MONTHYEARIR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20240022024-08-13013 August 2024 Integrated Inspection Report 05000336/2024002 and 05000423/2024002 IR 05000336/20244412024-08-0606 August 2024 Supplemental Inspection Report 05000336/2024441 and 05000423/2024441 and Follow-Up Assessment Letter (Cover Letter Only) IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 IR 05000336/20245012024-07-0101 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2024501 and 05000423/2024501 IR 05000336/20240102024-06-26026 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000336/2024010 and 05000423/2024010 ML24142A0952024-05-20020 May 2024 End of Cycle 22 Steam Generator Tube Inspection Report IR 05000336/20240012024-05-14014 May 2024 Integrated Inspection Report 05000336/2024001 and 05000423/2024001 and Apparent Violation IR 05000336/20244012024-04-30030 April 2024 Security Baseline Inspection Report 05000336/2024401 and 05000423/2024401 (Cover Letter Only) IR 05000336/20244402024-04-25025 April 2024 Special Inspection Follow-Up Report 05000336/2024440 and 05000423/2024440 and Preliminary Finding(S) of Greater than Very Low Significance and NRC Investigation Report No. 1-2024-001 (Cover Letter Only) IR 05000336/20240112024-04-0101 April 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000336/2024011 and 05000423/2024011 IR 05000336/20230062024-02-28028 February 2024 Annual Assessment Letter for Millstone Power Station, Units 2 and 3, (Reports 05000336/2023006 and 05000423/2023006) IR 05000336/20230042024-02-14014 February 2024 Integrated Inspection Report 05000336/2023004 and 05000423/2023004 IR 05000336/20234022024-01-30030 January 2024 Security Baseline Inspection Report 05000336/2023402 and 05000423/2023402 (Cover Letter Only) IR 05000336/20234402024-01-11011 January 2024 Special Inspection Report 05000336/2023440 and 05000423/2023440 (Cover Letter Only) IR 05000336/20230032023-11-0606 November 2023 Integrated Inspection Report 05000336/2023003 and 05000423/2023003 IR 05000336/20234202023-10-0404 October 2023 Security Inspection Report 05000336/2023420 and 05000423/2023420 IR 05000245/20230012023-09-19019 September 2023 Safstor Inspection Report 05000245/2023001 IR 05000336/20230102023-09-0808 September 2023 Commercial Grade Dedication Report 05000336/2023010 and 05000423/2023010 IR 05000336/20230052023-08-31031 August 2023 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Report 05000336/2023005 and 05000423/2023005) IR 05000336/20230022023-08-0909 August 2023 Integrated Inspection Report 05000336/2023002 and 05000423/2023002 IR 05000336/20234012023-07-17017 July 2023 Material Control and Accounting Program Inspection Report 05000336/2023401 and 05000423/2023401 - (Cover Letter Only) IR 07200047/20234012023-06-0808 June 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report No. 07200047/2023401 IR 05000336/20230012023-05-0808 May 2023 Integrated Inspection Report 05000336/2023001 and 05000423/2023001 IR 05000336/20234032023-05-0202 May 2023 Public - Millstone Power Station, Units 2 and 3 Final Significance Determination of Green Finding; Inspection Report 05000336/2023403 and 05000423/2023403 IR 05000336/20233022023-03-0707 March 2023 Operator Licensing Retake Examination Report 05000336/2023302 IR 05000336/20220062023-03-0101 March 2023 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Reports 05000336/2022006 and 05000423/2022006) IR 05000336/20220042023-02-13013 February 2023 Integrated Inspection Report 05000336/2022004 and 05000423/2022004 IR 05000336/20224012023-01-26026 January 2023 Security Baseline Inspection Report 05000336/2022401 and 05000423/2022401 and Preliminary Finding(S) of Greater than Very Low Significance and Apparent Violation(S) (Cover Letter Only) IR 05000245/20220012023-01-0909 January 2023 Safstor Inspection Report 05000245/2022001 IR 05000336/20224032023-01-0505 January 2023 Cyber Security Inspection Report 05000336/2022403 and 05000423/2022403 IR 05000336/20225012022-12-14014 December 2022 Reissued Emergency Preparedness Biennial Exercise Inspection Report 05000336/2022501 and 05000423/2022501 IR 05000336/20223012022-11-22022 November 2022 Initial Operator Licensing Examination Report 05000336/2022301 ML22325A1042022-11-21021 November 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2022501 and 05000423/2022501 IR 05000336/20220032022-11-14014 November 2022 Integrated Inspection Report 05000336/2022003 and 05000423/2022003 IR 05000336/20220102022-11-0101 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000336/2022010 and 05000423/2022010 IR 05000336/20220112022-09-0808 September 2022 Triennial Fire Protection Inspection Report 05000336/2022011 and 05000423/2022011 IR 05000336/20220052022-08-31031 August 2022 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Report 05000336/2022005 and 05000423/2022005) IR 05000336/20220022022-08-11011 August 2022 Integrated Inspection Report 05000336/2022002 and 05000423/2022002 IR 