ML20216H443

From kanterella
Jump to navigation Jump to search
Insp Repts 50-324/98-04 & 50-325/98-04 on 980209-13,0309-12 & 16-20.Violations Noted.Major Areas inspected:follow-up on Licensee Corrective Actions for Electrical Equipment Environ Qualification & Review of Instrument Response Time Testing
ML20216H443
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 04/16/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20216H421 List:
References
50-324-98-04, 50-324-98-4, 50-325-98-04, 50-325-98-4, NUDOCS 9804210139
Download: ML20216H443 (26)


See also: IR 05000324/1998004

Text


_ _____

'

. .

.

U. S. NUCLEAR REGULATORY COMMISSION

'

REGION II

Docket Nos: 50-325, 50-324

License Nos: DPR-71..DPR-62

Report No: 50-325/98-04. 50-324/98-04

Licensee: Carolina Power & Light (CP&L)

Facility: Brunswick Steam Electric Plant Units 1 & 2

Location: 8470 River Road. SE

Southport. NC 28461

.

Dates: February 9 - 13. March 9 - 12. and

March 16 - 20. 1998

Inspectors: J. Lenahan, Reactor Inspector

G. MacDonald. Project Engineer

Approved by: K. Landis. Chief

Engineering Branch

Division of Reactor Safety

., Enclosure 2

'

9804210139 980416

PDR ADOCK 05000324

G FDR

/

.

IS

EXECUTIVE SUMMARY

Brunswick Steam Electric Plant. Units 1 & 2

NRC Inspection Report 50-325/98-04. 50-324/98-04

This special inspection was conducted to followup on the licensee's corrective

i actions for electrical equipment environmental qualification and a review of I

instrument response time testing.

Results:

One violation and four apparent violations were identified:

.

An apparent violation for an inadequate 10 CFR 50.59 evaluation which i

resulted in deleting requirements for performance of response time j

testing of instrumentation (Paragraph M1.1).

l

.

An apparent violation for failure to perform RTT of reactor protection  ;

system instrumentation required by Technical Specification 4.3.1.3 I

(Paragraph M1.2).

.

An apparent violation for failure to perform RTT for actuation of the

primary and secondary containment isolation systems required 'oy TS

.

4.3.2.3 (Paragraph M1.2).

.

An apparent violation for failure to perform RTT for actuation of

the emergency core cooling system as required by TS 4.3.3.3

(Paragraph M1.2).

-

A violation for use of an ESR. which was not design verified (ED ESR).

to change plant design documents (Paragraph E.8.3).

l

I

'

1

-

'

-

. .

.

REPORT DETAILS

II. Maintenance

M1 Conduct of Maintenance i

M1.1 Instrument Resoonse Time Testina i

a. Insoection Scoce

The inspector reviewed the 10 CFR 50.59 safety evaluations which

were performed to delete performance of instrument response time

testing required by Technical Specification 3/4.1.3. 3/4.2.3. and

3/4.3.3.

b. Observations and Findinas

!

Generic Letter (GL) 93-05. Line-Item Technical Specifications

Improvements to Reduce Surveillance Requirements for Testing

During Power Operations, was issued by NRC on September 27. 1993.

This GL recommended deletion of isolation instrumentation response

time testing (RTT) requirements for functions where the required

response time corresponded to the diesel generator start time.

The GL specifically stated that a Technical Specification (TS) l

amendment was required to delete these response time testing

requirements from the TS.

1

On December 29, 1993. NRC issued GL 93-08. Relocation of Technical

Specification Tables of Instrument Response Time Limits. The GL

encouraged licensees to submit a TS Amendment request to relocate

these tables to the Updated Final Safety Analysis Report (UFSAR)

and then control changes to the tables using the 10 CFR 50.59

process. The licensee requested an amendment to remove Tables

3.3.1.2. 3.3.2.3 and 3.3.3 from the Technical Specifications and j

to relocate the tables to the UFSAR. This was approved by NRC in

TS Amendments 171 and 202 which were issued on May 31. 1994. The ,

licensee incorporated the Tables into the UFSAR as change number

31 which was issued by the licensee on June 17. 1994.

On October 3.1994. the licensee issued UFSAR change log number 4

94FSAR056 which deleted the isolation response time testing

requirements for instrumentation with the required response time

corresponded to the diesel generator start time (less than 13

seconds). This change was made in accordance with the

recommendations contained in GL 93-05. However a TS Amendment was

l

not requested by the licensee or approved by the NRC prior to ,

i elimination of the RTT requirements for these instruments. The

licensee revised the implementing plant procedures after the UFSAR

i change was issued. The UFSAR change was not submitted to NRC

4

-

'

l

l

. 1

2

'

prior to elimination of RTT for the instrumentation covered by GL 93-05.

-Instrumentation affected by this change is listed in Table 1, below.

Table 1

GL 93-05 Instrumentation *

1. Primary Containment Isolation

a. Reactor Vessel Water Level

1. Low, level 1

l

b. Drywell Pressure - High

c. Main Steam Line l

l

1. Radiation - High

2. Pressure - Low

3. Flow - High

..

4. Flow - High (Unit 2 only)

d. Main Steam Line Temperature - High

e. Condenser Vacumm - Low

2. Secondary containm3nt Isolation

a. Reactor Building Exhaust Radiation - High

I

b. Drywell Pressure - High

c. Reactor Vessel Water Level - Low. Level 2 l

3. Reactor Water Cleanuo System Isolation

e. Reactor Vessel Water Level - Low. Level 2

4. Core Standby Coolina Systems Isolation

a. High Pressure Coolant Injection System Isolation

1. HPCI Steam Line Flow - High

.4

!

