Monthly Operating Repts for May 1998 for Surry Power Station,Units 1 & 2.W/980610
ML18153A314
Person / Time
Site: Surry  Dominion icon.png
Issue date: 05/31/1998
From: Christian D, Mason D, Pincus J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
98-363, NUDOCS 9806190063
Download: ML18153A314 (17)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 June 10,1998 e

United States Nuclear Regulatory Commission Serial No.98-363 Attention: Document Control Desk SPS Lic/BCB RO Washington, D.C. 20555 Docket Nos. 50-280 50-281 License Nos. DPR-32 DPR-37 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 MONTHLY OPERATING REPORT The Monthly Operating Report for Surry Power Station Units 1 and 2 for the month of May 1998, is provided in the attachment.

. If you have any questions or require additional information, please contact us.

Very truly yours, D. A. Christian, Site Vice President Surry Power Station Attachment Commitments made by this letter: None cc: U.S. Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth Street, S. W.

Suite 23T85 Atlanta, Georgia 30303 Mr. R. A. Musser NRC Senior Resident Inspector Surry Power Station

  • ( 9806190063 980531 i PDR ADOCK 05000280

, R PDR

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION MONTHLY OPERATING REPORT REPORT No. 98-05 Approved: ~*JcL.10-"li?*

Site Vice President Date 1 *

-Surry Monthly Operating Report No. 98-05 Page 2 of 16 TABLE OF CONTENTS Section Page Operating Data Report - Unit No. 1 ******************************************************************:*********************************************************3 Operating Data Report - Unit No. 2 ............................................................................................................................4 Unit Shutdowns and Power Reductions - Unit No. 1 .................................................................................................. 5 Unit Shutdowns and Power Reductions - Unit No. 2 .................................................................................................. 6 Average Daily Unit Power Level - Unit No. 1 .............................................................................................................. 7 Average Daily Unit Power Level - Unit No. 2 .............................................................................................................. 8 Summary of Operating Experience - Unit Nos. 1 and 2 ............................................................................................. 9 Facility Changes That Did Not Require NRG Approval ............................................................................................ 10 Procedure or Method of Operation Changes That Did Not Require NRG Approval ................................................. 11 Tests and Experiments That Did Not Require NRG Approval. ................................................................................. 12 Chemistry Report ..................................................................................................................................................... 13 Fuel Handling - Unit Nos. 1 and 2 ............................................................................................................................ 14 Description of Periodic Test(s) Which Were Not Completed Within the Time Limits Specified in Technical Specifications ....................................................................................................................... 16

~Surry Monthly Operating Report No. 98-05

. Page 3 of 16 OPERATING DATA REPORT Docket No.: 50-280

  • Date: . 06/01/98
  • Completed By: D. K. Mason Telephone: (757) 365-2459
1. .
  • Unit Name: ............................................................ Surry Unit 1
2. Reporting Period: .................................................. May, 1998
3. Licensed Thermal Power (MWt): ......................... . 2546
4. Nameplate Rating (Gross MWe): ...... :.................. . 847.5
5. Design Electrical Rating (Net MWe): ................... . 788
6. Maximum Dependable Capacity (Gross MWe): ... . 840
7. Maximum Dependable Capacity (Net MWe): ....... . 801
  • *8. If Changes Occur in Capacity Ratings *(Items Number 3 Through 7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-To-Date Cumulative

11. Hours in Reporting Period 744.0 3623.0 223007.0

.

  • 12. Hours Reactor Was Critical 374.3 2952.6 156978.4
13. Reactor Reserve Shutdown Hours 0.0 0.0 3774.5
14. Hours Generator On-Line 361.3 2919.8 154519.3
15. Unit Reserve Shutdown Hours 0.0 0.0 3736.2
16. Gross Thermal Energy Generated (MWH) 910694.0 7390353.7. 363635369.3
17. Gross Electrical Energy Generated (MWH) 299707.0 2470739.0 119286493. 0
18. Net Electrical Energy Generated (MWH) 289639.0 2388990.0 113623211.0
19. Unit Service Factor 48.6% 80.6% 69.3%
20. Unit Availability Factor 48.6% 80.6% 71.0%

21 .. Unit Capacity Factor (Using MDC Net) 48.6% 82.3 % 65.4%

22. Unit Capacity Factor (Using DER Net) 49.4% 83.7% 64.7%
23. Unit Forced Outage Rate 51.4% 13.1% 14.7%

, 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Refueling, October 19, 1998, 35 Days 25: If Shut Down at End of Report Period, Estimated Date of Start-up:

26. Unit In Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

e ..

. .).