05000336/20224022022-05-23023 May 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000336/2022402 and 05000423/2022402 IR 05000336/20220012022-05-10010 May 2022 Integrated Inspection Report 05000336/2022001 and 05000423/2022001 IR 05000423/20223022022-03-0707 March 2022 Operator Licensing Retake Examination Report 05000423/2022302 IR 05000336/20210062022-03-0202 March 2022 Annual Assessment Letter for Millstone Power Station, Units 2 and 3 (Reports 05000336/2021006 and 05000423/2021006) IR 05000336/20210042022-02-10010 February 2022 Integrated Inspection Report 05000336/2021004 and 05000423/2021004 IR 05000336/20210112022-01-20020 January 2022 Post-Approval Site Inspection for License Renewal - Phase 4 Inspection Report 05000336/2021011 IR 05000336/20210032021-11-12012 November 2021 Integrated Inspection Report 05000336/2021003 and 05000423/2021003 IR 05000423/20213012021-11-10010 November 2021 Initial Operator Licensing Examination Report 05000423/2021301 IR 05000336/20210052021-09-0101 September 2021 Updated Inspection Plan for the Millstone Power Station, Units 2 and 3 (Report 05000336/2021005 and 05000423/2021005) IR 05000336/20210022021-08-0909 August 2021 Integrated Inspection Report 05000336/2021002 and 05000423/2021002 and Independent Spent Fuel Storage Installation Inspection Report 07200047/2021002 IR 05000245/20210012021-07-26026 July 2021 Safe Storage Inspection Report 05000245/2021001 2024-08-06
[Table view] Category:Letter
MONTHYEARML24248A2272024-09-0404 September 2024 Operator Licensing Examination Approval ML24240A1532024-09-0303 September 2024 Summary of Regulatory Audit Supporting the Review of License Amendment Request for Implementation of Framatome Gaia Fuel IR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20240022024-08-13013 August 2024 Integrated Inspection Report 05000336/2024002 and 05000423/2024002 IR 05000336/20244412024-08-0606 August 2024 Supplemental Inspection Report 05000336/2024441 and 05000423/2024441 and Follow-Up Assessment Letter (Cover Letter Only) ML24212A0742024-08-0505 August 2024 Request for Withholding Information from Public Disclosure - Millstone Power Station, Unit No. 3, Proposed Alternative Request IR-4-13 to Support Steam Generator Channel Head Drain Modification ML24211A1712024-07-25025 July 2024 Associated Independent Spent Fuels Storage Installation, Revision to Emergency Plan - Report of Change IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 IR 05000336/20245012024-07-0101 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2024501 and 05000423/2024501 ML24180A0932024-06-28028 June 2024 Readiness for Additional Inspection: EA-23-144 IR 05000336/20240102024-06-26026 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000336/2024010 and 05000423/2024010 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24165A1292024-06-0505 June 2024 ISFSI, 10 CFR 50.59 Annual Change Report for 2023 Annual Regulatory Commitment Change Report for 2023 ML24128A2772024-06-0404 June 2024 Issuance of Amendment No. 290 to Revise TSs for Reactor Core Safety Limits, Fuel Assemblies, and Core Operating Limits Report for Use of Framatome Gaia Fuel (EPID L-2023-LLA-0074) (Non-Proprietary) ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24109A0032024-05-21021 May 2024 Issuance of Amendment No. 289 to Revise Technical Specifications to Use Framatome Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limit (EPID L-2023-LLA-0065) (Non-Proprietary) ML24110A0562024-05-21021 May 2024 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2023-LLE-0013) (Letter) ML24141A2432024-05-20020 May 2024 Response to Request for Additional Information Regarding Alloy 600 Aging Management Program Submittal Related to License Renewal Commitment No. 15 ML24142A0952024-05-20020 May 2024 End of Cycle 22 Steam Generator Tube Inspection Report IR 05000336/20240012024-05-14014 May 2024 Integrated Inspection Report 05000336/2024001 and 05000423/2024001 and Apparent Violation ML24123A2042024-05-0202 May 2024 Pre-Decisional Replay to EA-23-144 IR 05000336/20244012024-04-30030 April 2024 Security Baseline Inspection Report 05000336/2024401 and 05000423/2024401 (Cover Letter Only) ML24123A1222024-04-30030 April 2024 Inservice Inspection Program - Owners Activity Report, Refueling Outage 22 IR 05000336/20244402024-04-25025 April 2024 Special Inspection Follow-Up Report 05000336/2024440 and 05000423/2024440 and Preliminary Finding(S) of Greater than Very Low Significance and NRC Investigation Report No. 1-2024-001 (Cover Letter Only) ML24114A2662024-04-24024 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report ML24116A1742024-04-24024 April 2024 Annual Radiological Environmental Operating Report ML24103A0202024-04-22022 April 2024 Summary of Regulatory Audit in Support of License Amendment Request to Use Framatome Small Break and Realistic Large Break Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limits ML24106A2032024-04-15015 April 2024 2023 Annual Environmental