-

. .

a

3

.,3. HPCI Steam Supply Pressure - Low -

b. Reactor Core Isolation. Cooling System Isolation

1. RCIC Steam Line Flow - High

  • Instrumentation with response times less than the diesel

_

generator start time (13 seconds).

.

NOTE: Numerical / letter identifications of instrumentation

L shown above corresponds with that shown in former TS

'-

and current UFSAR Table 7.3.1-3A

The BWR Owners Group submitted a report titled: BWR Owners Group

l Licensing Topical Report NED0-32291. " System Analyses for

! Elimination of Selected Response Time Testing Requirements."

i January 1994, in a letter to NRC dated January 14. 1994. The

report concluded that instrument calibration of selected

instruments would provide the data to detect degradation of RTT.

i and that RTT could be eliminated from surveillance requirements.

l These instruments were not included in GL 93-05. The NRC issued a

l- Safety Evaluation Report (SER) in a letter to the BWR Owners Group- ,

~ dated December 28, 1994. The SER approved the NEDO 32291 Report .

I

and provided guidance to licensees on the information required to

be submitted with TS change requests to implement the NED0-32291

i

'

~

recommendations. On February 14. 1995, the licensee initiated

UFSAR change log number 94FSAR100 to implement the recommendations

of NEDO-32291. The implementing plant procedures _were revised

after the UFSAR change was issued by the licensee and the RTT of

-instrumentation covered by NED0-32291 was deleted. The UFSAR

,

change was not submitted to NRC prior to elimination of the RTT.

l Instrumentation affected by this change is listed in Table 2.

below. j

Table 2

L

l Instrumentation Resoonse Time Deleted oer NEDO-32291

I

i.

<. UFSAR Table 7.2.1-3

! Reactor Protection System Instrumentation Resoonse Times

3. Reactor Vessel Steam Dome Pressure High s 0.55-

'4. Reactor Vessel Water Level - Low. Level 1 s 0.09

_

i'

i /

'

. .

!

I 4 ',

l l

l UFSAR Table 7.3.1-3A l

,

! l

'

Isolation System Instrumentation Resoonse Time l

i

1. Primary Containment Isolation

a. Reactor Vessel Water Level

'

l

2. Low, Level 3 s 1.0

l c. Main Steam line

3. Flow - High s 0.5

4. Flow - High s 0.5

UFSAR Table 7.3.3-5

l

Emeroency Core Coolina System Resoonse Times

1. Core Spray System s 27 seconds  ;

-

2. LPCI Mode of RHR System s 40 seconds

i

3. High Pressure Collant Injection System s 60 seconds

l

On May 16, 1996. the licensee initiated UFSAR change log number i

l 96FSAR015. This change updated the UFSAR Table 7.3.1-3A by '

changing the RTT for the primary containment isolation instrument i

number 1.g. Main Stack Radiation - High function to N/A. The 10 l

CFR 50.59 evaluation for this change was based on UFSAR change log

Number 94FSAR100. The basis for the change was that licensee j

engineers concluded that this RTT for this instrument should have '

been deleted under 94FSAR100, since it was covered by NE00-32291.

1

On March 21, 1997, the licensee notified NRC of a potential l

noncompliance with the Technical Specifications (TSs) for l

inappropriately deleting instrument response time testing

I surveillance requirements which were required by TS Sections i

4.3.1.3. 4.3.2.3. and 4.3.3.3. The licensee requested enforcement  !

discretion to permit continued operation of the Brunswick plant

until the issue could be resolved. The NRC exercised discretion

not to enforce compliance with the applicable TS sections for a

period of 30 days based on an evaluation that granting the request l

involved minimal or no safety impact on the public health and

-

safety. '

.<

!

l

'

y

. .

.

l

5

'

The inspectors reviewed the actions surrounding the deletion of

the instrument response time surveillance testing. Review of the

-

l

-

10 CFR 50.59 Safety Reviews for UFSAR changes log numbers

94FSAR056, 94FSAR100 and 96FSAR015 disclosed that the licensee's

reviewers incorrectly concluded that the proposed UFSAR changes j

did not involve a change to the Technical Specifications. The

licensee's reviewers incorrectly concluded that these UFSAR

changes only affected the Tables relocated from the TS to the

UFSAR per the recommendations of GL 93-08 approved by NRC in TS

Amendments 171 and 202. 10 CFR 50.59 permits licensees to make

changes in the facility or procedures without prior NRC approval

unless the proposed change involves an unreviewed safety question

or a change in the technical specifications. The elimination of

RTT did not involve an unreviewed safety question. These changes

were recommended and approved by NRC in GL 93-05 and the SER dated

December 28, 1994. However both documents clearly stated that the

RTT could not be deleted unless a TS change was requested and

approved by NRC. The requirements for RTT were specified in TS Sections 4.3.1.3. 4.3.2.3 and 4.3.3.3. Deletion of the RTT

constituted an unapproved change to the plant TSs. without prior

NRC approval. This was identified to the licensee as Apparent

Violation Item 50-325(324)/98-04-01. Inadequate 50.59 Evaluations

-

which Resulted in Deletion of TS Response Time Testing

Requirements.

Conclusions

An apparent violation was identified for deleting the RTT

specified in the TS from the UFSAR and surveillance procedures due

to an inadequate 50.59 safety review. This issue did not involve

an unreviewed safety issue.

M1.2 Performance of Resoonse Time Testina

a. Insoection Scone (61700)

The inspectors reviewed response time testing performed by the licensee  !

for conformance with Technical Specifications 4.3.1.3. 4.3.2.3. and I

l

4.3.3.3. '

b. Observations and Findinas

l

TS 4.3.1.3. 4.3.2.3, and 4.3.3.3 required demonstration that the

RTT was within its limit at least once per 18 months. TS 4.02

permits extension of the test interval by plus or minus 25

percent. Therefore, the RTT was required to be performed at a

maximum interval of 687 days (18 months plus 25%). The inspectors

4

[ ' -

-

a

. .