  • OPERATING DATA REPORT Surry Monthly Operating Report No. 98-05 Page 4 of 16 Docket No.: 50-281 Date: 06/02/98 Completed By: D. K. Mason Telephone: (757) 365-2459
1. Unit Name: ........................................................... . Surry Unit 2
2. Reporting Period: .................................................. May, 1998
3. Licensed Thermal Power (MWt): ......................... . 2546

. 4. Nameplate Rating (Gross MWe): ......................... . 847.5

5. Design Electrical Rating (Net MWe): ................... . 788
6. Maximum Dependable Capacity (Gross MWe): ... . 840

. 7. Maximum Dependable Capacity (Net MWe): ....... . 801

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-To-Date Cumulative

11. Hours in Reporting Period 744.0 3623.0 219888.0
12. Hours Reactor Was Critical 744.0 3623.0 154773.3
13. Reactor Reserve Shutdown Hours 0.0 0.0 328.1
14. Hours Generator On-Line 744.0 3623.0 152756.5
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1894101.8 9220308.5 360753875.8
17. Gross Electrical Energy Generated (MWH) 631500.0 3085960.0 118211568.0
18. Net Electrical Energy Generated (MWH) 609791.0 2985183.0 112628334.0
19. Unit Service Factor 100.0% 100.0% 69.5%

20 .. Unit Availability Factor 100.0% 100.0% 69.5%

21. Unit Capacity Factor (Using MDC Net) 102.3% 102.9% 65.5%
22. Unit Capacity Factor (Using DER Net) 104.0% 104.6% 65.0%
23. Unit Forced Outage Rate 0.0% 0.0% 11.7%
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

None

25. If Shut Down at End of Report Period, Estimated Date of Start-up:
26. Unit In Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

e .

  • UNIT SHUTDOWN AND POWER REDUCTION (EQUAL To OR GREATER THAN 20%)

Surry Monthly Operating Report

, No. 98-05 Page 5 of 16 REPORT MONTH: May, 1998 Docket No.: 50-280 Unit Name: Surry Unit 1 Date: 06/03/98 Completed by: J. R. Pincus Telephone: (757) 365-2863 (1) (2) (3) (4) (5)

. Method Duration of LER No. System Component Cause & Corrective Action Date Type Hours Reason Shutting Code Code to Prevent Recurrence Down Rx

'05/10/98 F 382.7 A 1 50/280- AB PSP Non-isolable weld leak on 009-00 "C" reactor coolant pump seal injection line.

Affected piping was replaced.

(1) (2) (3)

F: Forced REASON: METHOD:

S: Scheduled A - Equipment Failure (Explain) 1 - Manual B Maintenance or Test 2 . Manual Scram C Refueling 3 - Automatic Scram D Regulatory Restriction 4 Other (Explain)

E Operator Training & Licensing Examination F Administrative G Operational Error (Explain)

(4) (5)

Exhibit G - Instructions for Preparation of Data Entry Sheets Exhibit 1 - Same Source for Licensee Event Report (LER) File (NUREG 0161)

... ~. ,:: ,,,. *.,: ... *.

  • UNIT SHUTDOWN AND POWER REDUCTION (EQUAL To OR GREATER THAN 20%)

e Surry Monthly Operating Report No. 98-05 Page 6 of 16 REPORT MONTH: May, 1998 Docket No.: 50-281 Unit Name: Surry Unit 2 Date: 06/03/98 Completed by: J. R. Pincus Telephone: (757) 365~2863 (1) (2) (3) (4) (5)

Method Duration of LER No. System Component Cause & Corrective Action Date Type Hours Reason Shutting Code Code to Prevent Recurrence .

Down Rx None During the Reporting Period (1) (2) (3)

F: Forced REASON: METHOD:

S:

  • Scheduled A Equipment Failure (Explain) 1 Manual B - Maintenance or Test 2 - Manual Scram C Refueling 3 Automatic Scram D Regulatory Restriction 4 - other (Explain)

E Operator Training & Licensing Examination F Administrative G Operational Error (Explain)

' (4) (5) '

Exhibit G - Instructions for Preparation of Data Entry Sheets Exhibit 1 - Same Source for Licensee Event Report (LER) File (NUREG 0161)

.e e Surry Monthly Operating Report No. 98-05 Page 7 of 16 AVERAGE DAILY UNIT POWER LEVEL Docket No.: 50-280 Unit Name: Surry Unit 1 Date: 06/03/98 Completed by: Barry C. Bryant Telephone: (757) 365-2834 MONTH: May, 1998 Average Daily Power Level Average Daily Power Level Day (MWe- Net) Day (MWe - Net) 1 825 17 0 2 824 18 0 3 824 19 0 4 825 20 0 5 825 21 0 6 824 22 0 7 823 23 0 8 823 24 0 9 734 25 0 10 9 26 646 11 0 27 819 12 0 28 818 13 0 29 819 14 0 30 817 15 0 31 816 16 0 INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to the nearest whole megawatt.

