ML20012D976

From kanterella
Jump to navigation Jump to search
Responds to Insp Repts 50-324/88-36 & 50-325/88-36 Re Util Response to IE Bulletin 79-02.Verification That Pipe Support Base Plate Flexibility Accounted for in Calculation of Anchor Bolt Loads Addressed
ML20012D976
Person / Time
Site: Brunswick  Duke energy icon.png
Issue date: 03/22/1990
From: Harness J
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
BSEP-90-0244, BSEP-90-244, IEB-79-02, IEB-79-2, NUDOCS 9003290176
Download: ML20012D976 (6)


Text

, .,

3--

g i v# .

e..;

4 Carolina Power & Ught Company

(

  • 1 Brunswick Nuclear Project p

P. O. Box 10429 .

Southport, NC 28461-0429 March 22, 1990 PILE: B09-135100:

r. SERIAL: BSEP/90-0244 U U.S. Nuclear Regulatory Commission ATTN: Document Control Desk ,

Washington.-DC 20555 y-ji BRUNSWICK STEAM ELECTRIC PLANT UNITS 1 AND 2 L DOCKET NOS. 50-324 & 50-325

!- LICENSE NOS. DPR-62 & DPR-71 F

RESPONSE TO NRC IFI 50-325/88-36-02 AND 50-324/88-36-02 s

Gentlemen:

[ The Final Summary Report for 15' Bulletin 79-02 is submitted in response to NRC.

4 Inspection Report 50-325/88-36 and 50-324/88-36, dated November 3, 1988. Item 4 s- of thisl inspection report closed Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts - IEB 79-02, and opened Inspector Follow-up-Items 50-325/88-36-02 and 50-324/88-36-02, which stated that CP&L would submit a Final Summary Report summarizing the bulletin requirements.and BSEP's response. The review of Ililti Bolt allowables (Inspector Follow-up Item 50-325/88-36-03:and 50-324/88-36-03) will be addressed at a later date, a IE Bulletin 79-02 requirements coupled With appropriate CP&L actions are as follows:

'1. Verify that pipe support base plate flexibility was accounted for in the calculation'of anchor bolt loads.

CP&L action is as follows:

l'

References:

a. Details of NRC Exit Interview (dated 8/7/80)

A which reference LER 2-80-55

b. Letter BSEP/81-0440 (dated 2/25/81)
c. Letter BSEP/82-1616 (dated 7/26/82) which provides a chronological account of CP&Ls actions taken to assure compliance of already installed base plates to the bulletin flexibility position.

l 7

~

~9003290176 900322 PDR ADOCK0500ggj4 f69

- - - - z U.S. Nuclear' Regulatory Commission .

%u ' . .

Relative to new design, in order to ensure that new base ~ plate designs.took-into account the flexibility position, Attachment'l to CP&L Letter,.

Serial: -GD-79-1739 was adopted and issued as a part of Power Discipline Technical Bulletin 7B to be used as.a design _ guideline for base plate design, ,

This was'later included in UE&C's H-21 evaluation criteria and later in, '

the Brunswick Engineering Support Unit's (BESU). Structural Design Guides 2 and.7 which are the on-site guideline for pipe support design. l o

2 .- Verify that the concrete expansion anchor. bolts have the following minimum-factor of safety between the bolt design. load.and the bolt; ,

4 ultimate capacity determined'from static tests which sim'ulate:the actual

,. conditions of. installation. .

I i CP&L action is as-follows:-

r.

t

References:

a. Letter GD-79-1739 (dated 7/12/79) '
b. Letter GD-79-3130 (dated 12/6/79)
c. Letter BSEP/80-2139 (dated 12/30/80)  ;
d. Letter BSEP/81-0440 (dated 2/25/81)
e. Letter BSEP/82-1616-(dated 7/26/82)-
f. Letter NLS 84-214 (dated 11/26/84) ,:

which discuss in detail CP&L's anchor bolt testing and reanalysis l

, programs which assure compliance of "in place" anchor bolts relative to the accepted factors of safety. '

Power Discipline Technical Bulletin 7B covers the new design and was j written to include the factors of safety provided by Bulletin 79-02.

