MONTHYEARIR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) IR 05000280/20220062023-03-0101 March 2023 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2022006 and 05000281/2022006 ML22339A1582022-11-30030 November 2022 Requalification Inspection Notification Letter IR 05000280/20220052022-08-24024 August 2022 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Reports 05000280/2022005 and 05000281/2022005) ML22223A1192022-08-14014 August 2022 RP Inspection Document Request Letter Final ML22168A0272022-06-15015 June 2022 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000280/2022404; 05000281/202240 IR 05000280/20210062022-03-0202 March 2022 Annual Assessment Letter for Surry Power Station, Units 1 and 2 (Reports No. 05000280/2021006 and 05000281/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections IR 05000280/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for Surry Power Station, Units 1 and 2 (05000280/2021005 and 05000281/2021005) IR 05000280/20210012021-08-26026 August 2021 Updated Inspection Plan for Surry Power Station, Units 1 and 2 -(05000280/2021001 and 05000281/2021001) ML21239A0052021-08-26026 August 2021 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - (Report 05000280/2021001 and 05000281/2021001) IR 05000280/20200062021-03-0303 March 2021 Annual Assessment Letter for Surry Power Station, Units 1 and 2 NRC Inspection Reports 05000280/2020006 and 05000281/2020006 ML21061A0292021-03-0101 March 2021 2021 Sur - POV Inspection Information Request ML21050A0352021-02-18018 February 2021 Radiation Safety Baseline Inspection Information Request ML20315A2492020-11-0909 November 2020 Requal Inspection Notification Letter W Materials List IR 05000280/20200052020-08-24024 August 2020 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2020005 and 05000281/2020005) ML20175A7802020-06-23023 June 2020 Heat Sink RFI ML20092J5002020-04-0101 April 2020 Radiation Safety Baseline Inspection Information Request IR 05000280/20190062020-03-0303 March 2020 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2019006 and 05000281/2019006 IR 05000280/20190052019-08-27027 August 2019 Updated Inspection Plan for Surry Power Station, Units 1 and 2, NRC Report 05000280/2019005 and 05000281/2019005 IR 05000280/20180062019-03-0404 March 2019 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Report 05000280/2018006 and 05000281/2018006 ML19057A1052019-02-26026 February 2019 License Renewal Phase 4 2019003 RFI - SD ML18283A7332018-10-0101 October 2018 Rad Safety Inspection RFI IR 05000280/20180052018-08-23023 August 2018 Updated Inspection Plan for Surry Power Station Units 1 and 2, NRC Report 05000280/2018005 and 05000281/2018005 ML18215A1252018-08-0303 August 2018 U2 ISI SGI 2018004 - Notification of Inspection and RFI (Public) IR 05000280/20170062018-02-28028 February 2018 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2017006 and 05000281/2017006, 05000280/2017402 and 05000281/2017402, 05000280/2017501 and 05000281/2017501 ML18037B1092018-02-0505 February 2018 Emergency Preparedness Inspection and Request for Information ML17290A0592017-10-13013 October 2017 Radiation Safety Inspection Document Request IR 05000280/20170052017-08-21021 August 2017 Updated Inspection Plan for Surry Power Station, Units 1 and 2 - Report 05000280/2017005 and 05000281/2017005 IR 05000280/20160062017-03-0101 March 2017 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - Report 05000280/2016006 and 05000281/2016006 ML16307A1972016-11-0202 November 2016 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML16244A1262016-08-31031 August 2016 Mid-Cycle Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Report 05000280,281/2016005 ML16062A2732016-03-0202 March 2016 Annual Assessment Letter IR 05000280/20150052015-09-0101 September 2015 Mid-Cycle Letter for Surry Power Station Units 1 and 2 - NRC Assessment Report 05000280/2015005 and 05000281/2015005 ML15140A4142015-05-20020 May 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000280/20140012015-03-0404 March 2015 Annual Assessment Letter for Surry Power Station, Units 1 and 2 Report 05000280/2014001 and 05000281/2014001 IR 05000280/20140062014-09-0202 September 2014 Mid-Cycle Letter for Surry, Units 1 & 2, NRC Assessment Report 05000280/2014006, 05000281/2014006 IR 05000280/20130012014-03-0404 March 2014 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - Report 05000280/2013001 and 05000281/2013001 ML13262A1812013-09-17017 September 2013 Notification of Inspection and Request for Information ML13246A1352013-09-0303 September 2013 Mid Cycle Assessment Letter ML13123A3552013-05-0202 May 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000280/20120012013-03-0404 March 2013 Annual Assessment Letter, Surry Power Station, Units 1 and 2, 05000280/2012001 and 05000281/2012001 ML12248A1232012-09-0404 September 2012 Mid Cycle Assessment Letter Surry 2012 ML1206506182012-03-0505 March 2012 EOC Report 22 ML1124401072011-09-0101 September 2011 Report 22 - Surry Inspection/Activity Plan, 09/01/2011 - 12/31/2012 ML1106303102011-03-0404 March 2011 Inspection / Activity Plan 03/01/2011 - 06/30/2012, EOC Report 22 ML1024402372010-09-0101 September 2010 Report 22 - 2010 Mid-Cycle Inspection/Activity Plan ML1006209142010-03-0303 March 2010 Report 22 - 2010001 Inspection/Activity Plan ML0924405052009-09-0101 September 2009 Inspection/Activity Plan 09/01/2009 - 12/31/2010 ML0906305292009-03-0404 March 2009 Report 22, Surry Inspection/Activity Plan for 03/01/2009 - 06/30/2010 2023-08-23
