MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. ML23135A0412023-05-15015 May 2023 2022 Annual Radioactive Effluent Release Report and 2022 Annual Radiological Environmental Operating Report ML23121A0482023-05-0101 May 2023 R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 ML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML23114A1152023-03-29029 March 2023 Electronic Reporting of Exposure Data for 2022 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23075A0872023-03-15015 March 2023 R. E. Ginna Nuclear Power Plant - Project Manager Assignment ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23060A1622023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators ML22287A0692023-02-0808 February 2023 R. E. Ginna Station - Forward Fit Analysis (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23031A2992023-02-0707 February 2023 R. E. Ginna Nuclear Power Plant - Withdrawal of an Amendment Request ML23010A0112023-02-0101 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Value RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 ML22362A0382022-12-28028 December 2022 R. E. Ginna Nuclear Power Plant - Letter to Withdraw Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22348A2062022-12-14014 December 2022 Re. Ginna Nuclear Power Plant - Annual Commitment Change Notification RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator 2024-02-05
[Table view] Category:Notice of Violation
MONTHYEARML19261A0832019-09-18018 September 2019 R. E. Ginna Nuclear Power Plant: Design Bases Assurance Inspection (Teams) Report 05000244/2019010 and Notice of Violation ML16262A2132016-09-20020 September 2016 LLC - Final Significance Determination for a White Finding with Assessment Follow-up and Notice of Violation - Inspection Report 05000244/2016009 IR 05000244/20160092016-09-20020 September 2016 LLC - Final Significance Determination for a White Finding with Assessment Follow-up and Notice of Violation - Inspection Report 05000244/2016009 IR 05000244/20150072015-02-24024 February 2015 Notice of Violation - Severity Level III Problem - NRC Inspection Report 05000244/2015007 IR 05000317/20120082012-11-0101 November 2012 Notice of Violation - Constellation Energy Nuclear Group MEMO ML12213A1822012-11-0101 November 2012 Notice of Violation - Constellation Energy Nuclear Group Memo IR 05000220/20120082012-11-0101 November 2012 Notice of Violation - Constellation Energy Nuclear Group MEMO IR 05000244/20120072012-11-0101 November 2012 Notice of Violation - Constellation Energy Nuclear Group MEMO IR 05000244/20090082009-11-12012 November 2009 EA-09-249, R. E. Ginna Nuclear Power Plant, LLC, Notice of Violation - NRC Inspection Report No. 05000244-09-008 ML0931602002009-11-12012 November 2009 EA-09-249, R. E. Ginna Nuclear Power Plant, LLC, Notice of Violation - NRC Inspection Report No. 05000244-09-008 IR 05000244/20090022009-06-0808 June 2009 IR 05000244-09-002, for R. E. Ginna - Final Significance Determination of White Finding with Assessment Follow-up, and Notice of Violation IR 05000244/20085022008-04-0707 April 2008 R. E. Ginna Nuclear Power Plant - Notice of Violation, NRC Supplemental Inspection Report No. 05000244/2008502 ML0409004872004-03-30030 March 2004 IA-04-005, B. Flynn, Notice of Violation, OI Report 1-2003-021 ML0409003572004-03-30030 March 2004 EA-04-003, Ginna, Notice of Violation, OI Investigations Report 1-2003-021 ML0233002832002-11-26026 November 2002 EA-02-121, EA-02-142, Peach Bottom, NOV & Green and White Findings ML0229504172002-10-22022 October 2002 IA-02-041, Diprospero, Notice of Violation ML0227700652002-10-0404 October 2002 Final Significance Determination for White Finding EA-02-141 & Notice of Violation 2019-09-18
[Table view] Category:Inspection Report
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) IR 05000244/20220042023-01-31031 January 2023 LLC - Integrated Inspection Report 05000244/2022004 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 IR 05000244/20224202022-11-22022 November 2022 Security Baseline Inspection Report 05000244-2022420 Cover Letter IR 05000244/20220032022-11-0303 November 2022 LLC - Integrated Inspection Report 05000244/2022003 IR 05000244/20225012022-09-21021 September 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000244/2022501 IR 05000244/20220102022-09-13013 September 2022 Biennial Problem Identification and Resolution Inspection Report 05000244/2022010 IR 05000244/20220052022-08-31031 August 2022 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2022005) IR 05000244/20224022022-08-0303 August 2022 Security Baseline Inspection Report 05000244/2022402 IR 05000244/20220022022-08-0303 August 2022 LLC - Integrated Inspection Report 05000244/2022002 ML22160A3962022-06-0909 June 2022 R. E. Ginna Nuclear