Monthly Operating Repts for Jan 1985
ML20112A559
Person / Time
Site: Surry  Dominion icon.png
Issue date: 01/31/1985
From: Jones V, Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Beebe M
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
85-100, NUDOCS 8503180361
Download: ML20112A559 (40)


Text

' ,

o .

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION MONTHLY OPERATING REPORT REPORT NO. 85-01 APPROVED BY: .) V X 2-v STATION 41ANAGER 8503180361 850131 PDR R

ADOCK 05000200 PDR h I

r i

Section Page Operating Data Report - Unit #1 1 Operating Data Report - Unit #2 2 Unit Shutdowns and power Reductions - Unit #1 3 Unit Shutdowns and Power Reductions - Unit #2 5 Load Reductions Due to Environmental Restrictions - Unit #1 6

. Load Reductions Due to Environmental Restrictions - Unit #2 7 Average Daily Unit Power Level- Unit #1 8 Average Daily Unit Power Level- Unit #2 8 Summary of Operating Experience 9 Amendments to Facility License or Technical Specifications 13 Facility Changes Requiring NRC Approval 14 1

1 Facility Changes That Did Not Require NRC Approval 15 Tests and Experiments Requiring NRC Approval 17 Tests and Experiments That Did Not Require NRC Approval 17 Other Changes, Tests and Experiments 18 i

J Chemistry Report ,

19 Description of AllInstances Where Thermal Discharge 20 Limits Were Exceeded

Fuel Handling 21 Procedure Revisions That Changed the Operating Mode i Described in the.FSAR 23 l

l Description of Periodic Tests Which Were Not Completed l Within the Time Limits Specified in Technical Specifications 24

11 Section Page Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit #1- Mechanical Maintenance 25 Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit i2 - Mechanical Maintenance 28 Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit #1- Electrical Maintenance 30 Maintenance of Safety Related Systems During Outage or ,

Reduced Power Periods - Unit # 2 - Electrical Maintenana 33 Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit #1-Instrument Maintenance 35 Maintenance of Safety Related Systems During Outage or Reduced Power Periods - Unit #2 -Instrument Maintenance 38 e

I i

VEPCU UPER AllNG DAT A REPORT DUCKEI NO. 50-280 DATE JANUARY I, 1985 LOMPL(TED Bf v. JUNES TELEPHONE 804-357-3194 OPERAllNG SIAIUS

1. UNii NAME SURRV UNii I
2. REPORi!NG PERIOD JANUARY 1985
3. LICENSED IHERMAL PUwER -Mwi- 2441
4. NAME PL ATE R A TING -GRUSS MAE- 847.5
5. DE5lGN ELECTRICAL H A T ING -NE T MwE - 788 *
6. MAXIMUM DEPEND AHL E C AP AC liv -GROSS MWE- 811
7. MAxlMUM DEPENDAHLE CAPACITY -NE T MwE- FF5
8. IF CHANGES OCCUR IN CAPACIIY R A T I NGS

-liEM5 3 IHR out.H F- SINCE LAST REPORT. GivE RE4 SONS

9. P0wfR LEVEL TO WHICH RESTRitiED, IF ANY i

-NEI Mut-

10. RE ASONS FUa RESTRICil0NS, IF ANY THIS MUNIH VR-TU-DATE CUMMUL Ail vE

,  !!. HOUR 5 IN REPORilHG PERIOD F44.0 T44.0 106176.0 ""

12. NUMBER UF HOURS REACIOR WAS CRITICAL 687.8 687 . 8 65064. 5 ' r
13. REALIUR RESERvC $HufUUwN HOUR 5 0.0 0.0 3774.5
14. Hudd5 GINERAIOR DN-LINE 663.3 6'63.3 ' 3672 6 .4
15. UNIT RESERVE SHUIOUWN HOURS 0.0 0.0 3736.2
16. GROSS IltFRMAL E NERGY GENER AT ED -M WH- 1292093 2 1292093.2 14 7306270.3
  • IF. GRUSS ELEC TRIC AL E NERGY GENER A T ED -MwH- 427375 0 427375.0 4 T 279338.0
19. NET EL FC TRIC AL ENERGY GENERATED -MwH- 403158.0 403158 0 44 81500LO
19. UNII SERVILE FACIUR 89 2% 89 25 60.0 %
20. UNii AvalLABILIIV FACIOR 8 %2 s 89 2% 63.5%
21. UNii (APAClif FACIDR -USING MOL NET- 69.9% 69 9% 54 5%
22. UNIT CAPAtlif FACTUR -USING DER NET- 68.84 68 8% 53 6%
23. UNI T FORCED OUT AGE R A TE 10.64 10 8% 20 3t
24. SHuiDUwMS SCHEDULED UWER NExi 6 M ON TH S

-iVPE, DATE AND DURAil0N OF EACH- Snubber / Maintenance 06-14-85 10 Days

25. IF SHUI DOwN AT END OF REPORT FERIUD, E5ilMATE IIME UF STARIUP
26. UNIIS IN TEST STATUS FORELAST ACHIEvfD

-PRIOR TO LUMMERCIAL UPEkAilON-

/

INiilAL CRiflCALITY INITIAL ELECIRICITV COMMERCIAL UPERATION ud #

~

i i~

WEPCO UPERAIING UATA REPORI

, 00CKET No. 50-281 '

UAIE JANUARf 1. 1985 COMPLETED Bf v. JONE S UPERATING STAIUS

' l. UNIf NAME SURRY UNil 2

2. REPORilNG PERIUU JANUARY 1985 g 3. LICENSEU THERMAL POWER FMWI- 2*"I 4 NAME PL ATE R4T ING -GROSS MwE- 847.5
5. UE S IGN E LE C TR IC AL R A TING -NE T MWE- 788
6. MAXIMUM DEPENDABLE CAPACITY -GRuS5 MwE- 811 I

T. MAXIMUM DEPENDABLE C AP AC IT Y -NET MwE- TT5

8. IF CHANGES UCCUR IN CAPAClif R A l l NG5 I -I TEM 5 3 IHROUGH F- SI NC E LAST ,

REPORI, GlvE REASONS

9. PUwER LLVEL fu WHIC'l RESTRICIED, IF ANY I -NET Mwl-
10. RE ASONS FOR RE51RICil0N5, IF ANY I

THIS MONTH VR-id-UAIE CUMMUL AT I VE I II. HOURS IN REPORilNG PERIOD 744.0 744 0 101056.0 bJ

12. NUMhER OF HOURS RE AC IOR W AS CR I TIC AL 744.0 744,0 ' '
13. REALTUR RESERVE SHUf00wN HOUR 5 N.750*2 0.0 00 328 1 I
14. HOUR 5 GENER AIUR UN-CINE 144.0 744 0 65651.6 g 15. UNIf RESERVE SHUTUUwN HOURS 0.0 00 00
16. GRUSS THERMAL ENERGY GENERATED -MwH- 1747371.6 1747371.6 153745776. 9 g JT. GRUSS ELELIRICAL ENERGY GENE R A IED -MWH- 560080.0 560080.0 49850554. 0
18. HET ELECINICAL ENERGY GENERATEU -MwH- 531250. 0 531250. 0 '47247692.0
19. UNIT SLRvlCE FACIOR 100.04 100 04 61.74 I 20. UNIT AvalLABILliv FACIOR 100.04 100.0% 63 7% .
21. UNii CAPACIff FACTOR -USING MOC NET- 92.1% 92. 1% 51 2*
22. UNll CAPAltiv FACIOR -USING UER NET- 90. 6 % 90. 6% 58 24 I 23. UNIT FURLEO UUIAGE RATE 0 05 U.03 14.44
24. SHUIDOWNS SCHEUULED UvfR NENT 6 MUNIHS

