

Federal Regulations 55.59(a)(2), "Requalification Requirements," of the NRC's

"Operator's Licenses." The inspector performed an in-office review of the overall

pass/fail results of the individual operating examinations, and the crew simulator

operating examinations in accordance with Inspection Procedure (IP) 71111.11,

"Licensed Operator Requalification Program and Licensed Operator Performance."

These results were compared to the thresholds established in Section 3.03,

"Requalification Examination Results," of IP 71111.11.

The inspectors evaluated the licensed operator examination failure rates for the

requalification annual operating examinations completed on March 17, 2023.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2

Samples)

(1)

The inspectors observed and evaluated licensed operator performance in the control

room during the performance of 1-PT-25.1, Quarterly Testing of Condensate and

Service Water System Valves, on November 13, 2023.

(2)

The inspectors observed and evaluated licensed operator performance in the control

room during the performance of 0-OP-VS-006, Control Room and Relay Room

Ventilation System on November 27, 2023, and 0-OPT-VS-001, Main Control Room

A/C System Pump and Valve In-service Testing, on December 19, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)

The inspectors observed licensed operator requalification training involving scenarios

which included a loss of chemical and volume control system letdown during grid

instability and a loss of coolant accident outside of containment on October 12, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (5 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components (SSCs) remain capable of performing their intended

function:

(1)

Unit 1 and Unit 2 circulating water system spray shield maintenance practices

(condition report [CR] 1231640)

(2)

Unit 1 1-VS-E-4B, '4B' main control room chiller reliability (CR1210646, CR1210932,

CR1211314, CR123428, CR1214802, CR1221869, CR1224811, CR1225502,

CR1225718, CR1240870, and CR1242640)

(3)

Canal level probes reliability (CR1236508, CR1236724, CR1237102, CR1238870,

and CR1240613)

(4)

Control room isolation dampers reliability (CR12300047, CR1230765, CR1233787,

CR1238582, CR1241210, and CR1241731)

(5)

2-IA-C-4A, Unit 2 containment instrument air compressor reliability (CR1238454,

CR1235314, CR1236542, and CR1237897)

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1)

Unit 1 and Unit 2 emergent risk assessment due to failure of 01-VS-E-4B, '4B' control

room chiller, and service water leak from 01-VS-P-1C, control and relay room chiller

condenser '4C' service water pump, on October 18, 2023

(2)

Unit 1 and Unit 2 elevated risk during #1 EDG surveillance on December 4, 2023

(3)

Unit 1 and Unit 2 emergent risk assessment due to #2 EDG declared inoperable as a

result of battery voltage below operability threshold on December 13, 2023

(4)

Unit 1 and Unit 2 elevated risk assessment during performance of 0-OPT-VS-001,

Main Control Room Air Conditioning System Pump and Valve Inservice Testing, and

switchyard 500 kilovolts line switching on December 19, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1)

CR1240848, Unit 1 containment area radiation monitor (high range) annunciator 0-

RMA-A1, in containment high radiation alert/trouble, received on October 18, 2023

(2)

CR1240698, #2 EDG fuel oil pressure trouble on initial engine start on October 16,

2023

(3)

CR1242190, 2-SW-FI-205B, recirculation heat exchangers B and C service water

supply flow, declared non-functional on October 29, 2023

(4)

CR1245002, 2-CH-P-210B, '2B' charging pump auxiliary oil pump, was found cycling

on and off on November 29, 2023

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1

Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)

Design equivalent change package SU-23-00122, Modify Lower Bearing Drip Pan, on

December 28, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system

operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (7 Samples)

(1)

0-ECM-0901-02, Opening and Sealing of Fire Barriers, following repair of Unit 1 cable

tray room penetrations on September 28, 2023 (work order [WO] 38204336276)

(2)

Post installation inspection following sealing gap along northwest corner of wall Unit 1

cable tray room and mechanical equipment room #1 on September 28, 2023

(WO38204336313)

(3)

Visual leak inspection following the repair of service water leak from 01-VS-P-1C,

control and relay room chiller condenser '4C' service water pump, on October 18,

2023 (WO38204337198)

