Letter Finding 11/5/08 Application for Amendment Acceptable for Review
ML083500575
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 12/18/2008
From: Tam P
Plant Licensing Branch III
To: O'Connor T
Northern States Power Co
Tam P
References
TAC MD9990
Download: ML083500575 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 December 18, 2008 Mr. Timothy J. O'Connor Site Vice President Monticello Nuclear Generating Plant Northern States Power Company 2807 West County Road 75 Monticello, MN 55362-9637

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT -ACCEPTANCE FOR REVIEW OF APPLICATION FOR LICENSE AMENDMENT PERTAINING TO EXTENDED POWER UPRATE (TAC NO. MD9990)

Dear Mr. O'Connor:

By letter dated November 5, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML083230111), Northern States Power Company submitted the SUbject application. The Nuclear Regulatory Commission (NRC) staff performed an acceptance review to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the application address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed the SUbject application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements. If additional information is needed for the NRC staff to complete its technical review, you will be advised by separate correspondence. Please contact me if you have any questions.

~~v~

Peter S. Tam, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-263 cc: Distribution via ListServ

December 18, 2008 Mr. Timothy J. O'Connor Site Vice President Monticello Nuclear Generating Plant Northern States Power Company 2807 West County Road 75 Monticello, MN 55362-9637

SUBJECT:

MONTICELLO NUCLEAR GENERATII\IG PLANT - ACCEPTANCE FOR REVIEW OF APPLICATION FOR LICENSE AMENDMENT PERTAINING TO EXTENDED POWER UPRATE (TAC NO. MD9990)

Dear Mr. O'Connor:

By letter dated November 5, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML083230111), Northern States Power Company submitted the subject application. The Nuclear Regulatory Commission (NRC) staff performed an acceptance review to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the application address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed the subject application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements. If additional information is needed for the NRC staff to complete its technical review, you will be advised by separate correspondence. Please contact me if you have any questions.

Sincerely, I RAJ Peter S. Tam, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-263 cc: Distribution via ListServ DISTRIBUTION PUBLIC LPL3-1 r/f RidsNrrDorlLpl3-1 Resource RidsNrrPMMonticello Resource RidsNrrLATHarris Resource RidsOGCRp Resource RidsAcrsAcnw MailCTR Resource RidsNrrDirsSbpb RidsRgn3MailCenter Resource RidsNrrDorlDpr Accession No'.. ML083500575 OFFICE LPL3-1/PM LPL3-1/LA LPL3-1/BC NAME PTam THarris LJames DATE 12/18/08 12/18/08 12/18/08 OFFICIAL RECORD COpy