ML17261B126

From kanterella
Jump to navigation Jump to search
Clarifies Commitment Made in 900316 RO Re Restoring Inoperable Fire Damper I-411-21-P.Util Plans to Design Removable Track Which Will Allow Charcoal Drawer to Be Manipulated.Definitive Schedule Will Be Provided in 60 Days
ML17261B126
Person / Time
Site: Ginna Constellation icon.png
Issue date: 07/30/1990
From: Mecredy R
ROCHESTER GAS & ELECTRIC CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9008080300
Download: ML17261B126 (4)


Text

ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM 0 t REGULATORY INFORMATION DISTRIBUTXON SYSTEM (RIDS)

ACCESSION NBR:9008080300 DOC.DATE: 90/07/30 NOTARIZED: NO DOCKET FACIL:50-244 Robert Emmet Ginn'a Nuclear Plant, Unit 1, Rochester G 05000244 AUTH. NAME AUTHOR AFFILIATION MECREDY,R.C. Rochester Gas & Electric Corp.

RECIP.'NAME RECIPXENT AFFILIATION Document Control Branch (Document Control Desk)

SUBJECT:

Clarifies commitment made in 900316 inoperable Fire Damper I-411-21-P.

ltr re restoring D

DISTRIBUTXON CODE: IE22D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: 50.73/50.9 Licensee Event Report (LER), Incident Rpt, etc.

NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72). 05000244 RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR EN CL ID CODE/NAME LTTR ENCL PD1-3 LA 1 PD1-3 PD D JOHNSON,A 1 D

INTERNAL: ACNW AEOD/DOA AEOD/ DS P/TPAB AEOD/ROAB/DSP NRR/DET/ECMB 9H NRR/DET/EMEB9H3 NRR/DLPQ/LHFB11 NRR/DLPQ/LPEB10 NRR/DOEA/OEAB11 NRR/DREP/PRPB11 NRR/DST/SELB 8D NRR/DST/SXCB 7E FfD LB8D1 NRR/DST/SRXB 8E REG FXL 02 RES/DSIR/EIB FILE 01 EXTERNAL EG&G BRYCE g J ~ H L ST LOBBY WARD LPDR NRC PDR NSIC MAYS,G NSIC MURPHY,G.A NUDOCS FULL TXT D

D D

NOTE TO ALL "RIDS" RECIPIENTS:

S PLEASE HELP US TO REDUCE %VASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOXI Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED! 1 TOTAL NUMBER OF COPIES REQUIRED: LTTR 32 ENCL

ROCHESTER GAS AND ELECTRI CORPORATION ~ 89 EAST AVENUE, ROCHESTER, N.Y. I 4649 TCLCe~Cs'QUA COgf-. T1( 5+6

+o~'uly 30, 1990'.S.

Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Attr: Allen R. Johnson Project Directorate I-3

Subject:

Change to Thirty (30) Day Special Report Inoperable Fire Damper I-411-21-P R.E. Ginna Nuclear Power Plant, Unit No. 1 Docket No. 50-244

Reference:

Letter from R.C. Mecredy (RG&E) to W.T. Russell (NRC)

Dated March 16, 1990

Dear Mr. Johnson:

The purpose of this letter is to clarify a commitment made in our March 16, 1990 letter, as related to restoring inoperable fire damper I-411-21-P. In tha't letter RG&E stated that the replacement damper would be procured and installed by July, 1990. Fire damper I-411-21-P is installed just in front of the spent fuel pool charcoal filte drawers. This fire damper has been procured and received. During the attempted installation of this fire damper, it. was determined that the new damper would not allow the charcoal filter drawer to be pulled out/changed.

written to resolve this A non-conformance report interference. The existing (NCR) has been damper will remain in place.

The planned resolution of the NCR is to design a removable track which will allow the charcoal drawer to be manipulated. This design will require approval from Ruskin, the manufacturer of the damper to ensure U.L. listing is not voided.

If this resolution requires downgrading the 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> U.L. listing, RG&E proposes to remove the existing frame and damper and install a larger damper which would allow proper clearances for charcoal filter drawer manipulations. This option would require extensive

- 008080=-00 DR AFIOCK

'"00! """

C).'.000244 r.DC.

~ wg g i(p

engineering and installation work. A definitive schedule for the resolution of the fire damper to operable status will be provided within the next sixty (60) days.

RG&E has established an hourly fire watch in accordance with Technical Specification 3.14.6.1 until other compensatory measures can be approved and implemented.

Very truly yo rs