-ffPE, UATE AND OURATION OF EACH- Ref ueling D3-22-85 87, Days k

25. IF 5Hui UUwN AT ENU UF REPDRI PERIOU.

E5flMAIL TIME OF STARIUP I 26. UNII5 (N TEST STATUS FORECAST ACHIEVEU

-PRIUR fu COMMFRCIAL UPERAllON-

, INiilAL CRiflCALITY INITIAL ELEClullair COMMERL I AL UPER ATION

%d

  • 50-280 IPOCKET NO.

UNITSilUIDowNS ANI) POWER REDUCTIONS Surry I llNIT NAME

<DA1E 02-07-85 Janu 4, .TED M L Jmm REPORT MONill 1ELEril0NE ~K7-31R4 m

3

  • Eb 3 )yM g U l.lcensee (* Cause A Cosiecilve Aralim to blie. Date E- Event ts i l N $ j#5 Reppel # D f Psevesel Recussence

--85-1 01-12-85 F 29.8 A 1 Reactor shutdown to allow repair of I-RG-

  • 63, packing was adjusted and valve was backseated to stop leakage.

85-2 01-13-85 F 4.5 G 3 85-002 Reactor trip during startup caused lo-lo S/G level in "B" S/G. Inexperienced operat-or on feed control.

e 85-3 01-22-85 P 0.0 )I I Unit was reduced to 29% power (150 MW's)

" ^

due to loss of intake canal level caused by icing and low tide at the low level intake.

85-4 01-26-85 F' 38.9 A 3 Reactor trip caused by overpoweroT signal from channels I & H. Channel II was in trip due to failed RTD and a vital bus spike was received from V.B. I when breaker tripped for unknown reasons. I:WR was performed prior to startup running channel II control RTD to the protection racks allowing chan-nelII to be taken out of trip.

3 4 I 2 Reasim: Methal: Enlilble G Instsucilims F: FenceJ for Psepseselon of pass 5: Scheduled A Equipment Felluse(Emplain) 1 Manuel 2-Mannel Sesem. F.niry Sheels Ion I.icensee R. Maintenance of Tesi F Refueling 3-Aulomatic Screm. Event Repose (l.ER) File INilRI.G-D-Regelsioey Restslction 4 01hes (Emplehil 0161)

E-Opesalos Tosining & Ucense Examineilon -

3 F Adndnisitellve G Opernelonsl Esso (Explain) Eslilble I- Same Souwe l'8/ F7 ) ll-Othes (Emplain)

l

)

l IM)CKET No. 50-280 l UNITSilU1 DOWNS AND FOWER REDUCTIONS ilNIT NAME _ Surry I

  • pATE 02-07-85 COMPLETED BY V. Innm:

REFORT MONrtl January.1985 1ELErilONE 357-31114 m ~h .

.I j $ 3 s.E.

1icensee $4 Cause & Coerecalve No. , Date k g se j Event

  • wg Actkin so

{

F o$ ev. j di Repml # j hevent Recurrence 85-5 01-28-85 C 7.5 G 3 85-003 Reactor trip by turbine trip. Turbine trip 85-004 by anti-motoring trip which was caused by 85-005 the anti-motoring sensing line being isolated.

Revise valve-line-ups and drawings to show valves in correct position and mark drawings to show anti-motoring sensor. i a

i

./

I 2 3 4 F: Fmced Reason: Methml: Enhible G . Insieucihins S: SciwduleJ A Equipment Falluse(Emplain) 1 Manuel for Peepseselon of Dans 2 Manant Scism. Entry Slieets for 1.icensee 8-Maintenance or Test C-Refueling 3-Automsele Scrain. Event Repues (l.ER) File INUREG-D Regulaquey Restilction 44)ther (Emplain) 0161)

E-Openseur T:sining & Ucense Examinathm . -

5 F.Adadnistisilve G.Operationel 1 : ve (Emplain) thhlbit 1 Same Source l9/77) Il-Other (Emplahi)

f)OCKET NO. 50-281 UNITsiluillowNs ANI)l'OWER REDUCTIONS Surry II llNIT NAME DA1E 02-07-85 COMPl.ETER) fly V. Jones REFORT MONygt January,1985 1El.F.plHJNE 357-3184 i

.l "L

  • 8 5esh h Cauw A Cosseceive

~

g 3Eg ] '3 Eg II"""' $*. g4 g,' 9,,,

y -

g te 3 W 3di E""8 Repool #

E

"} } Psevent Recurrence Acelim to 0.0 Unit was reduced to 20% power (130 MW's) 85-1 01-22-85 P 11 1 85-001 due to loss of intake canal level caused by icing and low tide at the low levelintake.

I u.

e j , ,/

4 3 4 i

i 1 Method: Enidbit G . instancilims F: Forced Ressem:

for prepstation of Data 5: Scheduled A. Equipment Fallwe(Emplain) 1 Manuel 2-Manual Severn. Entry Sheces for I.leemee B Maintenance of Test Event Repms (LER) File INUREG-C. Refueling 3- Automatic Scram.

4 Other (Emplain) 0161)

D-Regulstoey Restelettem

E Opesatos Tsaining & IJcense Examinelkm -

5 F Adadnisteenive Enlilble i . Same Souste G-Opesallonal Essus (Emplain) l'8/77) 11 Otises (Emplahi)

?

LOAD REDUCTIONS DUE TO ENVIRONMENTAL RESTRICTIONS UNIT NO. ] MONTE: January,1985 I

l  !

DATE TIME HOURS LOAD, L' REDUCTIONS,IG MWH REASON l

None During This Reporting Period e

i e

e O

MONTHLY TOTAL t +

LOAD REDUCTIONS DUE TO DWIRONMENTAL RESTRICTIONS UNIT NO. 1 MONTE: Tanuary.1985

, t DATE THE HOURS LOAD, MW PIDUCTIONS, K4 KJH REASON l

i.

None During This Reporting Pericd

  • O O

l MONTHLY TOTAL I

A M - 14 A s. 4 4 -4 --

-e -

o

_g_

1

< l d

L.

