ML19092A093

From kanterella
Jump to navigation Jump to search
Revision 32 to Updated Safety Analysis Report. Responses to NRC Questions 005.1 Through 031.20
ML19092A093
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 03/11/2019
From:
Wolf Creek
To:
Office of Nuclear Reactor Regulation
Shared Package
ML19092A099 List: ... further results
References
WO 19-0010
Download: ML19092A093 (205)


Text

WOLF CREEK Questions 005.1 through 031.20, are the November 17, 1977 NRC questions which were addressed to all construction permit applications that referenced RESAR-3.

The following provides the response, as applicable to WCGS.

Q005.1 Provide the list of transients that were analyzed in determining the maximum steam system pressure

transient for sizing the steam generator safety

valves.

RESPONSE Refer to Section 5.2.2.

Q005.2 In reference to Section 5.3.4, provide Reactor Coolant System Temperature - Percent Power map for

plant with loop stop valves if different from Figure 5.3-1.

RESPONSE Since WCGS does not incorporate loop stop valves, this question is not applicable.

Q005.2.2 Provide a discussion of the consequences of inadvertent overpressurization resulting from a

malfunction or operator error when the reactor

coolant system is water-solid during startup or

shutdown. The discussion should include

consideration of the pressure-temperature operating

limitations on the reactor vessel to protect against

brittle fracture. In addition, discuss any design

provisions that will be incorporated into the

facility design to prevent overpressurization

incidents that would exceed allowable pressures in

this particular plant condition.

RESPONSE Refer to Section 5.2.2.

Q005.2.7 Discuss the ability to assure that the operational capability of the valves that are required to

function in the short and long term LOCA modes of

ECCS operation are not impaired by potential

crystallization of boric acid solutions on the valve

stem due to leakage. Appropriate methods may

include the ability to detect individual valve stem

leakoff or periodic operational testing of the

valves.

RESPONSE Refer to Section 6.3.2.2. 005-1 Rev. 0 WOLF CREEK Q005.3 Justify the fouling factor resistance specified in Section 5.5.2.3.1. Correct the difference between

Section 5.5.2.3.1 and Table 5.5-3 with regard to the

fouling factor.

RESPONSE The fouling factor is discussed in Section 5.4.2.5.1 and is consistent with the value reported in Table 5.4-3.

Q005.4 Provide pressurizer relief and safety valve capacities when discharging water liquid.

RESPONSE Refer to Section 5.4.13.2. 005-2 Rev. 0 WOLF CREEK Q006.1 Item 6.3.2.11 of the "Standard Format and Content of Safety Analysis Reports for Nuclear Power Plants" (Revision 1, October 1972) indicates the need to

distinguish between true redundancy incorporated in

a system and multiple components. To complement the

SAR discussions in this regard, provide a summary of

a systematic core cooling functional analysis of

components required over the complete range of

coolant pipe break inside the containment. The

summary should be shown in the form of simple block

diagrams beginning with the event (pipe break),

branching out to the various possible sequences for

the different size breaks, continuing through

initial core cooling and ending with extended to

long-term core cooling. When complete, the diagram

should clearly identify each safety system required

to function to cool the core for all coolant pipe

breaks inside the containment during any plant

operating state. The attached Figure 6-1 is

provided as a guide.

RESPONSE System reliability of the ECCS, including a discussion of redundancy compliance with the single failure criteria, is provided in Section 6.3.2.5. Functioning

of the various ECCS components for various accidents, including large and small

LOCAs, is discussed in Section 6.3.3. The actual LOCA analyses are discussed

in Section 6.2 and 15.6.5.

Also refer to the Response to Question 015.0(1).

Q006.2 For each engineered safety feature identified in Question 6.1, list the auxiliaries required for its

operation.

RESPONSE Refer to Section 6.3.2.2 and the Response to Question 015.0(1). 006-1 Rev. 0 WOLF CREEK Q010.01 Describe the device located on the suction side of the auxiliary feedwater pumps. This item is

identified as SS001, SS002, and SS003 on Figure

10.4-9.

RESPONSE The P&ID legend is provided on Figure 1.1-1. 010-1 Rev. 0 WOLF CREEK Q015.0(1) For each transient and accident analyzed in Chapter 15, provide the following information:

(1) The step-by-step sequence of events from event initiation to the final stabilized condition.

This listing should identify each significant

occurrence on a time scale, including for

example: flux monitor trip, insertion of

control rods begin, primary coolant pressure

reaches safety valve set point, safety valves

open, safety valves close, containment

isolation signal initiated, containment

isolated, etc. All required operator actions

should also be identified.

(2) The extent to which normally operating plant instrumentation and controls are assumed to

function.

(3) The extent to which plant and reactor protection systems are required to function.

(4) The credit taken for the functioning of normally operating plant systems.

(5) The operation of engineered safety systems that is required.

RESPONSE The sequence of events listed for each transient is provided in Tables in Chapter 15.0. The assumptions for instrumentation, controls, protection

systems, and ESF systems are described for each transient analyzed in Chapter

15.0.Figures of the step-by-step sequence of events for each transient are also provided in Chapter 15.0.

Q015.0(2) Section 15.2.4 of RESAR-3 UNCONTROLLED BORON DILUTION , analyzes the effects of a dilution at power. The analysis discusses the causes of the incident, and the automatic actions of the Reactor

Protection System and the manual actions prompted by

alarms and instrumentation that would mitigate the

consequences of the accident. 015-1 Rev. 0 WOLF CREEK However, there is a possible situation, involving the loss of offsite power, where a dilution incident

may not be as readily apparent as that described in

Section 15.2.4 and where no automatic Reactor

Protection System action is available.

In order to assess the potential severity of a dilution accident after a loss of offsite power, provide the results of an analysis that assumes the

anticipated equipment configurations in normal use

prior to the event that results in the most severe

consequences. The analysis should include a

dilution operation in progress with the Chemical and

Volume Control System mode selector switch being in

the DILUTE position (or ALTERNATE DILUTE mode). The

loss of offsite power is then assumed to occur with

the minimum shutdown reactivity insertion due to

control rods. Both diesel generators start and

sequence the loss of offsite power loads.

The concerns are that the charging pumps again automatically start running after being loaded to

the diesel generators and from electrical schematics

of control circuits for the reactor makeup water

pumps, that the reactor makeup water pumps would

also again automatically start with the mode selector switch in DILUTE. Therefore, a dilution of

the Reactor Coolant System is again in progress

which could potentially result in a return to

critical.

If the reactor makeup water batch integrator is assumed to malfunction by not automatically cutting

off flow at the pre-selected value, provide the time

available for manual action before the total

shutdown margin is lost due to this dilution. If

operator action is to be prompted by alarms, describe the features that will alert the operator

to this specific action at a time when alarms from

many plant systems are occurring simultaneously.

RESPONSE This question is not applicable to WCGS since the reactor makeup water pumps cannot be supplied by the emergency diesel generators. 015-2 Rev. 0 WOLF CREEK Q031.1 Section 3.9.1.2 of RESAR-3 states that dynamic (3.10) testing procedures concerning Westinghouse supplied

safety-related mechanical equipment will be provided

in the applicant's FSAR. It is our position that as

a minimum you commit to conduct a seismic

qualification program to conform to the criteria as

contained in Attachment A. State your intent to

employ the criteria as contained in Attachment A for

all Westinghouse Category I mechanical equipment in

order to confirm the functional operability of such

equipment during and after a seismic event up to and

including the SSE.

RESPONSE Refer to Section 3.9(N).2.2.

Q031.2 Section 3.9.2.4.1 of RESAR-3 states that the pump (3.10) motor and vital auxiliary electrical equipment will

be qualified by meeting the requirements of IEEE

Standard 344-1971. Since the standard has undergone

a major revision, state your intent to meet the

requirements of the 1975 version of IEEE Standard

344. IEEE Standard 344-1975 includes requirements

which are applicable to all plants with C.P.

applications docketed after October 1972.

RESPONSE Refer to Section 3.9(N).3.2.

Q031.3 The seismic qualification criteria for electrical (3.10) equipment as stated in Section 3.10 of the proposed

Amendment 6 to RESAR-3 is not completely acceptable because it is only applicable to certain specific

conditions when single frequency input to an

individual axis is justifiable. A broader criterion

to account for overall considerations should be

provided. The major concern is the possible

directional coupling and the concurrent multi-mode

response. An acceptable response is to conduct a

seismic qualification program as recommended by the

1975 version of IEEE-344 Standard. State your

intent to use this recommended criteria.

RESPONSE Refer to Section 3.10(N).

031-1 Rev. 1 WOLF CREEK Q031.4 The lists of safety-related equipment and components (3.11) provided in Section 3.11.1 of RESAR-3 are not

complete. Identify all individual components and

complete the lists.

RESPONSE Refer to Section 3.11(N).

Q031.5 Section 3.11.2 of RESAR-3 does not give a complete (3.11) and acceptable description of the qualification

tests and analyses for each type of safety-related

equipment and component. Provide this information

for each item.

RESPONSE Refer to Section 3.11(N).

Q031.6 RESAR-3 Section 7.1.2.5. Describe how your design (3.11) complies with IEEE Standard 323-1971, or IEEE

Standard 323-1974, for all applications for which

the construction permit safety evaluation report was

issued July 1, 1974 or later. Identify and justify

all exceptions.

RESPONSE Refer to Section 3.11(N).

Q031.7 In accordance with the implementation dates (noted (7.1) in parentheses) and as they apply to your

application, describe the extent to which the

recommendations of the following regulatory guides

will be met. Identify and justify any exception.

Regulatory Guide 1.22 (Safety Guide 22), "Periodic Testing of Protection System Actuation Functions" (Guide dated 2/17/72)

Regulatory Guide 1.29, "Seismic Design Classifications;" (Revision 1 dated August 1973) 031-2 Rev. 1 WOLF CREEK Regulatory Guide 1.30 (Safety Guide 30), "Quality Assurance Requirements for the Installation, Inspection, and Testing of Instrumentation and

Electric Equipment;" (Guide dated August 11, 1972)

Regulatory Guide 1.40, "Qualification Tests of Continuous-Duty Motors Installed Inside the

Containment of Water-Cooled Nuclear Power Plants;"

(Guide dated 3/16/73)

Regulatory Guide 1.47, "Bypassed and Inoperable Status Indication for Nuclear Power Plant Safety

Systems;" (Guide dated May 1973)

Regulatory Guide 1.53, "Application of the Single-Failure Criterion to Nuclear Power Plant Protection

Systems;" (Guide dated June 1973)

Regulatory Guide 1.62, "Manual Initiation of Protective Actions;" (Guide dated October 1973)

Regulatory Guide 1.63, "Electric Penetration Assemblies in Containment Structures for Water

Cooled Nuclear Power Plants;" (Guide dated October

1973)

Regulatory Guide 1.68, "Preoperational and Initial Startup Test Programs for Water-Cooled Power

Reactors;" (Guide dated November 1973)

Regulatory Guide 1.73, "Qualification Tests of Electric Valve Operators Installed Inside the

Containment of Nuclear Power Plants;" (Guide dated

January 1974)

Regulatory Guide 1.75, "Physical Independence of Electric Systems." The physical identification of

safety-related equipment should also be addressed in

this section; (Guide dated February 1974)

Regulatory Guide 1.80, "Preoperational Testing of Instrument Air Systems;" (Guide dated June 1974) and Regulatory Guide 1.89, "Qualification of Class IE Equipment for Nuclear Power Plants." (Applicable to

all plants with an SER issued after July 1, 1974).

031-3 Rev. 0 WOLF CREEK RESPONSE Refer to Appendix 3A.

Q031.8(1) Provide a discussion and the results of an analysis (7.1) showing how your design of the test and calibration

features of the safety systems meets the

requirements of Section 4.10 of IEEE Std 279-1971.

RESPONSE Refer to Sections 7.1.2.5.2, 7.1.2.6.2, and 7.3.8.2 item (5) and Figures 7.3-2 and 7.3-3.

Q031.8(2) Based on Figure 7.2-1, Sheet 7 of 17, of RESAR-3 we (7.2) have concluded that the proposed design for the

steamline differential pressure circuits does not

conform to the requirements of IEEE Standard

279-1971. Specifically, during operation with a

loop isolated, the logic for the operable steamlines

is effectively changed to 2-out-of-2 which does not

meet the single failure criterion. Our position is

that in order to comply with IEEE Std 279-1971, the

design should incorporate positive means of assuring

that these circuits continue to meet the single

failure criterion during operation with a coolant

loop isolated. Discuss your intent to comply with

this position and describe the necessary design

changes, or justify any exceptions by discussing

your reasons for concluding that such exceptions are

in accordance with the requirements of IEEE Standard

279-1971. In addition as committed on Page 7.2-30

of RESAR-3, provide the results of an analysis that

will determine whether automatic tripping of the

steamline differential pressure bistables is

required for N-1 loops operating.

RESPONSE Refer to Figure 7.2-1 (Sheet 7) and Table 7.3-13.

Q031.9 RESAR-3 Section 7.2.1.1.2(1)(d) and Figure 7.2-1 (3.7.2) Sheet 3 address a power range high neutron flux rate

"Positive" trip. This trip is used as protection

against a rod ejection accident. The referenced

Westinghouse Topical Report WCAP-7380-L (pages 2-8 031-4 Rev. 0 WOLF CREEK and 3-12) provides a diagram and a description for the "Negative" flux rate trip but does not provide

for the "Positive" flux rate trip. Provide a

description and diagram covering "Positive" flux

rate trip.

RESPONSE WCAP-7380-L was replaced with WCAP-8255.

Refer to Section 7.2.4.

Q031.10 The reactor trip system contains logic circuits that (7.2) can initiate trips for the purpose of anticipating

the approach to a limiting condition for operation.

Specifically, these reactor trips are:

(1) Generation of a reactor trip by tripping the main coolant pump breakers, (2) Generation of a reactor trip by tripping the turbine, (3) Generation of reactor trip by underfrequency conditions on reactor coolant pump bus, and (4) Generation of reactor trip by undervoltage conditions on reactor coolant pump bus.

Our position requires that all inputs to the reactor trip system be designed to meet IEEE Standard 279-1971, with an exception for anticipatory trips

(trips not required for safety actions in the

accident analysis - Chapter 15). The exception is

that sensors for anticipatory trips are not required

to be located in a qualified seismic Category I

structure. Discuss your intent to comply with this

position or justify any exceptions you may have in

this regard. Your response should include a

discussion of the testability of these circuits

while the reactor is at power.

RESPONSE (1) Refer to Section 7.2.1.1.2, item d.2.

(2) Refer to Section 7.2.1.1.2, item f.

(3) Refer to Section 7.2.1.1.2, item d.3.

(4) Refer to Section 7.2.1.1.2, item d.3.

031-5 Rev. 0 WOLF CREEK Q031.11 Testing of the reactor trip system and the engi-(7.2, 7.3) neered safety feature actuation system to verify

that the "systems" response times are equal to or

less than the values assumed in the accident

analysis is discussed on Page 7.1-19, 7.2-24, and

7.3-13 of RESAR-3. In addition to the proposed

response time testing during preoperational start-up

testing and following the replacement of a component

that affects response time, our position requires

that these systems be designed to permit periodic

verification that the response times are within the

values assumed in the accident analysis. Discuss

your intent to comply with this position or justify

any exceptions.

It is stated in RESAR-3 on Page 7.3-26 that the response time specified in Paragraph 4.1 of IEEE

Standard 338-1971 is not checked periodically as is

the setpoint accuracy. Provide justification for

the exception to this requirement.

RESPONSE Refer to Section 7.1.2.6.2.

Q031.12 With regard to the motor operated accumulator isola-(7.3) tion valves, we require that the proposed design

include the following features in order to conform

to the requirements of IEEE Std 279-1971:

(1) Automatic opening of the accumulator valves when either (a) the primary coolant system

pressure exceeds a preselected value (to be

specified in the Technical Specifications) or

(b) a safety injection signal has been

initiated. Both signals shall be provided to

the valves.

(2) Visual indication in the control room of the open or closed status of the valve, actuated by

sensors on the valve.

(3) An audible alarm, independent of Item (2), that is actuated by a sensor on the valve when the

valve is not in the fully open position.

031-6 Rev. 0 WOLF CREEK (4) Utilization of a safety injection signal to automatically remove (override) any bypass

feature that may be provided to allow an

isolation valve to be closed for short periods

of time when the reactor coolant system is at

pressure (in accordance with the provisions of

the proposed Technical Specifications).

Discuss your intent to comply with these

requirements or justify any exceptions to these

requirements.

RESPONSE Refer to Section 7.6.4. and Figure 7.2-1 (Sheet 6).

Q031.13 Based on the information provided in Section 7.3 of (7.3) RESAR-3, we conclude that the proposed design for

manual initiation of steam line isolation does not

conform with the requirements of Section 4.17 of

IEEE Standard 279-1971. In addition, there is not

sufficient information on the design provision for

manual initiation of containment isolation and

containment depressurization to determine whether

these functions are designed in accordance with

Section 4.17 of IEEE Standard 279-1971. Our

position is that a design which meets the following

is an acceptable means of meeting the requirements

of Section 4.17 of IEEE Standard 279-1971:

(1) Means should be provided for manual initiation of each protective action (e.g., reactor trip, containment isolation) at the system level, regardless of whether or not means are also

provided to initiate the protective action at

the component or channel level (e.g.,

individual control rod, individual isolation

valve).

(2) Manual initiation of a protective action at the system level should perform all actions

performed by automatic initiation such as

starting auxiliary or supporting systems, sending signals to appropriate valves to assure

their correct position, and providing the

required action-sequencing functions and

interlocks.

031-7 Rev. 0 WOLF CREEK (3) The switches for manual initiation of protective actions at the system level should

be located in the control room and be easily

accessible to the operator so that action can

be taken in an expeditious manner.

(4) The amount of equipment common to both manual and automatic initiation should be kept to a

minimum. It is preferable to limit such common

equipment to the final actuation devices and

the actuated equipment. However, action-

sequencing functions and interlocks (of

Position 2) associated with the final actuation

devices and actual equipment may be common

providing individual manual initiation at the

component or channel level is provided in the

control room. No single failure within the

manual, automatic, or common portions of the

protection system should prevent initiation of

protective action by manual or automatic means.

(5) Manual initiation of protective actions should depend on the operation of a minimum of

equipment consistent with 1, 2, 3, and 4 above.

(6) Manual initiation of protective action at the system level should be so designed that once

initiated, it will go to completion as required

in Section 4.16 of IEEE Standard 279-1971.

Discuss your intent to comply with this position or justify any exceptions by discussing your reasons

for concluding that such exceptions are in

accordance with the requirements of IEE Standard

279-1971.

RESPONSE Refer to Section 7.3.8.2, item b.7.

Q031.14 General Design Criterion 37 requires, in part, that (7.4) the emergency core cooling system be designed to

permit testing the operability of the system as a

whole. On Page 7.3-26 of RESAR-3, it is stated that

the safety injection and residual heat removal pumps

are made inoperable during the system tests. Our

position is that in order to comply with the

requirements of Criterion 37, these pumps must be

included in the system test. Discuss your intent to

comply with this position or justify any exception.

031-8 Rev. 0 WOLF CREEK RESPONSE Refer to Section 6.3.4.2.

Q031.15 Section 6.3.5.1 of RESAR-3 states that only "one (7.3, 6.3) temperature detector which provides heater control

for the immersion heater, control room alarm and

control room indication" is provided for the boron

injection surge tank. Provide the results of an

analysis which addresses the effect of a single

failure in this system. This analysis should

include possible boron dilution during

recirculation. Also, it is our position that the

monitoring system for the boron injection system

meet IEEE Standard 279-1971. Discuss your intent to

comply with this position or justify any exceptions

you may have in this regard.

RESPONSE Refer to Section 6.3.2.2.

Q031.16 The description of the Emergency Safety Feature sys-(7.3.1) tems provided in Section 7.3.1 of RESAR-3 is

incomplete in that it does not provide all of the

information requested in Section 7.3.1 of the

Standard Format for those safety-related systems, interfaces and components supplied by the applicant

which match with the RESAR-3 scope systems. Provide

all of the descriptive and design basis information

requested in the Standard Format for these systems.

In addition, provide the results of an analysis, as

requested in Section 7.3.2 of the Standard Format, to demonstrate how the requirements of the General

Design Criteria and IEEE Standard 279-1971 are

satisfied and the extent to which the

recommendations of applicable Regulatory Guides are

satisfied. Identify and justify each exception.

RESPONSE Refer to Section 7.3.8.

Q031.17 Provide analyses showing that no adverse effects (7.3.1) will occur or a discussion of such adverse effects

that could occur as a result of power interruption

to the Engineered Safety Features Actuation System

at any time following the onset of a LOCA or other

accident conditions in the plant.

031-9 Rev. 0 WOLF CREEK RESPONSE Refer to Section 7.3.

Q031.18 General Design Criterion 25 requires that the pro-(7.4, tection system be designed to assure that specified

15.3.6) acceptable fuel design limits are not exceeded from

an accidental withdrawal of a single rod control

cluster assembly (not ejection). In the accident

analysis, presented in Section 15.3.6 of RESAR, it

is stated that "no single electrical or mechanical

failure in the rod control system could cause the

accidental withdrawal of a single rod control

cluster assembly." However, Chapter 7.0 does not

describe how the design prevents such an

occurrence. Provide a detailed description of the

control circuitry and discuss how the design meets

the requirements of Criterion 25.

RESPONSE Refer to Section 7.7.2.2 and Figure 7.7-15.

Q031.19 Provide a discussion which supplements those in (7.4, 7.5 Sections 7.4, 7.5 and 7.6 of RESAR-3 and which

7.6) addresses the Standard Format information

requirements for the safe shutdown systems, the

safety-related display instrumentation and other

safety systems and equipment outside the RESAR-3

scope which are assumed in the RESAR-3 and the PSAR

Chapter 15 accident analyses.

RESPONSE The safety-related systems are identified in Section 7.1.1. The safe shutdown safety-related system and other safety-related systems are discussed in

Sections 7.4, 7.5, and 7.6.

Q031.20 In addition to the design features discussed in (7.6.2) Section 7.6.2 of RESAR-3, it is our position that

the design of the RHR isolation valves satisfy the

following:

(1) The interlocks shall utilize diverse equipment, and (2) The interlocks shall be designed in accordance with the intent of IEEE Standard 279-1971. 031-10 Rev. 0 WOLF CREEK The information presented in Section 7.6.2 of RESAR-3 does not address the requirements for diverse

equipment and describes a degree of testability that

conflicts with the requirements of IEEE Standard

1971. In addition, it is stated that the position

indications for the RHR valves differ from those for

the accumulator isolation valves but these

differences are not identified. Discuss your intent

to comply with the requirements that the design

shall utilize diverse equipment and shall include

complete on-line test capability without opening the

isolation valves, or justify any exceptions. In

addition, identify the differences in the position

indications provided for the RHR valves compared to

the accumulator valves and discuss the reasons for

the differences.

RESPONSE Refer to Section 5.4.7. 031-11 Rev. 0 WOLF CREEK Q040.01 Figure 8.3-1 shows a "hold" symbol next to MCC PG 12J. Explain.

RESPONSE See revised Figure 8.3-1.

Q040.02 Figure 8.3-2 has several loads listed as "later." Indicate the status of these loads.

RESPONSE See revised Figure 8.3-2. 040-1 Rev. 0 WOLF CREEK Q110.01 Section 3.10(B).2 addresses only Bechtel's scope of (3.10(B).2) supply. Discuss your compliance with IEEE 344, 1975

and Regulatory Guide 1.100 for equipment outside

Bechtel's scope of supply.

RESPONSE Section 3.10 is presented in two parts: 3.10(B) and 3.10(N). Section 3.10(N) contains discussions on the compliance of the NSSS (Westinghouse) equipment to

IEEE-344, 1975 and Regulatory Guide 1.100. All equipment subject to Regulatory

Guide 1.100 is discussed in Section 3.10(B) or Section 3.10(N). 110-1 Rev. 0 WOLF CREEK Q123.01 Identify whether SA-540 Class 1 or 2 material was used for closure bolting in the reactor coolant

pumps. If SA-540 Class 1 or 2 materials were used

for closure bolting in reactor coolant pumps, demonstrate the generic adequacy of the fracture

toughness and demonstrate compliance with Paragraph

I.C of Appendix G, to 10 CFR Part 50.

RESPONSE SA-540 Class 1 or 2 material was not used for closure bolting in the reactor coolant pumps for WCGS. See Table 5.2-2.

Q123.02 Indicate whether the individuals performing the fracture toughness tests were qualified by training

and experience and whether their competency was

demonstrated in accordance with a written

procedure. If the above information cannot be

provided, state why the information cannot be

provided and identify why the method used for

qualifying individuals is equivalent to those of

Paragraph III.B.4 Appendix G, 10 CFR Part 50.

RESPONSE See Section 5.2.3.3.1.

Q123.03 Duplicate questions were received by SNUPPS and WCGS. See Q251.1.

RESPONSE See Response to Q251.1

Q123.04 Duplicate questions were received by SNUPPS and WCGS. See Q251.2.

RESPONSE See Response to Q251.2

Q123.05 Revise the FSAR to indicate that the conclusions of Westinghouse Topical Report WCAP 9292 are applicable

to Wolf Creek SA-533 Grade A, Class 2 steel and SA

508 Class 2a steels.

RESPONSE Refer to Section 5.2.3.3.1. 123-1 Rev. 0 WOLF CREEK Q123.06 Duplicate questions were received by SNUPPS and WCGS. See Q251.3.

RESPONSE See response to Q251.3.

Q123.07 Duplicate questions were received by SNUPPS and WCGS. See Q251.4.

RESPONSE See response to Q251.4.

Q123.08 Duplicate questions were received by SNUPPS and WCGS. See Q251.5.

RESPONSE See response to Q251.5.

Q123.09 Duplicate questions were received by SNUPPS and WCGS. See Q251.6.

RESPONSE See response to Q251.6.

Q123.10 Duplicate questions were received by SNUPPS and WCGS. See Q251.7.

RESPONSE See response to Q251.7.

Q123.11 Submit for review an inservice inspection program for the pump flywheels which complies with Paragraph

C.4l of Safety Guide 14, October 27, 1971.

RESPONSE See Appendix 3A. 123-2 Rev. 0 WOLF CREEK Q210.1 Duplicate questions were received by SNUPPS and WCGS. See Q110.01.

RESPONSE See Response to Q110.01.

Q210.2 The applicant states that all circumferential breaks in the RCS piping are assumed to result in a limited

separation such that the maximum flow area is less

than a full break area. The applicant must provide

the design information assumed for each location

where limited break areas are postulated including

gap size, restraint stiffness, blowdown force, and

maximum restraint deflection. The results of the

time-history analysis (if used) should include the

break area vs. time and mass flux rate vs. time

which were used to calculate the subcompartment

pressurization.

In addition, all restraint locations on the RCS piping must be shown.

RESPONSE Refer to revised Sections 3.6.2 and 5.4.14.

Q210.3 In Section 1.8 of the Callaway SER (NUREG-0830), the staff identified a confirmatory item regarding the

testing of pressure isolation valves. In Section

3.9.6 of the SER, the staff stated that the

applicants have addressed the leak testing of only

those check valves with an Event V configuration

which form an interface between RCS pressure and low

pressure coolant injection systems. The applicant's

response for the Event V configuration is documented

in a letter from N. Petrick to H. Denton dated

September 11, 1981. However, the SER also stated

that other low pressure interfacing systems exist

with valve configurations whose failure could lead

to an intersystem LOCA. These other systems include

the accumulator discharge check valves, the boron

injection system pressure isolation valves, and the

motor operated valves in the RHR system. The SER

stated, as a confirmatory item, that the staff will

require that the leak-tight integrity of the

pressure isolation valves in the above systems be

verified by testing. 210-1 Rev. 0 WOLF CREEK In order to complete the confirmatory item, it will be necessary for the applicants to identify all

pressure isolation valves that will be included in

their leak test program. The staff requires that

these valves be included in the Callaway and Wolf

Creek Technical Specifications. Limiting conditions

for operation which will require corrective action

and surveillance requirements which state the

testing frequency should also be provided in the

Technical Specifications. The applications should

also submit four sets of Piping and Instrumentation

Drawings (P&ID) for each system containing the

pressure isolation valves to be tested. After

reviewing the list of pressure isolation valves and

provided we find it acceptably complete, we will

consider the confirmatory item completed.

It should be emphasized that a proposed maximum allowable leakage limit of 10 gpm is not acceptable

to the staff. The staff will require a maximum

allowable leakage limit of 1.0 gpm in the Callaway

and Wolf Creek Technical Specifications unless

adequate justification is made for an exception.

RESPONSE See the Technical Specifications and Figures 5.1-1, 5.4-7, and 6.3-1. 210-2 Rev. 0 WOLF CREEK Q220.1 The staff has determined that Section 3.7(B).4.1 of the SNUPPS FSAR does not comply with the intent of

R.G. 1.12, Rev. 1, as it claims. Nevertheless, it

does comply, to a greater extent although not fully, with the positions of R.G. 1.12, Proposed Rev. 2, than that of R.G. 1.12, Rev. 1. The staff would

accept that section of the FSAR if it is revised to

comply with the positions of R.G. 1.12, Proposed

Rev. 2, July, 1981.

RESPONSE See Section 3.7(B).4.1.

Q220.2 Provide a discussion on how major cable tray test results were used in arriving at the 20% modal

damping. The discussion should assure consistency

of observed data and calculations used.

RESPONSE See Section 3.7(B).3.16.

Q220.3 Why was cable tray test input loading applied at a 45 degree angle instead of simultaneous horizontal

and vertical load input? What are the implications

of this testing method upon the validity of the

recommended 20% damping (e.g., with respect to

statistical independency requirements of different

directional inputs)?

RESPONSE See Section 3.7(B).3.16.

Q220.4 Will sprayed-on fireproofing affect cable friction and thus the damping ratios?

RESPONSE See Section 9.5.1.2.2.3.

Q220.5 The cable tray test conditions do not reflect the actual physical site situation. Provide the

rationale for extending the test results to the

actual design which is different from the test

configuration. 220-1 Rev. 0 WOLF CREEK RESPONSE See Section 3.7(B).3.16.

Q220.6 Specify different conditions under which different modal damping ratios ranging from 7-20% are used.

(cable tray)

RESPONSE See Section 3.7(B).3.16.

Q220.7 It appears that the scope of the cable tray test and the number of tests may not support direct extension

to SNUPPS (the appropriate project) cable tray

design. Justify that the scope of test conducted is

adequate for direct design application.

RESPONSE See Section 3.7(B) 3.16.

Q220.8 Justify the use of 7% critical damping for conduit supports for all seismic input levels.

RESPONSE See Section 3.7(B).3.16.

Q220.9 On Page 4 in last paragraph you stated that the method was selected in compliance with Standard

Review Plan (SRP). Indicate which version of SRP

you have referred to.

RESPONSE See revised Section 3C.1.2.2.1.

Q220.10 The second sentence on top of Page 5 implies that the original FLUSH Analysis is unconservative and

unrealistic. Clarify this statement.

RESPONSE There is no implication that FLUSH results are unconservative. It is stated that a fixed base analysis is more conservative but still realistic when

compared to the FLUSH results. 220-2 Rev. 0 WOLF CREEK Q220.11 Under item C on Page 5, you stated that the presence of the soil surrounding the embedded portion of the

structure was conservatively omitted. However, in

staff's opinion your omission of the soil may result

in a frequency shift and may, therefore, not be

conservative. Your response to this staff's concern

is requested.

RESPONSE See revised Section 3C.1.2.2.1.

Q220.12 In the results of analyses for both fixed base and using FLUSH, there is substantial shift of maximum

response. It is requested that response spectra

enveloping the results of two analyses should be

used unless your justification for not doing so is

provided.

RESPONSE See revised Section 3C.1.2.2.1.

Q220.13 On Page 9 in the second paragraph you indicated the consideration of torsional effects. Describe in

detail how the torsional effects have been

considered in the analysis.

RESPONSE See revised Section 3C.1.2.2.2. 220-3 Rev. 0 WOLF CREEK Q230.1 Provide a figure to illustrate the geographic regions used in the probability calculations

discussed on FSAR Page 2.5-144.

RESPONSE Figure 2.5-75 of the USAR illustrates the geographic regions used in the probability calculations.

Q230.2 Provide figure similar to FSAR Figure 2.5-82 comparing the SSE and (a) the scaled response

spectra discussed on Pages 2.5-148 to 2.5-149 and

(b) Nuttli's proposed spectra discussed on Page 2.5-

149.

RESPONSE See revised Section 2.5.2.5.

Q230.3 Current Staff Practice is to approach the development of response spectra by performing

statistical analyses on the strong motion records

for sites with similar foundation conditions. (See

for example, Lawrence Livermore Laboratory, 1979, Draft, Seismic Hazard Analysis: Site Specific

Response Spectra Results). Estimate the magnitudes

of (a) the maximum random earthquake near the site

and (b) the maximum event associated with the Nemaha

Uplift. Accordingly, estimate the ground motion at

the Wolf Creek site assuming (a) the maximum random

event less than 25 km from the site, and (b) the

maximum event associated with the Nemaha Uplift

about 50 miles from the site.

Select response spectra from accelerograms for recording sites with foundation conditions similar

to Wolf Creek. Choose those events that are within

one-half the estimated magnitudes. For the data set

compute 50 and 84 percentiles for the response

spectra assuming the spectral ordinates are log

normally distributed. On a plot similar to FSAR

Figure 2.5-82 compare these spectra to the SSE.

