|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217F8231999-10-13013 October 1999 Informs That on 990930,NRC Completed mid-cycle PPR of Catawba Nuclear Station.Based on Review,Nrc Did Not Identify Any New Areas That Warranted More than Core Insp Program Over Next Five Months.Historical Listing of Issues,Encl ML20217H0041999-10-13013 October 1999 Forwards MOR for Sept 1999 & Revised MOR for Aug 1999 for Catawba Nuclear Station,Units 1 & 2 ML20217F1301999-10-0707 October 1999 Forwards Rev 1 to Request for Relief 99-03 from Requirements of ASME B&PV Code,In Order to Seek Relief from Performing Individual Valve Testing for Certain Valves in DG Starting (Vg) Sys ML20212J3011999-10-0101 October 1999 Forwards Exemption from Certain Requirements of 10CFR54.17(c) Re Schedule for Submitting Application for Operating License Renewal.Se Also Encl ML20217K2651999-10-0101 October 1999 Forwards Retake Exams Repts 50-413/99-302 & 50-414/99-302 on 990921-23.Two of Three ROs & One SRO Who Received Administrative Section of Exam Passed Retake Exam, Representing 75 Percent Pass Rate 05000414/LER-1999-004, Forwards LER 99-004-01,providing Correction to Info Previously Provided in Rev 0 of Rept.Planned Corrective Actions Contain Commitments1999-09-27027 September 1999 Forwards LER 99-004-01,providing Correction to Info Previously Provided in Rev 0 of Rept.Planned Corrective Actions Contain Commitments 05000413/LER-1999-015, Forwards LER 99-015-00 Re Inoperability of Auxiliary Bldg Ventilation Sys That Exceeded TS Limits Due to Improperly Positioned Vortex Damper.Commitments Are Contained in Corrective Actions Section of Encl Rept1999-09-27027 September 1999 Forwards LER 99-015-00 Re Inoperability of Auxiliary Bldg Ventilation Sys That Exceeded TS Limits Due to Improperly Positioned Vortex Damper.Commitments Are Contained in Corrective Actions Section of Encl Rept ML20217A7911999-09-24024 September 1999 Forwards Insp Repts 50-413/99-05 & 50-414/99-05 on 990718- 0828 at Catawba Facility.Nine NCVs Identified Involving Inadequate Corrective Actions Associated with Degraded Svc Water Supply Piping to Auxiliary Feedwater Sys ML20212E6471999-09-24024 September 1999 Discusses GL 98-01 Issued by NRC on 980511 & DPC Responses for Catawba NPP & 990615.Informs That NRC Reviewed Response for Catawba & Concluded That All Requested Info Provided.Considers GL 98-01 to Be Closed for Catawba ML20212F0941999-09-21021 September 1999 Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals for Cns,Units 1 & 2 ML20212M2001999-09-20020 September 1999 Confirms 990913 Telcon Between M Purser & R Carroll Re Management Meeting to Be Conducted on 991026 in Atlanta,Ga to Discuss Operator Licensing Issues 05000414/LER-1999-005, Forwards LER 99-005-00 Re Missed EDG TS Surveillance Concerning Verification of Availability of Offsite Power Sources Resulted from Defective Procedure.Planned Corrective Actions Stated in Rept Represent Regulatory Commitments1999-09-20020 September 1999 Forwards LER 99-005-00 Re Missed EDG TS Surveillance Concerning Verification of Availability of Offsite Power Sources Resulted from Defective Procedure.Planned Corrective Actions Stated in Rept Represent Regulatory Commitments ML20212D5321999-09-15015 September 1999 Informs That Duke Energy Corp Agrees to Restrict Max Fuel Rod Average Burnup to 60,000 Mwd/Mtu,In Order to Support NRC Final Approval & Issuance of Requested Amend ML20212B4641999-09-14014 September 1999 Forwards Monthly Operating Repts for Aug 1999 & Revised Monthly Operating Rept for Catawba Nuclear Station,Units 1 & 2 ML20212A4131999-09-14014 September 1999 Informs That TR DPC-NE-2009P Submitted in 990817 Affidavit, Marked Proprietary,Will Be Withheld from Public Disclosure, Pursuant to 10CFR2.709(b) & Section 103(b) of Atomic Energy Act of 1954,as Amended ML20212M1931999-09-13013 September 1999 Refers to 990909 Meeting Conducted at Region II Office Re Presentation of Licensee self-assessment of Catawba Nuclear Station Performance.List of Attendees & Licensee Presentation Handout Encl ML20212A3751999-09-10010 September 1999 Informs That Postponing Implementation of New Conditions Improved by RG 1.147,rev 12,acceptable Since Evaluation on Relief Based on Implementation Code Case for Duration of Insp Interval ML20212A5191999-09-0808 September 1999 Requests NRC Approval for Relief from Requirements of ASME Boiler & Pressure Vessel Code,Section XI,1989 Edition,App VI,VI-2430(c) & 2440(b).Approval of 99-GO-002 Is Requested by 000301 05000413/LER-1999-014, Forwards LER 99-014-00, Missed Surveillance & Operation Prohibited by TS Occurred as Result of Defective Procedures or Program & Inappropriate TS Requirements. Planned Corrective Action Stated in Rept Represents Commitment1999-09-0101 September 1999 Forwards LER 99-014-00, Missed Surveillance & Operation Prohibited by TS Occurred as Result of Defective Procedures or Program & Inappropriate TS Requirements. Planned Corrective Action Stated in Rept Represents Commitment 05000414/LER-1999-003, Forwards LER 99-003-01, Unplanned