MONTHYEARML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22103A0592022-04-13013 April 2022 PSDAR Meeting Summary ML20279A5392020-10-0505 October 2020 August 19, 2020, Summary of Public Webinar with Nextera Energy Duane Arnold, LLC to Discuss Future Request for a One Time Exemption to Certain Requirements of 10 CFR Part 50, Appendix E at Duane Arnold Energy Center (EPID L-202-LRM-0078) ML20253A0022020-09-30030 September 2020 Summary of Public Webinar with NextEra Energy Duane Arnold, LLC, to Discuss a Future Request for a One-Time Exemption to Certain Requirements of 10 CFR Part 50, Appendix E at Duane Arnold Energy Center ML20233A7902020-08-20020 August 2020 Summary of the July 30, 2020, Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center and the Point Beach Nuclear Plant ML20023A3432020-01-23023 January 2020 Summary of January 9, 2020, Closed Meeting with Nextera Energy Duane Arnold, Llc, Regarding Security Plan Change for the Duane Arnold Energy Center ML19179A0662019-07-17017 July 2019 Summary of Closed Meeting with Nextera Energy, LLC, to Discuss Security-Related Information for Point Beach Nuclear Plant, Unit 1 and 2, and Duane Arnold Energy Center ML19113A0412019-04-23023 April 2019 Summary of Public Outreach/Open House to Discuss the NRC 2018 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center ML18099A2352018-04-0909 April 2018 April 4, 2018 Summary of the Public Outreach/Open House to Discuss the NRC 2017 End-of-Cycle Plant Performance Assessment of the Duane Arnold ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML17151B0702017-05-31031 May 2017 Public Meeting Summary of May 23, 2017, Teleconference with Nextera Energy Duane Arnold, LLC ML17136A0862017-05-17017 May 2017 May 1, 2017, Summary of Pre-Application Teleconference with Nextera Energy Duane Arnold, Llc, for License Amendment Request for Adoption of TSTF-542 ML17115A0782017-04-24024 April 2017 Summary of Outreach/Open House to Discuss the NRC 2016 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center ML16201A3102016-07-21021 July 2016 July 13, 2016 Summary of Pre-Application Teleconference with Nextera Energy Duane Arnold, LLC, for License Amendment Request for Change in Duane Arnold Energy Center Emergency Planning Zone Boundary Beyond 10 Mile Zone ML16197A1762016-07-19019 July 2016 Summary of June 30, 2016, Pre-Application Teleconference with NextEra Energy Duane Arnold, LLC, for License Amendment Request for Change in Duane Arnold Energy Center Emergency Plan Staff Augmentation Response Times ML16148A0742016-06-0202 June 2016 Summary of Teleconference Meeting with NextEra Energy Duane Arnold, LLC, for Duane Arnold on Development of Confirmatory Success Criteria Analyses ML16111A5032016-04-20020 April 2016 Summary of Public Outreach/Open House to Discuss the NRC 2015 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center ML16028A1162016-01-29029 January 2016 January 7, 2016, Summary of Pre-Application Teleconference with NextEra Energy Duane Arnold, LLC, for Duane Arnold Spent Fuel Criticality Analyses ML16006A0422016-01-0707 January 2016 Summary of Pre-Application Meeting with NextEra Energy Duane Arnold, LLC, for Duane Arnold Spent Fuel Criticality Analyses ML15113B3802015-04-23023 April 2015 April 16, 2015 Summary of the Duane Arnold Public Meeting to Discuss the 2014 Annual Assessment Results ML14121A2872014-04-30030 April 2014 Summary of Public Meeting to Discuss the 2013 Annual Assessment Results, Slides ML13326A0662013-11-21021 November 2013 11/5/2013 - Summary of Public Meeting with NextEra Energy Duane Arnold, LLC ML13107B5272013-04-17017 April 2013 4/11/2013 - Summary of Open House Public Meeting to Discuss NRC Activities, Nuclear Power Issues, and the Duane Arnold Energy Center 2012 End-Of-Cycle Plant Performance Assessment ML12122A8832012-05-0101 May 2012 Summary of Open House Public Meeting to Discuss NRC Activities, Nuclear Power Issues, and the Duane Arnold Energy Center 2011 End-of-Cycle Plant Performance Assessment ML11341A0612011-12-0606 December 2011 Ltr 120611 Summary of the November 30, 2011, Non-Public Meeting to Discuss Duane Arnold Protective Strategy Change ML11292A1612011-10-20020 October 2011 Summary of Meeting with Beyond Nuclear Regarding Their 10 CFR 2.206 Petition to Suspend Operating Licenses of General Electric Mark I Boiling Water Reactors ML11166A1342011-06-22022 June 2011 Meeting Summary with the Beyond Nuclear Petitioners Regarding Their 2.206 Petition to Suspend Operating Licenses (Ols) of General Electric (GE) Boiling Water Reactors (Bwrs) Mark I (Bwrs) ML1108208272011-04-21021 April 2011 Summary of Pre-application Meeting with NextEra Energy, Inc., and Florida Power & Light Company, on Turkey Point, Units 3 and 4, St. Lucie, Units 1 & 2, Point Beach, Units 1 & 2, Duane Arnold Transition to NFPA-805 ML1013702862010-05-17017 May 2010 Letter Summary of May 4, 2010 Non-Public Meeting to Discuss End-of-Cycle Security Performance for Calendar Year 2009 ML0919100122009-07-17017 July 2009 04/22/2009-Summary of Public License Renewal Overview and Environmental Scoping Meetings Related to the Review of the Duane Arnold Energy Center License Renewal Application ML0919001952009-07-0909 July 2009 Summary of Meeting Between NRC Region III Management and NextEra Energy Duane Arnold, LLC Representatives to Discuss the Nrc'S Assessment ML0917500752009-07-0202 July 2009 06/15/09 - 06/17/09-Summary of Environmental Site Information Review (Site Audit), Related to Review of the License Renewal Application for Duane Arnold Energy Center ML0835705522009-01-0707 January 2009 12/16/08 Summary of Telephone Conference Call Between NRC and FPL Energy Duane Arnold, LLC, Pertaining to the Review Status of Duane Arnold Energy Center, License Renewal Application ML0810602422008-04-14014 April 2008 Summary of Meeting Between NRC Region III Management and FPL Energy Duane Arnold Representatives to Discuss the Nrc'S Assessment ML0800705272008-01-10010 January 2008 Public Meeting Summaries on the Duane Arnold Frequently Asked Question (FAQ) Appeal Meeting on November 14, 2007, and the Reactor Oversight Process Meeting Held on December 5, 2007 ML0729601702007-10-31031 October 2007 Public Meeting Summary on the Reactor Oversight Process ML0725306142007-09-21021 September 2007 Public Meeting Summary on the Reactor Oversight Process ML0720000582007-07-26026 July 2007 7/18/07 Public Meeting Summary on the Reactor Oversight Process ML0716603252007-06-14014 June 2007 Conference Call Record and Chronology, Duane Arnold Energy Center Relief Request to Use Alternative to ASME Section XI Requirements to Use Code Cases N-504-2 and N-638-1 for Weld Overlay Repairs ML0707105832007-03-0909 March 2007 Ltr 3/9/2007 Re Duane Arnold Summary of the March 1, 2007 Public Regulatory Conference to Discuss a Preliminary White Finding and an Apparent Violation ML0618900052006-07-17017 July 2006 Summary of 04/14/2006 Meeting to Discuss Calculations Associated with the Submittal Pertaining to the Elimination of the Main Steamline Radiation Monitor Trips ML0610403292006-04-14014 April 2006 Public Meeting Summary with Florida Power and Light to Discuss Duane Arnold Energy Center End-of-Cycle Plant Performance Assessment ML0604700392006-02-23023 February 2006 Summary of Public Meeting with Florida Power and Light Company Regarding Proposed Submittal to Adopt a Common Quality Assurance Topical Report Format ML0603905002006-02-17017 February 2006 Summary of Meeting with Licensee to Discuss Turbulent Penetration as Related to Duane Arnold Energy Center'S High Pressure Coolant Injection (HPCI) System ML0513706142005-05-13013 May 2005 Public Meeting Summary Duane Arnold End-of-Cycle Plant Performance Assessment ML0435801802004-12-22022 December 2004 Summary of Public Meeting with Nuclear Management Company, Llc. to Discuss Engineering Initiatives ML0411803482004-04-20020 April 2004 Public Meeting Summary, Duane Arnold 2003 End-of-Cycle Assessment ML0312504802003-04-11011 April 2003 Summary of Meeting with Nuclear Management Co., LLC to Discuss Duane Arnold Energy Center End of Cycle Plant Performance Assessment ML0214900232002-05-31031 May 2002 Meeting with Nuclear Management Company, LLC, to Discuss Their Response to Interim Compensatory Measure B.2.b of the Security Orders ML0208603012002-03-27027 March 2002 Summary of March 18, 2002 Meeting with Duane Arnold Nuclear Power Station to Discuss Performance 2022-09-14
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 April 23, 2015 LICENSEE: NextEra Energy Duane Arnold, LLC FACILITY: Duane Arnold Energy Center
SUBJECT:
SUMMARY
OF THE APRIL 16, 2015, DUANE ARNOLD PUBLIC MEETING TO DISCUSS THE 2014 ANNUAL ASSESSMENT RESULTS On April 16, 2015, the U.S. Nuclear Regulatory Commission (NRC) held a public meeting at the Hiawatha Community Center in Hiawatha, Iowa, to discuss the 2014 annual assessment results for the Duane Arnold Energy Center. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML15077A013 and ML15112B135, respectively. A list of principal NRC and licensee meeting participants can be found in the Enclosure.
