L-MT-13-020, Enclosure 1 - Responses to the Gap Analysis
ML13064A433 | |
Person / Time | |
---|---|
Site: | Monticello |
Issue date: | 02/27/2013 |
From: | Xcel Energy, Northern States Power Co |
To: | Office of Nuclear Reactor Regulation |
References | |
L-MT-13-020, TAC MD9990 | |
Download: ML13064A433 (201) | |
Text
L-MT-13-020 ENCLOSURE 1 RESPONSES TO THE GAP ANALYSIS Introduction On November 20, 2012, Northern States Power - Minnesota (NSPM) presented to the NRC the results of a Gap Analysis performed to verify the adequacy of the extended power uprate (EPU) documentation. Due to the delay in review of the Monticello Nuclear Generating Plant (MNGP) EPU License Amendment Request (LAR), the NRC was concerned that various aspects of the NRC review were no longer applicable.
Through the Gap Analysis, NSPM demonstrated that various technical items required revision and some design and licensing bases information had changed, but overall the body of EPU documentation was correct with the exception of the issues identified for correction.
As part of that discussion, NSPM provided the NRC with a table of items that had changed in the EPU documentation. This table was discussed and NRC provided their comments on the documentation needed to close the items.
On January 21, 2013 NSPM provided a response to many of the Gap analysis items.
This enclosure contains a brief synopsis of each of the remaining items discussed in the Gap Analysis, the information the NRC needed to close the gap (from the November 20, 2012 meeting with NRC), and the NSPM response to the identified gap.
Contents Provided below are responses to the following items from the Gap Analysis:
Item 1- Main Steam Line High Flow Trip - 10 CFR 21 Error Notification Item 2- RADTRAD - 10 CFR 21 Error Notification Item 3- Condenser Free Volume Change Item 4- Feedwater Transient Response Commitment Change Item 5- Environmental Assessment (EA) Changes Page 1 of 15
L-MT-13-020 Enclosure 1 ITEM 1 - MAIN STEAM LINE HIGH FLOW TRIP - 10 CFR 21 ERROR NOTIFICATION NRC REQUESTED INFORMATION: General Electric-Hitachi issued a 1-0 CFR 21 60-day Interim Notification on September 27, 2012 concerning a potential non-conservatism in calculation of Main Steam Line (MSL) choked flow rates. The NRC needs reasonable assurance that current configuration is acceptable. NSPM will need to provide a technical discussion of why 10CFR21 Notification is not applicable to MNGP or provide a change to MNGP Technical Specification Allowable Value.
NSPM RESPONSE:
Background
NSPM issued letter L-MT-08-052 (Reference 1-1) to the NRC which requested approval of an extended power uprate (EPU). As part of the EPU NSPM provided changes to the MNGP Technical Specifications (TS) associated with-the planned power level change.
NSPM did not identify the Main Steam Line High Flow trip as an impact of the EPU.
Subsequently, NSPM issued:
- L-MT-09-026 (Reference 1-2), which provided a response to EICB RAI No. 1..
Included in this response was a description of NSPM calculation CA-95-075, Main Steam Line High Flow Setpoint, Revision 1. NSPM also provided a copy of the calculation for NRC review.
- L-MT-09-027 (Reference 1-3), which provided a response to EICB RAI No. 3. This response stated that the Main Steam Line Flow - High TS setting (TS Table 3.3.6.1-1, Primary Containment Isolation Instrumentation, Function 1.c) was affected and that NSPM would provide the TS changes in the future, and
- L-MT-09-047 (Reference 1-4) which supplemented the EPU with additional TS changes. One of the TS changes included in L-MT-09-047 involved TS Table 3.3.6.1-1, Primary Containment Isolation Instrumentation, for Main Steam Line Flow
- High (Function 1.c).
Issue
'GEH issued a 10 CFR Part 21 Communication entitled "Error in Main Steam Line High Flow Calculational Methodology," SC 12-18, R1, issued on December 12, 2012 (Reference 1-5). The document indicated that GEH had discovered the potential for non-conservative values of the MSL Flow - High instrument setpoint, established from non-conservatively calculated values of the MSL choked flow rate. Further investigation of the issue revealed that the choices of input values that led to the previous non-conservative values of choked flow rate also led to overly-conservative values of associated flow-instrument pressure drop, which compensated for the non-conservatism in the MSL choked flow rate.
GEH updated the calculation technique used to evaluate the choked flow rate and the associated MSL flow-instrument pressure drop for the MNGP at Current Licensed Thermal Power (CLTP) conditions and at EPU conditions. The evaluation determined that the Analytical Limits for the MSL Flow - High instrument trip, as calculated for Page 2 of 15
L-MT-13-020 CLTP and EPU conditions remain conservative with respect to MSL choked flow conditions.
The revised calculation model changes the relationship between MSL flow and flow-instrument pressure drop, and provides a higher instrument pressure drop value (in psid) for a given flow rate (in % rated flow), which accounts for the change in MSL high flow setpoint and setpoint margins. For this reason, the current values of % rated flow and MSL flow rate for the current Analytical Limit and Allowable Value no longer directly correspond to each other (although these current values can conservatively be used as they are, as explained below in the discussion of setpoint options).
Because the revised calculation method now results in lower values of flow rate corresponding to a given flow-instrument pressure drop (in psid), MNGP determined that changes were needed to the TS setpoint value to account for the error.
Revision to the Setpoint Per GEH the existing setpoint Allowable Value and Analytical Limits are actually more conservative with respect to ensuring a trip well below choked flow considering the results from the new methodology. These setpoint values, expressed as differential pressures, are not being changed for EPU. However, L-MT-09-047 defined the EPU Allowable value for the MSL High Flow Main steam isolation valve (MSIV) isolation function as a percent of flow, vs. a differential pressure. This is consistent with the existing TS.
Due to the revised data from GEH regarding the flow element differential pressure vs.
mass flow relationship, the setpoint requested for EPU (<123.6% of EPU flow Allowable Value) is no longer valid. Per GEH, the instrument Allowable Value of *151.95 psid corresponds to *116.9% of rated EPU flow. Therefore a revision to the setpoint is required to change the Allowable Value for the MSL High Flow trip function from
- 123.6% to *116.9% of rated EPU steam flow.
Other Considerations Because the current values of the MSL Flow - High instrument Analytical Limit and Allowable Value as expressed in psid are conservative with respect to the revised choked flow rate, those setpoint values in psid can be retained as they are. But because the revised calculation method now results in lower values of flow rate corresponding to a given flow-instrument pressure drop (in psid), the, MNGP Allowable Value (TS value) requires revision based on the associated flow rate. An advantage to this approach is that it retains the existing flow-instrument setpoint values (in psid), and the MSL Flow - High instrument trip function would continue to operate as it did previously. Because the calculated flow corresponding to this setpoint is lower than previously assumed, this would ensure the mass releases for a main steam line break.
(MSLB) remain bounding. Therefore, no changes to the MSLB analyses are required.
Page 3-of 15
L-MT-13-020 Enclosure 1 Conclusion
.The error correction used to support SC 12-18, R1, modifies the relationship between the instrument Allowable Value as expressed in psid and the % flow rate value stated in TS Table 3.3.6.1-1, Primary Containment Isolation Instrumentation, for MSL Flow-High (Function 1.c). Therefore, it is necessary to change the TS value from 123.6% to 116.9%. However, the actual flow and psid values have not changed so other analyses are not affected.
See Enclosure 2 for mark ups to L-MT-09-026, L-MT-09-027 and L-MT-09-047. See Enclosure 3 for a proprietary copy of the GEH evaluation of SC 12-18. See Enclosure 4 for a non-proprietary copy of the GEH evaluation of SC 12-18 and NSPM calculation 05-75, Revision 11 that support the revised MSL Flow - High instrument setpoint.
References 1-1 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC), "License Amendment Request: Extended Power Uprate (TAC MD9990)," L-MT-08-052, dated November 5, 2008. (ADAMS Accession No. ML083230111) 1-2 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC), " Monticello Extended Power Uprate: Response to NRC Instrumentation & Controls Branch Request for Additional Information (RAI) dated March 11, 2009, and April 6, 2009, and Fire Protection Branch RAIs dated March 12, 2009 (TAC No.
MD9990)," L-MT-09-026, dated May 13, 2009. (ADAMS Accession No. ML091410120) 1-3 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC), "Monticello Extended Power Uprate: Response to Instrumentation and Controls Branch RAI No. 3 dated April 6, 2009 (TAC MD9990)," L-MT-09-027, dated August 19, 2009.
(ADAMS Accession No. ML092320064) 1-4 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC),
"Supplement to Extended Power Uprate License Amendment Request: Revision to Proposed Technical Specification Changes in Response to Staff Comments (TAC MD9990)," L-MT-09-047, dated August 31, 2009. (ADAMS Accession No. ML092440171) 1-5 GEH 10 CFR Part 21 Communication, SC 12-18, "Error in Main Steam Line High Flow Calculational Methodology," Revision 1, dated December 12, 2012.
Under L-MT-09-026 NSPM provided the NRC with calculation CA-95-075, Main Steam Line High Flow Setpoint, Revision 1. The NSPM calculation provided in Enclosure 4 to this letter also has the same number and revision number. Since the EPU change had never been approved by the NRC this calculation revision number was reissued to incorporate changes to address SC 12-18.
Page 4 of 15
L-MT-1 3-020 ITEM 2 - RADTRAD - 10 CFR 21 ERROR NOTIFICATION NRC REQUESTED INFORMATION: NSPM was notified by a vendor that RADTRAD analyses contained error concerning use of deposition model for Alternative Source Term (AST) analyses. Provide a revised analysis description to NRC and provide new AST event values. Confirm X/Qs for events has not changed. Confirm no other changes were made to the Loss of Coolant Accident (LOCA) AST analysis.
NSPM RESPONSE:
On September 25, 2012, the RADTRAD Users Group members were notified of an error in Version 3.03 of the RADTRAD code. This code was used for MNGP in the application of the AST for post-accident dose consequence analyses.
The error reported by the RADTRAD Users Group results in a non-conservatism in the calculation of natural deposition effects inside the drywell after a LOCA. It was determined through test cases that the change in BWR doses was less than 0.1 Rem.
Revisions to the MNGP EPU LOCA dose consequence analyses are required to apply model changes that correct this code deficiency. No other accident analyses are affected by this RADTRAD error.
The following calculations are being revised. These calculations were provided for NRC review in References 2-1 and 2-2 (see also Reference 2-3 for additional TSC dose revision discussion and Reference 2-4 for final dose results).
" MNGP-003, "MNGP AST - LOCA Radiological Consequence Analysis", Rev 3 to be updated to Rev 4
" ALION-CAL-MNGP-4370-02, "MNGP EPU - CR and TSC Direct Dose," Rev 0 to be updated to Rev 1
" ALION-CAL-MNGP-4370-03, "MNGP EPU - TSC Internal Dose," Rev 1 to be updated to Rev 2 There is no change to the calculation inputs, including atmospheric dispersion coefficients (X/Qs). The only modeling change is in the RADTRAD software treatment of the Powers natural deposition model in the drywell. No other changes to the LOCA AST analysis have been made. Both inhalation and direct dose are affected for the Control Room and TSC.
The limiting dose cases for the MNGP LOCA analyses were reanalyzed using the model change discussed above. The results demonstrate that the LOCA dose increases less than 5 mrem TEDE in each case. These cases are being incorporated into the MNGP LOCA analyses.
Doses remain well within the limits of 10CFR50.67 and RG 1.183. The reported dose does not change as the increase is too small to be seen using two significant figures.
Page 5 of 15
L-MT-13-020 Regulatory Limit Reported EPU Updated EPU (10CFR50.67 & RG Dose Dose 1.183)
Control Rm 3.80 Rem 3.80 Rem 5 Rem TEDE (increases 4 mrem or 0.1%)
EAB 1.46 Rem 1.46 Rem 25 Rem TEDE.
(increases 2 mrem or 0.1%)
LPZ 1.99 Rem 1.99 Rem 25 Rem TEDE (increases 1 mrem or 0.05%)
TSC 0.92 Rem 0.92 Rem 5 Rem TEDE (increases 2 mrem or 0.2%)
See Enclosure 2 for mark ups to L-MT-08-036, Enclosures 2, 5 and 6, L-MT-08-052, and L-MT-09-042, Enclosure 1. L-MT-08-052, Enclosure 4 is also impacted by this change; however, these markups are provided in the revised environmental assessment provided in Enclosure 5.
References 2-1 Letter from T J O'Connor (NSPM) to Document Control Desk (NRC), "Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplement Regarding Radiological Analysis," L-MT-08-036, dated May 20, 2008. (ADAMS Accession No. ML081430494) 2-2 Letter from T J O'Connor (NSPM) to Document Control Desk (NRC), "Monticello.
Extended Power Uprate: Updates to Docketed Information (TAC MD9990)," L-MT-10-072, dated December 21, 2010. (ADAMS Accession No. ML103570026) 2-3 Letter from M A. Schimmel (NSPM) to Document Control Desk (NRC),
"Monticello Extended Power Uprate (EPU): Supplement for Gap Analysis Updates (TAC MD9990)", L-MT-12-114, dated January 21, 2013.
2-4 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC), "License Amendment Request: Extended Power Uprate (TAC MD9990)," L-MT-08-052, dated November 5, 2008. (ADAMS Accession No. ML083230111)
Page 6 of 15
L-MT-13-020 ITEM 3 - CONDENSER FREE VOLUME CHANGE NRC REQUESTED INFORMATION: The first sentence on page 2-143 of L-MT 052, Enclosure 5, states that the condenser's use as a holdup volume is not impacted by EPU since it is not being modified. However, elsewhere in L-MT-08-052, Enclosure 5, it states that the condenser level will be increased for the new condensate pumps.
Provide a discussion of revised calculation, including a table of changes. Indicate Loss of Coolant Accident (LOCA) is not affected. For steam jet air ejector (SJAE), identify changed assumptions, confirm other assumptions have not changed, and report the results. Also, provide a table of the assumptions being changed and why the regulatory limits are. still met. Confirm no other changes have been made to the Control Rod Drop Accident (CRDA) Alternative Source Term (AST) analysis.
NSPM RESPONSE:
New condensate pumps being installed for EPU will require a higher operating hotwell level. The increase in hotwell level will decrease the available condenser free volume assumed in the design basis accident (DBA) CRDA radiological consequences analysis, resulting in a slight increase in dose for some CRDA cases.
This change in hotwell level does not affect any other DBA radiological dose analyses.
The Loss of Coolant Accident (LOCA) analysis utilizes a condenser free volume that is based on condenser volume above the entry of the main steam drain line, which is well above the normal condenser hotwell level, and is therefore unaffected by an increased hotwell level. The other accidents (Fuel Handling Accident and Main Steam Line Break Accident) do not involve the condenser.
The CRDA accident analysis uses the condenser free volume to determine the radioisotope activity concentration in the condenser resulting from transport of the CRDA fuel damage activity to the condenser. The total amount of activity in the condenser available for release to the environment will not change; however, the activity concentration (activity per cubic foot) increases as the condenser free volume decreases.
The condenser free volume does not impact doses for release cases involving an isolated condenser which leaks at a volume fraction per day (1% volume per day), since the total activity in the condenser does not change.
The decrease in condenser free volume does impact release cases which involve a specified flow rate since increasing the activity concentration (activity per cubic foot) will result in higher amounts of activity released to the environment for a given flow rate.
The affected cases are condenser release through the Mechanical Vacuum Pump (MVP) and SJAE via the offgas stack. The SJAE release case is the limiting case for the CRDA.
Page 7 of 15
L-MT-13-020 Calculation MNGP-005, "MNGP AST - CRDA Radiological Consequence Analysis," Rev 2, was updated in Rev 3 to incorporate the revised condenser free volume based on the new hotwell operating volume. Rev 2 was provided for NRC review in Reference 3-1 (incorporated as MNGP Calculation 04-040). No other inputs or assumptions were changed in the CRDA AST analysis. The limiting dose (SJAE release) increased approximately 2%. Doses remain well within the limits of 10CFR50.67 and Regulatory Guide 1.183.
Regulatory Limit Reported EPU Updated EPU (10CFR50.67 & RG Dose Dose 1.183)
Control Rm 1.86 Rem 1.89 Rem, 5 Rem TEDE EAB 1.96 Rem 2.00 Rem 6.3 Rem TEDE LPZ 0.90 Rem 0.91 Rem 6.3 Rem TEDE See Enclosure 2 for mark ups to L-MT-08-036, Enclosure 3 and L-MT-08-052, .
References 3-1 Letter from T J O'Connor (NSPM) to Document Control Desk (NRC), "Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplement Regarding Radiological Analysis," L-MT-08-036, dated May 20, 2008. (ADAMS Accession No. ML081430494)
Page 8 of 15
L-MT-13-020 ITEM 4 - FEEDWATER TRANSIENT RESPONSE COMMITMENT CHANGE NRC REQUESTED INFORMATION: A current NRC commitment for the EPU project states: "NSPM will perform an analysis priorto EPU implementation to predict combined Condensate and Feedwatersystem performance for normal operationand for transientsincluding Single Feedwaterpump trip, FeedwaterControlSystem Failureand Single Condensate Pump Trip. Acceptance criteriawill include adequate margin to preclude loss of both reactorfeedwater pumps from low suction pressure or flow." This commitment is not complete at this time and NSPM wishes to revise the commitment.
At a meeting held between NSPM and NRC on November 20, 2012 the NRC agreed that commitment can be changed. NSPM will revise commitment and explain the results of our analyses in this area. NSPM will describe the basic strategy employed during Feedwater transients. NRC requested that NSPM assess BOP failures with this approach in terms of Probabilistic Risk Assessment (PRA) impact. This includes assessing the change in commitment for Feedwater/Condensate pump trips for impact on PRA.
NSPM RESPONSE:
In NSPM letter L-MT-09-046 (Reference 4-1), NSPM provided a supplement to the EPU LAR that included the following commitment.
NSPM will perform an analysispriorto RF025 to predict combined Condensate and Feedwatersystem performance for normal operationand for transientsincluding Single Feedwaterpump trip, FeedwaterControl System Failureand Single Condensate Pump Trip. Acceptance criteria will include adequate margin to preclude loss of both reactorfeedwater pumps from low suction pressure or flow.
Subsequently, NSPM revised this commitment in letter L-MT-1 1-044 (Reference 4-2), to read as follows:
NSPM will perform an analysispriorto EPU implementation to predict combined Condensate and Feedwatersystem performance for normal operationand for transientsincluding Single Feedwaterpump trip, FeedwaterControl System Failure and Single CondensatePump Trip. Acceptance criteria will include adequate margin to preclude loss of both reactorfeedwater pumps from low suction pressureor flow.
NSPM has evaluated this commitment and has determined that a change is necessary.
NSPM performed evaluations of events that could impact Condensate/Feedwater (CFW) flow availability during or after a transient. NSPM evaluated the following transient conditions.
" Single feedwater pump trip
, Single condensate pump
" Loss of13.8kV Bus11 or12 Page 9 of 15
L-MT-1 3-020
- 2R to 1R transfer event
- Condensate demineralizer bypass valve opening transient analysis
- Steady state operation with feedwater regulating valves wide open (Runout)
- Feedwater pump recirculation valve fail open
" Feedwater pump cold starts 0 Evaluation of condensate and feedwater pump hot start scenario Of these events only the loss of a condensate pump and loss of Bus #11 or #12 will affect the availability of feedwater flow following the event. A discussion of these events is provided below.
Evaluation of Condensate/Feedwater Pump Transients NSPM completed evaluation of Condensate and Feedwater pump transients using a dynamic CFW system model and other modeling techniques. The model provides an integrated plant response and includes the effects of the recirculation pump runback that automatically occurs following a single condensate pump or feedwater pump trip.
The model has shown that a single feedwater pump trip will not result in a loss of both reactor feedwater pumps at EPU and MELLLA+ conditions.
A separate sensitivity study has shown that the trip of a single condensate pump challenges the reliability of the feedwater system as the feedwater flow demand due to the large steam/feedwater flow mismatch is beyond the design capacity of the remaining (single) condensate pump. In this scenario, the remaining condensate pump will be in a sustained run out condition with unstable flow as the feedwater flow demand will be at maximum, and it is possible that both feedwater pumps will trip due to lack of sufficient suction pressure.
The mismatch between available pump flow and required reactor makeup will result in a reactor water level automatic scram irrespective of whether a single condensate pump is available, as the runback final power state point is approximately 70% power at EPU and approximately 80% of EPU power within the MELLLA+ operational domain, which is beyond the rated capacity of a single condensate pump.
The steam/feedwater mismatch cannot be significantly reduced by lowering the limit stop of the recirculation runback that automatically occurs following a single condensate pump trip, as the limit stop is constrained to prevent a post transient power/flow operating condition inside the stability exclusion region.
The MNGP CFW system does not have multi-pump redundancy and does not include backup condensate or condensate booster pumps that were included in later BWR designs. NSPM has confirmed that there are no design basis performance requirements for the MNGP recirculation pump runback with respect to preventing a reactor water low level scram or assuring the reliability of the feedwater system after a single condensate pump trip. The stability constraint and the integrated system design Page 10 of 15
L-MT-13-020 is such that a reactor scram due to low reactor water level cannot be prevented without requiring the operator to reduce power with control rods very quickly.
It is not part of the MNGP design basis to demonstrate continued operation of a feedwater pump after a single condensate pump trip or to demonstrate that a reactor low level scram does not occur during this event. In addition, it is not prudent to require challenging operator actions to try to reduce steam/feedwater flow sufficiently in an effort to avoid a scram with control rod insertions. This operator action would have little safety benefit in the event of a single condensate pump trip from rated power.
Loss of Bus #11 or 12 The loss of Bus #11 or #12 will result in the loss of a reactor recirculation pump, a feedwater pump and a condensate pump. The event does not directly result in the initiation of reactor recirculation pump runback logic. The power level following a trip of one reactor recirculation system pump will be up to 77% under MELLLA+ operation with the highest possible rod line. This flow rate is beyond the capacity of the single remaining condensate pump and a low reactor water level automatic scram will result.
The evaluation of feedwater availability requires the power level to be at or below 69%
after the transient for feedwater flow to remain available through the event. Therefore, the loss of either bus #11 or #12 will result in the loss of feedwater flow.
It is not part of the MNGP design basis to demonstrate continued operation of a feedwater pump after a single condensate pump trip or to demonstrate that a reactor low level scram does not occur during this event.
Feedwater Control System Failure Evaluations of failures of the feedwater level control system are completed as part of the transient analyses for each reload and were included in EPU analyses submitted to the NRC. See Reference 4-3, Enclosure 5, sections 2.4.1.2 and 2.8.5.1 for details.
Each of these evaluations determined that the Feedwater control system failure is within the requirement of the current licensing basis following implementation of the EPU. The fuel design limits and reactor coolant pressure boundary limits previously evaluated under EPU conditions are not challenged by these events.
In addition, the EPU Startup Testing program includes the following steps to confirm the operational capability of the level control system (Reference 4-3, Enclosure 5, Section 2.12.1).
Control system tests will be performed for the reactorfeedwater/reactorwater level controls, pressure controls, and recirculationflow controls, if applicable.
These operationaltests will be made at the appropriateplant conditions for that test at each of the power increments, to show acceptable adjustments and operationalcapability.
The analysis concluded that feedwater availability is maintained.
Page 11 of 15
L-MT-1 3-020 Conclusion The analyses conclude that for most transient events feedwater availability is maintained. Based on the evaluation and operations experience described above, it is prudent to change operating procedures to require a manual scram following a single condensate pump trip from higher rod lines without reactor water level recovery, as this action lowers feedwater demand, enhances the reliability of the remaining condensate pump, and places the reactor in a stable and safe condition from which the operators can attempt to recover the CFW system if necessary.
Bus #11 or #12 failure evaluations were also completed. These evaluations indicate that EPU conditions will result in a loss of feedwater for this event.
For Feedwater Control System failures, previous evaluations determined that fuel design limits and reactor coolant pressure boundary limits will not be exceeded under EPU conditions and have not changed. The analysis concluded that feedwater availability is maintained.
In light of the conclusions above a.nd the completed evaluations, NSPM is superseding the commitment included in L-MT-09-046 and L-MT-11-044 as cited above. The revised commitment is as follows:
Priorto EPU implementation NSPM will revise operatingprocedures for Condensate/Feedwater(CFW) transientevents, to take prudent actions to recover CFW flow, and place the reactorin a safe and stable condition.
No markups to EPU documentation are necessary based on the change of commitment.
Supplemental Risk Assessment Information This item requests a change of commitment associated with operation of FW/Condensate after a transient on the system has occurred. The following assesses the effect the change in commitment will have on the MNGP PRA model.
Questions have been raised regarding feedwater system response following plant transients, including those initiated by a perturbation in the feedwater system itself. As this is a complicated question dependent on many variables such as initial power level, cause of the transient, feedwater level control response, status of feedwater support systems and human intervention, the PRA mnodel has always made the assumption that both feedwater pumps will trip following any initiating event. This is a conservatism in the PRA model since several initiating events may not necessarily result in a trip of one or both feedwater pumps, and NSPM is attempting to make adjustments that will allow the feedwater system to remain on line when possible following plant trips.
The assumption is supported by some historic plant-specific post-transient experience, and requires that human intervention including starting a pump is always necessary to Page 12 of 15
L-MT-1 3-020 reestablish high pressure feedwater flow to the reactor vessel. The MNGP PRA model continues to implement this conservative feature in its feedwater system assumptions.
Restarting an electrically driven feedwater pump is a relatively simple action provided its support systems are functional and pump interlocks are satisfied. As human actions are virtually always necessary post transient to allow continued feedwater operation, even if a feedwater pump remains initially untripped, this assumption is not overly conservative.
References 4-1 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC), " Monticello Extended Power Uprate: Response to NRC Balance of Plant Review Branch (SBPB) Request for Additional Information (RAI) dated March 23, 2009 (TAC No.
MD9990)," L-MT-09-046, dated June 12, 2009. (ADAMS Accession No. ML091670410) 4-2 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC), " Monticello Extended Power Uprate (EPU): Update on EPU Commitments (TAC MD9990),"
L-MT-1 1-044, dated August 30, 2011. (ADAMS Accession No. ML11249A045) 4-3 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC), "License Amendment Request: Extended Power Uprate (TAC MD9990)," L-MT-08-052, dated November 5, 2008. (ADAMS Accession No. ML083230111)
Page 13 of 15
L-MT-13-020 ITEM 5 - ENVIRONMENTAL ASSESSMENT (EA) CHANGES NRC REQUESTED INFORMATION: Later Resource Plan and census data will impact the Environmental Assessment (EA) provided in L-MT-08-052, Enclosure 4. NRC requested some discussion of inputs that may have changed (e.g. land use, environmental justice, new endangered species, NPDES permit changes, etc.) or confirm that they did not change. Also look at the criteria in 10 CFR 51.92 for environmental impact statement changes. Provide some assessment of the issued EA performed by NRC and indicate that conclusions remain valid.
NSPM RESPONSE:
NSPM letter L-MT-08-052 (Reference 5-1), Enclosure 4 provided an EA of operation of the MNGP at EPU conditions. The EA was performed in 2008. NSPM supplemented the 2008 EA with letter L-MT-09-003 (Reference 5-2), Enclosure 1, which provided response to NRC Environmental Branch Requests for Additional Information in January 2009. NSPM has reviewed both the 2008 EA and the 2009 supplement to determine what information has changed since submittal of those documents. Enclosure 5 contains a revised EA that replaces L-MT-08-052, Enclosure 4 in its entirety. NSPM also included updates to data presented in the 2009 supplement when necessary, therefore, the data provided in L-MT-09-003 is also being replaced.
The revised 2008 EA contains a vertical line in the right-hand column to indicate places where our analysis has been updated using the most recent, available data 2. Data not edited remains unchanged and continues to be valid. The results of these changes do not modify the overall conclusions of the EA, that there is minimal impact to the environment from the MNGP EPU.
NSPM also reviewed the EA and Finding of No Significant Impact (FONSI) published by the NRC on January 11, 2010 (Reference 5-3). Although some of the data presented in the NRC's EA and FONSI will be updated by the above-referenced edits to the 2008 EA-and 2009 supplemrent, the NRC's conclusion that the proposed action (extended power uprate) will not have a significant effect on the quality of the human environment remains valid.
Per 10 CFR 50.92, the edits to the EA offered as part of the proposed amendment do not involve a significant increase in the probability or consequences of an accident previously evaluated, create the possibility of a new or different kind of accident from any accident previously evaluated, or involve a significant reduction in a margin of safety.
See Enclosure 2 for mark ups to L-MT-08-052, Enclosure 4 and L-MT-09-003, .
2 Table 7.3.8-1 in the EA was updated to reflect the correct regulatory dose limits for a Fuel Handling Accident.
Page 14 of 15
L-MT-13-020 A revised copy of the Environmental Assessment is provided in Enclosure 5.
References 5-1 Letter from T J O'Connor (NSPM), to Document Control Desk (NRC), "License Amendment Request: Extended Power Uprate (TAC MD9990)," L-MT-08-052, dated November 5, 2008. (ADAMS Accession No. ML083230111) 5-2 Letter from T J O'Connor (NSPM) to Document Control Desk (NRC), "Response to NRC Environmental Branch Requests For Additional Information (RAIs) dated December 18, 2008 (TAC MD9990)," L-MT-09-003, dated January 29, 2009.
(ADAMS Accession No. ML090300303) 5-3 Letter from P S Tam (NRC) to T J O'Connor (NSPM), "
Subject:
Monticello Nuclear Generating Plant (MNGP) - Final Environmental Assessment and Finding of No Significant Impact Related to the Proposed Extended Power Uprate (TAC No. MD9990)," dated January 11, 2010. (ADAMS Accession No.
MIL093220925)
Page 15 of 15
L-MT-13-020 ENCLOSURE 2 MARKED UP PAGE CHANGES TO EPU DOCUMENTATION BASED ON THE GAP ANALYSIS RESULTS Item 1 - Markup to L-MT-09-026, Enclosure 1; L-MT-09-027, Enclosure 1; and L-MT-09-047, Enclosures 1, 2 and 3 Item 2 - Markup to L-MT-08-036, Enclosures 2, 5 and 6; L-MT-09-042, Enclosure 1; and L-MT-10-072, Enclosures 5 and 7 Item 3 - Markup to L-MT-08-036, Enclosure 3; and L-MT-08-052, Enclosure 5 Item 4 - No markup required.
Item 5 - Markup to L-MT-08-052, Enclosure 4, and L-MT-09-003, Enclosure 1 24 pages follow
L-MT-09-026 Page 2 of 16 employs NEDC-31336P-A, Class 3, General Electric Instrument Setpoint Methodology, in determining instrumentation setpoints.
Item Setpoint Description/Basis 1151.951 1 Main Steam Line Flow - High I Main Steamline Flow -High ,
Parameter CLTP Reference EPU Reference AL 160.63 psid CA-95-075 RO 165 CA-95-075 R1 AV 159.5 psid CA-95-075 RO 469-6 psid CA-95-075 R1 AV 142 % CA-95-070 RO 4123.614 % (rnd to CA-95-075 R1 NTSP 143.0 psid CA-95-075 RO 143.0 psid I CA-95-075 R1 CPPU Effect: Increased reactor power level and steam flow. 1116.9%1 CPPU Basis: This setpoint is used to isolate the Group 1 primary containment isolation valves. The only safety analysis event that credits this trip is the main steamline break accident (MSLBA). The main steamline flow restrictor limits coolant lost through the break and the subsequent radioactive exposure. 120.5 302E6 The analytical limit for high main steamline fl isolation for PU was raised slightly to account for error terms but was maintain well below the rrent rated steam flow for the flow restrictor in each main steam Ii . he main steamli e high flow analytical limit is 9~448% of CLTP steam flow or 2% of uprated therm power conditions which is well below the restrictor choke flow point specified as 2 227-6 lb/hr or 4644% of EPU rated steam flow per line. The MSL flow rate is monitored using differential l"ssure. MNGP has elected to maintain the Allowable Value and Nominal Trip Setpoints at th Isame absolute steam flow and differential pressure values as currently implemented. 9 The allowable value has been calculated to maintain the value at essentially the same absolute steam flow by calculating the new value of percent steam flow at EPU conditions that provides the same differential pressure (151.95 psid) across the flow sensors as the current AV.
Item 1I ENCLOSURE I ATTACHMENT 1 CALCULATIONS CA-95-073, REV. 4 - REACTOR LOW WATER LEVEL SCRAM SETPOINT CA 06 076-, REV.I MAIN STEAM LINE HIGH FLOW SETPONT IDocument Superseded CA-96-054, REV. 5 - TURBINE STOP VALVE CLOSEIGENERATOR LOAD REJECT SCRAM BYPASS CA-08-050, REV. 0 - INSTRUMENT SETPOINT CALCULATION - AVERAGE POWER RANGE MONITOR (APRM) NON-FLOW BIASED PRNM SETPOINTS FOR CLTP and EPU
- ATTACHMENT 3 - AVERAGE POWER RANGE MONITOR SELECTED PRNM LICENSING SETPOINTS EPU OPERATION (NUMAC)
Iltem 1 IThis document has been superseded. This document is no longer applicable to Ithe MNGP EPU.