Operating Report ML24088A3302024-04-0404 April 2024 Regulatory Audit Plan in Support of License Amendment Request to Implement Framatome Gaia Fuel IR 05000336/20240112024-04-0101 April 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000336/2024011 and 05000423/2024011 ML24093A2162024-04-0101 April 2024 Response to Request for Additional Information Regarding License Amendment Request to Use Framatome Small Break and Realistic Large Break Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limits ML24093A1022024-04-0101 April 2024 Alternative Request IR-4-13, Proposed Alternative Request to Support Steam Genera Tor Channel Head Drain Modification ML24092A0752024-03-28028 March 2024 3R22 Refueling Outage Inservice Inspection (ISI) Owners Activity Report Extension ML24088A2352024-03-26026 March 2024 Decommissioning Funding Status Report ML24086A4802024-03-22022 March 2024 Alternative Request IR-4-14, Proposed Alternative Request to Defer ASME Code Section XI Inservice Inspection Examination for Pressurizer and Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles ML24086A4762024-03-22022 March 2024 Application for Technical Specification Change to Extend the Inspection Interval for Reactor Coolant Pump Flywheels Using the Consolidated Line-Item Improvement Process ML24051A1922024-03-0808 March 2024 – Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000336/20230062024-02-28028 February 2024 Annual Assessment Letter for Millstone Power Station, Units 2 and 3, (Reports 05000336/2023006 and 05000423/2023006) ML24053A2632024-02-21021 February 2024 Unit 3, and Independent Spent Fuel Storage Installation, Notification Pursuant to 10 CFR 72.212(b)(1) Prior to First Storage of Spent Fuel Under a General License ML24057A0612024-02-19019 February 2024 and Virgil C. Summer Power Nuclear Stations - Nuclear Property Insurance Coverage ML24043A0062024-02-15015 February 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Support Implementation of Framatome Gaia Fuel IR 05000336/20230042024-02-14014 February 2024 Integrated Inspection Report 05000336/2023004 and 05000423/2023004 IR 05000336/20234022024-01-30030 January 2024 Security Baseline Inspection Report 05000336/2023402 and 05000423/2023402 (Cover Letter Only) ML24030A7522024-01-30030 January 2024 Technical Specification Bases Pages ML23341A0172024-01-12012 January 2024 Issuance of Amendment No. 288 Revision to Applicability Term for Reactor Coolant System Heatup and Cooldown Pressure-Temperature Limitations Figures IR 05000336/20234402024-01-11011 January 2024 Special Inspection Report 05000336/2023440 and 05000423/2023440 (Cover Letter Only) ML24004A1052024-01-0404 January 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000336/2024010 & 05000423/2024010 ML23361A0942023-12-21021 December 2023 Response to Request for Additional Information Regarding Proposed License Amendment Request to Revise Technical Specifications for Reactor Core Safety Limits, Fuel Assemblies and Core Operating Limits Report . 2024-09-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION I
475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 August 5, 2010 I I
Mr. David Heacock J'
President and Chief Nuclear Officer Dominion Resources 5000 Dominion Boulevard Glen Allen, VA 23060~6711 I I
SUBJECT: MILLSTONE POWER STATION - NRC INTEGRATED INSPECTION REPORT I'
05000336/2010003 AND 05000423/2010003 II'
Dear Mr,
Heacock:
On June 30,2010, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at I
your Millstone Power Station Unit 2 and Unit 3. The enclosed inspection report documents the inspection results, which were discussed on July 21, 2010, with Mr. A. J, Jordan and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and I
compliance with the Commission's rules and regulations, and with the conditions of your I license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
This report documents one Severity Level IV non-cited violation (NCV). This report also documents four self-revealing findings of very low safety significance (Green). Two of these findings were determined to involve a violation of NRC requirements. However, because of the very low safety significance and because they have been entered into your corrective action program, the NRC is treating these violations as NCVs, consistent with Section VI.A. 1 of the NRC Enforcement Policy. If you contest any NCV in this report, you should provide a response within 30 days of the date of this inspection report. with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator. Region I; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Senior Resident Inspector at Millstone. In addition, if you disagree with the cross-cutting aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region I, and the NRC Senior Resident Inspector at Millstone. In accordance with Title 10 of the Code of Federal Regulations (CFR) Part 2.390 of the NRC's
"Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system {ADAMS}.