Actuation of ESFAS Due to a SG High Level Caused by Inadequate Procedural Guidance. Suppl Rept Provides Info Re Root Cause & Corrective Actions Associated with Event Developed Subsequent to Rev1999-08-31031 August 1999 Forwards LER 99-003-01, Unplanned Actuation of ESFAS Due to a SG High Level Caused by Inadequate Procedural Guidance. Suppl Rept Provides Info Re Root Cause & Corrective Actions Associated with Event Developed Subsequent to Rev 0 of LER ML20211H1741999-08-30030 August 1999 Forwards Comments on Catawba Nuclear Station Units 1 & 2 & McGuire Nuclear Station,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid.Ltr Dtd 990107,rept ATI-98-012-T005 & Partial marked-up Rept WCAP-14995 Encl ML20211M4451999-08-30030 August 1999 Forwards Summary of Util Conclusions Re Outstanding Compliance Issue Re Staff Interpretation of TS SR 3.0.1,per Insp Repts 50-369/99-03 & 50-370/99-03,as Discussed with NRC During 990618 Meeting 05000413/LER-1999-013, Forwards LER 99-013-00,re RHR Heat Exchanger Bypass Valves Not Verified Per TS Surveillance.Surveillance Procedures Have Been Revised & There Are No Further Planned Corrective Actions or Commitments in LER1999-08-25025 August 1999 Forwards LER 99-013-00,re RHR Heat Exchanger Bypass Valves Not Verified Per TS Surveillance.Surveillance Procedures Have Been Revised & There Are No Further Planned Corrective Actions or Commitments in LER ML20211M8191999-08-25025 August 1999 Confirms 990825 Telcon Between G Gilbert & R Carroll Re Mgt Meeting to Be Held on 990909 in Atlanta,Ga,To Allow Licensee to Present self-assessment of Catawba Nuclear Station Performance ML20211A9641999-08-20020 August 1999 Forwards SE Authorizing Licensee 990118 Request for Approval of Proposed Relief from Volumetric Exam Requirements of ASME B&PV Code,Section XI for Plant,Units 2 ML20211C1191999-08-18018 August 1999 Forwards ISI Rept Unit 1 Catawba 1999 RFO 11, Providing Results of ISI Effort Associated with End of Cycle 11 ML20211B9471999-08-18018 August 1999 Forwards Request for Relief 99-02,associated with Limited Exam Results for Welds Which Were Inspected During Unit 1 End of Cycle 11 RFO ML20211C3651999-08-17017 August 1999 Forwards Rev 25 to Catawba Nuclear Station Units 1 & 2 Pump & Valve Inservice Testing Program, Which Includes Reformatting of Manual & Addl Changes as Noted in Attached Summary of Changes ML20211F2971999-08-17017 August 1999 Forwards non-proprietary & Proprietary Updated Pages for DPC-NE-2009,submitted 980722.Pages Modify Fuel Design & thermal-hydraulic Analysis Sections of DPC-NE-2009. Proprietary Page 2-4 Withheld,Per 10CFR2.790 05000413/LER-1999-011, Forwards LER 99-011-00,re Missed Surveillance on Both Trains of CR Area Ventilation Sys Resulting in TS Violation.Planned Corrective Actions Stated in LER Represent Regulatory Commitment1999-08-16016 August 1999 Forwards LER 99-011-00,re Missed Surveillance on Both Trains of CR Area Ventilation Sys Resulting in TS Violation.Planned Corrective Actions Stated in LER Represent Regulatory Commitment ML20211B1121999-08-16016 August 1999 Forwards Topical Rept DPC-NE-2012, Dynamic Rod Worth Measurement Using Casmo/Simulate, Describing Results of Six Drwm Benchmark Cycles at Catawba & McGuire & Discusses Qualification to Use Drwm at Catawba & McGuire ML20210V0321999-08-13013 August 1999 Forwards Insp Repts 50-413/99-04 & 50-414/99-04 on 990606- 0717.Six Violations of NRC Requirements Identified & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20210S2751999-08-12012 August 1999 Forwards Monthly Operating Repts for July 1999 for Catawba Nuclear Station,Units 1 & 2.Revised Rept for June 1999,encl ML20210Q3751999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Authorized Representative of Facility Must Submit Ltr as Listed,Thirty Days Before Exam Date,In Order to Register Individuals for Exam ML20210N9521999-08-0404 August 1999 Forwards Changes to Catawba Nuclear Station Selected Licensee Commitments Manual.Documents Constitutes Chapter 16 of Ufsar.With List of Effective Pages IR 05000413/19980131999-08-0202 August 1999 Discusses Integrated Insp Repts 50-413/98-13,50-414/98-13, 50-413/98-16,50-414/98-16 & NRC Special Repts 50/413/99-11 & 50-414/99-11 Conducted Between Aug 1998 & May 1999.Six Violations Occurred,Based on OI Investigation & Insp ML20210M6411999-07-29029 July 1999 Forwards Request for Relief 99-03 from Requirements of ASME Boiler & Pressure Vessel Code,In Order to Seek Relief from Performing Individual Valve Testing for Certain Valves in DG Starting Air (Vg) Sys 05000413/LER-1999-010, Forwards LER 99-010-01 Which Replaces LER 99-002.Rept Number Has Been Changed in Order to Conform to Numbering Convention Specified in NUREG-1022,since Primary Event Involved Both Units1999-07-22022 July 1999 Forwards LER 99-010-01 Which Replaces LER 99-002.Rept Number Has Been Changed in Order to Conform to Numbering Convention Specified in NUREG-1022,since Primary Event Involved Both Units IR 05000413/19990101999-07-22022 July 1999 Discusses Insp Rept 50-413/99-10 & 50-414/99-10 on 990314- 