ISSUE
SUMMARY
Form SOP-0402-07, Revision 7B DESIGN CONTROL
SUMMARY
IENT Northern States Power company UNIT NO.: 1 Page No.: 1 P JECT NAME: Monticello Nuclear Generating Plant CALC. N CA-95-075, Revision 1 PRO CT NO.: 11972-049 ED NUCLEAR SAFETY- RELAT
[E NOT NUCLEAR SAFETY-LATED TITLE: Main Steam Line High Flow Setpoint EQUIPMENT NO DPIS-2-116/718/9 A,B,C&D
%I IDE GCATION OF PAGES ADDED/REVISED/SUPERSEDEDNOIDED & REVIEW M 0 This revision completely rsedes Revision 0 INPUTS/ ASSUMPTIONS 0 VERIFIED
[I UNVERIFIED REVIEW METHOD: Detailed REV. 1 STATUS: Approved TE FOR REV.: 12/18/2008 PREPARER Nicholas Torres / - DATE: 12/18/2008 Eric Kolodziejczyk -
REVIEWER John O'Hara/ ON ./ DATE: 12/18/2008 Greg Rainey APPROVER Steven Malak DATE: 12/18/2008 IDENTIFICATION OF PAGES AbE/VI" RSDIODD & REVIEW METHOD
~INPUTS/ ASSUMPTIONS
[]0VERIFIED El UNVERIFIED REVIEW METHOD: REV."
STATUS: DATE FOR REV.:
PREPARER DATE:
REVIEWER z DATE:
APPROVER DATE:
IDENTIFICATIONF PAGES ADDED/REVISED/SUPERSEDEDNOIDED & R VIEW METHOD PUTS/ ASSUMPTIONS
- uERIFIED E, U E RIF IE D REVIEW METH REV.
STATUS: DATE FOR REV.:
PREPARE REVI DATE:
DATE:
APPER DATE:
NOTE: PRINT AND SIGN INTHE SIGNATURE AREAS SOPO40207.DOC Page I of I Rev. Date: 11-12-2007
FItem 1 I L-MT-09-027 Enclosure 1 Page 4 of 5 In addressing the setpoint methodology issues, the licensee identified TS Table 3.3.1.1-1, Function 2.a, "APRM Neutron Flux-High (Setdown), "Function 2.b, "APRM Simulated Thermal Power - High," and Function 2.f, "OPRM Upscale," as functions that are not LSSS SL-related. The NRC staff agrees with the licensee's determination that the above functions are not LSSS.
Therefore, in accordance with the plant-specific analysis provided by the NSPM as approved by the NRC Safety Evaluation for the PRNMS amendment, the NSPM is not proposing TSTF-493 style footnotes for the APRM Simulated Thermal Power - High function.
The second allowable value change involved a change to the Main Steam Line Flow -
High function. It was identified that Function 1.c within TS Table 3.3.6.1-1, "Primary Containment Isolation Valves," which provides isolation of the Main Steam Lines on high flow, should also have been revised as part of the EPU license amendment request as a function requiring a change to the associated allowable value. The allowable value for Function 1.c within TS Table 3.3.6.1-1 will be revised as follows:
Current Proposed Allowable Value Allowable Value Function 1.c, Main Steam Line 142 percent 123.6 percent Flow-High I-116"9I The revision to the allowable value for Function 1.c will be provided to the NRC in a separate letter.
Attachment A to Reference 2, "Identification of Functions to be Annotated with the TSTF-493 Footnotes," provides the disposition of Functions to be included in TSTF-493.
As stated in Reference 2:
The indicated generic dispositions were discussed with the NRC in a teleconference held on February 11, 2009 and the NRC staff agreed that the Attachment indicates those functions applicable to all licensees for which no plant-specific analysis is required.
The Main Steam Line Flow - High function (Function 1.c) in TS Table 3.3.6.1-1 is not included in the list of functions contained in Attachment A (see section for NUREG-1433, Boiling Water Reactor / 4 Plants) and hence application of the interim TSTF-493 style footnotes is not required nor is proposed for this function by the NSPM.
Conclusion In accordance with the NRC Safety Evaluation for the PRNMS license amendment, the NSPM is not adopting interim TSTF-493 footnotes for the APRM Simulated Thermal
L-MT-09-047 Page 2 of 6 3.0 ANALYSIS OF THE PROPOSED CHANGES 3.1 Main Steam Line Flow- High (Function 1.c) of TS Table 3.3.6.1-1 This change revises the Allowable Value in TS Table 3.3.6.1-1, Primary Containment Isolation Instrumentation, for the Main Steam Line Flow - High (Function 1.c), from < 142 % rated steam flow to < .3.6 % rated steam flow.
By letter dated May 13, 2009 (Reference 2), NSPM identified two errors with the Main Steam Line Flow - High isolation Allowable Value in the EPU documentation.
- 1. The entry for Main Steam Line (MSL) isolation on high flow in PUSAR(1)
Table 2.4-1 was incorrectly labeled as an Analytical Limit (AL) instead of an Allowable Value (AV), and the associated EPU AV had been transposed incorrectly from PUSAR page 2-102.
- 2. The associated TS changes to the AV for the Main Steam Line (MSL) isolation on high flow function had been evaluated but the affected TS pages had inadvertently been omitted from the submittal.
NSPM also indicated that the above changes would be submitted by a supplemental letter. Accordingly, the associated TS changes are included in Enclosure 3. A change to Table 1 of Enclosure 1 of the EPU License Amendment request is also included in Enclosure 2. This table provides the description and basis for the TS change. In addition, the NSPM is providing a marked up PUSAR page to correct the error in item 1 above in Enclosure 2.
The associated TS change represents a correction to an omission made by NSPM in the EPU LAR. The basis for this change has been previously provided and is described in detail in the following docketed correspondences.
- Section 2.4.1.3 of the PUSAR(')
- NSPM response to EICB RAI Question 1 (Reference 2). Please see Item 1, Main Steam High Flow, in the table included in the response to this question.
" MNGP Calculation CA-95-075 Rev. 1, Main Steam Line High Flow Setpoint, which was provided within Enclosure-$-ofRefeR-,e2.
" '.--LMT'-13-0ý20
- 1. The PUSAR was provided as Enclosure 5 to letter L-MT-08-052 (Reference 1).
Fe-m--11 Table 1 Monticello Proposed Operating License and Technical Specification Channes TS Section Description of Change Basis for Change 3.3.1.1, RPS Instrumentation SR Revise the frequency from Revises the frequency to 3.3.1.1.6 2000 EFPH to 1000 MWD/T conform to the BWR4 Standard average core exposure Technical Specification value for this surveillance requirement.
Table 3.3.6.1-1 Revise the Allowable Value Revises the value to reflect the (AV) from : 142% to < relative change due to the Function 1.c 42"0/o change in rated steam flow at EPU. The differential pressure value across the flow sensors for the EPU AV is the same as that for CLTP.
The analytical limit for high main steamline flow isolation for EPU was raised slightly to account for error terms but was maintained well below the steam flow for the flow restrictor in each main steam line. The main steamline high fio 120.5 analytical limit is 20o which is well below the restrictor I choke flow point speci 144.9 3.22-7N lb/hr or . 0of EPU rated steam flow per line.
3.5.1 ECCS Operating Clarifies the format Editorial correction in response to NRC Review Branch comment
MARKUP OF TABLE 2.4-1 of ENCLOSURE 7 of the MONTICELLO EPU LICENSE AMENDMENT REQUEST DATED NOVEMBER 5, 2008 NEDO-33322, Revision 3 Table .4-1 Analytical ULmf mad AllowamI Values for Sepolats AYKM kIfinraflof urs kMWI)
APRiM Newmaon Flies H1g0 Scrm AL 125 NO Chloip 2
TO(%R7TP) 06MW+ 61.6 0.55W+6115 SLO(%RTP) 0.66(W.Ata W) + 61.6 0SS(W-4da W) + 61.5 Clamp (%RTP) 116 NoCbmi APIRMSRV(Rod Block) AVs,'~ ___
1W (%R71P) 0.6W + S5.6 035W + 5333 SLO (%RTP) 4A6(W-dekm W) + SSA 0355(W-dudw W) 4 553 lamnp (%RTP) lie NoChamW APRM Scudown in Su"up Mode AV9 Scani (¶%RTP) 20 No chang Rod Block (%RTP) IS No Csam Rod Block Monitor AVs See ncin 3 No Change Rod Wonh Miniamzer LPSP AV (%RTP) 10 Nocag Main Stem Lime High Flow Isolatdo W(%
L 142 42346.
,ntdOwa flow) AV -- <--
Tarbin First-Sge Pressure Scram Byp'as AL 4S.0% 40.0/
(%RTP)
Reactor Water Level - Low (SCRAM) (inches 02.5 above Indicaed zero) (AL)
Notes.
I. No credit i taue in any sOy anslysis for *te flow eferenced seepolats.
- 3. Isued to des-rmnla any dump I she rod block " setpohm.
The cycle specific reload ansaysis The RBM *lpsctpaits lisW amebed on an O(rAt U Limit Minimum Mica! Power Ratio (OLmemCPR) of 1.30.
Primary Containment Isolation Instrumentation 3.3.6.1 Table 3.3.6.1-1 (page 1 of 3)
Primary Containment Isolation Instrumentation APPLICABLE CONDITIONS MODES OR REQUIRED REFERENCED OTHER CHANNELS FROM SPECIFIED PER TRIP REQUIRED SURVEILLANCE ALLOWABLE FUNCTION CONDITIONS SYSTEM ACTION C.1 REQUIREMENTS VALUE
- 1. Main Steam Line Isolation
- a. Reactor Vessel 1,2,3 2 D SR 3.3.6.1.1 Ž -48 Inches Water Level - Low SR 3.3.6.1.2 Low SR 3.3.6.1.3 SR 3.3.6.1.5 SR 3.3.6.1.6
- b. Main Steam Line 2 E SR 3.3.6.1.2 Pressure - Low SR 3.3.6.1.4 SR 3.3.6.1.6
- c. Main Steam Line 1,2,3 2 per D SR 3.3.6.1.1 :* 4Q% rated Flow- High MSL SR 3.3.6.1.2 steam flow SR 3.3.6.1.4 SR 3.3.6.1.6
- d. Main Steam Line 1,2,3 2 per trip D SR 3.3.6.1.5 5209°F Tunnel string SR 3.3.6.1.6 Temperature - High
- 2. Primary Containment Isolation
- a. Reactor Vessel 1,2,3 2 F SR 3.3.6.1.1 > 7 inches Water Level - Low SR 3.3.6.1.2 SR 3.3.6.1.3 SR 3.3.6.1.5 SR 3.3.6.1.6
- b. Drywell Pressure - 1,2,3 2 F SR 3.3.6.1.2 <2.0 psig High SR 3.3.6.1.4 SR 3.3.6.1.6
- 3. High Pressure Coolant Injection (HPCI) System Isolation
- a. HPCI Steam Line 1,2,3 2 F SR 3.3.6.1.2
- 300,000 Flow - High SR 3.3.6.1.4 Ib/hour with SR 3.3.6.1.6
- 5.58 second time delay Monticello 3.3.6.1-5 Amendment No. *44&._.
Fit---1 Enclosure 2 to L-MT-08-036 MNGP-003, "MNGP AST - LOCA Radiological Consequence Analysis", Rev 3 This calculation has been superseded.
See L-MT-1 3-020, Item 2 for the revised results.
This calculation has been superseded.
See L-MT-1 3-020, Item 2 for the revised results.
U DESIGN CALCULATION Alion Science & Technology -
Flte-m 2-1 Enclosure 5 to L-MT-08-036 ALION-CAL-MNGP-4370-02, "MNGP EPU - CR and TSC Direct Dose," Rev 0 This calculation has been superseded.
See L-MT-1 3-020, Item 2 for the revised results.
Ft -m1 This calculation has been superseded.
See L-MT-1 3-020, Item 2 for the revised results.
ALION DESIGN CALCULATION AND ANALYSIS COVER PAGE /
ulation No: ALION-CAL-MNGP4370-02 Revision: 0 Page I of 26 Calcul on
Title:
MNGP EPU -CR & TSC Direct Dose Project No: 64-4370 TProject Name: onticello Nuclear Generating Plant Extended Power Uprate (EPU) Project Client: Nuclear M!a ement Company Document Purpose/S iry: The purpose of this calculation is to determine the direct dose co lrbution to the control room (CR) and technical , 't center (TSC) operators at the Monticello Nuclear Generatinc lant (MNGP) site following a design basis losl fcooling accident (LOCA). The analysis is performed based,,n plant operation at 102% of the Extended Power Uprate ( U) power level of 2004 MWth using the Alternative Sour Term (AST) in accordance with the guidance provided by Nuclear Regulatory Commission (NRC) in Regulato Guide 1.183 (July 2000) and as allowed by 10 CFR 50.67. All ca lated doses are shown to be below the regulato imits for each specified locations.
in/**/ .5 ,Use ofC o mnpui er Softw are a nd Err or
"ý All sot wa e se min thi p r p: r to n 'o fth° 7on Reporting requirements.
Preparer Signature: Not Reouired -____Date;___________
DESIGN VERIFICATION METHOD QA APPLICABILITY LEVEL SDesign Review Nu ear Safety Related SAlternative Calculation F]Quality iguificant
[] Qualification Testing [1 Nuclear No -Safety Related Professional Engineer Approval /required) Not Require Date_
Signature
/
Alion Science & Technology. -
Ite-m 21 Enclosure 6 to L-MT-08-036 ALION-CAL-MNGP-4370-03, "MNGP EPU - TSC Internal Dose," Rev 0 This calculation has been superseded.
See L-MT-13-020, Item 2 for the revised results.
Ite-m 21 This calculation has been superseded.
See L-MT-1 3-020, Item 2 for the revised results.
10,ON DESIGN CALCULATION
& "AND ANALYSIS COVER PAGE
[&lculat'~i<No: ALION-CAL-MNGP-4370-03 Calculation Tie: MNGP EPU - TSC Internal Dose Project No: 264-4 0 Project Name: Monticyo Nuclear Generating Plant Extended Power Uprate (EPU) Project
-pClient:Nuclear Managemet Company Document Purpose/Summary 'he purpose of this calculation is to determine the internal clou dose contribution to the technical support center (TSC) a rators at the Monticello Nuclear Generating Plant (MNG site following a design basis loss of cooling accident (LOCA). 'Vhe analysis is performed based on plant operation at 12% of the Extended Power Uprate (EPU) power level of 2004 th using the Alternative Source Term (AST) in aocordance with the guidance provided by the Nuclear Regulatory C mission (NRC) in Regulatory Guide 1.183 (J y 2000) and as allowed by 10 CFR 50.67. All calculated doses are shownt e below the regulatory limits for each s ified locations.
Pre tarerth" 3.5. ofComputer:_________________
Reporting requirements.,t SPreparer Signature: Not Reqguired Date:
DESIGN VERIFICATION METHOD QA APPLICABILITY LEVEL SDesign Review 0 Nuclear
\ fety Related iZ Alternative Calculation C1 Quality Signi ant
_ Qualification Testing I] Nuclear Non-Sa Related Professional Engineer Approval frequired Not *red Date
/eo Signature
\ ,
Form 3.4. "
Revisi Effe J Date: 2/28f07 Alion Science & Technology. -
Iltem 2 1 L-MT-09-042 Enclosure 1 Page 11 of 11 - Corrected Page NRC RAI No. 4 The Safety Analysis Report for the Monticello Constant Power Uprate, dated October 2008, on page 2-340, within Table 2.9-1, indicates the dose consequences in the Control Room and the Technical Support Center, from a design-basis loss-of-coolant accident under EPU conditions, as 3.80 rem and 0.83 rem, respectively. Verify that these results include direct radiation exposure from plant systems containing the accident source term, consistent with the assumptions in NUREG-0737, item ll.B.2. If not, demonstrate that the direct radiation dose rates for these two vital areas meet the GDC-19 dose criteria, as specified in NUREG-0737, item ll.B.2.
NSPM RESPONSE The Control Room and Technical Support Center (TSC) total calculated doses include a component due to direct shine dose from plant systems and the reactor building as required by NUREG-0737 Item ll.B.2. The shine contribution for the Control Room is 0.771 Rem of the total 3.8 Rem and the TSC is 0.0939 Rem of the total 0.92 Rem.
I(+2 mrem)
rl -te-m2-I NEDC-33322P Revision 3- Corrected Page Table 2.9-1 LOCA Radiological Consequences TEDE Dose (REM)
Receptor Location CR FEAB. LPZ T$C Calculated Dose CLTP 1 3.40 1.31 1.72 0.854 Calculated Dose EPU 2 3.80 1.46 1.99 0.92 Allowable TEDE Limit3 5 5 5 5 1+4mrem I + 2mrem 1+1 mrem H +2 mrem Table 2.9-2 FRA Radiological Consequences TEDE Dose (REM)
Receptor Location CR FAB LPZ.
Calculated Dose CLTP 1 4.29 1.61 0.31 2
Calculated Dose EPU 4.67 1.74 0.34 Allowable TEDE Limit 3 5 6.3 6.3 Table 2.9-3 CRDA Radiological Consequences TEKDE Dose (REMA)
_ _Receptor Location
__ __ __ __ I CR FAB LPZ Calculated Dose CLTP1 1.70 1.73 0.79 2
Calculated Dose EPU 1.86 1.96 0.90 Allowable TEDE Limit 3 5 6.3 6.3 Tables 2.9-1, 2.9-2 and 2.9-3 notes:
I. CLTP Power Level Assumption = 1880 MWt x 1.02 = 1918 MWt
- 2. EPU power Level Assumption = 2004 MWt x 1.02 = 2044 MWt
- 3. RG 1.183 Table 6 2-340
NEDO-33322, Revision 3 - Corrected Page Table 2.9-1 LOCA Radiological Consequences TEDE Dose (REM)
_ _ Receptor Location CR EAB LPZ TSC 1
Calculated Dose CLTP 3.40 1.31 1.72 0.854 Calculated Dose EPU2 3.80 1.46 1.99 0.92 3
Allowable TEDE Limit 5 25 25 5 I+E4 mremiI I+2Imrem +1 mrem +2mrem Table 2.9-2 FHA Radiological Consequences TEDE Dose (REM)
______________Receptor Location CR EAR LPZ 1
Calculated Dose CLTP 4.29 1.61 0.31 Calculated Dose EPU 2 4.67 1.74 0.34 3
Allowable TEDE Limit 5 6.3 6.3 Table 2.9-3 CRDA Radiological Consequences TEDE Dose (REM)
____...._________: :Receptor Location! ___________
CR EAR LPZ Calculated Dose CLTP' 1.70 1.73 0.79 Calculated Dose EPU2 1.86 1.96 0.90 Allowable TEDE Limit3 5 6.3 6.3 Tables 2.9-1, 2.9-2 and 2.9-3 notes:
- 1. CLTP Power Level Assumption = 1880 MWt x 1.02 = 1918 MWt
- 2. EPU power Level Assumption = 2004 MWt x 1.02 = 2044 MWt
- 3. RG1.183Table6 2-340
Iltem 3 Enclosure 3 to L-MT-08-036 MNGP-005, "MNGP AST - CRDA Radiological Consequence Analysis," Rev 2 This calculation has been superseded.
See L-MT-13-020, Item 3 for the revised results.
Iltem 3
,This calculation has been superseded.
jSee L-MT-1 3-020, Item 3 for the revised results.
OL 0 N DESIGN CALCULATION AND ANALYSIS COVER PAGE Calculan No: MNGP-005 Revision: 2 Page I of 6 Calculation tle: MNGP AST - CRDA Radiological Consequence Analysis Project No: 264N70 Project Name: Monti lo Nuclear Generating Plant Extended Power Uprate (EPU) Project Client: Nuclear Managem t Company Document Purpose/Summary: The purpose of this calculation is to determine the dose to e control room operator and to a person at the Exclusion Arear undary (EAB) and the Low Population Zone (LPZ) ate Monticello Nuclear Generating Plant (MNGP) site following a de in basis Control Rod Drop Accident (CRDA). Thanalysis is performed based on plant operation at 102% of the Exteed Power Uprate (EPU) power level of 2004 Wth using the Alternative Source Term (AST) in accordance with the g ance provided by the Nuclear Regulator ommission (NRC) in Regulatory Guide 1.183 (July 2000) and as allowed by 10 NR 50.67. All calculated doses are s n to be below the regulatory limits for all three specified locations.
All software used in the preparation of this calc tionmee QAP 3.5, Use of Computer Software and Error Reporting requirements.
Preparer Signature: Date: /2-DESIGN VERIFICATION METHO QA APPLICABILITY LEVEL
[ Design Review / Nuclear ety Related El Alternative Calculation El Quality Signi ant El Qualification Testing El Nuclear Non-Safe Related Professional Engineer App val (if required) 10 nut !ldeguitti
\,r,-.
ate ___________
Sigpnature Alion Science & Technology.
Item 3 I NEDC-33322P, Revision 3 Table 2.9-1 LOCA Radiological Consequences TEDE Dose (REM)
Receptor Location CR EAB LPZ TSC Calculated Dose CLTP1 3.40 1.31 1.72 0.77 Calculated Dose EPU 2 3.80 1.46 1.99 0.83 3
Allowable TEDE Limit 5 25 25 5 Table 2.9-2 FHA Radiological Consequences TEDE Dose (REM)
Receptor Location CR EAB LPZ Calculated Dose CLTP' 4.29 1.61 0.31 Calculated Dose EPO2 4.67 1.74 0.34 3
Allowable TEDE Limit 5 6.3 6.3 Table 2.9-3 CRDA Radiological Consequences TEDE Dose (REM)
Receptor Location CR EAB LPZ Calculated Dose CLTP' 1.70 1.73 0.79 Calculated Dose EPU2 47M - 00W 3
Allowable TEDE Limit 5 6.31 6.3 Tables 2.9-1, 2.9-2 and 2.9-3 notes: E 1ji ný
- 1. CLTP Power Level Assumption = 1880 MWt x 1.02= 1918 MWt
- 2. EPU power Level Assumption - 2004 MWt x 1.02 = 2044 MWt
- 3. RG 1.183 Table 6 2-340
Iltem -51 Enclosure 4 to L-MT-08-052 MNGP Extended Power Uprate Environmental Assessment This Environmental Assessment has been superseded.
See NSPM letter L-MT-1 3-020, Enclosure 4 for the revised Environmental Assessment.
FIt-em-51 ENCLOSURE 4 MNGP EXTENDED POWER UPRATE ENVIRONMENTAL ASSESSMENT NOVEMBER 2008 This Environmental Assessment has been superseded.
See NSPM letter L-MT-1 3-020, Enclosure 4 for the revised Environmental Assessment.
NORTHERN STATES POWER COMPANY, A MINNESOTA CORPORATION (NSPM)
MONTICELLO NUCLEAR GENERATING PLANT MONTICELLO, MINNESOTA RENEWED LICENSE NO. DPR-22 DOCKET NO. 50-263 1 of 69
FIt-em 51 ENCLOSURE 1 MONTICELLO NUCLEAR GENERATING PLANT NSPM Response To Environmental Branch RAIs dated December 18, 2008 The responses to these RAIs have been superseded, revised or augmented. See NSPM letter L-MT-13-020, Enclosure 4 for the revised Environmental Assessment which supersedes, revises or augments the responses to these RAIs.
Ilte-m -5 NSPM Response To Environmental Branch RAIs dated December 18, 2008 The responses to these RAts have been superseded, revised or augmented. See NSPM letter L-MT-1 3-020, Enclosure 4 for the revised Environmental Assessment which supersedes, revises or augments the responses to these RAls.
Withdrawn during December 16, 2008 conference call.
NRC Review Item (2)
Please provide additional information or clarification of the potential increase in water consumption with the uprate. The description of water use in the EA should be made clearer. Specifically, the consumptive use during current operations assuming 130 days per year of cooling tower use is 7800 acre-feet/year. With the power uprate and an increase in cooling tower use to 150 days, the estimated consumptive use is 7700 acre-feet/year, a reduction. This is counterintuitive and needs either a correction or a detailed explanation.
NSPM Response Section 6.2.2 of Enclosure 4 to Reference 1 discusses this issue. This section states:
Currently, the surface water consumption due to open cycle evaporative losses and cooling tower evaporationand drift is estimated at approximately6,800 acre-ft/year assuming 130 days of cooling tower operation, 235 days of open-cycle operation and nominal values of cooling tower flow (approximately509 cubic feet/second). Using the maximum surface water appropriationlimit of 645 cubic feet/second as the cooling tower flow value results in an estimated total consumption of 7,800-acre-ft/year.
For extended power uprate, assuming an increase in open cycle consumption of 20 percent,an increasein days of cooling tower operation to 150 days/year, and nominal values of cooling tower flow, results in an estimated consumption of 7,700 acre-ft/year. Using the maximum surface water appropriationlimit of 645 cubic feet/second as the cooling tower flow value results in an estimated total consumption of approximately8,700 acre-ft/year. Note that using the appropriationlimit for cooling tower flow is very conservative because the cooling towers are typically operatedin "Helper'mode (i.e., not all circulatingwaterflow is passed over the cooling towers).
The first paragraph quoted above discusses expected consumptive use under current licensed thermal power of 1775 MWt. This recognizes that the NPDES permit requires cooling tower operation to meet specified discharge canal temperature limits. NPDES permit limits are a maximum daily average discharge canal temperature of 95°F during the months of April through October, 850 F in November and March, and 80°F in December through February. This has historically required about 130 days of cooling tower operation per year which is expected to increase to 150 days per year with higher heat loads associated with extended power uprate. Additionally, the nominal consumptive use discussed in the first sentence of the first quoted paragraph recognizes that while the water appropriation limit is 645 cubic feet/second the circulation water system capacity is less than this value and the cooling tower capacity is normally insufficient to process all circulating Page 1 of 6
L-MT-13-020 ENCLOSURE 4 ANALYSES TO SUPPORT MAIN STEAM LINE HIGH FLOW TRIP REVISED TECHNICAL SPECIFICATION SETPOINT This enclosure contains the following documents as referenced from Item 1 in
- General Electric - Hitachi Report GE-MNGP-AEP-3263, Enclosure 2, Effect of GEH 10-CFR Part 21 Communication entitled "Error in Main Steam Line High Flow Calculational Methodology at Monticello Nuclear Generation Plant"- 4 pages
" NSPM Calculation 95-075, Revision 1 - 188 pages- NOTE: Attachment 10 to this calculation is redacted as it contains GEH proprietary information.
192 pages follow
ENCLOSURE 2 GE-MNGP-AEP-3263 Effect of GEH 10 CFR Part 21 Communication entitled "Error in Main Steam Line High Flow Calculational Methodology at Monticello Nuclear Generation Plant" Non-Proprietary Information - Class I (Public)
NON-PROPRIETARY NOTICE This is a non-proprietary version of Enclosure 1 of GE-MNGP-AEP-3263, which has the proprietary information removed. Portions of the document that have been removed are indicated by an open and closed bracket as shown here (( I].
GE-MNGP-AEP-3263 GEH Non-proprietary Information Page 2 of 4
Background
In December 13, 2012 Letter to Northern States Power Company of Minnesota [ML12338A006],
the NRC provided comments on presentations Monticello had made on their gap analysis of changes to information previously submitted in Extended Power Uprate (EPU) License Amendment Request. This is the GEH response to the Nuclear Regulatory Commission (NRC) comment on the Main Steam Line (MSL) High Flow Trip.
GEH Response GEH has evaluated the Monticello Nuclear Generating Plant (MNGP) for implications of the choked flow rate issue described most recently in the GEH 10 CFR Part 21 Communication entitled "Error in Main Steam Line High Flow Calculational Methodology," Safety Communication (SC) 12-18 Revision 2 and MFN 12-111 Revision 2, February 8, 2013. (SC 12-18 Revision 2 contains MFN 12-111 Revision 2, and both documents were issued to update affected licensees and the NRC, respectively, on the closure of the GEH Part 21 evaluation, the status of which had been previously communicated with the 60-day Interim Report Notification in SC 12-18 Revision 1 and MFN 12-111 Revision 1 on December 12, 2012). To address this issue, GEH established a new, more-accurate calculation method for MSL two-phase steam flow,
)). This updated calculation was used to evaluate the choked flow rate and the associated MSL flow-instrument pressure drop for MNGP at Current Licensed Thermal Power (CLTP) conditions and at EPU conditions.
The evaluation has determined that the Analytical Limit (AL) for the MSL Flow - High instrument trip, as calculated for CLTP and EPU conditions and communicated to GEH in Xcel Energy Design Information Transmittal (DIT) 13638-24, remains conservative with respect to MSL choked flow conditions. In fact, the Analytical Limit (( )) has considerably more margin to the choked flow condition than the GEH recommended margin, as shown in the bottom two lines of Table 1 (i.e., the current margin is greater than the revised minimum margin recommended by GEH). This determination is applicable for the rated dome pressure of 1025 psia and also for off-rated dome pressure values down to 965 psia. (Dome pressure of 965 psia has been used in the MNGP Updated Safety Analysis Report MSL Break analysis.)
Specific values determined for 965 psia and 1025 psia dome pressure, including comparison of the flow-instrument pressure drop currently used as the MSL Flow - High Analytical Limit, are provided in Table 1.
Please note that the revised calculation model changes the relationship between MSL flow and flow-instrument pressure drop, and provides ((
)), which could impact the MSL high flow setpoint and
GE-MNGP-AEP-3263 GEH Non-proprietary Information Page 3 of 4 setpoint margins. For this reason, the current values of % rated flow and MSL flow rate for the current Analytical Limit and Allowable Value no longer directly correspond to each other.
However, these current values can conservatively be used as they are, and the current documented values of the AL in % of rated flow and the AV in psid remain conservative.
The revised values of flow rate (in % of rated EPU flow) that will produce the current flow-instrument pressure drop values (in psid) are provided in Table 2 below. Note that in this table the flow rates associated with current flow-instrument pressure drop values were determined ((
))from the updated calculation.
The spurious trip margin for the MSL high-flow instrumentation should be calculated ((
))
Conclusion GEH has determined, based on results from a revised and more accurate calculation of MSL flow and flow-instrument pressure drop that the condition described in SC 12-18, Revision 1 has no impact on the function of the MSL Flow - High instrument trip at reactor dome pressure of 965 psia and above. For these conditions, the flow-instrument trip, with its current setpoints, will actuate the trip function prior to attaining choked flow in the MSL.
GE-MNGP-AEP-3263 GEH Non-proprietary Information Page 4 of 4 Table 1 - Revised Values of Choked Flow Rate Dome P~ressure 965 psia 1025 psia Operating Conditions CLTP EPU CLTP EPU Choked Flow Rate (Mlbm/hr) 2.84 2.84 3.02 3.02 Choked Flow Rate 156.3 136.2 166.3 144.9
(% Rated Flow)
Flow Instrument Pressure Drop at Choked Conditions 369.4 369.4 391.2 391.2 (psid)
Current MSL Flow - High Analytical Limit 160.63 165 160.63 165 (psid) per DIT 13638-24 GEH Recommended Choked Flow-to-AL Flow Margin ]
(psid)
Current MSL Choked Flow-to- 208.77 204.4 230.57 226.2 AL Flow Margin (psid)
Table 2 - Revised Flow Rates Corresponding to Current MNGP Setpoints Values - Rated Dome Pressure SP Current MNGP Flow- Calculated Flow Rate etit Paa r Instrument Pressure Drop (% EPU Flow) at Rated Dome (psid) Pressure Analytical Limit (AL) 165 R Allowable Value (AV) 151.95 Nominal Trip Setpoint (NTSP) 143 ]
- Obtained by linear interpolation
Document Information NSPM Calculation (Doc) No: 95-075 Revision: 01
Title:
Main Steam Line High Flow Setpoint Facility: 2 MT El P1 Unit: 01 2 Safety Class: Z SR El Aug.Q El Non SR Special Codes: El Safeguards El Proprietary Type: Calc Sub-Type:
NOTE:. Print and sign name in signature blocks, as required.
Major Revisions El N/A EC Number: 13638 El Vendor Calc.
Vendor Name or Code: Vendor Doc No:
Description of Revision: See Purpose section of calculation The following calculation and attachments have been reviewed and deemed El acceptable as a legible QA record I Prepared by: (sign) , / (print) Rhon Sanderson Date: /-/
Reviewed by:(sign) Qht,* /I(print) Mike Cray Date:,Ql io101 Type of Review: 0 Design e)rificatioY [E Tech Review El Suitability Review Method Used (For DV Only): M Review [E Alternate Calc El Test Approved by: (sign)/,/J/. t)Tl 6A),,14,j Date: /a 3 /,d Minor Revisions El N/A EC No: El Vendor CaIc:
Minor Rev. No:
Description of Change:
Pages Affected:
The following calculation and attachments have been reviewed and deemed El acceptable as a legible QA record Prepared by: (sign) / (print) Date:
Reviewed by: (sign) / (print) Date:
Type of Review: El Design Verification El Tech Review El Suitability Review Method Used (For DV Only): El Review E] Alternate Calc El Test Approved by: (sign) /(print) Dat Record Retention: Retain this form with the associated calculation for the life of the plant.
This reference table is used for data entry into the PassPort Controlled Documents Module reference tables (C012 Panel). It may NOTE: also be used as the reference section of the calculation. The input documents, output documents and other references should all be listed here. Add additional lines as needed by using the "TAB" key and filling in the appropriate information in each column.