Ae' stated before this information was used in UE&C's M-21 evaluation criteria and in BESU's Structural Design Guides 2 and 7.

3. Describe the. design requirements, if applicabic,-for anchor bolts to  !

withstand cyclic loads such as seismic' loads and high cycle' operating  ;

loads, E CP&L. action is as. follows:

t

References:

a. Letter GD-79-1739 (dated 7/12/79)  ;
b. Letter BSEP/82-1616 (dated 7/26/82)
c. Letter NLS-84-214-(dated 11/26/84)  !

. which explain the position taken by CP&L relative to cyclic loading and the torquing program that was adopted to ensure that existing  ;

, expansion anchors could withstand such loading.

v h

-t a

~

pq 3 r ,

qx ; < . ,,

?y 6, ,

pp. ~

fy %l) *

, - 4 .

L ,

U;S. Nuclear Regulatory Commission-  %

$ jl A

  • To ensure that e.'# design.is acceptable 1 relative to. cyclic loading

.f -the same series of-design documents. listed under requirements i and 2 _.

above nyre updated with the new pretensioning loads _ relative to the  ;

design allowable as mentioned in CP&L's torquing program.; '

~4. Verify from-existing QC documentation that design requirements have been met for anchor bolts relative to cyclic loading and bolt size and type.

. CP&L's compliance with this part of Bulletin 79-02/is. covered by'the= -l testing program as described in the letters referenced in Section11' j above. That test program was used to check:for-indication of-incorrect- l proload'and incorrect bolt size, type,.and embedment.

cf For nos design work- QC hold points were established-~as a part of site, '

, installation specification BSEP 248-107, to ensure that these require-ii ,

monts were met'. i

?

5. Determine the extent that= expansion anchor bolts were used in-concrete

+ ' block (masonry)' walls to attach piping supports in Seismic Category- ,,

1/ Safety Related systems.

]

, CP&L ldid- noti use expansion anchors . to attach safety-related'systen s'

~

to concrete block walls.

6', Determine:the extent that pipe supports with expansion" anchor' bolts used' N structural steel shapes instead of base. plates. 3

-As stated in CP&L Letter GD-79-3130, support.. meeting this criteria were included in the inspection and reanalysis program which was-

,I established.at the beginning of the bulletin compliance effort and w continued until-program completion.

Relative:to new design work-the same criteria established in the design documents in Sections l', 2,-and 3 above' applies to supports. H

" with' standard' structural steel shapes used in lieu of base plates, [

!~

although base plates are used almost exclusively for new design on t safety-related systems.

N lTho'remainderzof the requirements listed in IE Bulletin 79-02 refer to the-scheduling of requirement completion.  ;

Attachmcrit 1 provides a short synopsis'of those correspondences referred to in this letter.

This report summarizes the correspondence between the Brunswick Steam Electric  !

Plant and the NRC pertaining to the requirements-of IE Bulletin 79-02.

t h

1

[ d!

v Ir g, y

_.1 _'* ' ' . , _ _

'r #

(% . . s -/ f. f 1 1 . ,7 4 $ 1

+ > t as T, .4 :

1)O -%" '

4 tjp?ggf%m m) 7We p' ,m ,r E ;d; i n. ' ' T ,s,

, . a, y ,

WNhk$d ( .lN th,.'l, ' ?

l'- kNU l$4 U:g'.'m, 4 ~~-W, * * ; ,'

  • i +

G s E \ ai goo - a w. .n., 4 Cy [ 44j '. - [ . ., Q; .g 4

4

^

~

' ;t 7=  ;

x ;e 4 (r-

-4 ( I

. . j-f

(. 3

.T'- t e.+

}

-f Q.*_ . j'c,. 2 y iv  ;> r ura t + --

t p - m'1
, t.. 2 < .L F 74a - i

' _ ( , i e 1

9- , -

.g m_, f' 's,v. . 't_ff f s h~ f l:)l

, 3

= m e

'd '

+ c , , , ,

{g[x).g ,.