0424 & Forwards Notice of Violation Re Failure to Comply with TS 3.7.13,when Misalignment of Two Electrical Breakers Rendered SSS Inoperable from 981216-29 ML20217G5241999-07-20020 July 1999 Forwards Exam Repts 50-413/99-301 & 50-414/99-301 on 990524- 27,0603,07-10 & 16.Of Fourteen SRO & RO Applicants Who Received Written Exams & Operating Tests,Eight Applicants Passed & Six Failed Exam 05000413/LER-1999-009, Forwards LER 99-009-00,re Inoperability of Containment Valve Injection Water Sys Valve in Excess of TS Limits.Root Cause & Corrective Actions Associated with Event Are Being Finalized & Will Be Provided in Supplement to Rept1999-07-19019 July 1999 Forwards LER 99-009-00,re Inoperability of Containment Valve Injection Water Sys Valve in Excess of TS Limits.Root Cause & Corrective Actions Associated with Event Are Being Finalized & Will Be Provided in Supplement to Rept 05000414/LER-1999-001, Forwards LER 99-001-01 Re Unanalyzed Condition Associated with Relay Failure in Auxiliary Feedwater Sys,Due to Inadequate Single Failure Analysis.Rev Is Being Submitted to Include Results of Failure Analysis Which Was Performed1999-07-15015 July 1999 Forwards LER 99-001-01 Re Unanalyzed Condition Associated with Relay Failure in Auxiliary Feedwater Sys,Due to Inadequate Single Failure Analysis.Rev Is Being Submitted to Include Results of Failure Analysis Which Was Performed ML20209H4431999-07-14014 July 1999 Forwards Monthly Operating Repts for June 1999 for Catawba Nuclear Station,Units 1 & 2.Revised Rept for May 1999 on Unit Shutdowns Also Encl ML20210A5771999-07-14014 July 1999 Forwards Revsied Catawba Nuclear Station Selected Licensee Commitments Manual, Per 10CFR50.71(e),changing Sections 16.7-5,16.8-5,16.9-1,16.9-3,16.9-5 & 16.11-7.Manual Constitute Chapter 16 of UFSAR ML20216D3941999-07-14014 July 1999 Forwards Revs to Catawba Nuclear Station Selected Licensee Commitments Manual NUREG-1431, Forwards SER Agreeing with Util General Interpretation of TS LCO 3.0.6,but Finds No Technical Basis or Guidance That Snubbers Could Be Treated as Exception to General Interpretation1999-07-0909 July 1999 Forwards SER Agreeing with Util General Interpretation of TS LCO 3.0.6,but Finds No Technical Basis or Guidance That Snubbers Could Be Treated as Exception to General Interpretation ML20196L0371999-07-0808 July 1999 Approves Requested Schedule Change of Current two-year Requalification Examinations to non-outage dates.Two-year Cycle Will Start on 991001 & Will End on 020930 05000413/LER-1999-008, Forwards LER 99-008-00,re Operation Prohibited by TS 3.5.2. Rev to LER Will Be Submitted by 990812 Which Will Include All Required Info About Ventilation Sys Pressure Boundry Breach1999-07-0808 July 1999 Forwards LER 99-008-00,re Operation Prohibited by TS 3.5.2. Rev to LER Will Be Submitted by 990812 Which Will Include All Required Info About Ventilation Sys Pressure Boundry Breach ML20196J9001999-07-0606 July 1999 Informs That 990520 Submittal of Rept DPC-NE-3004-PA,Rev 1, Mass & Energy Release & Containment Response Methodology, Marked Proprietary Will Be Withheld Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954 IR 05000413/19990031999-07-0101 July 1999 Discusses Insp Repts 50-413/99-03 & 50-414/99-03 Completed on 990605 & Transmitted by Ltr .Results of Delibrations for Violation Re Discovery of Potentially More Limiting Single Failure Affecting SGTS Analysis Provided 1999-09-08
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217F8231999-10-13013 October 1999 Informs That on 990930,NRC Completed mid-cycle PPR of Catawba Nuclear Station.Based on Review,Nrc Did Not Identify Any New Areas That Warranted More than Core Insp Program Over Next Five Months.Historical Listing of Issues,Encl ML20217K2651999-10-0101 October 1999 Forwards Retake Exams Repts 50-413/99-302 & 50-414/99-302 on 990921-23.Two of Three ROs & One SRO Who Received Administrative Section of Exam Passed Retake Exam, Representing 75 Percent Pass Rate ML20212J3011999-10-0101 October 1999 Forwards Exemption from Certain Requirements of 10CFR54.17(c) Re Schedule for Submitting Application for Operating License Renewal.Se Also Encl ML20212E6471999-09-24024 September 1999 Discusses GL 98-01 Issued by NRC on 980511 & DPC Responses for Catawba NPP & 990615.Informs That NRC Reviewed Response for Catawba & Concluded That All Requested Info Provided.Considers GL 98-01 to Be Closed for Catawba ML20217A7911999-09-24024 September 1999 Forwards Insp Repts 50-413/99-05 & 50-414/99-05 on 990718- 0828 at Catawba Facility.Nine NCVs Identified Involving Inadequate Corrective Actions Associated with Degraded Svc Water Supply Piping to Auxiliary Feedwater Sys ML20212F0941999-09-21021 September 1999 Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals for Cns,Units 1 & 2 ML20212M2001999-09-20020 September 1999 Confirms 990913 Telcon Between M Purser & R Carroll Re Management Meeting to Be Conducted on 991026 in Atlanta,Ga to Discuss Operator Licensing Issues ML20212A4131999-09-14014 September 1999 Informs That TR DPC-NE-2009P Submitted