Summary of Pre-application Meeting with NextEra Energy, Inc., and Florida Power & Light Company, on Turkey Point, Units 3 and 4, St. Lucie, Units 1 & 2, Point Beach, Units 1 & 2, Duane Arnold Transition to NFPA-805ML110820827 |
Person / Time |
---|
Site: |
Saint Lucie, Point Beach, Turkey Point, Duane Arnold ![NextEra Energy icon.png](/w/images/9/9b/NextEra_Energy_icon.png) |
---|
Issue date: |
04/21/2011 |
---|
From: |
Jason Paige Plant Licensing Branch II |
---|
To: |
|
---|
Paige, Jason C, NRR/DORL,301-415-5888 |
Shared Package |
---|
ML110820814 |
List: |
---|
References |
---|
NFPA-805 |
Download: ML110820827 (5) |
|
|
---|
Category:Meeting Summary
MONTHYEARML23276A1852023-09-25025 September 2023 Subsequent License Renewal Draft EIS Public Meetings: Meeting Summary ML23221A3782023-08-16016 August 2023 Summary of Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Transition to a 24-Month Fuel Cycle ML23199A0262023-07-18018 July 2023 Summary of Public Outreach to Discuss the NRC 2022 End of Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML23166A0042023-06-15015 June 2023 Summary of Meeting Concerning 2023 Annual Assessment of the Saint Lucie and the Turkey Point Nuclear Plants ML23118A1762023-05-0404 May 2023 Audit Summary for License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue 191 ML23108A2752023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 ML23087A0692023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 ML23058A4262023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML23068A0712023-04-28028 April 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 (EPID L-2022-LLA-0105) - Nonproprietary ML23107A2312023-04-18018 April 2023 Summary Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23081A5022023-03-28028 March 2023 Summary of Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Transition to a 24-Month Fuel Cycle ML23066A0872023-03-15015 March 2023 Summary of Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23069A0282023-03-15015 March 2023 Summary of January 31, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23044A4172023-03-0606 March 2023 Summary of January 17, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23048A0492023-03-0303 March 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML22357A0742023-01-19019 January 2023 Summary of December 1, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22350A7082023-01-17017 January 2023 Summary of November 21, 2022, Presubmittal Meeting with Florida Power and Light on St. Lucie License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML22349A0012023-01-0505 January 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML22327A2402022-12-0808 December 2022 Summary of October 27, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22276A2302022-10-0606 October 2022 Summary of September 13, 2022, Public Meeting with FPL Concerning Supplemental Information Needed for Acceptance of License Amendment Request to Replace Instrumentation with Digital Systems on Turkey Point, Units 3 and 4 ML22263A0122022-09-27027 September 2022 Summary of August 29, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests (EPID Nos. L-2021-LLI-0000 and L 2021 Lli 0002) ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22238A2762022-08-29029 August 2022 Summary of August 17, 2022, Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Extend the Completion Time for an Inoperable Reactor Trip Breaker ML22229A5252022-08-24024 August 2022 Summary of August 11, 2022, Mtg. with Florida Power & Light/Nextera on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Request (EPIDs L-2021-LLI-0000 & -0002) ML22228A2352022-08-23023 August 2022 Summary of July 28, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22228A2032022-08-22022 August 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22195A1752022-07-27027 July 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22186A0812022-07-15015 July 2022 Summary of June 22, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Fire Protection Program Changes ML22181B1182022-06-30030 June 2022 Summary of the June 23, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML22167A1852022-06-30030 June 2022 Summary of June 6, 2022, Meeting with Duke Energy to Discuss Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI) 191 ML22160A3792022-06-30030 June 2022 Summary of May 24, 2022, Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Reactor Coolant Pump Seal Replacements ML22154A5202022-06-0909 June 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22154A5112022-06-0707 June 2022 Summary of May 19, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22145A3932022-05-25025 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting 20220434 ML22137A2512022-05-19019 May 2022 Summary of Pre-Application Meeting with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 ML22129A1812022-05-11011 May 2022 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 ML22118A3582022-05-10010 May 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22103A0592022-04-13013 April 2022 PSDAR Meeting Summary ML22089A1382022-04-0505 April 2022 Summary of March 24, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22066A7852022-03-23023 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22070A5632022-03-21021 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22054A0082022-03-0303 March 2022 Summary of February 17, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Intake Cooling Water Discharge Piping Proposed