[Table view] Category:Letter
MONTHYEARIR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000280/20230102024-01-18018 January 2024 Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 ML23312A1922024-01-18018 January 2024 Issuance of Amendment Nos. 316 & 316 Regarding a Risk Informed Approach for Tornado Classification of the Fuel Handling Trolley Support Structure ML24003A9022024-01-0303 January 2024 Stations, Units 1 and 2, Emergency Plan Revision - Relocation of the Technical Support Center (TSC) - Editorial Correction IR 05000280/20233012023-12-28028 December 2023 NRC Operator License Examination Report 05000280/2023301 and 05000281/2023301 ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23352A3692023-12-18018 December 2023 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change ML23334A2342023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23242A2292023-11-0707 November 2023 Issuance of Amendment Nos. 315 and 315, Regarding Emergency Procedure Relocation of the Technical Support Center ML23200A2622023-11-0202 November 2023 Issuance of Amendment Nos. 314 and 314, Regarding Technical Specification and Spent Fuel Pool Criticality Change IR 05000280/20230032023-10-25025 October 2023 Integrated Inspection Report 05000280/2023003 and 05000281/2023003 ML23286A0372023-10-13013 October 2023 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J ML23285A0922023-10-12012 October 2023 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests ML23277A1172023-10-0303 October 2023 Operator Licensing Examination Approval 05000280/2023301 and 05000281/2023301 ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23256A2672023-09-21021 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations IR 05000280/20220042023-09-0101 September 2023 Reissue - Surry Power Station - Integrated Inspection Report 05000280/2022004 and 05000281/2022004 ML23244A0142023-08-30030 August 2023 Inservice Inspection Owner'S Activity Report IR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) ML23226A1862023-08-10010 August 2023 Proposed License Amendment Request - Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML23220A1492023-08-0707 August 2023 Independent Spent Fuel Storage Installation - Submittal of Cask Registrations for Spent Fuel Storage ML23220A1482023-08-0707 August 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Response to Request for Additional Information IR 05000280/20230022023-08-0404 August 2023 Integrated Inspection Report 05000280/2023002 and 05000281/2023002 ML23208A0922023-07-26026 July 2023 Request for Approval of Appendix F of Fleet Report DOM-NAF-2-P Qualification of Framatome ORFEO-GAIA and OORFE-NMGRID CHF Correlations in the Dominion Energy Vipre-D Computer Code Response ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations ML23198A0322023-07-18018 July 2023 Regulatory Audit Report Regarding Review of License Amendment to Modify Emergency Plan Staff Augmentation Times ML23193A9382023-07-18018 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML23173A0602023-07-11011 July 2023 Audit Summary for License Amendment Request Revision of the Emergency Plan to Support Relocation of the Technical Support Center ML23136B1392023-06-29029 June 2023 Issuance of Amendment No. 313 Administrative Changes to Subsequent Renewed Operating Licenses and Technical Specifications ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23152A0432023-06-22022 June 2023 Audit Plan License Amendment Requests to Change Emergency Plan Staff Augmentation Times ML23153A1732023-06-16016 June 2023 Correction to Amendment Nos. 346 & 286 Millstone, 294 & 277 North Anna, 311 & 311 Surry, and 225 Summer to Revise Technical Specifications to Adopt TSTF-554,Rev Reactor Coolant Leakage Requirement ML23163A2352023-06-12012 June 2023 Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for the SPS Sixth Inservice Inspection (Isi) Intervals and VCSNS Fifth ISI Interval ML23151A6612023-05-31031 May 2023 ES-2.1-1, Surry 2023-301 Corporate Notification Letter (Revised) ML23167B0072023-05-31031 May 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Supplemental Information - LOCA Dose Calculation Summary ML23117A0952023-05-10010 May 2023 Audit Plan License Amendment Request to Support Relocation of the Technical Support Center ML23130A3742023-05-10010 May 2023 Request to Delay NRC Intial Licensing Examination 2024-02-06
[Table view] |
Inspection Report - Surry - 2021005 |
---|
|
|
Text
August 31, 2021
SUBJECT:
UPDATED INSPECTION PLAN FOR SURRY POWER STATION UNITS 1 AND 2 (05000280/2021005 AND 05000281/2021005)
Dear Mr. Stoddard:
This letter is being reissued to revise incorrect inspection report numbers (05000280/2021001 and 05000281/2021001) in the subject line of the previously issued letter (ADAMS Assecion Number ML21239A010). The enclosed inspection plan lists the inspections scheduled through June 30, 2023, for Surry Power Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:
https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling. The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections is being developed by the NRC staff. The staff expects to communicate the schedule for these inspections to each utility separately.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 301-415-1321 with any questions you have regarding this letter.
Sincerely,
/RA/
Stewart N. Bailey, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No. 05000280 and 05000281 License No. DPR-32 and DPR-37 Enclosure: Inspection Plan cc Distribution via ListServ