Power Plant, LLC - Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2022010 IR 05000244/20224032022-05-24024 May 2022 R. E. Ginna Nuclear Power Plant, LLC - Cyber Security Inspection Report 05000244/2022403 (Cover Letter Only) IR 05000244/20220012022-05-0303 May 2022 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2022001 IR 05000244/20224012022-03-0404 March 2022 LLC - Security Baseline Inspection Report 05000244/2022401 IR 05000244/20210062022-03-0202 March 2022 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2021006) IR 05000244/20210042022-01-20020 January 2022 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2021004 IR 05000244/20220112021-12-16016 December 2021 R. E. Ginna Nuclear Power Plant, LLC - Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000244/2022011 IR 05000244/20210032021-11-0404 November 2021 Integrated Inspection Report 05000244/2021003 IR 05000244/20215012021-09-29029 September 2021 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2021501 IR 05000244/20210052021-09-0101 September 2021 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, Llc (Report 05000244/2021005 IR 05000244/20210022021-08-0303 August 2021 LLC: Integrated Inspection Report 05000244/2021002 IR 05000244/20214012021-07-0202 July 2021 R. E. Ginna Nuclear Power Plant: Security Baseline Inspection Report 05000244/2021401 IR 05000244/20210102021-06-0707 June 2021 LLC: NRC Inspection Report 05000244/2021010 IR 05000244/20210012021-05-0505 May 2021 LLC: Integrated Inspection Report 05000244/2021001 IR 05000244/20210112021-04-27027 April 2021 LLC: Temporary Instruction 2515/194 Inspection Report 05000244/2021011 IR 05000244/20200032021-04-15015 April 2021 R. E. Ginna Nuclear Power Plant, LLC: Reissued Integrated Inspection Report 05000244/2020003 IR 05000244/20200062021-03-0303 March 2021 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020006) IR 05000244/20200132021-02-17017 February 2021 R. E. Ginna Nuclear Power Plant, LLC: Design Basis Assurance Inspection (Programs) Inspection Report 05000244/2020013 IR 05000244/20200042021-02-0808 February 2021 R. E. Ginna Nuclear Power Plant, LLC: Integrated Inspection Report 05000244/2020004 IR 07200067/20200022021-01-21021 January 2021 Independent Spent Fuel Storage Installation (ISFSI) NRC Inspection Report No. 07200067/2020002 IR 05000244/20203012020-12-0101 December 2020 R. E. Ginna Nuclear Power Plant, Initial Operator Licensing Examination Report 05000244/2020301 ML20315A3682020-11-10010 November 2020 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2020003 IR 05000244/20200052020-08-31031 August 2020 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020005) IR 05000244/20204022020-07-30030 July 2020 R. E. Ginna Nuclear Power Plant: Security Baseline Inspection Report 05000244/2020402 IR 05000244/20190102020-06-29029 June 2020 Revised Design Bases Assurance Inspection (Teams) Report 05000244/2019010 IR 05000244/20200012020-05-0606 May 2020 LLC: Integrated Inspection Report 05000244/2020001 and Independent Spent Fuel Storage Installation Report 07200067/2020001 IR 05000244/20200122020-04-0606 April 2020 LLC: Biennial Problem Identification and Resolution Inspection Report 05000244/2020012 IR 05000244/20190062020-03-0303 March 2020 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2019006) IR 05000244/20190042020-02-0505 February 2020 R.E Ginna Nuclear Power Plant, LLC: Integrated Inspection Report 05000244/2019004 IR 05000244/20194102019-11-21021 November 2019 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2019410 IR 05000244/20190032019-10-30030 October 2019 LLC - Integrated Inspection Report 05000244/2019003 2024-02-05
[Table view] |
Inspection Report - Ginna - 2009002 |
---|
|
|
|
Text
une 8, 2009
SUBJECT:
FINAL SIGNIFICANCE DETERMINATION OF WHITE FINDING, WITH ASSESSMENT FOLLOW-UP, AND NOTICE OF VIOLATION - R.E. GINNA NUCLEAR POWER PLANT [NRC Inspection Report No. 05000244/2009002]
Dear Carlin:
This letter provides you the final significance determination of the preliminary White finding sent to you with the NRC letter dated May 4, 2009, as well as the result of our assessment of the current performance of R.E. Ginna Nuclear Power Plant (Ginna). This updated assessment of Ginna supplements, but does not supersede, our annual assessment letter issued on March 4, 2009. The finding, described in detail in the subject inspection report, is associated with inadequate implementation of the preventative maintenance (PM) program for the turbine-driven auxiliary feedwater (TDAFW) pump governor that led to a failure of the pump to operate properly during a December 2, 2008, surveillance test. The finding was reviewed during an inspection completed on March 31, 2009, for which an exit meeting was held on April 16, 2009.