Alternative ML22020A4032022-02-0707 February 2022 Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002) ML22020A4052022-01-24024 January 2022 Summary of January 14, 2022, Teleconference with Florida Power & Light Co. Regarding Verbal Authorization of Request for Alternative to the Requirements of ASME Code for Examination of Closure Head CEDM Housing 27 Canopy Seal Weld ML22019A2792022-01-20020 January 2022 Summary of Public Webinar with NextEra Energy Point Beach, LLC Regarding Future License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant ML22004A0772022-01-0606 January 2022 Summaries of December 8, 2021 Draft Supplemental Environmental Impact Statement for Subsequent License Renewal Application Public Meetings ML21342A3752022-01-0606 January 2022 Summary of Meeting with Florida Power and Light/Nextera on Proposed Improved Technical Specification Conversions ML21337A1962021-12-16016 December 2021 Public Scoping Meeting Summary for the Environmental Review of the Subsequent License Renewal Application for St. Lucie Plant, Units 1 and 2 ML21327A1802021-12-0707 December 2021 Summary of August 25, 2021 Observation Public Meeting with FPL to Discuss Proposed Alternative Report for the Intake Cooling Water System 2023-09-25
[Table view] |
Text
- ......P.B REGUj
.;;:,c, .....J,
">~ "01'... NUCLEAR REGULATORY COMMISSION
- " WASHINGTON, D.C. 20555-0001
<I:
~
ca,~
- 0 Pi; April 21, 2011
~
-'1) ~o
- iC LICENSEE: NextEra Energy, Inc., and Florida Power & Light Company FACILITIES: Turkey Point, Units 3 and 4, St. Lucie, Units 1 and 2, Point Beach, Units 1 and 2, and Duane Arnold
SUBJECT:
SUMMARY
OF MARCH 22, 2011, PRE-APPLICATION MEETING WITH NEXTERA ENERGY, INC., AND FLORIDA POWER & LIGHT COMPANY, ON TURKEY POINT, UNITS 3 AND 4, ST. LUCIE, UNITS 1 AND 2, POINT BEACH, UNITS 1 AND 2, AND DUANE ARNOLD TRANSITION TO NFPA-B05 REQUIREMENTS On March 22,2011, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of NextEra Energy, Inc., Florida Power &
Light Company (NextEra, the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the pre-application meeting was to discuss the proposed license amendment requests (LARs) to transition to the requirements of National Fire Protection Association (NFPA) - B05 for Turkey Point, Units 3 and 4, St. Lucie, Units 1 and 2, Point Beach, Units 1 and 2, and Duane Arnold Energy Center. A list of attendees is provided as an enclosure.
The licensee provided a PowerPoint presentation prior to the meeting to help facilitate the discussion (Agencywide Document and Management System (ADAMS) Accession No. ML110770349). As a result of the meeting, the licensee revised the presentation to reflect the discussions during the meeting (ADAMS Accession No. ML 11 OB20699). The licensee presented fleet challenges on the NFPA-B05 project, projected schedules for submitting the LARs, and provided site specific updates.
The licensee began the presentation by providing its project schedule for submitting the LARs for each site. The licensee plans to submit the Duane Arnold, St. Lucie, and Point Beach LARs by June 29, 2011, and the Turkey Point LAR by June 24, 2011. The licensee stated that these schedules have little to no float.
After the licensee provided an NFPA-B05 transition project plan overview, NextEra provided insight of its fleet level issues. Some of the issues discussed were the limitation of specialized skill sets and probabilistic risk assessment (PRA) resources, major spring outages at three of the four sites (Turkey Point, St. Lucie, and Point Beach) supporting concurrent proposed extended power uprates, and the acquisition of external resources to complete the focused scope peer reviews to remove the open findings and observations previously identified at each site. Per Regulatory Guide 1.200, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities," the licensee performed a peer review at each site to determine how well it complies with the American Society of Mechanical Engineers I American Nuclear Society PRA standards. As a result of these peer reviews, findings and observations (F&Os) were identified. For risk-informed applications, licensees need to provide the F&Os and discuss how they are resolved. Even though not
- 2 required, the licensee has scheduled focused scope peer reviews to resolve the F&Os. The focused peer reviews are scheduled late in the process for submitting the LARs.
Another issue the licensee discussed was open circuit current transformers (CTs), which NextEra categorized as an industry generic issue. More specifically, the licensee stated that there is no firm guidance on CT failures causing a secondary fire and how to resolve the issue, even though industry is aware of CT failures causing undesirable situations. The licensee continued by stating that this issue was not resolved via the pilot plants due to one plant using transducers and therefore this issue does not apply, and the other pilot plant not resolving the issue at the time of the safety evaluation. The NRC staff asked for the licensee's plan forward for addressing the issue in the proposed LARs. The licensee stated that they are resolving this issue in parallel with the generation of the LAR applications. If the issue is not resolved by June 29, 2011, or when the applications are submitted to the NRC staff, then the LARs will include a commitment to provide a supplement at a later date regarding the resolution of the issue. The NRC staff believes that this is an acceptable approach.
