Letter Sequence Other |
|---|
|
Results
Other: ML19209B241, ML19209D051, ML19225A294, ML19253C727, ML19254D131, ML19260C591, ML19261A687, ML19271A997, ML19289F192, ML19290G682, ML19290G684, ML19296B603, ML19305C421, ML19305C425, ML19309C609, ML19310A216, ML19312E060, ML19316B059, ML19318D060, ML19321B061, ML19321B275, ML19321B278, ML19321B279, ML19321B280, ML19323G448, ML19323G697, ML19323G716, ML19323G721, ML19323G724, ML19327A031, ML19327A034, ML19330A930, ML19330B134, ML19330B773, ML19331C780, ML19332A973, ML19339C903, ML19339C906, ML19340D089, ML19340D375, ML19340D378, ML19341D543, ML19343A468, ML19343B697, ML19343B738, ML19345B741, ML19345B745, ML19345D494, ML19347A955, ML19351D831... further results
|
MONTHYEARML20150A6581978-09-21021 September 1978 Order Re Responses to NRC Interrogatories by Coalition for Safe Pwr & Consolidation.Cfsp Must:Respond W/In 14 Days to S1,S2,E1,G1,G2,G3,G8 & All Other Interrogatories;Clarify the Status of Spokesmen.Motion for Reconsideration Is Denied Project stage: Approval ML20062C1421978-10-11011 October 1978 Notice of Evidentiary Hearing on Issue of Interim Operation & Limited Appearance.Hearing to Determine Whether Interim Operation Should Be Permitted Prior to Mods Required by Order Will Be Held on 781023 & 1030-1101 Project stage: Other ML20062D3481978-11-0606 November 1978 Cross-examination or Testimony Re Analysis & Review by Licensee Poge of safety-related Matls in Control-Auxiliary- Fuel Bldg Complex Will Be Taken at 781211 Hearing.Nrc Given Time to Reply to Interrogs.Proposed Findings Due 781120 Project stage: Other ML19261A6871979-01-30030 January 1979 Intervenors Are to File Contentions by 790226 & Close Discovery by 790328,after Which Evidentiary Hearing Re Phase 2 Issues Will Commence Project stage: Other ML19261C3481979-03-0808 March 1979 Notification of Prehearing Conference in Portland,Or,On 790329-30 Re Phase II Control Bldg Proceeding.Conference Will Consider Intervenors Contentions,Scheduling Matters & Status of NRC Review of Mod Project stage: Approval ML19289F1921979-04-12012 April 1979 Confirms Action Taken During Prehearing Conference,Phase II, Re Contentions of Coalition for Safe Power & Consolidated Intervenors.Directs Intervenors to Give Fuller Responses to Interrogatories.Adopts Phase II Schedule Project stage: Other ML19225A2941979-06-15015 June 1979 Order Directing Consolidated Intervenors & Coalition for Safe Power to Respond Promptly to NRC 790515 Second Set of Interrogatories.Order Relates to NRC 790614 Request Project stage: Other ML19209B2411979-07-27027 July 1979 Order Consolidating Intervenors N Bell & Consolidated Intervenors W/E Rosolie & Coalition for Safe Power Project stage: Other ML19254D1311979-09-12012 September 1979 Notifies of 790920 Hearing in Bethesda,Md,On NRC 790906 Motion to Postpone Phase II Evidentiary Hearing Scheduled for 791010 in Portland,Or Project stage: Other ML19209D0511979-09-18018 September 1979 Order Vacating NRC 790906 Motion to Postpone Hearing,Denying Intervenors 790913 Motion for Change of Venue & Granting State of or & Intervenors Motion for Extension of Time to Respond to Licensee Motion for Summary Disposition Project stage: Other ML19253C7271979-11-30030 November 1979 Modifies ASLB Partial Initial Decision Permitting Interim Operation of Facility.Operation Will Not Resume Pending Further Order.Nrc Shall Inform ASLB of Unresolved Items Re Seismic Issues Project stage: Other ML19260C5911979-12-12012 December 1979 Notice of 791228 Public Hearing Re Seismic Considerations & Interim