J~ ','g. . . . . . c . 2 - , .. - -M '. . -[ . . f . s

/n. TR.w m f~ ; U.S. ' Nuclearc-Regul' , , - ,

atory, Commission;,.

4 c - 4,- > +

p,.p 0,w;w; ' s* ,

~

p r.w- i ,

y-E , , i q.Q 4 - <- -

t,,. s .+ , = . , 1 hM q  ! Please'refertany(questionsfregarding'this- submittal'to Mr.1Je W.: Moystrat.;

' > y y W '

~ ~

L(919) 457-24041' b

~ , y,._

t, -. f l T w7.-Q:r n ,

1 -

9L - -

.g-~ (

y

{gbi Very,trulyfyoursb ,

n+

D.

, 1

-g g,1i 1

m s s

f-- .

7_ ,

, -i

. L. IJarness,E General' Manager' s

a , A - , .

f

, t- -

. Brunswick NucleartProjectJ ..

4 a -

=

, .v ..,

p' ~ TMJ/mcg1 ,

1q

.u .

pgy.p. ,

H cw s

! Enclosure. '

- m

, -.. ry

.n v  ; . >. . r: .

R '+ 'cc: - Mrs S.: D. iEbneteri -

M y -Mr.1E d G.5:Tourigny _ '

~j dia 'BSEP<NRC Resident Office < '

s .4:

u

\

g ,'4ey

+

' 4' / -' -f .'1-

+

t -..g 5

4  : (t' a , 4. )

- , / [wi,il'., ;5 4

'3 g *1 . t y

w:v..r

wy > ,

4 , .,*

A , m

(~ 51 ,. t g

[ ,  ! i ;. i j :. '

-=

p; v) :-, rm. . u . - g <

.(

j;. Q , A; ' '

q

, e

/ $,

.;f3_  ;;: ;m '. p .7 r e

+ ~ - _-'

q '{ n . ( ,:

3) gu -p. . -

i

. p

L ,i m: n r s 1 ,e e  %

-h "s, ' . r g'

n ' ;-

s f: f.,'4.-

}

4 'h .

4 4 3 .g; ..g.

J '"

g

'-\_, l'.'

'*.b*-1'e '

?l .?y

's 4'

i) i J

f 4 L r  ; >

l i,  % 1 Ev , ,7 ;

y .

r I

&4-g - +j

^~'f. g r 4. , .* -.2 '

}.

I -)

(

l ...l..

4'

\ 'i&%

s 4

.t>

Q,, '- f;-  ?-

3*-

i .-r < y .  :-- \;. :T Ista ' Ii Nk t s' o x'!- -+

cw u ,

, f f W d i s n.

Y!h . h b' t a:

%,pqQC3'*

1 j

,w h j[.N. E i

. I' v y.. .y. m; r.,- -
  • j r}:c

.?

g .i,

=q-l i S w .p..f i 3

pm f,,. ,

.vk

\ .,j ,'

y' k 4g ' ' '.  !

b r'

, ->,'.;-.11 l ( ', v' ,

i r'e 3 Yy % 1 p h f.iw  ?,e i Yh = o Y

. p 9

Q ? .7 X. r. 2!  !

h s ,4w &., V .s. . ,. e ..tu - )J.

y ..e d' ["e

~~

t >.

y:c .

l;>

fa Z h:# j

  • I f [, .; .5 w%ynn,'

fv'% 'j.. m+u - p. ,w' y1

..w M. e .m,N'; N P . ,

. m ..sKa:n y.g v

ho , ' : 'p p t ,q' . c 3 ..-g. g .. , -

r s; q.

g h" f ,.,

p . .. I ,p- :P*'{.'

..v, -

+t

6. 'e -,i,u..'