  • AVERAGE DAILY UNIT POWER LEVEL e Surry Monthly Operating Report Docket No.: 50-281 No. 98-05 Page 8 of 16 Unit Name: Surry Unit 2 Date: . 06/03/98 Completed by: Barry C. Bryant Telephone: (757) 365-2837 MONTH: May, 1998 Average Daily Power Level Average Daily Power Level Day (MWe- Net) Day (MWe- Net) 1 822 17 824 2 823 18 822 3 822 19 822
4. 821 20 821 5 821 21 : 821 6 820 22 820 7 821 23 819 8 822 24 813 9 823 25 809 10 822 26 817 11 825 27 819 12 825 28 818 13 826 29
  • 801 14 826 30 805 15 825 31 811 16 . 824 INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to
  • the nearest whole megawatt.

e *

  • Surry Monthly Operating Report No. 98-05 Page 9 of 16

SUMMARY

OF OPERATING EXPERIENCE MONTHNEAR: May, 1998 The following chronological sequence by unit is a summary of operating experiences for this month which req.uired .

load reductions or resulted in significant non-load related incidents.

UNIT ONE:

05/01/98 0000 Unit operating at 100% power, 855 MWe.

05/09/98 1720 Began power reduction to reduce dose rate to facilitate an investigation of a noted increase in reactor coolant leakage.

05/09/98 2112 Stopped power reduction at 50%, 400 MWe.

05/09/98 2304 Began power reduction to place unit at Cold Shutdown as required by Technical Specification 3.1.C.4 due to a non-isolable weld leak on the "C" reactor coolant pump seal injection line.

05/10/98 0151 Generator off-line.

05/10/98 0223 Reactor manually tripped.

05/25/98 1206 Reactor critical.

05/26/98 0032 Generator on-line. Began power increase.

05/26/98 1330 Stopped power increase at 100%, 850 MWe.

05/31/98 2400 Unit operating at 100% power, 850 MWe.

I UNITTwo:

05/01/98 0000 Unit operating at 100% power, 855 MWe.

05/31/98*. 2400 Unit operating at 100% power, 845 MWe.

<~~ r

Surry Monthly Operating Report

. No. 98-05

  • Page 10 of 16 FACILITY CHANGES THAT DID NOT REQUIRE NRC APPROVAL MONTHNEAR: May, 1998
  • DCP 92-22 Design Change Package 05/07/98 Design Change Package 92-22 replaced various older model Unit 1 and Unit 2 solenoid-operated valves (SOV) with newer models. The modification did not affect the original design function or operation of the SOVs.

TM S2-98-02 Temporary Modification 05/12/98 (Safety Evaluation 98-056)

Temporary Modification S2-98-02 replaced the failed manual actuator for service water system isolation valve, 2-SW-478, with a valve handwheel.

Temporary Modification (TM) S1-98-12 installed a cap to isolate the failed capillary tubing on the discharge of the Unit 1 turbine bearing lift pump. Installation of the TM also isolated the pump discharge pressure gauge.

SE 98-060 Safety Evaluation 05/21/98 Safety Evaluation 98-060 was performed to assess the installation of a freeze seal to facilitate the replacement of Unit 1 reactor coolant system valve, 1-RC-6. The evaluation concluded that the installation of the freeze seal in accordance with Mechanical Corrective Maintenance procedure O-MCM-1918-03, "Freeze Seal of Piping," was acceptable.

TM S1-98-13 Temporary Modification 05/24/98 (Safety Evaluation 98-061)

Temporary Modification S1-98-13 installed a recorder on the acoustic monitors used to monitor the performance of the Unit 1 pressurizer safety valves;*

PROCEDURE OR METHOD OF OPERATION CHANGES

  • Surry Monthly* Operating Report
  • No. 98-05 Page 11 of 16 THAT DID Nor REQUIRE NRC APPROVAL
  • MONTHNEAR: May, 1998 FS 98-16 UFSAR Change 05/04/98 .

(Safety Evaluation 98-052)

UFSAR Section 17.2, "Operational Quality Assurance Program Topical Report," was revised to reflect the replacement of the Instruction Manual for Architect/Engineers with a General

  • Nuclear Standard which describes the interface between the company and its contractors.

FS 98-10 :uFSAR Change 05/07/98

. (Safety Evaluation 98-053)

UFSAR Section 7.2.3.2.7, "Anticipated Transient Without SCRAM (ATWS) Mitigation System Actuation Circuitry (AMSAC)," was revised to clarify the licensing basis associated with the AMSAC C-20 interlock setpoint.