Operation Motions & Orders Project stage: Other ML19296B6031980-02-0707 February 1980 Notice of 800331 Evidentiary Hearing on Phase II of Control Bldg Proceeding Re Safety of Mods.Hearing Will Be Held at Court of Appeals Courtroom,Portland,Or & May Continue on 800416 at Bonneville Power Admin Auditorium.W/Svc List Project stage: Other ML19305A7511980-02-0808 February 1980 Corrections to Transcript on 791229 Meeting in Portland,Or Hearing Re Control Bldg Project stage: Meeting ML19312D7611980-03-17017 March 1980 Forwards NRC Testimony of F Clemenson & Je Knight Re Mod Work Effects,Ks Herring & D Persinko Re Coalition for Safe Power Contentions 20,12/13 & 16 & CM Tramwell Re Railroad Spur & Safety Evaluation Authors Project stage: Approval ML19309C6091980-03-20020 March 1980 Order Re 800311-12 Prehearing Conference,Phase II of Control Bldg Proceeding,Held in Portland,Or.Licensee Motion for Summary Disposition of Contention 3 Granted.Interim Operation Will Constitute Issue in Evidentiary Hearing Project stage: Other ML19305C4211980-03-24024 March 1980 Forwards NRC 800324 Testimony of Ks Herring & D Persinko Re Structural Adequacy of Proposed Mods,Served on All Parties & Intervenors Per 800311 Prehearing Conference Agreement Project stage: Other ML19305C4251980-03-24024 March 1980 NRC Testimony Re Structural Adequacy of Proposed Control Bldg Mods.Presents Basis for Requiring Mods,Position Re Interim Operation & Assessment of Structural Adequacy Project stage: Other ML19316B0591980-05-0707 May 1980 Proposed Findings of Fact & Conclusions of Law Re Design Mods for Control Bldg.Mods Should Be Permitted Per Amend to OL Restoring Intended Design Margins of Revised Tech Spec 5.7.1 Project stage: Other ML19323G7241980-05-19019 May 1980 Memo of Points & Authorities in Support of State of or Proposed Findings of Fact & Conclusions of Law.Proposed Findings Are Intended to Increase Likelihood That Mods to Facility Will Meet Seismic Safety Stds Project stage: Other ML19323G7211980-05-19019 May 1980 State of or Proposed Findings of Fact & Conclusions of Law Re Design Mods for Facility.If Proposed Findings Are Included by ASLB in Initial Decision,State of or Will Concur W/Proposed Licensee Findings & Conclusions Project stage: Other ML19323G7161980-05-19019 May 1980 Forwards State of or Proposed Findings of Fact & Conclusions of Law Re Design Mods for Facility & Memo of Points & Authorities in Support of State of or Proposed Findings of Fact & Conclusions of Law Project stage: Other ML19305E7791980-05-19019 May 1980 Proposed Findings of Fact & Conclusions of Law on Mod to Control Bldg.Urges ASLB to Permit Mods Subj to Terms & Conditions Amending OL Per Encl Proposed Draft Order. Certificate of Svc Encl Project stage: Draft Other ML19323G4481980-05-22022 May 1980 Order Instituting Corrections to 800331-0403 & 0416-17 Evidentiary Hearing Transcripts.Pp 3,640-4,828.W/Certificate of Svc Project stage: Other ML19323G6971980-05-29029 May 1980 Response to NRC & State of or Proposed Findings of Fact & Conclusions of Law.Reporting Requirement Will Detract from Other Licensee Responsibilities & Should Not Be Imposed.Nrc Agrees to Footnotes 2,3 & 4.Certificate of Svc Encl Project stage: Other ML19312E0601980-05-30030 May 1980 Admits & Corrects Error in NRC 800519 Proposed Findings of Fact & Conclusions of Law on Control Bldg Mod,Stated in Footnote 34 on Page 134 Project stage: Other ML19310A2161980-06-0202 June 1980 Order Requesting Licensee to Supply Affidavit Re Licensee 800519 Rept on Discovery of Inadequate Connection