RESPONSE See revised Section 2.5.2.6.

Q230.4 Discuss the following recent studies and their significance to the Wolf Creek site: 230-1 Rev. 0 WOLF CREEK

1) Yarger, H. L., 1981, Aeromagnetic Survey of Kansas, EOS Transactions, v. 62, n. 17, 173-

178.

2) Steeples, D. W., and M. E. Bickford, 1981, Piggyback Drilling in Kansas: An Example for

the Continental Scientific Drilling Program, EOS Transactions, v. 62, n. 18, 473-476.

RESPONSE See revised Section 2.5.1.1.5.1.19. 230-2 Rev. 0 WOLF CREEK Q231.1 Prepare a new figure (or revise an existing figure) locating the noncapable shear zones, shear planes, and faults mapped at the site and described in the

FSAR (Page 2.5-102). Also prepare a table listing

the above deformations, the site location of the

deformation, and the Dames & Moore report where the

deformation mapping and description appears.

RESPONSE See revised Section 2.5.1.2.4.1.

Q231.2 A number of lineaments, other than those numerically identified, are shown in Coffey County (the site

county) on FSAR Figures 2.5-14a and 2.5-14b.

Identify these unnumbered lineaments and present

your interpretation of the origin/cause of each.

Include in your discussion the relationship, if any, between each of the Coffey County lineaments

(including those presently shown on FSAR Figures

2.5-14a and 2.5-14b) and the folds and faults

identified on FSAR Figures 2.5-15 and 2.5-16.

RESPONSE See revised Section 2.5.1.1.5.1.18.

Q231.3 Expand the LANDSAT lineament presentation (Revision 4, July 1981) to include a discussion of the

relationship between the lineaments discussed, folds

and faults (FSAR Figures 2.5-15 and 2.5-16),

Precambrian surface folds and faults (FSAR Figure

2.5-14b), and earthquake epicenters.

RESPONSE See revised Section 2.5.1.1.5.1.18.

Q231.4 Please provide a copy of the Dames & Moore report(s) discussing and portraying the Saddle Dam IV

faulting. These reports are referenced in the D & M

Second Interim Report of July 1979 (Dames & Moore, 1977; 1978a). Also provide a copy of the report(s)

which includes the geologic map (and accompanying

description) of the Drum Building excavation.

RESPONSE Saddle Dam IV is described in Section 2.5.6.4.1.2. 231-1 Rev. 0 WOLF CREEK Q231.5 Discuss the following recent studies and their significance to the Wolf Creek site:

1) H. Yarger et al. 1981, Bouguer gravity map of Southeastern Kansas, Kansas Geological Survey, Open-File Report.
2) Steeples, D.W., 1981, Microearthquake network activities, Fiscal Year 1980, Kansas Geological

Survey, Report to the Kansas City District

Corps of Engineers.

3) Steeples, D.W., 1981, Structure of the Salina-Forest City interbasin boundary from seismic

studies, Kansas Geological Survey, prepared for

the W.H. McNutt Memorial Lecture Series.

RESPONSE See revised Section 2.5.1.5.1.18. 231-1 Rev. 0 WOLF CREEK Q240.0 HYDROLOGIC & GEOTECHNICAL ENGINEERING BRANCH Q240.1 In Section 2.4.10 you state that the ESWS screen (2.4.10) house was designed to withstand a high water

elevation of 1100.2 feet, which corresponds to the

maximum wave runup elevation from a wave height of

5.0 feet, with a period of 3.3 seconds. Using the

PMF water surface elevation of 1095 feet, the

combined wind set-up and runup must have been 5.2

feet. The staff's independent analysis at the ESWS

screenhouse shows the maximum runup including set-up

is 6.60 feet resulting in a high water elevation of

1101.60 feet. Our analysis is based on the

following assumptions: 1) an effective fetch of 2.1

miles, 2) average fetch depth of 34 feet, 3) over

land windspeed of 40 mph adjusted for over-water (50

mph), and 4) average depth along the south side of

the structure of 17.8 feet. Either justify your

wave runup calculations or use the staff's estimates

and discuss the effects of the resulting higher wave

runup elevation on the ESWS screenhouse.

RESPONSE See Section 2.4.10.

Q240.2 Table 2.4-25. The natural evaporation used to eval-(2.4.11.3) uate cooling lake drawdown are data for Fall Reservoir. Provide geographical coordinates of Fall

Reservoir location. Since evaporation is a micro-

climatically dependent phenomenon, provide

sufficient justification (i.e., similarity of

meteorological variables - wind speed, vapor

pressure, etc.) for using Fall Reservoir natural

evaporation in the analysis of cooling lake

evaporation.

RESPONSE See Section 2.4.11.3.2.

Q240.3 Table 2.4-27. Provide a detailed description of (2.4.11.3) your procedure for calculating forced evaporation from the cooling lake as presented in Table 2.4-26.

Accompany the description with an example

calculation including all data required to perform

the example calculation. 240-1 Rev. 0 WOLF CREEK RESPONSE See Section 2.4.11.3.2 Q240.4 During the August 13, 1981 site visit, you indicated (2.4.11.6) that concrete pads were placed on the bottom of the

ultimate heat sink and essential service water

intake canal, and that sedimentation rates would be

monitored by divers. Please discuss details of

sampling methods, locations and frequency. Also, provide details of dredging procedures to restore

capacity if and when it is reduced below the

required capacity.

RESPONSE See Section 2.4.11.6.

Q240.5 It is stated in Section 9.2.5.3 that the UHS dam (9.2.5.3) embankment structure will withstand overflow

conditions that would result if the main cooling

lake were to be drawn down below the UHS dam crest

elevation. Please provide the maximum expected

overflow velocities at the UHS dam during a

postulated loss of the main cooling lake dam event

and a discussion of the analysis including all

pertinent assumptions. Provide evidence that the

unprotected soil abutments of the UHS dam will not

be eroded during the postulated event to the extent

that there will be a loss of essential service water

from behind the UHS dam.

Two cases were investigated to have an effect on the UHS for a postulated failure of the cooling lake

main dam. Case I postulated the simultaneous

failure of the cooling lake Main Dam and the Baffle

Dike 'A' in front of the UHS. In Case II it was

assumed that Baffle Dike 'A' fails subsequent to the

main dam failure.

RESPONSE See Section 9.2.5.3.

Q240.6 Please provide a description of the trash collection (9.2) and removal procedures from the service water and

essential service trash racks. 240-2 Rev. 0 WOLF CREEK RESPONSE See Section 9.2.1.1.2 and 9.2.1.2.3.

Q240.7 What is the criteria used to determine which wells will be sealed and what is the status of well

sealing?

RESPONSE See Section 2.4.13.1.1.2.

Q240.8 Please provide a revised Figure 2.4-52 showing the cooling lake at its normal operating level and the

WCGS property boundary superimposed on the well

inventory within five miles of the plant.

RESPONSE See Figure 2.4-52.

Q240.9 Section 2.4.2.3.1 of the SNUPPS FSAR states that (2.4.2.3) any rainfall in excess of design intensity (7.4

inches) will overflow the roof curb and the building

walls to the site drainage system. Describe in more

detail the roofs of safety related structures

regarding their ability to pond water. State the

maximum heights of any curbs or parapets on the

roofs and the dimensions and locations of scuppers

or other openings that will limit the depth of water

during the PMP event.

RESPONSE See Section 2.4.2.3.

Q240.10 State whether any permanent underdrains or ground water dewatering systems are installed, being

constructed or planned at the plant site. If so, provide the information called for Branch Technical

Position HMB/GSB, "Safety-Related Permanent

Dewatering Systems." RESPONSE See Section 2.4.13.5.1. 240-3 Rev. 0 WOLF CREEK Q241.1 In Figure 2.5-97a through 2.5-97e show the data

points used in developing these curves. Also plot

the mean and the standard deviation curves.

RESPONSE See Section 2.5.4.7.

Q241.2 Provide a summary of the results of field density

and moisture content tests used for quality control

during construction of structural fill under and

backfill around the Category I structures. Present

the results as a statistical distribution plot or by

other convenient method(s) to be able to verify that

the specified compaction has been attained. Provide

the above data for each type of fill separately for

the Power Block Unit, the ESWS pumphouse, the ESWS

discharge structure and the seismic Category I

pipelines and electrical duct banks. NOTE: The ESWS Discharge Structure was removed from service after replacement of the ESWS underground piping.

RESPONSE See Section 2.5.4.5.1.5.

Q241.3 Provide details of the six different types of

backfill and the bedding materials used in the

construction of ECCS seismic Category I piping and

electrical duct banks including gradation and

plasticity index requirements, and principal

construction criteria.

RESPONSE See Section 2.5.4.5.3.5.

Q241.4 For the ESWS discharge structure, submit drawings showing plans and typical cross-sections of the limits of excavation and types of fill and backfill materials. NOTE: The ESWS Discharge Structure was removed from service after replacement of the ESWS underground piping.

RESPONSE See Section 2.5.4.5.4.

Q241.5 1) In Figure 2.5-47 show locations and limits of

soft material, if any, that was replaced by

competent material during construction.

241-1 Rev. 28 WOLF CREEK

2) For the ECCS pipeline, provide typical

transverse cross section showing the excavation

limits, pipe, bedding, and different kinds of

backfill materials.

3) Provide typical longitudinal section and cross

section details of excavation and backfill near

the interface between the ECCS pipes and the

structures.

4) What are the estimated total and differential

settlements of the ECCS pipe and the structures

at their interface due to both static and

dynamic loads?

5) What is the estimated settlement of the ECCS

piping due to both static and dynamic loads?

RESPONSE See Section 2.5.4.10.3.1.

Q241.6 Provide a copy of the Bechtel Topical Report

(2.5.4.7) BC-TOP-4A, referenced on Page 2.5-199 of the FSAR.

RESPONSE Bechtel Topical Report, BC-TOP-4A, was approved by the NRC on October 31, 1974.

Q241.7 Provide a plot of the magnitude and distribu-

(2.5.4.10.1.3) tion of lateral earth and water pressures used

in the design of subsurface walls and, on the

same figure, plot the dynamic lateral pressures

computed from the soil-structure interaction

analyses due to the building and soil response

under dynamic loading conditions. Provide such

plots for the main powerblock structures, the

ESWS pumphouse, and the ESWS discharge

structure. NOTE: The ESWS Discharge Structure was removed from service after replacement of the ESWS underground piping.

RESPONSE See Section 2.5.4.10.1.3.

Q241.8 Revise FSAR Figure 2.5-111 to show the location (Figure of sections GG and HH.

2.5-111)

241-2 Rev. 28 WOLF CREEK RESPONSE See USAR Figure 2.5-108 and 2.5-111.

Q241.9 In Figure 2.5-112 show the following missing (Figure information:

2.5-112) 1) The water levels and the piezometric surfaces used in the stability analyses for all

conditions analyzed.

2) Show the minimum factor of safety and the corresponding critical sliding wedge.

RESPONSE See Figure 2.5-112 of the USAR.

Q241.10 1) In Figure 2.5-113 show the following missing (Figure 2.5- information:

113) a) Subsurface soil profile and the soil

parameters for each soil layer that were

used in the slope stability analyses.

b) Show the water levels and the piezometric surfaces used in the stability analyses

for all conditions analyzed.

c) Show the minimum factors of safety and the corresponding critical slip circles for

each of the cases investigated.

2) Discuss the validity of using slip circle method of analysis, particularly for the side

slopes of the pumphouse intake channel (3H:1V),

considering that a) the hard rock layer is in

the immediate vicinity of the toe of the slope, b) for the UHS slope you choose to use the

sliding wedge method of analysis. Justify the

validity of the slip circle method of analysis

or investigate the stability of the slopes of

the ESWS pumphouse intake channel using the

sliding wedge method. 241-3 Rev. 0 WOLF CREEK

3) For the cross section presented in Figure 2.5-113 explain why the minimum factor of safety

for the stability of (3H:1V) slope is higher

than the minimum factor of safety for the

stability of (5H:1V) slope.

RESPONSE 1) The information requested is shown on USAR Figure 2.5-113a through 2.5-113h. Section 2.5.5.2.2.2 had been revised to

include a reference to these figures.

2) See Section 2.5.5.2.2.2.
3) See Section 2.5.5.2.2.2

Q241.11 Show the critical slip circle and the corresponding (Figure minimum factor of safety for the cases investigated

2.5-115) in the stability analyses presented on Figure 2.5-

115. Also, correct Detail A that shows the fine

filter layer between the coarse filter layer and the

riprap layer.

RESPONSE USAR Figures 2.5-115b through 2.5-115d show the critical slip circles and Factors of Safety for the cases investigated. Section 2.5.6.5.1.2 has been

revised to include a reference to these figures. Detail A on Figure 2.5-115 (this was changed to USAR Figure 2.5-115a) has been corrected.

Q241.12 Provide a description of the monitoring system that (2.5.6.8.4) is being used to measure the movements of the UHS

dam. Summarize the data collected to date and

compare the results with the estimated movements of

the UHS dam. Comment on the results of this

comparison and its safety implication.

RESPONSE See revised Section 2.5.6.8.4.

Q241.13 Provide a summary of the results of field density and moisture content tests performed in connection

with quality control during construction of the UHS

dam. Present the results as a statistical

distribution plot or by other convenient method(s)

to verify that the specified compaction has been

attained. 241-4 Rev. 0 WOLF CREEK Compare the compacted in-situ density and moisture content of the embankment fill with those of the

test specimens from which the design strength

parameters have been determined by laboratory

testing. Based on the above comparison, comment on

the validity of the physical and strength parameters

used in the design.

RESPONSE See revised Section 2.5.6.4.2.1.1.

Q241.14 Identify the local and federal agencies that have regulatory authority over the main dam, and the

license or permit number(s); provide a brief

description of the safety inspection program

required and confirm your commitment to meet these

requirements.

RESPONSE See Section 2.5.6.8.1.

Q241.15 A seep was noticed in the grandular toe drain on the downstream side of the main dam during staff site

visits in August and December 1981. At that time, the reservoir was not filled up to normal the

operating level. This dam is a back-up structure

for the safety-related UHS dam.

1) The possibility that the main dam embankment material may be a dispersive clay is of

concern.

2) Provide a commitment to monitor the vertical and lateral deformation of the main dam and

seepage through the dam during operation of the

Nuclear Power Plant. Submit for review by the

NRC details of the performance monitoring

program presented in Section 2.5.6.8 of the

FSAR.

3) Summarize the data collected to date and compare the results with estimated movements of

the main dam. Comment on the results of this

comparison and its safety implication.

RESPONSE See Section 2.5.6.6.1. 241-5 Rev. 0 WOLF CREEK Q241.16 The UHS dam embankment material was tested to determine the dispersive characteristics of the

clay. The FSAR does not address this topic beyond

the presentation of the laboratory test data.

Provide the following:

1) Full details of your study, including any input from outside consultant, on this item.
2) Provide the test procedure, details of the data monitored and conclusions for the field test

(filling only UHS pond) performed on the UHS

dam.

3) Amend the FSAR to include the above information.

RESPONSE 1. See Section 2.5.6.4.1.4.1.14.

2. See Section 2.5.6.4.1.4.1.14.
3. See Section 2.5.6.4.1.4.1.14.

Q241.17 Provide specification for the cohesive backfill (2.5.4.5.1.5.12) material.

RESPONSE See Section 2.5.4.5.1.5.1.2.

Q241.18 Provide clear prints of Figures 2.5-108 and 2.5-111.

(2.5.5.2)

Show on Figure 2.5-108 the location of the sections

analyzed for stability.

RESPONSE See Section 2.5.5.2.2.2.

Q241.19 Docket a write-up on the computer program used (2.5.5.2.2.1) for the sliding wedge method of stability

analysis. If you have not used a computer

program, provide detailed write-up of the

method of analysis. 241-6 Rev. 0 WOLF CREEK RESPONSE See Section 2.5.5.2.2.1.

Q241.20 1) What is the elevation of the water table for (2.5.5.2) end-of-construction condition for UHS slope and

Intake Channel Slopes? Is it el 1053.0 ft or

el 1070.0 ft?

2) Justify using the water table elevation of 1070.0 ft rather than the normal cooling lake

level of elevation 1087.0 ft for steady-state

condition.

3) The drop in the water level for rapid drawdown condition should be from an initial elevation

of 1087.0 ft to elevation of 1070.0 ft in the

event of main dam failure, and to elevation of

1065.0 ft in the event of both main dam and UHS

dam failure. Justify the water table

elevations used in the stability analysis for

rapid drawdown conditions presented in Figures

2.5-113d and 2.5-113h.

4) Revise Figures 2.5-113a through h to show the proper water levels and if required, revise the

analysis to reflect the revised water table.

5) Provide analysis and factor of safety for the stability of the UHS slope (analyzed by Sliding

Wedge Method) for the rapid drawdown condition.

6) Justify using total stress shear strength parameters for the residual soil in the

analysis presented in Figure 2.5-113h.

Revise your analysis using effective stress strength parameters and proper water table.

7) Table 2.5-57 and analysis presented in Figures 2.5-113g and 2.5-113h are not compatible.

Revise Table 2.5-57.

RESPONSE 1. See Sections 2.5.5.2.2.1 and 2.5.5.2.2.2.

2. See Section 2.5.5.2. 241-7 Rev. 0 WOLF CREEK
3. Analyses have been presented in Section 2.5.5.2 for 5:1 slopes for rapid drawdown from elevations 1087 to 1070 ft. Drawdown

to elevation 1065 ft would only occur if the UHS dam failed

in which case there would be no water in the UHS and therefore

a stability analysis is not needed.

4. See Figures 2.5-113a through h and Table 2.5-57.
5. Figure 2.5-112 has been revised to clarify these conditions.
6. Section 2.5.5.2 has been revised.
7. Figures 2.5-113a through h and Table 2.5-57 have been revised to reflect the revised analysis.

Q241.21 The FSAR does not address the dynamic stability and (2.5.5.2) liquefaction potential aspects of the UHS slopes and

intake channel slopes. Amend the FSAR to include

these items.

RESPONSE See Subsections 2.5.5.2.3 and 2.5.5.2.4.

Q241.22 1) Provide settlement versus time plots for Category I structures based on data from the

settlement monitoring program.

2) What are the maximum total and differential settlements measured to date and also expected

in the future?

3) Compare the measured settlements with the anticipated settlements assumed in the analysis

of these structures and their appurtenances, and evaluate the impact of any difference

between the measured and anticipated

settlements on the design and construction of

these structures and appurtenances.

RESPONSE See Section 2.5.4.10.1.2 for items 1 through 3.

Q241.23 Solution channels filled with clay were discovered in the Plattsmouth Limestone formation during

geologic mapping of the UHS dam foundation

excavation. This was not reported in the FSAR. 241-8 Rev. 0 WOLF CREEK

1) What was the areal extent and depth of these solution channels, and are there any continuous

channels across the dam foundation?

2) How did you determine the presence or absence of these solution features within the limestone

formations?

3) Was the soil in the solution cavities tested for the properties resistant to piping and for

erosion under the design conditions?

4) Evaluate the effect of these solution channels on the safety of the UHS dam.

RESPONSE 1. A description of these features is provided in revised Section 2.5.1.2.5.3.

2. The subsurface exploration program for the UHS and the UHS dam are described in Section 2.5.6.2.1.

A description of the extent and depth of the solution features observed in the UHS dam foundation is provided in Section

2.5.1.2.5.3.

3. No tests related to resistance to piping and erosion were performed on the material in the solution features. However, see Item 4 below.
4. The solution features discovered in the Plattsmouth Limestone during the mapping of the UHS dam foundation are discussed in

Section 2.5.1.2.5.3.

Q241.24 Provide the following information on the UHS dam filling test:

1) What was the quantity of water pumped into the UHS dam during the 30-day monitoring period?
2) What was the quantity of water pumped from the downstream toe to maintain a water level of

elevation 1955 feet?

3) What were the estimate seepages through the UHS dam and through the UHS dam foundations? 241-9 Rev. 0 WOLF CREEK
4) Compare the estimated vertical and lateral deformation of the UHS dam with "those measured

during the filling and subsequent 30-day

monitoring of the UHS dam." Evaluate the

impact of any differences between the measured

and estimated deformations on the safety of the

UHS dam.

5) Provide a copy of the report "Final Report, Surveillance of Earthwork, UHS and UHS Dam" by

Dames & Moore, 1981.

RESPONSE 1. See revised Section 2.5.6.8.4

2. See revised Section 2.5.6.8.4
3. See revised Section 2.5.6.8.4
4. See revised Section 2.5.6.8.4
5. A copy of the report was provided.

Q241.25 Provide copies of the following reports:

1) "Engineering Data Compilation for the Wolf Creek Lake" Sargent Lundy Report SL-3830
2) "Engineering Data Compilation for Water Control Structures at Wolf Creek Lake" Sargent and

Lundy Report SL-3831 RESPONSE The requested documents were provided to the NRC in letter KMLNRC 82-177, dated March 16, 1982.

Q241.26 The responses to the following inquires are the result of a meeting held with the NRC on March 19, 1982. These inquiries were never formally

transmitted to KG&E by the NRC.

NRC Inquiry (1):

For the UHS dam (include riprap on top to elevation 1077.0, in your analysis). 241-10 Rev. 0 WOLF CREEK a) pseudo - static; seismic coefficient 0.12, 0.15.

b) dynamic FEM analysis for SSRS.

RESPONSE a. See Section 3C.1.2.3.1.

b. See section 3C.1.2.3.1.

NRC Inquiry (2):

UHS Slopes

a) pseudo - static analysis - seismic coefficient 0.15.

RESPONSE a. See Section 3C.1.2.3.1.

NRC Inquiry (3):

Seismic Category I Buried Pipes and Electrical Duct Banks Comment on dynamic stability for SSRS loading.

RESPONSE See Section 2.5.4.5.3.6. 241-11 Rev. 0 WOLF CREEK Q251.1 To demonstrate compliance with the beltline material test requirements of Paragraph III.C.2 of

Appendix G, 10 CFR Part 50:

a) Provide a schematic for the reactor vessel showing all welds, plates and/or forgings in

the beltline. Welds should be identified by

shop control number, weld procedure

qualification number, the heat of filler metal, and type and batch of flux. Provide the

chemical composition for these welds

(particularly Cu, P, and S content).

b) Indicate the post-weld heat treatment used in the fabrication of the test welds.

c) Indicate the plates used to fabricate the test welds.

d) Indicate whether the test specimen for the longitudinal seams was removed from excess

material and welds in the vessel shell course

following completion of the longitudinal weld

joint.

RESPONSE See Figure 5.3-2, Table 5.3-7 and Section 5.3.1.1.

Q251.2 To demonstrate compliance with the fracture toughness requirements of Paragraph IV.A.1 of

Appendix G, 10 CFR Part 50:

a) Provide the RT NDT for all RCPB welds which may be limiting for operation of the reactor vessel.

b) Indicate whether there are any RCPB heat-affected zones which require CVN impact testing

per paragraph NB-4335.2 of the 1977 ASME Code.

Provide CVN impact test data for these heat-

affected zones which may be limiting for

operation of the reactor vessel.

c) Indicate that there are no ferritic RCPB base metals other than in vessels which require

fracture toughness testing to NB-2300 of the

ASME Code. If there are ferritic RCPB base

metals other than in vessels which require 251-1 Rev. 0 WOLF CREEK fracture toughness testing to NB-2300 of the ASME Code, provide CVN impact and drop weight

data for all materials which will be limiting

for operation of the reactor vessel.

RESPONSE See Section 5.3.1.5.

Q251.3 Provide actual pressure-temperature limits for Callaway Unit 1 (Wolf Creek) based upon the limiting

fracture toughness of the reactor vessel material

and the predicted shift in the adjusted reference

temperature, RT NDT , resulting from radiation damage. The pressure-temperature limits for the

following conditions must be included in the

technical specifications when they are submitted.

a) Preservice hydrostatic tests, b) Inservice leak and hydrostatic tests, c) Heatup and cooldown operations, and

d) Core operation.

RESPONSE See the Technical Specifications.

Q251.4 Provide full CVN impact curves for each weld and plate in the beltline region. Provide the data in

tabulated and graphical form.

RESPONSE See Section 5.3.1.5 and Tables 5.3-8 through 11.

Q251.5 To demonstrate the surveillance capsule program complies with Paragraph II.C.3 of Appendix H:

a) Provide the withdrawal schedule for each capsule.

b) Provide the lead factors for each capsule.

c) Indicate the estimated reactor vessel end of life fluence at the 1/4 wall thickness as

measured from the ID. 251-2 Rev. 0 WOLF CREEK RESPONSE See Section 5.3.1.6.

Q251.6 Identify the location of each material surveillance capsule and the materials in each capsule.

a) For each base metal and heat-affected zone surveillance specimen provide the specimen

type, the orientation of the specimen relative

to the principal rolling direction of the

plate, the heat number, the component code

number from which the sample was removed, the

chemical composition especially the copper (Cu)

and phosphorus (P) contents, the melting

practice and the heat treatment received by the

sample material.

b) For each weld metal surveillance specimen provide the weld identification from which the

sample was removed, the weld wire type and heat

identification, flux type and lot

identification, weld process and heat treatment

used for fabrication of the weld sample.

c) Provide a sketch which indicates the azimuthal location for each capsule relative to the

reactor core.

RESPONSE See Section 5.3.1.6.

Q251.7 Indicate the normal operating temperature of the flywheels and provide CVN impact and drop weight

test data from each flywheel that indicates the RT NDT of the flywheels are 100 F less than their normal operating temperatures.

RESPONSE See Section 5.4.1.5.2.2. 251-3 Rev. 0 WOLF CREEK Q260.0 QUALITY ASSURANCE BRANCH Q260.1 Table 17.2-3 and its referenced Appendix 3A should (Table incorporate the following:

17.2-3) Regulatory Guide Rev. Date Appendix 3A Table 17.2-3 1.8 1-R 5/77 OK OK 1.26 2 6/75 Missing Missing

1.29 3 9/78 Missing Missing

1.30 - 8/72 OK OK

1.33 2 2/78 OK OK

1.37 - 3/73 OK OK

1.38 2 5/77 OK OK

1.39 2 9/77 OK OK

1.58 1 9/80 8/73 8/73

1.64 2 6/76 OK OK

1.74 - 2/74 OK OK

1.88 2 10/76 OK OK

1.94 1 4/76 Missing OK

1.116 0-R 5/77 OK OK

1.123 1 7/77 OK OK

1.144 1 9/80 1/79 1/79

1.146 - 8/80 Missing Missing A commitment to 10 CFR 50.55a is also required.

The following is in reference to the KG&E discussion regarding the Regulatory Guide noted.

1.33 The discussion states that the recommendations of R.G. 1.33 are met through the specific ANSI

daughter standards listed in Table 17.2-3.

This could be construed to mean that the

Regulatory Position of R.G. 1.33 is not met

. Clarify.

1.38 The discussion states that KG&E may prescribe protective measures, in lieu of manufacturer's

standards or minimum requirements. The

standard says that the manufacturer's

documented standard or minimum requirements

shall be considered when classifying items, and the point of the discussion regarding this is not clear. Clarify. 260-1 Rev. 0 WOLF CREEK 1.39 The discussion states that KG&E procedures require general housekeeping practices to be

maintained at the station during normal

operations. Describe what is meant by "general housekeeping practices

. 1.74 It is the staff position that certificates of

conformance and certificates of compliance

should be signed by a responsible party from

the certifier's organization. Commit to meet

this position or submit an alternative for our

evaluation.

1.144 a) The first discussion paragraph regarding the classification of certain audit

personnel as lead auditors implies that

all KG&E auditors meet the requirements

for lead auditors. This may require

clarification based on commitment to R.G.

1.146

. b) The first sentence of the second

discussion paragraph is unacceptable. The

staff-position given in Section C.3b.(2) of R.G. 1.144 is a minimum requirement

. More frequent audits, based on status and

importance to safety, are acceptable.

Clarify.

RESPONSE See Table 17.2-3 and Appendix 3A.

Commitments regarding 10 CFR 50.55a are provided in Table 1.3-4.

Q260.2 Provide the qualification requirements for the Manager Quality Assurance. Section 17.2.1.4.1

states that the qualifications of the Manager

Quality Assurance (Site) are at least equivalent to

those specified in ANSI/ANS 3.1. Verify that this

commitment is to the draft standard ANS 3.1 dated

December 6, 1979, and identify the applicable

part(s) of this draft standard.

RESPONSE See Sections 17.2.1.4 and 17.2.1.4.1. 260-2 Rev. 0 WOLF CREEK Q260.3 Describe the significance of the dashed line from (Figure the QC Supervisor and Health Physicist on Figure

13.1-1) 13.1-1. Provide the number of individuals planned

to be assigned to the QC Supervisor shown on Figure

13.1-2.

RESPONSE The revised Quality Organization is described in Section 13.1.2.4 and Figure 13.1-4. The Health Physicist is described in Section 13.1.2.2.4 and Figure 13.1-1.

Q260.4 Provide a commitment that the Manager Quality (17.2.1.4 & Assurance, the Manager Quality Assurance (Site), and

13.1.2.2) the QC Supervisor have not duties or reponsibilities

unrelated to QA that would prevent their full

attention to QA matters. Where is the Manager

Quality Assurance (Site) located?

RESPONSE See Section 17.2.1.4.

Q260.5 Provide a commitment to notify NRC of changes (1)

(17.2.2.3) for review and acceptance in the accepted

description of the FSAR QA program prior to

implementation and (2) in organizational elements

within 30 days after announcement.

RESPONSE See Section 17.2.2.3.

Q260.6 FSAR Revision 1 deleted the statement that Table 3.2-1 of the Standard Plant FSAR is maintained

current by the Manager Nuclear Services with changes

to the table approved by the Manager Quality

Assurance and Manager Nuclear Plant Engineering.

Describe KG&E responsibilities regarding this table

and discuss how these responsibilities are met.

Also, it is not clear how Table 3.2-1 applies during

the operations phase in regards to the column headed

"Quality Assurance." While the Bechtel and

Westinghouse QA programs were applicable during the

design and construction phases, it is not clear how

(or if) KG&E would use these programs during the

operations phase. Clarify.

RESPONSE See Section 17.2.2.2. 260-3 Rev. 14 WOLF CREEK Q260.7 Item 2 on page 17.2-8 is headed "Operating Quality (17.2.2.4 & Assurance Program Manual." Although Table 17.2-1

17.2-1) is titled "Controlled Procedure Manuals," the

Operating Quality Assurance Program Manual is not

identified in the table. Clarify. Also discuss the

Manager Quality Assurance's responsibility regarding

this manual.

RESPONSE The Operating Quality program previously described in the Operating Quality Assurance Program Manual has been replaced by certain Directives contained in

the Wolf Creek Project Policy Manual. See Table 17.2-1a.

Q260.8 Section 17.2.0.3 indicates that computer codes are (17.2.2) controlled by the OQAP. Describe how the QA program

will be applied. Include a description of related

organizational responsibilities for internal and

external efforts.

RESPONSE See revised Section 17.2.0.3.

Q260.9 Section 17.2.2.6 of the Wolf Creek FSAR discusses (17.2.2) verification of QA program implementation through

audits. Provide a commitment that KG&E management

above the QA organization maintains frequent contact

with the QA program through meetings and reports, including review of audit reports. Verify that in

this way, and through preplanned and documented

annual assessments, this management regularly

assesses the scope, status, adequacy, and compliance

of the QA program to 10 CFR Part 50 Appendix B.

RESPONSE See Section 17.2.1.9.

Q260.10 The second sentence in Section 17.2.3.3 states that (17.2.3) design changes shall be communicated to appropriate

plant personnel when such changes may affect

performance. Clarify that this means each

individual's performance of his duties.

RESPONSE See Section 17.2.3.7. 260-4 Rev. 0 WOLF CREEK Q260.11 Provide a commitment that action to correct errors (17.2.3) found in design process and action to assure control

of changes are documented.

RESPONSE See Section 17.2.3.6.

Q260.12 Clarify the first sentence of Section 17.2.3.3 which (17.2.3) states: "Design requirements and changes thereto

shall be...so that deviations from quality standards remain visible throughout the design process." (Underline added.)

RESPONSE See Section 17.2.3.3.

Q260.13 Section 17.2.3.5 indicates KG&E procedures will con-(17.2.3) trol design interfaces. Describe the controls.

RESPONSE See Section 17.2.3.5.

Q260.14 Section 17.2.3.6 of the Wolf Creek FSAR states:

(17.2.3) "Design verification shall be performed by personnel

other than those who performed the original design

and shall be accomplished prior to relying upon the

component, system, or structure to perform its

function." Concerning the personnel, provide a

commitment that the verifier is qualified and is not

directly responsible for the design or design change

(i.e., neither the designer nor his immediate

supervisor). Concerning the timing, provide a

commitment that design verification is normally

completed prior to release for procurement, manufacture, or installation or to another

organization for use in other design activities.

Where this timing cannot be met, justification for

deferral should be documented and the unverified

portion should be identified and controlled.

Include such a commitment.

RESPONSE See Section 17.2.3.6. 260-5 Rev. 0 WOLF CREEK Q260.15 In the area of design verification, clarify that (17.2.3) procedures identify the responsibilities of the

verifier, the areas and features to be verified, the

pertinent considerations to be verified, and the

documentation required. Also provide a commitment

that specialized reviews are used when uniqueness or

special design considerations warrant.

RESPONSE See Sections 17.2.3.1 and 17.2.3.6.