in 990817 Affidavit, Marked Proprietary,Will Be Withheld from Public Disclosure, Pursuant to 10CFR2.709(b) & Section 103(b) of Atomic Energy Act of 1954,as Amended ML20212M1931999-09-13013 September 1999 Refers to 990909 Meeting Conducted at Region II Office Re Presentation of Licensee self-assessment of Catawba Nuclear Station Performance.List of Attendees & Licensee Presentation Handout Encl ML20212A3751999-09-10010 September 1999 Informs That Postponing Implementation of New Conditions Improved by RG 1.147,rev 12,acceptable Since Evaluation on Relief Based on Implementation Code Case for Duration of Insp Interval ML20211M8191999-08-25025 August 1999 Confirms 990825 Telcon Between G Gilbert & R Carroll Re Mgt Meeting to Be Held on 990909 in Atlanta,Ga,To Allow Licensee to Present self-assessment of Catawba Nuclear Station Performance ML20211A9641999-08-20020 August 1999 Forwards SE Authorizing Licensee 990118 Request for Approval of Proposed Relief from Volumetric Exam Requirements of ASME B&PV Code,Section XI for Plant,Units 2 ML20210V0321999-08-13013 August 1999 Forwards Insp Repts 50-413/99-04 & 50-414/99-04 on 990606- 0717.Six Violations of NRC Requirements Identified & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20210Q3751999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Authorized Representative of Facility Must Submit Ltr as Listed,Thirty Days Before Exam Date,In Order to Register Individuals for Exam IR 05000413/19980131999-08-0202 August 1999 Discusses Integrated Insp Repts 50-413/98-13,50-414/98-13, 50-413/98-16,50-414/98-16 & NRC Special Repts 50/413/99-11 & 50-414/99-11 Conducted Between Aug 1998 & May 1999.Six Violations Occurred,Based on OI Investigation & Insp IR 05000413/19990101999-07-22022 July 1999 Discusses Insp Rept 50-413/99-10 & 50-414/99-10 on 990314- 0424 & Forwards Notice of Violation Re Failure to Comply with TS 3.7.13,when Misalignment of Two Electrical Breakers Rendered SSS Inoperable from 981216-29 ML20217G5241999-07-20020 July 1999 Forwards Exam Repts 50-413/99-301 & 50-414/99-301 on 990524- 27,0603,07-10 & 16.Of Fourteen SRO & RO Applicants Who Received Written Exams & Operating Tests,Eight Applicants Passed & Six Failed Exam NUREG-1431, Forwards SER Agreeing with Util General Interpretation of TS LCO 3.0.6,but Finds No Technical Basis or Guidance That Snubbers Could Be Treated as Exception to General Interpretation1999-07-0909 July 1999 Forwards SER Agreeing with Util General Interpretation of TS LCO 3.0.6,but Finds No Technical Basis or Guidance That Snubbers Could Be Treated as Exception to General Interpretation ML20196L0371999-07-0808 July 1999 Approves Requested Schedule Change of Current two-year Requalification Examinations to non-outage dates.Two-year Cycle Will Start on 991001 & Will End on 020930 ML20196J9001999-07-0606 July 1999 Informs That 990520 Submittal of Rept DPC-NE-3004-PA,Rev 1, Mass & Energy Release & Containment Response Methodology, Marked Proprietary Will Be Withheld Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954 IR 05000413/19990031999-07-0101 July 1999 Discusses Insp Repts 50-413/99-03 & 50-414/99-03 Completed on 990605 & Transmitted by Ltr .Results of Delibrations for Violation Re Discovery of Potentially More Limiting Single Failure Affecting SGTS Analysis Provided ML20209E2701999-07-0101 July 1999 Forwards Insp Repts 50-413/99-03 & 50-414/99-03 on 990425- 0605.Six Violations of NRC Requirements Occurred & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209E3931999-06-28028 June 1999 Informs of 990618 Meeting Conducted at Facility to Present Results of Most Recent Periodic Plant Performance Review for Plant.List of Attendees Encl ML20196G8861999-06-24024 June 1999 Discusses GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structrual Integrity 950816 & 960729 Responses.Rvid,Version 2 Released as Result of Review.Rvid Should Be Reviewed & Comments Should Be Received by 990901 If Not Acceptable for Plant ML20196G6541999-06-17017 June 1999 Confirms 990614 Telephone Conversation Re Rescheduling of Two Predecisional Enforcement Conferences Originally Scheduled for 990623.SSS Conference Rescheduled for 990712 & Ice Condenser Conference Rescheduled for 990720 ML20196A5781999-06-14014 June 1999 Discusses Notice of Enforcement Discretion for Duke Energy Corp Re Catawba Nuclear Station Unit 1 TSs 3.5.2 & 3.7.12 ML20195E9171999-06-0303 June 1999 Confirms Conversation with Bradshaw on 990526 Re Rescheduling 990607 Predecisional Enforcement Conference to Discuss Apparent Violation in Insp Repts 50-413/99-10 & 50-414/99-10.Conference Will Be on 990623 in Atlanta,Ga ML20195F4141999-06-0202 June 1999 Forwards Insp Repts 50-413/99-11 & 50-414/99-11 on 990422-23 & 0503.Apparent Violation Identified & Being Considered for Escalated Enforcement Action.Violation Involved Failure to Maintain Unit 1 Ice Condenser Lower Inlet Door Operable ML20207D0671999-05-20020 May 1999 Informs That During Meeting on 990512,arrangements Modified for Administration of Licensing Exams at Catawba Nuclear Station