in Auxiliary Bldg Wall.Cause of Occurrence & Other Related Matters Should Be Identified.Certificate of Svc Encl Project stage: Other ML19318D0601980-06-28028 June 1980 Submits Revised Criteria to Be Used in Analysis of out-of- Plane Behavior of Heavyweight Double Wythe Masonry Walls. Includes All Masonry Walls Having Safety Significance.All Masonry Walls Will Comply W/Revised Criteria by 801031 Project stage: Other ML19330A9301980-07-11011 July 1980 Initial Decision Modifying OL Immediately.Exceptions May Be Filed within 10 Days,Briefs within 30 Days & Supporting or Objecting Briefs within 30 Days of Original Briefs.Decision Shall Constitute Final Action within 45 Days Project stage: Other ML19321B2791980-07-23023 July 1980 Proposed Findings of Fact & Conclusions of Law Re Design Mods for Control Bldg.If ASLB Will Include Proposed Suppls & Additions in Initial Decision,Appellant Will Concur in Licensee Proposed Findings & Conclusions Project stage: Other ML19321B2751980-07-23023 July 1980 Forwards Motion for Reconsideration of Initial Decision, Memorandum of Points & Authorities in Support of Motion for Reconsideration & Proposed Findings of Fact & Conclusions of Law Re Design Mods for Control Bldg Project stage: Other ML19321B0611980-07-23023 July 1980 Forwards NRC Motions for Extension of Time to File Exceptions to ASLB 800711 Initial Decision & Other Related Requests.Nrc Will Issue License Amend Per ASLB Order Issued W/Initial Decision Due to Desire to Restore Seismic Margins Project stage: Other ML19321B2801980-07-23023 July 1980 Memorandum of Points & Authorities in Support of State of or Proposed Findings of Fact & Conclusions of Law.Findings & Conditions Proposed by Appellant Will Increase Likelihood That Mods Will Meet Seismic Safety Stds Project stage: Other ML19321B2781980-07-23023 July 1980 Memorandum of Points & Authorities in Support of Motion for Reconsideration of Initial Decision.Decision Does Not Discuss Issues Raised in State of or Proposed Findings of Fact & Conclusions of Law.Certificate of Svc Encl Project stage: Other ML19330B1341980-07-24024 July 1980 Order Granting Extension of Date for Filing Exceptions to ASLB 800711 Initial Decision Re Mods to Control Bldg. Executive Legal Director Requested to Remind Staff of Necessity for Compliance W/App a Requirements Project stage: Other ML19330B7731980-07-25025 July 1980 Amend 47 to License NPF-1 Permitting Proposed Mods to Control Bldg & Consisting of Tech Spec Changes Project stage: Other ML19330B7891980-07-25025 July 1980 Notice of Issuance of Amend 47 to License NPF-1 Project stage: Approval ML19330B7621980-07-25025 July 1980 Forwards ASLB 800711 Initial Decision Re Control Bldg Mods, Amend 47 to License NPF-1 Consisting of Changes to Tech Specs & Notice of Issuance of Amend to Facility OL Project stage: Approval ML19327A0311980-07-29029 July 1980 Response to NRC Motion for Clarification of ASLB 800711 Initial Decision Re License Condition on Control Bldg Mod. Does Not Object to Including NRC & Licensee Proposals in Condition 2.C.11 Project stage: Other ML19327A0341980-07-29029 July 1980 Response to State of or 800723 Motion for Reconsideration of Initial Decision.If Addition of Discussions Determined,Basis for Elaboration Is Set in Licensee 800529 Response to NRC & State of or Proposed Findings of Fact.W/Certificate of Svc Project stage: Other ML19351D8341980-07-31031 July 1980 Rept on Criteria & Methodology for Evaluation of Out-of- Plane Loading on Masonry Walls at Trojan Power Plant Project stage: Other ML19271A9971980-08-0707 