Reference Documents (PassPort C012 Panel from C020)
Document Name Document Doc Ref Type**
- Controlled*
Doc?+ Type Number Rev INPUT OUTPUT 1 x CALC MNGP EPU Task Report: Transient Analysis T0900, EC 11250 0 X 2 DIT: High Main Steam Flow Analytical Limit and Tech Spec Limit EPU-0258, Att. 4 X 3 DIT: High Main Steam Line High Flow Setpoint EPU-0259, Aft. 5 X 4 MNGP EPU Task Report: Environmental Qualification T1004, EC 11836 0 X 5 Ashcroft Digital Test Gauge Operating Instructions X 6 X VTM Mansfield and Green Pneumatic Dead Weight Tester NX-1 7448 0 X 7 X CALC MNGP EPU Task Report: Moisture Carryover in MSL T2005, EC 11256 X 8 "General Electric Setpoint Methodology", September 1996 NEDC 31336P-A x 9 "Setpoint Calculation Guidelines for the Monticello Nuclear GE-NE-901-021-Generating Plant", DRF A-00-01 932-1 0492 10 X Engineering Standards Manual ESM-03.02 "Design Requirements, ESM-03.02 12 X X PROC Practices, &Topics (Instrumentation & Controls)" EM0212 11 ANSI/ISA Standard ISA-$67.04 - Part I "Setpoints for Nuclear ISA-$67.04 Safety-Related Instrumentation" 1994 12 ISA Recommended Practice RP67.04 - Part II "Methodologies for the Determination of Setpoints for Nuclear Safety-Related RP67.04 Instrumentation" 1994 13 EPRI report TR-1 03335, "Guidelines for Instrument Calibration TR-1 03335 X Extension / Reduction Programs" 3/94 14 Monticello Plant Component Master List (CML) Database X X 15 Barton product bulletin 288A/289A-7, "Differential Pressure X Indicating Switches (Attachment 6 of this calculation) 16 X PROC ESM-03.02-APP-I, GE Methodology Instrumentation and ESM-03.02-APP-I 4. X Record Retention: Retain this form with the associated calculation for the life of the plant.
Controls 17 X DRAW NX-7829-67-1, Rack (25-26) C-126, Rev. B NX-7829-67-1 76 X 18 X SPEC, Purchase Spec 21A1058, Controlled Specification Data Sheet MPS-0165 4 X Steam Flow Restrictor 19 X CALC "Calculation to Determine Discharge Coefficient Changes for the 97-216 0 X Main Steam Line Flow Restrictors" 20 X CALC Determine Instrument Service Conditions for Input into Setpoint 95-027 1 X Calculations 21 X PROC "GE Methodology Instrumentation and Controls" ESM-03.02-APP-III 5 X 22 MEDO-10544, April 1972, "Modified Steam Line Flow Limiting X Venturi Test Results" (Attachment 7 of this calculation) 23 Telephone conversation record from Bechtel Power Setpoint x Group to ITT Barton (Attachment 8 of this calculation) 24 X CALC "Environmental Qualification of Barton Pressure Switches Models98-011 0 X 278, 288, 288Aand 289A 25 Generic Letter 91-04, Changes in Technical Specification 91-04 X Surveillance Intervals to Accommodate a 24-Month Fuel Cycle 26 X PROC Operations Daily Log - Part J OutPlant 107 X 27 x PROC Maint Steam Line High Flow Group I Instrument Test 0051 31 x 28 GE Hitachi DRF Section 0000-0156-8601, dated January 17, 2013. (Attachment 10 of this calculation) 29 GEH 10 CFR Part 21 Communication, "Error in Main Steam Line High Flow Calculational Methodology," SC 12-189, R1, issued December 12, 2012.
- Controlled Doc marked with an "X"means the reference can be entered on the C01 2 panel in black. Unmarked lines will be yellow. Ifmarked with an "X", also list the Doc Type, e.g., CALC, DRAW, VTM, PROC; etc.
- Mark with an "X"ifthe calculation provides inputs and/or outputs or both. Ifnot, leave blank. (Corresponds to PassPort "Ref Type" codes: Inputs I Both =
"ICALC", Outputs = "OCALC", Other Unknown = blank)
Other PassPort Data Record Retention: Retain this form with the associated calculation for the life of the plant.
Paae 4 of 5 QF-0549 (FP-E-CAL-01) Rev. 7 Pace 4 of 5 XceiEnergy Calculation Signature Sheet Associated System (PassPort CO1l, first three columns) OR Equipment References (PassPort C025, all five columns):
Facility Unit System Equipment Type Equipment Number MT 1 MST INDREC DPIS-2-116 A, B, C, D MT 1 MST INDREC DPIS-2-117 A, B, C, D MT 1 MST INDREC DPIS-2-118 A, B, C, D MT 1 MST INDREC DPIS-2-119 A, B, C, D Superseded Calculations (PassPort C019):
Facility Calc Document Number Title MT CA-95-075 Rev. 0 Maint Steam Line High Flow Setpoint Drift Analysis Description Codes - Optional (PassPort C018):
Code Description (optional) Code Description (optional)
Notes (Nts) - Optional (PassPort X293 from C020):
Topic Notes Text
- Calc Introduction I Copy directly from the calculation Intro Paragraph or -I See write-up below El (Specify)
Record Retention: Retain this form with the associated calculation for the life of the plant.
QF-0549 (FP-E-CAL-01), Rev. 7 Page 5 of 5 XceIEnergy- Calculation Signature Sheet Monticello Specific Information N YES El N/A Topic Code(s) (See MT Form 3805): RATE El YES El N/A Structural Code(s) (See MT Form 3805):
Does the Calculation:
El YES [ No Require Fire Protection Review? (Using MT Form 3765, "Fire Protection Program Checklist", determine if a Fire Protection Review is required.) If YES, document the engineering review in the EC. If NO, then attach completed MT Form 3765 to the associated EC.
El YES [ No Affect piping or supports? (IfYes, Attach MT Form 3544.)
El YES Z No Affect IST Program Valve or Pump Reference Values, and/or Acceptance Criteria? (IfYes, inform IST Coordinator and provide copy of calculation.)
Record Retention: Retain this form with the associated calculation for the life of the plant.
QF-0527 (FP-E-MOD-07) Rev. 4 Page 1 of 1 XcelEnergy- Design Review Checklist EC Nube orDcmntNme ITilI eiinNmbr A9-7.Mi EC Number or Document Number / Title / Revision Number: CA-95-075, Main Steam Line High Flow Setpoint, Rev. 1 Verifier's Name: Mike Cray Discipline: Design Engineer, Electrical DESIGN REVIEW CONSIDERATIONS: Yes No N/A
- 1. Were the inputs correctly selected and incorporated into design? Li
- a El
- 2. Are assumptions necessary to perform the design activity adequately described and reasonable? Where necessary, are the assumptions identified for subsequent re-verifications when the detailed design activities are completed?
19 EI E]
- 3. Are the appropriate quality and quality assurance requirements specified?
- 4. Are the applicable codes, standards, and regulatory requirements including issue E]
and addends properly identified and are their requirements for design met? [] Li
- 5. Have applicable construction and operating experience been considered? [] Li LI
- 6. Have the design interface requirements been satisfied? El Li
[] Li Li
- 7. Was an appropriate design method used? El
[] Li
- 8. Is the output reasonable compared to inputs?
- 9. Are the specified parts, equipment and processes suitable for the required application?
- 10. Are the specified materials compatible with each other and the design environmental conditions to which the material will be exposed?
- 11. Have adequate maintenance features and requirements been specified? IS. EL Li
- 12. Are accessibility and other design provisions adequate for performance of needed Li maintenance and repair? [P L
- 13. Has adequate accessibility been provided to perform the in-service inspection expected to be required during the plant life? 14 1:
- 14. Has the design properly considered radiation exposure to the public and plant Li personnel?
- 15. Are the acceptance criteria incorporated in the design documents sufficient to allow Li Li:
verification that design requirements have been'satisfactorily accomplished?
- 16. Have adequate pre-operational, subsequent periodic test and inspection requirements been appropriately specified, including acceptance criteria?
- 17. Are adequate handling, storage, cleaning, and shipping requirements specified? E] Li
- 18. Are adequate identification requirements specified? Li Li
- 19. Are requirements for record preparation, review, approval, and retention adequately El Li specified?
- 20. Have Design and Operational Margi ns been considered and documented? N 0 0 COMMENTS: None '% Attached (Use Form QF-0528) EL In.EC Topic Notes Form retained in accordance with record retention schedule identified in FP-G-RM-01.
QF-0528 (FP-E-MOD-07) Rev. 1 Sheet I of DOCUMENT NUMBER/ TITLE: CA-95-075, Main Steam Line High Flow Setpoint REVISION: 1 DATE:
ITEM REVIEWER'S COMMENTS PREPARER'S REVIEWER'S
- I RESOLUTION DISPOSITION I 4ect,ýt4 c.-
.) I- 6 NYAI 4
- h. 'tV-kc k 11~k eolc. c4 e6
~ V
.,L (Vca Reviewer: Mike Cray ib Date:L, .I Preparer: Rhon Sanderson Date:
ortýu4c-,ý-
Page 1 of I
CA-95-075, Rev. 1 TABLE OF CONTENTS Item Description Pages QF-0549 Calculation Signature Sheet 5 QF-0527 Design Review Checklist 1 QF-0528 Design Review Comment Form 1.
TOC Table of Contents 1 Calculation Body 17 Attachment . Setpoint Relationships 1 Drift Analysis 7 Drift Analysis Spreadsheets 123 DIT EPU-0258 2 DIT EPU-0259 2 BARTON product bulletin 288A/289A-7, "Differential Pressure Indicating Switches 5 NEDO-10544, April 1972, Modified Steam Line Flow Limiting Venturi Test Results 8 Telephone conversationrecord between Bechtel Power Setpoint Group to ITT Barton 1 Signature Sheet, Sargent & Lundy vendor doc. no. 11972-049 7 0 GE Hitaci DRF Section 0000-0156-8601, dated January 17, 2013 5 1 Summary of Changes to Main Steam Line High Flow Allowable Value... 2 Total 188 Page 1 of 1
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 IPage 1 of 17
- 1. PURPOSE The Main Steam Line high flow trip portion of the reactor isolation system detects and isolates breaks in the large steam lines outside the reactor containment. The Main Steam Line Differential Pressure Switches provide the high steam flow MSIV signal.
The purpose of this calculation is to determine acceptable instrument settings for the main steam lines high flow instruments DPIS-2-116 to DPIS-2-119 A, B, C, & D. Instrument settings include the Nominal Trip Setpoint, the Allowable Value and ALT /AFT values. Calculation outputs will be used to verify the adequacy of current setpoints. Revision 1 of this calculation takes into consideration the effects of extended power uprate (EPU) and the new Analytical Limit. This calculation was performed with a goal of retaining the current setpoint value of 143 psid (Reference 10.7). This is considered acceptable because the current setpoint remains conservative under EPU conditions.
Revision 1 of this calculation also incorporatesnew main steam line flow element choked flow and differential pressure information provided in General Electric DRF 0156-8601 (Input 4.9).
This DRFis a Monticello plant-specific follow up to a GE Part21 communication (Reference 10.19). An improved modelling methodology was used by GE to revise the previously assumed values for choked flow and the relationshipbetween break flow and the correspondingflow element differential pressure.
Revision I of this calculation was originallypreparedand reviewed by Sargent & Lundy (S&L vendor document no. 11972-049). The original QF-0549 calculationsignaturesheet for the S&L preparedand Monticello site reviewed and approved revision I of this calculationwill be included as Attachment 09. As the originalrevision 1 was not issued, it will be further changed to reflect the GE information noted above but this new version will still be considered and ultimately issued as revision 1.
The changes per the GE DRF to this calculationdo not result in a change to the previously submitted Analytical Limit, Allowable Value, or Nominal Setpoint, which were and are all defined as a differential pressure across the flow element(s). The As-Left and As-Found tolerances are being increasedslightly to bring them in line with practical/&C calibration capabilities. These increasedsetting tolerance values leave considerablemargin with respect to protection of the defined Analytical Limit andAllowable Value differential pressures. The licensing (Tech Specs) Allowable Value will be re-calculatedas this value was expressed as a percent of rated (100% EPU power)steam flow. Per GE the retention of the previously evaluated Analytical Limit andAllowable Value expressed as a differential pressure (in units of psid) ensures conservative margin for operation of the main steam line high flow trip instruments vs. the differentialpressure modelled for break (choked) flow.
Changes to this calculation body subseguent to the 2009 approval are identified by italic, underlined text.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision i Page 2 of 17
- 2. METHODOLOGY This calculation is performed using the GE Setpoint Methodology as a guide as described in Appendix I to Engineering Standards Manual Section ESM-03.02, Revision 4, Design Requirements, Practices, &Topics (Instrumentation and Controls) (Reference 10.9). This methodology utilizes statistical estimates of the various instrument errors to achieve conservative, but reasonable, predictions of instrument channel uncertainties. The objective of the statistical approach to setpoint calculations is to achieve a workable compromise between the need to ensure instrument trips when appropriate, and the need to avoid spurious trips -that may unnecessarily challenge safety systems or disrupt plant operation.
The determination of the differential pressure switch drift value used in this calculation is performed in accordance with ESM-03.02-APP-III (Reference 10.14).
- 3. ACCEPTANCE CRITERIA The setpoint and instrument settings should be such that the Analytical Limit will not be exceeded when all applicable instrumentation uncertainties are considered. The existing setpoints and As-found/As-left ranges will be verified to provide sufficient margin -using the GE methodology as a guide. A setpoint value will be established with a 95%/95% tolerance interval as a criteria of uncertainties (Reference 10.9). That is, there is a 95% probability that the constructed limits contain 95% of the population of interest for an 18-month +25%
calibration interval (Reference 10.18) for the pressure switches (although these devices are calibrated every 3 months). Ifthe existing setpoint and ranges do not provide sufficient margin, new setpoints or ranges will be specified by this calculation.
- 4. INPUTS 4.1 MNGP EPU Task Report T0900: Transient Analysis EC11830. GE-NE-0000-0062-2932 OPL-3, Transient Protection Parameters Verification for Reload Licensing Analysis.
Cycle 24 Value EPU Value Rated Flow 7.259 10' lb/hr 8.335 10' lb/hr 4.2 DIT EPU-0258 EPU Value % EPU flow I Proposed Tech Spec Limit (AV)(AV 1151.95 psid 5.5Did 1123.64%
2.4 IrIoe Tc e Lii
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 1 Page 3 of 17 4.3 DIT EPU-0259 1 140% existing flow 1147.7 psid I 4.4 MNGP EPU Task Report T1004: Environmental Qualification EC11836, Rev. 1. March 2008. This Input demonstrates environmental conditions used in the evaluation of Reference 10.13 will not change due to EPU. This reference provides the environmental conditions for the instruments in this calculation.
4.5 Monticello Component Master List (CML). The CML contains information regarding the pressure switches and calibration tools listed in this calculation.
FXPI-9021 Calibration Device Description Ashcroft 2089 Mansfield and Green TQ-50 I
XPS-95171 4.6 NX-63626, Ashcroft DigitaliTest Gauge Operating Instructions
-Calibration Device Range Accuracy XPI-9021 (Ashcroft 2089) 0-500 psig 0.05% Full Scale 4.7 NX-17448, Mansfield and Green Pneumatic Dead Weight Tester.
Calibration Device Range Accuracy XPS-95171 (Mansfield and Green TQ-50) 100-5000 psig 0.025% Reading 4.8 MNGP EPU Task Report T2005, Moisture Carryover in MSL (EC1 1845). This Input evaluates the effect of increased moisture carryover on the main steam flow instrumentation.
4.9 GE HitachiDRF Section 0000-0156-8601, dated January 17, 2013. This document is included as Attachment 10.
- 5. ASSUMPTIONS Validated Assumptions 5.1 M&TE reference accuracy were assumed to be 3 sigma values unless otherwise noted.
5.2 No seismic data is available for the Barton switches. Per Section 6.2.1.2, the ZPA of the C-1 26 the rack is 0.41g. Normal vibration effects are considered as part of the analyzed drift. Per Section 6.1.1, seismic events are not considered as a service condition for the DPIS devices.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint -Revision 1 Page 4 of 17
- 6. ANALYSIS 6.1 Instrument Channel Arrangement 6.1.1 Loop Information:
DPIS-2-116 to DPIS-2-1 19 A, B, C & D are used during a Main Steam Line Break to close the MSIVs due to high steam flow. The flow in each of four steam lines is monitored by 4 DPIS switches across each of the flow elements. In the event of a Main Steam Line Break, the element restricts the flow to 200% of the original rated mass flow or less. This rate is the design safety limit. A one out of two twice high flow signal in any one steam line will result in isolating all four Main Steam Lines.
These instruments are required to function immediately upon a Main Steam Line Break and are not required to maintain setpoint accuracy during long term post accident conditions. As such, long term harsh environment effects are not applicable in this calculation.
The Barton Model 278 DPIS devices are Mercury type switches. As such, seismic events have a significant impact on the performance of the devices.: Per Reference 10.13, seismic events are not considered as a service condition for the DPIS devices. As such, seismic events are not applicable in this calculation.
6.1.2 Loop Diagram:
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 5 of 17 6.2 Instrument Definition and Determination of Device Error Terms 6.2.1 Device 1:
6.2.1.1 Instrument Definition:
Component ID: DPIS-2-116 to 119 A, B, C, D Reference I Input Location Reactor Building 935' East C-126 10.7 Manufacturer: Barton 10.7 Model Number: 278 10.7 Range: 200 psid 10.7 Input Signal: Main Steam Line Process 10.7 Differential Pressure Current Setpoint: 143 psid (increasing) 10.7 Output Range: N/A (i.e. contact opens/closes) 6.2.1.2 Environmental Process and Physical Interfaces:
Calibration Conditions (Environmental): Reference I Input Temperature: 65 to 90'F 10.13, 4.4 Radiation: Negligible 10.13, 4.4 Pressure: Normal atmospheric 10.13, 4.4 Humidity: 20 to 90% 10.13, 4.4 Calibration Surveillance Interval: 3 mos +/- 25%
Normal Plant Conditions (Environmental): Reference I Input Temperature: 60 to 104'F 10.13,4.4 Radiation: lNegligible 10.13, 4.4 Pressure: Normal atmospheric 10.13; 4.4 Humidity: 20 to 100% 10.13, 4.4 Trip Conditions (Environmental): Reference I Input Temperature: 104 to 173°F 10.13, 4.4 Radiation: Negligible 10.13, 4.4 Pressure: 15.3 psia 10.13, 4.4 Humidity: 100% 10.13, 4.4 Seismic Conditions: Reference OBE: (Instrument Rack C-126) 0.41g 5.2, 10.13 Main Steam Line Process Conditions: I Reference Test Pressure 1200 psi 10.10
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 6 of 17 6.2.1.3 Device Accuracy (AiN AiT &Aip):
Term Value Sigma Reference VA: + 0.4 psid Note 1 2 10.8 ATE: 0 Note 2 N/A 10.8 OPE: 0 Note 3 N/A Section 6.2.1.2, 10.8 SPE: +/- 0.6 psid (bias) Note 4 2 10.16 SE: 0 N/A Section 6.1.1 RE: 0 N/A Section 6.2.1.2 HE: 0 Note 5 N/A 10.8 PSE: N/A Note 6 N/A N/A REE: N/A Note 6 N/A N/A Note 1: Vendor Accuracy (VA) is based on switch repeatability error equal to +
0.2% of Full Scale.
(+/- 0.002) * (200 psid) = + 0.4 psid Note 2: The maximum operating temperature of the switch is 200 OF. Vendor does not provide temperature effect values. Per Section 6.2.1.2, the maximum environmental temperature of 173 OF is bounded by the operating range of the device. Additionally, the vendor states that the devices contain a temperature compensator, which automatically protect the unit from zero and calibration drift when the instrument is subjected to a change in ambient temperature. Therefore, temperature effects are considered to be included in the vendor accuracy term.
Note 3: The switch has been selected to operate within the Main Steam Line maximum pressure of 1200 psi as specified per Section 6.2.1.2. Therefore, Overpressure Effects are not applicable.
Note 4: Per Reference 10.16, the SPE for a Barton Model 288A is 0.25 % FS per 1000 psi. Per Calculation CA-98-011 (Reference 10.17) the only significant difference between Model 278 and 288A is the use of a mercury switch vs. a snapping action switch. As such, the static pressure effect for a Barton Model 288A is applicable to the MSL High Flow DPIS devices as well. Per Section 6.2.1.2, the maximum line pressure is 1200 psi.
Effects of static pressure, not accounted for during calibration, are considered bias values. It is not known whether effects of static pressure will impact the DPIS devices in the positive or the negative direction. As such, SPE is considered a (+/-)
bias value and will be applied to both sides of the process outside of the SRSS.
[(+/- 0.0025) * (1200 psi /1000 psid)] = +/- 0.3 % FS
+/- 0.3 % FS
- 200 psid = +/- 0.6 psid (bias)
Note 5: Per Section 6.2.1.2, the maximum environmental humidity is 100%. Per Reference 10.8, switch model 278 is housed inside of a Weather-Proof casing.
Environmental humidity has no effect on the devices.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow.Setpoint Revision I Page 7 of 17 Note 6: The switches are mechanical devices and therefore power supply and EMI
/RFI effects are not applicable in this calculation.
Based on environmental conditions (Section 6.2.1.3 Note 2), the accuracy under Normal Conditions (AiN) is the same as Accuracy Under Trip Conditions (Aim).
Accuracy under Long Term Post Accident Conditions (Alp) is not required.
Ai = SRSS of random terms + bias terms This loop consists ofione device, therefore:
AL = AiN = AiT = +/-0.4 +/-0.6 bias (2 sigma) 6.2.1.4 Analyzed Device Drift (AD)
Per-Attachments 2 and 3, the 3.75-month (3 months + 25%) predicted drift uncertainty for the Main Steam Line High Flow DPIS devices is 2.00 psid.
Term - Value Sigma ReferenceI AD 2.0 psid 2 Attachments 2 and 3 This, loop consists of. one device, therefore:
DL = AD = + 2.0 psid Note that the drift data used covers a period up through year 2008. This calculationrev. 1 was approved for issue in early 2009. The additionalchanges made (see Purpose section) do not require an updated drift analysis to justify. No changes are made to the Analytical -
Limit orAllowable Value (expressed as differential pressures)vs. the document approved in 2009. Settihg tolerances are increasedsliqhtly but will remain conservative with respect to the Analytical Limit and Allowable Value with margin.
6.2.1.5 As Left Tolerances (ALT)
The suggested limit on the magnitude of the ALT calculated per Section 5.2.5 of Reference 10.9 is given as:
(c) 2 + (Cs.)
2 ALT = (VA2 +
ALT = 2V(0.4/2) 2 +(0.25/3)2 + (0.125/3)2 = 0.44psid (Calibration error terms are calculated in Section 6.2.1.6)
The existing As-Left Tolerance specified on the calibration worksheet is +/-4.5 psid..
This tolerance value is unacceptable because it is considered excessive and will force selection of As-Found tolerances that could "mask" instrument performance degradation. The calculated ALT value of +/- 0.44 psid is also considered,
MONTICELLO NUCLEAR GENERA TING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 1Page 8 of 17 unacceptable because previous instrument performance suggests that this value is not routinely achievable and therefore impractical.
Therefore, it is suggested that the ALT be revised to +/- 1.5 psicq. This value will prevent "masking" instrument performance degradation and is routinely achievable per Attachment 2.
6.2.1.6 Device Calibration Error (C)
Value Sigma Reference Calibration Tool Error Cj: 0.25 psi 3 4.6, Note 1 Tool Calibration Error CiSTD: 0.125 psi 3 4.7, Note 2 As Left Tolerance ALT: 1.5 psi 2 6.2.1.5 Note 1: Per Input 4.5, the differential pressure switches are calibrated with XPI-9021 (Ashcroft 2089). From Input 4.6, the vendor accuracy of the Ashcroft 2089 is 0.05% of full scale. Therefore, the XPI-9021 has an accuracy of 0.25 psi at 500 psi.
Calibration Device Range Accuracy Reference XPI-9021 (Ashcroft 2089) 0-500 psig 0.05% Full Scale 4.6 Note 2: Per Input 4.5, the Ashcroft 2089 is calibrated using the XPS-95171 dead weight tester. From Input 4.7, the vendor accuracy of the Mansfield and Green dead weight tester is 0.025% of output pressure. Therefore, the XPS-95171 has an accuracy of 0.125 psi at 500 psi.
Calibration Device Range Accuracy Reference XPS-95171 (Mansfield and 100-5000 psig 0.025% Reading 4.7 Green Deadweight tester)
Since calibration term values are controlled by 100% testing they are assumed to represent 3 sigma values. Individual calibration error terms are combined using the SRSS method and normalized to a 2 sigma confidence level:
CL Device 1Calibration Error 2
2 CL =- +CSTD2+/---ALT CL =2 (0.25/3)2 +(0.125/3)2 +(1.5/2)2 CL =1.52psid CL = 1.52 psid
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Page 9 of 17 6.3 Determination of Primary Element Accuracy (PEA) and Process Measurement Accuracy (PMA)
PEA: There is a Primary Element Accuracy value associated with the steam flow restrictor (flow element). Per the purchase specification, Reference 10.11, the accuracy of the steam flow restrictors is to be within +/- 2% of original rated flow. Per Reference 10.1, the 2% error is valid at 140% of original rated flow. The existing setpoint of 143 psid is within this flow rate. Therefore, the 2% error is taken as the PEA value for this calculation. Per Reference 10.5, since the effect of the PEA value cannot be predicted at a particular future instant, it is considered a random value; and is thus eligible for SRSS combination. Therefore:
PEA = + 2% of flow (random term).
PMA: Per Reference 10.1, Section 3.13.5, the actual differential pressure signal from the flow element is proportional to the specific volume of the steam. At pressures higher than the design pressure, process measurement accuracy (PMA) error exists.
Per Reference 10.1, Section 3.13.5, a PMA allowance of 2% rated flow is utilized for determining the Main Steam Line High Flow Setpoint. Although Reference 10.1 does not specify whether or not this effect should be applied as a random or bias value, the PMA causes a known effect on the instrument loop and should be applied as a bias term. For simplicity purposes, the PMA value is considered a (+/-) bias value and will be applied to both sides of the process outside of the SRSS. Errors due to pressures lower than the design pressure will create an early (conservative) trip and are not evaluated in this calculation. Therefore:
PMA = +/- 2% of flow (bias term).
The values of PEA and PMA specified above are given in units of flow. In order to combine these effects with other loop uncertainty values, PEA and PMA must be converted to units of differential pressure at the flow rate of interest. This calculation uses the existing trip setpoint flow rate as the flow rate of interest. Converting from DP to Flow is done using the general Flow / DP relationship:
Flow = K * (DP) 112 or DP = (Flow/ K)2 Per Input 4.3:
140% of existing flow = 147.7 psid Per Input 4.1:
Rated flow 7.259 *106 lb/hr existing Rated flow 8.335 *106 lb/hr after EPU Solving for K using the existing flow rate of 7.259*106 lb/hr:
(1.40)*7.259*106= K * (147.7)1/2 K = ((1.40)*7.259*106) / ((147.7)1/2) = 836208 This is the collective K value for all four steam lines. To get the K value for an individual steam venturi, the value is divided by four.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision-1 I ,Page 10 of 17_
Individual K value = 836208 /4 = 209052 Using the above equation to determine the flow rate at 143 psid (existing setpoint):
Flow 1 4 3 psid = 209052 * (143.)1f2 Flow @143 psid = 2.4999
- 10 lb/hr.
Therefore, a 2% flow error (PEA and.PMA),is calculated as follows:
Flow @2% error = 1.02 * (2.4999
- 10 6 lb/hr.)
Flow @2% error.= 2.5499
- 106 lb/hr.
Converting to differential pressure:
DP@2% error = (2.5499
- 106 lb/hr. / 209052)2 DP@2oo error = 148.78 psid 2%.Error= (DP at 2% error- DP at setpoint) 2% Error= 148.78- 143 2% Error= 5.78 psid The improved GE modelling methodology for 2-phase break flow through the flow elements shows a different relationshipbetween flow element differential pressure.and mass flow than assumed in defining the PMA error. Reviewing Table I of Input 4.9 shows that with respect to protection of the true analyticallimit being protected, i.e. the calculated dp at choke flow conditions less recommended margin, an additionalmargin of 139 psid exists. In other words, the Analytical Limit of 165 psid (Section 6.5.1) chosen to be the fimitinq value for calculating instrument settings in this document is conservative by a margin of 139 psid. Due to this large margin, instrument errors that impact evaluation of spurious trip avoidance and LER avoidancewill continue to be determined based on theoreticalflow element performance assuming dry steam.
6.4 Determination of Other Error Terms Term Value Operator Reading Error (ORE) N/A Insulation Resistance (IRE), N/A Other 2,5 psid (random term)
The conversion from DP to steam flow has been derived Using test -data from NEDO - 10544 (Reference 10.15). Per Reference 10.15, the flow limiters have an effective discharge coefficient of 0.97 compared to a predicted value of 1.0. This is equivalent to an error in differential pressure of 2.5 psid. This unpredicted variance of - 0.03 has an additional effect on the accuracy of the flow element (PEA) determined in Section 6.3.
Per Reference 10.12, the change is flow coefficient for EPU conditions is negligible.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 11 of 17 Since the Coefficient of Discharge is directly related to the accuracy of the flow element, this effect is considered a component of PEA and thus a random value; eligible for SRSS combination.
6.5 Calculation of Allowable Value and Operating Setpoint 6.5.1 Allowable Value (AV):
Per Reference 10.2, the original Analytical Limit (AL) is 140% of original rated flow, which was considered to correspond to 160.63 psid across the flow elements. This value was chosen by GE to provide a margin above the originaloperationallimit.
GE DRF 0156-8601 (Input 4.9) documents the results of improved modelling of the actual flow element differential Dressurevs. flow considerinawet steam conditions.
Per Table 2 of this DRF, an Analytical Limit of 160.63 psid would correspond to a lessor flow value, roughly 120 %. As the GE DRF guidance iustifies the conservatism of the existing differential pressureinstrument settings, the Analytical Limit differential Dressure will be selected at 165 Dsid. Table I of the DRF demonstrates that an Analytical Limit of 165 osid has more than the recommended margin to the differentialpressure correspondingto choked flow under break conditions.
An Analytical Limit of 165 psid is an acceptable value as it is low enough to trip during a break of any main steam line. The AL is well below the Design Safety Limit of 200% of original rated flow and the choke flow of the venturis. It is also high enough above the operational limit to avoid spurious trips due to transients and valve testing. Per Table I of input 4.9, an additional 139 psid of margin exists above the chosen Analytical Limit of 165 psid with respect to ensuring an instrument trip at choked flow conditions.
This value is used along with the following terms to calculate the Allowable Value.
Term Value Sigma Reference AiT +/- 0.4 (random) 2 'Section 6.2.1.3 AiT +/- 0.6 (bias) N/A Section 6.2.1.3 CL +/- 1.52 *2 Section 6.2.1.6 PEA +/- 5.78 (random) 2 Section 6.3 PMA +/- 5.78 (bias) N/A Section 6.3 Other +/- 2.5 (random) 2 Section 6.4
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 12 of 17 AV:* AL_ 1.6 4 5J4(A 2 +/-C2 + PEA 2 ++/-OTHER RANDOM) +biastermns AV: 165 (.65)i0.4 2 +1.522 5.782 + 2.52 )- 5.78-o0.6 AV
- 165-5.34-5.78-0.6 AV *153.28 The proposed Tech Spec Limit of 151.95 is conservative and will be used as the Allowable Value. This results in an extra margin of 1.33 psidto be included in the determination of NTSPi.
Therefore, AV = 151.95 psid Per Table 2 of Input 4.9, the corresponding value of flow would be interpolatedas 116.9% EPU flow 6.5.2 Nominal Trip Setpoint (NTSP):
Per Reference 10.5 and 10.9, for processes approaching a setpoint from a single side of interest, a reduction factor of (1.645 /2) may be applied for random terms.
NTSP1 -AL 1645>AT ++/-C2+ D 2 + PEA2 + OTHER 2 +.bias terms+ 'margin NTSP 1 =165- (1.645O.42 +1.522 + 2.02 +5.782 +2.52 -5.78-0.6-1.331, NTSP1 = 151.7 6.5.3 Licensee Event Report (LER) Avoidance Evaluation:
The purpose of the LER Avoidance Evaluation is to ensure that there is sufficient margin provided between the AV and the NTSP to reasonably avoid violation of the AV. For a single instrument channel a Z value of greater than 1.29 provides sufficient margin between the NTSP and the AV. Although this is a multi channel loop, a Z of 1.29 will be used for conservatism. Therefore, NTSP 2 is calculated to provide a lower bound for the NTSP based on LER avoidance criteria.
Sigma(LER) (FA~2 ~ +D )
)+bias Sigma(LER) = F042 +1.522 +2.02) +0.6 Sigma(LER) 1.87
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 13 of 17 NTSP 2 = AV - Z x Sigma(LER)
NTSP 2 = 151.95 - (1.29 x 1.87)
NTSP 2 = 149.5 Therefore, an NTSP < 149.5 psid will result in a Z greater than 1.29 and provide sufficient margin between the NTSP and the AV.
6.5.4 Selection of Operating Setpoint:
NTSP < Controlling NTSP- ALT NTSP < NTSP, - ALT NTSP *_ 149.5 -1.5 NTSP
- 148.0 The current setpoint of 143 psid (Reference 10.7) is conservative and is considered acceptable.
6.5.5 Leave Alone Zone:
Leave Alone Zones/Tolerances are not used at the MNGP per Reference 10.9.
6.5.6 Establishing As-Found Tolerance (AFT):
An As-Found Tolerance is calculated to provide suggested limits for use during the surveillance testing:
2 AFT= /ALT 2 +AD AFT = /1.52 + 2.02 AFT = 2.5 In order to better bound expected instrument performance as indicated by the data in Attachment 3, the calculated As-Found tolerance will be increased by 0.5 psid, to 3.0 psid. This value remains tight enough to serve as a flag for degrading instrument performance (excessive drift).
AFT = +/- 3.0 psid
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 14 of 17 6.5.7 Required Limits Evaluation:
The purpose of a Required Limits Evaluation is to ensure that the combination of errors present during calibration of each device in the channel is accounted for while allowing for the possibility that the devices may both be recalibrated. Since this loop contains only one device, an evaluation is not required.