Q260.16 Clarify that design documents subject to procedural (17.2.3) control include, but are not limited to, specifications, calculations, computer programs, system descriptions, SAR when used as a design

document, and drawings including flow diagrams, piping, and instrument diagrams, control logic

diagrams, electrical single line diagrams, structural systems for major facilities, site

arrangements, and equipment locations.

RESPONSE See Section 17.2.3.4.

Q260.17 Provide a commitment that supplier QA programs are (17.2.4) reviewed and found acceptable by KG&E's QA

organization before initiation of activities

affected by the program.

RESPONSE See Section 17.2.4.5.

Q260.18 Section 17.2.4.2 indicates KG&E's Quality Assurance (17.2.4) Department is responsible for quality requirements

for procurement. Verify that the QA Department

review of procurement documents determines that the

quality requirements are correctly stated, inspectable, and controllable; that there are

adequate accept/reject criteria; and that the

procurement documents have been prepared, reviewed, and approved in accordance with KG&E's QA program

requirements.

RESPONSE See Section 17.2.4.5. 260-6 Rev. 0 WOLF CREEK Q260.19 Section 17.2.6.2 of the Wolf Creek FSAR identifies (17.2.6) the types of documents which are controlled. Expand

this list such that it includes the following:

a) Other design documents (e.g., calculations and analyses) including documents related to

computer codes.

b) Instructions and procedures for such activities as fabrication, construction, modification, installation, test, and inspection.

c) As-built drawings.

d) Wolf Creek Project Policy Manual.

e) Wolf Creek Generating Station Procedures Manuals.

f) KG&E Procedures Manual.

g) FSAR.

h) Topical reports.

RESPONSE See Section 17.2.6.2.

Q260.20 Discuss the role of the quality assurance organiza-(17.2.6) tion in the review of and concurrence with documents

under the control of the quality assurance program

regarding the QA-related aspects.

RESPONSE See Sections 17.2.2.2, 17.2.4.5, 17.2.6.6 and 17.2.7.7. Other review and approval activities conducted by the Quality Branch are described in the

following Sections: 17.2.1.6, 17.2.2.5, 17.2.3.3, 17.2.4.4, 17.2.4.7, 17.2.4.11, 17.2.5.5, 17.2.7.2, 17.2.7.3, 17.2.7.6, 17.2.7.10, 17.2.9.2, 17.2.9.3, 17.2.10.2, 17.2.10.6, 17.2.15.2, 17.2.18.4, and 17.2.18.9.

Q260.21 Provide a commitment that the quality assurance (17.2.6) organization reviews and concurs with instructions

and procedures used for maintenance, modification, and inspection at Wolf Creek to determine, 260-7 Rev. 0 WOLF CREEK a) The need for inspection, identification of inspection personnel, and documentation of

inspection results.

b) That the necessary inspection requirements, methods, and acceptance criteria have been

identified.

RESPONSE See Section 17.2.6.6.

Q260.22 Section 17.2.7.7 of the Wolf Creek FSAR addresses (17.2.7) supplier monitoring in accordance with procedures.

Verify that the procedures are documented, that they

assure conformance to the purchase document

requirements, that they identify organizational

responsibilities, and that they specify the

characteristics or processes to be witnessed, inspected, or verified, and accepted, the method of

surveillance, and the documentation required.

Clarify that the procedures are reviewed and

approved by the quality assurance organization.

RESPONSE See second paragraph of Section 17.2.7.7.

Q260.23 Provide a commitment that the bases of supplier (17.2.7) selection is documented and filed. Also clarify

that when an LCVIP letter of confirmation or the

CASE register is used to establish a supplier's

qualification, the documentation will identify the

"letter" or "audit" used.

RESPONSE See Section 17.2.7.2.

Q260.24 Provide a commitment that procurement of spare or (17.2.7) replacement parts for safety-related structures, systems, and components is subject to present QA

program controls, to applicable codes and standards, and to technical requirements equal to or better

than the original technical requirements, or as

required to preclude repetition of defects. 260-8 Rev. 0 WOLF CREEK RESPONSE See Section 17.2.4.11.

Q260.25 Provide a commitment that suppliers' certificates of (17.2.7) conformance are periodically evaluated by audits, independent inspections, or tests to assure they are

valid.

RESPONSE See Section 17.2.7.10.

Q260.26 Section 17.2.7.6 states that the extent of accept-(17.2.7) ance methods and associated verification activities

will vary as a function of the relative importance

and complexity of the purchased item or service and

the supplier's past performance. It is the staff's

position that the extent of quality verification

should also reflect the item's or service's

importance to safety or relative safety importance.

Section 17.2.7.6 then goes on to state that procedures will provide for the acceptance of

simple, off-the-shelf items based exclusively on

receiving inspection with no quality verification

documentation requirements. It is the staff's

position that the involved design engineering

organization and quality assurance organization

should jointly determine the extent of inspection

verification and the quality verification

documentation requirements based on the item's end

use.

Revise the FSAR to reflect this position.

RESPONSE See Section 17.2.7.6.

Q260.27 Describe the involvement of KG&E's QA and QC organizations in the acceptance of items by post-

installation test.

RESPONSE See Section 17.2.7.6.

Q260.28 Describe the involvement of KG&E's QA and QC organi-(17.2.7) zations in the final acceptance of service. 260-9 Rev. 0 WOLF CREEK RESPONSE See Section 17.2.7.10.

Q260.29 Describe the involvement of KG&E's QA and QC organi-(17.2.9) zations in the control of special processes.

RESPONSE See 17.2.9.2 and 17.2.9.3.

Q260.30 Expand the list of processes given in (17.2.9) Section 17.2.9.1 of the Wolf Creek FSAR so that the

list is as complete as possible.

RESPONSE See Section 17.2.9.1.

Q260.31 Describe measures which assure the recording of evi-(17.2.9) dence of acceptable accomplishment of special

processes using only qualified procedures, equipment, and personnel.

RESPONSE See Section 17.2.9.2.

Q260.32 Identify the KG&E organization(s) responsible for (17.2.9.1) qualifying special process equipment and for

maintaining the qualification of such equipment.

Discuss the records associated with qualifying

special process equipment.

RESPONSE See Section 17.2.9.2.

Q260.33 It is not clear that KG&E personnel who perform (17.2.10) inspections and process monitoring are part of the

QC organization under the QC Supervisor. Clarify.

Since QA personnel do not perform inspections and

process monitoring, provide a commitment that

procedures, personnel qualification criteria, and

personnel independence from undue pressure of cost

and schedule are reviewed and found acceptable by

the QA organization prior to initiating the

inspection or monitoring. 260-10 Rev. 0 WOLF CREEK RESPONSE See Section 17.2.10.

Q260.34 Section 17.2.10b of the Wolf Creek FSAR indicates (17.2.10 & that inspections and NDE may be accomplished by

17.2.11) "outside organizations." Describe how KG&E assures

acceptable inspection/NDE procedures, qualification

of the inspection/NDE personnel, and independence

from undue cost and schedule pressures for these

outside organizations. Provide the same information

for testing activities performed by outside

organizations.

RESPONSE See Sections 17.2.4 and 17.2.7.

Q260.35 Provide a commitment that procedures specify cri-(17.2.11) teria for determining when a test is required or how

and when tests are performed.

RESPONSE See Section 17.2.11.2.

Q260.36 The description of the control of measuring and test (17.2.12) equipment in Section 17.2.12.2 of the Wolf Creek

FSAR includes the following sentence: "Permanently

installed process instrumentation is not included in

this listing" (of controlled equipment). Describe

the QA controls over permanently installed process

instrumentation and discuss the differences between

these controls and the controls described in Section

17.2.12.

RESPONSE See Section 17.2.12.3.

Q260.37 Provide a commitment that measuring and test equip-(17.2.12) ment is labeled or tagged to indicate the due date

of the next calibration.

RESPONSE See Section 17.2.12.3.

Q260.38 Discuss the documentation and management authoriza-(17.2.12) tion required by KG&E when: 260-11 Rev. 0 WOLF CREEK a) M&TE cannot be calibrated against standards that have an accuracy at least four times the

required accuracy of the M&TE.

b) Calibrating standards do not have greater accuracy than standards being calibrated.

RESPONSE See Section 17.2.12.3 and 17.2.12.4.

Q260.39 Section 17.2.13.2 states that storage procedures may (17.2.13) prescribe requirements "in lieu of" requirements

contained in the manufacturer's recommendations. It

appears that "supplementary to" or "in addition to" would be more appropriate than "in lieu of".

Clarify.

RESPONSE See Section 17.2.13.2.

Q260.40 Describe provisions the storage of chemicals, (17.2.13) reagents (including control of shelf life),

lubricants, and other consumable materials.

RESPONSE See Section 17.2.13.2

Q260.41 Describe how KG&E controls the application and (17.2.14) removal of inspection stamps, welding stamps, and

status indicators such as tags, markings, labels, and other stamps.

RESPONSE See Section 17.2.14.2.

Q260.42 Section 17.2.14.4 states that KG&E will control the (17.2.14) sequence of tests, inspections, and other operations

in accordance with administrative procedures.

Describe the procedure for such control. Such

actions should be subject to the same controls as

the original review and approval.

RESPONSE See Section 17.2.14.4. 260-12 Rev. 0 WOLF CREEK Q260.43 Clarify what is meant by the statement in 17.2.14.3 (17.2.14) that procedures shall address methods for

"initiating, maintaining, and releasing equipment

control for maintenance, etc..." RESPONSE The second sentence of Section 17.2.14.3 has been revised for clarity.

Q260.44 Clarify Section 17.2.15.1 of the Wolf Creek FSAR (17.2.15) that nonconformances also include inoperative and

malfunctioning structures, systems, and components.

RESPONSE See Section 17.2.15.1.

Q260.45 Describe QA controls over conditionally released (17.2.15) nonconforming items. Identify reinspection criteria

for repaired and reworked items and indicate how

reinspection requirements and performance are

documented. Identify individuals (by position

title) or groups with authority to disposition

nonconformances. Identify the individual (by

position title) or group that performs the trend

analysis discussed in Section 17.2.15.7.

RESPONSE See Sections 17.2.15.2 and 17.2.15.7.

Q260.46 Provide commitment that nonconformances are cor-(17.2.15) rected or resolved prior to initiation of the

preoperational test program on the item.

RESPONSE See Section 17.2.15.2.

Q260.47 Discuss the timeliness of actions taken to close out (17.2.16) CARs and the followup action.

RESPONSE See Section 17.2.16.3.

Q260.48 Discuss the "surveillance" portion of the KG&E audit (17.2.18) system as mentioned in Section 17.2.18.1 of the

FSAR. 260-13 Rev. 0 WOLF CREEK RESPONSE See Section 17.2.18.1.

Q260.49 Section 17.1.2.2 of the standard format (Regulatory Guide 1.70) requires the identification of safety-

related structures, systems, and components

controlled by the QA program. You are requested to

supplement and clarify Table 3.2-1 of the Wolf Creek

FSAR in accordance with the following:

a) The following items do not appear on FSAR Table 3.2-1. Add the appropriate items to the table

and provide a commitment that the remaining

items are subject to the pertinent requirements

of the FSAR operational quality assurance

program or justify not doing so.

a.1 Safety-related masonry walls (IE Bulletin 80-11).

RESPONSE There are no safety-related masonry walls utilized in the Wolf Creek design.

Q260.49a.2 Biological shielding within the fuel building, auxiliary building, control building, and reactor

building.

RESPONSE Permanent biological shielding is constructed as part of safety- related buildings (refer to Section 8.1 and Table 3.2-1). Also see Section 12.1.4.

Q260.49a.3 Missile barriers within the fuel building, auxiliary building, control building, diesel-generator

building, essential service water pump house.

RESPONSE See Table 3.2-1, Sections 3.0 and 8.1. Also, permanent shields are part of the structures identified in Section 8.1 of Table 3.2-1.

Q260.49a.4 Spent fuel pool liner. 260-14 Rev. 0 WOLF CREEK RESPONSE See Table 3.2-1 and Section 8.2. (This item is not safety- related).

Q260.49a.5 Refueling machine.

RESPONSE See Table 3.2-1 and Section 3.0.

Q260.49a.6 Spent fuel handling tool.

RESPONSE See Table 3.2-1 and Section 3.0.

Q260.49a.7 Radiation shielding doors.

RESPONSE See Table 3.2-1 and Section 8.2. (This item is not safety- related.) Also see Section 12.1.4.

Q260.49a.8 Radiation monitoring (fixed and portable).

RESPONSE It is the Operating Agent's position that items 8-16 of Q260.49 (a) should not be included in Table 3.2-1, or be subject to the requirements of the

operational Quality program. See Section 12.1.4.

Q260.49a.9 Radioactivity monitoring (fixed and portable).

RESPONSE Refer to a.8 above.

Q260.49a.10 Radioactivity sampling (air, surfaces, liquids).

RESPONSE Refer to a.8 above.

Q260.49a.11 Radioactive contamination measurement and analysis. 260-15 Rev. 0 WOLF CREEK RESPONSE Refer to a.8 above.

Q260.49a.12 Personnel monitoring internal (whole body counter) and external (TLD system).

RESPONSE Refer to a.8 above.

Q260.49a.13 Instrument storage, calibration, and maintenance.

RESPONSE Refer to a.8 above.

Q260.49a.14 Decontamination (facilities, personnel, equipment).

RESPONSE Refer to a.8 above.

Q260.49a.15 Respiratory protection, including testing.

RESPONSE Refer to a.8 above.

Q260.49a.16 Contamination Control.

RESPONSE Refer to a.8 above.

Q260.49a.17 Radiation shielding (permanently installed).

RESPONSE Refer to a.2 above.

Q260.49a.18 Accident-related meteorological data collection equipment.

RESPONSE See Sections 2.3.3.2.3 and 2.3.3.5.1. 260-16 Rev. 0 WOLF CREEK Q260.49a.19 Expendable and consumable items necessary for the functional performance of safety-related structures, systems, and components (weld rod, fuel oil, boric

acid, snubber oil, etc.)

RESPONSE See Section 17.2.13.2.

Q260.49a.20 Roof drains and parapets of buildings which house safety-related equipment.

RESPONSE See Section 2.4.2.3.

Q260.49a.21 Site drainage system including grading, culverts, and channels.

RESPONSE See note 14 of Table 3.2-1 and Section 2.4.2.2.

Q260.49a.22 Steam generators (primary and secondary).

RESPONSE See Table 3.2-1 and Section 1.1.

Q260.49a.23 Steam generator piping located inside containment.

RESPONSE See Sections 5.1 and 5.2 of Table 3.2-1.

Q260.49a.24 Valve operators for all safety-related valves.

RESPONSE Valve operators are considered part of each safety-related valve. See Table 3.2-1 and fourth paragraph of Section 3.2.

Q260.49a.25 Motors for all safety-related pumps.

RESPONSE Motors are considered part of each safety-related pump. See Table 3.2 and the fourth paragraph of Section 3.2. 260-17 Rev. 0 WOLF CREEK Q260.49 b) The following items from FSAR Table 3.2-1 need expansion and/or clarification as noted.

Revise the list as indicated or justify not

doing so.

1) Identify the safety-related instrumentation and control systems to the

same scope and level of detail as provided

in Chapter 7 of the FSAR. (This can be

done by footnote). Verify that this

includes I & C for:

Q260.49b.1(a) Containment spray system.

RESPONSE See Section 1.5 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49b.1(b) Containment cooling system.

RESPONSE See Section 1.6 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49b.1(c) Containment hydrogen control system.

RESPONSE See Section 1.8 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49b.1(d) Containment pressure indication.

RESPONSE See Section 9.0 of Table 3.2-1 and the fourth paragraph of USAR Section 3.2.

Q260.49b.1(e) Containment water level indication.

RESPONSE See Section 9.0 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49b.1(f) Containment hydrogen indication. 260-18 Rev. 0 WOLF CREEK RESPONSE See Section 1.8 of Table 3.2-1 and the fourth paragraph of USAR Section 3.2.

Q260.49b.2 For the systems shown below, expand the list in Table 3.2-1 to include the indicated components

under the pertinent 10 CFR 50 Appendix B quality

assurance requirements or verify that they are

included as part of the components already listed.

Q260.49b.2.1.5 Containment spray system containment sump.

RESPONSE See Section 8.1 of Table 3.2-1.

Q260.49b.2.1.6 Containment cooling system ductwork.

RESPONSE See Section 1.6 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49b.2.1.8 Containment hydrogen control system piping and valves.

RESPONSE See Section 1.8 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49c Enclosure 2 of NUREG-0737, "Clarification of TMI Action Plan Requirements" (November 1980)

identified numerous items that are safety-

related and appropriate for OL application and

therefore should be on Table 3.2-1. These

items are listed below. Add appropriate items

to Table 3.2-1 and provide a commitment that

the remaining items are subject to the

pertinent requirements of FSAR operational QA

program or justify not doing so.

Q260.49c.1 Plant safety-parameter display console. 260-19 Rev. 0 WOLF CREEK RESPONSE See Section 9 of Table 3.2-1.

Q260.49c.2 Reactor coolant system vents.

RESPONSE See Section 1.1 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49c.3 Plant shielding.

RESPONSE Refer to a.2 above.

Q260.49c.4 Post accident sampling capabilities.

RESPONSE The equipment used for inplant post-accident sampling is not safety-related and therefore is not included in Table 3.2-1. However, the portions of the system

which are involved in maintaining containment integrity are procured and

installed as safety-related equipment. See Section 1.7 of Table 3.2-1 and

Section 12.1.4 and 8.1.

Q260.49c.5 Valve position indication.

RESPONSE Position indication of each pressurizer safety valve and PORV is considered part of the valve. Therefore, this is included in Section 1.1 of Table 3.2-1

and see fourth paragraph of Section 3.2.

Q260.49c.6 Auxiliary feedwater system.

RESPONSE See Section 5.4 of Table 3.2-1.

Q260.49c.7 Auxiliary feedwater system initiation and flow. 260-20 Rev. 0 WOLF CREEK RESPONSE See Section 5.4 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49c.8 Emergency power for pressurizer heaters.

RESPONSE See Section 1.1 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49c.9 Dedicated hydrogen penetrations.

RESPONSE Not applicable to Wolf Creek.

Q260.49c.10 Containment isolation dependability.

RESPONSE See Section 1.7 of Table 3.2-1.

Q260.49c.11 Accident monitoring instrumentation.

RESPONSE See Section 9.0 of Table 3.2-1.

Q260.49c.12 Instrumentation for detection of inadequate core-cooling.

RESPONSE See the fourth paragraph of Section 3.2.

Q260.49c.13 Power supplies for pressurizer relief valves, block valves, and level indicators.

RESPONSE See Section 1.1 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49c.14 Automatic PORV isolation. 260-21 Rev. 0 WOLF CREEK RESPONSE See Section 1.1 of Table 3.2-1 and the fourth paragraph of Section 3.2.

Q260.49c.15 Automatic trip of reactor coolant pumps.

RESPONSE Not applicable to Wolf Creek.

Q260.49c.16 PID controller.

RESPONSE Not functional in Wolf Creek design.

Q260.49c.17 Anticipatory reactor trip on turbine trip.

RESPONSE See Section 9.0 of Table 3.2-1 for the Reactor Protection System. The remainder of the system is non-IE but meets special criteria as defined in Section

7.2.1.1.2.f.

Q260.49c.18 Power on pump seals.

RESPONSE Included as part of Section 2.3 of Table 3.2-1.

Q260.49c.19 Emergency plans (and related equip).

RESPONSE Emergency plans are not systems, structures or components, are not considered safety-related and are therefore not included in Table 3.2-1. However, Emergency Plan effectiveness is verified through periodic drills and exercises

as described in the Emergency Plans.

Q260.49c.20 Equipment and other items associated with the emergency support facilities.

RESPONSE These are not considered safety-related and are therefore not included in Table 3.2-1. However, periodic checks of radiation measurement and communication

equipment is required by written procedure. Appropriate engineering and

reference documents (i.e., 260-22 Rev. 0 WOLF CREEK FSAR, prints, procedure manuals) will be placed in Wolf Creek emergency response facilities. The controls and update of reference documents will be

handled in accordance with procedures. Emergency procedures will be subject to

audit by individuals who are not directly responsible for procedure

implementation. See Emergency Plans and Procedures.

Q260.49c.21 In-plant I 2 radiation monitoring.

RESPONSE Inplant iodine monitoring is not considered safety-related and is therefore not included in Table 3.2-1. Provisions for monitoring of inplant iodine levels

are incorporated within the scope of the Wolf Creek Health Physics Manual and

procedures as described in Section 12.1.4.

Q260.49c.22 Control room habitability.

RESPONSE See Section 7.1 of Table 3.2-1. 260-23 Rev. 0 WOLF CREEK Q270.1 Correlate the systems listed in Table 3.2-1 of the (SRP 3.11) FSAR with the systems listed in Appendix B of the

environmental qualification (EQ) program submittal

of March 10, 1983. Provide justification for any

system listed in Table 3.2-1 which is excluded from

Appendix B (e.g., all components of the system are

located in a mild environment, etc.). Identify the

Class 1E function for all systems in Appendix B.

RESPONSE Comparing Table 3.2-1 (USAR) to Appendix B (submittal) is inappropriate since the two listings were developed to different criteria and for different

purposes.It should also be noted that the listing of Appendix B includes all systems receiving Class 1E electrical power. No systems have been deleted due to their

location (e.g., in a mild environment) as indicated by your questions.

Three systems identified in Appendix B are listed only because some portion of the system provides electrical isolation. The system identifiers are PN, RJ, and RK. These systems do not have any other Class 1E function. Note 1 of

Appendix B clearly identifies this fact. Accordingly, no "X"s are provided for

these systems.

Q270.2 Identify, by categories listed in NUREG-0737, the (SRP 3.11) components included in the qualification program in

response to TMI Action Plan Requirements.

RESPONSE See Section 3.11(B).1 and 18.0. It should be noted that much of the equipment required to satisfy NUREG-0737 concerns already existed in the plant design.

Q270.3 The description of the criteria used for establish-(SRP 3.11) ing environmental qualification does not reference

Section II.B.2 of NUREG-0737 as the basis for

establishing radiation dose from recirculating

fluids. Discuss your compliance with the

recommendations of this section of the Action Plan.

RESPONSE Section 18.2.2 discusses in detail the WCGS position concerning Section II.B.2 of NUREG-0737.

270-1 Rev. 0 WOLF CREEK Q270.4 Provide a statement that 1E equipment located in (SRP 3.11) areas which experience a significant increase in

radiation during a LOCA has been reviewed for

possible damage to solid state devices.

RESPONSE See Section 3.11(B).1 and 3.11(B).2.1.f.

Q270.5 Section 8.11 of the March 10, 1983 EQB program sub-(SRP 3.11) mittal indicates a minimized coverage of synergistic

effects. Discuss what activity will be undertaken

to identify known synergistic effects and how these

will be factored into the EQ program.

RESPONSE See Section 3.11(B).5.8.

Q270.6 To demonstrate compliance with 10 CFR 50.49, (10 CFR 50.49) the following information must be submitted

before an operating license is granted:

a) In accordance with the scope defined in 10 CFR 50.49, provide:

- A list of all nonsafety-related electrical equipment located in a harsh

environment whose failure under

postulated environmental conditions

could prevent satisfactory

accomplishment of safety functions by

the safety-related equipment. A

description of the method used to

identify this equipment must be

included. The nonsafety-related

equipment identified must be included in

the environmental qualification program.

- A statement that all safety-related electric equipment in a harsh

environment, as defined in the scope of

10 CFR 50.49, is included in this list

of equipment identified in the March 10, 1983 submittal (including equipment

required for MELB, spent fuel rod drop

accident, etc.).

270-2 Rev. 0 WOLF CREEK

- A list of all Category 1 and 2 post-accident monitoring equipment currently

installed, or to be installed before

plant operation, in response to

Regulatory Guide 1.97, Revision 2. The

equipment identified must be included in

the environmental qualification program.

b) Provide information demonstrating qualification of all equipment in a harsh

environment within the scope of 10 CFR

50.49, or provide justification for

interim operation pending completion of

qualification as required by 10 CFR

50.49. This material should be submitted

to allow sufficient time for staff review

and approval before issuance of an

operating license.

RESPONSE a) The WCGS design is based on utilizing only Class 1E powered electrical equipment to mitigate the consequences of the units

identified in Section 2.3 of the submittal. See USAR Section

3.11(B).1 and Question 720.3 for additional information.

- Section 2.0 identifies that Appendix A includes all safety-related electrical equipment, regardless of the accident

that required the equipment to be categorized as Class 1E.

No Class 1E equipment is excluded from the list due to

location or any other reason.

- Appendix 7A of the USAR identifies the WCGS position on Regulatory Guide 1.97. A categorized list of equipment is

included in Appendix 7A. Section 8.2 of the submittal

references the FSAR response and indicates that all

Regulatory Guide 1.97 Category 1 instruments are included in

the listing of Appendix A of the submittal. Additionally, all Category II electrical components powered by a Class 1E

power source (as shown in Appendix A of the USAR) are also

included.

b) Please refer to the submittal transmittal letter (SLNRC 83-0015, dated March 10, 1983) which states "...corrective

actions will be taken to establish equipment qualification

prior to fuel loading or justification will be provided for

interim operation until corrective actions are completed."

This information was submitted. See Section 3.11(B).3.

270-3 Rev. 0 WOLF CREEK Q270.7 Indicate your compliance with a one hour time margin (SRP 3.11) for equipment with operability times less than 10

hours, or provide justification for reduced margins.

RESPONSE See Section 3.11(B).5.2.

Q270.8 Before the Safety-Related Mechanical (SRM) equipment (SRP 3.11) audit items can be selected, you must indicate the

qualification status of the SRM equipment. If

qualification is not complete, briefly describe the

tasks to be performed. Provide a list of SRM

equipment which is considered qualified from which

audit items can be selected. Your review of

equipment should be essentially complete before

items are selected.

RESPONSE The Operating Agent considers the safety-related mechanical equipment to be qualified for its intended use. See Section 3.11(B).6.

Q270.9 Table I Master Qualification Summary,Section II of (SRP 3.11) the March 10, 1983 submittal, indicates that the

qualification status has not been determined for 16

out of 74 qualification packages (3 packages -

review is in progress, 13 packages - review has not

started). The Equipment Qualification Branch

considers the review incomplete until at least 85%

of all equipment items have been categorized.

RESPONSE This information was provided prior to receipt of the Operating License. See Section 3.11(B).6.

Q270.10 A number of Qualification Summary Sheets state that (SRP 3.11) qualification documentation is auditable but is

incomplete, yet the equipment is considered

qualified. Please explain this apparent

contradiction.

RESPONSE There is no contradiction involved. At the time the question was originally asked, when the submittal indicated that specific equipment documentation was

auditable but incomplete and the equipment was considered qualified, then one

of two conditions 270-4 Rev. 0 WOLF CREEK existed. Either a) the majority of the information was submitted and reviewed and the remaining documentation was considered proprietary, but the content was

known and was at the vendor's facility available for audit, or b) the majority

of the information was submitted and reviewed and the remaining documentation

would only enhance the existing documentation. In either case, the vendor was

contacted to determine the content of the missing information before the

equipment was considered qualified.

It should also be noted that a review of the qualification summaries indicated only one case in which the documentation was incomplete, but the equipment was

considered qualified. The incomplete documentation was an enhancement, but the

vendor was requested to supply the documentation. The appropriate

documentation has been received, and Revision 1 of the qualification summary

has been changed to reflect the documentation being complete.

Q270.11 The justification given to reconcile test failures, (SRP 3.11) tests not performed and inconsistencies between test

parameter levels and plant requirements seem

strained in a number of instances (e.g., E028, E029, E093, E062, M 223A, etc.). Please review the basis

for determining qualification and, if appropriate, strengthen the justifications or re-evaluate the

qualification status.

RESPONSE Specifications E028 and E093 are not considered qualified. Accordingly, the qualification summaries for these specifications do not indicate that they

are qualified. For the remaining identified specifications (and all others),

it should be noted that only the summary is submitted. Additional data leading

to the conclusion reached is available in the associated utility files. Due to

the extensive conservatism built into the qualification review program, we feel

that the justifications are not strained. No changes of qualification status

are necessary.

Q270.12 Provide an example of the equipment surface tempera-(SRP 3.11) ture calculations referenced in Section 6.2.2 of the

EQ submittal which allows credit for specific

equipment surface temperature response for MSLB

environments.

RESPONSE See Section 3.11(B).1.

270-5 Rev. 0 WOLF CREEK Q270.13 Provide an example of the equipment specific (SRP 3.11) analysis referenced in Section 6.3.1 of the EQ

submittal to demonstrate how radiation dose

reductions were obtained.

RESPONSE See Section 3.11(B).1.2.3.

Q270.14 Provide information on the specific maintenance/(SRP 3.11) surveillance programs to be applied to 1) Cables

located inside containment, 2) Limitorque valve

operators, 3) Amphenol electrical penetrations, 4)

Motor control center relays and circuit breakers, and 5) Barton pressure transmitters.

RESPONSE See 3.11(B).5.6.

Q270.15 The temperature profiles shown for postulated HELBs (SRP 3.11) outside containment do not meet the screening

criterion of saturation temperature at the

calculated pressure. Please provide an example of

the analysis used to determine the environmental

conditions resulting from a line break outside

containment.

RESPONSE See Section 3.11(B)-1.

Q270.16 The applicant is requested to identify the systems (SRP 3.11) listed in FSAR Table 3.2-1 which include

Instrumentation and Control (I&C) equipment. This

may be done by modifying Table 3.2-1 to include

Instrumentation and Control as subsets or portions

of the systems identified.

RESPONSE See Note 14 of Table 3.2-1.

Q270.17 Describe the criteria used to determine the I&C (SRP 3.11) systems and components important to safety to be

covered by the equipment qualification program.

270-6 Rev. 0 WOLF CREEK RESPONSE See response to Question 270.6 (a). Additionally, USAR Section 7.1.1, Identification of Safety-Related Systems, identifies the criteria for the

selection of I&C equipment as being safety related.

Q270.18 Describe the method used to identify each specific (SRP 3.11) I&C component covered.

RESPONSE See Note 14 of Table 3.2-1.

270-7 Rev. 0 WOLF CREEK Q271.1 In accordance with the requirements of GDC 2 and 4 all safety-related equipment is required to be

designed to withstand the effects of earthquakes and

dynamic loads from normal operation, maintenance, testing and postulated accident conditions. GDC 2

further requires that such equipment be designed to

withstand appropriate combinations of the effects of

normal and accident conditions with the effects of

earthquake loads.

The criteria to be used by the staff to determine the acceptability of your equipment qualification

program for seismic and dynamic loads are IEEE Std.

344-1975 as supplemented by Regulatory Guides 1.100

and 1.92, and Standard Review Plan Sections 3.9.2, 3.9.3 and 3.10. State the extent to which the

equipment in your plant meets these requirements and

the above requirements to combine seismic and

dynamic loads. For equipment that does not meet

these requirements justification will be needed for

the use of other criteria.

RESPONSE All safety-related equipment is designed to withstand the effects of earthquake and dynamic loads. The extent to which the powerblock equipment meets the

requirements of the questioned documents is provided in the USAR Sections

referenced below.

IEEE Std. 344-1975: 3.10(B), 3.10(N)

Regulatory Guide 1.100: 3.10(B), Appendix 3A

Regulatory Guide 1.92: Appendix 3A, 3.7(B), 3.7(N)

Standard Review Plan (SRP) 3.9.2: 3.9.2(B), 3.9.2(N)

SRP 3.9.3: 3.9.3(B), 3.9.3(N)

SRP 3.10: 3.10(B), 3.10(N)

In addition, the extent to which powerblock equipment meets the recommendations of Regulatory Guide 1.29, "Seismic Design Classification" is provided in

Section 3.2 and Appendix 3A.

271-1 Rev. 0 WOLF CREEK Q271.2 To confirm the extent to which the equipment impor-(271.3) tant to safety meets the requirements of General

Design Criterion 2 and 4, the Seismic Qualification

Review Team (SQRT) will conduct a plant site

review. For selected equipment, SQRT will review

the combined required response spectra (RRS) or the

combined dynamic response, examine the equipment

configuration and mounting, and then determine

whether the test or analysis which has been

conducted demonstrates compliance with the RRS if

the equipment was qualified by test, or the

acceptable analytical criteria if qualified by

analysis.

In order to select equipment types for a detailed review it is necessary to obtain a list of all equipment important to safety. Equipment should be divided first by system then by component type.

Attachment #1 shows a tabular format which should be

followed to present the status summary of seismic

and dynamic qualification of all equipment important

to safety. Attachment #2 shows suggested categories

of component type to be listed in Attachment #1.

Provide a complete set of floor response spectra

identifying their applicability to the equipment

listed in Attachment #1.

After the information on Attachment #1 is received, a selection will be made of the equipment to be

reviewed by the site audit. Specific information on

equipment selected for audit should be presented as

shown on Attachment #3 which should be provided to

the NRC staff two weeks prior to the plant site

visit. The applicant should make available at the

plant site for SQRT review all the pertinent

documents and reports of the qualification of the

selected equipment. After the visit, the applicant

should be prepared to submit certain selected

documents and reports for further staff review.

The purpose of the site audit is to confirm the acceptability of the seismic and dynamic

qualification of all equipment important to safety

based on the review of a few selected pieces. If a

number of deficiencies are observed or significant

generic concerns arise, the deficiencies should be

removed for all equipment important to safety subject to confirmation by a follow-up audit of

randomly selected items before the fuel loading

date.