August 1980 Order Granting Extension Until 800818 for NRC to Respond to State of or 800723 Motion for Reconsideration of Initial Decision Issued in Control Bldg Proceeding.Certificate of Svc Encl Project stage: Other ML19331C7801980-08-15015 August 1980 Response in Support of State of or 800723 Motion for Reconsideration of Initial Decision Re Basis for Rejection of Proposed Condition.Rejection of Condition Re Minor Deviation Reporting Was Proper.Certificate of Svc Encl Project stage: Other ML19331D3411980-08-27027 August 1980 Order Clarifying ASLB 800711 Initial Decision Re Control Bldg Mods.Provisions of PGE-1020 Through Revision 4 & PG&E Exhibit 27 Will Be Solely Imposed as License Conditions.All Other Matl Will Become Part of Amended FSAR Project stage: Approval ML19343A4681980-09-0404 September 1980 Order Adhering to ASLB 800711 Initial Decision Which Rejected State of or Proposed License Conditions Re Accelerated Reporting Project stage: Other ML19337A2011980-09-0505 September 1980 Advises That NRC Will Not File Exceptions to ASLB 800711 Initial Decision,Per ASLB 800827 Clarifying Order Project stage: Approval ML19332A9731980-09-15015 September 1980 Order Extending Until 800929 Time for State of or to Either Withdraw Exceptions to ASLB 800711 Decision,Amend Exceptions in Light of Ruling or Notify Aslab of Intent to Proceed W/ Appeal on Basis of Exceptions as Now Formulated Project stage: Other ML19347A9551980-09-23023 September 1980 Amended Exceptions to Initial Decision Re License Conditions & to ASLB Order Re State of or Motion for Reconsideration. Accelerated Reporting of Design Changes & Completion of Seismic Evaluation Must Be Imposed.Certificate of Svc Encl Project stage: Other ML20062J5401980-10-22022 October 1980 Brief in Support of Exceptions to ASLB 800711 Initial Decision & to Aslab 800904 Order.Urges That Decision Be Modified to Include Accelerated Reporting Conditions & That Oral Argument Be Held Re Exceptions.W/Certificate of Svc Project stage: Other ML19351D8311980-11-0404 November 1980 Informs That ASLB 800827 Condition Imposed Re Mods of Control Bldg Design Deficiencies Must Be Added to Fsar. Tech Spec 5.7.2.1 Should Be Modified.Response Requested within 30 Days Project stage: Other 1980-05-19
[Table View] |
Text
.+
C.
f* **%g ff&
fi
,o UNITl!D STATES y "
, *' g NUCLEAR REGULATORY COMMISSION p,
j WASHINGTON, D. C. 20555 z
.,3 D,
NOVEM8ER 2 4 1960 3
M n
Alan S. Rosenthal, Esq., Chairman j
f$
Dr. John H. Buck, Member j$$
3, Dr. W. Reed Johnson, Member MI?$
Atomic Safety and Licensing Appeal Board 3
Washington, D.C.
20555 ms
~
O "S
g m,
In the Matter of a
Portland General Electric Comany, et al.
a (Trojan Nuclear Plant)
Docket No. 50-344 (Control Building)
Gentlemen:
Enclosed is a letter from the Office of Inspection and Enforcement, Region V (IE:V), to Portland General Electric Cogany dated October 14, 1980. The letter and its enclosure set forth.the results of the first Systematic Appraisal of Licensee Performance for licensee Portland General Electric Cogany.
The letter and enclosure (p.2) state that IE:V plans to increase the frequc" icy and/or scope of future inspection activities in certain areas.
In particular, page 2 of the enclosure states that the Trojan Regional Pei formance Evaluation Board (Board) recomends increased inspection activity for cogleteness of licensee's review process as it relates to tne requirements of 10 CFR 50.59, based on apparent weaknesses in this area recently identified in a Health Physics Appraisal for Trojan Nuclear Plant.