4

1

6

reviewed the results RTT performed on instrumentation listed in

Tables 1 and 2. above. The results of last RTT performed which

complied with TS are shown in Attachments 1 for Unit 1 and

Attachment 2 for Unit 2. The inspectors determined that as of

March 21. 1997, the licensee failed to perform RTT within the TS

required interval for the instrumentation listed in Table 2 above.

Enforcement discretion was granted for a period of thirty days

which permitted plant operation pending the issuance of a TS

amendment which approved deletion of RTT. Further review by the

inspectors disclosed that the licensee failed to request

enforcement discretion for the instrumentation listed in Table 1.

above. However approval to delete the RTT for this

instrumentation was also included in TS Amendments 184 and 215

issued on April 18, 1997.

Further review by the licensee disclosed that the RTT for the main

stack radiation monitor deleted by UFSAR change log Number

96FSAR015 did not meet the requirements of NED0-32291. The

licensee initiated Condition Report (CR) 97-02806 on August 19.

1997, to document and disposition this problem. The

instrumentation was declared inoperable. The licensee then

performed the required RTT on August 22, 1997, for Unit 2 and on l

-

August 23. 1997, for Unit 1. The inspectors reviewed the results

of the RTT which were documented in WR/JO 97-AFBT1 for Unit 1 and

WR/JO 97-AQUB for Unit 2.

The following apparent violations were identified by the '

!

inspectors for failure to perform RTT as required by the

applicable Technical Specifications (Amendment 175 - Unit 1 and

Amendment 206 - Unit 2):

-

Apparent violation item 50-325 (324)/98-04-02. Failure to

Perform RTT for Reactor Protection System Instrumentation as

Required by TS 4.3.1.3.

-

Apparent violation item 50-325 (324)/98-04-03. Failure to

Perform RTT for Instrumentation for Actuation of the Primary

and Secondary Containment Isolation Systems as Required by

TS 4.3.2.3.

-

Apparent violation item 50-325 (324)/98-04-04 Failure to

Perform RTT for Instrumentation for Actuation of ECCS as

Required by TS 4.3.3.3.

.4

l

f

[-

-

. .

i .

7

'

c. Canclusions

The inspectors concluded that the licensee failed to perform response

time testing in accordance with Technical Specifications 4.3.1.3.

4.3.2.3, and 4.3.3.3. The failure to perform RTT was identified as

Apparent Violations (50-325. 324/9804-02. -03, and -04).

M1.3 Imolementation of BWROG Licensina Tooical Reoort. NED0-3229

a. Insoection Scooe (62700. 61700)

The inspectors reviewed the licensee's implementation of NED0-32291 for

conformance with the NRC's December 28, 1994 Safety Evaluation Report

(SER).

'

b. Observations and Findinas

The December 28, 1994 SER that accepted NEDO-32291 required that

licensees confirm the implementation of seven conditions as part of any

license amendment application to eliminate response time testing. The

inspectors reviewed the licensee's conformance with the seven

conditions. Review of licensee records and discussions with licensee

-

engineers disclosed that the licensee documented compliance with the

seven conditions in response to a finding in a Nuclear Assessment

Section (NAS) review and in ESR 9700205. The NAS assessment of the  !

Technical Specifications and Operating License performed from June 3 to

14. 1996. identified an issue regarding documentation of NRC required

actions for deletion of RTT. The results of the self assessment are

documented in Assessment Report number B-OL-96-01 dated July 3. 1996. l

The issue, documented in CR96-01804, concerned the fact that RTT was i

deleted from some procedures without documentation that required actions )

were being performed. ESR 9700205. Response Time Test Elimination. '

Revision 0 dated March 21, 1997. documented the review performed by

licensee engineers of the seven conditions in the December 28. 1994 SER.

The seven conditions and the licensee's conformance with those

conditions follow:

(1) Condition

Prior to installation of a new transmitter / switch or following

refurbishment of a transmitter / switch (e.g., sensor cell or

,

variable damping components). hydraulic response time testing

shall be performed to determine an initial sensor-specific

j response time value.

l

.s

-

,

L .

.

0

'

Response

.

l

The licensee determined, based on an engineering review, that

revised procedures and an enhanced trending program will provide

sufficient means of identifying suspect transmitters.

'

(2) Condition

For transmitters and switches that use capillary tubes, capillary

tube testing shall be performed after initial installation and

after any maintenance or modification activity that could damage

the capillary tubes.

Response

~

The inspectors found that instruments installed at Brunswick do

not use capillary tubes.

(3) Condition

Calibration shall be performed with equipment designed to provide

a step function or fast ramp in the process variable.

, Response

The licensee's test equipment was designed to provide a step

function or fast ramp in the process variable. Test procedures

were revised to provide a fast ramp change of r.ransmitter input

while monitoring the transmitter output.

(4) Condition

Provisions shall be made to ensure that operators and technicians,

through an appropriate training program, are aware of the

consequences of instrument response time degradation, and

applicable procedures have been reviewed and revised, as

necessary, to assure that technicians monitor for. response time

degradation during the performance of calibrations and functional

tests.

Response

l The inspectors reviewed Lesson Plan IC7C078. Rosemount Transmitter

(Loss of Fill Oil), dated May 30. 1995. The consequences of

instrument response time degradation (sluggish response) were

discussed in this training. The inspectors reviewed the

procedures listed below and verified that I&C personnel verify

..

'

.

.

9

monitor response time degradation. This is performed by verifying

instantaneous output response to input. Procedures reviewed were:

2MST-HPCI21R. 2MST-RHR22R. and 2MST-RPS23R. This requirement was

also covered during quarterly training.