4

,4 q ,'- s. . g ~ fh N O D ?,ya-g'l

,i r .-'r b i, 1

+ j , g

' \ N' '

""h*

1 3

- o ,

p x.; p .

git l- ,V .--

b i /, ' L ATTACllMENT 11 Q/,

y:'

y  !$hesfollowing list is composed of pertinent letters and memorandums dealing-

~

'gf  ; with' tho' BSEP closure of IEB 79-02 along with the . appropriate actions taken to

. . resolve any'open items., --Note that this. list,is intended to deal with IEB-

'79-02_tnly, even though much of the information-included references IEB'79-07.-

.and:IEB 79-14,

~

4 -1. LLetter GD-79-1739 CP&L to NRC, dated July 12, 1979 R

y This letter explained, item by item, CP&L's current position regarding -

g- cach-facet of IEB 79-02. Safety-related~ piping base plates ' wore -

reanalyzedifor new loads per the.new IEB 79.-07. guidelines. This was' done

. . 'by BSEP Plant ModAfications79-123'and 79-124. Work was ongoing to-J comply with the noe safety factors for expansion anchora. The nuts on if expansion anchorsJwere to be retorqued to satisfy the requirements for

. cyclic loading. . An expansion alachor test program was initiated at.BSEP, y the results of which would be m31ntained on. site' for. NRC inspection.

2. Letter GD-79-3130, CP&L to NRC, dated December 6,1979 m~

This letter stated that the requirements of IEB 79-02'had'been satisfied

.by CP&L, -A few. inaccessible hangers were noted, butischeduled for ..

E completion during the next outage. Appropriate documentation was in the-

~

plant vault available~.for NRC review.

3.. Detall's-of:NRC Exit Interview, dated August 7, 1980 Due to-LER 2-80-55, it was realized that the CRD-linerb4se plates were

~

y, not included in the base plate flexibility roanalysis. Because of this, 3;j,"

~

the-Bulletin would remain open. 'A completion commitment date of LDecember 31,~1980, was given<by CP&L.

4. Letter BSEP/80-2139, CP&L to NRC, dated December- 30~ 1980 CP&L stated that approximately 300- additional supports per unit' had been (identified for expansion anchor testing. requiring.that the final IEBs79-02 schedule be pushed forward. The final schedule would be presented-February-25, 1981.

,W 5. ~. Letter BSEP/81-0440, CP&L to NRC, dateel February 25,L 1981

' Flexure acolysis was completied for the essential-CRD base plates.

Completion of base plate flexibility tecting relative to piping not-j

, essential to safe shutdown was scheduled as.a part of the Phase IIc

~f program.(March 51,.1982). Test.ing of the-accessiblo-portion of the 600-o ' additional supports (see above) was scheduled for completion by July 31,.

p, 1981.

1

\

Q' .

t l

}

e 1

I 4' ' ,.

g h'a% ,

4

NCT;46 .I g , Wpy

  • W ' <

j, oh 1y S ** , ,

p; ATTACHMENT 1:(Cont'd)
6. ' Letter.BSEPL82-1616,- CP&L to NRC' dated July' 26,11982 ,

CP&L stated that nonessential-portions of the CRD system (Phase II) are.

~

not safety related;and, therefore, reanalysis is not-required. Also.

4 7 stated was the fact that the. additional BSEP-2 support: testing was: .

completed. -BSEP-1 testing-is essentially. complete with.the few: remaining supports to be finished during the-upcoming' September 1982 outage. -t

7. Letter NLS 84-214, CP&L to NRC,' dated November 26, 1984 .,

-This was the last submittal concerning'IEB.79-02.~ . It statedLthat the" c t expansion anchor testing was completed. The BSEP-1-CRD support; fixes ,  ;

were' completed and BSEP-2 CRD supports'are to be completed pending

-redesign of the Reactor Pressure-Vessel foundation wall window supports.

The remaining work toL complete the obligation in Letter NLS 214 = (Item 7 - -

above) was done by;PlantiModification 82-147. This documents'the. completion, s of the brunswick Steam Electric Plant. work pertinent to IE' Bulletin 79-02. .i Based onJthe information provided'to the NRC' relative to this Bulletin,' we-  ?

request the closure.of-IEE 79-02. i P

r k

]

W 't

+

-i c

gf 4

i 9

~

.I

/

i,b 1

t C 41 3 .- r

,- < ii