6.5.8 Spurious Trip Avoidance Evaluation:
The STA is evaluated against the edge of the As-Left Tolerance band for conservatism. Refer to Reference 10.1 for more detail. Per Sec ion 6.5.4, the operating setpoint is 143 psid. Per Section 6.2.1.5, the ALT is';sid. Therefore,],eq (NTSP -ALT) = 143psid - 1.5 psidr e, (NTSP - ALT) = 141.5 psid Sigma(STA) jA,~% 2 +CL 2
+ DL 2 + PEA2 + OTHERRANDOM 2 + bias
=(i1J0.42 +1.522 + 2.002 +53782 +2.2)s7+/-6
'im(TA Sigma(STA) = 9.78 Per Section 3.13.3 of Reference 10.1, the existing operational limit is considered to be 127 % rated flow based on operating experience. The same operational limit will be used for EPU during Main Steam valve testing. The valve testing occurs at reduced power and therefore the existing operational limit of 121.54 psig is acceptable.
IAdjzusted NTSP -Operational Limitl.
SlA Sigma(STA)
ZsA = 1141.5 -121.541 9.78 ZsA = 2.0 Therefore, the adjusted NTSP of 141.5 results in a ZsTAgreater than 1.65 and provides assurance that no spurious trips will occur.
6.5.9 Elevation I Density Correction:
An elevation /line correction is not required for the DPIS switches. Ifa head pressure or process temperature does exist, a pressure or density change will be exerted on both sides of the switch equally and will have no noticeable effect on
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 15 of 17 differential pressure detected by the switch. As such, no significant error is introduced due to elevation or density changes.
Reference 10.15 indicates that there may be a zero offset possibly caused by a water leg between the steamline tap and the condensing chamber. This offset creates an indicated differential pressure larger than actual differential pressure.
For increasing setpoints, this effect is conservative because it results in an early trip.
Task Report T2005 (Input 4.8) assessed the effect of increased moisture carryover on the main steam flow instrumentation at EPU conditions. The increase in measured pressure drop with moisture increase was found to have an insignificant influence on the main steam flow instrumentation.
6.6 Channel Error Calculation Channel error calculation is not required to be determined. Instrument operation is required immediately upon main steam line break. Long term post accident evaluation is not needed.
- 7. CONCLUSIONS The results of the calculations are as follows:
Term Value (psid)
AiN +/- 0.4 (random) +/- 0.6 (bias)
AIT +/- 0.4 (random) +/- 0.6 (bias)
AD +/- 2.0 CL +/- 1.52 PEA +/- 5.78 PMA +/- 5.78 OTHER +/- 2.5 ALT +/- 1.5 AL 165 AV 151.95 AFT +/-3.0 NTSP 143 Based on these results, it is concluded that the Analytical Limit is not exceeded when-all applicable uncertainties are considered.
M0M TItCFI 10 UICIFAP rFANFPATINt PLAAT fA-95-0l75 C
TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 16 of 17
- 8. FUTURE NEEDS 8.1 Plant procedure and CML changes will be implemented in accordance with the MNGP setpoint change process.
8.2 New Allowable Value expressed as a percent of rated flow derived per GE guidance must be submitted for license approval(see Attachment 11 for submittal recommendation).
- 9. ATTACHMENTS
- 1. Setpoint Relationships
- 2. Drift Analysis
- 3. Drift Analysis Spreadsheets
- 4. DIT EPU-0258
- 5. DIT EPU-0259
- 6. BARTON product bulletin 288A/289A-7, "Differential Pressure Indicating Switches (Reference 10.8).
- 7. NEDO-10544,,April 1972, Modified Steam Line Flow Limiting Venturi Test Results (Reference 10.15).
- 8. Telephone conversation record between Bechtel Power Setpoint Group to ITT Barton (Reference 10.16).
- 9. Signature sheet, Sargent & Lundy vendor doc. no. 119 72-049
- 10. GE Hitachi DRF Section 0000-0156-8601, dated January 17, 2013. This document is included as Attachment 10
- 11. Summary of Change to Main Steam Line Hiqh Flow Allowable Value in accordance with GE Hitachi DRF Section 0000-0156-8601
- 10. REFERENCES 10.1 NEDC 31336P-A, September 1996, "General Electric Setpoint Methodology".
10.2 GE-NE-901-021-0492 "Setpoint Calculation Guidelines for the Monticello Nuclear Generating Plant", DRF A0O-ol 932-1.
10.3 Engineering Standards Manual ESM 03.02 "Design Requirements, Practices, & Topics (Instrumentation & Controls)" Rev. 9.
10.4 ANSI/ISA Standard ISA-$67.04 - Part I "Setpoints for Nuclear Safety-Related Instrumentation", dated September 1994.
10.5 ISA Recommended Practice RP67.04 - Part II"Methodologies for the Determination of Setpoints for Nuclear Safety-Related Instrumentation", dated 1994.
MONTICELLO NUCLEAR GENERA TING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Page 17 of 17 10.6 EPRI report TR-103335, "Guidelines for Instrument Calibration Extension/Reduction Programs", dtd 3/94.
10.7 Monticello Plant Component Master List (CML) Database.
10.8 BARTON product bulletin 288AN289A-7, "Differential Pressure Indicating Switches."
10.9 ESM-03.02-APP-I, GE Methodology Instrumentation and Controls.
10.10 NX-7829-67-1, Rack (25-26) C-126, Revision B.
10.11 Purchase specification 21A1 058, Controlled Specification Data Sheet Steam Flow Restrictor.
10.12 CA-97-216, Revision 0, Calculation to Determine Discharge Coefficient Changes for the Main Steam Line Flow Restrictors.
10.13 CA-95-027, Revision 1, Determine of Instrument Service Conditions for Input into Setpoint Calculations.
10.14 ESM-03.02-APP-lII, GE Methodology Instrumentation and Controls.
10.15 NEDO-10544, April 1972, Modified Steam Line Flow Limiting Venturi Test Results.
10.16 Telephone conversation record from Bechtel Power Setpoint Group to ITT Barton.
10.17 CA-98-01 1, Environmental Qualification of Barton Pressure Switches Models 278, 288, 288A and 289A.
10.18 Generic Letter 91-04, Changes in Technical Specification Surveillance Intervals to Accommodate a 24-Month Fuel Cycle.
10.19 GEH 10 CFR Part21 Communication, "Errorin Main Steam Line Hiqh Flow CalculationalMethodoloav." SC 12-189. R1. issued December 12. 2012.
MONTICELLO NUCLEAR GENERA TING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint. Attachment I SI Page 1 of 1 For Illustration Only Not to Scale Differential Pressure (psid)
Instrument Range 200 psid Upper Limit Analytical Limit 165 151.95 (116.9 % EPU flow Allowable Value LER Avoidance j NTSP 2 149.5 As-Found
+ 3.0 psid 144.5 Setpoint (NTSP) 143.0 As-Left
+/- 1.5 psid 141.5 As-Found 140.0 -3.0 psid Instrument Range 0 psid Lower Limit
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Attachment 2 Page I of 7 A1.1 Data Grouping The following Barton model 278 differential pressure indicating switches are included in this analysis:
Equipment ID Range Setpoint (desired)
DPIS-2-116A 0 - 200 psid 143 psid DPIS-2-116B 0 - 200 psid 143 psid DPIS-2-116C 0 - 200 psid 143 psid DPIS-2-116D 0 - 200 psid 143 psid DPIS-2-117A 0 - 200 psid 143 psid DPIS-2-117B 0 - 200 psid 143 psid DPIS-2-117C 0 - 200 psid 143 psid DPIS-2-117D 0 - 200 psid 143 psid DPIS-2-118A 0 - 200 psid 143 psid DPIS-2-118B 0 - 200 psid 143 psid DPIS-2-118C 0 - 200 psid 143 psid DPIS-2-118D 0 - 200 psid 143 psid DPIS-2-119A 0 - 200 psid 143 psid DPIS-2-119B 0 - 200 psid 143 psid DPIS-2-119C 0 - 200 psid 143 psid DPIS-2-119D 0 - 200 psid 143 psid As shown in section 6.2.1.2, the devices are exposed to similar environmental conditions with the same calibration frequency. Therefore, the individual drift data for the devices can be grouped without further numerical testing, following the criteria set forth in step 5.4.8 of ESM-03.02-APP-Ill (Input 12).
A1.2 Populating the Spreadsheet Calibration data for the switches included the date of calibration, as well as the As-Found and As-Left setpoint values. This data was input into a Microsoft Excel spreadsheet, and included in Attachment 2.
The calibration interval was determined by taking the difference between the current and previous calibration dates. Per step 5.3.9 of ESM-03.02-APP-lIl, the calibration interval was converted to months by dividing the number of days by 30.5 days per month.
The Drift value was calculated by taking the difference between the current calibration As-Found value and the previous calibration As-Left value.
None of the data points were removed from the final data set. Although the outlier test results showed several potential outliers, the points were kept in the analysis. Per the instructions of Attachment I from Input 12, there were no valid reasons for removing the outliers.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Attachment 2 Page 2 of 7 A1.3 Spreadsheet Performance of Basic Statistics The following information was determined for each instrument individually:
The average or mean value (x) of the drift data for each instrument was determined by using the "Average" function in Microsoft Excel. This function uses the following equation:
-lxi n
where x = average of data set x, = individual drift value n = total number of values The standard deviation of a data set returns the measure of. how widely dispersed the values are in relation to the mean of the data. The standard deviation for each instrument was determined using the "STDEV" function. Microsoft Excel uses the following equation in the "STDEV" function:
lZX 12 - ZX n(n-1) where s = standard deviation of sample x= individual drift value n = total number of values The variance (s 2) is another measure of data spread from the mean. The variance for each instrument was determined by using the "VAR" function in Microsoft Excel. The variance is calculated as follows:
n2=x,2-(EX n(n -1) where S2 = variance of sample x= individual drift value n =total number of values The largest positive drift value for each instrument was determined by using the "MAX" function.
The largest negative drift value for each instrument was determined by using the "MIN" function.
The number of data points (n) for each instrument was determined using the "COUNT" function.
The psid values for average, standard deviation, and largest positive and negative drift were converted to a percent of instrument span using the following formula:
% span = psid value x100%
psid span
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Attachment 2 Page 3 of 7 A Drift Trend Plot was developed for each instrument by plotting the drift value versus calibration date. Bounds corresponding to + 2s (2 standard deviations) are shown on the plot.
Page 49 of Attachment 2 presents the combined drift data statistics for the subject units.
The combined statistics were determined using the preceding methods.
A1.4 Outlier Detection and Expulsion Per step 5.5 of ESM-03.02-APP-lII, the t-Test is used to detect the presence of outliers in the final data set. The t-Test requires the use of the following equation:
tx - xI s
where t = individual t-Test statistic s = standard deviation of sample x, = individual drift value x = individual drift value The t-Test involves calculating the individual 't statistic for each data point, and comparing them to a critical value. The critical value depends on the sample size, and is obtained from Table 9.2 of Input 12.
The t-Test is shown on pages 50 through 74 of Attachment 2. Based on a sample size of 1094, the critical value utilized in the t-Test is 4.0. Seven of thecalculated individual t-Test statistics exceeded the critical value which, according to the t-Test, identifies them as outliers. However, based on the criteria of Attachment 1 to ESM-03.02-APP-III, none of the seven points were eliminated from the final data set.
AI.5 Normality Tests Most statistical analyses make the assumption that the values in question are normally distributed. The criteria in Input 12 require that the data set be tested for normality. It is recommended that for samples of over 50 data points, the D' Test be utilized.
D' (D-Prime) Test The D' Test calculates a test statistic value for the sample population and compares the calculated value to the values for the D' percentage points of the distribution, which are tabulated in Table 9.7 of ESM-03.02-APP-III. The D' Test is two-sided, which means that the two-sided percentage limits at the stated level of significance must bound the calculated D' value. For the given sample size, the calculated value of D' must lie with the two values provided in Table 9.7 in order to accept the hypothesis for normality.
To perform a D' Test, the drift value data set is sorted and numbered in ascending order from smallest to largest.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Attachment 2 Page 4 of 7 Calculate the S2 value for the group:
2 S2 = (n - 1)Xs where S 2 = sum of the squares about the mean S2= unbiased estimate of the sample population variance n = total number of data points Calculate the linear combination (T) of the sample group:
'.T=Y.ti where T= linear combination of the sample t= individual component of T i = number of sample point n = total number of data points x= individual sample data point Calculate the D' value for the sample group. The following equation is used:
Dl= T S
Determine the critical D' values based on the sample size using Table 9.7 in Input 12. If the exact sample size is not listed in Table 9.7, interpolate the values to obtain an estimate of the critical D' values.
Refer to pages 75 through,98 of Attachment 2 to see the D' Test for the drift data. For a sample size of 1094, the critical D values are 9833.6 and 9959.7. The calculated D' value was 9551.5. Based on this result, the assumption of normality is rejected.
Coverage Analysis Since the assumption of normality was rejected by the D' Test, a coverage analysis was performed per section 4.7.5.E of ESM-03.02-APP-IIl. A coverage analysis is discussed for cases in which the hypothesis tests reject the assumption of normality, but the assumption of normality may still be a conservative representation of the data. The coverage analysis involves the use of a histogram of the data set, overlaid with the equivalent probability distribution curve for the normal distribution, based on the data sample's mean and standard deviation. Visual examination of the plot is used, and the kurtosis is.analyzed to determine if the distribution of the data is near normal. If the data is near normal, then a normal distribution model which adequately covers the set of drift data as observed is derived. This normal distribution will be used as the model for the drift of the device.
Sample counting is used to determine an acceptable normal distribution. The standard deviation of the group is computed. The number of times the samples are within 2 standard deviations of the mean is computed. The count is divided by the total number of
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Attachment 2 Page 5 of 7 samples in the group to determine a percentage. If the percentage of data within 2 standard deviations of the mean is greater than 95.45%, the existing standard deviation is acceptable to be used for the encompassing normal distribution model. In case the percentage is less than required, the standard deviation should be enlarged. The required multiplier for the standard deviation in order to provide this coverage is termed the Normality Adjustment Factor (NAF). If no adjustment is required, the NAF is equal to one.
The coverage analysis is presented on page 99 of Attachment 2. Visual inspection shows a moderate kurtosis, as most of the data points are found within 1.5 standard deviations of the mean. Calculations using the table on page 99 of Attachment 2 show that 95.9% of the data is encompassed within 2 standard deviations of the mean. Therefore, it is concluded that a normal distribution is a conservative representation of the data, and thus NAF is equal to 1.
A1.6 Selection of Final Data Set The devices in question are only calibrated to one setpoint. Therefore, all data points will be utilized and no further analysis is required in determining the final data set.
A1.7 Time-Dependency Analysis Standard statistical analyses do not consider time-dependency. The following tests attempt to uncover any time-related performance and the impact of any time-dependency on the analysis.
Drift Interval Plot A drift interval plot is an XY scatter plot that shows the data set plotted against the time interval between calibrations. It relies on visual inspection to discriminate the plot for any trend in the data to exhibit a time dependency. A prediction line can be added to this plot to aid in the analysis.
Page 100 of Attachment 2 shows the drift interval plot for this data set. The plot shows a scatter of drift values, both positive and negative around the 1.5 and 3 month calibration intervals. As these were the most common intervals, most of the data points are found near these two time periods. Based on the equation of the regression line, there may. be a slight time-dependency present. The drift interval plot includes the tolerance interval (TI). This tolerance interval is equal to the random drift term calculated in section A1.9.
Standard Deviations and Means at Different Calibration Intervals (Binning Analysis)
The binning analysis is the most recommended method of determining time dependent tendencies in a given sample pool. Following the instructions in step 4.8.3 of Input 12, the drift data was segregated into different groups (bins) corresponding to different ranges of, calibration intervals. In order for further analysis to be done, at least 2 valid bins must exist. In order to be considered valid, a bin must contain more than five data points and' more than 10% of the total data count. The binning analysis (Attachment 2, pages 101-123) shows that only 1 valid bin exists. Therefore, per the criteria in Input 12, the data will be established as moderately time dependent for the purposes of extrapolation of the drift value.
Due to the fact that multiple valid bins did not exist in the binning analysis, no further time-dependency testing is available.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Attachment 2 Page 6 of 7 A1.8 Drift Bias Determination The absolute value of the average calculated drift for the trip units is 0.009 psid. Similarly, the absolute value of the average calculated drift is less than 0.1% of the calibrated span (200 psid). Based on the criteria of ESM-03.02-APP-lII, it is concluded that the instrument drift does not have a bias. Therefore, the drift bias terms will be taken as 0 in this analysis..
A1.9 Analyzed Drift Value Bias Term Based on the section A1.8, the instruments do not have a bias. Therefore, the bias term will be equal to 0.
Random Term The random term of the analyzed drift value is calculated with the below equation:
ADrWd,d = s x TIF x NAF where ADrandom = random term for analyzed drift s = drift standard deviation TIF = 95%/95% tolerance interval factor NAF = Normality Adjustment factor The value of TIF is obtained from Table 9.1 of ESM-03.02-APP-III. Based on a sample size of 1094, TIF is equal to 1.960. From the coverage analysis, NAF was determined to be 1. From page 49 of Attachment 2, the standard deviation of the sample is 0.88. Thus the random term is equal to 1.73 psid.
30-Month Predicted Drift (Random Term)
Since the drift was determined to be moderately time dependent, the following equation was used to extrapolate the drift uncertainty:
AD =admADrhl~doni X -CIE, C'0 where ADE.randomr extended period drift term ADrandom = random term for analyzed drift ClE = extended calibration interval (surveillance interval +25%)
ClO = average observed calibration time interval from bin with longest time interval The value of the random term for the analyzed drift was determined to be 1.73 psid. The extended calibration interval is equal to the surveillance calibration interval (3 months) plus an additional 25% (0.75 months). Therefore, CIE is equal to 3.75 months. ClO is
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Attachment 2 Page 7 of 7 determined from a valid bin of data with the longest calibration interval. There was only one valid bin, with a calibration interval range of 1.25 to 3.75 months. The average calibration interval within this bin is equal to 2.8 months. These values produce a 30-month predicted drift term of 2.00 psid.
Per the criteria in step 5.10.4.B, a check was made to ensure that the calculated 30-month predicted drift uncertainty is greater than the uncertainty calculated with the 99%/95% tolerance factor. Based on the large sample size ( > 1000 data points), the TIF for 99%/95% is equal to the TIF for 95%/95%. The uncertainty calculated using the 99%/95% TIF of 1.960 is 1.73 psid.
Therefore, the 30-month predicted drift uncertainty is 2.00 psid.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 1 of 123 Drift Data for DPIS-2-116A Calibration As- Drift Drift Date Interval Found As-Left (psid) N (Months) 5/5/2008 3.0 140.9 140.9 0.1 0.05 2/4/2008 2.7 140.8 140.8 -0.2 -0.10 11/15/2007 3.3 141.0 141.0 1.0 0.50 8/6/2007 3.0 140.0 140.0 -0.8 -0.40 5/7/2007 2.9 140.8 140.8 -1.2 -0.60 2/8/2007 3.1 142.0 142.0 1.0 0.50 11/6/2006 3.0 141.0 141.0 0.7 0.35 8/7/2006 3.0 140.3 140.3 -0.5 -0.25 5/8/2006 3.0 140.8 140.8 0.0 0.00 2/6/2006 3.2 140.8 140.8 -0.5 -0.25 10/31/2005 3.0 141.3 141.3 0.3 0.15 8/1/2005 3.0 141.0 141.0 0.0 0.00 5/2/2005 1.7 141.0 141.0 0.0 0.00 3/10/2005 1.2 141.0 141.0 -0.5 -0.25 1/31/2005 3.0 141.5 141.5 0.5 0.25 11/1/2004 3.0 141.0 141.0 0.5 0.25 8/2/2004 1.4 140.5 140.5 -0.5 -0.25 6/20/2004 1.6 142.0 141.0 3.5 1.75 5/3/2004 3.0 138.5 138.5 -3.0 -1.50 2/2/2004 3.0 141.5 141.5 0.5 0.25 11/3/2003 3.0 141.0 141.0 -1.5 -0.75 8/4/2003 3.4 142.5 142.5 0.5 0.25 4/23/2003 2.6 142.0 142.0 -1.0 -0.50 2/3/2003 3.0 143.0 143.0 1.0 0.50 11/4/2002 3.0 142.0 142.0 0.0 0.00 8/5/2002 3.0 142.0 142.0 -1.0 -0.50 5/6/2002 3.0 143.0 143.0 -0.5 -0.25 2/4/2002 3.0 143.5 143.5 0.5 0.25 11/6/2001 2.9 143.0 143.0 0.5 0.25 8/10/2001 3.1 142.5 142.5 -0.5 -0.25 5/7/2001 3.0 143.0 143.0 1.5 0.75 2/5/2001 3.0 141.5 141.5 -0.5 -0.25 11/6/2000 3.0 142.0 142.0 -2.0 -1.00 8/7/2000 3.0 144.0 144.0 1.5 0.75 519/2000 2.9 142.5 142.5 -1.0 -0.50 2/11/2000 0.7 143.5 143.5 0.5 0.25 1/20/2000 2.4 143.0 143.0 -1.5 -0.75 11/8/1999 3,0 144.5 144.5 0.0 0.00 8/9/1999 3.0 144.5 144.5 4.0 2.00 5/10/1999 3.0 140.5 140.5 -3.0 -1.50 2/8/1999 3.0 143.5 143.5 -1.0 -0.50 11/9/1998 1.3 144.5 144.5 1.5 0.75 9/30/1998 1.7 121.0 143.0 -4.0 -2.00
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 2 of 123 8/10/1998 3.0 125.0 125.0 0.0 0.00 5/12/1998 2.9 125.0 125.0 -0.5 -0.25 2/12/1998 3.0 125.5 125.5 0.5 0.25 11/11/1997 3.0 125.0 125.0 3.5 1.75 8/11/1997 1.4 121.5 121.5 -4.5 -2.25 6/30/1997 4.6 126.0 126.0 4.0 2.00 2/10/1997 3.0 122.0 122.0 -4.0 -2.00 1111111996 3.0 126.0 126.0 0.0 0.00 8/13/1996 2.7 126.0 126.0 -2.0 -1.00 5/24/1996 3.3 128.0 128.0 3.0 1.50 2/13/1996 3.0 125.0 125.0 0.5 0.25 11/13/1995 3.0 124.5 124.5 -0.5 -0.25 8/15/1995 3.0 125.0 125.0 -0.5 -0.25 5/15/1995 3.0 125.5 125.5 0.5 0.25 2/13/1995 3.0 125.0 125.0 -1.0 -0.50 11/15/1994 1.6 126.0 126.0 -1.0 -0.50 9/26/1994 1.4 127.0 127.0 0.5 0.25 8/15/1994 3.0 126.5 126.5 0.0 0.00 5/17/1994 3.0 126.5 126.5 1.5 0.75 2/15/1994 3.0 125.0 125.0 -1.0 -0.50 11/16/1993 3.0 126.0 126.0 -0.5 -0.25 8/17/1993 3.0 126.5 126.5 0.5 0.25 5/18/1993 2.9 126.0 126.0 -1.0 -0.50 2/19/1993 3.0 127.0 127.0 0.0 0.00 11/19/1992 3.0 127.0 127.0 0.0 0.00 8/18/1992 3.0 127.0 127.0 -0.5 -0.25 5/18/1992 127.5 127.5 Basic Statistics for DPIS-2-116A Average x (psid) -0.1 Standard Deviation s (psid) 1.61 Variance $ (psid) 2.59 Largest Positive Drift (psid) 4.0 Largest Negative Drift (psid) -4.5 Number of Samples n 69 Average NO) -0.06 Standard Deviation s (%) 0.80 Largest Positive Drift (%) 2.00 Largest Negative Drift (%) -2.25
Z CD Drift Trend Plot for DPIS-2-116A
)rr 4.0 2.0 S0.0
.: -2.0 ili i
-4.0 CAZ cn
,*-6.0 2,.
416/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/1 4/2005 9/9/2008 M Date
,-."DPIS-2-116A- - -+2s - - - -2s CD fw=
0 to 2CD
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075'..
TITLE: Main Steam Line High Flow Setpoint ReVision I Drift Analysis Spreadsheets Attachment 3
'Page 4 of 123 Drift Data for DPIS-2-1168 Date Calibration Interval As- Ass-LeftDif Drift Drift De (Months) Found As-Left (psid) (%)
5/5/2008 3.0 141.4 141.4 -0.1 -0.05 2/5/2008 2.7 141.5 141.5 -0.5 -0.25 11/15/2007 3.3 142.0 142.0 1.1 0.55.
8/6/2007 3.0 140.9 140.9 -0.6 -0.30 5/7/2007 2.9 141.5 141.5 -0.9 -0.45 2/8/2007 3.1 142.4 142.4. 1.1 0.55 11/6/2006 3.0 141.3 141.3 0.5 0.25 8/7/2006 3.0 140.8 140.8 -0.4 -0.20 5/8/2006 3.0 141.2 141.2 0.0 0.00 2/6/2006 3.2 141.2 141.2 -0.4 -0.20 10/31/2005 3.0 141.6 141.6 1.1 0.55 8/1/2005 3.0 140.5 140.5 -1.0 -0.50 5/2/2005 1.7 141.5 141.5 0.5 0.25 3/11/2005 1.3 141.0, 141.0 -0.5 -0.25 1/31/2005 3.0. 141.5 141.5 0.0 0.00 11/1/2004 3.0 141.5 141.5 0.0 0.00 8/2/2004 3.0 141.5 141.5 0.5 0.25 5/3/2004 3.0 141.0 141.0 -1.0 -0.50 2/2/2004 3.0 142.0 142.0 0.5 0.25 11/3/2003 3.0 141.5 141.5 0.0 0.00 8/4/2003 3.4 141.5 141.5 -0.5 -0.25 4/23/2003 2.6 142.0 142.0 .0.0 0.00 2/3/2003 3.0 142.0 142.0 1.0 0.50 11/4/2002 3.0
- 141.0 141.0 0.0 0.00 8/5/2002 3.0 141.0 141.0 -0.5 -0.25 5/6/2002 3.0 141.5 141 .5 :1.0 -0.50 2/4/2002 3.0 142.5 142.5 1.0 0.50 11/6/2001 2.9 141.5 141.5 0.0 0.00 8/10/2001 3.1 141.5 141.5 -1.0 -0.50 5/7/2001 3.0 142.5 142.5 '0.5 0.25 2/5/2001 3.0 142.0 142.0 -0.5 -0.25 11/6/2000' 3.0 142.5 142.5 1.0 0.50 8/7/2000 3.0 141.5 141.5 -1.0 -0.50 5/9/2000 2.9 142.5 142.5 -0.5 -0.25 2/11/2000 0.7 143.0 143.0 0.5 025 1/21/2000 2.4. 142.5 142.5 -0.5 -0.25 11/8/1999 3.0 143.0 143.0 0.5 0.25 8/9/1999 3.0 142.5 142.5 0.5 0.25 5/10/1999 3.0 142.0 142.0 0.0 0.00 2/8/1999 3.0 142.0 142.0 -0.5 -0.25 11/9/1998 113 142.5 142.5 1.0 0.50 9/30/1998 1.7 123.5 141.5 0.3 0.15 8/10/1998 3.0 123.2 123.2 0.2 "0.10
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 5 of 123 5/12/1998 1 2.9 123.0 123.0 -1.5 -0.75 2/12/1998 3.0 124.5 124.5 1.0 0.50 11/11/1997 3.0 123.5 123.5 -0.5 -0.25 8/11/1997 1.4 124.0 124.0 1.0 0.50 6/30/1997 4.6 123.0 123.0 -1.0 -0.50 2/10/1997 3.0 124.0 124.0 0.5 0.25 11/11/1996 3.0 123.5 123.5 0.0 0.00 8/13/1996 2.7 123.5 123.5 -1.0 -0.50 5/24/1996 3.3 124.5 124.5 1.0 0.50 2/13/1996 3.0 123.5 123.5 -1.0 -0.50 11/13/1995 3.0 124.5. 124.5 1.5 0.75 8/15/1995 3.0 123.0 123.0 -0.5 -0.25 5/15/1995 3.0 123.5 123.5 -0.5 -0.25 2/13/1995 3.0 124.0 124.0 0.0 0.00 11/15/1994 1.5 124.0 124.0 0.5 0.25 9/29/1994 1.5 123.5 123.5 0.0 0.00 8/15/1994 3.0 123.5 123.5 -0.5 -0.25 5/17/1994 3.0 124.0 124.0 1.0 0.50 2/15/1994 3.0 123.0 123.0 -0.5 -0.25 11/16/1993 3.0 123.5 123.5 -0.5 -0.25 8/17/1993 3,0 124.0 124.0 0.0 0.00 5/18/1993 2.9 124.0 124.0 0.0 0.00 2/19/1993 3.0 124.0 124.0 0.0 0.00 11/19/1992 3.0 124.0 124.0 0.5 0.25 8/18/1992 3.0 123.5 123.5 0.5 0.25 5/18/1992 123.0 123.0 Basic Statistics for LIS-2-3-657B Average X (psid) 0.0 Standard Deviation s (psid) 0.69 Variance s2 (psid) 0.48 Largest Positive Drift (psid) 1.5 Largest Negative Drift (psid) -1.5 Number of Samples n 68 Average x (%) 0.00 Standard Deviation s (%) 0.35 Largest Positive Drift (%) 0.75 Largest Negative Drift (%) -0.75
Drift Trend Plot for DPIS-2-116B CI) a)D-n G) 2.0
-0 6i 4
-S0 re, 0n 4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/1 4/2005 9/9/2008 Date
-.-DPIS-2-116B -- - +2s - - - -2s CD cn CD0 0
- 01. CD CA)
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 7 of 123 Drift Data for DPIS-2-116C Calibration As- Drift Drift Date Interval (Mnh) Found As-Left (psid) (%)
(Months) 5/5/2008 3.0 142.0 142.0 -0.2 -0.10 2/5/2008 2.7 142.2 142.2 0.4 0.20 11/15/2007 3.3 141.8 141.8 -0.2 -0.10 8/6/2007 3.0 142.0 142.0 -0.8 -0.40 5/7/2007 2.9 142.8 142.8 0.8 0.40 2/8/2007 3.1 142.0 142.0 0.8 0.40 11/6/2006 3.0 141.2 141.2 0.0 0.00 8/7/2006 3.0 141.2 141.2 -1.1 -0.55 5/8/2006 3.0 142.3 142.3 0.0 0.00 2/6/2006 3.2 142.3 142.3 1.0 0.50 10/31/2005 3.0 141.3 141.3 0.4 0.20 8/1/2005 3.0 140.9 140.9 -0.6 -0.30 5/2/2005 1.7 141.5 141.5 0.0 0.00 3/11/2005 1.3 141.5 141.5 -0.5 -0.25 1/31/2005 3.0 142.0 142.0 0.0 0.00 11/1/2004 3.0 142.0 142.0 1.0 0.50 8/2/2004 3.0 141.0 141.0 0.0 0.00 5/3/2004 3.0 141.0 141.0 -0.5 -0.25 2/2/2004 3.0 141.5 141.5 0.5 0.25 11/3/2003 3.0 141.0 141.0 -0.5 -0.25 8/4/2003 3.4 141.5 141.5 0.0 0.00 4/23/2003 2.6 144.5 141.5 0.5 0.25 2/3/2003 3.0 144.0 144.0 -0.5 -0.25 11/4/2002 3.0 144.5 144.5 0.0 0.00 8/5/2002 3.0 144.5 144.5 '0.5 0.25 5/6/2002 3.0 144.0 144.0 -1.0 -0.50 2/4/2002 3.0 145.0 145.0 0.5 0.25 11/6/2001 -2.9 144.5 144.5 0.5 0.25 8/10/2001 3.1 144.0 144.0 -1.0 -0.50 5/7/2001 3.0 145.0 145.0 0.5 0.25 2/5/2001 3.0 144.5 144.5 -0.5 -0.25 11/6/2000 3.0 145.0 145.0 0.5 0.25 8/7/2000 3.0 144.5 144.5 -0.5 -0.25 5/9/2000 2.9 145.0 145.0 0.0 0.00 2/1112000 0,7 145.0 145.0 -0.2 -0.10 1/21/2000 2.4 145.2 145.2 1.2 0.60 11/8/1999 3.0 144.0 144.0 0.0 0.00 8/9/1999 3.0 144.0 144.0 -1.0 -0.50 5/10/1999 3.0 .145.0 145.0 0.0 0.00 2/8/1999 3.0 145.0 145.0 0.0 0.00 11/9/1998 1.3 145.0 145.0 1.0 0.50 9/30/1998 1.7 127.0 144.0 0.0 0.00 8/10/1998 3.0 127.0 127.0 0.0 0.00
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 8 of 1.23 5/12/1998 2.9 127.0 127.0 -1.0 -0:50 2/12/1998 3.0 128.0 128.0 0.5 0.25 11/11/1997 3.0 127.5 127.5 0.5 0.25 8/11/1997 1.4' 127.0 127.0 -1.0 -0.50 6/30/1997 4.6 128.0 128.0 0.0 0.00 2/10/1997 3.0 128.0 128.0 0.2 0.10 11/11/1996 .3.0 ,127.8 127.8 0.8 -0.40 8/13/1996 2.7 127.0 127.0 -1.5 -0.75 5/2411996 3.3 128.5 128.5 1.5 0.75 2/13/1996 3.0 127.0 127.0 -0.8 -0.40 11/13/1995 3.0 127.8 127.8 0.8 0.40 8/15/1995 3.0 127.0 127.0 0.0 0.00 5/15/1995 3.0 127.0 127.0 -0.5 -0.25 2/13/1995 3.0 127.5 127.5 0.5 0.25 11115/1994 1.6 127.0 .127.0 -0.5 -0.25 9/28/1994 1.4 .127.5 127.5 0.5 0.25 8/15/1994 3.0 127.0 127.0 -0.5 -0.25 5/17/1994 30 127.5 127.5 0.5 0.25 2/15/1994 3.0 127.0 127.0 -0.5 -0.25 11/16/1993 3.0 127.5 127.5 0.0 0.00 8/17/1993 3.0 127.5 127.5 -0.5 -0.25 5/1.8/1993 2.9 128.0 128.0 0.0 0.00 2/19/1993 3.0 128.0 128.0 0.0 0.00 11/19/1992 3.0 128.0 128.0 1.0 0.50 8/18/1992 3.0 127.0 127.0 0.0 .0.00 5118/1992 127.0 127.0 Basic Statistics for DPIS-2-116C iAverage x (psid) 0.0 Standard Deviation s (psid) 0.63 Variance s2 (psid) 0.40 Largest Positive Drift., (psid) 1.5 Largest Negative Drift (psid) -1.5 Number of Samples n 68
- Average x ()0.01
'Standard Deviation S(% 0.31 Largest Positive Drift ()0.76 1Largest Negative Drift ()-0.75
0 rri 0-I-
h~i Q) hi zi CA,-
0n 0:
0>
CD CDO0 0;5 0 .3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 10 of 123 Drift Data for DPIS-2-116D Calibration As- Drift Drift Date Interval Found As-Left (pid) N (Months) 5/5/2008 3.0 140.0 140.0 -0.9 -0.45 2/5/2008 2.7 140.9 140.9 -0.3 -0.15 11/15/2007 3.3 141.2 141.2 1.0 0.50 81612007 3.0 140.2 140.2 -0.2 -0.10 5/7/2007 2.9 140.4 140.4 -1.4 -0.70 2/8/2007 3.1 141.8 141.8 1.3 0.65 11/6/2006 3.0 140.5 140.5 0.3 0.15 8/7/2006 3.0 140.2 140.2 -0.6 -0.30 5/8/2006 3.0 140.8 140.8 -0.1 -0.05 2/6/2006 3.2 140.9 140.9 -0.6 -0.30 10/31/2005 3.0 141.5 141.5 1.1 0.55 8/1/2005 3.0 140.4 140.4 -0.1 -0.05 5/2/2005 1.6 140.5 140.5 0.0 0.00 3/13/2005 1.3 140.5 140.5 0.0 0.00 1/31/2005 3.0 140.5 140.5 -0.5 -0.25 11/1/2004 3.0 141.0 141.0 1.0 0.50 8/2/2004 3.0 140.0 140.0 -0.5 -0.25 5/3/2004 3.0 140.5 140.5 -1.0 -0.50 2/2/2004 3.0 141.5 141.5 -0.5 -0.25 11/3/2003 3.0 142.0 142.0 0.0 0.00 8/4/2003 3.4 142.0 142.0 0.5 0.25 4/23/2003 2.6 141.5 141.5 0.0 0.00 2/3/2003 3.0 141.5 141.5 0.0 0.00 11/4/2002 3.0 141.5 141.5 0.5 0.25 8/5/2002 3.0 141.0 141.0 -1.0 -0.50 5/6/2002 3.0 142.0 142.0 0.0 0.00 2/4/2002 3.0 142.0 142.0 0.0 0.00 11/612001 2.9 142.0 142.0 1.5 0.75 8/1012001 3.1 140.5 140.5 -1.0 -0.50 5/7/2001 3.0 141.5 141.5 0.5 0.25 2/5/2001 3.0 141.0 141.0 -0.5 -0.25 11/6/2000 3.0 141.5 141.5 0.5 0.25 8/7/2000 3.0 141.0 141.0 -0.5 -0.25 5/9/2000 2.9 141.5 141.5 0.5 0.25 2/11/2000 0.7 141.0 141.0 -1.5 -0.75 1/22/2000 2.5 142.5 142.5 1.0 0.50 11/8/1999 3.0 141.5 141.5 -0.5 -0.25 8/9/1999 3.0 142.0 142.0 0.0 0.00 5/10/1999 3.0 142.0 142.0 -0.5 -0.25 2/8/1999 3.0 142.5 142.5 0.0 0.00 11/9/1998 1.3 142.5 142.5 0.5 0.25 9/30/1998 1.7 123.0 142.0 0.2 0.10 8/10/1998 3.0 122.8 122.8 -0.2 -0.10
MONTICELLO NUCLEAR GENERATING PLANT, CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Analysis Spreadsheets Drift A D Attachment 3 Page 11 of 123 5/12/1998 2.9 123.0 123.0 0.0 0.00 2/12/1998 3.0 123.0 123.0 0.0 0.00 11/11/1997 3.0 123.0 123.0 1.0 0.50 8/11/1997 1.4 122.0 122.0 -1.0 -0.50 6/30/1997 4.6 123.0 123.0 0.0 0.00 2/10/1997 3.0 123.0 123.0 0.0 0.00 11/11/1996 3.0 123.0 123.0 1.0 0.50 8/13/1996 2.7 122.0 122.0 -2.0 -1.00 5/24/1996 3.3 124.0 124.0 1.0 0.50 2/13/1996 3.0 123.0 123.0 0.0 0.00 11/13/1995 3.0 123.0 123.0 0.0 0.00 8/15/1995 3.0 123.0 123.0 0.5 0.25 5/1511995 3.0 122.5 122.5 -0.5 -0.25 2/13/1995 3.0 123.0 123.0 1.0 0.50 11/15/1994 1.5 122.0 122.0 0.5 0.25 9/29/1994 1.5 123.0 121.5 0.0 0.00 8/15/1994 3.0 124.0 123.0 0.5 0.25 5/17/1994 3.0 123.5 123.5 -0.5 -0.25 2/15/1994 3.0 124.0 124.0 0.5 0.25 11/16/1993 3.0 123.5 123.5 -0.5 -0.25 8/17/1993 3.0 124.0 124.0 -2.0 -1.00 5/18/1993 2.9 126.0 126.0 1.0 0.50 2/19/1993 3.0 125.0 125.0 0.5 0.25 11/19/1992 3.0 124.5 124.5 0.5 0.25 8/18/1992 3.0 124.0 124.0 0.0 0.00 5/18/1992 124.0 124.0 Basic Statistics for DPIS-2-116D Average x (psid) 0.0 Standard Deviation s (psid) 0.74 Variance s2 (psid) 0.55 Largest Positive Drift (psid) 1.5 Largest Negative Drift (psid) -2.0 Number of Samples n 68
- Average X (%) 0.00 Standard Deviation s (%) 0.37 Largest Positive Drift (%) 0.75 Largest Negative Drift (%) -1.00
-3 Drift Trend Plot for DPIS-2-116D r-
- 0. 0 0 :
CA,
-1.0 CD
- -2.0 -0
-3 .0 ....