271-2 Rev. 0 WOLF CREEK RESPONSE A list of all safety-related equipment was provided to the NRC by SLNRC 82-06 dated February 4, 1982. The list was updated by SLNRC 83-026 dated May 9, 1983. 271-3 Rev. 0 WOLF CREEK Q280.1 Provide a table that lists all equipment including instrumentation and vital support system equipment

required to achieve and maintain hot and/or cold

shutdown. For each equipment listed:

a) Differentiate between equipment required to achieve and maintain hot shutdown and equipment

required to achieve and maintain cold shutdown, b) Define each equipment's location by fire area, c) Define each equipment's redundant counterpart, d) Identify each equipment's essential cabling (instrumentation, control, and power). For

each cable identified: (1) Describe the cable

routing (by fire area) from source to

termination, and (2) Identify each fire area

location where the cables are separated by less

than a wall having a three-hour fire rating

from cables for any redundant shutdown system, and e) List any problem areas identified by item 1.d.(2) above that will be corrected in

accordance with Section III.G.3 of Appendix R

(i.e., alternate or dedicated shutdown

capability).

RESPONSE The final fire hazards analysis, USAR Appendix 9.5B, identifies all redundant post-fire safe shutdown components and circuits on a fire area by fire area basis, and demonstrates that either the required separation exists or that alternate means are available to perform the safe shutdown function.

Section 7.4 provides a safe shutdown discussion and lists of systems and components required for hot standby and cold shutdown.

Table 3.11(B).3, identifies all the equipment required for safe shutdown, differentiates between hot and cold shutdown requirements, and identifies the

location of each component.

Q280.2 Provide a table that lists Class 1E and Non-Class 1E cables that are associated with the essential safe

shutdown systems identified in item 1 above. For

each cable listed: (*Note).

  • NOTE Option 3a is considered to be one method of meeting the requirements of Section II.G.3 Appendix R. If option 3a is selected the information requested in items

2a and 2c above should be provided in general terms and the information

requested by 2b need not be provided.

280-1 Rev. 14 WOLF CREEK a) Define the cables' association to the safe shutdown system (common power source, common

raceway, separation less than IEEE Standard-384

guidelines, cables for equipment whose spurious

operation will adversely affect shutdown

systems, etc.), b) Describe each associated cable routing (by fire area) from source to termination, and c) Identify each location where the associated cables are separated by less than a wall having

a three-hour fire rating from cables required

for or associated with any redundant shutdown

system.

RESPONSE As stated in Section 8.1.4.3, in complying with Regulatory Guide 1.75, associated circuits are separated and identified as if they are safety-related.

The final fire hazards analysis, Appendix 9.5B, demonstrates that adequate separation is provided for post-fire safe shutdown systems.

Q280.3 Provide one of the following for each of the

circuits identified in item 2c above:

a) The results of an analysis that demonstrates that failure caused by open, ground, or hot

short of cables will not affect it's associated

shutdown system, (*Note) b) Identify each circuit requiring a solution in accordance with Section III.G.3 of Appendix R, or c) Identify each circuit meeting or that will be modified to meet the requirements of Section

III.G.2 of Appendix R (i.e., three-hour wall, 20 feet of clear space with automatic fire

suppression, or one-hour barrier with automatic

fire suppression).

  • NOTE Option 3a is considered to be one method of meeting the requirements of Section II.G.3 Appendix R. If option 3a is selected the information requested in items

2a and 2c above should be provided in general terms and the information

requested by 2b need not be provided.

280-2 Rev. 14 WOLF CREEK RESPONSE As stated in Section 8.1.4.3, there are no associated circuits whose failure would affect safe shutdown systems.

Q280.4 To assure compliance with GDC 19, we require the following information be provided for the control

room. If credit is to be taken for an alternate or

dedicated shutdown method for other fire areas (as

identified by item 1e or 3b above) in accordance

with Section III.G.3 of new Appendix R to 10 CFR

Part 50, the following information will also be

required for each of these plant areas.

a) A table that lists all equipment including instrumentation and vital support system

equipment that are required by the primary

method of achieving and maintaining hot and/or

cold shutdown.

b) A table that lists all equipment including instrumentation and vital support system

equipment that are required by the alternate, dedicated, or remote method of achieving and

maintaining hot and/or cold shutdown.

c) Identify each alternate shutdown equipment listed in item 4b above with essential cables

(instrumentation, control, and power) that are

located in the fire area containing the primary

shutdown equipment. For each equipment listed

provide one of the following:

1) Detailed electrical schematic drawings that show the essential cables that are

duplicated elsewhere and are electrically

isolated from the subject fire areas, or

2) The results of an analysis that demonstrates that failure (open, ground, or hot short) of each cable identified

will not affect the capability to achieve

and maintain hot or cold shutdown.

d) Provide a table that lists Class 1E and Non-Class 1E cables that are associated with the

alternate, dedicated, or remote method of

shutdown. For each item listed, identify each

associated cable located in the fire area 280-3 Rev. 0 WOLF CREEK containing the primary shutdown equipment. For each cable so identified provide the results of an analysis that demonstrates that failure (open, ground, or hot short) of the associated cable will not adversely affect the

alternate, dedicated, or remote method of shutdown.

RESPONSE A discussion of safe shutdown and a list of systems necessary for safe shutdown are in Section 7.4. Section 7.4 also describes the capability of the auxiliary shutdown panel for safe shutdown from outside the control room.

The final fire hazards analysis, USAR Appendix 9.5B, considers primary, alternate, and associated circuits and demonstrates that any single fire will

not prevent the safe shutdown of the plant.

Q280.5 The residual heat removal system is generally a low pressure system that interfaces with the high

pressure primary coolant system. To preclude a LOCA

through this interface, we require compliance with

the recommendations of Branch Technical Position RSB

5-1. Thus, this interface most likely consists of

two redundant and independent motor operated valves

with diverse interlocks in accordance with Branch

Technical Position ICSB 3. These two motor operated

valves and their associated cable may be subject to

a single fire hazard. It is our concern that this

single fire could cause the two valves to open

resulting in a fire-initiated LOCA through the

subject high-low pressure system interface. To

assure that this interface and other high-low

pressure interfaces are adequately protected from

the effects of a single fire, we require the

following information:

a) Identify each high-low pressure interface that uses redundant electrically controlled devices

(such as two series motor operated valves) to

isolate or preclude rupture of any primary

coolant boundary.

b) Identify each device's essential cabling (power and control) and describe the cable routing (by

fire area) from source to termination.

280-4 Rev. 14 WOLF CREEK c) Identify each location where the identified

cables are separated by less than a wall having

a three-hour fire rating from cables for the

redundant device.

d) For the areas identified in item 5c above (if

any), provide the bases and justification as to

the acceptability of the existing design or any

proposed modifications.

RESPONSE The reactor coolant system high-low pressure interfaces that rely on redundant

electrically controlled devices for isolation include the RHR letdown isolation

valves.

The fire hazards analysis, Appendix 9.5B, demonstrates that no single credible

fire could cause the spurious opening of these valves in a manner that would

breach the primary coolant boundary.

Q280.6 Notification of Appendix R to 10 CFR Part 50 as a

Licensing Requirement.

Appendix R to 10 CFR Part 50 will also be used as

guidance for our review of your fire protection

program. Your compliance with the requirement set

forth in Appendix R as modified by accepted

exceptions will be made a license condition.

Identify any exceptions your program takes to the

requirements of Appendix R as well as BTP ASB 9.5-1, and describe your alternative for providing an

equivalent level of fire protection.

RESPONSE Table 9.5E-1 provides the requested comparisons and identifies the exceptions

of the Wolf Creek Generating Station to 10 CFR 50 Appendix R. Table 9.5B-1

provides the WCGS Fire Protection comparisons to APCSB 9.5-1 Appendix A.

280-5 Rev. 25 WOLF CREEK Q281.1 Indicate the total amount of protective coatings and organic materials (including conduit covered and

uncovered cable insulation) used inside the

containment that do not meet the requirements of

ANSI N101.2 (1972) and Regulatory Guide 1.54.

Evaluate the generation rates vs. time of

combustible gases that can be formed from these

unqualified organic materials under DBA conditions.

Also evaluate the amount (volume) of solid debris

that can be formed from these unqualified organic

materials under DBA conditions that can reach the

containment sump. Provide the technical basis and

assumptions used for this evaluation.

RESPONSE See Section 6.2.5.2.3 c and d.

Q281.2 Regarding the fuel pool cooling and cleanup system, indicate the sampling frequency and criteria for

filter and/or ion exchanger resin replacement.

Items to be addressed should include (1)

decontamination factor, (2) radiation level, and (3)

differential pressure.

RESPONSE See Section 9.1.3.2.3.2.

Q281.3 Describe the provisions to meet the requirements of post-accident sampling of the primary coolant and

containment atmosphere. The description should

address all the requirements outlined in Section

II.B.3 of Enclosure 3 in NUREG-0737 (Clarification

TMI Action Plan Requirements) and should include the

appropriate P & ID's. In addition, if gas

chromatography is used for reactor coolant analysis, special provisions (e.g., pressure relief and

purging) should be provided to prevent high-pressure

carrier gas from entering the reactor coolant. With

respect to clarification (4) in Section II.B.3 of

NUREG-0737, if the chloride concentration in the

reactor coolant samples exceeds the limit in the

Technical Specification, verification that oxygen is

less than 0.1 PPM will be mandatory. Provide also

either (a) a summary description of procedures for 281-1 Rev. 1 WOLF CREEK sample collection, sample transfer or transport, sample analysis and analytical accuracy or

(b) copies of procedures for sample collection, sample transfer or transport, sample analysis and

analytical accuracy.

RESPONSE See Section 18.2.3.

281-2 Rev. 0 WOLF CREEK Q282.1 To evaluate the compatibility of the control rod (4.5.1) drive structural materials with the reactor coolant

water, provide the list of materials and

specifications which are used for each component of

the control rod drive mechanism. The information in

the FSAR does not adequately identify the materials.

RESPONSE The requested information is located in Table 5.2-2.

Q282.2 Provide the following on your secondary water (10.3.5) chemistry control and monitoring programs:

a) Sampling schedule for the critical parameters and of control points for these parameters for

the cold startup mode of operation; b) Procedures used to measure the values of the critical parameters; c) Procedure for recording and management of data;

d) Procedures defining corrective actions* for off-control point chemistry conditions; and e) A procedure identifying (1) the authority responsible for the interpretation of the data

and (2) the sequence and timing of

administrative events required to initiate

corrective action.

Verify that the steam generator secondary water chemistry control program incorporates technical

recommendations of the NSSS. Any significant

deviations from NSSS recommendations should be noted

and justified technically.

________________________

  • Branch Technical Position MTEB 5-3 describes the acceptable means for monitoring secondary side water chemistry in PWR steam generators including

corrective actions for off-control point chemistry conditions. However, the

Staff is amenable to alternatives, particularly to Branch Technical Position

B.3.b(9) of MTEB 5-3 (96 - hour time limit to repair or plug confirmed

condenser tube leaks).

282-1 Rev. 0 WOLF CREEK RESPONSE These items have been covered by plant procedures.

The steam generator secondary water chemistry control program incorporates the technical recommendations of Westinghouse.

As stated in Section 10.3.5.1, the requirements of MTEB 5-3 are met.

282-2 Rev. 0 WOLF CREEK Q310.1 Figure 2.1-7 shows an abandoned A.T.&S.F. railroad line passing through the Wolf Creek site. Please

explain the status of the line. Discuss any

easements which may exist relative to this railroad

line.

RESPONSE Refer to Section 2.2.1.4.

Q310.2 The population of Burlington in the year 2010, as shown in Figure 2.1-13, is difficult to read.

Please provide the population estimates for

Burlington for the years 1990, 2000, 2010 and 2020.

RESPONSE See Figures 2.1-10 through 2.1-14.

Q310.3 Discuss any recreational areas within the Wolf Creek site boundary.

RESPONSE See Section 2.1.2.5.

310-1 Rev. 0 WOLF CREEK 320.0 OFFICE OF STATE PROGRAMS The Nuclear Regulatory Commission amended 10 CFR Part 2, Rules of Practice for Domestic Licensing

Proceedings and 10 CFR Part 50, Domestic Licensing

of Production and Utilization Facilities, effective

March 31, 1982, to eliminate entirely requirements

for financial qualifications review and findings for

electric utilities that are applying for

construction permits or operating licenses for

production or utilization facilities (47 FR 13750, March 31, 1982).

Accordingly, the 320 Series questions and responses were no longer required and were deleted.

320-1 Rev. 0 WOLF CREEK Q331.0 RADIOLOGICAL ASSESSMENT BRANCH Q331.1 Section 12.1.2.5b addresses a neutron shield design (12.1.2.5b) at the RPV in containment. Please specify the

neutron and gamma dose equivalent rates that will

exist at specific locations within the various

levels of containment prior to shield installation

and after the shield is installed. A figure or

table showing respective dose rates would be a

suitable format. Describe your plan for neutron

personnel dosimetry whenever an entry is made while

the reactor is at power, the frequencies at which

entries are made, and the number of people making

these entries.

RESPONSE See Section 3.8.3.1.4.

Q331.2 Radiation levels in excess of 100 R/hr can occur in (12.2.1.3) the vicinity of spent fuel transfer tubes;

therefore, all accessible portions of the transfer

tubes must be shielded during fuel transfer. Please

address the manner in which shielding, access

control and radiation monitoring will be

incorporated into the radiation protection program

to prevent either occupants or transient workers

from receiving very high exposures during transfer

of spent fuel from the reactor to the spent fuel

pool through the fuel transfer tubes. Use of

removable shielding for this purpose is acceptable.

Provide appropriate figures (e.g. plan and

elevation) that show the shielding arrays for all

direct gamma radiation and streaming pathways from

the spent fuel during the transfer. On the same

figure show the location of any administrative

controls by barriers, signs, audible and visual

alarms, locked doors, etc. All accessible portions

of the transfer tubes that cannot be adequately

shielded shall be clearly marked with a sign stating

that potentially lethal fields are possible during

fuel transfer.

RESPONSE See Section 9.1.2.2, and Figures 3.8-48 and 12.3-2.

331-1 Rev. 0 WOLF CREEK Q331.3 Describe the procedure for extracting a sample from (12.2.1.2.3) the Nuclear Sampling System of RCS, RHR and CVCS

with as low as is reasonably achievable exposures to

personnel withdrawing the sample. In your response

include use of shielding, area monitoring, portable

survey meters, hand contact with sample containers, dose rate levels in sampling area, dose rate level

of sample container, etc. Consider samples taken

during normal operations, anticipated operational

occurrences and accidents. The response to this

question should satisfy the requirements of NUREG-

0578 item 2.1.8.a, Post Accident Sampling, with

regard to Radiation Protection.

RESPONSE See Section 12.2.1.2.3.

Q331.4 Table 12.2-7 indicates the radionuclide concentra-(Table tion in the spent fuel pool (SFP) water. Relevant 12.2-7) reactor operating experience shows that the 60 Co activity, from crud transferred to the SFP from the interchange of the primary coolant water during

refueling, is several orders of magnitude greater

than that shown in the table even after purification

by the SFP clean-up system. Please justify the values given in the table for 60 Co, 58 Co, 134 Cs, and 137 Cs and show that these values will be retained after several years of reactor operation. Provide an estimate of the dose rate above the SFP during a

refueling operation and for the period thereafter.

Include in the estimate the effect on the dose rate

of any radioactive equipment that might be stored

therein.

RESPONSE See Table 12.2-7, Section 9.1.2.2.

Q331.5 Please clarify how iodine radioactivity levels (12.3.4.2.2.2.2.) can be "inferred from the particulate and noble

gas radioactivity levels" when monitoring the

exhaust from the radwaste and auxiliary

buildings as addressed in Sections

12.3.4.2.2.2.2 and 12.3.4.2.2.2.4.

RESPONSE See revised Sections 12.3.4.2.2.2.2 and 12.3.4.2.2.2.4.

331-2 Rev. 0 WOLF CREEK Q360.1 EFFLUENT TREATMENT Q360.1 Table 11.4-3 (sheet 2) of the SNUPPS FSAR indicates (11.4) that the estimated annual volume of dry and

compacted waste is based upon Table 2-49 of WASH-1258. The estimated volume was 3,380 ft

3. Page 11.4-8 of the SNUPPS FSAR states that the filled drums are sealed and moved to the dry waste storage

area in the radwaste building, where they are stored

until they are shipped offsite. Figure 1.2-3 of the

SNUPPS FSAR shows that the storage area has a

storage capacity of 722 drums, if stacked three

high, and 1055 drums, if stacked five high. Data

made available since the publication of WASH-1258

have made that document inappropriate for waste

projections. The dry waste volumes estimated by

WASH-1258 are much lower than those being generated

at operating reactors. NRC staff calculations, which are based on data from semi-annual effluent

reports, show that the volume of dry wastes

generated are independent of reactor size and amount to approximately 10,000 ft 3 (compacted) annually, which is a factor of three greater than the estimates presented in the SNUPPS FSAR. Also, the

growing uncertainty of the availability of burial

space has made the availability of adequate storage

space at the reactor facility an important issue.

Based upon the material presented above, provide information verifying that the storage space at

Callaway will be sufficient to handle the storage of

drummed waste in accordance with the requirements of

Branch Technical Position, ETSB 11-3 (Rev. 1), item

III (Waste Storage).

RESPONSE See revised Section 11.4.

Q360.2 Page 11.4-12 the SNUPPS FSAR discusses shielded (11.4) storage areas for "high-level" solidified radwaste

and "low-level" solid radwaste. The term "high-

level" is inappropriate and should be revised.

"High-level" generally refers to reprocessing wastes

resulting from the first cycle of solvent

extraction. More recently, use of the term has been

extended to cover spent reactor fuel. See 10 CFR

Part 50, Appendix F, item 2.

360-1 Rev. 0 WOLF CREEK RESPONSE The terms "high-level" and "low-level" were eliminated and replaced by primary and secondary, respectively, in Section 11.4 to differentiate drummed solid

wastes that require radiation shielding from those that do not.

360-2 Rev. 0 WOLF CREEK Q420.1 Loss of Non-Class IE Instrumentation and Control Power System Bus During Power Operation (IE Bulletin

79-27)

If reactor controls and vital instruments derive power from common electrical distribution systems, the failure of such electrical distribution systems

may result in an event requiring operator action

concurrent with failure of important instrumentation

upon which these operator actions should be based.

This concern was addressed in IE Bulletin 79-27. On

November 30, 1979, IE Bulletin 79-27 was sent to

operating license (OL) holders, the near term OL

applicants (North Anna 2, Diablo Canyon, McGuire, Salem 2, Sequoyah, and Zimmer), and other holders of

construction permits (CP), including Callaway 1 and

Wolf Creek. Of these recipients, the CP holders

were not given explicit direction for making a

submittal as part of the licensing review. However, they were informed that the issue would be addressed

later.

You are requested to address these issues by taking IE Bulletin 79-27 Actions 1 thru 3 under "Actions to

be Taken by Licensees". Within the response time

called for in the attached transmittal letter, complete the review and evaluation required by

Actions 1 thru 3 and provide a written response

describing your reviews and actions. This report

should be in the form of an amendment to your FSAR

and submitted to the NRC Office of Nuclear Reactor

Regulations as a licensing submittal.

RESPONSE See Section 8.1.4.3.

Q420.2 Engineered Safety Features (ESF) Reset Controls (IE Bulletin 80-06)

If safety equipment does not remain in its emergency mode upon reset of an engineered safeguards

actuation signal, system modification, design change

or other corrective action should be planned to

assure that protective action of the affected

equipment is not compromised once the associated

actuation signal is reset. This issue was addressed

in IE Bulletin 80-06 (enclosed). For facilities

with operating licenses as of March 13, 1980, IE

Bulletin 80-06 420-1 Rev. 0 WOLF CREEK required that reviews be conducted by the licensees to determine which, if any, safety functions might

be unavailable after reset, and what changes could

be implemented to correct the problem.

For facilities with a construction permit including OL applicantsBulletin 80-06 was issued for

information only.

The NRC staff has determined that all CP holders, as a part of the OL review process, are to be requested

to address this issue. Accordingly, you are

requested to take the actions called for in Bulletin

80-06 Actions 1 thru 4 under "Actions to be Taken by

Licensees". Within the response time called for in

the attached transmittal letter, complete the review

verifications and description.

RESPONSE See Section 7.3.

Q420.3 Qualification of Control Systems (IE Information Notice 79-22)

Operating reactor licensees were informed by IE Information Notice 79-22, issued September 19, 1979, that certain non-safety grade or control equipment, if subjected to the adverse environment of a high

energy line break, could impact the safety analyses

and the adequacy of the protection functions

performed by the safety grade equipment. Enclosed

is a copy of IE Information Notice 79-22, and

reprinted copies of an August 30, 1979 Westinghouse

letter, and a September 10, 1979 Public Service

Electric and Gas Company letter which address this

matter. Operating Reactor licensees conducted

reviews to determine whether such problems could

exist at operating facilities.

We are concerned that a similar potential may exist at light water facilities now under construction.

You are, therefore, requested to perform a review to

determine what, if any, design changes or operator

actions would be necessary to assure that high

energy line breaks will not cause control system

failures to complicate the event beyond your FSAR

analysis. Provide the results of your review, including all identified problems and the manner in

which you have resolved them to NRR.

420-2 Rev. 0 WOLF CREEK The specific "scenarios" discussed in the above referenced Westinghouse letter are to be considered

as examples of the kinds of interactions which might

occur. Your review should include those scenarios, where applicable, but should not necessarily be

limited to them. Applicants with other LWR designs

should consider analogous interactions as relevant

to their designs.

RESPONSE See Section 3.11(B).2.1.

Q420.4 The analyses reported in Chapter 15 of the FSAR are intended to demonstrate the adequacy of safety

systems in mitigating anticipated operational

occurrences and accidents.

Based on the conservative assumptions made in defining these design-basis events and the detailed

review of the analysis by the staff, it is likely

that they adequately bound the consequences of

single control system failures.

To provide assurance that the design basis event analyses adequately bound other more fundamental

credible failures you are requested to provide the

following information:

1) Identify those control systems whose failure or malfunction could seriously impact plant

safety.

2) Indicate which, if any, of the control systems identified in (1) receive power from common

power sources. The power sources considered

should include all power sources whose failure

or malfunction could lead to failure or

malfunction of more than one control system and

should extend to the effects of cascading power

losses due to the failure of higher level

distribution panels and load centers.

3) Indicate which, if any, of the control systems identified in (1) receive input signals from

common sensors. The sensors considered should

include, but should not necessarily be limited

to, common hydraulic headers or impulse lines

feeding pressure, temperature, level or other

signals to two or more control systems.

420-3 Rev. 0 WOLF CREEK

4) Provide justification that any simultaneous malfunctions of the control systems identified

in (2) and (3) resulting from failures or

malfunctions of the applicable common power

source or sensor are bounded by the analyses in

Chapter 15 and would not require action or

response beyond the capability of operators or

safety systems.

RESPONSE See Section 7.4.

420-4 Rev. 1 WOLF CREEK Q422.01 Please provide the Administrative Controls Section

of the Technical Specifications which describes the

PSRC supervisory and technical personnel referenced

in Section 13.4.1.1.

RESPONSE The description of the Plant Safety Review Committee is provided in the

Administrative Controls Section of the Wolf Creek Generating Station, Unit No.

1, Technical Specifications.

The description of the Plant Safety Review Committee is provided in the Quality Program Mannal.

422-1 Rev. 30 WOLF CREEK Q430.1 Operating experience at certain nuclear power plants (8.3) which have two cycle turbocharged diesel engines

RSP manufactured by the Electromotive Division (EMD) of

General Motors driving emergency generators have

experienced a significant number of turbocharger

mechanical gear drive failures. The failures have

occurred as the result of running the emergency

diesel generators at no load or light load

conditions for extended periods. No load or light

load operation could occur during periodic equipment

testing or during accident conditions with

availability of offsite power. When this equipment

is operated under no load conditions insufficient

exhaust gas volume is generated to operate the

turbocharger. As a result the turbocharger is

driven mechanically from a gear drive in order to

supply enough combusion air to the engine to

maintain rated speed. The turbocharger and

mechanical drive gear normally supplied with these

engines are not designed for standby service

encountered in nuclear power plant application where

the equipment may be called upon to operate at no

load or light load condition and full rated speed

for a prolonged period. The EMD equipment was

originally designed for locomotive service where no

load speeds for the engine and generator are much

lower than full load speeds. The locomotive

turbocharged diesel hardly ever runs at full speed

except at full load. The EMD has strongly

recommended to users of this diesel engine design

against operation at no load or light load

conditions at full rated speed for extended periods

because of the short life expectancy of the

turbocharger mechanical gear drive unit normally

furnished. No load or light load operation also

causes general deterioration in any diesel engine.

To cope with the severe service the equipment is normally subjected to and in the interest of

reducing failures and increasing the availability of

their equipment EMD has developed a heavy duty

turbocharger drive gear unit that can replace

existing equipment. This is available as a

replacement kit, or engines can be ordered with the

heavy duty turbocharger drive gear assembly.

To assure optimum availability of emergency diesel generators on demand. Applicant's who have in

place, or order or intend to order emergency

generators driven by two cycle diesel engines

manufactured by EMD should be provided with the

heavy duty 430-1 Rev. 0 WOLF CREEK turbocharger mechanical drive gear assembly as recommended by EMD for the class of service

encountered in nuclear power plants. Confirm your

compliance with this requirement.

RESPONSE WCGS diesel generators are not manufactured by EMD; they are Fairbanks Morse diesel engines.

As discussed in response to USAR Question 430.3 and 9.5.8.2.3, specific guidance has been provided by the diesel manufacturer on procedures for

operating the engines at light or no load.

Q430.2 Provide a detail discussion (or plan) of the level (8.3) of training proposed for your operators, maintenance

crew, quality assurance, and supervisory personnel

responsible for the operation and maintenance of the

emergency diesel generators. Identify the number

and type of personnel that will be dedicated to the

operations and maintenance of the emergency diesel

generators and the number and type that will be

assigned from your general plant operations and

maintenance groups to assist when needed.

In your discussion identify the amount and kind of training that will be received by each of the above

categories and the type of ongoing training program

planned to assure optimum availability of the

emergency generators.

Also discuss the level of education and minimum experience requirements for the various categories

of operations and maintenance personnel associated

with the emergency diesel generators.

RESPONSE See Section 13.2.2.14 Q430.3 Periodic testing and test loading of an emergency (8.3) diesel generator in a nuclear power plant is a

RSP necessary function to demonstrate the operability, capability and availability of the unit on demand.

Periodic testing coupled with good preventive

maintenance practices will assure optimum equipment

readiness and availability on demand. This is the

desired goal.

430-2 Rev. 10 WOLF CREEK To achieve this optimum equipment readiness status the following requirements should be met:

a) The equipment should be tested with a minimum loading of 25 percent of rated load. No load

or light load operation will cause incomplete

combustion of fuel resulting in the formation

of gum and varnish deposits on the cylinder

walls, intake and exhaust valves, pistons and

piston rings, etc., and accumulation of

unburned fuel in the turbocharger and exhaust

system. The consequences of no load or light

load operation are potential equipment failure

due to the gum and varnish deposits and film in the engine exhaust system.

b) Periodic surveillance testing should be performed in accordance with the applicable NRC

guidelines (R. G. 1.108), and with the

recommendations of the engine manufacturer.

Conflicts between any such recommendations and

the NRC guidelines, particularly with respect

to test frequency, loading and duration, should

be identified and justified.

c) Preventive maintenance should go beyond the normal routine adjustments, servicing and

repair of components when a malfunction

occurs. Preventive maintenance should

encompass investigative testing of components

which have a history of repeated malfunctioning

and require constant attention and repair. In

such cases consideration should be given to

replacement of those components with other

products which have a record of demonstrated

reliability, rather than repetitive repair and

maintenance of the existing components.

Testing of the unit after adjustments or

repairs have been made only confirm that the equipment is operable and does not necessarily

mean that the root cause of the problem has

been eliminated or alleviated.

d) Upon completion of repairs or maintenance and prior to an actual start, run, and load test a

final equipment check should be made to assure

that all electrical circuits are functional, i.e., fuses are in place, switches and circuit

breakers are in their proper position, no loose 430-3 Rev. 1 WOLF CREEK wires, and test loads have been removed, and all valves are in the proper position to permit

a manual start of the equipment. After the unit

has been satisfactorily started and load

tested, return the unit to ready automatic

standby service and under the control of the

control room operator.

Provide a discussion of how the above requirements have been implemented in the emergency diesel

generator system design and how they will be

considered when the plant is in commercial

operation, i.e., by what means will the above

requirements be enforced.

RESPONSE a) See Section 9.5.8.2.3 System Operation (Emergency Diesel Engine Combustion Air Intake and Exhaust System).

b) WCGS is in compliance with the requirements of Regulatory Guide 1.108. Refer to Section 8.1.4.3 for details.

c) See Section 8.3.1.1.3.

d) See Section 8.3.1.1.3.

Q430.4 The availability on demand of an emergency diesel (8.3) generator is dependent upon, among other things, the

RSP proper functioning of its controls and monitoring

instrumentation. This equipment is generally panel

mounted and in some instances the panels are mounted

directly on the diesel generator skid. Major diesel

engine damage has occurred at some operating plants

from vibration induced wear on skid mounted control

and monitoring instrumentation. This sensitive

instrumentation is not made to withstand and

function accurately for prolonged periods under

continuous vibrational stresses normally encountered

with internal combustion engines. Operation of

sensitive instrumentation under this environment

rapidly deteriorates calibration, accuracy and

control signal output.

Therefore, except for sensors and other equipment that must be directly mounted on the engine or

associated piping, the controls and monitoring

instrumentation should be installed on a free

standing floor mounted panel separate from the

engine 430-4 Rev. 0 WOLF CREEK skids, and located on a vibration free floor area.

If the floor is not vibration free, the panel shall

be equipped with vibration mounts.

Confirm your compliance with the above requirement or provide justification for noncompliance.

RESPONSE See Section 8.3.1.1.3.

Q430.5 The information regarding the onsite communications system (Section 9.5.2) does not adequately cover the

system capabilities during transients and

accidents. Provide the following information:

a) Identify all working stations on the plant site where it may be necessary for plant personnel

to communicate with the control room or the

emergency shutdown panel during and/or

following transients and/or accidents

(including fires) in order to mitigate the consequences of the event and to attain a safe

cold plant shutdown.

b) Indicate the maximum sound levels that could exist at each of the above identified working

stations for all transients and accident

conditions.

c) Indicate the types of communication systems available at each of the above identified

working stations.

d) Indicate the maximum background noise level that could exist at each working station and

yet reliably expect effective communication

with the control room using:

1) the page party communications systems, and
2) any other additional communication system provided that working station.

e) Describe the performance requirements and tests that the above onsite working stations

communication systems will be required to pass

in order to be assured that effective

communication with the control room or

emergency shutdown panel is possible under all

conditions.

430-5 Rev. 1 WOLF CREEK f) Identify and describe the power source(s) provided for each of the communications

systems.

g) Discuss the protective measures taken to assure a functionally operable onsite communication

system. The discussion should include the

considerations given to component failures, loss of power, and the severing of a

communication line or trunk as a result of an accident or fire.

RESPONSE a) Refer to Section 9.5.2.

b) Refer to Section 9.5.2.

c) Refer to revised Table 9.5.2-1.

d) Refer to Section 9.5.2.

e) Refer to Section 9.5.2.

f) Refer to Section 9.5.2.

g) Refer to Section 9.5.2.

Q430.6 Identify the vital areas and hazardous areas where emergency lighting is needed for safe shutdown of

the reactor and the evacuation of personnel in the

event of an accident. Tabulate the lighting system

provided in your design to accommodate those areas

so identified. Include the degree of compliance to

Standard Review Plan 9.5.1 regarding emergency

lighting requirements in the event of a fire.

RESPONSE Refer to Section 9.5.3.

Q430.7 Describe the instruments, controls, sensors and (9.5.4) alarms provided for monitoring the diesel engine

fuel oil storage and transfer system and describe

their function. Discuss the testing necessary to

maintain and assure a highly reliable

instrumentation, controls, sensors and alarm system

and where the alarms are annunciated. Identify the

temperature, pressure and level sensors which

alert the 430-6 Rev. 1 WOLF CREEK operator when these parameters are exceeded the ranges recommended by the engine manufacturer and

describe what operator actions are required during

alarm conditions to prevent harmful effects to the

diesel engine. Discuss the system interlocks

provided. (SRP 9.5.4, Part III, Item 1).

RESPONSE All applicable instruments, controls, sensors and alarms for the diesel fuel oil storage and transfer system are shown on USAR Figures 9.5.4-1 and 9.5.6-1, Sheets 1 and 2. See Section 9.5.4.

Q430.8 The diesel generator structures are designed to (9.5.4) seismic and tornado criteria and are isolated from

one another by a reinforced concrete wall barrier.

Describe the barrier (including openings) in more

detail and its capability to withstand the effects

of internally generated missiles resulting from a

crankcase explosion, failure of one or all of the

starting air receivers, or failure of any high or

moderate energy line and initial flooding from the

cooling system so that the assumed effects will not

result in loss of an additional generator. (SRP

9.5.4, Part III, Item 2).

RESPONSE See Section 3.5.2.5.

Q430.9 Figure 9.5.4-1 and the FSAR text state that the fuel (9.5.4) oil storage tank fill and vent lines are non-

seismic. We require these lines to be designed

seismic Category I and Quality Group C. Conform

your compliance with this position. Also describe

the design provisions made to protect the fuel oil

storage tank fill and vent lines from damage by

tornado missiles. (SRP 9.5.4, Part II).

