ML20087J809

From kanterella
Jump to navigation Jump to search
Final Deficiency Rept DER 83-72 Re Undersize Welds in Auxiliary Bldg.Initially Reported on 831026.Condition Determined Not Reportable Per 10CFR50.55(e)
ML20087J809
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 03/14/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-29061-BSK, DER-83-72, NUDOCS 8403230099
Download: ML20087J809 (6)


Text

_

1 Arizona Public Senice Company P o. BOX 21606 . PHOENIX. ARIZONA 85036 March 14, 1984 ANPP-29061-BSK/TRB _

Iik'

  • -p- si D

W.

U. S. Nuclear Regulatory Commission $' __ ,j Region V i O ],, [Q -

Creekside Oaks Office Park '

3

1450 Maria Lane - Suite 210 -

Walnut Craek, CA 94596-5368

'7; Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs 4

Subject:

Final Report - DER 83-72 A 50.55(e) Reportable Condition Relating to Undersize Welds in Unit 1 Auxiliary Building Discovered During NRC CAT Inspections File: 84-019-026; D.4.33.2

Reference:

A) Telephone Conversation between P. Narbut and R. Tucker on October 26, 1983 B) ANPP-28287, dated November 28, 1983 (Interim Report)

C) ANPP-28662, dated January 23, 1984 (Time Extension)

D) ANPP-28936, dated February 24, 1984 (Time Extension)

Dear Sir:

Attached is our final written report of the deficiency referenced above, which has been determined to be Not Reportable under the requirements of 10CFR50.55(e).

I Very truly you ,

L -

CALL 'n c.LL_

E. E. Van Brunt, Jr.

APS Vice President, Nuclear ANPP Project Director EEVB/TRB:db Attachment ,

cc: See Page Two 8403230099 840314 ' /G~- L T '

PDR ADOCK 05000528 I-S pm k i

F

" _ . - - - _j

Mr. T. W. Bishop -

DER 83-72 Page Two ec: Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

W. E. Ide D. B. Fasnacht A. C. Rogers B. S. Kaplan L. A. Souza J. Vorees J. R. Bynum P. P. Klute .

A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson .

L. E. Vorderbrueggen C. A. Fiore11i S. R. Frost J. Self D. Canady Records Center Institute of Nuclear Power Operations .

1100 circle 75 Parkway, Suite 1500 Atlanta, CA 30339

FINAL REPORT - DER 83-72 DEFICIENCY EVALUATION 50.55(e)

ARIZONA PUBLIC SERVICE COMPANY (APS)

PVNCS UNITS 1, 2, & 3 1

I. Description of Deficiency Specification 13-CM-320, Rev. 8 Paragraph 9.2, states: "All welds shall be visually inspected, to verify, at least, the following:

i (a) Welds are correct size, length, and location. (b) No specified I weld has been omitted. -(c) No unspecified weld has been added without approval, except as otherwise covered in this specification. (d) Cracks in weld or. base metal or other i discontinuities do not exist."

As the result of NRC CAT Audit 50/528 and a review of-NCR CA-4320, a follow-up reinspection of 144 structural welds for steel framing on Unit 1 Auxiliary Building at elevation 51'-6" '

! was performed. The inspection revealed that 18 undersize welds as documented on NCR CA-4366, did not meet the requirements of drawing 13-C-ZAC-500, Rev. 10, but were previously accepted by-

Quality Control.

1 As the result of NCR CA-4366, an additional inspection of 204 structural welds.at various elevations'of Unit 1. Auxiliary Building was conducted; This inspection program revealed 2 more undersize welds and 20 oversize welds, as documented on NCR CA-4415. The nonconf arming welds were also previously accepted:,

i by Quality, Control.'

Bechtel Engineering has reviewed the undersize-welds based on .

~

calculation analysis;(13-CC-ZA-0!m-),. to ensure the non-conforming welds would not constitute a degradation of the structural integrity.of the steel framing:in the area;where the welds appear. The requirement for 5/16" fillet _ welds 1on design drawing 13-C-ZAS-500 is .not a ' structural or strength requirement, but rather the minimum size fillet recommended' by AISC,'8th Edition, Section 1.17.2.

Bechtel: Engineering' hss reviewed the findings of oversize welds .

and requested a reinspection to check'for weld. cracking ~,-

conditions of 'the base material, and any~ unusual ; joint:

distortion. The evalu'ation of this reinspection is. contained in:

PartfII of this report.