4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/1, 4/2005 9/9/2008 Date
- DIDPIS-2-116D - - +2s - - - -2s ILI CD 0(DO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 13 of 123 Drift Data for DPIS-2-117A Calibration As- As-Left Drift Drift Date Interval F(As-Left (Months) Found (psid) (N) 5/5/2008 3.0 141.8 141.8 -0.5 -0.25 2/4/2008 2.7 142.3 142.3 -0.3 -0.15 11/15/2007 3.3ý 142.6 142.6 0.6 0.30 8/6/2007 3.0 142.0 142.0 0.0 0.00 5/7/2007 2.9 142.0 142.0 -0.5 -0.25 2/8/2007 3.1 142.5 142.5 0.2 0.10 11/6/2006 3.0 142.3 142.3 0.2 0.10 8/7/2006 3.0 142.1 142.1 -0.4 -0.20 5/8/2006 3.0 142.5 142.5 0.1 0.05 2/6/2006 3.2 142.4 142.4 -0.9 -0.45 10/31/2005 3.0 143.3 143.3 0.9 0.45 8/1/2005 3.0 142.4 142.4 0.5 0.25 5/2/2005 1.7 141.9 141.9 -0.1 -0.05 3/11/2005 1.3 142.0 142.0 -0.5 -0.25 1/31/2005 3.0 142.5 142.5 0.0 0.00 11/1/2004 3.0 142.5 142.5 0.0 0.00 8/2/2004 3.0 142.5 142.5 0.5 0.25 5/3/2004 3.0 142.0 142.0 -1.0 -0.50 2/2/2004 3.0 143.0 143.0 1.0 0.50 11/3/2003 3.0 142.0 142.0 0.0 0.00 8/4/2003. 3.4 142.0 142.0 -0.5 -0.25 4/23/2003 2.6 142.5 142.5 0.0 0.00 2/3/2003 3.0 142.5 142.5 -0.5 -0.25 11/4/2002 3.0 143.0 143.0 0.5 0.25 8/5/2002 3.0 142.5 142.5 0.0 0.00 5/6/2002 3.0 142.5 142.5 -0.5 -0.25 2/4/2002 3.0 143.0 143.0 0.0 0.00 11/6/2001 2.9 143.0 1,43.0 1.0 0.50 8/10/2001 3.1 142.0 142.0 0.0 0.00 5/7/2001 3.0 142.0 142.0 -0.5 -0.25 2/5/2001 3.0 142.5 142.5 -1.0 -0.50 11/6/2000 3.0 143.5 143.5 1.0 0.50 8/7/2000 3.0 142.5 142.5 0.0 0.00 519/2000 2.9 142.5 142.5 '0.2 0.10 2/11/2000 0.7 142.3 142.3 -1.2 -0.60 1/20/2000 2.4 143.5 143.5 0.5 0.25 11/8/1999 3.0 143.0 143.0 0.5 0.25 8/9/1999 3.0 142.5 142.5 0.0 0.00 5/10/1999 3.0 142.5 142.5 0.5 0.25 2/8/1999 3.0 142.0 142.0 -0.5 -0.25 11/9/1998 1.3 142.5 142.5 0.5 0.25 9/30/1998 1.7 125.0 142.0 -0.4 -0.20 8/110/1998 3.0 125.4 125.4 0.4 0.20
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 14 of 123 5/12/1998 2.9 125.0 125.0 0.0 0.00 2/12/1998 3.0 125.0 125.0 0.5 0.25 11/11/1997 3.0 124.5 124.5 -0.5 -0.25 8/11/1997 1.4 125.0 125.0 -0.5 -0.25 6/30/1997 4.6 125.5 125.5 0.5 0.25 2/10/1997 3.0 125.0 125.0 -1.0 -0.50 11/11/1996 3.0 126.0 126.0 0.5 0.25 8/13/1996 2.7 125.5 125.5 -1.5 -0.75 5/24/1996 3.3 127.0 127.0 1.0 0.50 2/13/1996 3.0 126.0 126.01 0.5 0.25 11/13/1995 3.0 125.5 125.5 0.5 0.25 8/15/1995 3.0 125.0 125.0 0.5 0.25 5/15/1995 3.0 124.5 124.5 -1.0 -0.50 2/1311995 3.0 125.5 125.5 -0.5 -0.25 11/15/1994 1.6 126.0 126.0 0.5 0.25 9/27/1994 1.4 125.5 125.5 0.5 0.25 8/15/1994 3.0 125.0 125.0 -0.5 -0.25 5/17/1994 3.0 125.5 125.5 0.5 0.25 2/15/1994 3.0 125.0 125.0 0.5 0.25 11/16/1993 3.0 124.5 124.5 -1.0 -0.50 8/17/1993 3.0 125.5 125.5 0.5 0.25 5118/1993 2.9 125.0 125.0 -1.0 -0.50 2/19/1993 3.0 126.0 126.0 1.0 0.50 11/19/1992 3.0 125.0 125.0 0.0 0.00 8/18/1992 3.0 125.0 125.0 0.0 0.00 5/18/1992 125.0 125.0 Basic Statistics for DPIS-2-117A Average x (psid) 0.0 Standard Deviation s (psid) 0.61 Variance s2 (psid) 0.37 argest Positive Drift (psid) 1.0 Largest Negative Drift (psid) -1.5 Number of Samples n 68 Average X (%) 0.00 Standard Deviation s (%) 0.30 Largest Positive Drift (%) 0.50 Largest Negative Drift (%) -0.75
-I mI 0
C)
Z?
c-Ch
.0
-n ClD 0D V
=n CL I--
CD G)
Li CD 0
1>
CD 0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 16 of 123 Drift Data for DPIS-2-117B Calibration As- Drift Drift Date Interval Found As-Left (psid)
(Months) 5/5/2008 3.0 141.9 141.9 -2.0 -1,00 2/5/2008 2.7 143.9 143.9 -0.3 -0.15 11/15/2007 3.3 144.2 144.2 0.8 ,0.40 8/6/2007 3.0 143.4 143.4 -0.4 -0.20 5/7/2007 2.9 143.8 143.8 -1.2 -0.60 2/8/2007 3.1 145.0 145.0 3.2 1.60 11/6/2006 3.0 141.8 141.8 0.5 0.25 8/7/2006 3.0 141.3 141.3 0.1 0.05 5/8/2006 3.0 141.2 141.2 -1.2 -0.60 2/6/2006 3.2 142.4 142.4 -0.2 -0.10 10/31/2005 3.0 142.6 142.6 1.7 0.85 8/1/2005 3.0 140.9 140.9 -0.1 -0.05 5/2/2005 1.7 141.0 141.0 1.0 0.50 3/12/2005 1.3 140.0 140.0 -1.5 -0.75 1/31/2005 3.0 141.5 141.5 0.0 0.00 11/1/2004 3.0 141.5 141.5 -0.5 -0.25 8/2/2004 3.0 142.0 142.0 -1.0 -0.50 5/3/2004 3.0 143.0 143.0 -0.5 -0.25 2/2/2004 3.0 143.5 143.5 0.0 0.00 11/3/2003 3.0 143.5 143.5 0.0 0.00 8/4/2003 3.4 144.0 143.5 0.5 0.25 4/23/2003 2.6 143.5 143.5 -0.5 -0.25 2/3/2003 3.0 144.0 144.0 0.5 0.25 11/4/2002 3.0 143.5 143.5 0.0 0.00 8/5/2002 3.0 143.5 143.5 0.0 0.00 5/6/2002 3.0 143.5 143.5 -i.0 -0.50 2/4/2002 3.0 144.5 144.5 1.0 0.50 11/6/2001 2.9 143.5 143.5 0.5 0.25 8/10/2001 3.1 143.0 143.0 -1.0 -0.50 5/7/2001 1.2 144.0 144.0 1.5 0.75 3/31/2001 1.8 144.0 142.5 -1.5 -0.75 2/5/2001 3.0 145.5 145.5 -0.5 -0.25 11/6/2000 3.0 146.0 146.0 -0.5 -0.25.
8/7/2000 3.0 146.5 146.5 1.0 0.50 5/9/2000 2.9 145.5 145.5 1.0 0.50 2/11/2000 0.7 144.5 144.5 -0.5 -0.25 1/21/2000 2.4 145.0 145.0 0.0 0.00 11/8/1999 3.0 145.0 145.0 1.0 0.50 8/9/1999 3.0 144.0 144.0 0.0 0.00 5/10/1999 3.0 144.0 144.0 -1.5 -0.75 21811999 3.0 145.5 145,5 1.5 0.75 11/9/1998 1.3 144.0 144.0 0.5 0.25 9/30/1998 1:7 128.0 143.5 4.5 2.25
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 17 of 123 8/10/1998 3.0 123.5 123.5 -0.5 -0.25 5/12/1998 2.9 124.0 124.0 0.0 0.00 2/12/1998 3.0 124.0 124.0 0.5 0.25 11/11/1997 3.0 123.5 123.5 0.0 0.00 8/11/1997 1.4 123.5 123.5 0.5 0.25 6/30/1997 4.6 123.0 123.0 -1.0 -0.50 2/10/1997 3.0 124.0 124.0 0.0 0.00 11/11/1996 3.0 124.0 124.0 -0.5 -0.25 8/13/1996 2.7 124.5 124.5 0.0 0.00 5/24/1996 3.3 124.5 124.5 1.0 0.50 2/13/1996 3.0 123.5 123.5 -0.3 -0.15 11/13/1995 3.0 123.8 123.8 -0.2 -0.10 8/15/1995 3.0 124.0 124.0 1.5 0.75 5/15/1995 3.0 122.5 122.5 -0.5 -0.25 2/13/1995 3.0 123.0 123.0 -1.0 -0.50 11/15/1994 1.5 124.0 124.0 0.5 0.25 9/29/1994 1.5 123.5 123.5 0.0 0.00 8/15/1994 3.0 123.5 123.5 0.0 0.00 5/17/1994 3.0 123.5 123.5 0.5 0.25 2/15/1994 3.0 123.0 123.0 -0.5 -0.25 11/16/1993 3.0 123.5 123.5 0.5 0.25 8/17/1993 3.0 123.0 123.0 0.0 0.00 5/18/1993 2.9 123.0 123.0 -1.0 -0.50 2/19/1993 3.0 124.0 124.0 0.0 0.00 11/19/1992 3.0 124.0 124.0 1.0 0.50 8/18/1992 3.0 123.0 123.0 0.0 0.00 5/18/1992 123.0 123.0 _
Basic Statistics for DPIS-2-117B Average x (psid) 0.1 Standard Deviation s (psid) 1.03 Variance s2 (psid) 1.06 Largest Positive Drift (psid) 4.5 Largest Negative Drift (psid) -2.0 Number of Samples n 69 Average X (%) 0.04 Standard Deviation s (%) 0.52 Largest Positive Drift (%) 2.25 Largest Negative Drift (%) -1.00
Cn Drift Trend Plot for DPIS-2-117B
-n
" 6 .0 -------
0) 2=0 (D CD,
"*0. 0
-2.0 st-6 4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/14/2005 9/9/2008 0 Date
- .DPIS-2-117B - - - +2s - - - -2s ODO3 0 0 CD L
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 19 of 123 Drift Data for DPIS-2-117C Calibration As- Drift Drift Date Interval Found As-Left (psid) (%)
(Months) 5/5/2008 3.0 .142.8 142.8 -0.6 -0.30 2/5/2008 2.7 143.4 143.4 0.1 0.05 11/15/2007 3.3 143.3 143.3 0.5 0.25 8/6/2007 3.0 142.8 142.8 -0.6 -0.30 5/7/2007 2.9 143.4 143.4 -0.6 -0.30 2/8/2007 3.1 144.0 144.0 0.8 0.40 11/6/2006 3.0 143.2 143.2 0.4 0.20 8/7/2006 3.0 142.8 142.8 -0.4 -0.20 5/8/2006 3.0 143.2 143.2 -0.2 -0.10 2/6/2006 3.2 143.4 143.4 -0.1 -0.05 10/31/2005 3.0 143.5 143.5 0.8 0.40 8/1/2005 3.0 142.7 142.7 -0.3 -0.15 5/2/2005 1.7 143.0 143.0 0.0 0.00 3/11/2005 1.3 143.0 143.0 -0.5 -0.25 1/31/2005 3.0 143.5 143.5 0.5 0.25 11/1/2004 3.0 143.0 143.0 0.0 0.00 8/2/2004 3.0 143.0 143.0 0.0 0.00 5/3/2004 3.0 143.0 143.0 0.0 0.00 2/2/2004 3.0 143.0 143.0 0.4 0.20 11/3/2003 3.0 142.6 142.6 -0.4 -0.20 8/4/2003 3.4 143.0 143.0 -0.5 -0.25 4/23/2003 2.6 143.5 143.5 -0.5 -0.25 2/3/2003 3,0 144.0 144.0 0.5 0.25 11/4/2002 3.0 143.5 143.5 0.5 0.25 8/5/2002 3.0 143.0 143.0 -0.5 -0.25 5/6/2002 3.0 143.5 143.5 -0.5 -0.25 2/4/2002 3.0 144.0 144.0 0.5 0.25 11/6/2001 2.9 143.5 143.5 0.5 0.25 8/10/2001 3.1 143.0 143.0 -0.5 -0.25' 5/7/2001 3.0 143.5 143.5 0.5 0.25 2/5/2001 3.0 143.0 143.0 -1.0 -0.50 11/6/2000 3.0 144.0 144.0 0.5 0.25 8/7/2000 3.0 143.5 143.5 0.0 0.00 5/9/2000 2.9 143.5 143.5 0.0 0.00 2/11/2000 0.7 143.5 143.5 -0.5 -0.25 1/21/2000 2A4 144.0 144.0 0.5 0.25 11/8/1999 3.0 143.5 143,5 0.5 0,25 8/9/1999 3.0 143.0 143.0 -1.0 -0.50 5/10/1999 3.0 144.0 144.0 2.0 1,00 2/8/1999 3.0 142.0 142.0 -2.0 -1.00 11/9/1998 1.3 144.0 144.0 1.0 0.50 9/30/1998 1.7 125.0 143.0 -0.5 -0.25 8/10/1998 3.0 125.5 125.5 0.5 0.25
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 20 of 123 5/12/1998 2.9 125.0 125.0 -1.0 -0.50 2/12/1998 3.0 126.0 126.0 0.0 0.00 11/11/1997 3.0 126.0 126.0 0.5 0.25 8/11/1997 1.4 125.5 125.5 -0.5 -0.25 6/30/1997 4.6 126.0 126.0 0.0 0.00 2/10/1997 3.0 126.0 126.0 0.0 0.00 11/1111996 3.0 126.0 126.0 1.5 0.75 8/13/1996 2.7 124.5 124.5 -2.5 -1.25 5/24/1996 3.3 127.0 127.0 0.5 0.25 2/13/1996 3.0 126.5, 126.5 0.3 0.15 11/13/1995 3.0 126.2 126.2 2.2 1.10 8/15/1995 3.0 124.0 124.0 -1.5 -0.75 5/15/1995 3.0 125.5 125.5 -0.5 -0.25 2/13/1995 3.0 126.0 126.0 1.0 0.50 11/15/1994 1.6 125.0 125.0 -0.5 -0.25 9/28/1994 1.4 125.5 125.5 0.5 0.25 8/15/1994 3.0 125.0 125.0 -0.5 -0.25 5/17/1994 3.0 125.5 125.5 0.5 0.25 2/15/1994 3.0 125.0 125.0 -1.0 -0.50 11/16/1993 3.0 126.0 126.0 1.0 0.50 8/17/1993 3.0 125.0 125.0 -1.0 -0,50 5/18/1993 2.9 126.0 126.0 -0.5 -0.25 2/19/1993 3.0 126.5 126,5 1.0 0.50 11/19/1992 3.0 125.5 125.5 0.5 0.25 8/18/1992 3.0 125.0 125.0 0.0 0.00 5/18/1992 125.0 125.0 Basic Statistics for DPIS-2-117C Average x (psid) 0.0 Standard Deviation s (psid) 0.80 Variance s2 (psid) 0.64 Largest Positive Drift (psid) 2.2 Largest Negative Drift (psid) -2.5 Number of Samples n 68 Average x()0.00 Standard Deviation s N% 0.40 Largest Positive Drift N% 1.10 Largest Negative Drift N% -1.25
r-I i-l
,m O-I Drift Trend Plot for DPIS-2-117C
- 4. 0 -~-
=0.0 CA, (D
> -2.0 Ci) 03
-4.0*....... .. C-)
CI-4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/14/2005 9/9/2008 50 Date CD0 0C
-. DPIS-2-117C +2s -2s
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 22 of 123 Drift Data for DPIS-2-117D Calibration As- Drift Drift Date Interval Found As-Left (psid)
(Months) 5/5/2008 3.0 140.5 140.5 -0.2 -0.10 2/5/2008 2.7 140.7 140.7 -0.6 -0.30 11/15/2007 3.3 141.3 141.3 1.4 0.70 8/6/2007 2.9 139.9 139.9 -1.0 -0.50 5/9/2007 3.0 140.9 140.9 -1.1 -0.55 2/8/2007 3.1 142.0 142.0 0.3 0.15 11/6/2006 3.0 141.7 141.7 2.4 1.20 8/7/2006 3.0 139.9 139.3 -1.1 -0.55 5/8/2006 3.0 141.0 141.0 0.2 0.10 C 2/6/2006 3.2 140.8 140.8 -0.7 -0.35 10/31/2005 3.0 141.5 141.5 1.7 0.85 8/1/2005 3.0 139.8 139.8 -0.7 -0.35 5/2/2005 1.6 140.5 140.5 -1.5 -0.75 3/13/2005 1.3 142.0 142.0 0.0 0.00 1131/2005 3.0 142.0 142.0 -0.5 -0.25 11/1/2004 3.0 142.5 142.5 2.0 1.00 8/2/2004 3.0 140.5 140.5 -0.5 -0.25 5/3/2004 3.0 141.0 141.0 -1.0 -0.50 2/2/2004 3.0 142.0 142.0 0.5 0.25 11/3/2003 3.0 141.5 141.5 0.5 0.25 8/4/2003 3.4 141.0 141.0 -1.0 -0.50 4/23/2003 2.6 142.0 142.0 0.0 0.00 2/3/2003 3.0 142.0 142.0 0.5 0.25 11/4/2002 3.0 141.5 141.5 1.5 0.75 8/5/2002 3.0 140.0 140.0 -1.0 -0.50 5/6/2002 3.0 141.0 141.0 -0.5 -0.25 2/4/2002 3.0 141.5 141.5 -1.0 -0.50 11/6/2001 2.9 142.5 142.5 1.5 0.75 8/10/2001 3.1 141.0 141.0 -1.0 -0.50 5/7/2001 3.0 142.0 142;0 1.0 0.50 2/5/2001 3.0 141.0 141.0 -1.0 -0.50 11/6/2000 3.0 142.0 142.0 1.0 0.50 8/7/2000 3.0 141.0 141.0 -0.5 -0.25 5/9/2000 2.9 141.5 141.5 -0.5 -0.25 2/11/2000 0.7 142.0 142.0 -1.0 -0.50 1/22/2000 2.5 143.0 143.0 2.0 1.00 11/8/1999 3.0 141.0 141.0 -1.5 -0.75 8/9/1999 3.0 142.5 142.5 0.5 0.25 5/10/1999 3.0 142.0 142.0 0.5 0.25 2/8/1999 3.0 141.5 141.5 -1.5 -0.75 11/9/1998 1.3 143.0 143.0 0.0 0.00 9/30/1998 1.7 122.5 143.0 0.5 0.25 8/10/1998 3.0 122.0 122.0 -1.0 -0.50
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 23 of 123 5/12/1998 2.9 123.0 123.0 1.0 0.50 2/12/1998 3.0 122.0 122.0 -0.5 -0.25 11/11/1997 3.0 122.5 122.5 1.0 0.50 8/11/1997 1.4 121.5 121.5 -1.5 -0.75 6/30/1997 4.6 123.0 123.0 0.0 0.00 2/10/1997 3.0 123.0 123.0 0.2 0.10 11/11/1996 3.0 122.8 122.8 1.3 0.65 8/13/1996 2.7 121.5 121.5 -2.0 -1.00 5/24/1996 3.3 123.5 123.5 1.5 0.75 2/13/1996 3.0 122.0 122.0 -1.6 -0.80 11/13/1995 3.0 123.6 123.6 1.6 0.80
,8/15/1995 3.0 122.0 122.0 -0.5 -0.25 5/15/1995 3.0 122.5 122.5 -1.5 -0.75 2/13/1995 3.0 124.0 124.0 1.0 0.50 11/15/1994 1.5 123.0 123.0 0.5 0.25 9/29/1994 1.5 122.5 122.5 0.5 0.25 8/15/1994 3.0 122.0 122.0 -1.5 -0.75 5/17/1994 3.0 123.5 123.5 0.5 0.25 2/15/1994 3.0 123.0 123.0 0.0 0.00 11/16/1993 3.0 123.0 123.0 0.5 0.25 8/17/1993 3.0 122.5 122.5 -1.5 -0.75 5/18/1993 2.9 124.0 124.0 1,0 0.50 2/19/1993 3.0 123.0 123.0 -1.0 -0.50 11/19/1992 3.0 124.0 124.0 1.0 0.50 8/18/1992 3.0 123.0 123.0 1.0 0.50 5/18/1992 122.0 122.0 Basic Statistics for DPIS-2-117D Average x (psid) 0.0 Standard Deviation s (psid) 1.08 Variance s (psid) 1.17 Largest Positive Drift (psid) 2.4 Largest Negative Drift (psid) -2.0 Number of Samples n 68 Average x (%) -0.01 Standard Deviation s (%) 0.54 Largest Positive Drift (%) 1.20 Largest Negative Drift (%) -1.00
-I I-m 0 rn Drift Trend Plot for DPIS-2-117D r-
-I A)
.4'
- "4.0 C, rn A) "-I S2.0 U) 30
=0.0 cn 0
A)
> -2.0 0.
U) 0 64.0 0 Cl) 4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/14/2005 9/9/2008 Date
-.-- DPIS-2-117D - . =+2s . 2s C)
ID 0,
CD 0
- 0 0
6.
0' 41
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 25 of 123 Drift Data for DPIS-2-118A Calibration Drift Drift Date Interval (Mnh)'Found FoAs- As-Left Drift (psid) (%)
(Months) 5/5/2008 3.0 140.3 140.3 -- 0.3 -0.15 2/4/2008 2.7 140.6 140.6 -0.5 -0.25 11/15/2007 3.3 141.1 141.1 1.1 0.55 8/6/2007 3.0 140.0 140.0 -0.3 -0.15 5/7/2007 2.9 140.3 140.3 -1.3 -0.65 2/8/2007 3.1 141.6 141.6 1.2 0.60 11/6/2006 3.0 140.4 140.4 0.2 0.10 8/7/2006 3.0 140.2 140.2 -0.1 -0.05 5/8/2006 3.0 140.3 140.3 -0.1 -0.05 2/6/2006 3.2 140.4 140.4 -0.4 -0.20 10/31/2005 3.0 140.8 140.8 1.5 0.75 8/1/2005 3.0 139.3 139.3 -0.8 -0.40 5/2/2005 1:7 140.1 140.1 0.1 0.05 3/11/2005 1.3 140.0 140.0 -1.0 -0.50 1/31/2005 3.0 141.0 141.0 0.0 0,00 11/1/2004 3.0 141.0 141.0 0.5 0.25 8/2/2004 3.0 140.5 140.5 0.0 0.00 5/3/2004 3.0 140.5 140.5 -1.0 -0.50 2/2/2004 3.0 141.5 141.5 0.9 0.45 11/3/2003 3.0 140.6 140.6 0.1 0.05 8/4/2003 3.4 140.5 140.5 0.0 0.00 4/23/2003. 2.6 145.0 140.5 0.5 0.25 2/3/2003 3.0 144.5 144.5 -1.0 -0.50 11/4/2002 3.0 145.5 145.5 1.0 0.50 8/5/2002 3.0 144.5 144.5 0.0 0.00 5/6/2002 3.0 144.5 144.5 -1.0 -0.50 2/4/2002 3.0 145.5 145.5 0.5 0.25 11/6/2001 2.9 145.0 145.0 0.0 0.00 8/10/2001 3.1 145.0 145.0 0.0 0.00 5/7/2001 3.0 145.0 145.0 0.0 0.00 2/5/2001 3.0 145.0 145.0 -0.5 -0.25 11/6/2000 3.0 145.5 145.5 0.5 0.25 8/7/2000 3.0 145.0 145.0 -0.5 -0.25 5/9/2000 2.9 145.5 145.5 1.0 0.50 2/11/2000 0.7 144.5 144.5 -1.5 -0.75 1/20/2000 2.4 146.0 146.0 0.5 0.25 11/8/1999 3.0 145.5 145.5 0.5 0.25 8/9/1999 3.0 145.0 145.0 -0.5 -0.25 5/10/1999 3.0 145.5 145.5 1.0 0.50 2/8/1999 3.0 144.5 144.5 -1.0 -0.50 11/9/1998 1.3 145.5 145.5 1.0 0.50 9/30/1998 1.7 127.0 144.5 0.0 0.00 8/10/1998 3.0 127.0 127.0 0.0 0.00
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 26 of 123 5/12/1998 1 2.9 127.0 127.0 0.0 0.00 2/12/1998 3.0 127.0 127.0 0.0 0.00 11/11/1997 3.0' 127.0 127.0 0.5 0,25 8/11/1997 1.4 126.5 126.5 -0.5 -0.25 6/30/1997 4.6 127.0 127.0 0.0 0.00 2/10/1997 3.0 127.0 127.0 -1.0 -0.50 11/11/1996 3.0 128.0 128.0 1.0 0.50 8/13/1996 '2.7 127.0 127.0 -1.5 -0.75 5/24/1996 3.3 128.5 128.5 1.5 , 0.75 2/13/1996 3.0 127.0 127.0 0.0 0.00 11/13/1995 3.0 127.0 127,0 1.0 0.50 8/15/1995 3.0 126.0 126.0 -1.0 -0.50 5/15/1995 3.0 127.0 127.0 -1.0 -0.50 2/13/1995 3.0 128.0 128.0 1.0 0.50 11/15/1994 1.6 127.0 127.0 0.0 0.00 9/27/1994 1.4 127.0 127.0 0.0 0.00 8/15/1994 3.0 127.0 127.0 -1.0 -0.50 5/17/1994 3.0 128.0 128.0 1.0 0.50 2/15/1994 3.0 127.0 127.0 0.5 0.25 11/16/1993 3.0 126.5 126,5 -0.5 -0.25 8/17/1993 3.0 127.0 127.0 0.0 0.00 5/18/1993 2.9 127.0 127.0 -0.5 -0.25 2/19/1993 3.0 127.5 127.5 0.0 0.00 11/19/1992 3.0 127.5 127.5 0.5 0.25 8/18/1992 3.0 127.0 127.0 0.0 0.00 5/18/1992 127.0 127.0 Basic Statistics for DPIS-2-118A Average x (psid) 0.0 Standard Deviation s (psid) 0.74 Variance s2 (psid) 0.54 Largest Positive Drift (psid) 1.5 Largest Negative Drift (psid) -1,5 Number of Samples n 68 Average x (%) 0.00 Standard Deviation s (%) 0.37 Largest Positive Drift (%) 0.75 Largest Negative Drift (%) -0.75
m 0 0
hi Drift Trend Plot for DPIS-2-118A
- " 2.0 1.0 "0.0
-1.0 01 (31 i*-2.0 0.0 4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/14/2005 9/9/2008 Date
+2s - 2s I s- DPIS-2-118A - -
(0 > CD S
S2.
