ML20107M814
ML20107M814 | |
Person / Time | |
---|---|
Site: | Clinch River |
Issue date: | 11/07/1984 |
From: | Willis W TENNESSEE VALLEY AUTHORITY |
To: | Harold Denton Office of Nuclear Reactor Regulation |
References | |
CON-#484-115 CP, NUDOCS 8411140278 | |
Download: ML20107M814 (1) | |
Similar Documents at Clinch River | |
---|---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20205L1831986-03-13013 March 1986
[Table view]Comments on Proposed Rule 10CFR9.Rule Opposed Due to Opinion That Broad New Class of Secret Sessions or Meetings W/O Transcripts Will Be Created ML20151R5611986-01-30030 January 1986 Summarizes 851216 Mgt Meeting at Oak Ridge Operations Ofc to Review & Inspect Redress & Reclamation of Crbr Site.Drawings Reviewed,Discussions Held & Tour of Site Performed.Site Restoration Concluded to Be as Described in Plans & Specs ML20138Q8301985-12-0303 December 1985 Further Response to FOIA Request for Records Re Voluntary or Required Redress of Sites Where Const Was Terminated, Including Crbr & Legal Analysis.Forwards App E Documents.App D & E Documents Available in Pdr.Photographs Also Available ML20128B2801985-06-27027 June 1985 Updates DOE .Bids for Redress of Crbr Site Opened on 850604.Contract Awarded to Beaver Excavating Co,Canton, Oh,On 850613.Contractor Scheduled to Complete Site Redress on or Before 851216 ML20133C7371985-06-14014 June 1985 Further Response to FOIA Request for Documents Re Site Redress Where Plant Const Begun,Including Clinch River Facility & NRC Legal Analysis Re Redress.Forwards App B Documents.App C Document Withheld (Ref FOIA Exemption 5) ML20128R0001985-06-0606 June 1985 Partial Response to FOIA Request for Records Re Desirability of Voluntary or Required Redress of Nuclear Plant Sites Where Work Undertaken But Const No Longer Contemplated. Forwards Documents Listed in App a ML20133C6881985-05-0808 May 1985 FOIA Request for Documents Re Redress of Sites Where Nuclear Plant Const Begun & NRC Legal Analysis of Need for Site Redress W/ or W/O Current CP & LWA ML20107M8141984-11-0707 November 1984 Clarifies & Reaffirms Util Commitments Re Redress of Site in Accordance W/Util 840305 Final Site Redress Plan & NRC 840606 Approval of Plan ML20107H8031984-11-0606 November 1984 Reaffirms Commitments to Redress Site in Accordance W/ 840305 Final Site Redress Plan & NRC 840606 Approval Ltr. Related Correspondence ML20140C6121984-06-18018 June 1984 Advises That Time for Commission to Review ALAB-761 Expired. Commission Declined Review.Decision Became Final Agency Action on 840611.Served on 840618 ML20087B4361984-03-0808 March 1984 Confirms That ASLB Intends to Vacate Notice of 840314 Conference & Reschedule Later Date Due to Delay in Funding for Review of Redress Plan & Possible Lack of Availability of One ASLB Member.Certificate of Svc Encl ML20086T4631984-03-0505 March 1984 Forwards Site Redress Plan. Minor Clarifications & Corrections to Draft Plan Submitted 840227 Made in Response to NRC Comments ML20087A4141984-03-0202 March 1984 Forwards Page 15 Inadvertently Omitted from 840227 Transmittal of Draft Crbr Plant Redress Plan.Related Correspondence ML20080T9331984-03-0101 March 1984 Forwards Page 15 of Crbr Program Redress Plan,Inadvertently Omitted from 840227 Transmittal.Certificate of Svc Encl ML20128R0161984-02-29029 February 1984 Expresses Thanks for 840222 Review of Site Redress Planning. Concurs W/Conceptual Approach & 1-yr Period for Development of Final Site Redress Plan & Investigation of Potential Use of Site.Ml Lacy Encl ML20080S6661984-02-27027 February 1984 Forwards Draft Site Redress Plan,In Response to N Grace 831208 Request.Plan Will Be Finalized for Submission on 840302,following