1 4 ~

ee .f E

. 45 t # .

T e e

\ ** T

.eu.

e".

s A

4 N E4O P O av 7 *) _

E e

- ce e T f*>> $ 3

  • O s N e 1 y a

=* Oe = $

  1. : =2 *= A ss. 4: e*f T r e c t *= O
  • c = N ? *. d : r C N o. zuCT 9 4 2" e e e o e o e o e e e o e o e o e e e e e e e e e e e e e e N
  • I ** O $ > 9 a.e CJ Pd g WS *d 7 en a.s **Ngf g@rg% .a f J ? N.* 1f,**E O 4 N g as .* O**  ?
  • 7 * ? 2 2 3 3 T
  • 3 7
  • 4 *** * *P C #*
  • t*9 h, E
  • L g

e

==

t g a= o., em m. p. p. p. m. a. a. a. m. m. e. e. p. m. == r .f. a. m m m. a. m. a. a. e. m. N 4 , A == 4 E 7 } <d C 0 2 _  :. :

j- *"'

1 .

1 2 i O s d 1 w 4 s

4 4 D 4

e

, T 4

7 j

4 I I Y

4

=

+e.9 4

i.

I e e

M S  %

e 9

- Te

(

s .

  • a K e+

t

[

j .

a r N

2 7*

8 1 3 1 end t

c a *

+ TJ l *J 4 CK t .

# 2 se

.> e Ow N O .e e e e c e s. c e t o m m e. m c. = e c .o r a m o e. .. ==

e

= l iw a-e e e e e e e e o e o e o . . e e e e e e o e o e e e e o e e

. J eeaNOa-r#st o e #, es e 3 e N ? e o o a- oos#-*

b l ?mm Gco# ) d=> E** CNm%

  • gLT j

.r, Q

- - s .=,",r<<<ceatcoN me , r S S.

  • P ~~ r-~~- e~~

) == s 2 a= a. 4?

I ' 9 w 7e

% < O

~P aJ w 7 3  ?

l = 3 4 4 2 x

( 3 .J i a

. m 4 l J **

i 7 N

F

. 4 K

I *

e. 4 - N a t o o ~ c := s 3 8 9 9 r e c am e>3-

.g 3 .. N. m .s. .e .o. m e. . .? v w N v N N av e N N

  • 9 D

s

  • L M

D e

9 e

U M M .' W W U M 'W W N '8 g- Ee w

  • - - ,-- v----&~--, ,*, , tr y v mw--,-- -m,<i----.--., v . , --

-t-vi-+. -, , ,- im- .- - - . - - - - -- e- e e .-- , . , - , e -

-9_

SUMMARY

OF OPERATING EXPERIENCE MONTH / YEAR January,1985 Listed below in chronological sequence by unit is a summary of operating experiences for this month which required load reductions or resulted in significant non-load related incidents.

UNIT ONE 01-01-85 0000 This reporting period begins with the unit at 35% power (180 MW's),

holding for Chemistry.

1130 Commenced power increase at 3%/ hour.

2245 Holding power at 65% (400 MW's) while NI's are being calibrated.

2335 NI's now reading 54% (400 MW's) after calttration.

01-02-85 0010 Commenced power increase at 3%/how.

0326 Holding power at 66% (495 MW's) while putting MSR's in service.

1030 MSR's in service, power at 70% (530 MW's) holding for Chemistry.

01-03-85 0420 Commenced power increase at 3%/ hour.

0630 Holding power at 76% (580 MW's) due to low feed pump suction pressure

, while recircing the HP drain system to hotwell.

1500 Commenced power decrease due to condeneer vacuum problems* while removing " A" water bcx from service to plug a tube leak.

1533 Holding power at 67% (465 MW's) 01-04-85 2248 Commenced power decrease to remove "B" main feed pump from service to repair seals.

2350 Holding power at 61% (440 MW's).

01-05-85 2314 Commenced power increase at 3%/ hour.

01-06-85 0800 Holding power at 79% (625 MW's) for Chemistry.

01-07-85 0305 Commenced power increase at a slow rate while monitoring Chemistry.  ;

0800 Holding power at 79% (625 MW's) for Chemistry. I 1

01-11-85 0709 Commenced power increase at slow rate while monitoring Chemistry.

0925 lloiding power at 89*.' ( 740 MU's) for Chemistry.

1

Pagm 2 Unit One (Continued) 01-12-85 0600 Commenced plant shutdown to repair 1-RC-63 at 150 MW/hr.

1049 Unit off the line.

1101 Reactor shutdown.

01-13-85 0631 Reactor critical 1632 Generator on the line.

J 1638 Reactor trip, caused by "B" S/G lo-lo level r, 1906 Reactor critical 2108 Generator on the line.

2140 Holding power at 30% (180 MW's) for Chemistry.

01-14-85 2304 Commenced power increase at 150 MW/hr.

01-15-85 0000 Holding power at 42% (310 MW's) evaluating RCS leak rate.

, 0459 Commenced power increase at 150 MW/hr.

1047 Holding power at 87% (730 MW's) for Chemistry.

01-17-85 1219 Commenced power increase, very slowly as Chemistry permits.

01-19-85 2045 tJnit at 100% power (820 MW's) 01-22-85 0722 Commenced a rapid power reduction, losing intake canal level due to icing at the-canallevelintake.

0850 Holding power at 29% (100 MW's) canal level is stabilized. Holding power increase for Chemistry.

180. Commenced power increase at 150 MW/hr. -

01-23-85 0429 Unit at 100% power (810 MW's).

01-26-85 0931 Rehetor trip, caused by overpower T signal (2/3). Channel II was 4n trip because of a failed RTD when a voltage spike on vital bus I causing a channel I reactor trip signal.

01-27-85 0242 Reactor critical.

0748 Reactor trip from 12% power caused by turbine trip when 4/4 stop valves drifted closed due to EHC problems.

1941 Reactor critical.

. _.. . ._ =-. - -

l Paga 3

- Unit One (Continued) 01-28-85 0028 Generator on the line.

0030 Reactor trip by turbine trip, turbine trip was a anti-motoring trip, found low side sensing line manually isolated to the anti-motoring D/P sensor.

0538 Reactor critical.

01-28-85 0800 Generator on the line, increasing power at 150 MW's/hr.

0900 Holding power at 30% (195 MW's) for Chemistry.

1245 Commenced a power increase at 3%/ hour.

01-29-85 1700 Unit at 100% power (820 MW's) 01-31-85 2400 This reporting period ends with the unit at 100% power (820 MW's).

4 O

a

. +

SUMMARY

OF OPERATING EXPERIENCE MONTH / YEAR January,1985 Listed below in chronological sequence by unit is a summary of operating experiences for this month which required load reductions or resulted in significan non-load related incidents.