The Board further recommends that the existence and adequacy of written safety evaluations for modifications to be made to f acility structures, systems, or components described in the f acility's Final Safety Analysis Report be examined more closely in future i nspections.
Because this information is related to the appeal of the State of Oregon in this proceeding which asks for accelerated reporting to the NRC staff of licensee safety evaluations made pursuant to 10 CFR 50.59 regarding changes to the Control Building modification program, the letter and its enclosure is fonvarded to you for your information.
Sincerely, ovak, Assistant Director for Operating Reactors Division of Licensing E nclosure:
SRC letter dated October 14, 1980 cc w/ enclosure:
See ner.t pace 8 012800 l $$
S Mr. Charles Goo 6 tin, Jr.
Portland General Electric Company cc:
Mr. Ronald W. Johnson, Esquire Mr. John A. Kullberg Corpordte Attorney Route One Portland General Electric Company Box 250Q 121 S.W. Salmon Street Sauvie Island, Oregon 97231 Portland, Oregon 97204 Maurice Axelrad, Esquire Robert M. Hunt, Chairman Lowenstein, Newman, Reis, Board of County Comissioners Axelrad and Toll Columbia County Suite 1214 St. Helens, Oregon 97051 1025 Connecticut Avenue, N.W.
Washington, D. C.
20036 Columbia County Courthouse Law Library, Circuit Court Room St. Helens, Oregon 97051 Frank W. Ustrander, Jr.
Counsel for Oregon Dept. of Director, Oregon Department of Energy E.nergy Labor and Industries Building,' Room lil 500 Pacific Building Salem, Oregon 97310 520. S.W. Y amhill Portland, Oregon 97204-Dr. Hugh D. Paxton rir. David B. McCoy 1229.41st Street Los Alamos, New Mexico 87544 348 Hussey Lane Grants Pass, Oregon 97526 Michael Malmros, Resident inspector U. S. Nuclear Regulatory Comission William Kinsey, Esquire Trojan Nuclear Plant 1002 N.E. Holladay P. O. Box 0.
Portland, Oregon 97232 Rainier, Oregon 97048 Ms. Hina Bell Dr. Kenneth A. McCollom, Dean -
.72S 5.E. 26th Street Division of Engineering, Pcrtland, Oregon 97214 Architecture and Technolocy Oklahcmi State University
" r. Eugene R. Rosclie Stillwater, Oklahoma 74074 t.,oalition for Safe Feuer 215 S.E. 9th Avenue Portland, Oregon 97214 ryw,-we-e-
Mr. Charles Goodwin, Jr.
Portland General Electric Company cc:
Marshall E. Miller, Esquire, Chairman Atomic Safety and Licensing Board U. S. Nuclear Regulatory Commission Washington, D. C.
20555 Atomic Sefety and Licensing Board Panel U. S. Nuclear Regulatory Comnission Washington, D. C.
20555 Docketing and Service Branch (7)
Office of the Secretary U. S. Nuclear Regulatory Comnission Washington, D. C.
20555 Alan S. Rosenthal, Esquire Atomic Safety and Licensing Appeal Board U. S. Nuclear Regulatory Commission Washington, D. C.
20555 Dr. John H. Buck Atomic Safety and Licensing Appeal Board U. S. Nuclear Regulatory Commission Washington, D. C.
20555 Dr. W. Reed Johnson Atomic Safety and Licensing Appeal Board U. S. Nuclear Regulatory Commission Washington, D. C.
20555 Atomic Safety and Licensing Appeal Panel '(5)
U. S. Nuclear Regulatory Commission Washington, D. C.
20555 6
-y w
-,,mo r---
e-n-
,r
- +
g<
g, e-es
..----,m--.
y.
ny
<-.w
-~ peq r
a w+-
kYh (
p,...yo UNITED STATES NUCLEAR REGULATORY COMMISSION i.'