(4)

Post repair inspection following 1-VS-MOD-103A, control room supply isolation

damper, repair on November 2, 2023 (WO38204233951)

(5)

0-MPM-1900-02, Flood Protection Backflow Preventer Testing and Installation,

following semi-annual flood protection planned maintenance on November 2, 2023

(WO38204305711)

(6)

Post repair inspection following Unit 1 1-VS-E-4B, '4B' main control room chiller,

instrumentation tubing relocation on December 14, 2023 (WO38204321174)

(7)

1-IPM-SI-L-920, SI Accumulator Tank 1-SI-TK-1A Level Loop L-1-920 Calibration,

following 'A' safety injection accumulator level channel 1 indicator repair on December

28, 2023 (WO38204339057)

Surveillance Testing (IP Section 03.01) (1 Sample)

(1)

0-OPT-VS-001, Main Control Room Air Conditioning System Pump and Valve

Inservice Testing, on December 19, 2023

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1)

0-MPM-1960-01, Semi-Annual or Annual Test of Beyond Design Bases (BDB)

Diverse and Flexible Coping Strategies Equipment, BDB auxiliary feedwater pump

'2C', on November 14, 2024

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

(1)

The inspector observed and evaluated the conduct of a simulator-based licensed

operator requalification training evolution involving a steam generator tube rupture

resulting in an Alert declaration on October 24, 2023.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1)

Unit 1: October 2022 through June 2023

(2)

Unit 2: October 2022 through June 2023

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1)

Unit 1: October 2022 through June 2023

(2)

Unit 2: October 2022 through June 2023

71152A - Annual Follow-up Problem Identification and Resolution

Annual Follow-up of Selected Issues (Section 03.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

(1)

Evaluation of Unit 1 cable tray room configuration for design adequacy and regulatory

compliance on December 14, 2023 (CA11362707)

(2)

Evaluation of the EDGs' protection against the effects of tornado-generated

differential pressure (CR1219861, CR1237702, CR1247481, CA11199376, and

CA12149255)

71152S - Semiannual Trend Problem Identification and Resolution

Semiannual Trend Review (Section 03.02) (1 Sample)

(1)

The inspectors reviewed the licensees corrective actions program and related

documents such as trend reports, licensee performance indicators, and system health

reports for potential adverse trends that might be indicative of a more significant

safety issue.

INSPECTION RESULTS

Non-functional Fire Barrier associated with Unit 1 Cable Tray Room

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000280/2023004-01

Open/Closed

[H.1] -

Resources

71111.05

The inspectors identified a finding of very low safety significance (Green) and an associated

non-cited violation (NCV) of License Condition 3.I, Fire Protection, associated with the

licensee's failure to implement and maintain in effect, the provisions of the approved fire

protection program as described in the UFSAR, which resulted in non-functional fire

penetrations in the Unit 1 cable tray room.

Description: On September 27, 2023, the inspectors performed a walkdown of the Unit 1

cable tray room, Fire Zone 46, elevation 9 feet - 6 inches. The inspectors identified three

penetrations on the wall between the Unit 1 cable tray room and the #1 mechanical

equipment room that did not appear to be completely sealed. ECM-0901-02, Opening and

Sealing of Fire Barriers, stated that the vendors required fire-retardant material depth is 10 -

12 inches. The sites Engineering staff determined that the depth of the fire-retardant material

was slightly less than 10 inches and contained voids and gaps.

CM-AA-FPA-100, Fire Protection/Appendix R (Fire Safe Shutdown) Program, states that

penetration seals must provide equal or greater fire rating than that of the fire barrier. The fire

rating of the fire barrier wall between the Unit 1 cable tray room and the #1 mechanical

equipment room is three hours. Engineering determined that the fire barrier would not meet

the three-hour requirement due to the degraded as-found condition of the penetrations.