ADAMS is accessible from the NRC Web Site at http://www.nrc.gov/reading~rm/adams.html (the Public Electronic Reading Room).
n~
Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects Docket Nos. 50-336,50-423 License Nos. DPR~65. NPF-49
Enclosure:
Inspection Report No. 05000336/2010003 and 05000423/2010003 w/Attachment: Supplemental Information
REGION I==
Docket No.: 50-336, 50-423 License No.: DPR-65, NPF-49 Report No.: 05000336/2010003 and 05000423/2010003 Licensee: Dominion Nuclear Connecticut, Inc.
Facility: Millstone Power Station, Units 2 and 3 Location: P. O. Box 128 Waterford, CT 06385 Dates: April 1. 2010 through June 30,2010 Inspectors: S. Shaffer, Senior Resident Inspector, Division of Reactor Projects (DRP)
J. Krafiy, Resident Inspector, DRP B. Haagensen, Resident Inspector, DRP D. Dodson, Project Engineer, DRP C. Bickett, Senior Project Engineer, DRP T. Moslak, Health Physicist, Division of Reactor Safety (DRS)
P. Kaufman, Senior Reactor Inspector, DRS J. Richmond, Senior Reactor Inspector, DRS J. Rady, Reactor Inspector, DRS Approved by: Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects Enclosure
Table of Contents
SUMMARY OF FINDINGS
..........................................................................................................3
REPORT DETAILS
.....................................................................................................................7 1. REACTO,R SAFETy............................................................................................................7 1R01 Adverse Weather Protection ..................................................................................................7 1R04 Equipment Alignment .....................................................................................................,....... 8 1ROS Fire Protection ..................................................................:................................................... 10 1R06 Flood Protection Measures ..................................................................................................11 1R07 Heat Sink Performance ........................................................................................................12 1ROB In-Service Inspection ...........................................................................................................13 1R11 Licensed Operator RequaJification Program ........................................................................ 17 1R12 Maintenance Effectiveness ..................................................................................................17 1R13 Maintenance Risk Assessments and Emergent Work Control ............................................ 18 1R15 Operability Evaluations ........................................................................................................18 1R18 Plant Modifications ...............................................................................................................19 1R19 Post-Maintenance Testing ...................................................................................................20 1R20 Refueling and Other Outage Activities ................................................................................. 21 1R22 Surveillance Testing .............................................................................................................25 1EP6 Drill Evaluation
RADIATION SAFETY
.........................................................................................................27 2RS01 Radiological Hazard Assessment and Exposure Controls ................................................... 27 2RS02 Occupational ALARA Planning and Controls .......................................................................29 2RS03 In-Plant Airborne Radioactivity Control and Mitigation .........................................................31 2RS04 Occupational Dose Assessment
OTHER ACTIVITIES
[OA] .................................................................................................33 40A1 Performance Indicator (PI) Verification ................................................................................. 33 40A2 Identification and Resolution of Problems ............................................................................ 33 40A3 Event Follow-up ....................................................................................................................36 40A5 Other Activities ...................................................................................................................... 39 40A6 Meetings, including Exit ........................................................................................................40 ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
..................................................................................................A-1
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
....................................................... A-2
LIST OF DOCUMENTS REVIEWED
...................................................................................... A-2