Receipt of Comments ML20079F9411984-01-13013 January 1984 Informs of Receipt & Storage,Through S&W Engineering,Of Spent Fuel Transfer Port Assembly Large Shield Plug.Due to Failure of Congress to Appropriate Addl Funding,Doe No Longer Seeking CP & Is Closing All Licensing Activities ML20083G3551984-01-10010 January 1984 Advises That Svc of DOE & Project Mgt Corp 831227 Notification Re Project Termination Affected Again on All Parties on Attached Svc List ML20083H2331983-11-15015 November 1983 Summarizes Current Status of SER Open Items Re Structural Response During Faulted Conditions & Beyond Dbas.Program Lacks Planned Analytical Support.Models to Support Experimental Efforts Should Be Developed ML20081B9721983-10-24024 October 1983 Summarizes 831004 Meeting W/Nrc,Acrs & Lnr Assoc Re Mgt of Crbr PRA Program.Viewgraphs & List of Meeting Attendees Encl ML20078A7571983-09-0707 September 1983 Forwards Evaluation Repts of Faults 1,2 & 3 Discovered on Site During Foundation Excavation.Faults Not Capable within Meaning of App a to 10CFR100.W/seven Photographs ML20076A8171983-08-17017 August 1983 Confirms Redirection for Shipping Applicant Voluminous Exhibits.Certificate of Svc Encl ML20076A7761983-08-17017 August 1983 Advises That Author Will Present Oral Argument on Behalf of Applicants & Forwards Motion Requesting Argument Be Rescheduled for 830928 ML20077J0781983-08-11011 August 1983 Forwards Pages from Transcript of Crbr CP 830810 Hearings Per ASLB Direction.Certificate of Svc Encl ML20081A5601983-08-11011 August 1983 Summarizes 830808 Informal Meeting on Contract Re PRA Review of Crbr (Task 4) & NRC Concerns Associated W/Technology for Energy Corp Deliverables Schedule ML20076H8811983-08-0909 August 1983 Expresses Appreciation for NRC Presentation on 10CFR21 & 10CFR50.55(e) Requirements.Info Should Be Most Useful to Personnel Involved in Project in Following Requirements ML20024E0391983-08-0505 August 1983 Forwards Errata Sheets for Applicant Prepared Testimony. Certificate of Svc Encl.Related Correspondence ML20077D1321983-07-25025 July 1983 Advises of Omission in Applicant 830722 Response Re CP Evidentiary Hearings.Hearings Did Not Commence on 830718 But Were Postponed Per 830713 Order.Order of 830719 Rescheduled Hearings for 830808-12.Certificate of Svc Encl ML20024D0291983-07-22022 July 1983 Forwards Clinch River Breeder Reactor Plant Sys Design Description - Nuclear Island HVAC Sys, as Example of Procedure Outlines Available for Performance of PRA ML20080A8311983-07-20020 July 1983 Opposes Plant Const Since Little Prior Experience Exists W/Breeder Reactor Design ML20024D5121983-07-19019 July 1983 Requests Specs for Electrical Power Cable Insulation to Be Used at Facility ML20077A5331983-07-19019 July 1983 Advises of Incorrectly Cited Ref on Page 1 of Attachment B & on Page 2 of Attachment C to .Certificate of Svc Encl ML20077H1911983-07-19019 July 1983 Responds to NRC Re Violations Noted in IE Insp Rept 50-537/83-05.Corrective actions:Westinghouse-Oak Ridge Audit Program Revised to Be Computerized Sys.Implementation Throughout Yr Will Be Measured by Planned Surveillances ML20072P1101983-07-15015 July 1983 Forwards Applicant Proposed Exhibit List for CP Hearings,For Review.Stipulation as to Authenticity & Admissibility Requested.Certificate of Svc Encl ML20024C1621983-07-0808 July 1983 Informs That Auxiliary Feedwater Sys Evaluation,Per PSAR App C,Section C.6.4 & App H,Section II.E.1.1,scheduled for Completion by mid-1985 ML20085A7291983-07-0606 July 1983 Forwards Rev 6 to Vol 2 to CRBRP-3, Assessment of Thermal Margin Beyond Design Base (Tmbdb) ML20105B9551983-07-0606 July 1983 Forwards Addl Info Per Request at 830610 