UNIT TWO 01-01-85 0000 This reporting period begins with the unit at 53% power (420 MW's),

holding while starting up Unit #1.

0407 Commenced power increase at 150 MW/hr.

0920 Unit at 100% power (790 MW's).

01-02-85 1730 Commenced power decrease. Isolated phase duct bus not properly grounded and overheating.

1814 Holding at 93% power (750 MW's) 01-03-85 0700 Unit at 100% power (785 MW's) 01-22-85 0723 Commenced rapid power reduction, losing intake canal level due to icing at the low level intake.

0857 Holding power at 20% (130 MW's).

1515 Commence.d power increase at 150 MW/hr.

1854 Holding power at 50% (350 MW's) due to flux penalities.

01-22-85 2030 Commenced power increase at 150 MW/hr.

01-24-85 0158 Holding power at 92% (695 MW's) while cleaning waterboxes.

0435 Commenced power increase at 150 MW/hr.

0551 Unit at 100% power (780 MW's).

01-31-85 2400 This reporting period ends with the unit at 100% power (780 MW's).

l .

AMENDMENTS TO FACILITY LICENSE OR TECHNICAL SPECIFICATIONS MONTH / YEAR January, 1985 The Nuclear Regulatcry Commission issued, on 10-12-84, Amendment No.'s 98/97 to the Operating License for Surry Power Station, Units 1 & 2. This amendment pertains to Auxiliary Feedwater Pumps - Operable to Available.

The Nuclear Regulatory Commission issued, on 10-12-84, Amendment No.'s 99/98 to the Operating License for Surry Power Station, Units 1 & 2. This amendment pertains to Charging Pump availability.

The Nuclear Regulatory Commission issued, on 10-15-84, Amendment No.'s 100/99 to the Operating License for Surry Power Station, Units 1 & 2. This amendment pertains to various NUREG-0737, item Technical Specificatiens.

O I

l

  • =

1- - 14 f

! FACILITY CHANGES REQUIRING

! NRC APPROVAL I

.J January,1985 i

I None During This Reporting Period 1

i B

4

! l i

t

(

l 5

i i

l i

l l

i

FACILITY CHANGES THAT DID NOT REQUIRE NRC APPROVAL January,1985 UNIT DC 83-45 Motor Control Center Fuse Installation 1 This design change installed fuses in all safety-related control circuits powered by Class IE motor control center control transformers to ensure that fire damage to control cables will not cause damage to safety related equipment.

Summary of Safety Analysis The installation of a fuse in the Safety-Related Control Circuit serves to protect the operation of equipment in the event of a fire.

DC 84-11 Fire Main Extension I&2 This design change provides an underground fire main from the existing station fire main loop to service two hydrants and pro-vide four tie-ins for future sprinkler systems in the Simulator Building, Training Center, LEOF Building, and Secondary Access Control Building.

Summary of Safety Analysis The added branch piping serves to increase the capability of the existing station fire protection system to non-safety-related areas.

DC 84-20 Installation of Hotleg Temperature Indication at Remote Monitoring Panel 1 This design change provides hot leg indication from two of the three main reactor coolant loops at the Remote Monitoring Panellocated in the Unit 1 Cable Tray Room. It will reduce the limiting conditions and surveillance requirements for the Remote Monitoring Panel.

Summary of Safety Analysis The modification enhances the availability of reactor parameter indication in the event of a fire. It adds a redundant method to monitor hot leg coolant system temperature to meet the require-ments of Appendix R.

FACILITY CHANGES THAT DID NOT CHANGE NRC APPROVAL

[ continued]

UNIT DC 84-22 _A ppendix R Modifications Containment Instrumentation 1

This design change relocated cable and/or installed noncombust-ible radiant energy shields to protect one train of equipment and

, cable for the pressurizer levelindication, Reactor Coolant System pressure indication and steam generator levelindication.

Summary of Safety Analysis The modification enhances the availability of reactor parameter indication in the event of a fire.

l 6

l l

I

l l

TESTS AND EXPERIMENTS REQUIRING NRC APPROVAL January,1985 None During This Reporting Period TESTS AND EXPERIMENM THAT DID NOT REQUIRE NRC APPROVAL January,1985 None During This Reporting Period l

1

. _ m _. _ _. _. _ _

OTHER CHANGES, TESTS AND EXPERIMENTS j

January,1985 None During This Reporting Period 1

i 1

4 i

I D 1

4 I

l; -

d 4

4 i

I I

i i

- ,-~ ~ w -we-,-. --e= - ~ - - - - - .--w- r v

POW 28-06 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION CHEMISTRY REPORT i

Jannam 19 85 l

1  !

.ARY COON UNIT NO. 1 UNIT NO. 2 ANALYSIS MAXIMUM' MINIMUM AVERAGE MAXIMUM MINIMUM AVERAGE Gross Radioact., uCi/ml 1.40E+0 5.65E-2 4.90E-1 1.04E-1 4.72E-2 7.80E-2 Suspended Solids, pom 0.50 0.50 0.50 0.00 0.00 0.00 Gross Tritium, uCi/ml 9.44E-2 4.85E-2 6.09E-2 9.12'E-2 3.62E-2 5.76E-2 f

Iodinel31, geifm1 1.56E-1 6.00E-4 5.00E-2 3.40E-4 8.03E-5 1.71E-4 7

131 fy l33 0.32 0.11 0.20 0.48 0.05 0.14 Hydrogen, cc/kg 38.3 27.1 34.2 35.2 26.0 29.3 Lithium, pom (A) 2.29 1.35 1.70 0.91 0.36 0.57

, Boron-10, ppm

  • 239 153 180 63 14 29 O x y g e'n , (D.O.),pom 50.005 50.005 s 'O.005 10.005 50.005 50.005 Chloride, ppm 50.02 50.02 50.02 s 0.02 50.02 s 0.02 i

pH 0 25'C 6.45 5.88 6.25 6.99 6.47 6.62 l

  • Boron-10 = Total Boron x 0.196 1 NON-RADIOACTIVE CHEMICAL

) RELEASES, POUNDS l T.S. 4.13.A.6 (B)

Phosphate -

Boron . 1008 Sulfate - Chromate 0.0 50% NaOH -

Chlorine -

REMARKS: (A) Mded the followinc amounts of Lithite to Unit ona- 266 men nn i-1. ?40 m-mm on 1-2,

  • 250 crams on 1-5. 240 cram on 1-7. 275 men on 1-4. ?An m me nn 1-11. 19sn m-me on 1-12, 300 crans on 1-13. 475 m en on 1-14. '24 m en nn 1-??. 1977 m me nn 1-97 'qn i grams on 1-28. The followine arrunts of Lithium were added to Unit Do; 266 orans on 1-1.

175 ttrams on 1-3, 300 crams on 1-22, 325 on 1-23, 195 arams on 1-29, 193 crans on 1-25.

j Cation bed placed in service on Unit one for Litblum rrrrual on 1-2. 1-17. 1-21. and 1 (B) The level of these chemicals should creduce no adverse environmental inoact.