The last fleet issue discussed in detail was the use of NUREG/CR 6850 alternative treatments used for three types of fires. The three types of fires discussed were electrical cabinet fires, transient fires, and hot work fires. Even though the licensee plans on using similar alternative methodologies as used for one of the pilot plants, the methods have not been generally accepted by the NRC. The NRC staff explained this issue by clarifying that the alternative methods were reviewed as part of the determination whether the site specific PRA analysis was acceptable. The NRC staff continued by stating that the pilot's PRA analysis was accepted because the NRC concluded that regardless of the use of these methods, there was a reduction in risk associated with the proposed transition to NFPA-805 requirements.
After the fleet issues, the licensee provided site-specific updates. They provided an update for each site for items complete/under review, essentially complete, and nearing completion. The licensee defined essentially complete as the document or evaluation is in-house, but there are open items and nearing completion as the document or evaluation is not in-house and there is a potential for open items. The licensee also discussed site-specific challenges, LAR gaps that will likely require supplements, and strategies to resolve the LAR gaps. Most of the challenges and LAR gaps are similar for each site except for Point Beach. Point Beach has its focused peer review scheduled for June 6,2011, and is projecting to have its final peer review report by August 2011.
At the conclusion of the meeting, the NRC staff asked, with the LAR gaps presented today and the potential to slip the LAR submittal dates, what are the expectations for providing updates of the LARs. The licensee stated that they will keep the respective NRC plant project managers up to date of any changes to the plan as discussed during the meeting. Also, the licensee asked, with the LAR gaps, if the staff sees any potential acceptance review issues. The NRC technical staff addressed the question by stating at this time, the staff does not see any major issues but noted, the staff cannot guarantee that the LARs would be accepted without seeing the applications.
- 3 Members of the public were in attendance. Public Meeting Feedback forms were offered, but none were received.
Please direct any inquiries to me at 301-415-5888, or Jason.Paige@nrc.gov.
as Paige, Project Mana I t Licensing Branch 11-2 ivision of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-335, 50-389, 50-266, 50-301, and 50-331
Enclosure:
List of Attendees cc w/encl: Distribution via ListServ
LIST OF ATIENDEES MARCH 22, 2011 MEETING WITH NEXTERA ENERGY, INC., AND FLORIDA POWER & LIGHT TRANSITION TO NFPA-805 LICENSE AMENDMENT REQUESTS U.S. Nuclear Regulatory Commission T. Orf R. Pascarelli A. Klein S. Lee S. Dinsmore D. Pickett T. Beltz H. Barrett P. Lain D. Broaddus K. Feintuch D. Frumkin J. Paige D. Harrison NextEra Energy, Inc., Florida Power & Light Co.
K. Frehafer S. Catron L. Nicholson V. Rubano A. Julka W. Cross Nuclear Energy Institute J. Butler T. Basso L. Young P. Grissom K. Lavin J. Ertman G. Meyer Enclosure
- 3 Members of the public were in attendance. Public Meeting Feedback forms were offered, but none were received.
Please direct any inquiries to me at 301-415-5888, or Jason.Paige@nrc.gov.
Sincerely, IRA!
Jason Paige, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-335, 50-389, 50-266,50-301, and 50-331
Enclosure:
List of Attendees cc w/encl: Distribution via ListServ DISTRIBUTION:
PUBLIC CSteger, NRR DFrumkin, NRR LPL2-2 Branch Reading SDinsmore. NRR RidsNrrDorlLpl3-1 Resource RidsAcrsAcnw_MailCTR Resource DPickett, NRR RidsNrrDra RidsNrrDorlLpl2-2 Resource NSanfilippo, EDO RidsNrrDraAfpb RidsNrrPMTurkeyPoint Resource RidsNrrPMPointBeach Resource RidsNrrDraApla RidsNrrLABClayton Resource HBarrett, NRR RidsNrrPMStLucie Resource RidsOgcRp Resource PLain, NRR RidsRgn2MailCenter Resource RidsNrrPMDuaneArnold Resource ADAM s Accession No. PKG ML110820814 Notice ML 10610427 SummaryM L11 0820827Handou Is M L110 77 0349 &ML110206998
IIOFFICE DORULPL2-2/PM DORULPL2-2/PM DORULPL3-1/PM DORULPL3*1/PM DORULPL2-2/LA DORULPL3-1/BC DORULPL2*2/BC I. NAME JPaige TOrf KFeinluch TBeitz BClayton RPascarelii DBroaddus (SLingam for) ilDATE 03/28/11 03/29/11 03/30/11 03/30/11 03/28/11 03/30/11 04/21/11 OFFICIAL RECORD COPY