RESPONSE The fuel oil storage tank vent and all lines are non-seismic above grade and are seismic Category I below grade (refer to USAR Figure 9.5.4-1). See Section

3.5.3.1.Q430.10 Discuss the means for detecting or preventing growth (9.5.4) of algae in the diesel fuel storage tank. If it

were detected, describe the methods to be provided

for cleaning the affected storage tank. (SRP 9.5.4, Part III, Item 4).

430-7 Rev. 0 WOLF CREEK RESPONSE See Section 9.5.4.2.1.

Q430.11 The FSAR text and Table 3.2-1 states that the com-(3.2) ponents and piping systems for the diesel generator

(9.5.4) auxiliaries (fuel oil system, cooling water, lubri-

(9.5.5) cation, air starting, and intake and combustion

(9.5.7) system) that are mounted on the auxiliary skids are

(9.5.8) designed seismic Category I and are ASME Section III

Class 3 quality. The engine mounted components and

piping are designed and manufactured to DEMA

standards, and are seismic Category I. This is not

in accordance with Regulatory Guide 1.26 which

requires the entire diesel generator auxiliary

systems be designed to ASME Section III Class 3 or

Quality Group C. Provide the industry standards

that were used in the design, manufacture, and

inspection of the engine mounted piping and

components. Also show on the appropriate P&ID's

where the Quality Group Classification changes from

Quality Group C.

RESPONSE Only those components and piping supplied with the standard diesel engine and which either make up an integral part of the engine or whose design and

reliability have been proven through years of previous diesel engine service

are not Quality Group C. All other piping, tubing, and components are ASME

Section III, Class 3. See Table 3.2-1.

The USAR figures for the diesel engine auxiliary systems differentiate between seismic and non-seismic portions of the systems and identify those portions of

the systems provided by the diesel engine manufacturer.

The standards used in the design, manufacture, and inspection of the Non-Quality Group C components are the manufacturer's standards, developed from his

manufacturing and testing experience. By nature of its design and

construction, the engine- mounted piping is considered to provide equivalency

to ANSI B31.1 standards.

Q430.12 Discuss what precautions have taken in the (9.5.4) design of the fuel oil system in locating the fuel

oil day tank and connecting fuel oil piping in the

diesel generator room with regard to possible

exposure to ignition sources such as open flames and

hot surfaces. (SRP 9.5.4, Part III, Item 6).

430-8 Rev. 0 WOLF CREEK RESPONSE See Section 9.5.4.

Q430.13 Identify high and moderate energy lines and (9.5.4) systems that will be installed in the diesel gener-

(9.5.5) ator room. Discuss the measures that will be taken

(9.5.6) in the design of the diesel generator facility to

(9.5.7) protect the safety related systems, piping and com-

(9.5.8) ponents from the affects of high and moderate energy

line failure to assure availability of the diesel

generators when needed. (SRP 9.5.4, Part III, Item 8, SRP 9.5.5, Part III, Item 4, SRP 9.5.6, Part

III, Item 8; SRP 9.5.7, Part III, Item 3; SRP 9.5.8, Part III, Item 6c).

RESPONSE See Section 3.5 and 3.6.

Q430.14 In section 9.5.4 of the FSAR you state that accumu-(9.5.4) lated sediment and moisture may be withdrawn, prior

to adding a new fuel oil, through the sample nozzle

to minimize the possibility of degrading the overall

quality of the new fuel in the unlikely event that

would require replenishment of fuel oil without

interrupting operation of the diesel generator.

This is unacceptable since the sample nozzle would

only permit removal of accumulated moisture but not

the sediment. Discuss what provisions that will be

made in the design of the fuel oil storage fill

system to minimize the creation of turbulence of the

sediment in the bottom of the storage tank.

Stirring of this sediment during addition of new

fuel has the potential of causing the overall

quality of the fuel to become unacceptable and could

potentially lead to the degradation of failure of

the diesel generator. Two methods of minimizing

this problem are suggested. 1) Design a fuel oil

storage tank fill system that will minimize

turbulence in the tank. 2) Cross connect the fuel

oil storage tank of each diesel in a manner that

will permit supply of fuel oil to either engine from

either tank. In this manner one tank could be

filled while the other tank supplies fuel to the

operating D/G. After filling the tank fuel would

not be drawn from the tank for a period of time to

permit settling of sediment.

430-9 Rev. 0 WOLF CREEK RESPONSE Refer to Section 9.5.4.2.1.

Q430.15 You state in Section 9.5.4.3 that diesel oil is (9.5.4) normally delivered to the site by tanker truck and

if road transportation is unavailable, it can be

delivered onsite by railroad tanker. Discuss your

sources where diesel quality fuel oil will be

available and the distance required to be traveled

from the source to the plant. Also discuss how fuel

oil will be delivered onsite under extremely

unfavorable environmental conditions including

maximum probable flood conditions.

RESPONSE See Section 9.5.4.2.3.

Q430.16 You state in Section 9.5.4.2 that the diesel gener-(9.5.4) ator fuel oil storage tank is provided with an

individual fill and vent line. Indicate where these

lines are located (indoor or outdoor) and the height

these lines are terminated above finished ground

grade. If these lines are located outdoors discuss

the provisions made in your design to prevent

entrance of water into the storage tank during

adverse environmental condition including maximum

probable flood conditions.

RESPONSE See Section 9.5.4.2.2.

Q430.17 Discuss the design margin (excess heat removal cap-(9.5.5) ability) included in the design of major components

and subsystems of the D/G cooling water system (SRP

9.5.5, Part III, Item I).

RESPONSE See Section 9.5.5.2.2.

Q430.18 Provide the results of the failure mode and (9.5.5) effects analysis to show that failure of a piping

connection between subsystems (engine water jacket, lube oil cooler, governor lube oil cooler, and

engine air inter-cooler) does not cause total

degradation of the diesel generator cooling water

system. (SRP 9.5.5, Part III, Item 1a). 430-10 Rev. 0 WOLF CREEK RESPONSE See Section 9.5.5.3.

Q430.19 Indicate the measures to preclude long-term corro-(9.5.5) sion and organic fouling in the diesel engine

cooling water system that would degrade system

cooling performance, and the compatibility of any

corrosion inhibitors or antifreeze compounds used

with the materials of the system. Indicate if the

water chemistry is in conformance with the engine

manufacturers recommendations. (SRP 9.5.5, Part

III, Item 1c.)

RESPONSE See Section 9.5.2.2.

Q430.20 You stated in Section 9.5.5.2.3 the diesel engine (9.5.5) cooling water is treated as appropriate to minimize

corrosion. Provide additional details of your

proposed diesel engine cooling water system chemical

treatment, and discuss how your proposed treatment

complies with the engine manufacturers

recommendations. (SRP 9.5.5, Part III, Item 1c).

RESPONSE See Section 9.5.2.2.

Q430.21 Describe the instrumentation, controls, sensors and (9.5.5) alarms provided for monitoring of the diesel engine

cooling water system and describe their function.

Discuss the testing necessary to maintain and assure

a highly reliable instrumentation, controls, sensors, and alarm system, and where the alarms are

annunciated. Identify the temperature, pressure, level, and flow (where applicable) sensors which

alert the operator when these parameters exceed the

ranges recommended by the engine manufacturer and

describe what operator actions are required during

alarm conditions to prevent harmful effects to the

diesel engine. Discuss the systems interlocks

provided. (SRP 9.5.6, Part III, Item 1c).

RESPONSE See Section 9.5.5.5. 430-11 Rev. 0 WOLF CREEK Q430.22 In Section 9.5.8.2 of the FSAR, you state that "To (9.5.5) reduce the possibility of accumulation of combustion

and lube oil products in the exhaust system at the

lower loads, the engine will be operated at 50

percent or higher loads for short periods at

stipulated time intervals as recommended by the

engine manufacturer. Provide the time duration of

the "short periods" and the manufacture's

recommended "time intervals". We require that this

"light load or no load operation" procedure be made

part of plant operating procedures. Confirm your

compliance with this position.

RESPONSE Refer to Response to 430.3.

Light load or no load operation is addressed in plant operating procedures.

Q430.23 Provide a discussion of the measures that have been (9.5.6) taken in the design of the standby diesel generator

air starting system to preclude the feeling of the

air start valve or filter with moisture and

contaminants such as oil carryover and rust. (SRP

9.5.6, Part III, Item 1).

RESPONSE See Section 9.5.6.2.1.

Q430.24 Describe the instrumentation, controls, sensors and (9.5.6) alarms provided for monitoring the diesel engine air

starting system, and describe their function.

Describe the testing necessary to maintain a highly

reliable instrumentation, control, sensors and alarm

system and where the alarms are annunciated.

Identify the temperature, pressure and level sensors

which alert the operator when these parameters

exceed the ranges recommended by the engine

manufacturer and describe any operator actions

required during alarm conditions to prevent harmful

affects to the diesel engine. Discuss system

interlocks provided. Revise your FSAR accordingly.

(SRP 9.5.6, Part III, Item 1).

RESPONSE See Section 9.5.6.5. 430-12 Rev. 0 WOLF CREEK Q430.25 Expand your description of the diesel engine start-(9.5.6) ing system. The FSAR text should provide a detail

system description of what is shown on Figure 9.5.6-

1. The FSAR text should also describe: 1)

components and their function, 2) instrumentation, controls, sensors and alarms, and 3) a diesel engine

starting sequence. In describing the diesel engine

starting sequence include the number of air start

valves used and whether one or both air start

systems are used.

RESPONSE The diesel engine air start system components and their functions are described in Section 9.5.6.2.2.

Refer to Section 9.5.6.5 for information relating to above (part 2).

System operation is discussed in Section 9.5.6.2.3.

Q430.26 Provide the source of power for the diesel engine air starting system compressors and motor

characteristics, i.e., motor hp, operating voltage, phase(s), and frequency. Revise your FSAR

accordingly.

RESPONSE Refer to Table 9.5.6-1 for the response to this question.

Q430.27 For the diesel engine lubrication system in Section (9.5.7) 9.5.7 provide the following information: 1) define

the temperature differentials, flow rate, and heat

removal rate of the interface cooling system

external to the engine and verify that these are in

accordance with recommendations of the engine

manufacturer; 2) discuss the measures that will be

taken to maintain the required quality of the oil, including the inspection and replacement when oil

quality is degraded; 3) describe the capability for

detection and control of system leakage. (SRP

9.5.7, Part II, Item 8a, 8b, 8c, Part III, Item I.)

RESPONSE 1) Requested information for lube oil cooler is given in Table 9.5.7-1. Design information given in Table 9.5.7-1 is

manufacturer's data. 430-13 Rev. 0 WOLF CREEK

2) See Section 9.5.7.2.1.
3) See Section 9.5.7.2.3.

Q430.28 What measures have been taken to prevent entry of (9.5.7) deleterious materials into the engine lubrication

oil system due to operator error during recharging

of lubricating oil or normal operation. (SRP 9.5.7, Part III, Item 1c).

RESPONSE See Section 9.5.7.2.

Q430.29 Describe the instrumentation, controls, sensors and (9.5.7) alarms provided for monitoring the diesel engine

lubrication oil system and describe their function.

Describe the testing necessary to maintain a highly

reliable instrumentation, control, sensors and alarm

system and where the alarms are annunciated.

Identify the temperature, pressure and level sensors

which alert the operator when these parameters

exceed the ranges recommended by the engine

manufacturer and describe any operator action

required during alarm conditions to prevent harmful

effects to the diesel engine. Discuss systems

interlocks provided. Devise your FSAR accordingly.

(SRP 9.5.7, Part III, Item 1c).

RESPONSE See Section 9.5.7.5.

Q430.30 Expand your description of the diesel engine lube (9.5.7) oil system. The FSAR text should include a detail

system description of what is shown on Figure 9.5.7-

1. The FSAR text should also describe: 1)

components and their function, and 2) a diesel

generator starting sequence for a normal start and

an emergency start. Revise your FSAR accordingly.

RESPONSE Refer to USAR Sections 9.5.7.2.1 through 9.5.7.2.3.

Q430.31 Provide the source of power for the diesel engine (9.5.7) prelube oil pump, lube oil transfer pump, clean lube

oil transfer pump and used lube oil tank transfer

pump, and motor characteristics, i.e., motor hp, 430-14 Rev. 0 WOLF CREEK operating voltage, phase(s) and frequency. Also provide the pump capacity and discharge head.

Revise your FSAR accordingly.

RESPONSE The WCGS diesel engine is equipped with a main lube oil pump, an auxiliary lube oil (keep warm) pump, a rocker lube oil pump, and a rocker prelube pump. Refer

to USAR Table 9.5.7-1 for the requested information.

Q430.32 In Section 9.5.7.2 of the FSAR you state that pre-lubrication of the rocker arm assembly during

standby conditions is done periodically in

accordance with the engine manufacturer's

recommendations. Provide the following:

a) We require that the electric prelube pump auto-(RSP) matically prelube the rocker arm assembly and

that alarms be provided which alert the

operator of pump failure to start on automatic

prelubrication.

b) Provide the manufacturer's periodic prelubrication recommendations.

c) Discuss how the lubricating oil in the rocker arm assembly lubrication system is cooler

during engine operation and kept warm to

enhance engine starting during standby

operation.

RESPONSE See Section 9.5.7.2.1 and 9.5.7.2.3.

Q430.33 Describe the instrumentation, controls, sensors and (9.5.8) alarms provided in the region of the diesel engine

combustion air intake and exhaust system which alert

the operator when parameters exceed ranges

recommended by the engine manufacturer and describe

any operator action required during alarm conditions

to prevent harmful effects to the diesel engine.

Discuss systems interlocks provided. Revise your

FSAR accordingly. (SRP 9.5.8, Part III, Item 1 &

4). 430-15 Rev. 0 WOLF CREEK RESPONSE See Section 9.5.8.5.

Q430.34 Provide the results of an analysis that demonstrates (9.5.8) that the function of your diesel engine air intake

and exhaust system design will not be degraded to an

extent which prevents developing full engine rated

power or cause engine shutdown as a consequence of

any meteorological or accident condition. Include

in your discussion the potential and effect of other

gases that may intentionally or accidentally be

released on site, on the performance of the diesel

generator. (SRP 9.5.8, Part III, Item 3).

RESPONSE See Section 9.5.8.2.3.

Q430.35 Discuss the provisions made in your design of the (9.5.8) diesel engine combustion air intake, D/G supply

ventilation system, and exhaust system to prevent

possible clogging, during standby and in operation, from abnormal climatic conditions (heavy rain, freezing rain, dust storms, ice and snow) that could

prevent operation of the diesel generator on

demand. (SRP 9.5.8, Part III, Item 5).

RESPONSE See Section 9.5.8.2.3.

Q430.36 Figure 1.2-1 of the Callaway (and Wolf Creek) FSAR (9.5.8) shows the ESF transformers located near the control/

diesel generator building complex. An ESF

transformer fire with the right meteorological

conditions could degrade engine operation by the

products of combustion being drawn into the D/G

ventilation system which supplies D/G combustion

air. Discuss the provisions of your design (site

characteristics, ventilation system and building

design, etc.) which preclude this event from

occurring.

RESPONSE See Section 9.5.8.2.3. 430-16 Rev. 0 WOLF CREEK Q430.37 Experience at some operating plants has shown that (9.5.8) diesel engines have failed to start due to

accumulation of dust and other deleterious material

on electrical equipment associated with starting of

the diesel generators (e.g., auxiliary relay

contacts, control switches - etc.) Describe the

provisions that have been made in your diesel

generator building design, electrical starting

system, and combustion air and ventilation air

intake design(s) to preclude this condition to

assure availability of the diesel generator on

demand.

Also describe under normal plant operation what procedure(s) will be used to minimize accumulation

of dust in the diesel generator room; specifically

address concrete dust control. In your response

also consider the condition when Unit 1 is in

operation and Unit 2 is under construction (abnormal

generation of dust).

RESPONSE See Section 9.5.8.2.2.

Q430.38 Section 9.5.8.2.2 and 3.2.2 of the FSAR state that (9.5.8) the portions of the EDEAIES outside the D/G build-(RSP) ing are non-seismic and Quality Group D. This is

unacceptable. We require that these portions of the

system also be designed seismic Category I and

Quality Group C. In addition we required also that

the exhaust stacks located outside the D/G building

be tornado missile protected. Separation by

distance does not constitute adequate protection.

Confirm your compliance with these positions.

RESPONSE See Section 3.5.

Q430.39 Provide a general discussion of the criteria and (10.1) bases of the various steam and condensate

instrumentation systems in Section 10.1 of the

FSAR. The FSAR should differentiate between normal

operation instrumentation and required safety

instrumentations. 430-17 Rev. 0 WOLF CREEK RESPONSE The criteria and bases of the various steam and condensate instrumentation are to monitor system variables to provide maximum plant availability, automatic

control of equipment and identification of abnormal conditions. Sections 7.3, 7.4, and 7.5 describe the required safety instrumentation associated with

Section 10.1. The remaining steam and condensate instrumentation systems

included in Section 10.1 are nonsafety-related and are used for normal

operation.

Q430.40 The FSAR discusses the main steam stop and control, (10.2) and reheat stop and intercept valves. Show that a

single failure of any of the above valves cannot

disable the turbine overspeed trip functions. (SRP

10.2, Part III, Item 3).

RESPONSE Section 10.2.2.3.2 describes the component redundancy which precludes single failure of any main stop, control, intermediate stop, and intercept valve from

resulting in rotor speed exceeding design overspeed. All the above valves have

independent operating controls and mechanisms.

Q430.41 In the turbine generator section discuss: 1) the (10.2) valve closure times and the arrangement for the main

steam stop and control and the reheat stop and

intercept valves in relation to the effect of a

failure of a single valve on the overspeed control

functions; 2) the valve closure items and extraction

steam valve arrangements in relation to stable

turbine operation after a turbine generator system

trip; 3) effects of missiles from a possible turbine

generator failure on safety related systems or

components. (SRP 10.2, Part III, Items 3, 4.)

RESPONSE See Section 10.2.2.2. Main stop and control valves, intermediate stop, and intercept valves' closure times are provided. Extraction nonreturn valves are

free swinging and close on decreasing flow as described in Section 10.2.2.2.

Valve arrangements and single failure effects plus stable turbine operation

after a trip are described in Sections 10.2.2.2 and 10.2.2.3.2, Table 10.2-1, and Figure 10.4-6. Turbine missiles are discussed in Section 3.5.1.3. 430-18 Rev. 0 WOLF CREEK Q430.42 Discuss the effects of a high and moderate energy (10.2) piping failure or failure of the connection from the

low pressure turbine to condenser on nearby safety-

related equipment or systems. Discuss what

protection will be provided the turbine overspeed

control system equipment, electrical wiring and

hydraulic lines from the effects of a high or

moderate energy pipe failure so that the turbine

overspeed protection system will not be damaged to

preclude its safety function. (SRP 10.2, Part III, Item 3).

RESPONSE The turbine overspeed protection system is not safety-related. The ultimate protection from turbine missiles is discussed in Section 3.5.1. No

high/moderate energy pipe break or hazards analysis is performed for nonsafety-

related turbine building piping or components. See Section 10.2.2.3.2.

Figures 1.2-32 and 1.2-33 show the physical separation between redundant stop/control valves and intermediate stop/intercept valves. Fail safe design

of the ETS hydraulic system and the trip power circuitry provide additional

turbine overspeed protection. Failure of the low pressure turbine/condenser

connection will draw air into the condenser and increase turbine backpressure

until trip occurs as stated in Section 10.2.2.3.4.

Q430.43 Describe with the aid of drawings, the bulk hydrogen (10.2) storage facility including its location and

distribution system. Include the protective

measures considered in the design to prevent fires

and explosions during operations such as filling and

purging the generator, as well as during normal

operations.

RESPONSE See Section 2.2.1.2.4.2.

Q430.44 Provide a tabulation in your FSAR showing the (10.4.1) physical characteristics and performance

requirements of the main condensers. In your

tabulation include such items as; 1) the number of

condenser tubes, material and total heat transfer

surface, 2) overall dimensions of the condenser, 3)

number of pauses, 4) hot well capacity, 5) special

design features, 6) minimum heat transfer, 7) normal

and maximum steam flows, 8) normal and maximum

cooling water temperature, 9) normal and maximum

exhaust steam temperature with no turbine by-pass

flow and 430-19 Rev. 0 WOLF CREEK with maximum turbine by-pass flow, 10) limiting oxygen content in the condensate in cc per liter, and 11) other pertinent data. (SRP 10.4.1, Part

III, Item 1).

RESPONSE Table 10.4-1 has been revised to include the requested information.

Q430.45 Discuss the measures taken; 1) to prevent loss of (10.4.1) vacuum, and 2) to prevent corrosion/erosion of

condenser tubes and components. (SRP 10.4.1, Part

III, Item 1).

RESPONSE Measures taken to prevent loss of vacuum and the Section describing them include: a) Hydrostatic test of condenser shell (10.4.1.4).

b) Water seal for the LP turbine/condenser connection expansion joint with level indication (10.4.1.2).

c) Operation of condenser vacuum pumps (10.4.2).

d) Control room indication of circulating water pump status (Section 10.4.5).

Measures taken to prevent corrosion/erosion of condenser tubes and components:

a) Provision of 304 stainless steel tubes in the impingement areas of all tube bundles (Table 10.4-1).

b) Feedwater/circulating water chemistry control (Section 10.3.5 and 10.4.5).

Q430.46 Indicate and describe the means of detecting and (10.4.1) controlling radioactive leakage into and out of the

condenser and the means for processing excessive

amounts. (SRP 10.4.1, Part III, Item 2). 430-20 Rev. 11 WOLF CREEK RESPONSE The means of detecting, controlling, and processing radioactive leakage into and out of the condenser resulting from a steam generator tube leak are

discussed in Chapter 11.0. The means for detecting and controlling radioactive

leakage into and out of the condenser are described in Sections 11.5.2.2.2.2, 11.5.2.2.2.3, 11.5.2.2.3.4, and 11.5.2.3.2.1. Processing of excessive

radioactive leakage is discussed in Sections 11.2.2 and 11.3.2.

Q430.47 Discuss the measures taken for detecting and con-(10.4.1) trolling and correcting condenser cooling water

leakage into the condensate stream. (SRP 10.4.1, Part III, Item 2).

RESPONSE The measures taken for detecting, controlling, and correcting condenser cooling water leakage into the condensate stream are discussed in Section 10.4.1.

Q430.48 Provide the permissible cooling water inleakage and (10.4.1) time of operation with inleakage to assure that

condensate/feedwater quality can be maintained

within safe limits. (SRP 10.4.1, Part III, Item 2).

RESPONSE The information is provided in Section 10.4.6, Condensate Cleanup System.

Q430.49 In Section 10.4.1.4 you have discussed tests and (10.4.1) initial field inspection but not the frequency and

extent of inservice inspection of the main

condenser. Provide this information in the FSAR.

(SRP 10.4.1, Part II).

RESPONSE See Section 10.4.1.4.

Q430.50 Indicate what design provisions have been made to (10.4.1) preclude failures of condenser tubes or components

from turbine by-pass blowdown or other high

temperature drains into the condenser shell. (SRP

10.4.1, Part III, Item 3). 430-21 Rev. 0 WOLF CREEK RESPONSE See Section 10.4.1.2.3.

Q430.51 Discuss the effect of loss of main condenser vacuum (10.4.1) on the operation of the main steam isolation valves

(SRP 10.4.1, Part III, Item 3).

RESPONSE Loss of main condenser vacuum does not trip the main steam isolation valves.

Loss of main condenser vacuum trips the turbine and blocks turbine by-pass.

Turbine trip at power levels above 50 percent results in a reactor trip as

described in Section 7.2. The effects of potential failure modes on the NSSS

and turbine system are addressed in Sections 15.1.4, 15.2.3, and 15.2.5.

Q430.52 Provide additional description (with the aid of (10.4.4) drawings) of the turbine by-pass system (condenser

dump valves and atmosphere dump valves) and

associated instruments and controls. In your

discussion include: 1) the size, principle of

operation, construction and set points of the

valves, 2) the malfunctions and/or modes of failure

considered in the design of the system.

RESPONSE Condenser Dump Valves Section 10.4.4.2.1, 10.4.4.2.2 and Figure 10.3-1, Sheet 3 provide a description of the turbine bypass system and the condenser dump valves. Section 7.7.1.8

and Figures 7.2-1, Sheet 10 and 10.3-1, Sheet 3 describe the associated

instruments and controls. The malfunctions and failure modes considered in

system design and their effect on the NSSS and turbine system are addressed in

Sections 15.1.4 and 15.2.3.

Steam Generator Atmospheric Relief Valves Section 10.3.2.2, Table 10.3-2 and Figure 10.3-1, Sheet 1 provide a description of the steam generator atmospheric relief valves. The valves are opened by pneumatic pressure and closed by spring action as stated in Section 10.3.2.2.

Section 7.4.1.2 and Figures 7.2-1, Sheet 10 and 10.3-1, Sheet 1 describe the

associated instruments and controls. The malfunctions and failure modes

considered in the system design are addressed in Section 7.4.1.2 and Section

15.1.4. 430-22 Rev. 13 WOLF CREEK Q430.53 Section 10.4.4 of the FSAR describes the turbine by-(10.4.4) pass system and states that the TBS dumps steam to

the condenser through condenser spargers. Figure

10.3.1, Sheet 3 in the FSAR shows the turbine by-

pass as described in Section 10.4.4. It also shows

six 3 inch lines branching off the TBS lines

upstream of the TBS valves. These lines are

labelled "To Condenser Sparger" and seem to have

normally open valves. Explain the purpose of these

lines and the status of these valves.

RESPONSE The purpose of these lines is to supply steam to the condenser hotwell spargers used for deaeration of the condensate, as described in Sections 10.3.5 and

10.4.1.2.3. The valves in phantom on Figure 10.3.1, Sheet 3 are shown on P&ID

M-02AD01 (Figure 10.4.2, Sheet 1) as normally closed.

Q430.54 In Section 10.4.4.4 you have discussed tests and (10.4.4) initial field inspection but not the frequency and

extent of inservice testing and inspection of the

turbine by-pass system. Provide this information in

the FSAR. (SRP 10.4.4, Part II).

RESPONSE See Section 10.4.4.4.

Q430.55 Provide the results of an analysis indicating that failure of the turbine by-pass system high energy

line will not have an adverse effect or preclude

operation of the turbine speed control system or any

safety-related components or system located close to

the turbine by-pass system. (SRP 10.4.4, Part III, Item 4).

RESPONSE See response to Question 430.42. There is no safety-related equipment in the vicinity of the turbine by-pass system, as stated in Section 10.4.4.3. 430-23 Rev. 0 WOLF CREEK Q440.1 Please provide a scheduled completion date for the plant administrative procedures which are referred

to in Section 13.5.1.

RESPONSE This information is provided in Section 13.5.1.2.

Q440.2 Please indicate that you intend to include procedures for design change processing, retest

after design changes, and control of plant documents

and records in the plant administrative procedures.

RESPONSE See Section 13.5.1.2.

Q440.3 The analyses of a locked reactor coolant pump rotor (Q440.1C) and a sheared reactor coolant pump shaft in the FSAR

assumes the availability of offsite power throughout

the event. In accordance with Standard Review Plan

15.3.3 and GDC 17, we require that this event be

analyzed assuming turbine trip and coincident loss

of offsite power to the undamaged pumps.

Appropriate delay times may be assumed for loss of offsite power if suitably justified.

Steam generator tube leakage should be assumed at the rates specified in the Technical Specifications.

The event should also be analyzed assuming the worst single failure of a safety-system active component.

Maximum technical specification primary system

activity and steam generator tube leakage should be

assumed. The analyses should demonstrate that

offsite doses are less than 10 CFR 100 guidelines

values.

RESPONSE See Section 15.3.3 for additional information.

Q440.106 In reviews of certain other Westinghouse-designed (5.2.2) plants, a failure of a D.C. power bus was identified

which could both initiate an overpressure event at

low temperature (by isolating letdown) and fail

closed one of the PORVs. A postulated single 440-1 Rev. 0 WOLF CREEK failure (closed) of the other PORV would fail mitigating systems for this event. Address this

scenario for the SNUPPS design.

RESPONSE See Section 5.2.2.3 for additional information.

Q440.207 The NRC wanted to know if the solid water condition between RHR suction valves could, because of

heating, expand and cause system damage or valve

inoperability.

RESPONSE RHR suction valve seat leakage is expected to prevent system damage or valve inoperability resulting from contained fluid thermal expansion. 440-2 Rev 0 WOLF CREEK Q450.0 In your description of the control room habitability (6.4) system, include the provisions for emergency food, water and medical supplies.

RESPONSE See Table 6.4-1, Position 15.

Q450.1 In the evaluation of toxic gas protection, document (6.4) the degree of leak-tightness of the control room

isolation dampers.

RESPONSE The total leak-tightness of the control room and its potential leakage paths are discussed in USAR Section 9.4.1.2.3 under EMERGENCY OPERATION. Also see Section 9.4.1.2.2.

Q450.2 Provide a description and drawing showing the loca-(6.4) tions of control room outside air inlets relative to

potential radiation releases.

RESPONSE See Section 9.4.1.2.3.

Q450.3 In your analysis of toxic gas protection for Control Room Personnel, provide the number and type of

respiratory devices, the type of operator training

for respiratory use, the estimated time for donning

or deploying the equipment, the length of time the equipment can be used, and the equipment testing and maintenance provisions.

RESPONSE See Table 6.4-1, Item 13.

Q450.4 List the areas, equipment and materials in the zone (6.4) serviced by the control room emergency ventilation

system.

RESPONSE The control room ventilation systems are described in Sections 6.4.2 and 9.4.1.

450-1 Rev. 1 WOLF CREEK Q450.5 Discuss how the control room design precludes the (6.4) buildup of noxious gases from control room equipment

such as gases from batteries.

RESPONSE See Section 6.4.2.4.

Q450.6 In Section 6.4.5, the testing and inspection of the (6.4) control room habitability systems is described. In

particular, the last paragraph states: "The control

room is classified as Type B per Regulatory Guide

1.78. Since the air exchanger rate exceeds 0.06 air

exchanges per hour for the control room, periodic

testing of the control room pressurization system is

not required per the exclusion provisions of the

Regulatory Guide." Apparently, there is some confusion as to the applicability of Regulatory Guide 1.95 (and 1.78) to

the control room ventilation design for radiological

protection. For a control room outside air makeup

rate during emergency pressurization less than 0.25

volume change per hour (as in Callaway), SRP Section

6.4 recommends the following:

a) acceptance test to verify adequate pressure, b) supporting calculations to verify adequate air flow, and c) periodic verification testing.

If this guidance is not followed, justify the departures.

RESPONSE a) See USAR Section 14.2.12.1.45.

b) See Section 6.4.2.3 and 9.4.1.2.3.

c) See Section 6.4.5.

Q450.7 In Section 6.5.2.2.3 of the SNUPPS FSAR, it stated (6.5.2) that the containment spray system recirculation flow

is manually initiated. It is the staff's position

that the containment spray switchover be automatic.

Justify your departure from this position. 450-2 Rev. 0 WOLF CREEK RESPONSE See Section 6.5.2.2.3.

Q450.8 With respect to rod ejection accident, provide the (15.4.8(A)) transient time for the depressurization of the

primary system to the termination of primary to

secondary leakage.

RESPONSE See Section 15.4.8.1.1.

Q450.9 The following information is currently missing from (15.6.3) the Callaway FSAR and is needed to complete our

review. For the steam generator tube rupture

accident provide the following figures:

a) SGTR break flow rate vs Time

b) SGTR integrated tube leak mass vs Time

c) Primary system pressure vs Time

d) Secondary system pressure vs Time

e) PORV flow rate vs Time

f) MS safety valve flow rate per steamline vs Time

g) Atmospheric dump valve flow rate vs Time

h) Steam generator steaming rate vs Time

i) Reactor coolant temperature vs Time

j) Feedwater flow rate into the steam generators vs Time k) Water level in the affected steam generator relative to the top of the tube bundle vs Time.

Also, provide the mass of secondary coolant in a steam generator.

RESPONSE Refer to Section 15.6.3. 450-3 Rev. 0 WOLF CREEK Q450.10 The SNUPPS FSAR indicates that the mode of initia-(6.5.2) tion of switchover of the containment spray system (RSP) suction from the Refueling Water Storage Tank to the

containment sump is manual. The staff finds that

this practice departs from that currently deemed

acceptable. SRP Section 6.5.2 (II. Acceptance

Criteria, Item 2.a) states "The Containment spray

system should be designed...and should be capable of

continuous operation thereafter until the design

objectives of the system have been achieved. In all

cases the operating period should not be less than

two hours." Manual initiation of the switchover

does not guarantee continuous operation for two

hours and does not provide assurance that the design

objectives of the spray system are achieved for

delayed fission product releases from the core. It

is the staff's position that we require a design

modification which will change from manual to

automatic the switchover of the containment spray

system from the RWST to the containment sump. State

your intent regarding compliance with our position.

RESPONSE See Section 6.5.2.2.3.

450-4 Rev. 0 WOLF CREEK Q451.0 ACCIDENT EVALUATION BRANCH Q451.1 Please provide hour-by-hour meteorological data for the periods 6/1/73 - 5/31/75 and 3/5/79 - 3/4/80 on

magnetic tape using the enclosed guidance on format

and tape attributes.

RESPONSE This data was forwarded to the NRC on 6/1/81.