I DESCRIPTION OF ALL INSTANCES WHERE THERMAL DISCHARGE LIMITS WERE EXCEEDED January,1985 None During This Reporting Period 1

I e

t b

1 i

i r

,- w - - w , -- - - - , - . - - - - , -,s. ------,,--- -_,._-, . ----,---., - - ----- - - .. --,----

PGEL HANDLING UNIT # #I MONTH / YEAR January,1985 DATE NO. OF ANSI NO. NEW OR SPENT FUEL SHIPPED / RECEIVED ASSEMBLIES PER SHIPMENT INITIAL ENRICHMENT SHIPPINGCASKACTIVITYLEVELf l

NONE DURIN G THIS REPORTING PER: OD.

I i

l

]

i

FUEL HANDLING UNIT # III MONTH / YEAR January,1985 DATE NO. OF ANSI NO. NEW OR SPENT FUEL

< HIPPED / RECEIVED ASSEMBLIES PER SHIPMENT INITIAL ENRICEMENT SHIPPING CASK ACTIVITY LEVE:

01-04-85 12 257 / 36 % <2.5 MR/hr 01-04-85 12 550 / 36 % <2.5 MR/hr 01-04-85 12 554 / 36 % <2.5 MR/hr 01-04-85 12 357 / 36 % <2.5 MR/hr 01-04-85 12 553 / 36 % <2.5 MR/hr 01-04-85 12 054 / 36 % <2.5 MR/hr 01-04-85 12 451 / 36% .

<2.5 MR/hr 01-04-85 12 052 / 36 % <2.5 MR/hr 01-04-85 12 252 / 36 % <2.5 MR/hr 01-04-85 12 557 / 36 % <2.5 MR/hr 01-04-85 12 359 / 36 % <2.5 MR/hr 01-04-85 12 156 / 36 % <2.5 MR/hr 01-04-85, 12 055 / 36% <2.5 MR/hr 01-04-85 12 355 / 36% <2.5 MR/hr 01-04-85 12 155 / 36 % <2.5 MR/hr 01-04-85 12 552 / 36% <2.5 MR/hr l 01-04-85 12 255 / 36 % <2.5 MR/hr

, 01-04-85

  • 12 159 / 36 % <2.5 MR/hr 01-04-85 12 353 / 36% <2.5 MR/hr 1 01-04-85 12 258 / 36 % <2.5 MR/hr 01-04-85 12 151 / 36 % <2.5 MR/hr

, 01-04-85 12 551 / 36 % <2.5 MR/hr 01-04-85 12 158 / 36 % <2.5 MR/hr 01-04-85 12 453 / 36 % <2.5 MR/hr

PROCEDURE REVISIONS THAT CHANGED THE OPERATING MODE DESCRIBED IN THE FSAR January,1985 None During This Reporting Period j

W 9

i 9

1 i

. . DESCRIPTION OF PERIODIC TESTS WIUCH WERE NOT COMPLETED WITHTN THE TIME LIMITS SPECIFIED IN TECHNICAL SPECIFICATIONS January,1985 None During This Reporting Period O

- i f

1 i

i i

. . . MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS ,

UNIT NO. I MECHANICAL MAINTENANCE

'l 4

e i  !

I i

9 I

VNT.0 SAFETY PILATED IMING Emr1"n POWER SORTE9 BY LH3T AND DEPARTENT FROM OU01/85 TWaj C U01/95 LMIT 01 SLERY RETURED TO WO DEPT SERVICE MARK NUMER NLNBER WO TITLE HISTORY SUMMMY  ;

R03 01/0UBS 01-CC -RCP -HA 010409 REPLACE 0AUGES ON CC LINES TO REPLACED GAUGES THAT LERE MISSING OIL COOLERS R03 OUOU85 01-CV -P -19 011019 PLMP HAS ZERO FLOW REPLACE PtNP REPLACED FUF WITH SPARE R03 OUOUBS 01-IA -PP -NA 010954 IA SUPftY LIE TO SONG-102A REPAIRED AIR LIE I R03 OU0U85 01-SS -HCV -102B 010349 NOOK LP AIR LIES, TWlEADS ON HOOKED UP AIR LIE.

EACH END R03 OU0U85 01-VS -F -7A 002239 LOUVERS ME BIEING REPAIR / REP- MOVED LOLNERS BY HAND.TEY WORK NOW T ALL ASSOCIATED R03 CU0U85 02-SI -PI -200 004890 PIPING LEMIE DOWSTREAM ,

R03 OUO4/85 01-RM -RMS -159 011094 FLOW ALARN DLE TO FLOW INDICA- FOLMD ROTAETER LHICH WAS INSTALLED MISSIE BEVERAL PIECES DLE TO APPAR

. TOR STUCK IN BOTTOM OF ENT PREVIOUS WORK. REPLACED ROT 0ETE FLOW TUBE. R AND REDUCERS NIPPLES Ale PIPE COLPLINGS (P SAT R03 0UO4/8E 01-CC -P -1C 011060 INBOARD ECHMICAL SEAL RENNEIl C(1PLIE EJARD,NOTGt BAE BG.TS.RIGtED ETOR(Alf (F WAY, REEVE D PtDP COLPLIls HEF,IWWtD EARIN 0 Ne leLEING, REMOVED (LD SEAL AND REPLACED WITH EW BELLINS. CARBON R03 0UO4/85 01-CH -P -2B 011123 SEATED COLPLIE FIRBS BG.TS 3 BACKED OUT 19ENtED COLPLIFE HALF CEED LP. INSTALLED N EW COLPLIFE HALF ON ETGt l R03 01/04/85 01-FP -C -M 007243 RECHMUE RETRIOERMT COPPRESS- RECHARGED WITH FREEN OR R03 OUO4/85 01-MS -90V -102B 011330 VALVE LEAKS BY REPLACE GAMETS R03 OUO4/85 01-VS -P -1C 002216 EXCESSIVE SEAL LEAKAGE AT PLDP REPLACED PUF PACKING WITH 3625512 MANLFACTUIED EW STEM AND BUSHING (CASE RIE) PLACED IN PtPP ROTIR.

R03 CU05/05 01-VS -PP -NA 005272 INSLLATION WALKED OFF-EEDS TO INGLLATION REPAIRED AND REP'. ACED IAERE ECESSMtY RC3 0U15/85 01-RC - -126 010049 REMOVE INSULATION FROM YALVE INSLLATION P9ENED & RE7tACED AND ADJUSTMENT PIPING FOLLOWING NDE INSPECTION.