(5) Condition

Surveillance testing procedures shall be reviewed and revised if

necessary to ensure calibrations and functional tests are

performed in a manner that allows simultaneous monitoring of both

the input and output response of instruments under test.

Response

In review of the three procedures listed above. the inspectors

verified that testing was performed in manner that provides for i

simultaneous monitoring of instrument input and output.

(6) Condition  !

!

'

For any request involving the elimination of response time testing

for Rosemount pressure transmitters, the licensee shall be in

-

compliance with the guidelines of Supplement 1 to NRC Bulletin 90- ,

01. " Loss of Fill-Oil in Transmitters Manufactured by Rosemount." !

l

Response

The inspectors determined that the licensee was in compliance with

the guidelines of Supplement 1 to NRC Bulletin 90-01. These j

requirements were reviewed in detail as part of training performed

under lesson plan IC7078.

(7) Condition

For those instruments where the manufacturer recommends periodic

response time testing as well as calibration to ensure correct

functioning, the licensee shall ensure that elimination of

response time testing is nevertheless acceptable for the

particular application involved.

'

Response

i

The licensee revieweo vendor information for NED0-32291 components

and determined that there were no specific recommendations to

perform periodic response time testing.

.4

/

w .

.

.

.

10

The inspectors also reviewed the types of instruments, components

and affected systems for which the response time testing was

eliminated using NED0-32291 and verified that the licensee

l complied with Tables 1 and 2 of the SER. The following

i

instruments were reviewed through walkdown inspections and/or

review of equipment data base records:

! -

Instrument Numbers B21-LTS-N024A-1-2, and B -l-2. and B21-

l LTS-N025A-1-2 and B-1-2 for reactor vessel water level. Low,

i Level 3. These instruments were Rosemount transmitters.

Associated relays were Agastat GP/EGP family.

-

Instrument Numbers B21-PDT-N006A. B. C. D and B21-PDT-008A.

B. C. D for main steam line high flow isolation. These

instruments were Rosemount transmitters. Associated relays

were Agastat GP/EGP family.

,

-

Instrument Numbers B21-PT-N023A. B. C. D for reactor

protection system high reactor pressure. These instruments

l'

were Rosemount transmitters. Associated relays were Agastat

GP/EGP family.

i - -

Instrument Numbers B21-LT-N017A-1. B-1. C-1. 0-1 for reactor

protection system reactor vessel water level. Low. Level 1.

These instruments were Rosemount transmitters. Associated

,

relays were Agastat GP/EGP family.

i c. Conclusions

The inspectors concluded that the instrumentation for which RTT was

deleted per NED0-32291 complied with the conditions listed in the

December 28, 1994. SER.

III. Enaineerina

E.1 Conduct of Engineering

E1.1 Environmental Qualification (92903)

a. Insoection Scone

The inspectors reviewed the licensee's corrective actions for the

Environmental Qualification (EO) program. in response to findings

identified during Self-Assessment Numbers 95-0041 and 96-0271 and

the violations identified in NRC Inspection Report 50-325. 324/96-

14. The licensee's corrective actions to resolve deficiencies in

.,

/

-

. .

.

11

the E0 program include revision and updating of Qualification Data

Packages (ODPs). The process for incorporating E0 program .

maintenance and replacement requirements into site procedures was

reviewed.

b. Observations and Findinas

The inspectors reviewed CP&L Procedure EGR-NGGC-0156. Environmental

Qualification of Electric Equipment Important to Safety. Revision 5. ,

dated February 27. 1998. which specifies the requirements for

preparation of the ODPs. Attachment 2 to the procedure contains the

specific requirements for preparation of the Brunswick ODP files,

including qualifications for E0 personnel responsible for preparation of

the ODPs. ODP format and content, qualification analysis. E0 equipment

data (summarized on system component evaluation worksheets).

qualification parameters, equipment test data, and maintenance

requirements. l

The inspectors reviewed the following ODPs:

ODP - 14. Westinghouse Electrical Penetrations. Class B. C. E. and F.

Revision 3. dated January 30, 1998.

.

ODP - 16. Okonite Tape Splices. Revision 3. dated March 6. 1998.

00P - 61. Honeywell PTK and PTS Series Control Switches. Revision 2.

dated February 23, 1998.

ODP - 99. R. G. Laurence Series 500 and 600 Solenoid Valves. Revision

0 dated December 23. 1997.

The inspectors verified the ODPs addressed the following: qualification

level (NUREG 0588 Cat. I): tag numbers of equipment covered in the ODP:

test report applicability; similarity of test specimens to installed

equipment: E0 parameters, temperature, pressure, relative humidity,

radiation, chemical spray, submergence: qualified life: E0 maintenance

requirements; test anomalies; and operating experience items. The

inspectors verified that similarity analysis was included in the ODPs. l

l

For ODP-14. the inspectors reviewed Patel Test Report PEl-TR-83-  !

14-4 which documents the design basis accident testing performed

by Westinghouse. The inspectors also reviewed penetration design

i

'

drawings, responses to NRC Information Notices and Bulletins, and

referenced ESRs. ESR 9700674. titled Evaluate E0 Status of

Westinghouse Electrical Penetrations documents a review of the l

Westinghouse electrical penetrations to determine which ones are

required to be environmentally qualified. The criteria for

.<

.

'

-

.

.

.

12 i

'

l determination of which penetrations were required to be E0 l

qualified were those which perform an electrical function '

important to safety. The inspectors noted that the 4160 volt

electrical penetrations, which supply power to the recirculation

pumps. were not included in the E0 program. The 4160 volt

-

electrical penetrations do not perform any electrical safety

related functions. -The inspectors determined from review of test

reports and the licensee's response to IE Bulletin 77-06.