Meeting on Programmatic Objectives Re Fuel Burnup.Fftf Operates W/Peak Burnup of Over 61,000 Megawatt Day/Mt.Burnup Occurred Under Temp & Power Conditions Similar to Crbr Conditions ML20079R7401983-06-23023 June 1983 Summarizes 830606 Meeting W/Crbr Project Personnel Re Schedule for Resolution of Confirmatory Items.All Identified Items & Preliminary Schedule Info Discussed.List of Attendees Encl ML20079R2661983-06-21021 June 1983 Lists Typographical & Transcription Errors in 830512 Deposition.Certificate of Svc Encl ML20024A6781983-06-20020 June 1983 Informs of Planned Optional Use of Mechanical Couplers for Reinforcing Bar Splice Sys in Nuclear Island Mat.Qa Program Will Be Established.Exception to ASME Code,Section III & Reg Guide 1.136 Requirements Encl ML20076J0951983-06-17017 June 1983 Summarizes Programmatic Objectives 830610 Meeting Re Fallbacks Identified in Chapter 4 of SER & Impact on Crbr Project.Viewgraphs & Supporting Documentation Encl ML20076J0511983-06-16016 June 1983 Advises That DOE Addressees Include Tj Garrish,L Silverstrom & Wd Luck.Rt Johnson & WE Bergholz Should Be Deleted from Svc List.Certificate of Svc Encl ML20023D9611983-05-27027 May 1983 Submits Agreements Reached at 830524 Meeting W/Crbr Project Re Pra.Description of Addl Tasks Needed to Integrate Plan I & II Efforts Encl ML20072B3431983-05-27027 May 1983 Forwards Crbr Erosion & Sediment Control Plan Rept, Providing Implementation Status of Control Plan Measures Currently Utilized ML20023D4031983-05-20020 May 1983 Forwards Amend 77 to PSAR ML20076D3151983-05-19019 May 1983 Forwards Rev 1 to Crbr Project Heat Transport Sys In-Containment Piping Reserve Seismic Margins & Rept Re Consequences of Leaks from Small Diameter Primary Heat Transport Sys Piping ML20076D2281983-05-17017 May 1983 Forwards Rev 5 to Vol 2 to Thermal Margin Beyond Design Base. Rev Incorporates Isotopic Inventory for Heterogeneous Core,Current Meteorology,Addl Organ Doses & More Realistic Pu Sparging Calculations ML20023C5821983-05-16016 May 1983 Submits Supplemental Info to 830401 Ltr Re Cable Separation by Confirming That Approx 75 Ft of DHR Svc & Steam Generator Auxiliary Heat Removal Sys Cable Will Be Run in Separate Conduits or Encl Raceways ML20079Q2881983-05-10010 May 1983 Forwards Corrected 830509 Response to NRDC & Sierra Club First Set of Interrogatories & Request to Produce Directed to Applicant.Original Document Not Identified as Response ML20024D9551983-05-0909 May 1983 Submits Estimate of LMFBR Safety & Licensing Review Needs Over Next Several Yrs.Preparation of Portions of FSAR Will Begin in 1984 1986-03-13 Category:INCOMING CORRESPONDENCE MONTHYEARML20205L1831986-03-13013 March 1986
[Table view]Comments on Proposed Rule 10CFR9.Rule Opposed Due to Opinion That Broad New Class of Secret Sessions or Meetings W/O Transcripts Will Be Created ML20128B2801985-06-27027 June 1985 Updates DOE .Bids for Redress of Crbr Site Opened on 850604.Contract Awarded to Beaver Excavating Co,Canton, Oh,On 850613.Contractor Scheduled to Complete Site Redress on or Before 851216 ML20133C6881985-05-0808 May 1985 FOIA Request for Documents Re Redress of Sites Where Nuclear Plant Const Begun & NRC Legal Analysis of Need for Site Redress W/ or W/O Current CP & LWA ML20107M8141984-11-0707 November 1984 Clarifies & Reaffirms Util Commitments Re Redress of Site in Accordance W/Util 840305 Final Site Redress Plan & NRC 840606 Approval of Plan ML20107H8031984-11-0606 November 1984 Reaffirms Commitments to Redress Site in Accordance W/ 840305 Final Site Redress Plan & NRC 840606 Approval Ltr. Related Correspondence ML20087B4361984-03-0808 March 1984 Confirms That ASLB Intends to Vacate Notice of 