At the meeting, the NRC provided an overview of the Reactor Oversight Process, the results of the 2014 annual assessment for Duane Arnold Energy Center, and the NRCs inspection plans for 2015. The NRCs presentation was followed by statements from the NextEra Duane Arnold officials, which included the licensees plans for plant upgrades, actions for sustainable human performance improvements, as well as information on current plant status. Patrick Louden, the Acting Deputy Regional Administrator for the NRCs Region III Office, acknowledged the information provided by the Duane Arnold officials and emphasized the importance of sustainability of these actions to improve human performance. The licensee presentation can be found in ADAMS as ML15112B130.
After the business part of the meeting ended, NRC and licensee representatives met with attendees of the meeting. One Linn County official attended the meeting.
/RA/____________________
James McGhee, Acting Chief Branch 1 Division of Reactor Projects Docket No. 50-331 License No. DPR-49
Enclosure:
List of Meeting Participants cc w/encl: Distribution via LISTSERV
Meeting Participants NRC P. Louden, Acting Deputy Regional Administrator, Region III M. Shuaibi, Deputy Division Director, Division of Reactor Safety, Region III G. Roach, Acting Chief, Branch 1, Division of Reactor Projects, Region III J. Steffes, Resident Inspector, Duane Arnold Energy Center P. Chandrathil, Public Affairs Officer, Region III Field Office M. Chawla, Project Manager, Division of Operating Reactor Licensing, Nuclear Reactor Regulation C. Norton, Project Manager, Japan Lessons-Learned Division, Nuclear Reactor Regulation NextEra Duane Arnold T. Vehec, Site Vice President G. Pry, Plant Manager K. Kleinheinz, Engineering Director P. Hansen, Performance Improvement Manager M. Davis, Manager of Licensing and Emergency Planning Enclosure
LICENSEE: NextEra Energy Duane Arnold, LLC FACILITY: Duane Arnold Energy Center
SUBJECT:
SUMMARY
OF THE APRIL 16, 2015, DUANE ARNOLD PUBLIC MEETING TO DISCUSS THE 2014 ANNUAL ASSESSMENT RESULTS On April 16, 2015, the U.S. Nuclear Regulatory Commission (NRC) held a public meeting at the Hiawatha Community Center in Hiawatha, Iowa, to discuss the 2014 annual assessment results for the Duane Arnold Energy Center. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML15077A013 and ML15112B135, respectively. A list of principal NRC and licensee meeting participants can be found in the Enclosure.
At the meeting, the NRC provided an overview of the Reactor Oversight Process, the results of the 2014 annual assessment for Duane Arnold Energy Center, and the NRCs inspection plans for 2015. The NRCs presentation was followed by statements from the NextEra Duane Arnold officials, which included the licensees plans for plant upgrades, actions for sustainable human performance improvements, as well as information on current plant status. Patrick Louden, the Acting Deputy Regional Administrator for the NRCs Region III Office, acknowledged the information provided by the Duane Arnold officials and emphasized the importance of sustainability of these actions to improve human performance. The licensee presentation can be found in ADAMS as ML15112B130.
After the business part of the meeting ended, NRC and licensee representatives met with attendees of the meeting. One Linn County official attended the meeting.
/RA/_____________________
James McGhee, Acting Chief Branch 1 Division of Reactor Projects Docket No. 50-331 License No. DPR-49
Enclosure:
List of Meeting Participants cc w/encl: Distribution via LISTSERV ADAMS Accession Number: ML15113B380 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME RNg:mt JMcGhee DATE 04/23/15 04/23/15 OFFICIAL RECORD COPY
Memorandum from James McGhee dated April 23, 2015
SUBJECT:
SUMMARY
OF THE APRIL 16, 2015, DUANE ARNOLD PUBLIC MEETING TO DISCUSS THE 2014 ANNUAL ASSESSMENT RESULTS DISTRIBUTION:
Kimyata MorganButler RidsNrrDorlLpl3-1 Resource RidsNrrPMDuaneArnold Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ROPassessment.Resource@nrc.gov