Potential Problems with Containment Penetration Assemblies, that

, environmental qualification of the electrical penetrations was not

affected by the 15 psi nitrogen pressure normally maintained in

the drywell penetrations. The reason the pressure was maintained

in the penetrations was to monitor potential leakage. Any

detected leakage was evaluated under the requirements of 10 CFR

50. Appendix J.

ODP-16 and the following associated DRs were reviewed:

-

DR 3.1-'2. Revision 5. dated August 5. 1997."0konite Report

No. NORN-3. Revision 4 Nuclear Environmental Qualification

Report for Okoguard Insulated Cables and T-95 & No. 35

Splicing Tapes. October 24. 1988".

.

-

DR 3.1-2A. Revision 1. dated December 10. 1997."Patel

Engineers Assessment Report No. PEI-TR-82-4-41. Revision 0.

Final Assessment Report on Okonite Tape Splice Insulation

for Power and Control Cables and Rockbestos Pyrotrol III and

Firewall III Cables Used in the James A. Fitzpatrick Nuclear

Power Plant. December 5, 1994".

The' inspectors concluded that.the ODP documentation was complete.

that the ODP was prepared in accordance with the requirements of

procedure EGR-NGGC-156. that appropriate ESRs.were incorporated

into the 0DP, and that generic industry communications were

addressed in the ODP. The inspectors identified several minor

inconsistencies'with the ODP which were addressed by the licensee.

These items included some inconsistencies between the SCEW sheets

and equipment master list an incorrect reference, and some test

results which were not discussed in the CDP. The inconsistencies

did not affect the accuracy of the ODP. The inspectors reviewed

Procedure OSPP-CBL003. Disconnection and Reconnection of Taped

Splices for Electrical Equipment. Revision 19. dated September 5,

1997, and verified that the procedure complied with the

installation requirements of the referenced qualification test

reports.

L

.+

/

, .

, ,

.

l- '13

'

ODP-61 and associated Document Reference (DR) DR 59.1. titled Nuclear

Environment'al Qualification Report of Terminal Blocks. Limit Switches.

Control Switches. Indicating Lights, and Solenoid Valves for BSEP Units

1 and.2 was reviewed. The inspectors concluded that the ODP

documentation was complete and addressed all qualification issues. The

inspectors determined that ODP was prepared in accordance with the

requirements of-Procedure EGR-NGGC-156. that appropriate ESRs were -

incorporated into the ODP. and that generic industry communications

! related to the switches were addressed in the ODP. The inspectors

l identified several minor inconsistencies' with the ODP which were

, addressed by the licensee. These items included some discrepancies in

L

'

the SCEW sheets and equipment data base system (EDBS), and a test

~ anomaly which was not addressed in the ODP. The minor discrepancies did

not affect the accuracy of the completed ODP.

j Review of ODP-99 showed that the valves used on the post accident'

sampling system met the requirements of 10 CFR 50.49. The

inspectors identified some minor editorial comments in the

completed ODP. but these did not affect the accuracy or

. conclusions of the ODP.

l

The inspectors also reviewed the licensee's process for

l

-

incorporating the maintenance and qualified life data into the

E

plant procedures upon completion and approval of ODPs by the E0

group. The licensee used a checklist to control the ODP' approval

process and post ODP approval items. The checklist contained l

requirements that the following items be completed by an engineer i

and checked by a second individual to verify that the actions were  !

, accomplished:

. EDBS changes

.

E0 maintenance activities match Preventive Maintenance (PM)

L models.

L

( . EQ Maintenance requirements are captured in appropriate

E procedures and/or installation specifications. l

L l

. Appropriate procurement specifications reflect E0 l

procurement requirements.

c. Conclusions

The ODPs were complete and addressed all environmental qualification

related issues and related industry communications. Minor

inconsistencies were identified with the ODPs which were addressed by

the licensee. The licensee has a controlled process to ensure that EQ

.4

/

f. ,

.

14

'

maintenance., qualified life, and procurement requirements are

incorporated into existing site procedures.

El.2 Review of Environmental Oualification Condition Reoorts (92903)

a. Insoection Scooe

The inspecters reviewed condition reports (CRs) initiated to

document and disposition discrepancies involving environmental I

qualification issues.

l

b. Observations and Findinas

The inspectors reviewed the corrective actions to disposition the

condition reports (CRs) listed below. These CRs were initiated by

the licensee to document and disposition nonconforming items which

were identified during the ongoing E0 reconstitution project. The

nonconforming items were identified as a result of E0 equipment

walkdowns, review and updating of E0 equipment qualification data

packages (00Ps) omissions from the original program, or changes

to the operating environment. The CRs reviewed were as follows:

-

CR 97-02844 was initiated to address a discrepancies in the

maximum secondary containment temperatures. This was the result ,

of NRC questions raised during review of ODP - 67 during the I

inspection documented in NRC Inspection Report numbers 50-325.

324/97-09. The licensee revised their operating instructions to

require that operations personnel monitor temperatures in the

reactor buildings on a daily basis and report any occurrences when

the ambient temperatures exceeds 100 F to angineering (EO) for

evaluation.

CR 97-02902 was initiated by maintenance to document a potential I

problem with the licensee's supply inventory system which did not

clearly designate between 0 listed parts and E0 parts. The

licensee reviewed 1010 work requests and determined that no

unqualified parts had been installed in E0 applications. ~he

problem documented in the CR involved the difficultly of the

process that maintenance planners were required to use to

determine if the parts they specify are required to be EQ

qualified. The corrective actions were to generate an engineering

bulletin on the subject of CR 97-02902 for use by maintenance

planners and procurement engineers to clirify E0 requirements when

designating replacement parts. ,

i

CR 98-00172 was initiated to document the existence of local " hot

spots" in some plant areas which may affect qualification of some

.,

/

-

.