E REGION V
~
sA
[
1990 N, CAllFORNI A SOULEV ARD e
SUITE 202. WALNUT CREEK PLAZA e.,,e WALNUT CREE K, CALIFORNIA 94596 October 14, 1980 4
Docket No. 50-344 Portland General Electric Company.
121 S. W. Salmon Street Portland, Oregon 97204 Attention: Mr. Bart D. Withers Vice President, Nuclear Gentlemen:
1 i
Subject:
NRC Regional Evaluation of Licensee Performance - Trojan This refers to the meeting held at Portland General Electric Company offices in Portland, Oregon, on October 10, 1980, between Mr. R. H. Engelken and members of the Region V staff with Messrs. W. J. Lindblad, and others of your staff. The purpose of this meeting was to discuss the results of NRC's regional evaluation of licensee performance for those activities authorized by NRC License No. NPF-1.
A copy of this evaluation and supporting data are enclosed.
Results of this, the first of NRC's planned hystematic Appraisal of Licensee Performance (SALP) evaluations conducted with regard to the Trojan plant, reveal areas which, although not of serious concern at this time, we plan to increase the frequency and/or scope of our future inspection activities. We feel these areas, identified in the enclosed evaluation, represent areas where you should direct particular management attention as well.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosures will be placed in the NRC's Public Document Rooms.
Should you have questions regarding the enclosed evaluation and supporting data, we will be glad to discuss them with you.
t Si c.e
[
. ! Ls C s, Chief eact r Operations and Nuclear Support Branch
(
Enclosure:
Regional Evaluation of Trojan September 1979 through August 1980, dtd 9/25/80 ep p
cc:
W. J. Lindblad, PGE 4
C. P. Yundt, PGE
))
]/
J. W. Durham, Esq., PGE F
+,,-_r--
.,,y n,,-,-
=
f y,,.-
r,,,w y
,_,,m
,..w,
,u m,
e, w
,-,w,.,
.-c-
+-eemmy
,,-.f.-~_
-+m-3
8ga ae <.,*'c, UNITED STATES l'
c /
,n NUCLEAR REGULATORY COMMISSION
{.
J. 8!
REGION V 1990 N. CALIFORNIA BOULEVARD o,
SUITE 202. WALNUT CREEK PLAZA g '.O
,e
WALNUT CREEK.CALIFORN4A 94696 e,,,
September 25, 1980 MEMORANDUM FOR:
J. L. Crews, Chief, Reactor Operations and Nuclear Support Branch, IE:RV FROM:
Regional Performance Evaluation Board - Trojan i
SUBJECT:
REGIONAL EVALUATION OF TROJAN - SEPTEMBER 1979 THROUGH AUGUST 1980
[
The Regional Performance Evaluation Board, consisting of representatives from Reactor Operations, Construction, Radiation Protection, Safeguards, and NRR, met on September 9,1980, and performed an evaluation of Trojan activities for the period of September 1,1979, through August 31, 1980. The Board's review encompassed the following:
1.
Licensee performance in each of the 17 functional areas identified in Appendix A of MC 2955.
2.
Enforcement actions for the period of September 1,1979, through August 31, 1980.
1 3.
Licensee event reports submitted during the period of September 1,1979, through August 31, 1980.
The Board reconsnends, based upon the results of the review, that increased or special inspection activity be performed in the functional areas of (1) manage-ment control and (2) design changes and modifications.
One aspect of management control which has raised the concern of the Board stems from the sequence of Licensee Event Report Nos. 80-08, 80-09, 80-10 and 80-11 each of which was attributed to personnel error and occurred during a major refueling-maintenance outage. The Board noted that the Oregon Department of Energy has also expressed a concern in this area, as discussed in a letter to the licensee dated July 25, 1980. It appears that improved management coordin-ation of plant activities with the requirements of the facility license during major plant outages could preclude incidents such as those described in the Licensee Event Reports.
Increased inspection attention to this facet of manage-ment control during future major plant outages is recommended for the resident inspectors and cognizant Region V inspectors.
e, n
g i
oF tcp il @ 4 a y
. --.....