4-J' L

.5 ' y

, .OD

,i  ?? "

1 ANPP-29061 Page Two II, Analysis of Safety Implications Reinspection of 348 additional structural welds was completed on November 7, 1983 and the evaluation of observed conditions is as follows:

Twenty of the total 348 welds or approximately 6 percent were found to be oversized. This condition is not safety significant. Oversize welds are of concern when they could result in lamellar tearing of the base metal. Particular concern is given to lamellar tearing when base materials greater than 1 inch in thickness are overwelded. The major purpose of limiting oversized welds on material less than 1 inch thick comes from economical and distortion considerations. The oversized welds identified here have been visually examined for excessive distortion and any indication of lamellar tearing. No cracking or unusual distortion was observed.

Out of the 348 welds inspected, a total of twenty or approximately 6 percent were found to be undersized, eighteen welds were between 1/31" and 1/16" undersised while two were 1/8" undersized. The design margin used for this type of connection is generally about 30 percent. Only a few connections are designed up to the allowable loads.

All design loads for the reinspected weld conditions were approximately 80 percent of the allowable loads. As is expected for the majority of the cases, where design loads apprcximate allowable loads, margin still exists (e.g., approximately 15 percent which can be demonstrated by testing or dynamic analysis).

A review of the undersize structural steel welds identified by NCRs CA-4320, 4366, and 4415, comprising all the undersize welds identified by the NRC inspection plus those found by the Bechtel reinspection program, have been evaluated for safety significance.

The review by Bechtel Engineering found that all identified weld sizing defects could be dispositioned "Use-As-Is" since, if left uncorrected, none of the defects would represent a safety significant condition; therefore, this conditien is evaluated as not reportable.

Combining the very conservative design loading requirements, the conservative AISC minimum weld requirements, and results of the reinspections which resulted in all weld defects being dispositiored "Use-As-Is", Bechtel Engineering concludes that the structural end miscellaneoun steel welding already completed in Units 1, 2, and 3 is adequate. Based on this evaluation, no additional reinspection of structural steel welds in Units 2 and 3 is warranted.

4

ANPP-29061 Page Three III. Corrective Action A. To more clearly define the structural and av elleneous steel welding and inspection requirements, the fcilowing actions have been taken:

1. Specification 13-CM-320 has been revised for clarification and ease of intsrpretation by Field Change Request (FCR) 71,023-C and 72,146 -C. Specification Change Notice 3568 has been issued. The changes specifically address undersize, oversize welds and undercut requirements, and inspection accept / reject criteria.
2. A revision to the Project Quality Program Manual, Procedure 18.6 - Project Quality Assurance Surveillance has been completed, This revision requires a QA review of structural steel welded connections accepted by QC, based on selective samplings.
3. The FSt.F will be revised by SAR Change Notice 1123, which will incorpocate the specific welding requirements currently contained in Specification 13-CM-320. The excepcions taken to AWS Dl.1-72, Revision 1, 1973 and the justification for the exceptions will be incorporated into the FSAR. This change clarifies the licensing document to incorporate the flexibility permitted by the Code. The change also provides consistency between the implemented practice reflected in the construction specification, as allowed by the Code, and the licensing document.
4. Training Sessions for QC Welding Inspectors were held on October and December 1983 to provide instructions on revised clarifications to Specification 13-CM-320.

Training Sessions were also given on the use of fille.t weld gauges.

5. Based on acceptable disposition of Unit 1 NCRs CA-4320, 4366 and 4415 as "USE-AS-IS", no reinspection of Unit 2 and 3 structural welds is anticipated.

s B. A preliminary review of the following construction specifications has been completed. No conflicts with the SAR have been identified.

Specification No. Deceription 13-CM-307 Design Installation, and Testing of Concrete Anchors i

13-CM-308 Installation and Testing of Concrete l Embeds and Insert Plates l

,s .

ANPP-29061 Page Four 13-CM-340 Field Erection of SS Liner Plate 13-CM-365 Forming, Placing, Finishing, and Curing Concrete 13-CM-170 Containment Building Liner Plate System

\

13-CM-375 Placing of Reinforcing Steel 13-CM-378 Installation Specification for Drilling Concrete Structure 13-CM-380 Construction Specification for the Containment Units 1, 2, and 3 13-EM-301 Installation Specification for Electrical Cables I Conduit and Duct Bank 13-EM-302 Installation Specification for Cable Tray Hangers 13-EM-304 Installation Specification for Seismic Category 1 Conduit Supports 13-EM-306 Installation Specification for Cable Splicing Termination and Supports 13-JM-702 Installation Specification for Quality Class Q, R, S, Equipment 13-PM-204 Field Fabrication and Installation of Nuclear Piping System The final, detailed review will be completed by May 1,1984 and the results will be documented by letter from Bechtel Power Corporation to Arizona Public Service Co. Any potentially reportable conditions found as a result of this review will be documented by issuance of new Deficiency Evaluation Reports, as applicable.

-