CDO 0
=3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 28 of 123 Drift Data for DPIS-2-118B Calibration Clbain As As- Drift Drift Date Interval (Mnh) Found As-Left Drift (psid) Drf
(%)
(Months) 5/5/2008 3.0 141.9 141.9 0.0 0.00 2/5/2008 2.7 141.9 141.9 -0.1 -0.05 11/15/2007 3.3 142.0 142.0 0.2 0.10 8/6/2007 3.0 141.8 141.8 -0.2 -0.10 5/7/2007 2.9 142.0 142.0 -1.1 -0.55 2/8/2007 3.1 143.1 143.1 0.7 0.35 1116/2006 3.0 142.4 142.4 0.8 0.40 8/7/2006 3.0 141.6 141.6 -0.6 -0.30 5/8/2006 3.0 142.2 142.2 0.1 0.05 2/6/2006 3.2 142.1 142.1 -0.1 -0.05 10/31/2005 3.0 142.2 142.2 0.2 0.10 8/1/2005 3.0 142.0 142.0 -0.3 -0.15 5/2/2005 1.7 142.3 142.3 -0.2 -0.10 3/12/2005 1.3 142.5 142.5 0.0 0.00 1/31/2005 3.0 142.5 142.5 0.0 0.00 11/1/2004 3.0 142.5 142.5 0.5 0.25 8/2/2004 3.0 142.0 142.0 -0.5 -0.25 5/3/2004 3.0 142.5 142.5 0.0 0.00 2/2/2004 3.0 142.5 142.5 0.0 0.00 11/3/2003 3.0 142.5 142.5 0.0 0.00 8/4/2003 3.4 142.5 142.5 0.0 0.00 4/23/2003 2.6 144.0 142.5 0.0 0.00 2/3/2003 3.0 144.0 144.0 0.0 0.00 11/4/2002 3.0 144.0 144.0 0.5 0.25 8/5/2002 3.0 143.5 143.5 -0.5 -0.25 5/6/2002 3.0 144.0 144.0 -1.0 -0.50 2/4/2002 3.0 145.0 145.0 1.0 0.50 11/6/2001 2.9 144.0 144.0 0.0 0.00 8/10/2001 3.1 144.0 144.0 -1.0 -0.50 5/7/2001 3.0 145.0 145.0 0.5 0.25 2/5/2001 3.0 144.5 144.5 -0.5 -0.25 11/6/2000 3.0 145.0 145.0 0.5 0.25 8/7/2000 3.0 144.5 144.5 0.0 0.00 5/9/2000 2.9 144.5 144.5 -1.5 -0.75 2/11/2000 0.7 146.0 146.0 1.0 0.50 1/21/2000 2.4 145.0 145.0 0.0 0.00 11/8/1999 3.0 145.0 145.0 0.0 0.00 8/9/1999 3.0 145.0 145.0 0.0 0.00 5/10/1999 3.0 145.0 145.0 0.0 0.00 2/8/1999 3.0 145.0 145.0 0.5 0.25 11/9/1998 1.3 144.5 144.5 0.5 0.25 9/30/1998 1.7 125.0 144.0 0.5 0.25 8/10/1998 3.0 124.5 124.5 -0.5 -0.25
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 29 of 123 5/12/1998 2.9 125.0 125.0 -1.0 -0.50 2/12/1998 3.0 126.0 126.0 -1.0 -0.50 11/11/1997 3.0 127.0 127.0 1.5 0.75 8/11/1997 1.4 125.5 125.5 0.0 0.00 6/30/1997 4.6 125.5 125.5 0.0 0.00 2/10/1997 3.0 125.5 125.5 0.5 0.25 11/11/1996 3.0 125.0 125.0 0.5 0.25 8/13/1996 2.7 124.5 124.5 -1.5 -0.75 5/24/1996 3.3 126.0 126.0 0.5 0.25 2/13/1996 3.0 125.5 125.5 1.0 0.50 11/13/1995 3.0 124.5 124.5 -0.5 -0.25 8/15/1995 3.0 125.0 125.0 0.0 0.00 5/15/1995 3.0 125.0 125.0 0.0 0.00 2/13/1995 3.0 125.0 125.0 0.0 0.00 11/15/1994 1.5 125.0 125.0 0.0 0.00 9/29/1994 1.5 125.'0 125.0 0.5 0.25 8/15/1994 3.0 124.5 124.5 -1.0 -0.50 5/17/1994 3.0 125.5 125.5 0.5 0.25 2/15/1994 3.0 125.0 125.0 0.0 0.00 11/16/1993 3.0 125.0 125.0 0.0 0.00 8/17/1993 3.0 125.0 125.0 0.0 0.00 5/18/1993 2.9 125.0 125.0 -1.0 -0.50 2/19/1993 3.0 126.0 126.0 1.0 0.50 11/19/1992 3.0 125.0 125.0 0.5 0.25 8/18/1992 3.0 124.5 124.5 0.5 0.25 5/18/1992 124.0 124.0 Basic Statistics for DPIS-2-118B Average x (psid) 0.0 Standard Deviation s (psid) 0.60 Variance s2 (psid) 0.37 Largest Positive Drift (psid) 1.5 Largest Negative Drift (psid) -1.5 Number of Samples n 68 Average x (%) 0.00 Standard Deviation s (%) 0.30 Largest Positive Drift (%) 0.75 Largest Negative Drift (%) -0.75
CA Drift Trend Plot for DPIS-2-118B
- -2.0- 03 S1.0 ~.cn
-0 P.O.
4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/1 4/2005 9/9/2008 Date
- DPIS-2-118B - - +2s - - - -2s CD (0 w)
CDO0 0
63
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 31 of 123 Drift Data for DPIS-2-118C Calibration Clbain As- Drift Drift Date Interval (Mnh) As-Found As-Left Drift (psid) D(%)
(Months) 5/5/2008 3.0 142.6 142.6 0.1 0.05 2/5/2008 2.7 142.5 142.5 0.6 0.30 11/15/2007 3.3 141.9 141.9 0.3 0.15 8/6/2007 3.0 141.6 141.6 0.0 0.00 5/7/2007 2.9 141.6 141.6 -0.8 -0.40 2/8/2007 3.1 142.4 142.4 0.4 0.20 11/6/2006 3.0 142.0 142.0 0.5 0.25 8/7/2006 3.0 141.5 141.5 -0.6 -0.30 5/8/2006 3.0 142.1 142.1 0.4 0.20 2/6/2006 3.2 141.7 141.7 -0.2 -0.10 10/31/2005 3.0 141.9 141.9 0.7 0.35 811/2005 3.0 141.2 141.2 -0.3 -0.15 5/2/2005 1.7 141.5 141.5 -0.5 -0.25, 3/11/2005 1.3 142.0 142'.0 -0.5 -0.25 1/31/2005 3.0 142.5 142.5 0.0 0.00 11/1/2004 3.0 142.5 142.5 0.5 0.25 8/2/2004 3.0 142.0 142.0 0.5 0.25 5/3/2004 3.0 141.5 141.5 -0.5 -0.25 2/2/2004 3.0 142.0 142.0 0.5 0.25 11/3/2003 3.0 141.5 141.5 0.0 0.00 8/4/2003 .3.4 141.5 141.5 -0.5 -0.25 4/23/2003 2.6 144,0 142.0 -1.0 -0.50 2/3/2003 3.0 145.0 145.0 0.0 0.00 11/4/2002 3.0 145.0 145.0 0.5 0.25 8/5/2002 3.0 144.5 144.5 0.5 0.25 5/6/2002 3.0 144.0 144.0 -1.0 -0.50 2/4/2002 3.0 145.0 145.0 0.0 0.00 11/6i2001 2.9. 145.0 145.0 0.5 0.25 8/10/2001 3.1 144.5 144.5 -0.5 -0.25 5/7/2001 3.0 145.0 145.0 0.0 0.00 2/5/2001 3.0 145.0 145.0 0.0 0.00 11/6/2000 3.0 145.0 145.0 0.5 0.25 8/7/2000 3.0 144.5 144.5 0.0 0.00 5/9/2000 2.9 144.5 144.5 0.0 0.00 2/11/2000 0.7 144.5 144.5 -1.0 -0.50 1/21/2000 2.4 145.5 145.5 1.5 0.75 11/8/1999 310 144.0 144.0 -0.5 -0.25 8/9/1999 3.0 144.5 144.5 -0.5 -0.25 5/10/1999 3.0 145.0 145.0 -0.3 -0.15 2/8/1999 3.0 145.3 145.3 -0.2 -0.10 11/9/1998 1.3 145.5 145.5 1.5 0.75 9/30/1998 1.7 126.0 144.0 0.5 0.25 8/10/1998 3.0 125.5 125.5 -0.5 -0.25
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 32 of 123 5/12/1998 2.9 126.0 126.0 0.0 0.00 2/12/1998 3.0 126.0 126.0 0.0 0.00 11/11/1997 3.0 126.0 126.0 0.0 0.00 8/11/1997 1.4 126.0 126.0 0.0 0.00 6/30/1997 4.6 126.0 126.0 0.0 0.00 2/10/1997 3.0 126.0 126.0 0.0 0.00 11il 11/1996 3.0 126.0 126.0 0.5 0,25 8/13/1996 2.7 125.5 125.5 -1.5 -0.75 5/24/1996 3.3 127.0 127.0 0.5 0.25 2/13/1996 3.0 126.5 126.5 0.1 0.05 11/13/1995 3.0 126.4 126.4 1.4 0.70 8/15/1995 3.0 125.0 125.0 -1.0 -0.50 5/15/1995 3.0 126.0 126.0 0.0 0.00 2/13/1995 3.0 126.0 126.0 0.0 0.00 11/15/1994 1.6 126.0 126.0 0.0 0.00 9/28/1994 1.4 126.0 126.0 1.0 0.50 8/15/1994 3.0 125.0 125.0 -0.5 -0.25 5/17/1994 3.0 125.5 125.5 0.5 0.25 2/15/1994 3.0 125.0 125.0 -0.5 -0.25 11/16/1993 3.0 125.5 125.5 -0.5 -0.25 8/17/1993 3.0 126.0 126.0 0.0 0.00 5/18/1993 2.9 126.0 126.0 -1.0 -0.50 2/19/1993 3.0 127.0 127.0 1.0 0.50 11/19/1992 3.0 126.0 126.0 0.0 0.00 8/18/1992 3.0 126.0 126.0 0.5 0.25 5/18/1992 125.5 125.5 Basic Statistics for DPIS-2-118C Average x (psid) 0.0 Standard Deviation s (psid) 0.60 Variance s2 (psid) 0.36 Largest Positive Drift (psid) 1.5 Largest Negative Drift (psid) -1.5 Number of Samples n 68 Average X (%) 0.01 Standard Deviation s (%) 0.30 Largest Positive Drift (%) 0.75 Largest Negative Drift (%) -0.75
0 I-.
0 Drift Trend Plot for DPIS-2-118C I
,G) 20 _n r
"*. 0.0 ,ii*
- iik ~i~!*~
.iii]ii*ii£ cn -
1.0 0.0I 4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/14/2005 9/9/2008 t-Date 0 - -
-1.
-.- DPIS-2-118C =. - = +2s =- - - -2s n-
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I DriftAn'alysis Spreadsheets' Attachment 3 Page 34 of 123 Drift Data for DPIS-2-118D Calibration *As- Drift Drift Date InterVal (Mnts) Found As-Left (psid) N%
(Months) 5/5/2008 3.0 141.8 141.8 0.4 0.20 2/5/2008 2.7 141.4 141.4 -0.6 -0,30 11/15/2007 3.3 142.0 142.0 0.0 0.00 8/6/2007 2.9 142.0 142.0 0.1- 0.05 5/9/2007 3.0 141.9 141.9 0.1 .0.05 2/8/2007 3.1 141.8 141.8 0.0 0.00 11/6/2006 3.0 141.8 141.8 0.0 0.00 8/7/2006 3.0 138.1 141.8 -0.9 -0.45 5/8/2006 3.0 139.0 139.0 0.2 0.10 2/6/2006 3.2 138.8 138.8 -0.5 -0.25' 10/31/2005 3.0 139.3 139.3 0.7 0.35 8/1/2005 3.0 138.6 138.6 -0.9 -0.45 5/2/2005 1.6 139.5 139.5 0.5 0.25 3/13/2005 1.3 139.0 139.0 0.0 0.00 1/31/2005 3.0 139.0 139.0 -0.5 -0.25 11/1/2004 3.0 139.5 139.5 1.0 0.50 8/2/2004 3.0 138.5 138.5 0.0 0.00 5/3/2004 3.0 138.5 138.5 -1.0 -0.50 2/2/2004 3.0 139.5 139.5 0.5 0.25 11/3/2003 3.0 139.0 139.0 -1.0 -0.50 8/4/2003 3.4 140.0 140.0 1.0 0.50 4/23/2003 2.6 139.0 139.0 0.0 0.00 2/3/2003 3.0 139.0 139.0 -1.0 -0.50 11/4/2002 3.0 140.0 140.0 1.0 0.50 8/5/2002 3.0 .139.0 139.0 -0.5 -0.25 5/6/2002 3.0 139.5 139.5 -0.5 -0.25 2/4/2002 3.0 140.0 140.0 0.0 0.00 11/6/2001 2.9 140.0 140.0 0.0 0.00 8/10/2001 3.1 140.0 140.0 -0.5 -0.25 5/7/2001 320 140.5 140.5 0.5 0.25 2/5/2001 3.0 140.0 140.0 -0.5 -0.25 11/6/2000 3.0 140.5 140.5 0.5 0.25 8/7/2000 3.0 140.0 140.0 -1.0 -0.50 5/9/2000 2.9 141.0 141.0 0.0 0.00 2/11/2000 0.7 141.0 141.0 -1.0 -0.50 1/22/2000 2.5 142.0 142.0 2.0 1.00 11/8/1999 3.0 140.0 140.0 -1.0 -0.50 8/9/1999 3.0 141.0 141.0 0.0 0.00 5/10/1999 3.0 141.0 141.0 0.5 0.25 2/8/1999 3.0 140.5 140.5 -1.0 -0.50 11/9/1998 1.3 141.5 141.5 0.5 0.25 9/30/1998 1.7 124.0 141.0 0.5 0.25 8/10/1998 3.0 123.5 123.5 -0.5 -0.25
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 3 Drift Analysis Spreadsheets *
- Attachment 3 Page 35 of 123 5112/1998 2.9 124.0 124.0 -0.5 -0.25 2/12/1998 3.0 124.5 124.5 0.5 0.25 11/11/1997 3.0 124.0 124.0 1.0 0.50 8/11/1997 1.4 123.0 123.0 -1.0 -0.50 6/30/1997 4.6 124.0 124.0 0.0 0.00 2/10/1997 3.0 124.0 124.0 0.0 0.00 1111111996 3.0 124.0 124.0 0.5 0.25 8/13/1996 2.7 123.5 123.5 -1.5 -0.75 5/24/1996 3.3 125.0 125.0 0.0 0.00 2/13/1996 3.0 125.0 125.0 -1.5 -0.75 11/13/1995 3.0 126.5 126.5 1.5 0.75 8/15/1995 3.0 125.0 125.0 1.0 0.50 5/15/1995 3.0 124.0 124.0 -1.0 -0.50 2/13/1995 3.0 125.0 125.0 1.0 0.50 11/15/1994 1.5 124.0 124.0 -2.0 -1.00 9/29/1994 1.5 125.5 126.0 1.5 0.75 8/15/1994 3.0 124.0 124.0 1.0 0.50 5/17/1994 3.0 123.0 123.0 -1.0 -0.50 2/15/1994 3.0 124.0 124.0 0.5 -0.25 11/16/1993 3.0 123.5 123.5 -3.5 -1.75 8/17/1993 3.0 127.0 127.0 2.0 1.00 5/18/1993 2.9 125.0 125.0 "2.0 1.00 2/19/1993 3.0 123.0 123.0 0.5 0.25 11119/1992 3.0 122.5 122.5 -2.0 -1.00 8/18/1992 3.0 124.5 124.5 1.0 0.50 5/18/1992 123.5 123.5 Basic Statistics for DPIS-2-118D Average x (psid) 0.0 Standard Deviation s (psid) 1.00 Variance S2 (psid) 0.99 Largest Positive Drift (psid) 2.0 Largest Negative Drift (psid) -3.5 Number of Samples n 68 Average X (%) -0.02 Standard Deviation s (%) 0.50 Largest Positive Drift (%) 1.00 Largest Negative Drift (%) -1.75
0 0
hi I-I-.
0 0
Drift Trend Plot for DPIS-2-118D h hi C) hi
-. 4.0- I-pp hi W.2.O -
U) C) 0*-.0- -o
> 1k (A-0 -I
"- 2 c,.3
,,, -4.0 f-9 4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/1 4/2005 9/9/2008 Date DPIS-2-118D - - -+2s -. 2s 0
CD S. (0 rou CA 0I 0
0, (0)
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 37 of 123 Drift Data for DPIS-2-1 19A Calibration Date Interval As- As-Left Drift Drift (Months) Found (psid) (%)
5/5/2008 3.0 141.2 141.2 -0.2 -0.10 2/5/2008 0.0 141.4 141.4 -0.1 -0.05 2/4/2008 2.7 141.5 141.5 -0.5 -0.25 11/15/2007 3.3 142.0 142.0 0.8 0.40 8/6/2007 3.0 141.2 141.2 -0.9 -0.45 5/7/2007 2.9 142.1 142.1 0.1 0.05 2/8/2007 3.1 142.0 142.0 0.6 0.30 11/6/2006 3.0 141.4 141.4 0.2 0.10 8/7/2006 3.0 141.2 141.2 0.0 0.00 5/8/2006 3.0 141.2 141.2 -0.1 -0.05 2/6/2006 3.2 141.3 141.3 -0.8 -0.40 10/31/2005 3.0 142.1 142.1 1.5 0.75 8/1/2005 3.0 140.6 140.6 -1.4 -0.70 5/2/2005 1.7 142.0 142.0 0.5 0.25 3/11/2005 1.3 141.5 141.5 0.0 0.00 1/31/2005 3.0 141.5 141.5 -0.5 -0.25 11/1/2004 3.0 142.0 142.0 1.0 0.50 8/2/2004 1.4 141.0 141.0 -0.5 -0.25 6/20/2004 1.6 144.0 141.5 0.5 0.25 5/3/2004 3.0 144.0 143.5 0.5 0.25 2/2/2004 3.0 144.5 143.5 1.3 0.65 11/3/2003 3.0 143.2 143.2 -0.3 -0.15 8/4/2003 3.4 143.5 143.5 0.2 0.10 4/23/2003 2.6 143.3 143.3 -0.7 -0.35 2/3/2003 3.0 144.0 144.0 0.5 0.25 11/4/2002 3.0 143.5 143.5 0.5 0.25 8/5/2002 3.0 143.0 143.0 0.0 0.00 5/6/2002 3.0 143.0 143.0 -1.5 -0.75 2/4/2002 3.0 144.5 144.5 1.5 0.75 11/6/2001 2.9 143.0 143.0 -0.5 -0.25 8/10/2001 3.1 143.5 143.5 0.0 0.00 5/7/2001 3.0 143.5 143.5 0.0 0.00 2/5/2001 3.0 143.5 143.5 -0.5 -0.25 11/6/2000 3.0 144.0 144.0 0.5 0.25 8/7/2000 3.0 143.5 143.5 -1.0 -0.50 5/9/2000 2.9 144.5 144.5 1.0 0.50 2/11/2000 0.7 143.5 143.5 -1.0 -0.50 1/20/2000 2.4 144.5 144.5 1.0 0.50 11/8/1999 3.0 143.5 143.5 0.0 0.00 8/9/1999 3.0 143.5 143.5 -1.0 -0.50 5/10/1999 3.0 144.5 144.5 1.0 0.50 2/8/1999 3.0 143.5 143.5 -0.5 -0.25 11/9/1998 1.3 144.0 144.0 1.0 0.50
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 38 of 123 9/30/1998 1.7 122.0 143.0 0.0 0.00 8/10/1998 3.0 122.0 122.0 0.0 0.00 5/12/1998 2.9 122.0 122.0 -0.5 -0.25 2/12/1998 3.0 122.5 122.5 -0.5 -0.25 11/11/1997 3.0 123.0 123.0 1.0 0.50 8/11/1997 1.4 122.0 122.0 -1.0 -0.50 6/30/1997 4.6 123.0 123.0 0.0 0.00 2/10/1997 3.0 123.0 123.0 0.5 0.25 11/11/1996 3.0 122.5 122.5 0.5 0.25 8/13/1996 2.7 122.0 122.0 -2.5 -1.25 5/24/1996 3.3 124.5 124.5 1.0 0.50 2/13/1996 3.0 123.5 123.5 1.2 0.60 11/13/1995 3.0 122.3 122.3 -0.7 -0.35 8/15/1995 3.0 123.0 123.0 0.5 0.25 5/15/1995 3.0 122.5 122.5 -0.5 -0.25 2/13/1995 3.0 123.0 123.0 0.0 0.00 11/15/1994 1.6 123.0 123.0 0.0 0.00 9/27/1994 1.4 123.0 123.0 0.5 0.25 8/15/1994 3.0 122.5 122.5 -1.0 -0.50 5/17/1994 3.0 123.5 123.5 0.5 0.25 2/15/1994 3.0 123.0 123.0 1.0 0.50 11/16/1993 3.0 122.0 122.0 -1.0 -0.50 8/17/1993 3.0 123.0 123.0 -1.0 -0.50 5/18/1993 2.9 124.0 124.0 0.0 0.00 2/19/1993 3.0 124.0 124.0 1.0 0.50 11/19/1992 3.0 123.0 123.0 0.0 0.00 8/18/1992 3.0 123.0 123.0 1.0 0.50 5/18/1992 122.0 122.0 Basic Statistics for DPIS-2-119A Average x (psid) 0.0 Standard Deviation s (psid) 0.80 Variance s2 (psid) 0.63 Largest Positive Drift (psid) 1.5 Largest Negative Drift (psid) -2.5 Number of Samples n 70 Average x (%) 0.02 Standard Deviation s (%) 0.40 Largest Positive Drift (%) 0.75 Largest Negative Drift (%) -1.25
-I R.
rri
~.CD
> 0)
G)
(A' CD-CL0
-0 cl*1 eID se:
IDO 0
ýi
- C3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 40 of 123 Drift Data for DPIS-2-119B Calibration Clbain As As- Drift Drift Date Interval (Mnh) Found As-Left Drift (psid) D(%)
(Months) 5/5/2008 3.0 141.6 141.6 -0.1 -0.05 2/5/2008 2.7 141.7 141.7 -0.5 -0.25 11/15/2007 3.3 142.2 142.2 1.1 0.55 8/6/2007 3.0 141.1 141.1 -1.2 -0.60 5/7/2007 2.9 142.3 142.3 -0.5 -0.25 2/8/2007 3.1 142.8 142.8 0.8 0.40 11/6/2006 3.0 142.0 142.0 0.7 0.35 8/7/2006 3.0 141,3 141.3 -0.8 -0.40 5/8/2006 3.0 142.1 142.1 0.4 0.20 2/6/2006 3.2 141.7 141.7 -0.5 -0.25 10/31/2005 3.0 142.2 142.2 1.1 0.55 8/1/2005 3.0 141.1 141.1 -0.4 -0.20 5/2/2005 1.6 141.5 141.5 -0.5 -0.25 3/13/2005 1.3 142.0 142.0 0.0 0.00 1/31/2005 3.0 142.0 142.0 0.0 0.00 11/1/2004 3.0 142.0 142.0 0.5 0.25 8/2/2004 3.0 141.5 141.5 0.0 0.00 5/3/2004 3.0 141.5 141.5 -0.5 -0.25 2/2/2004 3.0 142.0 142.0 0.5 0.25 11/3/2003 3.0 141.5 141.5 -0.5 -0.25 8/4/2003 3.4 142.0 142.0 0.5 0.25 4/23/2003 2.6 141.5 141.5 0.0 0.00 2/3/2003 0.3 141.5 141.5 -1.0 -0.50 1/24/2003 2.7 146.0 142.5 3.5 1.75 11/4/2002 3.0 148.0 142.5 3.0 1.50 8/5/2002 3.0 149.0 145.0 4.0 2.00 5/6/2002 3.0 145.0 145.0 0.0 0.00 2/4/2002 3.0 145.0 145.0 -1.0 -0.50 11/6/2001 2.9 146.0 146.0 1.5 0.75 8/10/2001 0.0 144.5 144.5 0.0 0.00 8/10/2001 3.1 144.5 144.5 0.5 0.25 5/7/2001 3.0 144.0 144.0 -1.0 -0.50 2/5/2001 3.0 145.0 145.0 1.0 0.50 11/6/2000 3.0 144.0 144.0 1.0 0.50 8/7/2000 3.0 143.0 143.0 -1.0 -0.50 5/9/2000 2.9 144.0 144.0 -0.5 -0.25 2/11/2000 0.7 144.5 144.5 -0.5 -0.25 1/21/2000 2.4 145.0 145.0 -0.5 -0.25 11/8/1999 3.0 145.5 145.5 2.0 1.00 8/9/1999 3.0 143.5 143.5 -0.5 -0.25 5/10/1999 3.0 144.0 144.0 0.5 0.25 2/8/1999 3.0 143.5 143.5 0.0 0.00 11/9/1998 1.3 143.5 143.5 0.5 0.25
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 41 of 123 9130/1998 1 1.7 126.0 143.0 0.5 0.25 8/10/1998 3.0 125.5 125.5 -0.5 -0.25 5/12/1998 2.9 126.0 126.0 -0.5 -0.25 2/12/1998 3.0 126.5 126.5 0.5 0.25 11/11/1997 3.0 126.0 126.0 0.0 0.00 8/11/1997 1.4 126.0, 126.0 0.0 0.00 6/30/1997 4.6 126.0 126.0 0.0 0.00 2/10/1997 3.0 126.0 126.0 0.0 0.00 11/11/1996 3.0 126.0 126.0 2.0 1.00 8/13/1996 2.7 124.0 124.0 -3.0 -1.50 5/24/1996 3.3 127.0 127.0 1.0 0.50 2/13/1996 3.0 126.0 126.0 -0.3 -0.15 11/13/1995 3.0 126.3 126.3 0.3 0.15 8/15/1995 3.0 126.0 126.0 0.5 0.25 5115/1995 3.0 125.5 125.5 -1.0 -0.50 2/13/1995 3.0 126.5 126.5 0.5 0.25 11/15/1994 1.5 126.0 126.0 0.0 0.00 9/29/1994 1.5 126.0 126.0 0.0 0.00 8/15/1994 3.0 126.0 126.0 -1.0 -0.50 5/17/1994 3.0 127.0 127;0 1.0 0.50 2/15/1994 3.0 126.0 126.0 -0.5 -0.25 11/16/1993 3.0 126.5 126.5 1.5 0.75 8/17/1993 3.0 125.0 125.0 -2.0 -1.00 5/18/1993 2.9 127.0 127.0 0.0 0.00 2/19/1993 3.0 127.0 127.0 0.5 0.25 11/19/1992 3.0 126.5 126.5 1.0 0.50 8/18/1992 3.0 125.5 125.5 0.0 0.00 5/18/1992 125.5 125.5 Basic Statistics for DPIS-2-119B Average x (psid) 0.2 Standard Deviation s (psid) 1.10 Variance s2 (psid) 1.21 Largest Positive Drift (psid) 4.0 Largest Negative Drift (psid) " -3.0 Number of Samples n 70 Average x (%) 0.09 Standard Deviation s (%) 0.55 Largest Positive Drift (%) 2.00 Largest Negative Drift (%) -1.50
--I 0
.m 0
rrn G)
CD I-I.-
- 0) 0
- 0. 0 6
CD CD0 0
0 Do
MONTICELLO NUCLEAR GENERA TING PLANT CA-95-075 Revision I TITLE: Main Steam Line High Flow Setpoint Drift Analysis Spreadsheets Attachment 3 Page 43 of 123 Drift Data for DPIS-2-119C Calibration Drift Date Interval As-Found As-Left Drift (%)
(Months) (psid) 5/5/2008 3.0 140.6 140.6 0.5 0.25 2/5/2008 2.7 140.1 140.1 -0.4 -0.20 11/15/2007 3.3 140.5 140.5 0.7 0.35 8/6/2007 3.0 139.8 139.8 0.9 0.45 5/7/2007 2.9 138.9 138.9 -2.0 -1.00 2/8/2007 3.1 140.9 140.9 0.7 0.35 11/6/2006 3.0 140.2 140.2 0.5 0.25 8/7/2006 3.0 139.7 139.7 -0.3 -0.15 5/8/2006 3.0 140.0 140.0 0.0 0.00 2/6/2006 3,2 140.0 140.0 -0.4 -0.20 10/31/2005 3.0 140.4 140.4 1.0 0.50 8/1/2005 3,0 139.4 139.4 -0.6 -0.30 5/2/2005 1.7 140.0 140.0 0.0 0.00 3/12/2005 1.3 140.0 140.0 -0.5 -0.25 1/31/2005 3.0 140.5 140.5 0.0 0.00 11/1/2004 3,0 140.5 140.5 0.5 0.25 8/2/2004 3.0 140.0 140.0 0.5 0.25 5/3/2004 3.0 139.5 139.5 -0.5 -0.25 2/2/2004 3.0 144.0 140.0 0.5 0.25 11/3/2003 3,0 143.5 143.5 0.0 0.00 8/4/2003 3.4 143.5 143.5 0.0 0.00 4/23/2003 2.6 143.5 143.5 -0.5 -0.25 2/3/2003 3.0 144.0 144.0 0.0 0.00 11/4/2002 3.0 144.0 144.0 0.0 0.00 8/5/2002 3.0 144.0 144.0 0.0 0.00 5/6/2002 3.0 144.0 144.0 -0.5 -0.25 2/4/2002 3.0 144.5 144.5 0.5 0.25 11/6/2001 2.9* 144.0 144.0 0.0 0.00 8/10/2001 3.1 144.0 144.0 0.0 0.00 5f7/2001 3.0 144.0 144.0 0.5 0.25 2/5/2001 3.0 143.5 143.5 -1.0 -0.50 11/6/2000 3.0 144.5 144.5 0.5 0.25 8/7/2000 3.0 144.0 144.0 0.0 0.00 5/9/2000 2.9 '144.0 144.0 -1.0 -0.50 2/11/2000 0.7 145.0 145.0 0.5 0,25 1/21/2000 2.4 144.5 144.5 0.0 0.00 11/8/1999 3.0 144.5 144.5 0.5 0.25 8/9/1999 3.0 144.0 144.0 -0.5 -0.25 5/10/1999 3.0 144.5 144.5 0.0 0.00 2/8/1999 3.0 144.5 144.5 -0.5 -0.25 11/9/1998 1.3 145.0 145.0 1.0 0.50 9/30/1998 1.7 124.5 144.0 0.5 0.25 8/10/1998 3.0 124.0 124.0 0.0 0.00 5/12/1998 2.9 124.0 124.0 -0.5 -0.25
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 44 of 123 2/12/1998 3.0 124.5 124.5 0.0 0.00 11/11/1997 3.0 .124.5 124.5 0.5 0.25, 8/11/1997 .1.4 124.0 124.0 -1.0 -0.50 6/30/1997 4.6 125.0 125.0 0.0 0.00 2/10/1997 3.0 125.0 125.0 0.0 0.00 11/11/1996 3.0 125.0 125.0 1.0 0.50 8/13/1996 2.7' 124. 0 124.0 -2.0 -1.00 5/24/1996 3.3 126.0 126.0 1.5 0.75 2/13/1996 3.0 124.5 124.5 -0.5 -0.25 11/13/1995 3.0. 125.0 125.0 1.0 0.50 8/15/1995 3.0 124.0 124.0 0.0 0.00 5/15/1995 3.0 124.0 124.0 -1.0 70.50 2/13/1995 3.0 125.0 125.0 1.0 0.50 11/15/1994 -1.6 124.0 124.0 -0.5 -0.25 9128/1994 1.4 125.5 124.5 0.5 0.25 8/15/1994 3.0 125.0 125.0 0.5 0.25 5/17/1994 3.0 124.5 124.5 -0.5 -0.25 2/15/1994 3.0. 125.0 125.0 0.0 0.00 11/16/1993 3.0:l 125.0 125.0 0.0 0.00 8/17/1993 3.0, 125.0 125.0 -1.0 -0.50 5/18/1993 2.9 126.0 126.0 -1.0 -0.50 2/19/1993 3.0 127.0 127.0 2.0 1.00 11/19/1992 3.0 125.0 125.0 -0.5 -0.25 8/18/1992 3.0 125.5 125.5 0.5 0.25 5/18/1992 125.0 125.0 Basic Statistics for DPIS-2-119C "Average x (psid) 0.0 Standard Deviation S (psid) 0.72 Variance s2 (psid) 0.51 Largest Positive Drift (psid) 2.0 Largest Negative Drift (psid) -2.0 Number of Sam' les . N. 68 Average x (%) 0.01 Standard Deviation s (%) 0.36 Largest Positive Drift (%) 1.00 Largest Negative Drift (%) -1.00
-I
-I*rr I-Drift Trend Plot for DPIS-2-119C 3.0
-. 9
"-1.0 *a 0.0 CD-
.- 2 .0 t,!)),,]i,!,,J',!!]i,]
CL 0 (DQ 4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/14/2005 9/9/2008 0 Date
-.-- DPIS-2-119C - - -+2s - - - -2s CD U) 0CDO
MONTICELLO NUCLEAR GENERATING PLANT' CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 46 of 123 Drift Data for DPIS-2-119D Date Calibration As-Found As-Left Drift Drift (%)
Interval (psid)
(Months) 5/5/2008 3.0 142.8 142.8 0.4 0.20 2/5/2008 2.7 142.4 142.4 0.4 0.20 11/15/2007 3.3 142.0 142.0 0.3 0.15 8/6/2007 2.9 141.7 141.7 -0.8 -0.40 5/9/2007 3.0 142.5 142.5 -0.3 -0.15 2/8/2007 3.1 142.8 142.8 0.3 0.15 11/6/2006 3.0 .142.5 142.5 0.8 0.40 8/7/2006 3.0 141.7 141.7 -0.9 -0.45 5/8/2006 3.0 142.6 142.6 0.1 0.05 2/6/2006 3.2 142.5 142.5 -0.2 -0.10 10/31/2005 3.0 142.7 142.7 0.9 0.45 8/1/2005 3.0 141.8 141.8 -0.4 -0.20 5/2/2005 1.6 142.2 142.2 -0.3 -0.15 3/13/2005 1.3 142.5 142.5 0.0 0.00 1/31/2005 3.0 142.5 142.5 -0.5 -0.25 11/1/2004 3.0 143.0 143.0 1.0 0.50 8/2/2004 3.0 142.0 142.0 0.0 0.00 5/3/2004 3.0 142.0 142.0. -1.0 -0.50 2/2/2004 3.0 143.0 143.0 0.5 0.25 11/3/2003 3.0 142.5 142.5 0.0 0.00 8/4/2003 3.4 142.5 142.5 0.0 0.00 4/23/2003 2.6 142.5 142.5 0.0 0.00 2/3/2003 3.0 142.5 142.5 -0.5 -0.25 11/4/2002 3.0 143.0 143.0 1.0 0.50 8/5/2002 3.0 142.0 142.0 -0.5 -0.25 5/6/2002 3.0 142.5 142.5 -0.5 -0.25 2/4/2002 3.0 143.0 143.0 0.0 0.00 11/6/2001 2.9. 143.0 143.0 0.5 0.25 8/10/2001 3.1 142.5 142.5 -0.5 -0.25 5/7/2001 3.0 143.0 143.0 0.5 0.25 2/5/2001 3.0 142.5 142.5 -1.0 -0.50 11/6/2000 3.0 143.5 143.5 1.0 0.50 8/7/2000 3.0 142.5 142.5 -0.5 -0.25 5/9/2000 2.9 143.0 143.0 0.0 0.00 2/11/2000 0.7 143.0 143.0 0.0 0.00 1/22/2000 2.5 144.0 143.0 0.5 0.25 11/8/1999 3.0 143.5 143.5 0.5 0.25 8/9/1999 3.0 143.0 143.0 -0.5 -0.25 5/10/1999 3.0 143.5 143.5 0.0 0.00 2/8/1999 3.0 143.5 143.5 0.0 0.00 11/9/1998 1.3 143.5 143.5 0.5 0.25 9/30/1998 1.7 122.0 143.0 0.5 0.25 8110/1998 3.0 121.5 121.5 -0.5 -0.25 5/12/1998 2.9 , 122.0 122.0 -2.0 -1.00
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 47 of 123 2/12/1998 3.0 124.0 124.0 1.0 0.50 11/11/1997 3.0 123.0 123.0 1.5 0.75 8/11/1997 1.4 121.5 121.5 -0.5 -0.25 6/30/1997 4.6 122.0 122.0 -3.0 -1.50 2/10/1997 3.0 125.0 125.0 0.5 0.25 11/11/1996 3.0 124.5 124.5 1.5 0.75 8/13/1996 2.7 123.0 123.0 -2.0 -1.00 5/24/1996 3.3 125.0 125.0 1.5 0.75 2/13/1996 3.0 123.5 123.5 -1.0 -0.50 11/13/1995 3.0 124.5 124.5 0.5 0.25 8/15/1995 3.0 124.0 124.0 0.0 0.00 5/15/1995 3.0 124.0 124.0 -0.5 -0.25 2/13/1995 3,0 124.5 124.5 1.0 0.50 11/15/1994 1.5 123.5 123.5 -1.0 -0.50 9/29/1994 1.5 124.5 124.5 0.5 0.25 8/15/1994 3.0 124.0 124,0 -0.5 -0.25 5/17/1994 3.0 124.5 124.5 0.5 0.25 2/15/1994 3.0 124.0 124.0 0.0 0.00 11/16/1993 3.0 124.0 124.0 0.0 0.00 8/17/1993 3.0 124.0 124.0 -1.0 -0.50 5/18/1993 2.9 125.0 125.0 -1.0 -0.50 2/19/1993 3.0 126.0 126.0 0.5 0.25 11/19/1992 3.0 125.5 125.5 1.0 0.50 8/18/1992 3.0 124.5 _124.5 0.5 0.25 5/18/1992 124.0 124.0 Basic Statistics for DPIS-2-1 19D Average x (psid) 0.0 Standard Deviation s (psid) 0.82 Variance s2 (psid) 0.68 Largest Positive Drift (psid) 1.5 Largest Negative Drift (psid) -3.G0 Number of Samples n 68 Average X (%) -0.01 Standard Deviation s (%) 0.41 Largest Positive Drift (%) 0.75 Largest Negative Drift (%) -1.50
0
>I-U Drift Trend Plot for DPIS-2-119D rn
-2.0 T 0.0 =D.a
-n
-20 S-4.0 00 4/6/1992 1/1/1995 9/27/1997 6/23/2000 3/20/2003 12/1 V/2005 9/9/2008 Date
- s. DPIS-2 119D - = -+2s -2s (D
o B 0CDO2 Z3
-h)CA
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 49 of 123 Basic Statistics for Combined Data Average mean (psid) 0.0 Standard Deviation s (psid) 0.88 Variance s2 (psid) 0.78 Largest Positive Drift (psid) 4.5 Largest Negative Drift (psid) -24.5 Number of Samples n 1094 Average mean N% 0.00 Standard Deviation s N% 0.44 Largest Positive Drift (%) 2.25 Largest Negative Drift N% -2.25
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 50 of 123 Outlier Test (t-Test) for Combined Data Set Calibration Drf T Equipment Interval Drift Outlier?