15

'

E0 equipment. The licensee prepared ESR 9800032 to address these

areas and updated DR-227. Environmental Qualification Service

Conditions. Revision 3. to address evaluation of the local high

temperatures. Equipment qualified under nine 0DPs were affected

by hot spots. The licensee determined that three ODPs may require

revision to consider the affects of the hot spots, while the

remaining six were acceptable. The licensee will perform

temperature monitoring in these areas to determine if-additional

revisions to the 0DPS are necessary,

c. Conclusions

The inspectors concluded that the licensee was making progress in

resolving and closing CRs identified by the E0 group.

E2 Engineering Support Of Facilities and Equipment

E2.1 Followuo on Service Water System Reoairs (37550)

a. Insoection Scooe

The inspector reviewed the licensee's followup actions to monitor

-

two through wall leaks in the Unit 1 vital service water header.

b. Findinos and Observations

The licensee identifi- two leaks in a section of piping on the

Division 1 vital service water header. These problems were

documented on CR Numbers 97-02013 and -02108. Each leak was

estimated to be approximately one drop per minute. Based on the

results of ultrasonic testing (UT) licensee engineerr determined

that the leaks were of the " pinhole" type. The inspectors

reviewed ESR 9700326. Revisions 0 and 1 which evaluated the piping

wall thickness using the guidance provided in Generic Letter 90-

05. The conclusion of the ESR was that the piping was operable

until the next refueling outage. The licensee submitted a relief

request to NRC regarding this issue in a letter dated July 3.

1997. The licensee committed to perform weekly assessments of the

leakage from the pinhole and to assess the integrity of the flawed

area once every three months using nondestructive examination

methods. The inspectors reviewed the results of UT evaluations

performed on June 15. 1997 August 19, 1997. November 3. 1997. and

January 30, 1998. The UT results showed the piping remained

serviceable. The inspectors also reviewed the results of weekly

inspections of the temporary repair which are performed by

operations personnel in accordance with Operating Instruction 1-

01-03.4.2. Auxiliary Operator Temporary Check Sheet. Unit 1

.,

i

. .

.

16

'

Reactor Building. The inspectors concluded that the licensee was

performing ongoing evaluations of the pipe flaws in accordance

with their commitments to NRC and good engineering practices.

c. Conclusions

The licensee's actions to followup on the pinhole leaks in the

Unit 1 vital service water header were performed in accordance

wi th -engi neeri ng - recommendati ons .

E.8 . Miscellaneous Engineering Issues

E.8.1 (Closed) Inspector Followup Item 50-325(324)/96-14-06. Accuracy of ERFIS

and SPDS Data.

I

Review of various documents resulted in identification of an issue

concerning the accuracy of reactor vessel level instrumentation

using the emergency response facilities information system (ERFIS)

and the accuracy of containment isolation valve position

l

indications in the safety parameters display system (SPDS). A

.

t

. problem had been identified in 1994 with the algorithm u;ed to

compute the water level for small break LOCA scenarios. A

software change, number SCR 94-0114. was generated to resolve the

y- problem. However, since the water level data displayed on ERFIS

was an average value. operators were trained not to depend on the

l ERFIS system when responding to accident scenarios. The

l inspectors noted the following caution in E0P-01-UG Attachment 6:

Reactor water level instruments may be used to determine reactor

water level only when the conditions for use as listed in Table 1

are satisfied for that instrument. Table 1 listed the conditions

for various instruments. The inspectors noted, during observation

of training that operators did not to rely on ERFIS data, The

operators were trained to rely on water level data indicated on

control board instruments using the limitations contained in the

E0Ps. The same was true regarding valve positions. The data

shown on SPDS was' used for information only. The operators

referred to the control board indications when determining valve

position.

E.8.2 (Closed) Unresolved Item 50-325(324)/97-05-06. Deletion of RTT

Requirements

Resolution of this URI is discusstJ in paragraphs M1.1 and M1.2,

above. Four apparent violations were identified.

E.8.3 (Closed) Unresolved Item 50-325(324)/97-09-02. Accuracy of Measured

Temperature Data for EQ Evaluations

.,

i

' 1

.

.

4

! 17

!

'

l Calculation..BNP-E0-5.003. Revision 0. Reactor Building Ambient

l Temperature For Qualified / Expected Life Calculations was reviewed. This

l calculation was performed to justify use of actual environmental

l temperature data in lieu of design maximam temperature data for

l determining qualified life. The calculation presented actual Brunswick

l plant temperature data from the ERFIS computer for various locations in

l Unit 1 and Unit'2 Reactor Buildings for 1992. 1993. 1996 and 1997. The

l data showed that Unit 1 had higher temperatures than Unit 2 and that

l 1993 was the highest temperature year from comparison of daily average ,

l temperature data for the past 20 years (20 year mean) for statewide and l

l Southport. North Carolina. This provided justification that if a i

temperature model could be shown to provide the same degradation as the l

l 1993 data. that the model would be conservative and representative of l

l past plant equipment aging due to actual plant environments. I

The calculation demonstrated that the actual data coulo be enveloped by

an ambient profile of 85 degrees Fahrenheit (F) for six months and 95

l

,

degrees F for six months. The analysis showed that the equivalent '

! degradation of the 85/95 degree F profile was worse than the degradation ,

due to the actual environmental data for the combined 1992 and 1993 l

years which had been previously shown to be higher than past

temperatures. The evaluation was performed using a spreadsheet which

-

had been validated by use of independent verification. Therefore, the

inspectors concluded that the temperature values used for evaluation of

the motor control centers were acceptable.