During Weeks of 990524 & 0607,respectively ML20207C8721999-05-20020 May 1999 Forwards Insp Repts 50-413/99-02 & 50-414/99-02 on 990314-0424.Three Violations Occurred & Being Treated as non-cited Violations.Activities Generally Characterized by Safety Conscious Operations & Sound Engineering & Maint ML20207C8061999-05-19019 May 1999 Confirms 990510 Telcon with R Jones Re Predecisional Enforcement Conference Requested by NRC & Scheduled for 990607 in Atlanta,Ga to Discuss Apparent Violation Associated with Potential Inoperability of SSS ML20207C7761999-05-19019 May 1999 Informs That on 990618,NRC Will Meet with Mgt of Duke Energy Corp to Discuss Performance of Catawba Facility & Extends Invitation to Attend Meeting as Observer ML20206P4911999-05-14014 May 1999 Forwards Safety Evaluation Accepting GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20206M4201999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation (NRR) Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt (DLPM) Created.Reorganization Chart Encl ML20206U4091999-05-10010 May 1999 Forwards Insp Repts 50-413/99-10 & 50-414/99-10 on 990314-0424.One Violation Occurred & Being Considered for Escalated Enforcement Action Involving Inoperability of Standby Shutdown Sys from 981216-29 ML20206N4191999-05-0606 May 1999 Informs That Team Will Inspect Dam at Standby Nuclear Service Water Pond on 990609.Purpose of Insp Will Be to Confirm That Structure Conforms with Design Documents & Capability of Performing Design Functions ML20205S5491999-04-21021 April 1999 Forwards SE Discussing DPC Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions. Response Acceptable ML20206B7941999-04-16016 April 1999 Confirms 990331 Telcon Between M Purser of Util & R Franovich of NRC Re Public Meeting Scheduled for 990618 in York,Sc to Discuss Results of NRC Recent Plant Performance Review for Catawba Nuclear Station ML20205N3471999-04-12012 April 1999 Forwards Safety Evaluation & Eri/Nrc 95-506, Technical Evaluation Rept on Submittal Only Review of IPE of External Events at Catawba Nuclear Station,Units 1 & 2 ML20205T3491999-04-0909 April 1999 Informs That on 990317,T Beedle & Ho Christensen Confirmed Initial Operator Licensing Exam Schedule for Catawba Nuclear Station for Y2K.No Y2K Exam Scheduled.Initial Exam Requested for Apr 2001 for Approx 18 Candidates ML20205N0531999-04-0606 April 1999 Forwards Insp Repts 50-413/99-01 & 50-414/99-01 on 990124-0313.DPC Conduct of Activities at Catawba Facility Generally Characterized by Safety Conscious Operations & Sound Engineering.Five Violations Noted & Treated as NCVs ML20196K9961999-03-30030 March 1999 Forwards Synopsis of NRC OI Completed Rept Re Alleged Compromise of Initial Licensed Operator Exam at Cns.Oi Did Not Substantiate Allegation That Initial Operator Exam Compromised.Plans No Further Action Re Matter ML20205M2651999-03-25025 March 1999 Discusses PPR Completed 990201.Advises of Planned Insp Effort Resulting from Catawba PPR Review.Forwards Plant Issues Matrix & Insp Plan ML20207L7741999-03-15015 March 1999 Requests That NRC Exercise Discretion Not to Enforce Compliance with Actions Required by Plant,Units 1 & 2 Re TS Limiting Conditions for Operation 3.3.7 & 3.3.8 ML20207M9091999-03-0505 March 1999 Informs That Info Submitted by Application, Marked as Proprietary Will Be Withheld from Public Disclosure Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954,as Amended ML20207A5821999-02-17017 February 1999 Forwards Insp Repts 50-413/98-12 & 50-414/98-12 & Notice of Violation.One Violation Being Considered for Escalated Enforcement Action ML20203G5161999-02-0505 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 990407. Representative of Facility Must Submit Either Ltr Indicating No Candidates or Listing of Candidates for Exam ML20203A2421999-02-0505 February 1999 Forwards SE Accepting Proposal to Revise Methodology in TR DPC-NE-3002-A,to Permit Use of single-node Model,Instead of multi-node Model,To Represent SG Secondary Sys for post-trip Phase of Loss of Normal Feedwater Analysis for Plant,Unit 2 ML20202J4751999-01-29029 January 1999 Responds to Concern Raised on 981020 Re Appropriateness of Interaction of NRC Headquarters Operations Officer with on-shift Operations Staff During Event ML20202C2511999-01-27027 January 1999 Forwards Request for Addl Info Re Util 980331 Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, for Catawba Nuclear Station. Response Requested within 60 Days of Date of Ltr 1999-09-24
[Table view] |
Text
_ ___ _ _ _. _ _____ _ _.- ___ .. _.____ _ -_ _._ _
May 16, 1997 l EA 97-179 I
Duke Power Company ATTN: Mr. W. R. McCollum Site Vice President ;
Catawba Site 4800 Concord Road York, SC 29745-9635
SUBJECT:
NOTICE OF VIOLATION l (NRC INSPECTION REPORT N0. 50 413/96 05, AND 50 414/96 05)
Dear Mr. McCollum:
We have completed our review of your response of June 27, 1996, to our Notice of Violation issued on May 31, 1996, concerning activities conducted at your Catawba facility. In your response, you admitted Violation A and denied Violation B.