As a result, Operations declared the fire barrier wall between the Unit 1 cable tray room and

the #1 mechanical equipment room non-functional and established an hourly fire watch in

accordance with Technical Requirements Manual (TRM) 3.7.8. In addition to the fire watch,

TRM 3.7.8 required that the penetrations be restored to a functional condition within seven

days.

The installation of the cables and penetrations occurred during a turbine control system

project from October 2022 to March 2023. The licensee determined that cable penetrations

were opened and originally sealed properly per 0-ECM-0901-02. However, the cables for the

project were coiled next to the penetration during cure time of the penetrations and not yet

placed in the cable tray. Following the completion of the cure time the cable installation

continued. This moved the cables from the resting position in the penetration foam, allowing

gaps and voids to form. The voids and gaps caused the depth of the fire-retardant material to

not meet the standard.

Corrective Actions: In addition to declaring the penetration non-functional and entering the

associated TRM action statement, the licensee conducted a human performance review and

initiated a corrective action assignment to update the procedure guidance for an additional

inspection if the cables are moved following final acceptance of the penetration.

Corrective Action References: CR1239083

Performance Assessment:

Performance Deficiency: The inspectors found that the licensees failure to implement the fire

protection program in accordance with licensee procedure CM-AA-FPA-100, which resulted

in degraded fire penetrations, is a performance deficiency within the licensees ability to

foresee and prevent.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Protection Against External Factors attribute of the

Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure

the availability, reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, the vendor specification for the depth of fire-

retardant material was not met and the as-left condition would have impacted the ability of the

penetration to function as a three-hour fire rated barrier. The inspectors used IMC 0612,

Appendix EProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 0612,</br></br>Appendix E" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., Examples of Minor Issues, dated January 1, 2021, to inform answers to the

more than minor screening questions and found this condition consistent with more than

minor Example 2.d.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix FProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 0609</br></br>Appendix F" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., Fire Protection and Post - Fire Safe Shutdown SDP. The finding was

determined to be of very low safety significance (Green) because there is adequate automatic

suppression on either side of the fire confinement element in accordance with IMC 0609,

Appendix FProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 0609,</br></br>Appendix F" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., Attachment 1, Step 1.4.4: Fire Confinement, Question 1.4.4-B.

Cross-Cutting Aspect: H.1 - Resources: Leaders ensure that personnel, equipment,

procedures, and other resources are available and adequate to support nuclear safety.

Specifically, the procedures used for sealing the fire barrier penetrations did not have

guidance for final inspection after the cable was moved within a cable tray, conduit, or

terminated.

Enforcement:

Violation: License Condition 3.I, Fire Protection, states in part, The licensee shall

implement and maintain in effect the provisions of the approved fire protection program as

described in the Updated Final Safety Analysis Report UFSAR Section 9.10.1, Design

Bases, states in part, Compliance with these criteria is contained in the following

documents Fire Protection Program documents and the associated Administrative

Procedures describe the administrative and technical controls. Licensee procedure CM-AA-

FPA-100, Fire Protection/Appendix R (Fire Safe Shutdown) Program, states, in part,

penetration seals must provide equal or greater fire rating than that of the fire barrier.

Contrary to the above, from approximately October 2022 through September 27, 2023, the

licensee failed to implement and maintain in effect, the provisions of the approved fire

protection program as described in the UFSAR, resulting in noncompliance with fire

penetration rating requirements as documented CM-AA-FPA-100. Specifically, the licensee

did not ensure that three fire penetration seals established on the fire barrier wall between the

Unit 1 cable tray room and the #1 mechanical equipment room, contained sufficient fire-

retardant material to provide a fire rating equal to or greater than that of the fire barrier.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Effectively Monitor Maintenance Rule Scoped Components

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000280,05000281/2023004-02

Open/Closed

[P.2] -

Evaluation

71111.12

The inspectors identified a finding of very low safety significance (Green) and NCV of 10 CFR 50.65(a)(2) for failure to demonstrate effective control of the performance of maintenance rule

scoped components through appropriate preventive maintenance. Specifically, the licensee

failed to monitor performance of the 96-inch circulating water expansion joint spray shields, in

accordance with their preventive maintenance program and did not implement (a)(1) goals

and corrective actions.