840314 Conference & Reschedule Later Date Due to Delay in Funding for Review of Redress Plan & Possible Lack of Availability of One ASLB Member.Certificate of Svc Encl ML20086T4631984-03-0505 March 1984 Forwards Site Redress Plan. Minor Clarifications & Corrections to Draft Plan Submitted 840227 Made in Response to NRC Comments ML20087A4141984-03-0202 March 1984 Forwards Page 15 Inadvertently Omitted from 840227 Transmittal of Draft Crbr Plant Redress Plan.Related Correspondence ML20080T9331984-03-0101 March 1984 Forwards Page 15 of Crbr Program Redress Plan,Inadvertently Omitted from 840227 Transmittal.Certificate of Svc Encl ML20080S6661984-02-27027 February 1984 Forwards Draft Site Redress Plan,In Response to N Grace 831208 Request.Plan Will Be Finalized for Submission on 840302,following Receipt of Comments ML20079F9411984-01-13013 January 1984 Informs of Receipt & Storage,Through S&W Engineering,Of Spent Fuel Transfer Port Assembly Large Shield Plug.Due to Failure of Congress to Appropriate Addl Funding,Doe No Longer Seeking CP & Is Closing All Licensing Activities ML20083G3551984-01-10010 January 1984 Advises That Svc of DOE & Project Mgt Corp 831227 Notification Re Project Termination Affected Again on All Parties on Attached Svc List ML20083H2331983-11-15015 November 1983 Summarizes Current Status of SER Open Items Re Structural Response During Faulted Conditions & Beyond Dbas.Program Lacks Planned Analytical Support.Models to Support Experimental Efforts Should Be Developed ML20081B9721983-10-24024 October 1983 Summarizes 831004 Meeting W/Nrc,Acrs & Lnr Assoc Re Mgt of Crbr PRA Program.Viewgraphs & List of Meeting Attendees Encl ML20078A7571983-09-0707 September 1983 Forwards Evaluation Repts of Faults 1,2 & 3 Discovered on Site During Foundation Excavation.Faults Not Capable within Meaning of App a to 10CFR100.W/seven Photographs ML20076A8171983-08-17017 August 1983 Confirms Redirection for Shipping Applicant Voluminous Exhibits.Certificate of Svc Encl ML20076A7761983-08-17017 August 1983 Advises That Author Will Present Oral Argument on Behalf of Applicants & Forwards Motion Requesting Argument Be Rescheduled for 830928 ML20081A5601983-08-11011 August 1983 Summarizes 830808 Informal Meeting on Contract Re PRA Review of Crbr (Task 4) & NRC Concerns Associated W/Technology for Energy Corp Deliverables Schedule ML20077J0781983-08-11011 August 1983 Forwards Pages from Transcript of Crbr CP 830810 Hearings Per ASLB Direction.Certificate of Svc Encl ML20076H8811983-08-0909 August 1983 Expresses Appreciation for NRC Presentation on 10CFR21 & 10CFR50.55(e) Requirements.Info Should Be Most Useful to Personnel Involved in Project in Following Requirements ML20024E0391983-08-0505 August 1983 Forwards Errata Sheets for Applicant Prepared Testimony. Certificate of Svc Encl.Related Correspondence ML20077D1321983-07-25025 July 1983 Advises of Omission in Applicant 830722 Response Re CP Evidentiary Hearings.Hearings Did Not Commence on 830718 But Were Postponed Per 830713 Order.Order of 830719 Rescheduled Hearings for 830808-12.Certificate of Svc Encl ML20024D0291983-07-22022 July 1983 Forwards Clinch River Breeder Reactor Plant Sys Design Description - Nuclear Island HVAC Sys, as Example of Procedure Outlines Available for Performance of PRA ML20080A8311983-07-20020 July 1983 Opposes Plant Const Since Little Prior Experience Exists W/Breeder Reactor Design ML20024D5121983-07-19019 July 1983 Requests Specs for Electrical Power Cable Insulation to Be Used at Facility ML20077H1911983-07-19019 July 1983 Responds to NRC Re Violations Noted in IE Insp Rept 50-537/83-05.Corrective actions:Westinghouse-Oak Ridge Audit Program Revised to