After careful consideration of the basis for your denial of Violation B, we )
- have concluded, for the reasons presented in the Enclosure to this letter, l l that although a violation of 10 CFR 50.59 as cited in Violation B did not occur, a violation of NRC requirements occurred. Violation B as stated in the Notice of Violation issued on May 31, 1996, is withdrawn and replaced by the i enclosed Notice of Violation. Please note that you are required to res>ond to this letter and should follow the instructions in the enclosed Notice w1en preparing your response. The NRC will use your response, in part, to determine whether further action is necessary to ensure compliance with l regulatory requirements. !
We are concerned regarding statements made in your response to Finding 2 of l l Violation B. Your response implies that you find it acceptable to implement i design changes prior to the certification and release of design calculations.
This practice is contrary to your design control measures which implement the requirements of 10 CFR 50, Appendix B. Criterion III. Your response should also address clarification of your understanding of your design control
- measures and the necessary corrective actions to comply with requirements of
! 10 CFR 50, Appendix B.
7 I
- ,I 4
9705290257 970516 PDR ADOCK 05000413 llllllllll]lllllllll0ll
... c
DPC 2
.In accordance with 10 CFR 2.790 of the NRC's Rules of Practice," a copy of this letter and its enclosures will t,e placed in the NRC Public Document Room (PDR).
Sincerely, Original signed by Johns P. Jaudon Johns P. Jaudon, Director l Division of Reactor Safety Docket Nos. 50 413, and 50 414 i License Nos. NPF 35, and NPF 52 l
Enclosures:
- 1. Evaluations and Conclusion
- 2. Notice of Violation
, cc w/encls: Max Batavia, Chief l H. S. Kitlan Bureau of Radiological Health <
l Regulatory Compliance Manager S. C. Department of Health l Duke Power Company and Environmental Control 4800 Concord Road 2600 Bull Street York, SC 29745 9635 Columbia, SC 29201 Paul R. Newton Richard P. Wilson, Esq.
Legal Department (PB05E) Assistant Attorney General Duke Power Company S. C. Attorney General's Office 422 South Church Street P. O. Box 11549 Charlotte, NC 28242 0001 Columbia, SC 29211 Robert P. Gruber Michael Hirsch Executive Director Federal Emergency Management Agency Public Staff - NCUC 500 C Street, Sw, Room 840 P. O. Box 29520 Washington, D. C. 20472 Raleigh, NC 27626 0520 North Carolina Electric J. Michael McGarry, III, Esq. Membership Corporation
, Winston and Strawn P. O. Box 27306 1400 L Street, NW Raleigh, NC 27611 Washington, D. C. 20005 l Karen E. Long North Carolina MPA 1 Assistant Attorney General
! Suite 600 N. C. Department of Justice i P. O. Box 29513 P. O. Box 629 l Raleigh, NC 27626 0513 Raleigh, NC 27602 f (cc cont'd - See page 3) l l
. . , _ . _ . _ _ . . . . _ _ . _ . _ . _ . ~ . . . _ . _ , _ _ _ _ . _ _ _ . _ . _ _ _ _ . . ~ _ . . _ _
l O-l DPC 3 :
(cc cont'd) Distribution w/encis: I Saluda River Electric P.. Tam, NRR .
Cooperative, Inc. R. Carroll, RII P. O. Box 929 R. V. Crienjak. RII i
. Laurens SC 29360 N. Economos, RII- '
l- . R. Baldwin, RII :
i Peter R. Harden IV PUBLIC I i- ' Account Sales Manager I Power Systems Field Sales NRC Resident Inspector l Westinghouse Electric Corporation U.S. Nuclear Regulatory Commission
, P. 0.-Box 7288 4830 Concord Road l Charlotte, NC 28241 York, SC 29745 i
L County Manager of York County l
York County Courthouse l- York, SC 29745 Piedmont Municipal Power Agency 121 Village Drive Greer, SC 29651 G. A. Copp Licensing EC050 Duke Power Company P. O. Box 1006 Charlotte, NC 28201 1006
- .T. Richard Puryear l Owners Group North Carolina Electric Membership Corporation ,
4800 Concord Road York, SC 29745 [ ehg f
f y l4 l
$'\W b4 i s# 2 SIGNATURE NAME f
JLenahan:od CCtristen
[
CCatto B ye. ,
DATE 05 / 11 / 97 05 / 1 3 / 97 05 / v1 / 97 48hf / 97 05 / /9'05 / / 9:
COPY? @ NO /TE3 NO YES d D 1/YES) NO YES YES OFFICIR. RECORD COPY DOCUNENT NME:kADRS\EB\CATEAR1.JL i b
I I
i . __ _ . _ - _ _ ,- _-_ _
I Evaluation and Conclusion '
On May 31, 1996, a Notice of Violation (Notice) was issued for violations identified during a routine NRC inspection. Duke Power Company responded to the Notice on June 27, 1996. Duke denied Violation B based on their
- contention that they com) lied with their procedures in the unreviewed safety question screening and t1e operability review 3erformed prior to. revising the auxiliary feedwater operating procedure. The NRC's evaluations and ,
conclusions regarding the licensee's denial are as follows: i l Restatement of Violation B .
l 10 CFR 50, Appendix B, Criterion V, requires that activities affecting '
quality be prescribed by documented instructions or procedures, and shall be accomplished in accordance with these instructions or procedures.
l 10 CFR 50.59 requires the performance of an evaluation to determine if changes to the facility (systems, structures, or components) or facility operating procedures described in the l Safety Analysis Report (SAR) involves an unreviewed safety question.