Description: Each of the 96-inch circulating water inlet, intermediate outlet, and outlet

expansion joints is enclosed by a removable flow restriction shield. These spray shields act

as a passive flow restraint to limit water flowrate in the event of a ruptured expansion joint.

On June 22, 2023, the inspectors performed a walkdown of flood protection measures in the

Units 1 and 2 turbine building. During the walkdown, the inspectors identified gasket material

that was loose and hanging from between the spray shield and the lower flange on the 2-CW-

REJ-201D, condenser water box circulating water pump outlet expansion joint. The licensee

determined that the gasket material was loose because the gap between the spray shield and

the lower flange was excessive and did not meet the acceptance criteria for gap size. The

license established a flood watch, conducted a repair of the spray shield, and entered the

issue into their corrective action program as CR1231640.

The inspectors reviewed the licensee's evaluation of CR1231640 to ascertain the cause of

the excessive gap measurement and to follow up on the licensees extent of condition review

and maintenance practices associated with circulating water system spray shields. The

licensee determined that the mostly likely cause of the excessive gap between the spray

shield and lower flange was thermal movement/expansion as the condenser is in service. The

licensees corrective actions included procedurally adding a buffer zone to account for

potential spray shield expansion that could occur during the 18-month period between

inspections of the circulating water system expansion joints and measuring the gap on the

remaining circulating water spray shields to determine any extent of condition.

The inspectors determined that the licensee did not implement the requirements of ER-AA-

MRL-100, Implementing Maintenance Rule. ER-AA-MRL-100, Attachment 6, Performance

Monitoring Information, Section 2.1.6, Reliability Non-Risk Significant Functions, states, A

measure of the expectation (assuming that the SSC is available), is that the SSC will perform

its function upon demand at any future instant in time. A failure of an SSC within a non-risk

significant function is an indicator of reliability which may require further evaluation for (a)(1).

The inspectors identified that the licensee did not have a maintenance activity in place to

ensure that the spray shield would function upon demand at any future instant. Specifically,

the licensee did not have an action in place to evaluate the validity of the buffer zone to

ensure that the as-left gap would not expand above the design value prior to the next

circulating water system expansion joint inspection activity. Alternatively, the licensee did not

have an activity in place such as as-found gap measurements, periodic measurements, or

walkdowns, to verify that the gap would not expand beyond the design value. In addition, the

inspectors identified that the licensee did not evaluate if the circulating water system

maintenance rule function CW008, To provide a means to minimize out leakage should a

circulating water expansion joint fail (spray shield), require further evaluation for (a)(1). This

issue could result in licensee not being aware of the spray shields being non-functional until a

flooding event due to expansion joint failure occurs.

Corrective Actions: The licensee entered the issue into their corrective action program for

further evaluation.

Corrective Action References: CR1248766

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensees failure to implement

the requirements of ER-AA-MRL-100, Implementing Maintenance Rule, Revision 15, was a

performance deficiency reasonably within the licensees ability to foresee and prevent.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Equipment Performance attribute of the Mitigating

Systems cornerstone and adversely affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, due to a lack of monitoring of the circulating water

expansion joint spray shields, the licensee failed to demonstrate that the performance of the

system is being effectively controlled through maintenance. This could result in the licensee

not being aware of the spray shields being non-functional until a flooding event due

expansion joint failure occurs. The condition is similar to the Inspection Manual Chapter 0612

Appendix EProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 0612</br></br>Appendix E" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. more than minor Example 8.g.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix AProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 0609</br></br>Appendix A" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., The Significance Determination Process (SDP) for Findings At-Power. Using

Inspection Manual Chapter 0609, Appendix A, Exhibit 2, Mitigating Systems Screening

Questions, Section A, the screening questions, were all answered as NO; therefore, the

inspectors determined the finding was of very low safety significance (Green).