In a telephone conversation with Mr. Glenn Dentel of NRC, Region I, on May 13, 2009, Mr. Thomas Harding, Director of Licensing, indicated that R.E. Ginna Nuclear Power Plant, LLC did not contest the characterization of the risk significance of this finding and did not desire to discuss this issue in a Regulatory Conference or to provide a written response. Therefore, after considering the information developed during the inspection, and having assessed the finding using the reactor safety significance determination process, the NRC has concluded that the finding is appropriately characterized as White, a finding of low to moderate safety significance.
The NRC has also determined that the finding is a violation of Technical Specification 5.4.1.a, Procedures, which requires, in part, that the applicable procedures recommended in Appendix A of Regulatory Guide (RG) 1.33, Quality Assurance Program Requirements (Operations),
shall be established, implemented and maintained, including the development of preventive maintenance schedules to specify lubrication schedules. The violation is cited in the attached Notice of Violation (Notice). In accordance with the NRC Enforcement Policy, the Notice is considered escalated enforcement action because it is associated with a White finding.
You are required to respond to this letter and should follow the instructions specified in the enclosed Notice when preparing your response.
As a result of our review of Ginna performance, including this White finding, we have assessed Ginna to be in the Regulatory Response column of the NRCs Action Matrix. Therefore, we plan to conduct a supplemental inspection using Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, when your staff has notified us of your
J. Carlin 2 readiness for this inspection. This inspection procedure is conducted to provide assurance that the root cause and contributing causes of risk significant performance issues are understood, the extent of condition is identified, and the corrective actions are sufficient to prevent recurrence.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC=s document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.
Sincerely,
/RA/
Samuel J. Collins Regional Administrator Docket No. 50-244 License No. DPR-18 Enclosure:
Notice of Violation cc w/encl:
M. J. Wallace, Vice - President, Constellation Energy B. Barron, President, CEO & Chief Nuclear Officer, Constellation Energy Nuclear Group, LLC M. Korsnick, Sr. Vice President, Nuclear Operations, Constellation Energy Nuclear Group, LLC C. Fleming, Esquire, Senior Counsel, Nuclear Generation, Constellation Nuclear Energy Nuclear Group, LLC T. Harding, Director, Licensing, Constellation Energy Nuclear Group, LLC P. Eddy, Electric Division, NYS Department of Public Service C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law A. Peterson, SLO Designee, New York State Energy Research and Development Authority F. Murray, President & CEO, New York State Energy Research and Development Authority G. Bastedo, Director, Wayne County Emergency Management Office M. Meisenzahl, Administrator, Monroe County, Office of Emergency Management T. Judson, Central New York Citizens Awareness Network
ML091550004 To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/ORA RI/DRP RI/DRS RI/DRP RI/DRS NAME **ADeFrancisco **GDentel **WCook **DLew **DRoberts DATE 05/14/09 05/18/09 05/18/09 05/21/09 05/28/09 OFFICE RI/ORA RI/ORA HQ/OE* RI/RA NAME **KFarrar **DHolody *GBowman SCollins DATE 05/29/09 05/ 26 /09 06/01/09 06/02/09
J. Carlin 3 DISTRIBUTION w/encl: E Hayden, OPA ADAMS (PARS) H Bell, OIG SECY G Caputo, OI CA S. Titherington-Buda, OCFO OEMAIL M. Williams, OCFO OEWEB S Collins, RI W Borchardt, EDO M Dapas, R B Mallett, DEDR D Lew, RI S Campbell, OEDO J Clifford, RI T Bloomer, OEDO D Roberts, RI C Carpenter, OE P Wilson, RI S Magruder, OE G Dentel, RI L Lopez,OE W Cook, RI N Hasan, OE K Kolaczyk, RI D Starkey, OE L Casey, RI N Hilton, OE D. Bearde, RI J Wray, OE D Screnci G Bowman, OE N Sheehan, RI E Leeds, NRR K Farrar, RI J Wiggins, NRR D Holody, RI B Boger, NRR A DeFrancisco, RI R Nelson, NRR M McLaughlin, RI D. V. Pickett, PM, NRR D Everhart, RI B. Vaidya, PM, NRR C ODaniell, RI Enforcement Coordinators RII, RIII, RIV R1DRPMailResource (C Evans, K O=Brien, W. Jones) Region I OE Files (with concurrences)