~

R03 CU14/85 01-CC -P -1C 004991 1-CC-P-1C VENT VALVE E EDS REPLACED PIPE CAP 3/t.", PIPE' CAP R03 CU14/85 01-CC -P -1D 004990 1-CC-P-1D VENT VALVE EEDS REPLACED PIPE CAP 3/4" PIP CAP R03 01/14/85 01-MS -SOV -102A 011016 VALVE LEMS BY OMALA.ED VALVE R03 01/15/85 01-BR -C -1A 002292 SUCTION LMION (N COPPRESSOR INSTALLED EW SUCTION LMI(N R03 0 U15/85 01-EPL- -99 012094 LNABLE TO OPEN FILL VALW TO REPAIRED FILL VALVE. FILLED PEE-ADD NITROGEN To PENE- TRATION TO 22 PSI 0F HITROEEN.

TRATION

-me-R03 CU15/85 01-RC -P -19 010800 Pt99 INGLLATION HAS FALLEN OP(T IN8LLATION REPLACED R03 0U15/85 01-SW - -37 011376 VALVE FCSITION INDICATOR INCOR LDS(LTED INDICATOR & REVERSED TO l

- - - ~ ~ - ~ - - ~

INCORRECT CGIRECT POSITION l l

l i .

5

  • en h

VEP3 . SAFETY RELATED ItRING REDLCED POWER SORTEL BY LNIT MD IGARTENT FROM 01/25/85 TEU 01/29/85 LMIT 01 SLRRY I

REilRNED TO WO IEPT ERVICE MARh MMER MMBER WO TITLE HISTORY

SUMMARY

R03 01/15/85 01-VS -MOD -53A 001830 REPAIR OP FIPLACE SEAL IN TE LNCulM.ED & REMOVED CLD ACTUATOR.

INSTALLED & COLFLED EW ACTUATOR.

DANGER MODULE DECOWEL & MOVED OLD ACTUATOR TO MACHIE SHOP TO PREPARE FIR SHIP-PING.

I R03 01/1?/95 01-GW - -10 001533 VALVE LEAKS BY REPLACED DIAPEAON AND 0 RIMES R03 01/17/95 01-GW -C -1A 012271 PM - ON DEMAND VIBRATION TEST

~

R03 01/25/95 01-CH -P -13 001353 INSTALL LAGGI E 0N E AT TRACED IMILLATION INSTAL 1ED DVER EAT LUBE OIL PIPING TRACED LIE R03 01/25/95 01-MS -W V -101C 007939 VALVE EEDS RE-INELLATED VALVE & ASSOCIATED PIPIMi H46 BED RE-INGLLATED. .

R03 01/25/95 01-M6 -PP -NA 006348 REWVE & REPLACE INGLLATION ON ASSESTOS PIPE COVERING RE W VED &

PIPING. REPLACED WITH AE K STOS FREE PIPE COVERING.

R03 01/25/95 01-M6 -PP -NA 007937 INGLLATION EEN REW(NEED INELATION (W ASSOCIATED PIPIM) AT

! STEAM IRIVEN AUX FEED Pt#F HA6 MEN EPAIRED & REPLACED A6 EEED.

l R03 01/28/95 C1-CV -P -19 011242 DVDHALL PLNF DVERHALLED PLfF.

6 O

9 l

l.___ _ ___.

a_

MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. 2 MECHANICAL MAINTENANCE f

l 1

l 6

i i

i

)

r

+

l e

. _ _ . . _ _ _ _ . . . . . . , _ , . . . . _ . _ _ . . _ _ _ . _ - , . _ . _ . . __ . , _ . . . _ . _ _ _ . , . . _ . , _ _ _ . - _ . . . ~ . . . _ . . . _ _ - _ , . . ._. _

~~

VEFC0 SAFETt RELATEb IGING REIOCED FGFR SORTED BY UNIT AND DEPARTIENT

. . FROM 01/12/85 Tmu 01/17/85 LMIT 02 SERY RETlJRNED TO WO DEPT SERVICE MMK NUMBER HUMBER WO TITlf HISTORY

SUMMARY

R03 01/14/85 02-EE -C -2 011417 CO.T FISSOR HAS A BLOWN HIGH REPLACED HP IEAD GA51TT PP' UU'.O "T.DE HEAD GASKET -

R03 01/17/85 02-FW -P -3B 011952 AMJST PACKING LEAK ADJUSTED PACKING R03 01/01/85 02-SI -PI -200 004290 PIPING LEANING DOWNSTREAM TIGHTENED ALL FITTIN35 ASSC;IA S WITH SI-PI-200, OP SAT.

R03 01/04/85 02-SS - -127 003106 VALVES LEAK RX COO _ ANT LEAK THRU gg VAL W STOC # TH 3/8" LHITEY p

R03 01/04/85 02-SS - -128 003107 VALVES LEAK RX C00UWT-LEAK g THRU TH 3/8" WHITNEY VA LVE STOCK p

)

e t

e O

L 5

4 O

f J

. MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO.1 ELECTRICAL MAINTENANCE l

l i

VEPCO -

  • S&~E7f REL/,TED DLRING REM FOWER SG33 BY LHIT M DEPARTENT.

FFIM 01/04/85 TEU 01/06/85 LFIT 01 SLRRY RETURED TO WO DEPT SERVICE MRK MMBER NUMBER WO TITLE HISTORY SLMtARY R04 01/04/85 01-EPH-BKR -15C3 007446 EW-P-RT-37 PROTECTIE RELAY ME00ERED.RELAYSRELAYS TESTED CHANGED FUSES (P CECKED MATERIAL USED SHAIMJT OT 30 AW DUANTY USED 4 PO GSY-09247 STOCK 0325248 R04 01/04/85 01-EPL-MCC -1H12N 006400 PERFORM TD-5 ON BREAKERS PERFORED BREAKER TEST ON TE BREAK ERS ON 1HI-2(N) TE TEST WAS NOT PERFORfED (W TE FILL 3WIE MEAKERS DLE TO VARIOUS PLANT CONDITIONS AT TE TIE TE TEST WAS DINE R04 01/04/85 01-EPL-MCC -1H12S 006479 PERFORM TP-5 ON BREAKER PERFORED BREAKER TESTIE AND OWRL DAD TESTIE ON TE BREAKERS ON MCC 1H1-2(S) DID ET PERFIRM TE TESTS ON TE Ft11(WIE BREAKERS ME TO VARIOUS PLANT CENDITIONS.