Cross-Cutting Aspect: P.2 - Evaluation: The organization thoroughly evaluates issues to

ensure that resolutions address causes and extent of conditions commensurate with their

safety significance. Specifically, resolutions did not fully address the cause of thermal

expansion to satisfy the expectation that the SSC will perform its function upon demand at

any future instant in time.

Enforcement:

Violation: 10 CFR 50.65(a)(1), requires, in part, each holder of an operating license for a

nuclear power plant under this part shall monitor the performance or condition of structures,

systems, or components, against licensee-established goals, in a manner sufficient to provide

reasonable assurance that these structures, systems, and components, as defined by 10 CFR 50.65(b), are capable of fulfilling their intended functions. 10 CFR 50.65(a)(2), requires,

in part, that monitoring as specified in 10 CFR 50.65(a)(1) is not required where it has been

demonstrated that the performance or condition of a structure, system, or component is being

effectively controlled through the performance of appropriate preventive maintenance, such

that the structure, system, or component remains capable of performing its intended function.

Contrary to the above, prior to January 19, 2024, the licensee failed to effectively monitor the

performance or condition of a structure, system, or component through the performance of

appropriate preventive maintenance, such that the structure, system, or component remained

capable of performing its intended function. Specifically, the licensee failed to monitor

performance of the 96-inch circulating water expansion joint spray shield, a maintenance rule

scoped system, in accordance with their preventive maintenance program and did not

implement (a)(1) goals and corrective actions.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Licensee-Identified Non-Cited Violation

71152A

This violation of very low safety significance was identified by the licensee and has been

entered into the licensee corrective action program and is being treated as a non-cited

violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: License Condition 3.I, Fire Protection, states in part, The licensee shall

implement and maintain in effect the provisions of the approved fire protection program as

described in the Updated Final Safety Analysis Report UFSAR Section 9.10.1, Design

Bases, states in part, Compliance with these criteria is contained in the following

documents Fire Protection Program documents and the associated Administrative

Procedures describe the administrative and technical controls. Licensee procedure CM-AA-

FPA-100, Fire Protection/Appendix R (Fire Safe Shutdown) Program, states, in part,

Penetration seals must provide equal or greater fire rating than that of the fire barrier. The

licensee identified a 10 drain line penetrating the fire barrier between the technical support

center and the Unit 1 cable tray room that did not provide the required three hour or greater

fire rating.

Significance/Severity: Green. The inspectors assessed the significance of the finding using

IMC 0609 Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. The finding was

determined to be of very low safety significance (Green) because there is an adequate

automatic suppression system on either side of the fire confinement element in accordance

with IMC 0609, Appendix F, Attachment 1, Step 1.4.4: Fire Confinement, Question 1.4.4-B.

Corrective Action References: CR1220302

Minor Violation

71152A

No Design Control Measure to Verify Protection against Tornado Differential Pressure

Minor Violation: Title 10 CFR 50, Appendix B, Criterion III, Design Control, requires, in part,

the licensee to have design control measures for verifying or checking the adequacy of

design, such as by the performance of design reviews, using alternate or simplified

calculational methods, or by the performance of a suitable testing program. Contrary to the

above, from at least July 24th, 2023, until January 23, 2024, the licensee did not have a

design control measure in place to verify the EDGs were protected against the effects of the

tornado-generated pressure differential.

Screening: The inspectors determined the performance deficiency was minor because if left

uncorrected, the performance deficiency would not lead to a more significant safety

concern. Specifically, the licensee evaluated the radiator louver design. The design was

similar in construction to industry tornado-rated louvers with a pressure rating of three pounds

per square inch differential (psid). Therefore, the licensee determined that the louver could

withstand a pressure difference up to three psi and the EDG would remain operable. Based

on this evaluation, there was reasonable assurance the EDGs could withstand the differential

pressure effects from a design-basis tornado.

Enforcement: This failure to comply with 10 CFR Part B, Criterion III, Design Control

constitutes a minor violation that is not subject to enforcement action in accordance with the

NRCs Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On January 24, 2024, the inspectors presented the integrated inspection results to David

Wilson, Site Vice President, and other members of the licensee staff.