Be Computerized Sys.Implementation Throughout Yr Will Be Measured by Planned Surveillances ML20077A5331983-07-19019 July 1983 Advises of Incorrectly Cited Ref on Page 1 of Attachment B & on Page 2 of Attachment C to .Certificate of Svc Encl ML20072P1101983-07-15015 July 1983 Forwards Applicant Proposed Exhibit List for CP Hearings,For Review.Stipulation as to Authenticity & Admissibility Requested.Certificate of Svc Encl ML20024C1621983-07-0808 July 1983 Informs That Auxiliary Feedwater Sys Evaluation,Per PSAR App C,Section C.6.4 & App H,Section II.E.1.1,scheduled for Completion by mid-1985 ML20085A7291983-07-0606 July 1983 Forwards Rev 6 to Vol 2 to CRBRP-3, Assessment of Thermal Margin Beyond Design Base (Tmbdb) ML20105B9551983-07-0606 July 1983 Forwards Addl Info Per Request at 830610 Meeting on Programmatic Objectives Re Fuel Burnup.Fftf Operates W/Peak Burnup of Over 61,000 Megawatt Day/Mt.Burnup Occurred Under Temp & Power Conditions Similar to Crbr Conditions ML20079R7401983-06-23023 June 1983 Summarizes 830606 Meeting W/Crbr Project Personnel Re Schedule for Resolution of Confirmatory Items.All Identified Items & Preliminary Schedule Info Discussed.List of Attendees Encl ML20079R2661983-06-21021 June 1983 Lists Typographical & Transcription Errors in 830512 Deposition.Certificate of Svc Encl ML20024A6781983-06-20020 June 1983 Informs of Planned Optional Use of Mechanical Couplers for Reinforcing Bar Splice Sys in Nuclear Island Mat.Qa Program Will Be Established.Exception to ASME Code,Section III & Reg Guide 1.136 Requirements Encl ML20076J0951983-06-17017 June 1983 Summarizes Programmatic Objectives 830610 Meeting Re Fallbacks Identified in Chapter 4 of SER & Impact on Crbr Project.Viewgraphs & Supporting Documentation Encl ML20076J0511983-06-16016 June 1983 Advises That DOE Addressees Include Tj Garrish,L Silverstrom & Wd Luck.Rt Johnson & WE Bergholz Should Be Deleted from Svc List.Certificate of Svc Encl ML20023D9611983-05-27027 May 1983 Submits Agreements Reached at 830524 Meeting W/Crbr Project Re Pra.Description of Addl Tasks Needed to Integrate Plan I & II Efforts Encl ML20072B3431983-05-27027 May 1983 Forwards Crbr Erosion & Sediment Control Plan Rept, Providing Implementation Status of Control Plan Measures Currently Utilized ML20023D4031983-05-20020 May 1983 Forwards Amend 77 to PSAR ML20076D3151983-05-19019 May 1983 Forwards Rev 1 to Crbr Project Heat Transport Sys In-Containment Piping Reserve Seismic Margins & Rept Re Consequences of Leaks from Small Diameter Primary Heat Transport Sys Piping ML20076D2281983-05-17017 May 1983 Forwards Rev 5 to Vol 2 to Thermal Margin Beyond Design Base. Rev Incorporates Isotopic Inventory for Heterogeneous Core,Current Meteorology,Addl Organ Doses & More Realistic Pu Sparging Calculations ML20023C5821983-05-16016 May 1983 Submits Supplemental Info to 830401 Ltr Re Cable Separation by Confirming That Approx 75 Ft of DHR Svc & Steam Generator Auxiliary Heat Removal Sys Cable Will Be Run in Separate Conduits or Encl Raceways ML20079Q2881983-05-10010 May 1983 Forwards Corrected 830509 Response to NRDC & Sierra Club First Set of Interrogatories & Request to Produce Directed to Applicant.Original Document Not Identified as Response ML20024D9551983-05-0909 May 1983 Submits Estimate of LMFBR Safety & Licensing Review Needs Over Next Several Yrs.Preparation of Portions of FSAR Will Begin in 1984 ML20073S2761983-05-0505 May 1983 Forwards Revised Responses to SER Item 6 Re Qa,Including Info to Complete Identification of safety-related Structures,Sys & Components Controlled by Crbr QA Program for PSAR.Marked-up Tech Specs Encl ML20073Q3491983-04-28028 April 1983 Forwards Revised Response