R04 01/or/85 01-EPL-NCC -1J12E 006477 PERFCRM TEP-5 ON BHEAKEP PERFIRED TEST ON MCC BREAKERS /DVER LDAD ASSEMLIES.DID ET PERF(RM TE TEST ON TE FELLOWIE BREAKERS DLE TO VARIOUS PLANT COEITIONS AND F(R j MAEGER PRIELEMS R04 01/04/95 01-EPL-MCC -1J12W 006464 PERFORM TEP-5 ON BREAKERS TEST PROCEDLRE PERFORPED (N BREAKER S ON 1J1-2W.TE TEST WAS MIT PERF(R ED ON TE FILLOWING MEAKERS DLE TO VARIOUS PUWT ColeITIONS CR ME (RER/EIRJIPENT PROBLEMS R04 01/04/85 01-MS -mV -101A 010995 VALVE LEAKS BY SEAT WEN LIMITS ERE OBSERWD INILE TE VALV CLOSED E WAS CYCLINGS NO PROBLEM WAS SEDi TE VALVE (PERATED SAT 12/26/94 R04 01/04/95 01-MS -m V -101C 010973 AIL 1JST LIMITS TORGE SWITCH REPLACED. VALVE WAS CYCLED SAT 12/26/94 R04 01/04/85 01-MS -SOV -101CA 011124 REFLACE SOU REPLACED SOLENDID VALVE  !

12-29-94 l

R04 01/04/85 01-MS -SOV -102A 01131S REMOVE INSTALL AND ADEST INSTALLED SWITCES & CYCLID VALW FOR LIGHTS, MS ALSO TIED VALVE l R04 01/04/85 01-RC -FQ -TR.A 010924 NO OUT7t'T, POER SIEPLY REPLACED FAILED POER SLPPLY PERFORt B PT 2.37A TO VERIFY SAT R04 01/04/85 01-RS -MOV -155A 009173 ELEC DISCOMECT/RECOMECT DISCOMECTED ELECT 11/9/94, RECON-ECTED 11/24/94. NOTE!MOV DRAWS DVER FLA WIRK ORDER SISMITTED TO WORK DLRING EXT GUTAGE.

R04 01/04/85 01-RS -NOV -155B 009174 ELEC DISCOMECT/RECOMECT ELECT DISCOBOECTED 11/08 RECIDDECTE

  • D 11/24/94eeeNOTEase MOV DRAWS OVER FLA WORK ORDER SUBMITTED TO IERK DLRIIS MDCT GUTAE 09991B R04 - 01/04/85 01-61 -ACC -1A 010659 REBOLT AND SECLRE SOV'S ASSOCI- FOLMD CLAPP A LITTLE LOOSE TIINTEN ATED WITH 1-S1-ACC-1A 12/16/94 .

R04 01/04/85 01-SI -ACC -1B 010660 REBOLT Ale SECLRE SOV'S ASSOCI- TI(MTEN CLAPP 12/14/94 v m 1-51'-ACC-1B R04 01/04/95 01-SI -ACC -1C 010661 T ANtFSECLRE SOV'S ASSOCI- EED 3/16 ROD FOR U BOLT THAT IS ATED WITH 1-SI-ACC-lc MISSING 2 MJTS WASERS INSTALLED HANIER 12/16/94 VOID TO E RESCEDLLED l

l R04 01/04/95 01-SW -MV - 105C 0032B2 ELECT DISCGOECT + REEDGECT DISCGOECTED LIMITS & MTR LEADS.

VALVE DEED 12-10 LUBS FtR ET!R LEADS &

BCREMB/MJTS FtR LEADS. BRIDED &

PEO(EED 11/2/94. RECG0ECTED MTR &

LIMIT SWITCH..

r VET ~.w, .SArr.n RELATEL DURIE FIDU'ED CER SORTG BY LHIT AND DEPARTMENT FROM OV12/85 T)ftU Cua7/85 LNXT 01 SLRR7 RETIRNED TO WO EPT SERVICE MARK WMBER NUMER WO TITLE HISTORY SUP9tARY ___ .

R04 01/04/85 01-SW -MOV -104B 003279 ElICT. DISCDOET + RECDGECT DISCOPDECTED MOTOR 9-29-94 NEED 12 20 LUG AND 8/32 SCREW AND MJT FOR REC 064ECT REC 0r4ECTED MOTOR 11/3/94 R04 0UO4/85 01-VS -E -4C 010575 REPAIR / REPLACE BREMER CKT BKR. REPLACED INSTALLED IN MCC 2 HI-1-51 12/14/94 RAN 1-VS-E-4C

, Aff-READINGS GOOD 12/17/94 R04 01/04/85 01-VS -SOV -101A 010593 DEFECTIVE VALVE, REPLAE. DISASSEMBLED SOV,CLEMED PARTS AND REASSEMBLED SOV 12-14-94 REPLACED SOV Af@ TESTED SAT AS PER ENGIPEDtI NG 12/2U94

~~

R04 01/1U95 01-EPC-BKR -1B 010962 BREAKER WILf ET STAY CLDIED INTA CEDOUAB PER STEPS 5.4.1

& 5.4.2 PC-DD-E/A1. REMOVED OIL COIL. DETALLED PEW LNTA & Cup 0ET-ED LEAKDE AB PER DP-C-EPL-106.

R04 0U11/95 01-FH -CR -5 008277 (PPER CGECTION BOX ON l# NIP. DISCD4ECTED FRAfE D0lN LIMIT, FRAPE LP LIMIT, Am TRAVEL LIMIT.

PLACED 499 0t5 ACROSS TERMINALS leERE LEADS IERE DIStoleECTED.

SWITDES REPAIRED & OtAIE RET /!ERV.

R04 0U11/95 01-RC -P -1B 003803 DISCODDECT ICTOR FIR SHIPENT DISCSOECTED MTOR & AUXILLARY TPC, /

RECGGECTED AUK. TEST RAN ICTGt LDCOLPLID, T)EN RLM ETGt COLPLED.

MOTOR INSTALLED IS A ICTER FROM MRTH Al944 P0tER STATI(M.

R04 01/11/95 01-RH -P -1B 011668 NO DIL IN LPPER (R L0bER SIGHT ADDED 1 GALLON TO LPPER & 1 GT TO L0bER POTS. WGtK GtDER SLBMITTED TO INVESTIGATE / REPAIR OIL LIAKS.

R04 01/11/95 01-VS -MIB -5BA 011526 ELECT DISCD4/ RECON LIPEAR DISC 0p4ECED PEB 504. EED CGGEC-TOR BODY FGt MOTOR DS. RECOISETED NB 504 FIR PEDIANICS.

R04 01/13/95 01-CC -P -1D 011011 PM - ON IEMAND PERFGtrED PMS R04 OU14/85 01-RM -RI -159 010402 FILTER FALLT SWITCH ACTUATING PIPAIRED FILER FALLT SWITCH. ALSD FOLMD SLPPLY RCLL SPGL TIDHT. GIV-ING TOO ltEH RESISTAfCE TO TAKELP.

REPLACED FILTER PAPER. Q.EAfED OUT COWENSATION IN PO(ITER.

R04 0U15/95 01-FW -FCV -1478 012092 DISCDGECT RECD 9ECT LIMIT DISColeETED LIMIT SWITDES & RECON SWITCHES FOR MECH. ECTED LIMIT SWITDES. VERIFIED LGT IN OPEN POSITION.