Q451.2 Describe the status of the onsite meteorological measurements program since 3/4/80 and provide

additional data for the period 3/5/80 - 3/4/81, if

available.

RESPONSE See Section 2.3.3.

Q451.3 Table 2.3-37 (Rev. 1, 2/81) of the FSAR indicates that extremely unstable (Pasquill Type A),

moderately stable (Pasquill Type F), and extremely

stable (Pasquill Type G) conditions have persisted

for long durations (e.g., greater than 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />) at

the WCGS site. Apparently, extremely unstable

conditions persisted for a 24-hour period during the

Phase 2 program. Persistence of these stability

classes for periods greater than 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> in

duration is very unusual. Discuss the causes of

persistent stability conditions for periods greater

than 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for classes A, F, and G. Identify the

synoptic conditions during the observed periods of

persistent stability for periods greater than 12

hours and discuss the possibility of instrument

malfunction.

RESPONSE See Section 2.3.2.1.7.

Q451.4 Table 2.3-29 (Rev. 1, 2/81) of the FSAR indicates a lower data recovery for joint frequency

distributions of wind speed and wind direction by

atmospheric stability for the period 3/5/79 - 3/4/80

than for the previous two years of data collection

(6/1/73 - 5/31/75) despite increased attention to

the onsite meteorological program. The major

difference between the Phase 1 (6/1/73 - 5/31/75)

program and the Phase 2 program (3/5/79 - 3/4/80) 451-1 Rev. 0 WOLF CREEK appears to be the type of data recording system, with the Phase 2 system consisting solely of analog

charts. Discuss the reasons for the lower data

recovery and indicate whether complete reliance on

an analog recording system could be a major factor

in reduced data recovery. Identify periods of

extended instrument outage (e.g., for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or

more) during the Phase 2 program and the cause of

the outage. Indicate the corrective measures taken

to minimize extended outages in the future. Describe

the data availability (e.g., remote display in the

control room or elsewhere) and data reduction

procedures to be used for the meteorological

measurements program during plant operation.

RESPONSE See Section 2.3.3.7.2.

Q451.5 Section 2.3.2.2 (Rev. 1, 2/81) of the FSAR (see also Revision 1, 4/81 to the Environmental Report Section

5.1.4) presents an analysis of the atmospheric

impacts of the heat dissipation facilities using the

model FOGALL. This analysis replaces the previous

analysis based on the model POND.

a) Describe the improvements in the analysis using FOGALL compared to the analysis using POND.

b) Describe the validation (or verification) of FOGALL for analyzing atmospheric impacts of a

5090 acre cooling lake.

c) Describe the meteorological measurements program to be used to evaluate actual

meteorological impacts of the heat dissipation

system once the cooling lake is filled and the

plant is operational.

RESPONSE a) See Section 2.3.2.2.

b) See Section 2.3.2.2.

c) See Section 2.3.2.2.

451-2 Rev. 0 WOLF CREEK Q451.6 Section 2.3.2.2 (Rev. 1, 2/81) of the FSAR also discusses the effect of the cooling lake on

atmospheric transport and diffusion and concludes

"for winds less than about 6 mph flowing from or

into this sector [south-southwest to south-

southeast] (and less than 2 mph in any sector over

the lake) modifications in the atmospheric stability

of the diffusion properties of the air may be

expected." Winds less than about 6 mph blowing from

or into the south-southwest to south-southeast

sector occur about 13% of the time. Discuss the

modifications to transport and dispersion

characteristics during these conditions and indicate

if the calculations in Sections 2.3.4 and 2.3.5 of

the FSAR should be changed to reflect the modified

dispersion conditions.

RESPONSE See Section 2.3.2.2.

Q451.7 Tables 2.3-59 and 2.3-60 of the FSAR (Rev. 1, 2/81) present terrain/recirculation correction factors to

be applied to a straight-line Gaussian dispersion

model to better characterize temporal variations in

meteorological conditions. These correction factors

were estimated based on the results of a variable-

trajectory puff advection model using one year of

hour-by-hour meteorological data from the Wolf Creek

site. Substantial reductions (up to a factor of 100

lower than the straight-line model) are suggested

for distances approaching 80 km. For several

directions, correction factors of zero are

suggested, implying that no release from the site

would affect a particular receptor location.

Discuss the reasonableness and appropriateness of

correction factors for receptors greater than 8 km

from the source developed by use of a variable

trajectory model with only a single source of

meteorological data as input. Indicate the merit of

a correction factor calculated to be zero.

RESPONSE See Section 2.3.5.1.4.

451-3 Rev. 0 WOLF CREEK Q451.8 The expected number of lightning strikes to ground per year in a square mile area surrounding the site

could be as high as 46 (p. 2.3-8 of the FSAR).

Provide seasonal and annual estimates of lightning

strikes to safety-related structures at the site, considering the "attractive area" of the

structures. A suggested reference for this type of

analysis is J. L. Marshall, Lightning Protection

, 1973.

RESPONSE See Section 2.3.1.2.5.

Q451.9 The tornado statistics presented in Section 2.3.1.2.6 are based on a regional data base that

ended in 1971. Identify any tornadoes that have

occurred in the vicinity of the site since 1971, and

provide estimates of the intensity (maximum wind

speed) and path area of each.

RESPONSE See Section 2.3.1.2.6.

Q451.10 a) Describe the procedures used for determining "the worst temperature period" and "the worst

evaporation period" (Table 2.3-9 A and B) used

for the analysis of the ultimate heat sink.

b) Regulatory Guide 1.27 (Rev. 2) recommends that the meteorological conditions used for analysis

of the ultimate heat sink be selected from a

recent 30-year period. Only 16 years of data

from Chanute Flight Service Station were used

in this evaluation (p. 2.3-12). Explain why 16

years of data (1949 through 1964) is considered

representative of regional climatological

conditions for analysis of the ultimate heat

sink.

RESPONSE a) See Section 9.2.5.3.

b) See Section 2.3.1.2.10.

451-4 Rev. 1 WOLF CREEK Q451.11 Review of the hour-by-hour meteorological data provided on magnetic tape in responses to question

451.1 indicates a number of concerns. First, the

tape has been mislabeled so that the intervals for

measurement of vertical temperature gradient are

incorrectly identified. Second, a sizable fraction

of the recorded temperature gradient measurements

exceed the auto-convective lapse rate. Third, occasionally the temperature difference measured

between the 10m and 60m levels is considerably

different than that measured between the 10m and 85m

levels. For example, on Julian day 160 1979, the

temperature difference between the 10m and 60m

levels indicated a moderately unstable (Pasquill

Type "B") condition while a slightly stable

(Pasquill Type "E") condition was indicated by the

temperature difference between the 10m and 85m

levels. Finally, 45% of moderately stable (Pasquill

Type "F") and 30% of extremely stable (Pasquill Type

"G") conditions occur with wind speeds greater than

3m/sec. Similarly, 60% of extremely unstable

(Pasquill Type "A") conditions occur with wind

speeds greater than 3m/sec. Occurrences of

extremely unstable, moderately stable, and extremely

stable conditions usually predominate during low

wind speeds (i.e., less than 1.5m/sec).

a) Provide a new magnetic tape of corrected hour-by-hour meteorological data for the 3 year

period of record in the format requested in

question 451.1. All invalid data (see b and c

below) should be properly identified.

b) Provide a description of the quality control checks used to identify invalid hourly data.

Discuss the validity of occurrences of

temperature gradients exceeding the auto-

convective lapse rates and the occurrences of

considerably different stability conditions

indicated by temperature gradients measured

between the 10m and 60m levels and those

measured between the 10m and 85m levels.

c) Discuss the validity of the relatively large number occurrences of extremely unstable, moderately stable, and extremely unstable

conditions with wind speeds greater than

3m/sec.

451-5 Rev. 1 WOLF CREEK RESPONSE a) The revised data was submitted.

b) See Section 2.3.3.7.2.

c) See Section 2.3.2.7.2.

451-6 Rev. 0 WOLF CREEK 471.0 RADIOLOGICAL ASSESSMENT BRANCH Q471.1 Please describe your plan to provide onsite backup coverage in the event of the absence of the site

Health Physicist and outline the qualifications (or

make reference to them in the appropriate section of

the FSAR) of the individual who will act as the

backup. It is our position that this individual

have a B.S. degree in science or engineering, and

two years health physics experience, one year of

which should be nuclear power plant experience, with

six months of this experience being onsite. It is

our position that this experience be health physics

experience.

RESPONSE See Section 12.5.1.

Q471.2 Section 13.1.2.3 "Shift Crew Composition" states that this area will be addressed in the Technical

Specification. The staff requires that an H.P.

technician will be onsite at all times, in

accordance with NUREG-0654 "Criteria for Preparation

and Evaluation of Radiological Emergency Response

Plans and Preparation in Support of Nuclear Power

Plants", after the reactor is at power. Please

state your intentions for having your technical

specification include a H.P. technician as part of

the shift crew. The qualifications of the H.P.

technician are described in ANSI 18.1.

RESPONSE See the WCGS Technical Specifications.

Q471.3 In accordance with 12.5.3 several procedures including respiratory protection, decontamination, glove boxes, tents, etc. will be used to reduce

possibility of personnel exposure to airborne

activity. Please discuss your radiation protection

provision for installation of temporary flexible

ducting and monitoring equipment at the site of

maintenance operations and repair activities, if a

high potential for airborne radioactivity exists, to

assure that 10 CFR Part 20.103 limits are not

excluded, that 10 CFR 20.103(b) actions are taken, and that exposure are maintained ALARA during the

operation.

RESPONSE See Section 12.5.3.

471-1 Rev. 0 WOLF CREEK Q471.4 Table 12.5-2 "Portable Health Physics Equipment" show quantities of instrumentation not adequate to

meet the anticipated needs of a radiation protection

program for a nuclear power plant. The staff

position is that sufficient numbers of

instrumentation be available in operating condition

to accommodate the need to monitor such large

numbers of operations that may be required in

radiation areas and high radiation areas throughout

the plant during major maintenance and refueling

outages and/or accidents. In arriving at a total

number, consideration should also be given to the

survey instruments that may be in a calibration, maintenance or inoperative-on-the-shelf status

during the outage and/or accidents. Additionally, the inventory should include the requirements for

selected ranges, sensitivities, types of radiation

to be monitored, accuracy required and types of

monitoring to be performed. Ten instruments that

read-out in the R/hr range of measurements, as shown

in Table 12.5.2, would probably not satisfy the

above criteria based on the findings at operating

nuclear power plants. Therefore, the table should

be revised to reflect these criteria in order to

provide the radiation protection instrumentation

inventory requirements of the plant.

RESPONSE See Table 12.5-2.

471-2 Rev. 0 WOLF CREEK Q490.1 Since the issuance of Construction Permits for SNUPPS plants, several significant changes have

taken place that will affect our review of Section

4.2, "Fuel System Design." The most fundamental

changes deal with the format and content of Section

4.2 as they relate to the Standard Review Plan; the

other changes deal with technical issues that have

arisen recently. All of these changes are discussed

below.

Standard Review Plan The basic fuel sections of the Standard Format (Rev.

3), the Standard Review Plan (Rev. 1, 1978), and the

SNUPPS FSAR are all the same: 4.2.1 Design Bases, 4.2.2 Description and Design Drawings, and 4.2.3

Design Evaluation. Unfortunately, 4.2.1 of the

Standard Format (and, hence, of the SNUPPS FSAR)

does not clearly call for a quantitative (usually

numerical) statement of all design bases as does the

Standard Review Plan. Similarly, the other sections

of the Standard Format and the SNUPPS FSAR mix up

design bases, design descriptions, and design

evaluations, but that information is sorted out

clearly in the Standard Review Plan.

Because of improvements in clarity and completeness in this 1978 version of the Standard Review Plan, we

will conduct our review and prepare the SER

according to the SRP. Our questions, then, will not

be open-end, but they will simply ask for the

residual information called for in the SRP but not

present in the SNUPPS FSAR. There are, thus, two

options at this stage of the review.

Option 1 - You could revise Section 4.2 of the SNUPPS FSAR to follow the details of the SRP (remember, the basic organization structure would be

unchanged). This would automatically bring out all

of the information that is needed.

Option 2 - A cross reference could be provided to link each item in the SRP with a paragraph in the SNUPPS FSAR. This method would leave Section 4.2 of

the SNUPPS FSAR in its present format, but might

lead to additional questions since all of the

information is not present.

490-1 Rev. 0 WOLF CREEK We recommend Option 1. Revision 1 of the SRP, to which we refer, was formally issued more than two

years ago. Therefore, we do not view this change as

either precipitous or disruptive. Furthermore, it

is likely that you will have to identify and justify

all deviations from the SRP under the provisions of

a proposed rule (Federal Register 45 , p. 67099, October 9, 1980) since your SER will be issued after

January 1, 1982.

We urge you to provide the information that would be needed to demonstrate compliance with the SRP at

your earliest convenience. To help you anticipate

an imminent revision to SRP-4.2, the following

comments are provided.

Revision 1 - This revision was issued in October 1978 and contains all of the basic requirements that you need to address. It will not be changed

significantly by the planned revision.

Revision 2 - This revision is planned for April 1981 and is the revision alluded to in the notice of proposed rulemaking on SRP compliance. In SRP-4.2

this revision will (a) add acceptance criteria for

mechanical response to seismic and LOCA loads, and

(b) make editorial change largely confined to adding

and correcting citations to regulations and

regulatory guides that are already addressed in Rev.

1. The acceptance criteria for mechanical response

were recently implemented as part of the resolution

of Unresolved Safety Issue, Task A-2 and are given

in Appendix E of NUREG-0609. Therefore, you can

base the SNUPPS FSAR revisions on SRP-4.2 Rev. 1

(current version) plus Appendix E of NUREG-0609, and

last-minute changes in referencing can be made in

April prior to your submittal of the additional

fuel-related information.

Recent Technical Issues The following is a list of current technical issues that have frequently been noted as outstanding

issues in recent SERs and that should be given

special attention in the SNUPPS FSAR.

490-2 Rev. 0 WOLF CREEK

1. Supplemental ECCS analysis with NUREG-0630.
2. Combined seismic and LOCA loads analysis.
3. Enhanced fission gas release analysis at high

burnups.

4. Fuel rod bowing and analysis.
5. Fuel assembly control rod guide tube wear

analysis.

6. Fuel assembly design shoulder gap analysis.
7. End-of-life fuel rod internal pressure

analysis.

RESPONSE A. See Section 4.2, 4.2.3, 15.4 and 15.6.

B. See Table 4.1-1, 4.3-1, Section 4.2.2.1, Figures 4.2-1 through 4.2-15 and Section 4.2-3.

Recent Technical Issues With regard to the seven current technical issues presented in question 490.1, it is WCGS's understanding that many of the generic issues have been resolved

in connection with NRC staff reviews of similar plants with fuel assembly

designs and fuel fabrication specifications that are the same as those for

SNUPPS. The following paragraphs address these issues.

1. Supplemental ECCS analysis with NUREG-0630 Section 6.2.5 describes the ECCS.
2. Combined seismic and LOCA loads analysis The combination of seismic effects and loads due to a double ended loss-of-coolant accident are discussed in Section 4.2.3.
3. Enhanced fission gas release analysis at high burnups The subject of fission gas release is discussed in Westinghouse topical report WCAP-8720/8785 (Reference 5 in

Section 4.2.)

490-3 Rev. 0 WOLF CREEK

4. Fuel rod bowing analysis The subject of fuel rod bowing is discussed in Section 4.2.3 as well as Westinghouse topical report WCAP-8691/8692

(Reference 11 of Section 4.2.)

5. Fuel assembly control rod guide tube wear analysis Westinghouse topical report WCAP-8278/8279 (Reference 10 of Section 4.2) presents flow test results for fretting wear at

contact points between the control rods and control rod guide

thimbles. Additional experimental data has been submitted to

the NRC by Westinghouse (see W letters NS-TMA-1936, 1992, and

2102), and a post-irradiation examination program has been

established to address this specific subject (see NUREG-0717).

6. Fuel assembly design shoulder gap analysis Appropriate rod-to-nozzle gap is provided in the WCGS fuel to accommodate thermal expansion and irradiation-induced growth

of the fuel rods relative to the overall fuel assembly

structure. Westinghouse's ability to model fuel rod growth

has been confirmed by comparison with measurements from 15 x

15 and 17 x 17 in-reactor data, and also is in good agreement

with established experimental results as discussed in

Reference 1.

7. End-of-life fuel internal pressure analysis The internal fuel rod pressure criteria are described in approved Westinghouse topical report WCAP-8963/8964 (Reference

7 to Section 4.2.)

References

1. Balfour, J.B., Destefan, J., Melehan, M.G., and Cerni, S.

"Evaluation and Performance of Westinghouse 17 x 17 Fuel,"

presented at the ANSI Topical Meeting on LWR Fuel Performance

held April 30 through May 2, 1979.

490-4 Rev. 0 WOLF CREEK Q492.2 The effects of fuel rod bowing must be included in the thermal-hydraulic design. The predicted extent

of rod bow (gap closure) versus exposure and the

effect of rod bowing on DNBR must be addressed. Use

of the staff report "Revised Interim Safety

Evaluation Report on the Effects of Fuel Rod Bowing

on Thermal Margin Calculations for Light Water

Reactors," February 16, 1977, represents an

acceptably conservative treatment of rod bowing.

RESPONSE See Section 4.3.3.3.1d.

Q492.3 Operating experience on two pressurized water reactors (not of the Westinghouse design) indicate

that significant reduction in core flow rate can

occur over a relatively short period of time as a

result of crud deposition on the fuel rods. In

establishing the Technical Specifications for

Callaway and Wolf Creek we will require provisions

to assure that the minimum design flow rates are not

exceeded. Therefore, provide a description of the

flow measurements capability for Callaway and Wolf

Creek as well as a description of the procedures to

measure flow and the actions to be taken in the

event of an indication of lower than design flow.

RESPONSE See Section 4.4.4.7.

Q492.4 The NRC approval of the THINC-IV code, for use in the thermal-hydraulic design, indicates that the

pressure gradient at the core exit must be modeled.

Provide a revised THINC-IV calculation at the steady

state reactor design conditions including the

modeling of the core exit radial pressure gradient.

Provide the following specific information from that

calculation:

1. minimum DNB ratio (value and location)
2. hot channel flow vs. axial position
3. hot channel enthalpy vs. axial position
4. hot channel void fraction vs. axial position
5. the assumed core exit pressure gradient.

492-1 Rev. 0 WOLF CREEK RESPONSE On October 25, 1977, Westinghouse met with the NRC to discuss the effects of nonuniform upper plenum pressure distribution as part of the NRC staff's review

of RESAR-414. The Westinghouse material presented at that meeting was

transmitted to the NRC via letter NS-CE-1591, dated November 2, 1977, from C.

Eicheldinger (Westinghouse) to J. F. Stolz (NRC). This letter addresses the

THINC-IV information requested by question 492.4, and is applicable to all

Westinghouse 4-loop plants, including the SNUPPS units.

In addition, this issue was pursued further by the NRC during the McGuire FSAR review. The McGuire fuel is identical to the SNUPPS fuel, and the same

thermal-hydraulic models and correlations were used. As a result of this

review, the staff concluded that this issue was adequately resolved. This

conclusion is equally applicable to WCGS.

Q492.5 Insufficient information has been provided to justify the design power level of 2389 Mwt (70% of

full power) during three-loop operation.

Temperature differences in the active cold legs of a

few degrees could exist during three-loop

operation. Therefore a radial power tilt and an

increase in enthalpy rise factor could result. As a

result, we request that a complete detailed

description of the following items be provided:

1. The method of determining the temperature distribution among the cold legs and the

associated radial power tilt;

2. The method of accounting for differences (if any) in the three-loop thermal-hydraulic

design;

3. The instrumentation available and monitoring procedures during three-loop operation;
4. The DNBR Technical Specification and how it will be implemented for three-loop operation;
5. The reactor protective system setpoints related to DNBR protection and how they are generated; 492-2 Rev. 0 WOLF CREEK
6. The effects of anticipated operational occurrences on the cold leg temperature

distributions and how this effect is included

in the design.

RESPONSE This question is not applicable to the SNUPPS Plants, since they do not currently plan to operate in the N-1 mode.

Q492.6 Please state your intent regarding the use of the Westinghouse optimized fuel assembly in your plant.

If the use of this design is being considered, provide a discussion of the status and schedule for

any revised submittals.

RESPONSE WCGS does not currently plan to incorporate Westinghouse optimized fuel for the first fuel cycles.

Q492.7 Please state your intent regarding the use of the Westinghouse "Improved Thermal Design Procedure" described in WCAP-8567, dated July, 1975. If you

intend to use these methods, responses to the

following questions will be required:

(a) Provide a block diagram depicting sensor, process equipment, computer, and readout

devices for each parameter channel used in the

uncertainty analysis. Within each element of

the block diagram, identify the accuracy, drift, range, span, operating limits and

setpoints. Identify the overall accuracy of

each channel transmitter to final output and

specify the minimum acceptable accuracy for use

with the new procedure. Also identify the

overall accuracy of the output value and

maximum accuracy requirements for each input

channel of this final output device.

(b) Discuss the method(s) for incorporating environmental effects (e.g., noise, EMI) on

instrument channels into the uncertainty

analysis.

492-3 Rev. 0 WOLF CREEK (c) Provide data to verify that the plant instruments will perform with a high degree of

confidence, within their design accuracies.

This information may be obtained from operating

history of identical instruments installed in

other plants. This request pertains to the

instruments affecting the uncertainties in the

design procedure (as identified in question 1

above), the overtemperature T trip, the high

flow trip, the low pressure trip and the pump

voltage trip.

(d) Provide the ranges of applicability of sensitivity factors.

(e) Demonstrate that the linearity assumption of equation 3-8 in WCAP-8567 is valid when the

WRB-1 correlation is used.

RESPONSE The Westinghouse Improved Thermal Design Procedure is not currently planned to be used. Q492.8 Standard format and content of Safety Analysis Reports, Regulatory Guide 1.70, states that in

Chapter 4 of the SAR

"...the applicant provide an evaluation and

supporting information to establish the

capability of the reactor to perform its safety

functions throughout its design lifetime under

all normal operation modes..."

Are the analyses presented in Section 4.4

representative of the initial core only or have

future cycles been analyzed? Provide a discussion

of how power distributions for future cycles are

considered in the FSAR analyses. Is there any

assurance that the Callaway Units (Wolf Creek) can

operate at the licensed power level without

excessive DNB trips throughout future cycles? Will

revisions to the design methodology be required in

order to maintain sufficient thermal margin?

492-4 Rev. 0 WOLF CREEK RESPONSE The goal of the reload safety evaluation is to confirm the validity of the existing safety analysis. The existing safety analysis is defined as the

reference safety analysis and is intended to be valid for all plant cycles.

Thus safety analysis input parameter values are selected to bound the values

expected in all subsequent cycles. This bounding analysis concept is the key

to the Westinghouse reload safety analysis methodology. When all reload

safety-related parameters for a given accident are bounded, the reference

safety analysis is valid. On the other hand, when a reload parameter is not

bounded, further evaluation is necessary. The purpose of this further

evaluation is to confirm that the margin of safety defined in the basis for any

technical specification is not reduced. This reload safety evaluation

methodology is applied whenever the input parameter values for a reference

safety analysis are available. In summary, Westinghouse reload safety

evaluation methodology consists of:

1. A systematic evaluation to determine whether the reload parameters are bounded by the values used in the reference

safety analysis.

2. A determination of the effects on the reference safety analysis when a reload parameter is not bounded to ensure that

specified design bases are met.

When the above process identifies either a need for a license amendment or a change in the plant Technical Specifications, the Operating Agent will make the appropriate notification to the NRC.

Q492.9 The staff has reviewed the applicants' response to the requirements of Item II.F.2 of NUREG-0737 and

found that the applicants have not provided the

documentation required by Item II.F.2. Therefore, the staff will require that the applicants provide

the documentation required by Item II.F.2 of NUREG-

0737.

RESPONSE See revised Section 18.2.13.

Q492.10 Justify that the single upper head penetration meets the single failure requirement of NUREG-0737 and

show that it does not negate the redundancy of the

two instrument trains.

492-5 Rev. 15 WOLF CREEK RESPONSE See Section 18.2.13.2.

Q492.11 Describe the location of the level system displays in the control room with respect to other plant

instrument displays related to ICC monitoring, in

particular, the saturation meter display and the

core exit thermocouple display.

RESPONSE See Section 18.2.13.2.

Q492.12 Describe the provisions and procedures for on-line verification, calibration and maintenance.

RESPONSE See Section 18.2.13.2.

Q492.13 Describe the diagnostic techniques and criteria to be used to identify malfunctioning components.

RESPONSE See Section 18.2.13.2.

Q492.14 Estimate the in-service life under conditions of normal plant operations and describe the methods

used to make the estimate, and the data and sources

used.

RESPONSE See Section 18.2.13.2.

Q492.15 Explain how the value of the system accuracy (given as +/- 6%) was derived. How were the uncertainties

from the individual components of the system

combined? What were the random and systematic

errors assumed for each component? What were the

sources of these estimates?

RESPONSE See Section 18.2.13.2.

492-6 Rev. 0 WOLF CREEK Q492.16 Assume a range of sizes for "small break" LOCA's.

What are the relative times available for each size

break for the operator to initiate action to recover

the plant from the accident and prevent damage to

the core? What is the dividing line between a

"small break" and a "large break"?

RESPONSE See Section 18.2.13.2.

Q492.17 Describe how the system response time was estimated. Explain how the response times of the

various components (differential pressure

transducers, connecting lines and isolators) affect

the response time.

RESPONSE See Section 18.2.13.2.

Q492.18 There are indications that the TMI-2 core may be up to 95% blocked. Estimate the effect of partial

blockage in the core on the differential pressure

measurements for a range of values from 0 to 95%

blockage.

RESPONSE See Section 18.2.13.2.

Q492.19 Describe the effects of reverse flows within the reactor vessel on the indicated level.

RESPONSE See Section 18.2.13.2.

Q492.20 What is the experience, if any, of maintaining D/p cells at 300% overrange for long periods of time?

RESPONSE See Section 18.2.13.2.

492-7 Rev. 0 WOLF CREEK Q492.21 Five conditions were identified which could cause the DP level system to give ambiguous indications.

Discuss the nature of the ambiguities for 1)

accumulator injection into a highly voided

downcomer, 2) when the upper head behaves like a

pressurizer, 3) upper plenum injection, and 4)

periods of void redistribution.

RESPONSE See Section 18.2.13.2.

Q492.22 No recommendations are made as to the uncertainties of the pressure or temperature transducers to be

used, but the choice appears to be left to the owner

or AE. What is the upper limit of uncertainties

that should be allowed? Describe the effect of

these uncertainties on the measurement of level.

What would be the effect on the level measurement

should these uncertainties be exceeded?

RESPONSE See Section 18.2.13.2

Q492.23 Only single RTD sensors on each vertical run are indicated to determine the temperatures of the

impulse lines. Where are they to be located? What

are the expected temperature gradients along each

line under normal operating conditions and under a

design basis accident? What is the worst case error

that could result from only determining the

temperature at a single point on each line?

RESPONSE See Section 18.2.13.2.

Q492.24 What is the source of the tables or relationships used to calculate density corrections for the level

system?

RESPONSE See Section 18.2.13.2.

492-8 Rev. 0 WOLF CREEK Q492.25 The microprocessor system is stated to display the status of the sensor input. Describe how this is

indicated and what this actually means with respect

to the status of the sensor itself and the

reliability of the indication.

RESPONSE See Section 18.2.13.2.

Q492.26 Describe the provisions for preventing the draining of either the upper head or hot leg impulse lines

during an accident. What would be the resultant

errors in the level indications should such draining

occur?

RESPONSE See Section 18.2.13.2.

Q492.27 Discuss the effect on the level measurement of the release of dissolved, noncondensible gases in the

impulse lines in the event of a depressurization.

RESPONSE See Section 18.2.13.2.

Q492.28 In some tests at Semi-scale, voiding was observed in the core while the upper head was still filled with

water. Discuss the possibility of cooling the core-

exit thermocouples by water draining down out of the

upper head during or after core voiding with a solid

upper head.

RESPONSE See Section 18.2.13.2.

Q492.29 Describe the behavior of the level measurement system when the upper head is full, but the lower

vessel is not.

RESPONSE See Section 18.2.13.2.

492-9 Rev. 0 WOLF CREEK Q492.30 One discussion of the microprocessor system states that water in the upper head is not reflected in the

plot. Does this mean that there is no water in the

upper head or that the system is indifferent to

water in the upper head under these conditions?

RESPONSE See Section 18.2.13.2.

Q492.31 Describe the details of the pump flow/Dp calculation. Discuss the possible errors.

RESPONSE See Section 18.2.13.2.

Q492.32 Have tests been run with voids in the vessel?

Describe the results of these tests.

RESPONSE See Section 18.2.13.2.

Q492.33 Estimate the expected accuracy of the system after an ICC event.

RESPONSE See Section 18.2.13.2.

Q492.34 Describe how the conversion of RTD resistance to temperature is made in the analog level system.

RESPONSE See Section 18.2.13.2.

492-10 Rev. 0 WOLF CREEK Q640.0 PROCEDURES AND TEST REVIEW BRANCH Q640.1 Certain exceptions to regulatory guides as listed (14.2.7) in Appendix 3A are not acceptable or require further

justification.

Provide the following information:

1) Regulatory Guide 1.68 Describe existing tests that verify acceptable plant response for a loss of turbine-generator

coincident with a loss of offsite power, or

delete this exception and include the

appropriate test description.

RESPONSE See Sections 14.2.12.1.74, 14.2.12.1.75, 14.2.12.3.36 and 14.2.12.3.39. The ability of the plant to respond to a loss of offsite power is demonstrated.

Additional testing is performed on the main generation system to verify the

operability and controls of the system. The combination of this testing

provides more information than could be obtained by performing the required

test. 2) Regulatory Guide 1.80 State which tests demonstrate that safety-related valves fail-safe on loss-of-instrument

air.

RESPONSE The failure position of safety-related valves is verified within the test procedure associated with the system to which the valve belongs. Also see

Section 14.2.12.1.90.

3) Regulatory Guide 1.118 The discussion states that nuclear instrumentation sensors are exempt from time

response testing since their worst case

response time is not a significant portion of

the total overall system response (i.e., less

than 5%). Given that this exemption is no

longer permitted by IEEE-338 (1977 version),

delete this exception or provide expanded

technical justification for not conducting time

response testing.

RESPONSE See Section 7.1.2.6.2 and Appendix 3A.

640-1 Rev. 0 WOLF CREEK 640.0WC PROCEDURES AND TEST REVIEW BRANCH Q640.1WC Subsection 14.2.2.4.4 states that GE will be respon-(14.2.2.4) sible for providing personnel experienced in the

startup and operation of the turbine generator and

related auxiliary equipment. Expand Subsection

14.2.2.4.4 to explain in greater detail what direct

support GE will provide (ex., supply and install

turbine-generator, instruct KG&E personnel in the

conduct of testing and operation, recommend

procedures for starting, operating, and shutting

down equipment).

RESPONSE See Section 14.2.2.4.4.

Q640.2 Your initial criticality description should be (14.2.10.2) expanded to include:

1) A source range count of at least 1/2 count per second should be visible on the startup

channels prior to commencing the startup.

2) The signal to noise ratio should be known to be greater than 2.
3) Criticality predictions for boron concentration and control rod positions should be provided, and criteria and actions to be taken should be

established if actual plant conditions deviate

from predicted values.

4) The approach to criticality should be slow enough to limit start up rate at criticality to

less than 1 decade per minute.

RESPONSE 1) The procedure requires greater than 1/2 counts per second.

2) See Section 14.2.12.3.9.
3) See Section 14.2.10.2.
4) Reactivity insertion rates on approach to criticality are so low that startup rate at criticality is not a function of the

rate of approach to criticality. Sufficient precautions are

included in the startup test procedures to preclude exceeding

a 1-decade-per-minute startup rate at criticality.

640-2 Rev. 0 WOLF CREEK Q640.2WC Subsection 14.2.2.6 refers to Section 13 regarding (14.2.2.6) the qualifications of key personnel involved in the

initial testing program. Subsection 13.1.3.1

references Regulatory Guide 1.8. Our current

position is that the individuals involved in

preoperational or startup testing should hold the

qualifications stated in Regulatory Position 3 of

proposed Revision 2 to Regulatory Guide 1.8, February 1979 (issued for comment). State that your

minimum qualification requirements will be in

accordance with this regulatory position or provide

justification for requiring any lesser

qualifications.

RESPONSE This area of review was covered by the NRC Management Structure and Technical Resources Review Team during the week of 1/18/82 at KG&E.

Q640.3 Section 14.2.11 of SNUPPS states that insofar as (14.2.11) practicable, test requirements will be completed

prior to exceeding 25-percent power for all plant

structures, systems and components that are relied

upon to prevent, limit or mitigate the consequences

of postulated accidents. According to Table 14.2-5

the following startup tests are performed after

exceeding 25-percent power:

1) S070012 - Rod Drop and Plant Trip
2) S07AB01 - Automatic Steam Generator Level Control
3) S07SF05 - Automatic Reactor Control System
4) S07SF07 - Startup Adjustments of Reactor Control System Perform these tests at 25% power or less, or provide technical justification for not fulfilling the

testing requirements of Section 14.2.11.

RESPONSE See Table 14.2-5.