ID (Months) (psid) YESINO DPIS 3.0 0.1 0.10 NO 116A 2.7 -0.2 0.24 NO 3.3 1.0 1.12 NO 3.0 -0.8 0.92 NO 2.9 -1.2 1.37 NO 3.1 1.0 1.12 NO 3.0 0.7 0.78 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.2 -0.5 0.58 NO 3.0 0.3 0.33 NO 3.0 0.0 0.01 NO 1.7 0.0 0.01 NO 1.2 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 1.4 -0.5 0.58 NO 1.6 3.5 3.95 NO 3.0 -3.0 3.41 NO 3.0 0.5 0.56 NO 3.0 -1.5 1.71 NO 3.4 0.5 0.56 NO 2.6 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 2.9 0.5 0.56 NO 3.1 -0.5 0.58 NO 3.0 1.5 1.69 NO 3.0 -0.5 0.58 NO 3.0 -2.0 2.27 NO 3.0 1.5 1.69 NO 2.9 -1.0 1.14 NO 0.7 0.5 0.56 NO 2.4 -1.5 1.71 NO 3.0 0.0 0.01 NO 3.0 4.0 4.52 YES 3.0 -3.0 3.41 NO 3.0 -1.0 1.14 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 51 of 123 1.3 1.5 1.69 NO 1.7 -4.0 4,54 YES 3.0 0.0 0.01 NO 2.9 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 3.5 3.95 NO 1.4 -4.5 5.11 YES 4.6 4.0 4.52 YES 3.0 -4.0 4.54 YES 3.0 0.0 0.01 NO 2.7 -2.0 2.27 NO 3.3 3.0 3.39 NO 3.0 0.5 .0.56 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 -NO 3.0 -1.0 1.14 NO 1.6 -1.0 1.14 NO 1.4 0.5 0.56 NO 3.0 0.0, 0.01 NO 3.0 1.5 1.69 NO 3.0 -1.0 1.14 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 2.9 -1.0 1.14 NO 3.0 0.0 0,01 NO 3.0 0.0 0.01 NO
+
,3.0 4
-0.5 +
0,58 4 NO DPIS 3.0 -0.1 0.12 NO 116B 2.7 -0.5 0.58 NO 3.3 1.1 1,24 NO 3.0 -0.6 0.69 NO 2.9 -0.9 1.03 NO 3.1 1.1 1.24 NO 3.0 0.5 0.56 NO 3.0 -0.4 0.46 NO 3.0 0.0 0.01 NO 3.2 -0.4 0.46 NO 3.0 1.1 1.24 NO 3.0 -1.0 1.14 NO 1.7 0.5 0.56 'NO
.1.3 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 52 of 123 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.4 -0.5 0.58 NO 2.6 0.0 0.01 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 2.9 0.0 0.01 NO 3.1 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 3.0 -1.0 1.14 NO 2.9 -0.5 0.58 NO 0.7 0.5 0.56 NO 2.4 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 1.3 1.0 1.12 NO 1.7 0.3 0.33 NO 3.0 0.2 0.22 NO 2.9 -1.5 1.71 NO 3.0 1.0 1,12 NO 3.0 -0.5 0.58 NO 1.4 1.0 1.12 NO 4.6 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 2.7 -1.0 1.14 NO 3.3 1.0 1.12 NO 3.0 -1.0 1.14 NO 3.0 1.5 1.69 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 1.5 0.5 0.56 NO 1.5 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 53 of 123 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 2.9 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.5 I 0.56 NO I
DPIS 3.0 -0.2 0.24 NO 116C 2.7 0.4 0.44 NO 3.3 -0.2 0.24 NO 3.0 -0.8 0.92 NO 2.9 0.8 0.90 NO 3.1 0.8 0.90 NO 3.0 0.0 0.01 NO 3.0 -1.1 1.26 NO 3.0 0.0 0.01 NO 3.2 1-.0 1.12 NO 3.0 0.4 0.44 NO 3.0 -0.6 0.69 NO 1.7 0.0 0.01 NO 1.3 -0.5 0.58, NO 3.0 0.0 0.01 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.4 0.0 0.01 NO 2.6 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 2.9 0.5 0.56 NO 3.1 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 2.9 0.0 0.01 NO 0.7 -0.2 0.24 NO 2.4 1.2 1.35 NO 3.0. 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 54 of 123.
3.0 0.0 0.01 NO 1.3 1.0 1.12 NO 1.7 0.0 0.01 NO 3.0 0.0 0.01 NO 2.9 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 1.4 -1.0 1.14 NO 4.6 0.0 0.01 NO 3.0 0.2 0.22 NO 3.0 0.8 0.90 NO 2.7 -1.5 1.71 NO 3.3 1.5 1.69 NO 3.0 -0.8 0.92 NO 3.0 0.8 0.90 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 1.6 -0.5 0.58 NO 1.4 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 2.9 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO t 1-DPIS 3.0 -0.9 1.03 NO 116D 2.7 -0.3 0.35 NO 3.3 1.0 1.12 NO 3.0 -0.2 0.24 NO 2.9 -1.4 1.60 NO 3.1 1.3 1.46 NO 3.0 0.3 0.33 NO 3.0 -0.6 0.69 NO 3.0 -0.1 0.12 NO 3.2 -0.6 0.69 NO 3.0 1.1 1.24 NO 3.0 -0.1 0.12 NO 1.6 0.0 0.01 NO 1.3 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 3.0 1.0 1.12 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 55 of 123 3.0 -0.5 0.58 NO 3.0 -1.0 1.14 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.4 0.5 0.56 NO 2.6 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 2.9 1.5 1.69 NO 3.1 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 2.9 0.5 0.56 NO 0.7 -1.5 1.71 NO 2.5 1.0 1.12 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 1.3 0.5 0.56 NO 1.7 0.2 0.22 NO 3.0 -0.2 0.24 NO 2.9 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 1.0 1.12 NO 1.4 -1.0 1.14 NO 4.6 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 1.0 1.12 NO 2.7 -2.0 2.27 NO 3.3 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 1.5 0.5 0.56 NO 1.5 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 56 of 123 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 -2.0 2.27 NO 2.9 1.0 1.12 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO DPIS 3.0 -0.5 0.58 NO 117A 2.7 -0.3 0.35 NO 3.3 0.6 0.67 NO 3.0 0.0 0.01 NO 2.9 -0.5 0.58 NO 3.1 0.2 0.22 NO 3.0 0.2 0.22 NO 3.0 -0.4 0.46 NO 3.0 0.1 0.10 NO 3.2 -0.9 1.03 NO 3.0 0.9 1.01 NO 3.0 0,5 0.56 NO 1.7 -0.1 0.12 NO 1.3 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.4 -0.5 0.58 NO 2.6 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0, 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3,0 0.0 0.01 NO 2.9 1.0 1.12 NO 3.1 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 2.9 0.2 0.22 NO 0.7 -1.2 1.37 NO 2.4 0.5 0.56 NO 3.0 0.5 0.56 NO 1 3.0 0.0 0,0 NO 3.0 0.0 0.01 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 57 of 123 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 1.3 0.5 0.56 NO 1.7 -0.4 0.46 NO 3.0 0.4' 0.44 NO 2.9 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 1.4 -0.5 0.58 NO 4.6 0.5 0.56 NO 3.0 -1.0 1.14 NO
'3.0 0.5 0.56 NO 2.7 -1.5 1.71 NO 3.3 1.0 1.12, NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 -0.5 0.58 NO 1.6 0.5 0.56 NO
- 1.4 0.5 0.56 NO 3.0 -0.5 0.58. NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO
'3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 2:9 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 0,0 0.01 NO
~1~
DPIS 3.0 -2.0 2.27 NO 117B 2.7 -0.3 0.35 NO 3.3 0.8 0.90 NO 3.0 -0.4 0.46 NO 2.9 -1.2 1.37 NO 3.1 3.2 3.61 NO 3.0 0.5 0.56 NO 3.0 0.1 0.10 NO 3.0 -1.2 1.37 NO 3.2 -0.2 0.24 NO 3.0 1.7 1.91 NO 3.0 -0.1 0.12 NO 1.7' 1.0 1.12 NO 1.3 -1.5 1.71 NO 3.0 0.0 NO 3.0 0.0 1 0,01 0.01 N
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 58 of 123 3.0 -0.5 0.58 NO 3.0 -1.0 1.14 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.4 0.5 0.56 NO 2.6 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 2.9 0.5 0.56 NO 3.1 -1.0 1.14 NO 1.2 1.5 1.69 NO 1.8 -1.5 1.71 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 2.9 1.0 1.12 NO 0.7 -0.5 0.58 NO 2.4 0.0 0.01 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -1.5 1.71 NO 3.0 1.5 1.69 NO 1.3 0.5 0.56 NO 1.7 4.5 5.09 YES 3.0 -0.5 0.58 NO 2.9 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 1.4 0.5 0.56 NO 4.6 -1.0 1.14 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 2.7 0.0 0.01 NO 3.3 1.0 1.12 NO 3.0 -0.3 0.35 NO 3.0 -0.2 0.24 NO 3.0 1.5 1.69 NO 3.0 -0.5 0.58 NO 3.0 -1.0 1.14 NO 1.5 0.5 0.56 NO 1.5 0.0 0.011 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 59 of 123 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 2.9 -1.0 1.14 NO 3,0 0.0 0.01 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO DPIS 3.0 -0.6 0.69 NO 117C 2.7 0.1 0.10 NO 3.3 0.5 0.56 NO 3.0 -0.6 0.69 NO 2.9 -0.6 0.69 NO 3.1 0.8 0.90 NO 3.0 0.4 0.44 NO 3.0 -0.4 0.46 NO 3.0 -0.2 0.24 NO 3.2 -0.1 0.12 NO 3.0 0.8 0.90 NO 3.0 -0.3 0.35 NO 1.7 0.0 0.01 NO 1.3 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.4 0.44 NO 3.0 -0.4 0.46 NO 3.4 -0.5 0.58 NO 2.6 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 2.9 0.5 0.56 NO 3.1 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 2.9 0.0 0.01 NO 0.7 -0.5 0.58 NO 2.4 0.5 10.56 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 S1,Page 60 of 123 3.0 1 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 2.0 2.25 NO 3.0 -2.0 2.27 NO 1.3 1.0 1.12 NO 1.7 -0.5 0.58 NO 3.0 0.5 0.56 NO 2.9 -1.0 1.14 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 1.4 -0.5 0.58 NO 4.6 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 1.5 1.69 NO
,2.7 -2.5 2.84 NO 3.3 0.5 0.56 NO 3.0 0.3 0.33 NO 3.0 2.2 2.48 NO 3.0 -1.5 1.71 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 1.6 -0.5 0.58 NO 1.4 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 -1.0 114. NO 2.9 -0.5 0.58 NO 3.0 1.0 1.12 NO
.3.0 0.5 0.56 NO 3.0 0.0 0.01 NO DPIS 3.0 -0.2 0.24 NO 117D 2.7 -0.6 0.69 NO 3.3 1.4 1.57 NO 2.9 -1.0 1.14 NO 3.0 -1.1 ' 1.26 NO 3.1 0.3 0.33 NO 3.0 2.4 2.71 NO 3.0 -1.1 1.26 NO 3.0 0.2 0.22 NO 3.2 -0.7 0.80 NO 3.0 1.7 1.91 NO 3.0 -0.7 0.80 NO 1.6 -1.5 1.71 NO 1.6 -1.5 1.71 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Analysiss Spreadsheets Drift Ana Drif Attachment 3 Page 61 of 123 1.3 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 2.0 2.25 NO 3.0 -0.5 0.58 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.4 -1.0 1.14 NO
'2.6 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 1.5 1.69 NO 3.0 -1.0 1.14 NO 3.0 -0.5 0.58 NO 3.0 -1.0 1,14 NO 2.9 1.5 1.69 NO 3.1 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 -0.5 0.58 NO 2.9 -0.5 0.58 NO 0.7 -1.0 1.14 NO 2.5 2.0 2.25 NO 3.0 -1.5 1.71 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -1.5 1.71 NO 1.3 0.0 0.01 NO 1.7 0.5 0.56 NO 3.0 -1.0 1.14 NO 2.9 1.0 1.12 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 1.4 -1.5 1.71 NO 4.6 0.0 0.01 NO 3.0 0.2 0.22 NO 3.0 1.3 1.46 NO 2.7 -2.0 2.27 NO 3.3 1.5 1.69 NO 3.0 -1.6 1.82 NO 3.0 1.6 1.80 NO 3.0 -0.5 0.58 NO 3.0 -1.5 1.71 NO 3.0 1.0 1.12 NO 1.5 " 0. 0.56 NO 1.6 0.-.6N
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 62 of 123 1.5 0.5 0.56 NO 3.0 -1.5 1.71 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -1.5 1.71 NO 2.9 1.0 1.12 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 1.0 1,12 NO 4 .4 DPIS 3.0 -0.3 0.35 NO 118A 2.7 -0.5 0.58 NO 3.3 1.1 1.24 NO 3.0 -0.3 0.35 NO 2.9 -1.3 1.48 NO 3.1 1.2 1.35 NO 3.0 0.2 0.22 NO 3.0 -0.1 0.12 NO 3.0 -0.1 0.12 NO 3.2 -0.4 0.46 NO 3.0 1.5 1.69 NO 3.0 -0.8 0.92 NO 1.7 0.1 0.10 NO 1.3 -1.0 1.14 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 0.9 1.01 NO 3.0 0.1 0.10 NO 3.4 0.0 0.01 NO 2.6 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 0,5 0.56 NO 2.9 0.0 0.01 NO 3.1 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 2.9 1.0 1.12 NO 0.7 -1,5 1.71 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 63 of 123 2.4 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 3.0 -1.0 1.14 NO 1.3 1.0 1.12 NO 1.7 0.0 0.01 NO 3.0 0.0 0.01 NO 2.9 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 1.4 -0.5 0.58 NO 4.6 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 2.7 -1.5 1.71 NO 3.3 1.5 1.69 NO 3.0 0.0 0.01 NO 3.0 1.0 1.12 NO 3.0 -1.0, 1.14 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 1.6 0.0 0.01 NO 1.4 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 2.9 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO
- 1
- 1 DPIS 3.0 0.0 0.01 NO 118B 2.7 -0.1 0.12 NO 3.3 0.2 0.22 NO 3.0 -0.2 0.24 NO 2.9 -1.1 1.26 NO 3.1 0.7 0.78 NO 3.0 0.8 0.90 NO 3.0 -0.6 0.69 NO 3.0 0.1 0.10 NO 3.2 -0.1 0.12 NO 3.0 0.2 0.22 NO
.3.0 -0.3 10.35 NO 3.0 -0.3 0.35 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint' Revision I Drift Analysis Spreadsheets Attachment 3 Page 64 of 123 1.7 -0.2 0.24 NO 1.3 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0,0 0.01 NO 3.0 0.0 0.01 NO 3.4 0.0 0.01 NO 2.6 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12. NO 2.9 0.0 0.01 NO 3.1 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 2.9 -1.5 1.71 NO 0.7 1.0 1.12 NO.
2.4 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3,0 0.5 0.56 NO 1.3 0.5 0.56 NO 1.7 0.5 0.56 NO 3.0 -0.5 0.58 NO 2.9 -1.0 1.14 NO 3.0 -1.0 1.14 NO 3.0 1.5 1.69 NO 1.4 0.0 0.01 NO 4.6 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 2.7 -1.5 1.71 NO 3.3 0.5 0.56 NO 3.0 1.0 1.12 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO
- 3. 0.0 0.01 NO 3.0 I 0.0 0.01 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 65 of 123 1.5 0.0 0.01 NO 1.5 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO
ý3.0 0.0 0.01 NO 2.9 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 0.5 0.56 NO i
3.0 +
0.5 0.56 NO DPIS 3.0 0.1 0.10 NO 118C 2.7 0.6 0.67 NO 3.3 0.3 0.33 NO 3.0 0.0 0.01 NO 2.9 -0,8 0.92 NO 3.1 0.4 0.44 NO 3.0 0.5 0.56 NO 3.0 -0.6 0.69 NO 3.0 0.4 0.44 NO 3.2 -0.2 0.24 NO 3.0 0.7 0.78 NO 3.0 -0.3 0.35 NO 1.7 -0.5 0.58 NO 1.3 -0:5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.4 -0.5 0.58 NO 2.6 -1.0 1.14 NO 3.0 0.0 0.01, NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 0.0 0,01 NO 2.9 0.5 0.56 NO 3.1 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO
-2.9- 0.0 0.01 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 66 of 123 0.7 -1.0 1.14 NO 2.4 1.5 1.69 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO 3.0 -0.3 0.35 NO 3.0. -0.2 0.24 NO 1.3 1.5 1.69 NO 1.7 0.5 0.56 NO 3.0 -0.5 0.58 NO 2.9 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 1.4 0.0 0.01 NO 4.6 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 2.7 -1.5 1.71 NO 3.3 0.5 0.56 NO 3.0 0.1 0.10 NO 3.0 1.4 1.57 NO 3.0 -1.0 1.14 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 1.6 0.0 0.01 NO 1.4 1.0 1.12 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO 3.0. 0.0 0.01 NO 2.9 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO DPIS 3.0 0.4 0.44 NO 118D 2.7 -0.6 0.69 NO 3.3 0.0 0.01 NO 2.9 0.1 0.10 NO 3.0 0.1 0.10 NO 3.1 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 -0.9 1.03 NO 3.0 0.2 0.22 NO 3.2 -0,5 0.58 NO 1 3.0 0.7 0.78 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 67 of 123 3.0 -0.9 1.03 NO 1.6 0.5 0.56 NO 1.3 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.4 1.0 1.12 -NO 2.6 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 -0.5 0.58 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 2.9 0.0 0.01 NO 3.1 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0,56 NO 3.0 -1.0 1.14 NO 2.9 0.0 0.01 NO 0.7 -1.0 1.14 NO 2.5 2.0 2.25 NO 3.0 -1.0 1.14 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 1.3 0.5 0.56 NO 1.7 0.5 ,0.56 NO 3.0 -0.5 0.58 NO 2.9 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 1.0 1.12 NO 1.4 -1.0 1.14 NO 4.6 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 2.7 -1.5 1.71 NO 3.3 0,0 0.01 NO 3,0 -1.5 1.71 NO 3.0 1.5 1.69 NO 3.0 1.0 1.12 NO 1 3.0 -1.0 1.14. NO0 3.0 -1.0 1.14 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 68 of 123 3.0 1.0 1.12 NO 1.5 -2.0 2.27 NO 1.5 1.5 1.69 NO 3.0 1.0 1.12 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 -3.5 3.97 NO 3.0 2.0 2.25 NO 2.9 2.0 2.25 NO 3.0 0.5 0.56 NO 3.0 -2.0 2.27 NO 3.0 1.0 1.12 NO DPIS 3.0 -0.2 0.24 NO 119A 0.0 -0.1 0.12 NO 2.7 -0.5 0.58 NO 3.3 0.8 0.90 NO 3.0 -0.9 1.03 NO 2.9 0.1 0.10 NO 3.1 0.6 0.67 NO 3.0 0.2 0.22 NO 3.0 0.0 0.01 NO 3.0 -0.1 0.12 NO 3.2 -0.8 0.92 NO 3.0 1.5 1.69 NO 3.0 -1.4 1.60 NO 1.7 0.5 0.56 NO 1.3 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 1:4 -0.5 0.58 NO 1.6 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 1.3 1.46 NO 3.0 -0.3 0.35 NO 3.4 0.2 0.22 NO 2.6 -0.7 0.80 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01. NO 3.0 -1.5 1.71 NO 3.0 1.5 1.69 NO 2.9 -0.5 0.58 NO 3.1 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift DPage Analysis Spreadsheets Attachment 3 69 of 123 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 2.9 1.0 1.12 NO 0.7 -1.0 1.14. NO 2.4 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 -0.5 0.58 NO 1.3 1.0 1.12 NO 1.7 0.0 0.01 NO 3.0 0.0 0.01 NO 2.9 -0.5 0.58 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 1.4 -1.0 1.14 NO 4.6 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 2.7 -2.5 2.84 NO 3.3 1.0 1.12 NO 3.0 1.2 1.35 NO 3.0 -0.7 0.80 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 1.6 0.0 0.01 NO 1.4 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 1.0 1.12 NO 3.0 -1.'0 1.14 NO 3.0 -1.0 1.14 NO 2.9 0.0 0.01 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 1.0 1.12 NO DPIS 3.0 -0.1 0.12 NO 119B 2.7 -0.5 0.58 NO 3.3 1.1 1.24 NO 3,0 -1.2 1.37 NO 2.9 -0.5 0.58' NO 3.1 0.8 0.90 NO 3.0 0.7 0.78 NO 1 3.0 -0.8 0.92 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 70 of 123 3.0 0.4 0.44 NO 3.2 -0.5 0.58 NO 3.0 1.1 1.24 NO 3.0 -0.4 0.46 NO 1.6 -0.5 0.58 NO 1.3 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3A4 0.5 0,56 NO 2.6 0.0 0.01 NO 0.3 -1.0 1.14 NO 2.7 3.5 3.95 NO 3.0 3.0 3.39 NO I I 3.0. 4.0 4.52 YES 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 2.9 1.5 1.69 NO 0.0 0.0 0.01 NO 3.1 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 1,0 1.12 NO 3.0 -1.0 1.14 NO 2.9 -0.5 0.58 NO 0.7 -0.5 0.58 NO 2.4 -0.5 0.58 NO 3.0 2.0 2.25 NO 3.0 -0.5 0.58 NO 3.0 .0.5 0.56 NO 3.0 0.0 0.01 NO 1.3 0.5 0.56 NO 1.7 0.5 0.56 NO 3.0 -0.5 0.58 NO 2.9 -0.5 0.58 NO 3.0 0.5 0,56 NO 3.0 0.0 0.01 NO 1.4 0.0 0.01 NO 4.6 0.0 0.01o NO 3.0 0.0 0.01 NO 3.0 2.0 2.25 NO 2.7 -3.0 3.41 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 71 of 123 3.3 1.0 1.12 NO 3.0 -0.3 0.35 NO 3.0 0.3 0.33 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 1.5 0.0 0.01 NO 1.5 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 -0.5 0.58 NO 3.0 1.5 1.69 NO 3.0 -2.0 2,27 NO 2.9 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 4 +
DPIS 3.0 0.5 1 0.56 NO S119C 2.7 -0.4 0.46 NO 3.3 0.7. 0.78 NO 3.0 0.9 1.01 NO 2.9 -2.0 2.27 NO 3.1 0.7 0.78 NO 3.0 0.5 0.56 NO 3.0 -0.3 0.35 NO 3.0 0.0 0.01 NO 3.2 -0.4 0.46 NO 3.0 1.0 1.12 NO 3.0 -0.6 0.69 NO 1.7 .0.0 0.01 NO 1.3 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.4 0.0 0.01 NO 2.6 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 1.2.9 0.0 0.01 1 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 72 of 123 3.1 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 2.9 -1.0 1.14 NO 0.7 0.5 0.56 NO 2.4 0.0 0.01 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 1.3 1.0 1.12 NO 1.7 0.5 0.56 NO 3.0 0.0 0.01 NO 2.9 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.5 0.56 NO 1.4 -1.0 1.14 NO 4.6 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 1.0 1.12 NO 2.7 -2.0 2.27 NO 3.3 1.5 1.69 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -1.0. 1.14 NO 3.0 1.0 1.12 NO 1.6 -0.5 0.58 NO 1.4 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 2.9 -1.0 1.14 NO 3.0 2.0 2.25 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO DPIS 3.0 0.4 0.44 NO 119D 2.7 0.4 0.44 NO 3.3 0.3 0.33 NO 2.9 -0.8 0.92 NO 3.0 -0.3 0.35 NO 3.1 0.3 0.33 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 73 of 123 3.0 0.8 0.90 NO 3.0 -0.9 1.03 NO 3.0 0.1 0.10 NO 3.2 -0.2 0,24 NO 3.0 0.9 1.01 NO 3.0 -0.4 0.46 NO 1.6 -0.3 0.35 NO 1.3 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 3.0 0.5 0.56 NO
'3.0 0.0 0.01 NO 3.4 0.0 0.01 NO 2.6 0.0 .0.01 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 3.0 -0U5 0.58 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 2.9 0.5 0.56 NO 3.1 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 -1.0 1.14 NO 3.0 1.0 1.12 NO 3.0 -0.5 0.58 NO 2.9 0.0 0.01 NO 0.7 0.0 0.01 NO 2.5 0.5 0.56 NO 3.0 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 1.3 0.5 0.56 NO 1.7 0.5 0.56 NO 3.0 -0.5 0.58 NO 2.9 -2.0 2.27 NO 3.0 1.0 1.12 NO 3.0 1.5 1.69 NO 1.4 -0.5 0.58 NO 4.6 -3.0 3.41 NO 3.0 0.5 0.56 NO 3.0 1.5 1.69 NO 2.7 -2.0 2.27 NO 3.3 1.5 1.69 NO 3.0 -1.0 1.14 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift.Analysis Spreadsheets Attachment 3 Page 74 of 123 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 -0.5 0.58 NO 3.0 1.0 1.12 NO 1.5 -1.0 1.14 NO 1.5 0.5 0.56 NO 3.0 -0.5 0.58 NO 3.0 0.5 0.56 NO 3.0 0.0 0.01 NO 3.0 0.0 0.01 NO 3.0 -1.0 1.14 NO 2.9 -1.0 1.14 NO 3.0 0.5 0.56 NO 3.0 1.0 1.12 NO
,3.0 0.5 10.56 NO
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 75 of 123 Normality Test - D' Test Data # Drift (i) (psid) 1 -4.5 2459.3 2 -4.0 2182.0 3 -4.0 2178.0 4 -3.5 1902.3 5 -3.0 1627.5 6 -3.0 1624.5 7 -3.0 1621.5 8 -3.0 1618.5 9 -2.5 1346.3 10 -2.5 1343.8 11 -2.0 1073.0 12 -2.0 1071.0 13 -2.0 1069.0 14 -2.0 1067.0 15 -2.0 1065.0 16 -2.0 1063.0 17 -2.0 1061.0 18 -2.0 1059.0 19 -2.0 1057.0 20 -2.0 1055.0 21 -2.0 1053.0 22 -2.0 1051.0 23 -2.0 1049.0 24 -2.0 1047.0
-25 -1.6 836.0 26 -1.5 782.3 27 -1.5 780.8 28 -1.5 779.3 29 -1.5 777.8 30 -1,5 776.3 31 -1.5 774.8 32 -1.5 773.3 33 -1.5 771.8 34 -1.5 770.3 35 -1.5 768.8 36 -1.5 767.3 37 -1.5 765.8 38 -1.5 764.3 39 -1.5 762.8 40 -1.5 761.3 41 -1.5 759.8 42 :1.5 758.3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 76 of 123 43 -1.5 756.8 44 -1.5 755.3 45 -1.5 753.8 46 -1.5 752.3 47 -1.5 750.8 48 -1.5 749.3 49 -1.5 747.8 50 -1.5 746.3 51 -1.4 695.1 52 -1.4 693.7 53 -1.3 642.8 54 -1.2 592.2 55 -1.2 591.0 56 -1.2 589.8 57 -1.2 588.6 58 -1.2 587.4 59 -1.1 537.4 60 -1.1 536.2 61 -1.1 535.1 62 -1.1 534.0 63 -1.0 484.5 64 -1.0 483.5 65 -1.0 482.5 66 -1.0 481.5 67 -1.0 480.5 68 -1.0 479.5 69 -1.0 478.5 70 -1.0 477.5 71 -1.0 476.5 72 -1.0 475.5 73 -1.0 474.5 74 -1.0 473.5 75 -1.0 472.5 76 -1.0 471.5 77 -1.0 470.5 78 -1.0 469.5 79 -1.0 468.5 80 -1.0 467.5 81 -1.0 466.5 82 -1.0 465.5 83 -1.0 464.5 84 -1.0 463.5 85 -1.0 462.5 86 -1.0 461,5 87 -1.0 460.5 88 -1.0 459.5 89 -1.0 458.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 77 of 123 90 -1.0 457.5 91 -1.0 456.5 92 -1.0 455.5 93 -1.0, 454.5 94 -1.0 453.5 95 -1.0 452.5 96 -1.0 451.5 97 -1.0 450.5 98 -1.0 449.5 99 -1.0 448.5 100 -1.0 447.5 101 -1.0 446.5 102 -1.0 445.5 103 -1.0 444.5 104 -1.0 443.5 105 -1.0 442.5 106 -1.0 441.5 107 -1.0 440.5 108 -1.0 439.5 109 -1.0 438.5 110 -1.0 437.5 111 -1.0 436.5 112 -1.0 435.5 113 -1.0 434.5 114 -1.0 433.5 115 -1.0 432.5 116 -1.0 431.5 117 -1.0 430.5 118 -1.0 429.5 119 -1.0 428.5 120 -1.0 427.5 121 -1.0 426.5 122 -1.0 425.5 123 -1.0 424.5 124 -1.0 423.5 125 -1.0 422.5 126 -1.0 421.5 127 -1.0 420.5 128 -1.0 419.5 129 -1.0 418.5 130 -1.0 417.5 131 -1.0 416.5 132 -1.0 415.5 133 -1.0 414.5 134 -1.0 413.5 135 -1.0 412.5 136 -1.0 411.5 137 -1.0 410.5.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 78 of 123 138 -1.0 409.5 139 -1.0 408.5 140 -1.0 407.5 141 -1.0 406.5 142 -1.0 405.5 143 -1.0 404.5 144 -1.0 403.5 145 -1.0 402.5 146 -1.0 401.5 147 -1.0 400.5 148 -1.0 399.5 149 -1.0 398.5 150 -1.0 397.5 151 -1.0 396.5 152 -1.0 395.5 153 -1.0 394.5 154 -1.0 393.5 155 -1.0 392.5 156 -1.0 391.5 157 -1.0 390.5 158 -1.0 389.5 159 -1.0 388.5 160 -1.0 387.5 161 -1.0 386.5 162 -1.0 385,5 163 -1.0 384.5 164 -1.0 383.5 165 -1.0 382.5 166 -1.0 381.5 167 -1.0 380.5 168 -1.0 379.5 169 -1.0 378.5 170 -0.9 339.8 171 -0.9 338.9 172 -0.9 338.0 173 -0.9 337.1 174 -0.9 336.2 175 -0.9 335.3 176 -0.9 334.4 177 -0.8 296.4 178 -0.8 295.6 179 -0.8 294.8 180 -0.8 294.0 181 -0.8 293.2 182 -0.8 292.4 183 -0.8 291.6 184 -0.8 290.8 185 -0.7 253.8
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 79 of 123 186 -0.7 253.0 1,87 -0,7 252.3 188 -0.7 251.6 189 -0.6 215.1 190 -0.6 214,5 191 -0.6 213.9 192 -0.6 213.3 193 -0.6 212.7 194 -0.6 212.1 195 -0.6 211.5 196 -0.6 210.9 197 -0.6 210.3 198 -0.6 209.7 199 -0.6 209.1 200 -0.6 208.5 201 -0.5 173.3 202 -0.5 172.8 203 -0.5 172.3 204 -0.5 171.8 205 -0.5 171.3 206 -0.5 170.8 207 -0.5 170.3 208 -0.5 169.8 209 -0.5 169.3 210 -0.5 168.8 211 -0.5 168.3 212 -0.5 167.8 213 -0.5 167.3 214 -0.5 166.8 215 -0.5 166.3 216 -0.5 165.8 217 -0.5 165.3 218 -0.5 164.8 219 -0.5 164.3 220 -0.5 163.8 221 -0.5 163.3 222 -0.5 162.8 223 -0.5 162.3 224 -0.5 161.8 225 -0.5 161.3 226 -0.5 160.8 227 -0.5 160.3 228 -0.5 159.8 229 -0.5 159.3 230 -0.5 158.8 231 -0.5 158.3 232 -0.5 157.8
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 80 of 123 233 -0.5 157.3 234 -0.5 156.8 235 -0.5 156.3 236 -0.5 155.8 237 -0.5 155.3 238 -0.5 154.8 239 -0.5 154.3 240 -0.5 153.8 241 -0.5 153.3 242 -0.5 152.8 243 -0.5 152.3 244 -0.5 151.8 245 -0.5 151.3 246 -0.5 150.8 247 -0.5 150.3 248 -0.5 149.8 249 -0.5 149.3 250 -0.5 148.8 251 -0.5 148.3 252 -0.5, 147.8 253 -0.5 147.3 254 -0.5 146.8 255 -0.5 146.3 256 -0.5 145.8 257 -0.5 145.3 258 -0.5 144.8 259 -0.-5 144.3 260 -0.5 143.8 261 -0.5 143.3 262 -0.5 142.8 263 -0.5 142.3 264 -0.5 141.8 265 -0.5 ' 141,3 266 -0.5 140.8 267 -0.5 140.3 268 -0.5 139.8 269 -0.5 139.3 270 -0.5 138.8 271 -0.5 138.3 272 -0.5 137.8 273 -0.5 137.3 274 -0.5 136.8 275 -0.5 136.3 276 -0.5 135,8 277 -0.5 135.3 278 -0.5 134.8 279 -0.5 134.3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 I Page 81 of 123 280 -0.5 133.8 281 -0.5 133.3 282 -0.5 132.8 283 -0.5 132.3 284 -0.5 131.8 285 -0.5 131,3 286 -0.5 130.8 287 -0.5 130.3 288 -0.5 129.8 289 -0.5 129.3 290 -0.5 128.8 291 -0.5 128,3 292 -0.5 127.8 293 -0.5 127.3 294 -0.5 126.8 295 -0.5 126.3 296 -0.5 125.8 297 -0.5 125.3 298 -0.5 124.8 299 -0.5 124.3 300 -0,5 123.8 301 -0.5 123.3 302 -0.5 122.8 303 -0.5 122.3 304 -0.5 121.8 305 -0.5 121.3 306 -0.5 120.8 307 -0.5 120.3 308 -0.5 119.8 309 -0,5 119.3 310 -0.5 118.8 311 -0.5 -118.3 312 -0.5 117.8 313 -0.5 1-17.3 314 -0.5 116.8 315 -0.5 116.3 316 -0.5 115.8 317 -0.5 115.3 318 -0.5 114.8 319 -0.5 114.3 320 -0.5 113.8 321 -0.5 113.3 322 -0.5 112.8 323 -0.5 112.3 324 -0.5 111.8 325 .-0.5 111.3 326 -0.5. 110.8 327 -0.5 110.3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 82 of 123 328 -0.5 109.8 329 -0.5 109.3 330 -0.5 108.8 331 -0.5 108.3 332 -0.5 107.8 333 -0.5 107.3 334 -0.5 106.8 335 -0.5 106.3 336 -0.5 105.8 337 -0.5 105.3 338 -0.5 104.8 339 -0.5 104.3 340 -0.5 103.8 341 -0.5 103.3 342 -0.5 102.8 343 -0.5 102.3 344 -0.5 101.8 345 -0.5 101.3 346 -0.5 100.8 347 -0.5 100.3 348 -0.5 99.8 349 -0.5 99.3 350 -0.5 98.8 351 -0.5. 98.3 352 -0.5 97.8 353 -0.5 97.3 354 -0.5 96.8 355 -0.5 96.3 356 -0.5 95.8 357 -0.5 95.3 358 -0.5 94.8 359 -0.5 94.3 360 -0.5 93.8 361 -0.5 93.3 362 -0.5 92.8 363 -0.5 92.3 364 -0.5 91.8 365 -0.4 73.0 366 -0.4 72.6 367 -0.4 72.2 368 -0.4 71.8 369 -0.4 71.4 370 -0.4 71.0 371 -0.4 70.6 372 -0.4 70.2 373 -0.4 69.8 374 -0.4 69.4
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 83 of 123 375 -0.4 69.0 376 -0.4 68.6 377 -0.3 51.2 378 -0.3 50.9 379 -0,3 50.6 380 -0.3 50.3 381 -0.3 50.0 382 -0.3 49.7 383 -0.3 49.4 384 -0.3 49.1 385 -0.3 48.8 386 -0.3 48.4.