1-0P-RC-011 Operating Procedure 05/11/98 (Safety Evaluation 98-054)

Operating Procedure 1-0P-RC-011, "Pressurizer Relief Tank Operations," was changed to provide instructions for the installation of a mechanical jumper that connects the Unit 1 pressurizer relief tank (PRT) vapor space sample line to the overh.ead gas system. The jumper allows the PRT to be continuously vented to the overhead system without batch releasing to the process vent.

  • GMP-011 General Maintenance Procedure 05/12/98 (Safety Evaluation 98-055)

General Maintenance Procedure GMP-011, "Installation and Removal of Stop Logs," was .

changed to provide instructions for the installation of an electrical jumper that will enable the circulating water intake level alarms to remain functional in the event that one of the intake

  • bays is stop logged.
  • e
  • Surry Monthly Operating Report No. 98-05 Page 12 of 16 TESTS AND EXPERIMENTS THAT DID NOT REQUIRE NRC APPROVAL MONTH/YEAR: May, 1998 None During the Reporting Period

4'urry Monthly Operating Report No. 98-05 Page 13 of 16 CHEMISTRY REPORT MONTH/YEAR: May, 1998 Unit No. 1 Unit No. 2 Primary Coolant Analysis Max. Min. Avg. Max. Min. Avg.

Gross Radioactivity, µCi/ml 3.93E-1 7.81 E-3 1.62E-1 1.88E-1 1.14E-1 1.45E-1 Suspended Solids, ppm 2.0  ::;;0.010 0.670 - - -

Gross Tritium, µCi/ml 1.40E-1 1.37E-1 1.39E-1 9.63E-1 9.30E-1 9.47E-1

  • 1131, µCi/ml 1.71 E-1 7.28E-4 2.54E-2 6.53E-5 3.73E-5 4.87E-5 113111133 0.27 0.12 0.20 0.11 0.06 0.08 Hydrogen, cc/kg 42.1 2.9 15.9 41.5 37.5 39.0 Lithium, ppm 2.34 0.70 1.76 2.34 2.08 2.23*

i Boron - 10, ppm* 297.1 77.6 200.9 184.8 169.5 177.8 Oxygen, (DO), ppm 6.0  ::;;0.005 0.410  ::;;0.005  ::;;0.005  ::;;0.005 Chloride, ppm 0.010 0.002 0.004 I 0.005 0.002 0.004 pH at 25 degree. Celsius 7.14 6.09 6.56 6.76 6.56 6.68

None

  • FUEL HANDLING 4ilurry Monthly Operating Report No. 98-05 Page 14 of 16 UNITS 1 & 2 MONTHNEAR: May, 1998 New Fuel Number of New or Spent Shipment or Date Stored or Assemblies Assembly ANSI Initial Fuel Shipping Cask No. Received per Shipment Number Number Enrichment Cask Activity Spent Fuel
  • Cask No.

TN 32-07 05/27/98 32 OP1 LM05Y5 3.6070 N/A OPS, LM05XF 3.6070 ORB LMOC1R 3.5947 OSB LMOESV 3.5955 1P2 LM05XG 3.6070 1P8 LM05X6 3.6070 I

  • 1R4 LMOC1W 3.5986 2C4 LMOBMK 3.3990 2E2 LMODFS 3.5973 2PO LM05X9 3.6070 2P1 LM05XB 3.6070 2P2 LM05X4 3.6070 2P4 LM05XN 3.6070 2P6 LM05XX 3.6070 3P1 LM05XP 3.6070 3P4 LM05YC 3.6070 4CO LM08N8 3.3990 4P2 LM05YT 3.6070
  • FUEL HANDLING

-urry Monthly Operating Report No. 98-05 Page 15 of 16 UNITS 1 &2 MONTHNEAR: May, 1998 New Fuel Number of New or Spent

    • Shipment or Date Stored or Assemblies Assembly ANSI Initial Fuel Shipping Cask No. Received per Shipment Number Number Enrichment Cask Activity

. Spent Fuel Cask No.

TN 32-07 (Continued) 4P3 LM05YB 3.6070 4P4 LM05YM 3.6070 4P6 LM05YL 3.6070 5E4 LMODEH 3.6048 5P2 LM05Y9 3.6070 5P3 LM05XU ' 3.6070 5P4 LM09PH 3.6070 5P5 LM05XM 3.6070 5P8 LM05YD 3.6070 5R2 LMOC2D 3.5971 5R6 LMOC1Z 3.5901.

5R9 LMOC2B 3.5885 6P5 LM09PG 3.6070 6P7 LM05YJ 3.6070

.'i:

-urry Monthly Operating Report*

No. 98-05 Page 16 of 16 DESCRIPTION OF PERIODIC TEST(S) WHICH WERE NOT COMPLETED WITHIN THE TIME LIMITS SPECIFIED IN TECHNICAL SPECIFICATIONS MONTHNEAR: May, 1998 None During the Reporting Period