640-3 Rev. 0 WOLF CREEK Q640.3WC Section 14.2.5 states that during Power Ascension (14.2.5) Testing, review and approval of initial startup test

procedure results is completed for each of the

plateaus. The first plateau is at 30%. In Section

14.2.11 of SNUPPS, a 25% power level is referenced.

This is given as the power level which will not be

exceeded until major plant test requirements are

completed satisfactorily. Modify Section 14.2.5 to

clarify how the applicable startup test results will

be reviewed prior to exceeding 25% power as

referenced in Section 14.2.11 of SNUPPS.

RESPONSE See Section 14.2.11.

Q640.4 Section 14.2.11 of SNUPPS states that startup (14.2.11) test procedures will be available for NRC review at

least 60 days prior to fuel loading. Table 14.2-5

indicates that twenty of thirty-eight startup tests

will be in the procedure preparation, review and

approval stage at that time. Modify Table 14.2-5 to

indicate by a note or legend alteration that

complete procedures will be available for review in

the time frame stated in Section 14.2.11.

RESPONSE See Table 14.2-5.

Q640.4WC Appendix 3A states in the Section on Regulatory (14.2.7) Guide 1.58 that an alternative method for qualifying

nuclear power plant inspection, examination and

testing personnel will be used. Insufficient detail

is available to determine whether or not the

alternative qualification program provides the same

quality training. Expand the description of the

alternative qualification method in Appendix 3A or

delete this exception to Regulatory Guide 1.58.

Note: Regulatory Positions C.5, 6, 7, 8 and 10 of

Regulatory Guide 1.58 (Rev. 1, 9/80) apply to the

Wolf Creek nuclear station.

RESPONSE This area of review was covered by the NRC Management Structure and Technical Resources Review Team during the week of 1/18/82 at KG&E.

640-4 Rev. 0 WOLF CREEK Q640.5 Provide a commitment to include in your test program (14.2.12) the design features to prevent or mitigate

anticipated transients without scram (ATWS) that may

now, or in the future, be incorporated into your

plant design (Subsection 15.8).

RESPONSE See Section 15.8.

Q640.5WC Subsection 14.2.8.2 of SNUPPS refers to Section (14.2.8.2) 14.2.8 of the Site Addendum for additional site

specific information. SNUPPS-WC contains no such

information. Provide the following:

1) Specify which individual at Wolf Creek will be responsible for incorporating reactor operating

and testing experiences of similar power plants

during the Initial Test Program.

2) Subsection 14.2.8.1 of SNUPPS only references development of preoperational test procedures.

Provide information on how information or other

plant's experiences will be used in the

preparation of Phase II-IV testing.

RESPONSE See Section 14.2.8.

Q640.6 List those tests that will only be performed on the (14.2.12) first SNUPPS unit. In addition cite the criteria

that will be used during subsequent unit testing

programs to ensure that follow-on units perform in

an identical manner regarding those tests to be

deleted.

RESPONSE See Section 14.2.8.

640-5 Rev. 0 WOLF CREEK Q640.6WC Certain terminology used in the individual test (14.2.12) descriptions does not clearly indicate the source of

the acceptance criteria to be used in determining

test adequacy. An acceptable format for providing

acceptance criteria for test results includes any of

the following:

o Referencing technical specifications o Referencing specific sections of the FSAR

o Referencing vendor technical manuals

o Providing specific quantitative bounds (only if

the information cannot be provided in any of

the above ways).

Modify the individual test description subsection presented below or, if applicable, add a paragraph

to Subsection 14.2.12 that provides an acceptable

description of each of the nuclear terms.

1) Within design specification 14.2.12.1.1

1.2

1.3

2.1

2.2

2.3

2) In accordance with design 14.2.12.1.1
3) Responds properly 14.2.12.1.2

2.1

2.2

2.3 RESPONSE See response to Question 640.10 which provides a description of the terminology used.Q640.7 Identify any of the post-fuel loading tests (14.2.12.3) described in Section 14.2.12.3. which are not

essential towards the demonstration of conformance

with design requirements for structures, systems, components, and design features that meet any of the

following criteria:

1) Will be relied upon for safe shutdown and cooldown of the reactor under normal plant 640-6 Rev. 0 WOLF CREEK conditions and for maintaining the reactor in a safe condition for an extended shutdown period.
2) Will be relied upon for safe shutdown and cooldown of the reactor under transient

(infrequent or moderately frequent events)

conditions and postulated accident conditions, and for maintaining the reactor in a safe

condition for an extended shutdown period

following such conditions.

3) Will be relied upon for establishing conformance with safety limits or limiting

conditions for operation that will be included

in the facility technical specifications.

4) Are classified as engineered safety features or will be relied upon to support or assure the

operation of engineered safety features within

design limits.

5) Are assumed to function or for which credit is taken in the accident analysis for the facility

(as described in the Final Safety Analysis

Report).

6) Will be utilized to process, store, control, or limit the release of radioactive materials.

RESPONSE All post-fuel loading tests essential to demonstrate conformance with design requirements for structures, systems, components, and design features for the

criteria specified in Question 640.7, items (1) through (6) are included in

Section 14.2.12.3.

Q640.7WC Verify that the ultimate heat sink cooling pond (14.2.12) (Subsection 9.2.5) is tested to demonstrate adequate

NPSH and the absence of vortexing over range of

basin level from maximum to the minimum calculated

30 days following LOCA.

RESPONSE See Sections 9.2.1.2.2.2 and 14.2.12.1.2.

Q640.8 The objectives specified for several tests are in-(14.2.12.3) appropriate. In general, appropriate test

objectives are:

640-7 Rev. 0 WOLF CREEK o to measure o to calibrate

o to obtain data

o to document

o to verify performance Provide appropriate objectives for the following tests:

14.2.12.3.1 3.2

3.3

3.8

3.22

3.33

3.35 RESPONSE See Sections 14.2.12.3.1, 14.2.12.3.2, 14.2.12.3.3, 14.2.12.3.8, 14.2.12.3.22, and 14.2.12.3.33. Section 14.2.12.3.35 has been deleted.

Q640.8WC Table 14.2-1 (Sheet 4) of SNUPPS states that for (14.2) S-X3GD01, S-X3EF01, and S-X3NG01 the X in the test

numbers will be a U or a K, depending on the test

site. In SNUPPS-WC, Section 14.2.12, the tests are

listed as S-13GD01, S-3EF01, and S-3NG01. Modify

Section 14.2.12 of SNUPPS-WC or Table 14.2-1 of

SNUPPS to eliminate this discrepancy (the test

numbers on the non-safety related tests should also

be corrected).

RESPONSE See the test abstracts in Section 14.2.12. The test abstracts, as identified in Section 14.2.12, are numbered per the method used at WCGS.

Q640.9 It is unacceptable to reference test instructions (14.2.12.3) for test prerequisites. Provide acceptable

prerequisites for the following tests:

14.2.12.3.1 3.4

3.5

3.6

3.7

3.8.2.a 640-8 Rev. 0 WOLF CREEK 3.13 3.14

3.21

3.22

3.23

3.24

3.25.2.a

3.26

3.27

3.29

3.30

3.31

3.32

3.33

3.34.2.b

3.35 RESPONSE See Sections 14.2.12.3.1, 14.2.12.3.4, 14.2.12.3.5, 14.2.12.3.6, 14.2.12.3.7, 14.2.12.3.8, 14.2.12.3.13, 14.2.12.3.14, 14.2.12.3.21, 14.2.12.3.22, 14.2.12.3.23, 14.2.12.3.24, 14.2.12.3.25, 14.2.12.3.26, 14.2.12.3.27, 14.2.12.3.29, 14.2.12.3.30, 14.2.12.3.31, 14.2.12.3.32, 14.2.12.3.33, and

14.2.12.3.34. Section 14.2.12.3.35 has been deleted.

Q640.10 Certain terminology used in the individual test (14.2.12) descriptions does not clearly indicate the source of

the acceptance criteria to be used in determining

test adequacy. An acceptable format for providing

acceptance criteria for test results includes any of

the following:

o Referencing technical specifications o Referencing specific sections of the FSAR

o Referencing vendor technical manuals

o Providing specific quantitative bounds (only if

the information cannot be provided in any of

the above ways).

Modify the individual test description subsection presented below or, if applicable, add a paragraph

to Subsection 14.2.12 that provides an acceptable

description of each of the unclear terms.

640-9 Rev. 0 WOLF CREEK

1) Within design specifications 14.2.12.1.3 1.4

1.5

1.7

1.9

1.10

1.11

1.12

1.15 (2 times)

1.18 (2 times)

1.21 (2 times)

1.23 (2 times)

1.24

1.25 (2 times)

1.26 (2 times)

1.27

1.28 (3 times)

1.29 (3 times)

1.30

1.32 (2 times)

1.33 (4 times)

1.34 (3 times)

1.36

1.37 (3 times)

1.39

1.41 (3 times)

1.42 (2 times)

1.43

1.44 (2 times)

1.45 (2 times)

1.46

1.47

1.48

1.49

1.50 (2 times)

1.51 (2 times)

1.52

1.53

1.59

1.60 (2 times)

1.61 (2 times)

1.62

1.64 (6 times)

1.65

1.66 (2 times)

1.68 (2 times)

1.71 640-10 Rev. 0 WOLF CREEK 1.72 2.1

2.2 (2 times)

2.3 (2 times)

2.4

2.5

2.6 (2 times)

2.7

2.8

2.10

2.11 (2 times)

2.14 (2 times)

2.15

2.16

2.19

2.22 (2 times)

2.25

3.15

3.18 (2 times)

3.20 (2 times)

RESPONSE The acceptance criteria provided in the individual test descriptions meet the requirements of Regulatory Guide 1.70, Revision 3, Standard Format and Content

of Safety Analysis Reports for Nuclear Power Plants. It is not the intent of

the test descriptions to provide a source of the acceptance criteria or

specific quantitative values to be utilized to determine test adequacy. The

acceptance criteria provided is a summary of the acceptance criteria provided

in the individual test procedures, which contain the specific criteria against

which success or failure of the test procedure is judged.

2) In accordance with design, in accordance with system design 14.2.12.1.1 (2 times) 1.6 (2 times)

1.8

1.44

1.45

1.46

1.48

1.51

1.54

1.55

1.56 (2 times)

1.57 640-11 Rev. 0 WOLF CREEK 1.58 (2 times) 1.59

1.63 (2 times)

1.64 (4 times)

1.65 (2 times)

1.66

1.68

1.69

1.70

1.71 (2 times)

1.72

1.73

2.15

2.16 RESPONSE See the response to item (1).

3) In accordance with design specification, in accordance with system design specification 14.2.12.1.39 2.1

2.9

2.11

2.12

2.13

2.20

2.21 (2 times)

2.24

2.26 RESPONSE See the response to item (1).

4) Design 14.2.12.1.10

1.11

1.17

1.35

1.42

1.65 (3 times)

1.67 (5 times)

1.70

1.80

2.17

2.18 640-12 Rev. 0 WOLF CREEK 3.15 3.17

3.37 RESPONSE See the response to item (1).

5) Within design limits, without exceeding design limits, within the limits predicted by design

analyses, within design requirements 14.2.12.1.16 (2 times) 1.29

1.32

1.35

1.37

1.41

1.62

1.64

1.73

1.78

1.79

3.16 RESPONSE See the response to item (1).

6) Within allowable limits, within required limits

14.2.12.1.22 1.38

1.62 RESPONSE See Sections 14.2.12.1.22, 14.2.12.1.38, and 14.2.12.1.62.

7) Required

14.2.12.1.10 1.22

1.64 (10 times)

1.65 (2 times)

1.85 640-13 Rev. 0 WOLF CREEK RESPONSE See Sections 14.2.12.1.10, 14.2.12.1.22, 14.2.12.1.64, 14.2.12.1.65, and 14.2.12.1.85.

8) Rated

14.2.12.1.62 1.64 (2 times)

1.65

1.82 (3 times)

RESPONSE See Sections 14.2.12.1.62, 14.2.12.1.64, 14.2.12.1.65, and 14.2.12.1.82.

9) Responds, responds properly, properly respond

14.2.12.1.12 1.34

1.36

1.48

1.49

1.51 RESPONSE See Sections 14.2.12.1.12, 14.2.12.1.34, 14.2.12.1.36, 14.2.12.1.48, 14.2.12.1.49, and 14.2.12.1.51.

10) In accordance with test instructions, is provided in test instructions, meets the

requirements of the test instructions, consistent with the acceptance criteria given

in the test procedure, agrees with the

acceptance criteria given in the test

procedure, as required by the test instructions 14.2.12.1.74 1.75

1.76

3.2

3.6

3.7

3.8

3.11

3.13 640-14 Rev. 0 WOLF CREEK 3.14 3.23

3.30

3.31

3.32

3.33 RESPONSE See Sections 14.2.12.1.74, 14.2.12.3.2, 14.2.12.3.6, 14.2.12.3.7, 14.2.12.3.8, 14.2.12.3.11, 14.2.12.3.13, 14.2.12.3.14, 14.2.12.3.23, 14.2.12.3.30, 14.2.12.3.31, 14.2.12.3.32, and 14.2.12.3.33.

11) Shall not exceed code-allowable stresses, must not exceed their code-allowable limits at the

test or design conditions 14.2.12.1.80 1.81

3.37 (2 times)

RESPONSE The phrases "code-allowable stresses" and "code-allowable limits" are specific and consistent with the requirements in FSAR Section 3.0. This is a design

verification program and specifying the codes as acceptance criteria is

consistent with the design criteria.

12) Set point tolerances

14.2.12.1.2

RESPONSE The phrase "set point tolerances" is referring to the lift point (set point) and band (tolerances) at which the main steam safety valves lift. Specific

values are provided in the Test Procedure S-03AB02.

13) Acceptable

14.2.12.1.14 1.64 (2 times)

2.17

2.18 640-15 Rev. 0 WOLF CREEK RESPONSE See Sections 14.2.12.1.14, 14.2.12.1.64, 14.2.12.2.17, and 14.2.12.2.18.

14) Adequate

14.2.12.1.37 1.83 RESPONSE See Sections 14.2.12.1.37 and 14.2.12.1.83.

15) Approximate

14.2.12.1.14 1.80

3.37 RESPONSE See Sections 14.2.12.1.14, 14.2.12.1.80, and 14.2.12.3.37.

16) Predicted

14.2.12.1.14

RESPONSE See Section 14.2.12.1.14.

17) Verified

14.2.12.1.14 1.22 RESPONSE See Sections 14.2.12.1.14 and 14.2.12.1.22.

18) Fails safe

14.2.12.1.73 640-16 Rev. 0 WOLF CREEK RESPONSE See Section 14.2.12.1.73.

19) Operate satisfactorily per design

14.2.12.1.83

RESPONSE See Section 14.2.12.1.83.

20) Impair design functions

14.2.12.1.83

RESPONSE See Section 14.2.12.1.83.

21) Slightly above

14.2.12.1.20

RESPONSE See Section 14.2.12.3.19 and 14.2.12.3.20.

Q640.11 Our review of your initial test program description (14.2.12) disclosed that the operability of several of the

systems and components listed in Regulatory Guide

1.68 (Rev. 2), Appendix A, may not be demonstrated.

Expand your FSAR to include appropriate test

descriptions (or identify existing descriptions)

that address the following items from Appendix A, or

provide technical justification for any exceptions

to the guide in Subsection 14.2.7:

1) Preoperational Testing 1.a.(2)(i) RCS safety valves

RESPONSE Component testing is not within the scope of the Preoperational Test Program; therefore, no test abstracts are provided. See Section 3.9 (N) 3.2.1, Pump and

Valve Operability Program.

1.b.(1) Control rod drive system test 640-17 Rev. 0 WOLF CREEK RESPONSE This test cannot adequately be performed prior to core loading. The system is tested prior to operation as described in Section 14.2.12.3.25.

1.e.(5) Steam extraction system

RESPONSE The operability of the steam extraction system is verified in the Plant Performance Test, S-090007. See Section 14.2.12.2.27.

1.e.(6) Turbine stop, control, and intercept valves RESPONSE See new test descriptions, Section 14.2.12.2.28, Turbine Trip Test (S-04AC02), and Section 14.2.12.2.29, Turbine System Cold Test (S-04AC03).

1.e.(10) Feedwater heater and drain systems

RESPONSE See new test description, Section 14.2.12.2.33, Secondary Vent and Drain System Preoperational Test Procedure S-04AF01.

1.h Test of protective devices such as leaktight covers, structures, or

housings provided to protect

Engineered Safety Features from

flooding RESPONSE The equipment location of safety-related equipment is such that no credit is taken for the above-mentioned protective devices except that credit is taken

for watertight doors. These doors are verified in the penetration closure

program. 1.h.(8) Tanks and other sources of water used for ECCS 640-18 Rev. 0 WOLF CREEK RESPONSE The operability of the control circuits associated with the refueling water storage tank and condensate storage tank are verified in the Residual Heat

Removal (RHR) System Cold Preoperational Test Procedure S-03EJ01, and the

Condensate System Pre-operational Test Procedure S-04AD01, respectively. See

Sections 14.2.12.1.34 and 14.2.12.2.1.

The instrumentation associated with the containment sumps is tested in S-03EJ01. See Section 14.2.12.1.34.

1.i.(5) Containment airlock leak rate test

RESPONSE The containment air lock is leak tested in the Local Containment Leak Rate Test Procedure S-030002. See Section 14.2.12.1.78.

1.i.(12) Containment air purification and cleanup system RESPONSE See Section 14.2.12.1.51.

1.i.(15) Containment penetration pressurization system tests RESPONSE WCGS does not have a containment penetration pressurization system.

1.j.(6) Loose parts monitoring system

RESPONSE See Section 14.2.12.2.36.

1.j.(7) Leak detection system for ECCS and containment spray system outside of

containment 640-19 Rev. 0 WOLF CREEK RESPONSE See Section 14.2.12.2.32.

1.j.(8) Reactor control system

RESPONSE Instrument alignment and calibration is performed during the component test program. Sections 14.2.12.3.25, 14.2.12.3.26, and 14.2.12.3.29 demonstrate the

capability of the reactor control system during power ascension testing.

1.j.(9) Pressure control systems designed to prevent leakage across boundaries RESPONSE WCGS does not have a pressure control system to prevent leakage across boundaries.

1.j.(11) Traversing incore probe system

RESPONSE This test cannot adequately be performed prior to core loading. The system is tested prior to operation as described in Section 14.2.12.3.39.

1.j.(13) Incore nuclear instrumentation

RESPONSE This test cannot adequately be performed prior to core loading. The system is tested prior to operation as described in Section 14.2.12.3.39.

1.j.(14) Instrumentation and controls that affect transfers of water supplies to

auxiliary feedwater pumps, ECCS pumps, and containment spray pumps RESPONSE See Sections 14.2.12.1.7., 14.2.12.1.28, 14.2.12.1.34, and 14.2.12.1.41.

1.j.(16) Hotwell level control system 640-20 Rev. 0 WOLF CREEK RESPONSE Procedure S-04AD01, Condensate System Preoperational Test, verifies the operability of the hotwell level control system. See Section 14.2.12.2.1.

1.j.(17) Feedwater heater temperature, level, and bypass control systems RESPONSE See Section 14.2.12.2.33.

1.j.(18) Auxiliary startup instrument test

RESPONSE See Section 14.2.12.3.21.

1.j.(20) Instrumentation used to detect internal and external flooding RESPONSE See Sections 14.2.12.2.31 and 14.2.12.2.32 for the instrumentation used to detect internal flooding. The WCGS design does not provide instrumentation for

the detection of external flooding as all sites are "dry sites." 1.j.(22) Instrumentation that can be used to track the course of postulated

accidents such as containment sump

level monitors and humidity monitors RESPONSE The operability of instrumentation utilized to track the course of postulated accidents is verified in the test procedures associated with the system in

which the instrument belongs.

1.j.(24) Annunciators for reactor control and engineered safety features RESPONSE See Sections 14.2.12.1.71, 14.2.12.1.72, and 14.2.12.1.73, respectively. 640-21 Rev. 0 WOLF CREEK In addition to the above integrated annunciator testing, the annunciator points associated with various reactor functions and ESF components are also tested in

the individual system preoperational test procedures.

1.j.(25) Process computers

RESPONSE The computer was tested and software verified prior to startup testing. During the startup program, verification of these calculations performed by the

computer to ensure the plant is operating within technical specification limits

were performed and results compared to hand calculations, installed

instrumentation, or other analytical programs.

1.l.(4) Isolation features for steam generator blowdown RESPONSE See Section 14.2.12.1.72.

1.l.(7) Isolation features for liquid radwaste effluent systems RESPONSE See Section 14.2.12.2.6.

1.m.(4) Dynamic and static load testing of cranes, hoists, and associated

lifting and rigging equipment, including the fuel cask handling

crane. Static testing at 125% of

rated load and full operational

testing at 100% of rated load RESPONSE Static testing at 125% of rated loads and crane bridge, trolley, and hoist speeds at rated loads is addressed in revised Sections 14.2.12.1.54, 14.2.12.1.56, and 14.2.12.1.58. Operability of the fuel handling system, using

a dummy fuel assembly, is addressed in Section 14.2.12.1.56.

1.n.(2) Closed loop cooling water systems 640-22 Rev. 0 WOLF CREEK RESPONSE See Section 14.2.12.2.34.

1.n.(6) Chemistry control systems for the reactor coolant and secondary coolant

systems RESPONSE See Sections 14.2.12.1.27, 14.2.12.1.28, 14.2.12.1.29, and 14.2.12.2.30.

1.n.(9) Vent and drain systems for contaminated or potentially

contaminated systems RESPONSE See Section 14.2.12.2.32.

1.n.(10) Purification and cleanup systems for the reactor coolant system RESPONSE See Sections 14.2.12.1.27, 14.2.12.1.28, and 14.2.12.1.29.

1.n.(12) Boron recovery system

RESPONSE See Section 14.2.12.1.27 and Section 14.2.12.1.29.

1.n.(14)(c) Battery room ventilation

RESPONSE Proper ventilation to battery rooms 1 through 4 is supplied by the control building HVAC system, and is verified in Procedure S-03GK01. See Section

14.2.12.1.45. 640-23 Rev. 0 WOLF CREEK 1.n.(16) Cooling and heating systems for the refueling water storage tank RESPONSE There is no cooling system associated with the refueling water storage tank. A source of heat, which is non-safety related, is supplied from the auxiliary

steam system and is controlled by a temperature control valve, which is

operationally tested in Procedure S-03EC01.

1.o Reactor components handling systems RESPONSE See Sections 14.2.12.1.54 through 14.2.12.1.59. The non-permanently installed fuel handling equipment is periodically inspected and verified operational

prior to fuel handling evolutions.

2) Initial Fuel Load and Precritical Testing 2.a Shutdown margin verification for the fully loaded core RESPONSE The verification of shutdown margin for a fully loaded core is provided by controlling the boron concentration. See revised Section 14.2.12.3.1.

2.b Control rod withdrawal and insertion speeds, sequencers and protective

interlocks RESPONSE See Sections 14.2.12.1.73, 14.2.12.3.26 and 14.2.12.3.29.

2.d Final reactor coolant system leak rate test RESPONSE Determination of the reactor coolant system leak rate is not conducted as a startup test, but is verified on a frequent and routine basis in accordance

with the technical specifications, and will be verified prior to initial

criticality. 640-24 Rev. 0 WOLF CREEK

4) Low Power Testing 4.b Confirm by analysis that rod insertion limits will be adequate to ensure a

shutdown margin consistent with accident

analysis assumptions, with the greatest

worth control rod stuck out of the core.

RESPONSE Verification of rod worth is accomplished by procedure S-07SF08, RCCA or Bank Worth Measurement at Zero Power, Section 14.2.12.3.32. When the results of

this test meet the acceptance criteria, shutdown margin is assured by operation

within the insertion limits.

4.c Pseudo-rod-ejection test

RESPONSE See Sections 14.2.12.3.32, 14.2.12.3.33, and 14.2.12.3.38.

4.e Flux distribution determination

RESPONSE See Section 14.2.12.3.38.

4.f Neutron and gamma radiation surveys

RESPONSE See Section 14.2.12.3.40.

4.g Determination of proper response of process and effluent radiation monitors RESPONSE The operability of the radiation monitors is demonstrated during the Preoperational Test Program. See Sections 14.2.12.1.86, 14.2.12.2.23, and

14.2.12.2.26.

4.h Chemical and radiochemistry tests

RESPONSE The operability of the primary and secondary sampling systems is verified during the Preoperational Test Program. See Sections 640-25 Rev. 0 WOLF CREEK 14.2.12.2.22 and 14.2.12.2.26. In addition, chemistry is maintained within technical specification limits during the startup program, using plant

procedures.

4.i Demonstration of the operability of control rod withdrawal inhibit or block

functions over the reactor power level

range during which such features must be

operable RESPONSE See the response to question 640.11(2).2.b.

4.j Demonstration of the capability of the primary containment ventilation system.

RESPONSE See Section 14.2.12.2.27.

4.n Demonstration of the operability of the control room computer system RESPONSE See the response to question 640.11(1)1.j.(25).

4.r Demonstration of the operability of reactor coolant system purification and

cleanup systems RESPONSE Preoperational testing of the chemical and volume control system (CVCS) is addressed in Sections 14.2.12.1.24 through 14.2.12.1.29. The ability of the

CVCS to control boron concentration is demonstrated throughout the startup

program. In addition, the chemistry limits for continued operation during the

startup program are maintained within those limits provided in the technical

specifications. No additional testing is required.

4.t Performance of natural circulation tests of the reactor coolant system to determine

that adequate heat removal capability

exists. NUREG-0694 "TMI Related

Requirements for New Operating Licenses,"

Item I.G.1, requires applicants to perform

"a special low power testing program 640-26 Rev. 0 WOLF CREEK approved by NRC to be conducted at power levels no greater than 5 percent

for the purposes of providing

meaningful technical information beyond

that obtained in the normal startup

test program and to provide

supplemental training." To comply with

this requirement new PWR applicants

have committed to a series of natural

circulation tests. To date such tests

have been performed at the Sequoyah 1, North Anna 2, and Salem 2 facilities.

Based on the success of the programs at

these plants, the staff has concluded

that augmented natural circulation

training should be performed for all

future PWR operating licenses.

Includes descriptions of natural

circulation tests that, in addition to

validating the operating procedures, fulfill the following objectives:

Testing The tests should demonstrate the following plant characteristics: length of time required

to stabilize natural circulation, core flow

distribution, ability to establish and maintain

natural circulation with or without onsite and

offsite power, the ability to uniformly borate

and cool down to hot shutdown conditions using

natural circulation, and subcooling monitor

performance.

Training Each licensed reactor operator (RO or SRO who performs RO or SRO duties, respectively) should

participate in the initiation, maintenance and

recovery from natural circulation mode.

Operators should be able to recognize when

natural circulation has stabilized, and should

be able to control saturation margin, RCS

pressure, and heat removal rate without

exceeding specified operating limits.

If these tests have been performed at a comparable prototype plant, they need to be

repeated only to the extent necessary to

accomplish the above training objectives. 640-27 Rev. 0 WOLF CREEK RESPONSE See Chapter 18, item I.G.1. A test description for the natural circulation test is provided in Section 14.2.12.3.41.

5) Power-Ascension Tests 5.b Determine that steady-state core performance is in accordance with design RESPONSE See Section 14.2.12.3.38.

5.d Demonstrate the capabilities of plant features and procedures for controlling

core xenon transients RESPONSE Xenon oscillation tests have been performed on other Westinghouse four-loop plants, and results have been documented and approved by the NRC. The

procedures associated with the control of xenon transients utilize similar

methods as those utilized for the reference plant.

5.e Pseudo-rod-ejection test

RESPONSE See the response to question 640.11(4).4.c.

5.f Single rod insertion and withdrawal

RESPONSE This test is scheduled at 50-percent power. See Section 14.2.12.3.33 and 14.2.12.3.38.

5.g Demonstrate operation of the control rod sequencers, and rod withdrawal block

functions RESPONSE See the response to question 640.11.(2).2.b. 640-28 Rev. 0 WOLF CREEK 5.h Check rod scram times from data recorded during the startup test phase RESPONSE Not applicable (BWR only).

5.i Demonstrate the capability of incore and excore neutron flux instrumentation to

detect a control rod misalignment equal to

or less than the technical specification

limits RESPONSE It is not a design requirement of the excore neutron detectors to be capable of detecting a control rod misalignment equal to or less than technical

specifications limits. The WCGS design relies on the rod position indication

system to provide indication of rod misalignment, with the incore neutron flux

instrumentation being available to further investigate the misalignment.

The design analysis allows a rod misalignment of 15 inches. The technical specifications require that the rods be within 7-1/2 inches of the demanded

position. This requirement, along with the accuracy of the rod position

indication system, which is less than 7-1/2 inches, ensures that the maximum

misalignment could be no greater than 15 inches. The rod position indication

system will detect this misalignment and is tested in Procedure S-07SF04. See

Section 14.2.12.3.28.

In addition, during the RCCA or Bank Worth Measurement at Power Test, Procedure S-07SF09, measurements are made with incore detectors at incremental

rod insertion levels to acquaint operating personnel with methods of detection

of misaligned rods, but the misalignment is generally greater than that allowed

by the technical specifications.

5.l Demonstrate design capability of all systems and components provided to remove

residual or decay heat from the reactor

coolant system RESPONSE See Sections 14.2.12.1.1, 14.2.12.1.7, 14.2.12.1.8, 14.2.12.1.13, 14.2.12.1.35, and 14.2.12.3.14. 640-29 Rev. 0 WOLF CREEK 5.m Demonstrate that reverse flows through idle loops and differential pressures

across the core are in agreement with

design values RESPONSE Not applicable. The WCGS design requires the operation of all four reactor coolant pumps at power.

5.n Obtain baseline data for reactor coolant system loose parts monitoring system RESPONSE See the response to question 640.11.(1).1.j.(6).

5.r Verification of input to, and output from control room process computer RESPONSE See the response to question 640.11.(1).1.j.(25).

5.s Verify the performance of the auxiliary feedwater control system, the hotwell

level control system, steam pressure

control system, and the reactor coolant

makeup and letdown control systems RESPONSE See Sections 14.2.12.1.7, 14.2.12.1.29, 14.2.12.2.1, 14.2.12.3.11, 14.2.12.3.14, 14.2.12.1.8, 14.2.12.1.27, and 14.2.12.2.27.

5.t Verify the response times, relieving capacities, and reset pressures for the

pressurizer relief valves; main steam line

safety valves; atmospheric relief valves; and the turbine bypass valves RESPONSE See the response to question 640.13 and Sections 14.2.12.1.1, 14.2.12.1.2, 14.2.12.1.4, 14.2.12.1.12, and 14.2.12.1.21. 640-30 Rev. 13 WOLF CREEK 5.u Verify operability and response times of main steam line isolation and branch steam

line isolation valves RESPONSE See Section 14.2.12.1.4.

5.v Verification of main steam system and feedwater system performance RESPONSE See Sections 14.2.12.1.7, 14.2.12.1.8, 14.2.12.2.27, 14.2.12.3.11, 14.2.12.3.13, 14.2.12.3.14, 14.2.12.3.37, 14.2.12.1.87 and 14.2.12.1.88.

5.w Demonstrate that concrete temperatures surrounding hot penetrations do not exceed

design limits.

RESPONSE Concrete temperatures surrounding hot penetrations are monitored during the Plant Performance Test S-090007.

5.y Verify the proper operation of the incore nuclear instrumentation and instruments

and systems used to perform a heat balance RESPONSE See Sections 14.2.12.3.22, 14.2.12.3.24, and 14.2.12.3.39.

5.z Demonstrate that process and effluent radiation monitoring systems are

responding correctly RESPONSE See the response to question 640.11.(4).4.g.

5.aa Demonstrate the operation of the chemical and radiochemical control systems RESPONSE See the response to question 640.11.(4).4.h. 640-31 Rev. 0 WOLF CREEK 5.bb Conduct neutron and gamma radiation surveys to establish the adequacy of

shielding RESPONSE See the response to question 640.11.(4).4.f.

5.cc Demonstrate the operation of the gas-eous and liquid radioactive waste

processing, storage, and release systems RESPONSE Preoperational testing of the gaseous and liquid radwaste systems is addressed in Sections 14.2.12.1.52, 14.2.12.2.6, and 14.2.12.2.7. These

systems are in operation during power ascension to support plant operation.

5.ff Demonstrate that ventilation systems maintain design temperatures RESPONSE See Section 14.2.12.2.27.

5.ii Demonstrate that the dynamic response of the plant is in accordance with design

for limiting reactor coolant pump trips RESPONSE See the response to Regulatory Guide 1.68, Revision 2, in Appendix 3A.

5.kk Demonstrate that the dynamic response of the plant is in accordance with design

for the loss of or bypassing of the

feedwater heaters RESPONSE See the response to Regulatory Guide 1.68, Revision 2, in Appendix 3A and Section 14.2.12.3.42. 640-32 Rev. 0 WOLF CREEK 5.mm Demonstrate that the dynamic response of the plant is in accordance with design

for the case of automatic closure of all

main steam line isolation valves at 100

percent reactor power RESPONSE See the response to Regulatory Guide 1.68, Revision 2, in Appendix 3A.

5.nn Demonstrate that the dynamic response of the plant is in accordance with design

for the case of full load rejection

(tripping of the main generator breakers)

RESPONSE The plant trip from 100-percent power will be initiated by opening the main generator output breakers. See Section 14.2.12.3.11.