[ The inspectors also reviewed DR 227. Environmental Qualification  ;

,

Service Condition. Revision 4. dated February 2. 1998. This

i document discusses environmental service conditions for

l environmental qualification of equipment in the reactor buildings

and drywells. In addition to temperature, precsure effects,

radiation and moisture are evaluated. The inspectors reviewed

various ESRs and the reactor building environmental report which

contain temperature data and verified that additional information

was not available which could possibly invalidate the conclusions

i of Calculation BNP-E0-5.003. However, during review of DR-227.

,

the inspectors identified the following problem. Reference 146 of

l DR-227 was ESR 9700314. Drywell Temperature Monitorng of Past

Outages. Revision 0. dated June 3, 1997. The purpose of this ESR

was to tabulate a listing of all plant outages and to calculate an

average outage temperature for the drywells, based on the reduced

drywell temperatures which occur during outages. This ESR. which

was incorporated into Section 4.1.1.1 of DR-227, was used to

reduce the temperatures used in the Arrhenius technique for E0

equipment life. The inspectors identified an error in the ESR

which failed to consider the dates Unit 2 was not operating for

extended periods in 1992 and 1993. Although the error was in the

.4

/

-

. .

'

i

18

conservative direction (slightly higher than actual drywell ,

temperatures resulted from evaluation), the inspectors noted that j

no design verification had been performed on the ESR since it was I

classified as an Engineering Disposition (ED) ESR. The definition 1

of an ED ESR per CP&L Procedure EGR-NGGC-0005. Engineering j

Service Rquests in part, was an ESR, which should not produce

design output documents. nor should it change existing engineering

documents. The use of an ED ESR as a design output document to

change plant design parameters (drywell temperatures) was

identified to the licensee as violation item 50-325 (324)/98-04-

05. Use of ED ESR to Revise Plant Design Data.

E.8.4 (Closed) Unresolved Item 50-325(324)/97-09-04 Effect of ,

Depressurized Electrical Penetrations on E0 Requirements )

Review of ODP-14. discussed in paragraph , above, disclosed that

the Westinghouse penetrations were not required to be pressurized

to maintain environmental qualification. The penetrations were

pressurized to identify potential leakage which could affect

compliance of the containment with 10 CFR 50. Appendix J.

E.8.5 (Closed) LER 1-97-003. Response Time Test Elimination

.

This LER covered the inappropriate elimination of response time

testing. Resolution of this LER is discussed in parage.,-hs M1.1

'

1

and M1.2. above.

V. MANAGEMENT MEETINGS

,

The inspectors presented the inspection results to members of licensee

management at the conclusion of the inspection on March 12. 1998, and

l during a telecon on March 26. 1998. The licensee acknowledged the

i findings presented. Dissenting comments were not received from the

! licensee. The licensee did not identify ar. materials used during the

inspection as proprietary information.

PARTIAL LIST OF PERSONS CONTACTED

Licensee

G. Attarian. Manager. E0 Task Force

R. Delong. Superintendent. Electrical /l&C. Brunswick Engineering Support

Section (BESS)

W. Dorman Manager. Licensing and Regulatory Affairs

J. Gawron, Manager. Nuclear Assessment Section

K. Jury. Manager. Regulatory Affairs

R. Krich. Chief Engineer. Nuclear Engineering (NED)

.4

!

I. .

l

.

I

.

f 19

J. Lyash Plant Manager

J. McPadden',' Project Engineer. BESS

G. Miller. Manager. BESS

'R. Mullis, Manager. Operations l

,

l S. Tabor Senior Specialist. Regulatory Compliance

Other licensee employees contacted included engineers Nuclear

Assessment personnel and administrative personnel.

INSPECTION PROCEDURES USED l

IP 37550: Engineering

IP 92903: Followup - Engineering

ITEMS OPENED, CLOSED, AND DISCUSSED l

'

Doened

50-325(324)/98-04-01 EEI Inadequate 10 CFR 50.59 Evaluations which

Resulted in Deletion of TS Response Time

Testing Requirements (Paragraph M1.1.b)

i

-

50-325(324)/98-04-02 EEI Failure to Perform RTl for Reactor j

l Protection System Instrumentation as i

Required by TS 4.3.1.3 (Paragraph M1.2.b)  !

l

50-325(324)/98-04-03 EEI Failure to Perform RTT for Actuation

of the Primary and Secondary .

Containment Isolation Systems as  !

l Required by TS 4.3.2.3 (Paragraph

M1.2.b)

l

l 50-325(324)/98-04-04 EEI Failure to Perform RTT for Actuation

of ECCS as Required by TS 4.3.3.3

l (Paragraph M1.2.b)

!

l

50-325(324)/98-04-05 VIO Use of ED ESR to Change Plant Design

Documents (Paragraph E'.8.3)

Closed

50-325(324)/96-14-06 IFI Accuracy of ERFiS and SPDS Data (Paragraph :

E.8.1)

.,

I

'

.

.

i

.

-

t

l

l

'

20

'

l 50-325(324)/97-05-06 URI Deletion of RTT Requirementh (Paragraph

i

l

E.8.2)

l

'

50-325(324)/97-09-02 URI Accuracy of Measured Temperature Data for

EO Evaluations (Paragraph E.8.3)

50-325(324)/97-09-04 URI Effect of Depressurized Electrical ,

,

Penetrations on E0 Requirements  !

(Paragraph E.8.4) j

LER 1-97-003 Response Time Test Elimination

(Paragraph E.8.5)

I

l 1

i

4

l

l

l . \

l

-

i

.4

l

/

~

.

. .1

.

21

'

ATTACHMENT .