C Marco, OGC ROPreports.Resource@nrc.gov
NOTICE OF VIOLATION R.E. Ginna Nuclear Power Plant, LLC Docket No. 50-244 R.E. Ginna Nuclear Power Plant License No. DPR-18 EA-09-045 During an NRC inspection, for which an exit was conducted on April 16, 2009, a violation of NRC requirements was identified. In accordance with the NRC Enforcement Policy, the violation is listed below:
Technical Specification 5.4.1.a, Procedures, requires, in part, that the applicable procedures recommended in Appendix A of Regulatory Guide (RG) 1.33, Quality Assurance Program Requirements (Operations), shall be established, implemented and maintained. RG 1.33, Appendix A, Section 9 (b), states, "Preventive maintenance schedules should be developed to specify lubrication schedules, inspection of equipment, replacement of such items as filters and strainers, and inspection or replacement of parts that have a specific lifetime such as wear rings. Ginna procedure M-11.5C, Auxiliary Feedwater Pump Minor Mechanical Inspection and Maintenance, Rev. 29 (M-11.5C), which is an 18 month inspection requirement for the turbine driven auxiliary feedwater pump (TDAFW), contains steps which would have ensured proper cleaning and lubrication maintenance on the governor linkage.
Contrary to the above, during March 2008, licensees technicians did not perform steps for cleaning and lubrication maintenance on the governor linkage in accordance with procedure M-11.5C. The steps to perform these activities were removed during the maintenance work planning. The subsequent lack of proper lubrication led to the operational failure of the TDAFW pump during testing on December 2, 2008.
This violation is associated with a White SDP finding.
Pursuant to the provisions of 10 CFR 2.201, R.E. Ginna Nuclear Power Plant, LLC is hereby required to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional Administrator, Region I, and a copy to the NRC Resident Inspector at the facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This reply should be clearly marked as a "Reply to a Notice of Violation; EA-09-045" and should include for each violation: (1) the reason for the violation, or, if contested, the basis for disputing the violation or significance, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved. Your response may reference or include previous docketed correspondence, if the correspondence adequately addresses the required response. If an adequate reply is not received within the time specified in this Notice, an order or a Demand for Information may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. Where good cause is shown, consideration will be given to extending the response time.
If you contest this enforcement action, you should also provide a copy of your response, with the basis for your denial, to the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001.
Notice of Violation 2 Because your response will be made available electronically for public inspection in the NRC Public Document Room or from the NRC=s document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the public without redaction. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a redacted copy of your response that deletes such information. If you request withholding of such material, you must specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request for withholding confidential commercial or financial information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.
In accordance with 10 CFR 19.11, you may be required to post this Notice within two working days.
Dated this 8th day of June 2009