Q640.12 We could not conclude from our review of your (14.2.12) individual test descriptions that comprehensive

testing is scheduled for several systems and

components. Therefore, clarify or expand the

appropriate test descriptions to address the

following items:

1) 14.2.12.1.1 - Clarify, or reference the FSAR section which clarifies, the purpose

of a decreasing condenser pressure signal.

RESPONSE See Section 14.2.12.1.1.

2) 14.2.12.1.5 - Provide acceptance criteria for steam generator feedwater pump

operation.

RESPONSE The main feedwater system preoperational test, S-03AE01, performs the initial operation of the steam generator feedwater pumps, using auxiliary steam. The

final acceptance of the steam generator feedwater pumps is demonstrated during

the Automatic Steam Generator Level Control Test Procedure S-07AB01. See

revised Section 14.2.12.3.13. 640-33 Rev. 0 WOLF CREEK

3) 14.2.12.1.7 - Subsection 10.4.9.2.3 indicates four separate actuation signals

can cause an automatic start of the motor-

driven auxiliary feed pump. Ensure these

four are included in your test description

acceptance criteria.

RESPONSE The Auxiliary Feedwater Motor-Driven Pump and Valve Preoperational Test Procedure S-03AL01 verifies the automatic start of the motor-driven pumps on

receipt of an ESFAS signal. The Engineered Safeguards (BOP) Preoperational Test

Procedure S-03SA02 verifies the input signals identified above. See Section

14.2.12.1.72.

4) 14.2.12.1.8 - Our review of licensee event reports has disclosed several instances of

turbine-driven auxiliary feedwater pump

failure to start on demand. It appears

that many of these failures could have

been avoided if more thorough testing had

been conducted during the plant's initial

test programs. In order to discover any

problems affecting pump startup and to

demonstrate the reliability of your

emergency cooling system, state your plans

to demonstrate at least five consecutive, successful, cold quick pump starts during

your initial test program.

RESPONSE The ability of the turbine-driven auxiliary feedwater pumps to successfully undergo five consecutive cold starts was demonstrated in the Auxiliary

Feedwater Turbine-Driven Pump and Valve Preoperational Test Procedure S-03AL02.

See Section 14.2.12.1.8.

5) 14.2.12.1.9 - Commit to verifying operation of any pump permissive

interlocks which serve to prevent cold

water addition accidents or serve to

protect RCS components from excessive

differential pressures at low

temperatures. 640-34 Rev. 0 WOLF CREEK RESPONSE There are no reactor coolant pump permissive interlocks that serve to prevent cold water addition accidents or protect RCS components from excessive

differential pressures at low temperatures. The WCGS design does not allow

operating at power with less than four reactor coolant pumps in operation.

6) 14.2.12.1.17 and 14.2.12.1.18 - State that flow and coastdown testing will be

performed for all permissible combinations

of pump operation.

RESPONSE The Reactor Coolant System Flow Measurement Procedure, S-03BB09, confirms that the reactor coolant flow rate in each loop, without the core installed, is

greater than design. See Section 14.2.12.1.17. The Reactor Coolant System

Flow Coastdown Test, S-03BB10, determines the rate of change of reactor coolant

flow, for the configurations identified in the accident analysis, for a

decrease in reactor coolant system flow, Section 15.3. See Section

14.2.12.1.18. It is not the intent of the above procedures to verify all

permissible combinations of pump operation.

7) 14.2.12.1.29 - Verify that the maximum obtainable boron dilution rate is less

than or equal to that assumed in your

accident analysis (Subsection 15.4.6).

RESPONSE Preoperational tests S-03BG01, S-03BG03, S-03BG04, S-03BG05, S-03BG06, and S-04BL01 demonstrated the performance characteristics of the charging and reactor

makeup water pumps in various system configurations. Procedure S-03BG06 also

verified that the letdown flowrates from the reactor coolant system are within

design specifications. Due to the conservatism provided in the accident

analysis, subsection 15.4.6, as related to the given dilution flow for the

postulated conditions, and considering the data obtained in the above

procedures, no additional testing should be necessary to verify the protection

margin to dilution. See Sections 14.2.12.1.24, 14.2.12.1.26, 14.2.12.1.27, 14.2.12.1.28, 14.2.12.1.29, and 14.2.12.2.2.

8) 14.2.12.1.34 - Ensure that the interlocks and isolation valves for overpressure

protection of the RHR system are tested

(Subsection 5.4.7.2.5). 640-35 Rev. 0 WOLF CREEK RESPONSE The interlocks and isolation valves for over pressure protection of the RHR system were tested in the RHR System Cold Preoperational Test Procedure S-

03EJ01. 9) 14.2.12.1.39 - State which safety signals are used to test boron recirculation pump

and valve response.

RESPONSE See Section 14.2.12.1.39.

10) 14.2.12.1.40 - Verify that paths for the air-flow test of containment spray nozzles

overlap the water-flow test paths of the

pumps to demonstrate that there is no

blockage in the flow path.

RESPONSE The supply path for the air-flow test of the containment spray nozzles, verified in Procedure S-03EN01, and the water discharge path of the containment

spray pumps, verified in Procedure S-03EN02, utilize the same test connection, therefore ensuring that no blockage exists in the system flow path.

11) 14.2.12.1.41 - State which safety signals are used to test containment spray pump

and valve response.

RESPONSE See Section 14.2.12.1.41.

12) 14.2.12.1.48 - Verify that the cooling fans can operate in accordance with design

requirements at the containment design

peak accident pressure.

RESPONSE The ability of the containment cooling fans to operate at the containment design peak accident pressure was verified during performance of the Integrated

Containment Leak Rate Test Procedure S-030001. See Section 14.2.12.1.77. 640-36 Rev. 0 WOLF CREEK

13) 14.2.12.1.64 - a) Verify that the transfer pump flow capacity (Subsection

14.2.12.1.53) is sufficient to satisfy the

fuel oil consumption rates. b) Ensure

that the 2 hr. and 22 hr. load tests are

accomplished within a 24 hr. period.

RESPONSE a) The fuel oil transfer pump capacity, determined in Procedure S-03JE01 (Section 14.2.12.1.53), was compared with the fuel

consumption rate determined in Procedure S-03NF02 (Section

14.2.12.1.64) to verify that the pump capacity exceeds the

consumption rate.

b) The 2-hour and 22-hour load tests were performed within a 24-hour period.

14) 14.2.12.1.73 - a) Account for process-to-sensor hardware (e.g., instrument lines, hydraulic snubbers) delay times; b)

Provide assurance that the response time

of each primary sensor is acceptable; and

c) Provide assurance that the total

reactor protection system response time is

consistent with your accident analysis

assumptions.

Note: Item 2 can be accomplished by

measuring the response time of each

sensor during the preoperational test, ensuring that the response time of each

sensor will be measured by the

manufacturer within two years prior to

fuel loading, or describing the

manufacturer's certification process in

sufficient detail for us to conclude that

the sensor response times are in

accordance with design.

RESPONSE a) See the response to Regulatory Guide 1.118, Revision 2, in Appendix 3A.

b) See the response to item (a).

c) The response times identified as acceptance criteria in Procedure S-03SB01 (14.2.12.1.73) are consistent with the

technical specifications and other design documents. 640-37 Rev. 0 WOLF CREEK

15) 14.2.12.2.6 - Verify that the operability of your liquid radwaste system will be

demonstrated by actually processing

representative chemical waste streams.

RESPONSE The Liquid Radwaste System Preoperational Test Procedure S-04HB01, utilizes various chemicals to verify the operability of the reverse osmosis unit.

Chemical waste streams were not injected in other portions of the system, since

it was not the intent of the preoperational test program to unnecessarily

contaminate the system. Adequate data was recorded during the Preoperational

Test Program to evaluate the system properly. The system has design provisions (i.e., heat tracing, pipe routing) to ensure proper functioning during

operation with actual chemical waste streams. The ability of the liquid

radwaste system to process wastes is accomplished during plant operations when

wastes are generated.

16) 14.2.12.3.7 - Ensure that the moderator temperature coefficient will be derived, and that it meets the applicable criteria.

RESPONSE See Section 14.2.12.3.7.

17) 14.2.12.3.9 - Include testing at approximately 50% power. Commit to

performing step and ramp changes of full

design value, or explain how changes of a

lower value can be used to determine the

proper response to design load swings.

RESPONSE See the response to Regulatory Guide 1.68, Revision 2, in Appendix 3A.

18) 14.2.12.3.27 - Commit to retesting rods, whose scram times fall outside the two-

sigma limit, at least three additional

times.

RESPONSE The Rod Drop Time Measurement Test Procedure S-07SF03 retests any rods, whose scram times fall outside the two-sigma limit, at least three additional times. 640-38 Rev. 0 WOLF CREEK Q640.13 We have noted on other plant startups that the (14.2.12) capacities of pressurizer or main steam power-operated relief valves are sometimes in excess of

the values assumed in the accident analyses for

inadvertent opening or failure of these valves.

Provide a description of the initial plant test or

manufacturer's test that demonstrates that the

capacity of these valves is consistent with your

accident analysis assumptions.

RESPONSE See Section 18.2.5 for performance testing of the pressurizer power-operated relief valves.

The specification for the main steam atmospheric relief valves required that no single valve capacity be greater than the value specified in the accident analysis (970,000 lbm/hr).

The valve manufacturer has indicated that the maximum flow through the valve based on design inlet pressure conditions with the valve full open is 670,000

lbm/hr. This value was determined using flow coefficients and calculational

methods in accordance with ANSI/ISA approved standards.

Due to the significant margin between the actual valve capacity and the value provided in the safety analysis, no capacity testing is required.

Q640.14 Commit to the demonstration of the operability of (14.2.12.1) the temperature sensors downstream of the primary

power operated relief valves and safety valves

(Figure 5.1-1, Sheet 2).

RESPONSE The pressurizer relief valve and PRT Hot Preoperational Test Procedure, S-03BB13 (Section 14.2.12.1.21), verified the operability of the temperature

sensors downstream of the power-operated relief valves and safety valves.

Q640.15 Failure of pressurizer overpressure protection (14.2.12) valves to reseat, coupled with false position

indication has occurred recently. One possible

failure cause which has been identified was galling

of the valve body due to dry stroking the valves

when setting release limits. Explain what

procedures will be used to protect valves during

limit setting. 640-39 Rev. 13 WOLF CREEK RESPONSE After the pressurizer power operated relief valves have been installed in the system, the valves can be stroked since the valves are shipped in a closed

position precluding any foreign material from lodging on the valve seat. Prior

to preoperational testing, the valve calibration is performed which checks the

closed, mid, and open positions as a minimum. This range is compared to the

stroke distance of the valve to check proper travel. The limit switches and/or

position indication is then set.

During operation, a periodic calibration schedule is maintained for use in checking the pressurizer power operated relief valves. At the time of

calibration, the proper clearance is obtained which will isolate and/or provide

the proper alignment. The valves are inspected for any damage or leaks. The

open, mid, and closed positions, as a minimum, are recorded. These values are

compared with the requirements in written and approved procedures to verify the

travel and range.

Q640.16 Verify that functional testing performed on valves (14.2.12.1) with two actuation trains, such as the Main Steam

(Subsection 10.3.2.2) and Main Feedwater (Subsection

10.4.7.2.2) Isolation Valves, includes verification

of the operability of each actuation train.

RESPONSE For those valves having two actuation trains, the operability of each actuation train is verified. See Sections 14.2.12.1.71 and 14.2.12.1.72.

Q640.17 Correct the following deficiencies that were noted (14.2.12.1) in your Containment Isolation Valve test

description:

1) Subsection 14.2.12.1.10 states that Pressurizer Relief Tank Nitrogen Isolation

Valves shut upon receiving a CIS, but

these valves do not appear in Table 6.2.4-

1.
2) The following valves should close upon receiving a CIS (Table 6.2.4-1) but are

not specifically addressed in your test

procedure descriptions: 640-40 Rev. 0 WOLF CREEK HV-7,8 - Containment Spray Recirculation FV Instrument Air to Reactor Building

FV-95,96 - Reactor Sump Pump to Floor

Drain Tank

HV-8843 - Boron Injection Tank to CIS Test

Line

3) Containment isolation valves should be tested in an integrated manner in as much

as practicable. Note that a commitment

satisfying this intent could be made in

Subsection 14.2.12.1.71.4.C.

RESPONSE 1) See penetration P-62 on Sheet 2 of Table 6.2.4-1. Figure 6.2.4-1, Page 44 indicates that the valves close on receipt of

a CIS.

2) The operability of containment isolation valves on receipt of a containment isolation signal was verified in the

preoperational tests associated with the system to which the

valve belongs. In addition, the response of the valves to a

containment isolation signal was verified in the Engineered

Safeguards (NSSS) Preoperational Test Procedure S-03SA01. See

Section 14.2.12.1.71.

3) The intent of Procedure S-03SA01, Engineered Safeguards (NSSS)

Preoperational Test, is to provide an integrated test inasmuch

as practicable.

Q640.18 Provide test descriptions 1) that will verify that (14.2.12.1) the plant's ventilation systems are adequate to

maintain all ESF equipment within its design

temperature range during normal operations; and 2)

that will verify that the emergency ventilation

systems are capable of maintaining all ESF equipment

within their design temperature range with the

equipment operating in a manner that will produce

the maximum heat load in the compartment. If it is

not practical to produce maximum heat loads in a

compartment, describe the methods that will be used

to verify design heat removal capability of the

emergency ventilation systems. 640-41 Rev. 0 WOLF CREEK Note that it is not apparent that post-accident design heat loads will be produced in ESF equipment

rooms during the power ascension test phase;

therefore, simply assuring that area temperatures

remain within design limits during this period will

probably not demonstrate the design heat removal

capability of these systems. It will be necessary

to include measurement of air and cooling water

temperature and flows and the extrapolations used to

verify that the ventilation systems can remove the

postulated post-accident heat loads.

RESPONSE The Plant Performance Test Procedure S-090007 (Section 14.2.12.2.27), records ambient room temperatures throughout the plant and cooling water system

conditions during hot functional testing and power ascension. The recorded

temperatures are evaluated to determine potential problems.

The ability of the ESF pump room coolers to maintain the ESF pump rooms within their design limits, for the conditions specified in Section 9.4.3.3, is

verified throughout the test program. Each room is monitored during the period

when the largest heat load is present. See Sections 14.2.12.1.29, 14.2.12.1.35, 14.2.12.1.37, 14.2.12.1.41, and 14.2.12.1.87. For rooms that do

not have coolers (e.g., diesel generator rooms) the WCGS program of verifying

the fan capacity provides adequate system verification.

Maintaining the containment air temperature within design limits is verified during the highest attainable heat load. See Section 14.2.12.2.27.

Containment cooler fan capacity and proper cooling water flow are verified.

See Sections 14.2.12.1.48 and 14.2.12.1.32, respectively. Containment cooler

operation at design peak accident pressure is also verified. See Section

14.2.12.1.77.

Since the containment air cooler post-accident heat removal mechanism is mainly steam condensation, and the normal operation heat removal mechanism is the

cooling of the air stream with little or no condensation, it is not possible to

accurately extrapolate preoperational test data to verify the post-accident

heat removal capability. On WCGS, the heat removal capability of the

containment air coolers is accurately determined by sophisticated mathematical

and computer modeling developed by the air cooler supplier. The accuracy of

the model was verified during the prototype testing of three different coils at

three different post-accident pressures. Topical Report AAF-TR-7101 (Reference

1 to USAR Section 6.2.2.3) provides a comparison of the 640-42 Rev. 0 WOLF CREEK measured heat removal during the tests to the computer analysis predictions.

The comparisons show very close agreement between the predicted and actual heat

removal abilities. The NRC has approved the topical report for reference in

Construction Permit and Operating License applications.

Q640.19 Modify the appropriate test description of the (14.2.12.1) Engineered Safety Features System to ensure that the

following items are addressed:

1) The starting of the ESF pumps should be verified for both emergency and normal

power sources.

2) The SI and RHR pumps should be run under full flow conditions to verify an adequate

margin to electrical trip.

3) ESF pumps should be verified able to start under maximum startup loading conditions.
4) Present or reference the full flow analysis done to satisfy the intent of

Regulatory Guide 1.79, C.la(2), as

committed to in Appendix 3A.

5) Ensure that the recirculation portion of the ECCS Sump Test (Subsection

14.2.12.1.83) verifies a value of NPSH

greater than that required under accident

temperature conditions.

RESPONSE 1) The ESF pumps were started off normal and emergency power sources in the LOCA Sequencer Preoperational Test Procedure S-

03NF02. See Section 14.2.12.1.64.

2) The SI and RHR pumps were run at full flow in accordance with the tests described in Sections 14.2.12.1.34, 14.2.12.1.37, and 14.2.12.1.64.
3) See Sections 14.2.12.1.64 and 14.2.12.1.65.
4) See the response to Regulatory Guide 1.79, Revision 1, in Appendix 3A. 640-43 Rev. 0 WOLF CREEK
5) Hydraulic model testing has been performed in lieu of the initially planned in-plant test. Data obtained during model

testing together with known pressure drops across suction

lines and valves (determined using standard engineering

calculations) verified that the available NPSH is equal to or

greater than that required at accident temperatures.

Q640.20 Recently, questions have arisen concerning the (14.2.12.1) operability and dependability of certain ESF pumps.

Upon investigation, the staff found that some

completed preoperational test procedures did not

describe the test conditions in sufficient detail.

Provide assurance that the preoperational test

procedures for ECCS and containment spray pumps will

require recording the status of the pumped fluid

(e.g., pressure, temperature, chemistry, amount of

debris) and the duration of testing for each pump.

In addition, provide preoperational test

descriptions to verify that each engineered safety

feature pump operates in accordance with the

manufacturer's head-flow curve. Include in the

description the bases for the acceptance criteria.

(The bases provided should consider both flow

requirements for ESF functions and pump NPSH

requirements).

RESPONSE The preoperational test descriptions requested are presently included. See Sections 14.2.12.1.34, 14.2.12.1.37, and 14.2.12.1.41.

Q640.21 Our review of licensee event reports has disclosed (14.2.12.1) that many events have occurred because of dirt, condensed moisture, or other foreign objects inside

instruments and electrical components (e.g., relays, switches, breakers). Describe administrative

controls that will be implemented to prevent

component failures such as these at your facility

including precautions that will be taken during

initial testing program.

RESPONSE Components such as relays, instruments, etc., are inspected prior to initial operation. At this time, a visual and/or functional check is performed. After

installation, but prior to preoperational testing, the item is checked and

calibrated if applicable. These measures should prevent component failure due

to dirt, moisture, or other foreign objects. 640-44 Rev. 0 WOLF CREEK During operation, a periodic calibration or preventive maintenance schedule is maintained for use in checking equipment. At this time, a check is made for

damage and obstructions. These activities should prevent component failure, since they are performed on a regular basis during operation.

Q640.22 For your DC Power System tests (Subsections (14.2.12) 14.2.12.1.67, 14.2.12.2.17 and 18), verify that

individual cell limits are not exceeded during the

design discharge test and demonstrate that the DC

loads will function as necessary to assure plant

safety at a battery terminal voltage equal to the

acceptance criterion that has been established for

minimum battery terminal voltage for the discharge

load test. Assure that each battery charger is

capable of floating the battery on the bus or

recharging the completely discharged battery within

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> while supplying the largest combined

demands of the various steady-state loads under all

plant operating conditions.

RESPONSE The 125-V (Class 1E) DC System Preoperational Test, S-03NK01; 250-V DC System Preoperational Test, S-04PJ01; and 125-V (Non-Class 1E) DC System

Preoperational Test, S-04PK01 verify that individual cell limits are not

exceeded during the performance of their design discharge test. Section

14.2.12.1.64 addresses the verification of the safety-related 125-V DC system

at minimum voltage. The ability of the battery chargers to recharge their

associated battery to normal conditions, after the battery has undergone a

design duty cycle, while simultaneously supplying power at a rate equivalent to

the design emergency loading, largest motor current load, and the design load, within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is verified in procedures S-03NK01, S-04PJ01, and S-04PK01, respectively.

Q640.23 Your test descriptions are not sufficiently (14.2.12) detailed to ascertain if the voltage levels at the

safety-related buses are optimized for the full load

and minimum load conditions that are expected

throughout the anticipated range of voltage

variations of the offsite power source by

appropriate adjustment of the voltage tap settings

of the intervening transformers. We require that

the adequacy of the design in this regard be

verified by actual measurement and by correlation of

measured values with analysis results. Provide a

description of the method for making this

verification. 640-45 Rev. 0 WOLF CREEK RESPONSE The Electrical Distribution System Voltage Verification Test Procedure S-090023 collects the data to be utilized to verify electrical system voltage analysis.

See Section 14.2.12.2.35.

Q640.24 Make a commitment in your test procedure descrip-(14.2.12.1) tions to perform the pre- and post- hot functional

examination for integrity as described in Subsection

3.9(N).2.4.

RESPONSE See Section 14.2.12.1.13.

Q640.25 There are a number of discrepancies between Tables (14.2) 14.2-1 and Table 14.2-4. Make the appropriate

corrections to address the following problems:

1) S-03BBll Reactor Coolant System Hydrostatic Test is included in Table

14.2-1 (Sheet 1) but missing from Table

14.2-4.

2) S-X3NG01 480-V Class IE System Preoperational Test is included in Table

14.2-1 (Sheet 4) but missing from Table

14.2-4.

RESPONSE 1) See Table 14.2-4.

2) See Table 14.2-4.

Q640.26 Table 14.2-5 (Sheet 3) lists S-090007 Plant Perform-(14.2) ance Test as one of the startup tests. This test is

not included in Table 14.2-3. Provide a footnote

indicating that the test is a continuation of a

nonsafety-related preoperational test.

RESPONSE See Table 14.2-5. 640-46 Rev. 0 WOLF CREEK Q640.27 Table 14.2-5 does not in many cases clearly in-(14.2) dicate the power levels specified by the test method

portion of the individual startup test

descriptions. Modify Table 14.2-5 to indicate the

power level or plateau at which each of the

individual startup tests will be conducted.

RESPONSE Table 14.2-5 has been revised to indicate the power levels specified in the test descriptions. It is not the intent of Table 14.2-5 to indicate the

plateaus at which the tests are performed. Table 14.2-5 indicates the power

level at which the tests begin and end. The test descriptions and test

procedures indicate the plateaus at which testing is performed.

See Table 14.2-5 and the individual test descriptions.

Q640.28 The response to Item 640.18 on the Plant Per-(14.2.12) formance Test (FSAR Subsection 14.2.12.2.27) should

restate that the heat removal capability of the

containment air coolers will be verified by

extrapolation of data taken from the actual test

conditions to the postulated post-accident heat load

condition.

RESPONSE Post-accident heat removal is predominantly by steam condensation ( 97 percent) while the plant performance test verifies the convective cooling capability of the containment air coolers. Extrapolation of test data to postulated post-

accident conditions, as requested, is thus not appropriate. Verification of

post-accident heat removal capability is provided via the vendor's Topical

Report which has been reviewed and approved for this purpose by the NRC (American Air Filter Topical Report, TR-7101). The response to Question 640.18

in the WCGS USAR has been revised to document this response and to reference

the Topical Report via USAR Section 6.2.2.3.

Q640.29 Recent FSAR revisions have made modification to (14.2.12) various test abstracts. Provide technical

justification for each of the following test

abstract modifications, or modify the test abstracts

accordingly. 640-47 Rev. 0 WOLF CREEK

1) The Spent Fuel Pool Crane Preoperational Test (FSAR Subsection 14.2.12.1.54) should reinstate

acceptance criteria regarding proper operation

of the control circuits and associated

interlocks.

2) The LOCA Sequencer Preoperational Test (FSAR Subsection 14.2.12.1.64) should reinstate

acceptance criteria for load group 2 and diesel

generator operation (Acceptance Criteria items

j through p have been deleted).

3) The Reactor Protection System Logic Test (FSAR Subsection 14.2.12.1.73) should reinstate the

acceptance criteria for all loop response times

measured in the test method.

4) The Plant Performance Test (FSAR Subsection 14.2.12.2.27) should provide objectives and

test method regarding evacuation alarm

audibility. Alternatively, the Public Address

System Preoperational Test (FSAR subsection

14.2.12.2.21) should provide acceptance

criteria regarding evacuation alarm audibility

in high noise areas.

RESPONSE 1) The test procedure as written for Wolf Creek include an acceptance criterion as requested.

2) These acceptance criteria were deleted inadvertently and have been reinstated as requested.
3) All loop response times are measured and recorded in this test. Response times for five of the trips are compared to

typical Westinghouse values but are not subject to WCGS

specific acceptance criteria since neither the WCGS USAR nor

the Technical Specifications establish quantitative limits for

these trips. NRC Office of Inspection and Enforcement, Region

III, raised this issue at Callaway in inspection report 50-

483/84-01(DE), February 22, 1984. After discussion and

further review, Region III concluded that the test approach, as described previously, was acceptable. Disposition of this

item is documented in inspection report 50-483/84-09, May 9, 1984. 640-48 Rev. 0 WOLF CREEK

4) The Plant Performance Test Abstract (S-090007) has been modified to include evacuation alarm audibility in the

objective as requested. The test method statement previously

in the abstract, together with the note under acceptance

criteria, provides a reasonable description of the means by

which audibility is verified. Operators are dispatched

throughout the plant to verify audibility and log location and

acceptability on appropriate data sheets. Problem areas are

reported for corrective action.

Much of the alarm audibility testing at WCGS was performed in conjunction with test S-04QF01, the public address system

preoperational test. The test procedure included an

acceptance criterion requiring alarm audibility in high noise

areas. This criterion implements a portion of the more

general one in the abstract, "The evacuation alarm system

operates in accordance with system design specifications."

This test was performed during hot functional testing high

noise conditions at WCGS. Testing performed under S-04QF01 to

the requirements of S-090007 was not repeated for the plant

performance test. 640-49 Rev. 0 WOLF CREEK Q730.1 The Atomic Safety and Licensing Appeal Board in ALAB-444 determined that the Safety Evaluation

Report for each plant should contain an assessment

of each significant unresolved generic safety

question. It is the staff's view that the generic

issues identified as "Unresolved Safety Issues" (NUREG-0606) are the substantive safety issues

referred to by the Appeal Board. Accordingly, we

are requesting that you provide us with a summary

description of your relevant investigative programs

and the interim measures you have devised for

dealing with these issues pending the completion of

the investigation, and what alternative courses of

action might be available should the program not

produce the envisaged result.

There are currently a total of 26 Unresolved Safety Issues discussed in NUREG-0606. We do not require

information from you at this time for a number of

the issues since a number of the issues do not apply

to your type of reactor, or because a generic

resolution has been issued. Issues which have been

resolved have been or are being incorporated in the

NRC licensing guidance and are addressed as a part

of the normal review process. However, we do

request the information noted above for each of the

issues listed below:

1. Waterhammer (A-1)
2. Steam Generator Tube Integrity (A-3)
3. ATWS (A-9)
4. Reactor Vessel Materials Toughness (A-11)
5. Steam Generator and Reactor Coolant Pump Support

(A-12)

6. Systems Interaction (A-17)
7. Seismic Design Criteria (A-40)
8. Containment Emergency Sump Performance (A-43)
9. Station Blackout (A-44)
10. Shutdown Decay Heat Removal Requirements (A-45)
11. Seismic Qualification of Equipment in Operating

Plants (A-46)

12. Safety Implications of Control Systems (A-47)
13. Hydrogen Control Measures and Effects of

Hydrogen Burns on Safety Equipment (A-48) 730-1 Rev. 0 WOLF CREEK RESPONSE In the Safety Evaluation Report for Virgil C. Summer and Comanche Peak (NUREG-0717 and -0797), the NRC Staff concluded that those plants could be operated

pending resolution of the unresolved safety issues. The reasoning that lead to

these conclusions is applicable to WCGS. In general, WCGS agrees with the

previous NRC Staff assessments of these issues and also have concluded that the

WCGS can be operated without risk to the health and safety of the public.

Programs and measurements taken for dealing with these generic issues are

discussed below.

A-1 Waterhammer The WCGS steam generator design incorporates a sealed thermal sleeve and J tubes on the feedring to prevent draining of water from the feedring in the

event the feedwater is lost and the steam generator water level drops below the

level of the feedring. The design also incorporates a short horizontal length

of feedwater piping to the feedring. A waterhammer test of the feedwater

system using normal plant procedures was conducted at the WCGS plant. The

feedwater connection on each of the steam generators is the highest point of

each feedwater line downstream of the main feedwater isolation valve. The

feedwater lines contain no high pockets which, if present, could trap steam and

lead to waterhammer. The feedwater inlet arrangement for a model F steam

generator is of such a design as to minimize the potential for flow-induced

tube vibration. A preoperational test for piping vibration and dynamic effects

was conducted. For further details refer to Sections 5.4.2.2, 10.4.7.2.1, 3.9(B).2.1, and 3.9(N).2.1.

A-3 Steam Generator Tube Integrity The WCGS design includes the Westinghouse Model F steam generator which was developed to minimize steam generator tube problems. In addition, WCGS plant

use full flow condensate demineralizers and all volatile treatment (AVT)

chemistry control. For further details refer to the following Sections:

5.4.2.2, 5.4.2.3.1, 5.4.2.3.3, 5.4.2.4.2, 5.4.2.5.4, 9.3.2, 10.4.6, 10.4.8, and

the response to Regulatory Guide 1.121 in Appendix 3A.

A-9 Anticipated Transients Without Scram Refer to Section 15.8.

730-2 Rev. 0 WOLF CREEK A-11 Reactor Vessel Materials Toughness Refer to Section 5.3 and responses to NRC questions (123.3, .4, .6, .7, .8, and

.9).A-12 Steam Generator and Reactor Coolant Pump Support The WCGS steam generator and reactor coolant pump supports were designed to meet the fracture toughness requirements of ASME Section III, subsection NF.

Westinghouse has concluded that compliance with subsection NF is sufficient to

resolve the concerns expressed in NUREG-0577. Refer to Sections 3.8.3.1.2, 3.8.3.1.3, and 5.4.14.

A-17 Systems Interaction The WCGS design is founded on principles of physical separation, independence of redundant safety systems, and protection against hazards such as high energy

line breaks, missiles, flooding, seismic events, fires, and sabotage. The

design has been subjected to multiple, interdisciplinary reviews. Examples of

such reviews include:

a. USAR Appendix 3B describes the WCGS hazards analysis review program which was conducted on a room-by-room

basis for each room in the power block. All components

within the rooms were reviewed for the effects of

earthquake-induced failures, effects of high and

moderate energy piping breaks (flooding, sprays, and jet

impingement), and the effects of missiles.

b. A separate review was also conducted on a room-by-room basis to evaluate the fire protection design and the

effects of fires in each fire area as discussed in USAR

Section 9.5.1.

c. The responses to NRC questions 420.3 and 420.4 describe the reviews conducted to analyze control systems

failures and how such failures impact interfacing safety

grade systems.

d. Heavy loads analyses as requested in NRC generic letter 81-07.
e. Review of environmental impacts on systems to ensure that they are designed to provide acceptable performance

during normal and design basis accident conditions as

described in WCGS USAR Sections 3.11(B) and 3.11(N). 730-3 Rev. 0 WOLF CREEK A-40 Seismic Design Criteria As discussed in Sections 3.7(B) and 3.7(N), the WCGS plant has been designed to current seismic design criteria.

A-43 Containment Emergency Sump Performance The WCGS containment sumps are described in Section 6.2.2.1.2.2 and Figure 6.2.2-3 (10 sheets). Thermal insulation used inside the containment in the

WCGS design will not be a significant source of debris. A detailed comparison

of the WCGS sumps with the design recommendations of Regulatory Guide 1.82 is

provided in Table 6.2.2-1. Sump testing is discussed in Appendix 3A response

to Regulatory Guide 1.79.

A-44 Station Blackout The offsite and onsite power systems are described in Sections 8.2 and 8.3.

Several responses to NRC questions in the 430-series are related to NUREG/CR

0660. The independence of the turbine-driven auxiliary feedwater pump train

from ac power is discussed in Section 10.4.9.2.2. Plans for emergency

procedures and training were provided in SNUPPS letter, SLNRC 81-35 dated May

27, 1981. Specific information regarding station blackout is given in Appendix 8.3A.A-45 Shutdown Decay Heat Removal Requirements The WCGS design includes provisions so that cold shutdown conditions can be

obtained using safety-grade equipment with only onsite or only offsite ac

power. Refer to Appendix 5.4.A. As noted in that appendix, the WCGS design

includes redundant, qualified, Class IE pressurizer power-operated relief and

block valves.

A-46 Seismic Qualification of Equipment in Operating Plants Current seismic criteria were used in the WCGS design. Refer to Sections 3.10(B) and 3.10(N).

A-47 Safety Implications of Control Systems The WCGS control and safety systems have been designed with the goal of ensuring that control system failures will not prevent automatic or manual

initiation and operation of any safety system equipment. This has been

accomplished by providing independence or isolation between safety and non-

safety systems. An analysis is documented in the response to NRC question

420.4. 730-4 Rev. 14 WOLF CREEK A-48 Hydrogen Control Measures and Effects of Hydrogen Burns on Safety Equipment Section 6.2.5 describes hydrogen control provisions in the WCGS design.

Principal containment design parameters are given in Table 6.2.1-2.

A-49 Pressurized Thermal Shock Section 5.3 and the responses to NRC questions (123.3, .4, .6, .7, .8, and .9) provide information concerning reactor vessel material properties, material

susceptibility to neutron irradiation induced embrittlement, and the increase

of nil ductility transition temperature with operating life.

730-5 Rev. 0