P Duke Power Nuclear Station Directive (NSD) 209, 10 CFR 50.59 Evaluation, Revision 3, effective October 1,1995, implements the requirements of 10 CFR 50.59. Section 209.10.2 of NSD 209 specifies the screening process required to be performed to determine if a facility or procedure change constitutes an unreviewed safety question which in part requires negative answers to the following questions:
Does the activity change the facility as described in the SAR?
Could the activity adversely affect any system, structure, or component that is necessary in accordance with the SAR?
NSD 209 defines the SAR as the set of documents used to support issuance of a plant operating license. These cacuments include, but are not limited to, the Facility Operating License, the NRC !
Safety Evaluation Report, the FSAR, the Technicel Specifications, l and other licensing documents. !
Section 101.4.3 of Engineering Directives Manual EDM 101, Engineering Calculations / Analyses, Revision 4, dated March 30. i 1995, requires certification of design calculatior s prior to release of calculation results.
l l Enclosure 1 l
i
. j l
2 Contrary to the above:
- 1. The 50.59 evaluation was inadequate in that the negative i responses to the NSD 209 questions were incorrect for addressing the February 21, 1996, change to Enclosure 4.12 l of procedure OP/1/A/6250/02, Auxiliary Feedwater System.
l Increasing the allowable auxiliary feedwater )iping j temperature to 250 F changed the design of t1e auxiliary I feedwater system, as described in the SAR. The reduction of
.the concrete expansion safety factor,.from four to two, to !
permit operability of the auxiliary feedwater piping at a '
i temperature of 250* F decreased the margin of safety and had l a potentially adverse effect on the design of the auxiliary L feedwater piping. NRC IE Bulletin 79 02, a licensing ,
document, requires a minimum safety factor of four for &
concrete expansion anchors. ,
l 2. Engineering calculations were released prior to completion i i
of the design certification process, in that on February 21, l 1996, a change to Enclosure 4.12 of Procedure OP/1/A/6250/02 l was made with uncertified calculations. In changing
, Procedure OP/1/A/6250/02, for raising the acceptable i l Auxiliary Feedwater suction temperature, approved February ,
21, 1996, engineering calculations supporting this change
~
l were not approved until on, or after, March 5, 1996. These calculations formed the bases for approval of the procedure change ,
=
This is a Severity Level IV violation (Supplement I) :
Summary of Licensee's Response ;
e The licensee contends that they complied with their procedures and NRC requirements for performing the 50.59 evaluation and that their responses made t in the Unreviewed Safety Question (USQ) screening were correct. The licensee ;
also contends that the calculations performed to determine the acceptability :
of 50.59 changes are not required to be design verified prior to j implementation of the change.
NRC Evaluation l i f i NRC has carefully reviewed the licensee's response. We have concluded that although a violation of 10 CFR 50.59 did not occur, the licensee failed to 5
, follow their procedures when performing the 50.59 screening (NSD 209) and the I
operability review (NSD 203). While the licensee's reasons for revising procedure OP/1/A/6250/02 to eliminate an operator workaround, and i
l l l Enclosure 1 !
! l i
?
I i l._______._. _ _ _ _ _ _ . _ . . -
~
3 to preclude frequent operation of the auxiliary feedwater pump are justified, their 50.59 evaluation and screening performed prior to implementing the procedure changes was not done in accordance with procedure NSD 209. The change to the operating temperatures for the AFW system was a design change.
NSD 203, Operability, Revision 4, effective date January 1, 1996, is the procedure which specifies the steas to be used in performance of. operability reviews. Paragraph 302.7.4 of NS) 203 requires performance of a 10 CFR 50.59 Evaluation for any system, structure, or component (SSC) which is concluded in an operability evaluation to be degraded. NSD 203 defines operable but degraded, in part, as a situation when a SSC relies on temporary changes to a design limit or design basis in order to remain operable. Paragraph 203.9.2 of NSD 203 requires that a calculation be originated in accordance with EDM-101, Engineering Calculations / Analyses, for a safety related (QA Condition)
SSC when the operability evaluation will change the design basis, design criteria, or design limit.
Nuclear System Directive (NSD) 209,10 CFR 50.59 Evaluations, is the licensee's procedure for performing reviews to determine if a design change changes the facility as described in the safety analysis report. NSD 209 provides an initial screening process which consist of five questions to determine if an unreviewed safety question evaluation is required. The five questions are as follows:
- 1. Does the activity change the facility as described in the SAR?
- 2. Does the activity change procedures, methods of operation, or alter a test or experiment as described in the SAR?
- 3. Does the activity appear significant enough to require inclusion in the SAR?
- 4. Could the activity adversely affect any SSC that is necessary to operate the facility in accordance with the SAR?
- 5. Does the activity perform a test or experiment that is NOT described in thn SAR?
The safety analysis report (SAR) is defined in NSD 209 as the set of documents used to support issuance of a plant operating license. These documents include, but are not limited to, the Facility Operating License, the NRC Safety Evaluation Report, the FSAR, the Technical Specifications and other licensing documents such as selected licensee commitments and other communications between the licensee and NRC.