R04 01/15/95 01-MS -65tV -101B 012090 VLV WILL NOT CYt1.E BRIDE & PEO(ERED. ADASTED PRES-SLNIE ON SWITCH arf 6 (N LSI MOV OPERATED SATISFACTORILY.

R04 01/15/95 014tS -P -1A 010877 INSTANTANIOLELY TRIPS, DEED TO A 0 TRIPPIIE AT 1440 MPS AS (F 12/ I RUN MOTOR UNCOUPLED 20/94. ADJETED BREAKER 'A' PHASE.

FG3G IELAY BAPS IN 'A' PHAE HAD l WT LOOSE ON T. TIS (TBED itJT AND TESTED BREAKER SAT. 12/20/94.

R04 0U15/95 01-VS -fE2 -5BA 011993 ADAIST LIMIT SIITDES AS ADalSTED LIMIT SWITCH AFTUt FAN NECESSARY STARTEII. CORRECT LIGHT IISICATINI IS AT HAND.

R04 0U16/95 01-96 -EP -NA 011440 NO PRESSutE INDICATING IN POETRATION DEDO SAT ON PT. 24 PENETRATION ON 1/12/95.

R04 01/14/95 01-EP -PE -7E 011099 REPAIR / REPLACE PDETRATISI PDE11tATION LEAK RATE WAS IETER-MIED TO BE SAT BY (PS/DEDEERIlO I AND PDETRATION DECKED SAT DOIMi i PT 34 Gi 1/12/95.-

R04 01/14/95 01-96 -90V -102B 011333 ET LIMITS Ft1R PECH REP'. ACED LIMIT SWITCH (M YALVE AND ADJJSTTD LISITS. IE. -

4 - -

, i MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. 2 ELECTRICAL MAINTENANCE 9

l MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO.1 INSTRUMENT MAINTENANCE O

4

VEPCD SAFETY FS.ATED IARING R~DUCED POWER SORTED BY UNIT AND DEPARTMENT FROM 01/04/85 TWtu 01/06/85 LNIT 01 SWRY RETLDC'D TO WO  !

DEDT SERVICE MARN MJMBEF. NUMBER WD TITLE HISTORY

SUMMARY

{

T22 01/11/85 01-CH -TI -1141 011463 CECK CALIBRATION OF TI-1141 FUFORDED LOOP CECKDUT, RACK MOUNTED EGJIFtENT CK GOOC, RTD I ELEMENT RESISTANCE IS 400. SIIB-MITTED WO TC REPLACE INTERMITTENT RTD AT COLD SHJTDOWN WD4183231 T22 01/13/85 01-EFC-ROD -M/A 012095 ROD CONTRCL SYSTEM DES ET INEERTED RODS & RESET ALL CG.NTERS GIVE PROPER OVERLAP TO ZERD. CECKED RDB CONTRG. & RPI CO W TERS FOR ZERO. P M RODS AGAIN FCR START-lF. IE PROR. EMS WITH ROD SKIPPIE SEDLDCE T22 01/14/85 01-MS -PI -137A 011377 INDICATION PEGGED LOW FOLMD WIRING ON FIELD SIDE OF TER-MINAL STRIP WIRED 15tCNG, IDED TE POSITION TRANSMITTER LEAD FROM TERMINAL 1 TO TERMINAL 2.

T22 01/14/85 01-NI -CHA -N-36 011285 CDFENSATION PROBLEM PERFORED APPLICABLE SECTION F CAL

-NI-048 AE ADJJSTED CDPENSATIE

~

VG.TAE LNTIL IEICATION WAS 10".

T22 01/14/95 01-RC -E -1A 002163 EDDY CtstREN INSPECTION TO E PERFGHED E.C. INSPEITION F TUBES.

PERFORMED ON 712 TUBES T22 01/14/85 01-RC -TI -1422C 011561 PLACE DW9EL II IN A SAFE PLACED DWSEL II (PDT D/T IN A CONDITION SAFE C(NDITI(N FOR MAINTEMICE ON GAI-TR(NICS. (POSSIBLE SPIKE IN VIT AL BUS). AFTER MAINT. PERFORMAN E RETl5DED CHAN. TO TRIP POSITION.

T22 01/14/85 01-RPI-PI -N9 - 011466 IRPI ROD POSITION DEVIATI E CALIBRATED NEW SIONN. CONDENSING EDLLE AND REPLACED INSTALLED MODLLE INDICATION M(NITGt.

PT SENT TO ENGIE ERING.

T22 01/14/85 01-VG -RM -110 010250 REPLACE RED RUBBERW)SE REPLACED BYPASS AND NERMAL FLOW TUBING. FLOW NOW 8 SCFM CGIRECTED, VACLAN 15", FLOW 10 SCFM, OP SAT. ,

T22 01/15/85 01-CH -P -2C 0057S7 REMOVE, CALIBRATE: AND FUt. ACE REPLACEDGAUGC WITH CALIBRATED GAUGE WORKING SAT.

T22 01/15/85 01-MS -PC -486 010937 REPLACE C0lPARATOR OUTFtJT OF CDPFARATOR READING OM.Y 100 VAC. REPLACED COMPARATGt. DECK ED SAT. PT SENT TO EEllEERING.

T22 01/15/85 01-RM -RI -151 009860 RAD MONITOR SPIKING REPLACED READOUT MODLLE, PERF(RED CAL-053, SAT. AFTER REPLACIlE Lal RAI E Alf BOARD.

T22 01/15/85 01-RPI- -N-9 012206 IRPI N.-9 IS LMSTABLE. PERFGUED IPP-C-RPI-32 APPLICABLE SECTIONS NAD N-9 LMDER SLRVELtJWG FGt ABGJT 20 MIN.TILD SHIFT SLFStVI SGt THAT E F0lMD NOTHIlE 6510E (PS OBSERVED 13 NtS DECKS SATISFAC f * .

s

  • I, L___

2 MAINTENANCE OF SAFETY RELATED SYSTEMS DURING OUTAGE OR REDUCED POWER PERIODS UNIT NO. 2 INSTRUMENT MAINTENANCE e

0 a e February 15, 1935 Mr. Maurice R. Beebe Serial No.85-100 Office of Resource Management N0/JDH/pa U. S. Ni.-lear Regulatory Commission Docket Nos. 50-280 Washingtort, D. C. 20555 50-281 License Nos.DPR-32 DPR-37 VIRGINIA POWER SURRY POWER STATION UNIT NOS. 1 AND 2 MONTHLY OPERATING REPORT Enclosed is the Monthly Operating Report for Surry Power Station Unit Nos. I and 2 for the month of January, 1985.

Very truly yours,-

N(

W. L. Stewart

's Enclosure (3 copies) cc: Mr. R. C. DeYoung, Director (12 copies)

Office of Inspection and Enforcement Dr. J. Nelson Grace (1 copy)

Regional Administrator Region II Mr. D. J. Burke NRC Resident Inspector Surry Power Station