to SER Item 6, Qa. Response Provides Addl Info Re Identification of safety-related Structures,Sys & Components Controlled by QA Program ML20073R2221983-04-27027 April 1983 Requests to Make Limited Appearance Statement at 830718 CP Hearings Re Regional Socioeconomic Impacts ML20069L1801983-04-27027 April 1983 Informs That Evaluation of Seismic Adequacy of Primary Heat Transport Sys Branch Line & Consequences of Line Failure Being Conducted,In Response to ACRS 830419 Request.Results Will Be Forwarded by 830517 ML20073K3441983-04-18018 April 1983 Forwards Static Tests of 1/20-Scale Models of Crbr Head in Support on LMFBR Safety Program ML20071G2761983-04-18018 April 1983 Recommends That Commission Retain Technical Cadre of Experts to Review Crbr & Overall DOE Breeder Program 1986-03-13 Category:UTILITY TO NRC MONTHYEARML20107M8141984-11-0707 November 1984
[Table view]Clarifies & Reaffirms Util Commitments Re Redress of Site in Accordance W/Util 840305 Final Site Redress Plan & NRC 840606 Approval of Plan ML20062G2711982-08-0909 August 1982 Package of Three Comments Supporting Crbr ML20062G2371982-08-0606 August 1982 Package of Two Comments Supporting Proposed Accelerated Site Preparation for Crbr ML20062C9231982-07-29029 July 1982 Comments on DOE Request to Accelerate Site Preparation for Crbr.Supports Request ML20062B1851982-07-29029 July 1982 Package of Two Comments Supporting Accelerated Site Preparation for Crbr ML20062B2801982-07-28028 July 1982 Package of Nine Comments Supporting Accelerated Site Preparation for Crbr ML20062C7521982-07-27027 July 1982 Comments on DOE Request to Accelerate Site Preparation for Crbr.Supports Request ML20062B0001982-07-27027 July 1982 Comments on DOE Request to Accelerate Site Preparation for Crbr.Supports Request ML20071L1781982-07-22022 July 1982 Package of 44 Comments Supporting Request by DOE to Accelerate Site Preparation for Crbr ML20050C2971982-04-0505 April 1982 Suppls 820329 Ltr Re Potential Onsite Generated Solid Waste. Approx 17,000 Lb Will Be Generated During Peak Const.Impact on Area Landfills Cannot Be Assessed,Pending Selection of Disposal Location ML20039E9711981-12-15015 December 1981 Forwards Three NRC Std Format Magnetic Data Tapes for Site & List of Parameters & Sample Dump for Each Tape,Corresponding to Three Distinct 1-yr Sets of Meteorological Data from Temporary & 110-meter Permanent Towers ML20054L6171981-12-10010 December 1981 Confirms 811209 Telcon Re Updated Commercial Fish Survey Data for Watts Bar Reservoir,In Response to NRC Question on Crbr EIS 1984-11-07 |
Text
p TENN:ssE3 VALLEY AUTHORITY KNOXVlLLE, TENNESSEE 37eOs NOV 7 1984 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Comunission Washington, D.C. 20555 Re: Docket No. 50-537CP
Dear Mr. Denton:
This is to clarlfy and reaffirm TVA's cosualtments in regard to redress of the Clinch River Breeder Reactor Project site. Appilcants, including, as Comppilcant, TVA, have committed to redress of the site in accordance with the final site redress plan submitted by letter dated March 5, 1984 (Attachment A to Applicants' Notion to Dismiss Proceeding dated October 19, 1984) and the Staff's letter approving that plan dated June 6, 1984 (Attachment E to Appilcants' October 19 Motion). In the event of any inconsistency between Exhibit 8 to Attachment F of Applicants' October 19 Motion (Supplemental Agreement between TVA and DOE dated August 31, 1984) and Attachments A and E thereto, we confirm our commitment that Attachments A and E will be controlling over Attachment P and govern site redress.
Sincerely, W. F. Willis A
General Manager cc: Service List p
ht e rl , ton 1 0 D 0 0 37 A PDR An Equal Opportunity Employer