If the answer to all five questions is "No", an unreviewed safety question l (USQ) evaluation is not required. The licensee's 50.59 evaluation for the I change to Procedure OP/1/A/6250/02 resulted in "No" answers to all five questions, thereby resulting in determination that a USQ evaluation was not t
Enclosure 1 l
l
4 I
required. The NRC determined that the answers to questions one and four ,
should have been "Yes", and that a USQ evaluation should have been performed.
The licensee contends that their "No" answers to these screening questions were correct.
For Question 1, the licensee argues that the change to the operating :
. temperature . limit did not affect the structural integrity of the auxiliary '
feedwater system, or reduce the margin of safety. The licensee stated in !
l their response that reduction of the factor of safety for loading of concrete ;
expansion anchors from four to two complies with IE Bulletin (IEB) 79 02, Pipe :
Support Base Plate Designs Using Concrete Expansion Anchor Bolts. IEB 79 02 i was used to su) port issuance of the plant operating license, and therefore, in '
accordance witi NSD 209, is included in the SAR. IEB 79 02 requires concrete expansion anchors to have a minimum factor of safety of four. The licensee !'
interprets IEB 79 02 as >ermitting interim operation with a factor of safety of two until the anchor )olts can be modified at the next refueling butage. !
NRC disagrees with the licensee regarding their interpretation of IEB 79 02.
The factor of safety of two criteria s)ecified in IEB 79-02 permitted interim l operations when concrete expansion anc1 ors were identified during inspections being performed by licensees to comply with IEB 79 02. Similar criteria for i interim operations for resolving degraded conditions are specified in NRC ;
Generic Letter 91 18. Neither IEB 79 02 nor GL 91-18 address implementation l of design changes which result in reducing the factor of safety for concrete expansion anchors below the minimum values specified in IEB 79-02.
Implementation of the procedure change, i. e. design change, permitted increasing the operating temperature of the auxiliary feedwater piping. The
- temperature increases resulted in increasing the loads acting on pipe support i concrete expansion anchors. Thus, this activity did affect the facility, !
s)ecifically the margin of safety for the concrete expansion anchors. i Tierefore, the answer to Question 1 should have been "Yes", based on the ~
l criteria of NSD 209.
IEB 79-02 was issued by NRC due to numerous problems identified at several facilities with installation of concrete expansion anchors. IEB 79 02 ;
required a minimum factor of safety of four for the drilled in shell or wedge type concrete expansion anchors used at the licensee's facility. The factor of safety is defined as the ultimate capacity of the anchor determined by !
! testing divided by the design load. This requirement is implemented in i paragraph 3.10 of Duke Specification CNS 1206.00-04 0001, Design Specification i for Nuclear Safety Related (QA Condition 1) and QA Condition 4 Component i Supports. The reduction of the factor of safety as much as 50 percent, from 1 i specified minimum value of four, to factors of safety as low as two, '
essentially doubled the design load carried by the anchors. This activity had the potential to adversely affect the AFW system, which is necessary to operate the 31 ant in accordance with the SAR. Therefore, the answers to question num)er 4 should have been "Yes".
! Enclosure 1 l
5 The positive answers to Questions one and four would have required the licensee to perform additional review of the issue to determine if the temperature changes would result in an unreviewed safety question. These additional reviews are described in NSD 209.
The licensee also contends that, in finding 2 of Violation B, NRC misinterpreted Duke arocedure NSD 209, which specifies the requirements for performance of 10 CFR 50.59 evaluations. The licensee stated since NSD 209 specifies that an engineering review was an adequate level of review to perform the 10 CFR 50.59 screening, the requirements for design control reasures do not apply to 50.59 changes. The licensee's response implies that it is not necessary to perform calculations and have the calculations design verified and certified prior to implementing a 10 CFR 50.59 change. However, as discussed above, Duke procedure requires origination of design calculations in accordance with EDM-101 for operability reviews for conditions which will change the design basis, design criteria, or design limit. Review of the licensee's justification for revising the operating temperature of the AFW piping was based on the design output from several calculations referenced in the inspection report. The change to the AFW system operating temperature was a design change. The requirements for design changes are specified in 10 CFR 50, Appendix B, Criterion III, which in part requires that measures be established to assure that the design basis are correctly translated into design output documents. Criterion III further recuires that the design control measures shall provide for verifying the acequacy of the design, and that design changes be subject to design control measures commensurate with those applied to the original design. The procedures which implement the A'pendix a B, Criterion III requirements are the Engineering Directives Manual, w1ich are the Duke Power Company design control measures. The design change that the licensee implemented to the AFW system operating temperature is required to comply with 10 CFR 50, Appendix B, Criterion III. Therefore the requirements of EDM 101, as referenced in Finding 2 of Violation B were correct. 10 CFR 50, Appendix B, Criterion V, requires that activities affecting quality be accomplished in accordance with prescribed instructions or procedures. Failure to implement the design verification and control measures as specified in EDM-101, and relying on unapproved calculations, to implement the design change, was a violation.
Furthermore, paragraph 203.9.2, Engineering Requirements, of procedure NSD 203 required operability evaluations to include preparation of a calculation in accordance with procedure EDH 101. The operability evaluation was required to be documented on a "203 Operability Notification Form".
NRC Conclusion For the above reasons, NRC concludes that a violation of 10 CFR 50.59, as stated in Violation B, did not occur. Therefore Violation B, issued on May L , 1996 is withdrawn. However, a violation of NRC requirements did occur as stated in the enclosed Notice of Violation.
Enclocure 1