UNIT 1 RESPONSE TIME TEST DATES

REACTOR PROTECTION SYSTEM (TS 4.3.1.3)

l

' TRIP FUNCTIONAL UNIT MOST RECENT SATISFACTORY TEST DATE (a) TEST REQUIRED BY (b)

Reactor Vessel

Steam Dome Pressure - High 3/24/94 2/10/96

'

Reactor Vessel

Water Level - Low. Level 1 1/31/94 12/19/95

I

ISOLATION SYSTEM INSTRUMENTATION (TS 4.3.2.3)

TRIP FUNCTION MOST RECENT SATISFACTORY TEST DATE (a) TEST REQUIRED BY (b)

Primary Containment

Isolation

Reactor Vessel' Water

Level Low. Level 1 & 3 1/31/94 12/19/95

l

Drywell Pressure digh '7/28/94 6/15/96

Main Steam Line

Pressure - Low 4/10/94 2/27/96

l

'

Main Steam Line

l

Flow - High 4/14/94 3/2/96

Main Steam Line Tunnel 1/30/94 12/18/95 l

Temperature - High

Condenser Vacuum - Low 4/11/94 2/28/96 >

Secondary Containment System

Isolation

Reactor Building Vent

Exhaust Plenum Radiation - High 2/1/94 12/20/95  ;

i

Drywell Pressure - High 7/28/94 6/15/96  !

!

. Attachment 1

.

I

l '

. .

.

22

'

Reactor Vessel

WaterLevel-Low, Level 2 4/28/95 3/16/96

Reactor Water Cleanup System

Isolation

Reactor Vessel

.Water Level Low. Level 2 4/28/95 6/9/96

Reactor Core Isolation Cooling

System Isolation

1

l

HPCI Steam Line Flow - High 1/30/94 12/18/95 l

HPCI Steam Supply Pressure - Low 1/31/94 12/19/95

RCIC Steam Line Flow - High 9/22/93 8/10/95

i

!

EMERGENCY CORE COOLING SYSTEM (T3 4.3.3.3) l

TRIP FUNCTION MOST RECENT SATISFACTORY TEST DATE (a) TEST REQUIRED BY (b)

..

Core Spray System 11/9/95 9/27/97

Low Pressure Coolant Injection 1/31/94 12/19/95

Mode of RHR System

High Pressure Core Spray System 2/10/94 12/29/95

(a) Dates in this column represent the most recent date when response time was

satisfactorily demonstrated for at least one channel in a trip system associated with

the trip functional unit or trip function.

(b) Dates in this column represent the required test date based on; the last

satisfactory test date in column (a): Technical Specification 4.3.1.3, 4.3.2.3. or

4.3.3.3 from License Amendment 175 which, respectively, required a demonstration of

response time at least every 18 months: and Technical Specification 4.0.2. which

allowed the surveillance interval to extended by a maximum of 25 percent. Dates in

column (b) are 687 days after thcse in column (a).

,,

.

Attachment 1

,

I

.

~

.

6

! 23

.

ATTACHMENT 2 l

UNIT 2 RESPONSE TIME TEST DATES

1

.

REACTOR PROTECTION SYSTEM (TS 4.3.1.3)

TRIP FUNCTIONAL UNIT MOST RECENT SATISFACTORY TEST DATE (a) TEST REQUIRED BY (b)

Reactor Vessel

Steam Dome Pressure - High 10/3/94 8/20/96

Peactor Vessel

Water Level - Low, level 1. 6/24/94 5/12/96

l l

ISOLATION SYSTEM INSTRUMENTATION (TS 4.3.2.3) i

I

TRIP FUNCTION MOST RECENT SATISFACTORY TEST DATE (a) TEST REQUIRED BY (b)

L Primary Containment

-

Isolation

,

Reactor Vessel Water

l. Level Low. Level 1 & 3 6/24/94 5/12/96

Drywell Pressure - High 4/17/93 3/5/95

Main Steam Line

Pressure - Low 3/9/93 1/25/95

Main Steam Line

, - Flow - High 6/7/94 4/25/96

Main Steam Line Tunnel 5/10/94 3/28/96

s Temperature - High

'

Condenser Vacuum - Low 3/9/93 1/25/95

Secondary Containment System

Isolation

Reactor Building Vent

Exhaust Plenum Radiation - High 4/15/93 3/3/95

., Attachment 2

!

l

! -

,

..

'

.

24

,

DrywellPressure-H5gh 4/17/93 3/5/95

i Reactor Vessel '

,

Water Level - Low Level 2 1/31/96 12/19/97

l

Reactor Water Cleanup System I

,

Isolation

!

Reactor Vessel

Water Level Low. Level 2 1/31/96 12/19/97

Reactor Core Isolation Cooling

System Isolation

l

i HPCI Steam Line Flow - High 8/5/93 6/23/95

l HPCI Steam Supply Pressure - Low 8/31/93 7/19/95

l

RCIC Steam Line Flow - High 3/10/93 1/26/95

..

l. EMERGENCY CORE COOLING SYSTEM (TS 4.3.3.3)

l

l; TRIP FUNCTION- MOST RECENT SATISFACTORY TEST DATE (a) TEST REQUIRED BY (b)

i Core Spray System 1/5/95 11/23/96

Low Pressure Coolant Injection 6/13/94 E/1/96

l Mode of RHR System

i

i High Pressure Core Spray System 5/11/93 3/29/95

l

(a) Dates in this column represent the most recent date when response time was

satisfactorily demonstrated for at least one channel in a trio system associated with

the trip functional unit or trip function.

(b) Dates in this column represent the required test date based on: the last

satist'actory test date in column (a): Technical Egecification 4.3.1.3. 4.3.2.3. or

4.3.3.3 from License Amendment 206 which. respectively. required a demonstration of

response time at least every 18 months; and Technical Specification 4.0.2. which

allowed the surveillance interval to extended by a maximum of 25 percent. Dates in

columa (b) are 687 days after those in column (a).

.

., Attachment 2

!

,

. _ . .