387 -0.3 48.1 388 -0.3 47.8 389 -0.3 47.5 390 -0.3 47.2 391 -0.3 46.9 392 -0.2 31.1 393 -0.2 30.9 394 -0.2 30.7 395 -0.2 30.5 396 -0.2 30.3 397 -0.2 30.1 398 -0.2 29.9 399 -0.2 29.7 400 -0.2 29.5 401 -0.2 29.3 402 -0.2 29.1 403 -0.2 28.9 404 -0.2 28.7 405 -0.2 28.5 406 -0.2 28.3 407 -0.2 28.1 408 -0.1 14.0 409 -0.1 13.9 410 -0.1 13.7 411 -0.1 13.6 412 -0.1 13.5 413 -0.1 13.4 414 -0.1 13.3.
415 -0.1 13.2 416 -0.1 13.1 417 -0.1 13.0 418 -0.1 12.9
- 419 -0.1 12.8 420 -0.1 12.7 421 0.0 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3
... . Page 84 of 123 422 0.0 0.0 423 0.0 0.0 424 0.0 0.0 425 0.0 0.0 426 0.0 0.0 427 0.0 0.0 428 0.0 0.0 429 0.0 0.0 430 0.0 0.0 431 0.0 0U0 432 0.0 0.0 433 0.0 0.0 434 0.0 0.0 435 0.0 0.0 436 0.0 0.0 437 0.0 0.0 438 0.0 0.0 439 0.0 0.0 440 0.0 0.0 441 0.0 0.0 442 0.0 0.0 443 0.0 0.0 444 0.0 0.0 445 0.0 0.0 446 0.0 0.0 447 0.0 0.0 448 0.0 0.0 449 0.0 0.0 450 0.0 0.0 451 0.0 0.0 452 0.0 0.0 453 0.0 0.0 454 0.0 0U0 455 0.0 0.0 456 0.0 0.0 457 0.0 0.0 458 0.0 0.0 459 0.0 0.0 460 0.0 0.0 461 0.0 0.0 462 0.0 0.0 463 0.0 0.0 464 0.0 0.0 465 0.0 0.0 466 0.0 0.0 467 0.0 0.0 468 0.0 0.0 469 0.0 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 85 of 123 470 0.0 0.0 471 0.0 0.0 472 0.0 0.0 473 0.0 0.0 474 0.0 0.0 475 0.0 0.0 476 0.0 0.0 477 0.0 0.0 478 0.0 0.0 479 0.0 0.0
,480 0.0 0.0 481 0.0 0.0 482 0.0 0.0 483 0.0 0.0 484 0.0 0.0 485 0.0 0.0 486 0.0 0.0 487 0.0 0.0 488 0.0 0.0 489 0.0 0.0 490 0.0 0.0 491 0.0 0.0 492 0.0 0.0 493 0.0 0.0 494 0.0 0.0 495 0,0 0,0 496 0.0 0.0 497 0.0 0.0 498 0.0 0.0 499 0.0 0.0 500 0.0 0.0 501 0.0 0.0 502 0.0 0.0 503 0.0 0.0 504 0.0 0.0 505 0.0 0.0 506 0.0 0.0 -
507 0.0 0.0 508 0.0 0.0 509 0.0 0.0 510 0.0 0.0 511 0.0 0.0 512 0.0 0.0 513 0.0 0.0 514 0.0 0.0 515 0.0 0.0 516 0.0 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3
.... Page 86 of 123 517 0.0 0.0 518 0.0 0.0 519 0.0 0.0 520 0.0 0.0 521 0.0 0.0 522 0.0 0.0 523 0.0 0.0 524 0.0 0.0 525 0.0 0.0 526 0.0 0.0 527 0.0 0.0 528 0.0 0.0 529 0.0 0.0 530 0.0 0.0 531 0.0 0.0 532 0.0 0.0 533 0.0 0.0 534 0.0 0.0 535 0.0 0.0 536 0.0 0.0 537 0.0 0.0 538 0.0 0.0 539 0.0 0.0 540 0.0 0.0 541 0.0 -0.0 542 0.0 0.0 543 0.0 0.0 544 0.0 0.0 545 0.0 0.0 546 0.0 0.0 547 0.0 0.0 548 0.0 0.0 549 0.0 0.0 550 0.0 0.0 551 0.0 0.0 552 0.0 0.0 553 0.0 0.0 554 0.0 0.0 555 0.0 0.0 556 0.0 0.0 557 0.0 0.0 558 0.0 0.0 559 0.0 0.0 560 0.0 0.0 561 0.0 0.0 562 0,0 0.0 563 0.0 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 87 of 123 564 0.0 0.0 565 0.0 0.0 566 0.0 0.0 567 0.0 0.0 568 0.0 0.0 569 0.0 0.0 570 0.0 0.0 571 0.0 0.0 572 0.0 0.0 573 0.0 0.0 574 0.0 0.0 575 0.0 0.0 576 0.0 0.0 577 0.0 0.0 578 0.0 0.0 579 0.0 0.0 580 0.0 0.0 581 0.0 0.0
-582 0.0 0.0 583 0.0 0.0 584 0.0 0.0 585 0.0 0.0 586 0.0 0.0 587 0.0 0.0 588 0.0 0.0 589 0.0 . 0.0 590 0.0 0.0 591 0.0 0.0 592 0.0 0.0 593 0.0 0.0 594 0.0 0.0 595 0.0 0.0 596 0.0 0.0 597 0.0 0.0 598 0.0 0.0 599 0.0 0.0 600 0.0 0.0 601 0.0 0.0 602 0.0 0.0 603 0.0 0.0 604 0.0 0.0 605 0.0 0.0 606 0.0 0.0 607 0.0 0.0 608 0.0 0.0 609 0.0 0.0 610 0.0 0.0 611 0.0 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 88 of 123 612 0.0 0.0 613 0.0 0.0 614 0.0 0.0 615 0.0 0.0 616 0.0 0.0 617 0.0 0.0 618 0.0 0.0 619 0.0 0,0 620 0.0 0.0 621 0.0 0.0 622 0.0 0.0 623 0.0 0.0 624 0.0 0.0 625 0.0 0.0 626 .0.0 0.0 627 0.0 0.0 628 0.0 0.0 629 0.0 0.0 630 0.0 0.0 631 0.0 0.0 632 0.0 0.0 633 0.0 0.0 634 0.0 0.0 635 0.0 0.0 636 0.0 0.0 637 0.0 0.0 638 0.0 0.0 639 0.0 0.0 640 0.0 0.0 641 0.0 0.0 642 0.0 0.0 643 0.0 0.0 644 0.0 0.0 645 0.0 0.0 646 0.0 0.0 647 0.0 0U0 648 0.0 0,0 649 0.0 0.0 650 0.0 0.0 651 0.0 0.0 652 0.0 0.0 653 0.0 0.0 654 0.0 0.0 655 0.0 0.0 656 0.0 0.0 657 0.0 0.0
- 658 0.0 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3
.... Page 89 of 123 659 0.0 0.0 660 0.0 0.0 661 0.1 11.3 662 0.1 11.4 663 0.1 11.5 664 0.1 11.6 665 0.1 11.7 666 0.1 11.8 667 0.1 11.9 668 0.1 12.0 669 0.1 12.1 670 0.1 12.2 671 0:1 12.3 672 0.1 12.4 673 0.1 12.6 674 0.2 25.3 675 0.2 25.5 676 0.2 25.7 677 0.2 25.9 678 0.2 26.1 679 0.2 26.3
.680 0.2 26.5 681 0.2 26.7 682 0.2 26.9 683 0.2 27.1 684 0.2 27.3 685 0.2 27.5 686 0.2 27.7 687 0.2 27.9 688. 0.3 42.1 689 0.3 42.4 690 0.3 42.7 691 0.3 43.1 692 0.3 43.4 693 0.3 43.7 694 0.3 44.0 695 0.3 44.3 696 0.3 44.6 697 0.4 59.8 698 0.4 60.2 699 0.4 60.6 700 0.4 61.0 701 0.4 61.4 702 0.4 61.8 703 0.4 62.2 704 0.4 62.6 705 0.4 63.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 90 of 123 706 0.4 63.4 707 0.4 63.8 708 0.5 80.3 709 0.5 80.8 710 0.5 81.3 711 0.5 81.8 712 0.5 82.3 713 0.5 82.8 714 0.5 83.3 715 0.5 83.8 716 0.5 84.3 717 0.5 84.8 718 0.5 85.3 719 0.5 85.8 720 0.5 86.3 721 0.5 86.8 722 0.5 87.3 723 0.5 87.8 724 0.5 88.3 725 0.5 88.8 726 0.5 89.3 727 0.5 89.8 728 0.5 90.3 729 0.5 90.8 730 0.5 91.3 731 0.5 91.8 732 0.5 92.3 733 0.5 92.8 734 0.5 93.3
.735 0.5 93.8 736 0.5 94.3 737 0.5 94.8 738 0.5 95.3 739 0.5 95.8
,740 0.5 96.3 741 0,5 96.8 742 0.5 97.3
.743 0.5 97.8 744 0.5 98.3 745 0.5 98.8 746 0.5 99.3 747 0.5. 99.8 748 0.5 100.3 749 0.5 100.8 750 0.5 101.3 751 0.5 101.8 752 0.5 102,3 753 0.5 102.8
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 91 of 123 754 0.5 103.3 755 0.5 103.8 756 0.5 104.3 757 0.5 104.8 758 0.5 105.3 759 0.5 105.8 760 0.5 106.3 761 0.5 106.8 762 0.5 107.3 763 0.5 107.8 764 0.5 108.3 765 0.5 108.8 766 0.5 109.3
.767, 0.5 109.8 768 0.5 110.3 769 0.5 110.8 770 0.5 111.3 771 0.5 111.8 772 0.5 112.3
- 773 0.5 112.8 774 0.5 113.3 775 0.5 113:8 776 0.5 114.3 777 0.5 114.8 778 0.5 115.3 779 0.5 115.8.
780 0.5 116.3.
781 0.5 116.8 782 0.5 117.3 783 0.5 117.8 784 0.5 118.3 785 0.5 118.8 786 0.5 119.3 787 0.5 119.8 788 0.5 120.3 789 0.5 120.8 790 0.5 121.3 791 0.5 121.8 792 0.5 122.3 793 0.5 122.8 794 0.5 123.3 795 0.5 123.8 796 0.5 124.3 797 0.5 124.8 798 0.5 125.3 799 0.5 125.8 800 0.5 126.3 801 0.5 126.8
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 92 of 123 802 0.5 127.3 803 0.5 127.8 804 0.5 128.3 805 0.5 128.8 806 0.5 129.3 807 0.5 129.8 808 0.5 130.3 809 0.5 130.8 810 0.5 131.3 811 0.5 131.8 812 0.5 132.3 813 0.5 132.8 814 0.5 133.3 815 0.5 133.8 816 0.5 134.3 817 0.5 134.8 818 0.5 135.3 819 0.5 135.8 820 0.5 136.3 821 0.5 136.8 822 0.5 137.3 823 0.5 137.8 824 0.5 138.3
'825 0,5 138.8 826 0.5 139.3 827 0.5 139.8 828 0.5 140.3 829 0.5 140.8 830 0.5 141.3 831 0.5 141.8 832 0.5 142.3 833 0.5 142.8 834 0.5 143.3 835 0.5 143.8 836 0.5 .144.3 837 0.5 144.8 838 0.5 145.3 839 0.5 145.8 840 0.5 146.3 841 0.5 146.8 842 0.5 147.3 843 0.5 147.8 844 0.5 .148.3 845 0.5 148.8 846 0.5 149.3 847 0.5 149.8 848 0.5 150.3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 93 of 123 849 0.5 150.8 850 0.5 151.3 851 0.5 151.8 852 0.5 152.3 853 0.5 152.8 854 0.5 153.3 855 0.5 153.8 856 0.5 154.3
=857 0.5 154.8 858 0.5 155.3 859 0.5 155.8 860 0.5 156.3 861 0.5 156.8 862 0.5 157.3 863 0.5 157.8 864 0.5 158.3 865 0.5 158.8 866 0.5 159.3 867 0.5 159.8 868 0.5 160.3 869 0.5 160.8 870 0.5 161.3 871 0.5 161.8 872 0.5 162.3 873 0.5 162.8 874 0.5 163.3 875 0.5 163.8 "876 0.5 164.3 877 0.5 - 164.8 878 0.5 165.3 879 0.5 165.8 880 0.5 166.3 881 0.5 166.8 882 0.5 167.3 883 0.5 167.8 884 0.5 168.3 885 0.5 168.8 886 0.5 169.3 887 0.5. 169.8 888 0.5 170.3 889 0.5 170.8 890 0.5 171.3 891 0.5 171.8 892 0.5 172.3 893 0.5 172.8 894 0.5 173.3 895 0.5 173.8 896 0.5. 174.3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 94 of 123 897 0.5 174.8 898 0.5 175.3 899 0.5 175.8 900 0.5 176.3 901 0.5 176.8 902 0.5 177.3 903 0.5 177.8 904 0.5 178.3 905 0.5 178.8 906 0.5 179.3 907 0.6 215.7 908 0.6 216.3 909 0.6 216.9 9.10 0.7 253.7 911 0.7 254.4 912 0.7 255.1 913 0.7 255.8 914 0.7 256.6 915 0.7 257.3 916 0.7 258.0 917 0.8 295.6 918 0.8 296.4 919 0.8 297.2 920 0.8 298.0 921 0.8 298.8 922 0.8 299.6 923 0.8 300.4 924 0.8 301.2 925 0.8 302.0 926 0.8 302.8 927 0.8 303.6 928 0.9 342.4 929 0.9 343.4 930 0.9 344.3 931 0.9 345.2 932 1.0 384.5 933 1.0 385.5 934 1.0 386.5 935 1.0 387.5 936 1.0 388.5 937 1.0 389.5 938 1.0 390.5 939 1.0 391.5 940 1.0 392.5 941 1.0 393.5 942 1.0 394.5 943 1.0 395.5 944 1.0 396.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 95 of 123 945 1.0 397.5 946 1.0 398.5 947 1.0 399.5 948 1.0 400.5 949 1.0 401.5 950 1.0 402.5 951 1.0 403.5 952 1.0 404.5 953 1.0 405.5 954 1.0 406.5 955 1.0 407.5 956 1.0 408.5 957 1.0 409.5 958 1.0 410.5 959 1.0 411.5 960 1.0 412.5 961 1.0 413.5 962 1.0 414.5 963 1.0 415.5 964 1.0 416.5 965 1.0 417.5 966 1.0 418.5 967 1.0 419.5 968 1.0 420.5 969 1.0 421.5 970 1.0 422.5 971 1.0 423.5 972 1.0 424.5 973 .1.0 425.5 974 1.0 426.5 975 .1.0 427.5 976 1.0 428.5 977 .1.0 429.5 978 1.0 430.5 979 1.0 431.5 980 1.0 432.5 981 1.0 433.5 982 1.0 434.5 983 1.0 435.5 984 1.0 436.5 985 1.0 437.5 986 1.0 438.5 987 1.0 439.5 988 1.0' 440.5 989 1.0 441.5 990 1.0 442.5 991 .1.0 443.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 96 of 123 992 1.0 444.5 993 1.0 445.5 994 1.0 446.5 995 1.0 447.5 996 1.0 448.5 997 1.0 449.5 998 1.0 450.5 999 1.0 451.5 1000 1.0 452.5 1001 1.0 453.5 1002 1.0 454.5 1003 1.0 455.5 1004 1.0 456.5 1005 1.0 457.5 1006 1.0 458.5 1007 1.0 459.5 1008 1.0 460.5 1009 1.0 461.5 1010 1.0 462.5 1011 1.0 463.5 1012 1.0 464.5 1013 1.0 465.5 1014 1.0 466.5 1015 1.0 467.5 1016 1.0 468.5 1017 1.0 469.5 1018 1.0 470.5 1019 1.0 471.5 1020 1.0 472.5 1021 1.0 473.5 1022. 1.0 474.5
.1023 1.0 475.5 1024 1.0 476.5 1025 1.0 477.5 1026 1.0 478.5 1027 1.1 527.4 1028 1.1 528.5 1029 1.1 529.6 1030 1.1 530.7 1031 1.1 531.8 1032 1.1 532.9 1033 1.1 534.0 1034 1.2 583.8 1035 1.2 585.0 1036 1.2 586.2 1037 1.3 636.3 1038 1.3 637.7 1039 1.3 639.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 97 of 123 1040 1.4 689.5 1041 1.4 690.9 1042 1.5 741.8 1043 1.5 743.3 1044 1.5 744.8 1045 1.5 746.3 1046 1.5 747.8 1047 1.5 749.3
.1048 1.5 750.8 1049 1.5 752.3 1050 1.5 753.8 1051 1.5 755.3 1052 1.5 756.8 1053 1.5 758.3 1054 1.5 759.8 1055 1.5 761.3 1056 1.5 762.8 1057 1.5 764.3 1058 1.5 765.8 1059 1.5 767.3 1060 1.5 768.8 1061 1.5 770.3 1062 1.5 771:8 1063 1.5 773.3 1064 1.5 774.8 1065 1.5 776.3 1066 1.5 777.8 1067 1.5 779.3 1068 1.5 780.8 1069 1.5 782.3 1070 1.5 783.8 1071 1.6 837.6 1072 1.7 891.6 1073 1.7 893.3 1074 2.0 1053.0 1075 2.0 1055.0 1076 2.0 1057.0 1077 2.0 1059.0 1078 2.0 1061.0 1079 2.0 1063.0 1080 2.0 1065.0 1081 2.0 1067.0 1082 2.0 1069.0 1083 2.2 1178.1 1084 2.4 1287.6
- 1085 3.0 1612,5 1086 3.0 1615.5 1087 3.2 1726.4
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page .98 of 123 1088 3.5 1891.8 1089 3.5 1895.3 1090 3.5 1898.8 1091 4.0 2174.0 1092 4.0 2178.0 1093 4.0 2182.0 1094 4.5 2459.3 D' Test Analysis D' Test S2 852.5 Total (n) 1094 T 278877.9 95% Significance Limits 9833.6 9959.7 D' 9551.5 Since the result of the D' test show the calculated value of D' is outside the 95% significance interval, the assumption of normality is rejected. According to this statistical test, the data set does not fall under the criteria of a normal distribution.
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 99 of 123 Normality Test - Coverage Analysis
- Per % Per Normal Bin # Bin Range Bin Bin Distribution 1 _" to -2.5s 10 0.009 0.0062 2 -2.5s to -2s 14 0.013 0.0166 3 -2s to -1.5s 28 0.026 0.0440 4 -1.5s to -s 124 0.113 0.0919 5 -s to -0.5s 188 0.172 0.1498 6 05s to - 296 0.271 0.1915 7 x to 0.Ss 47 0.043 0.1915 8 0.5s to s 220 0.201 0.1498 9 sto 1.5s 112 0.102 0.0919 10 1.5s to 2s 34 0.031 0.0440 11 2s to 2.5s 10 0.009 0.0166 12 2.5s to -o 11 0.010 0.0062 Coverage Analysis 0.300 0.200 0E 0.100(O 0 ~o
"ý U.) -r- U-) WU IDo -L U U-) 04 LO U)
PUo _ 0) .2 W 02 -0 CýC-14 cý E Bin Range I Drift Data - Normal Distribution Of the 1094 data points, 1049 are found within 2 standard deviations of the mean. This is approximately equal to 95.9% of the data.
Drift Tolerance Interval (TI) 95%195%
Tolarance Interval
.TI = s TIF *NAF S= 0.88 TIF 1.96 NAF I T1 1.73 Plot Time Dependency Testing - Drift Interval Drift Interval Plot 2.0 t - ..- - .--
-=* - - : i * -iL~~ *
- 2.0 1.,0 % " **ii*" * **" : ÷j I- f 41 5.0 0.0 0.5 1.0 1.5 2.0 2.5 3..
Calibration Interval (months)
- Drift Value - - " +TI -- TI - Linear (Drift Value)
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 101 of 123 Time Dependency Testing - Binnin Analysis 1 2 3 0 to 1.25 > 1.25 to 3.75 - > 3.75 to 7.5 months months months Cl Drift Cl Drift Cl Drift (Months) (psid) (Months) (psid) (Months) (psid) 0.0 0.0 1.3 -0.5 4.6 4.0 0.0 -0.1 1.3 -0.5 4.6 -1.0 0.3 -1.0 1.3 -0.5. 4.6 0.0 0.7 -1.5 1.3 -0.5 4.6 0.0 0.7 -1.0 1.3 -1.0 4.6 0.5 0.7 -1.0 1.3 -0.5 4.6 -1.0 0.7 0.0 1.3 0.0 4.6 0.0 0.7 0.5 1.3 1.5 4.6 0.0 0.7 -0.2 1.3 1.0 4.6 0.0 0.7 -0.5 1.3 1.0 4.6 0.0 0.7 -0.5 1.3 0.5 4.6 0.0 0.7 1.0 1.3 0.5 4.6 0.0 0.7 -1.0 1.3 -1.5 4.6 0.0 0.7 -0.5 1.3 0.5 4.6 0.0 0.7 0.5 1.3 1.0 4.6 0.0 0.7 0.5 1.3 0.0 4.6 -3.0 0.7 -1.2 1.3 1.0 0,7 -1.5 1.3 0.0 0.7. -1.0 1.3 0.5 1.2 1.5 1.3 1.5 1.2 -0.5 1.3 0.5 1.3 1.0 1.3 0.5 1.3 -0.5 1.3 1.0 1.3 0.5 1.3 0.0 1.3 0.0 1.3 0.0 1.3 0.0 1.3 0.0
.1.4 -4,5 1.4 0.5" 1.4 1.0 1.4 -1.0 1.4 -1.0 1.4 -0.5 1.4 0.5 1.4 -0.5 1.4 -1.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis.Spreadsheets Attachment 3 Page 102 of 123 1.4 -0.5 1.4 0.0 1.4 0.0 1.4 -1.0 1.4 -1.0 1.4 0.0 1.4 -1.0 1.4 -0.5 1.4 -0.5 1.4 0.5 1.4 0.0 1.4 -0.5 1.4 0.5 1.4 0.5 1.4 0.5 1.4 1.0 1.4 0.5 1.5 0.0 1.5 0.0 1.5 0.0 1.5 0.5 1.5 0.5 1.5 1.5 1.5 0.0 -_
1.5 0.5 1.5 0.5 1.5 0.5 1.51 0.5 1.5 0.5 1.5 0.0 1.5 -2.0 1.5 0.0 1.5 -1.0 1.6 3.5 1.6 -0.5 1.6 -0.5 1.6 0.0 1.6 U0.5 1.6 -0.5 1.6 0.5 1.6 0.0 1.6 0.0 1.6 -1.0 1.6 0.0 1.6 -1.5 1.6 0.5 1.6 -0.5 1.6 -0.3
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 103 of 123 1.7 -4.0 1.7 0.3 1.7 0.0 1.7 0.2 1.7 -0.4 1.7 1.0 1.7 4.5 1.7 -0.5 1.7 0.5 1.7 0.0 1.7 -0.2 1.7 0.5 1.7 0.5 1.7 0.5 1.7 0.0 1.7 0.5 1.7 0.0 1.7 0.5 1.7 0.5 1.7 0.5 1.7 0.0 1.7 -0.1 1.7 0.0 1.7 0.1 1.7 -0.5 1.7 0.5 1.7 0.0 1.8 -1.5 2.4 -1.5 2.4 0.5 2.4 0.5 2.4 1.0 2.4 -0.5 2.4 1.2 2.4 0.0 2.4 0.5 2.4 0.0 2.4 1.5 2.4 -0.5 2.4 0.0 2.5 1.0 2.5 2.0 2.5 2.0 2.5 0.5 2.6 -1.0 2.6 0.0 2.6 0.5 2.6 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 104 of 123 2.6 0.0 2.6 -0.5 2.6 -0.5 2.6 0.0 2.6 0.5 2.6 0.0 2.6 -1.0 2.6 0.0 2.6 -0.7 2.6 0.0 2.6 -0.5 2.6 0.0 2.7 -0.2 2.7 -2.0 2.7 -1.0 2.7 -1.5 2.7 -2.0 2.7 -0.3 2.7 -1.5 2.7 0.0 2.7 -2.5 2.7 -2.0 2.7 -0.5 2.7 -1.5 2.7 -1,5 2.7 -1.5 2.7 -1.5 2.7 -0.5 2.7 -2.5 2.7 3.5 2.7 -3.0 2.7 -2.0 2.7 -2.0 2.7 -0.5 2.7 0.4 2.7 -0.3 2.7 -0.3 2.7 0.1 2.7 -0.6 2.7 -0.1 2.7 0.6 2.7 -0.6 2.7 -0.5 2.7 -0.4 2.7 0.4 2.9 -1.2 2.9 0.5 2.9 -1.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 105 of 123 2.9 -1.0 2.9 -0.9 2.9 0.0 2.9 -0.5 2.9 0.0 2.9 0.8 _
2.9 0.5 2.9 0.0 2.9 0.0 2.9 '-1.4 2.9 1.5 2.9 0.5
_2.9 1.0 2.9 -0.5 2.9 1.0 2.9 0.2 2.9 -1.0 2.9 -1.2 2.9 0.5 2.9 1.0
_2.9 -1.0 2.9 -0.6 2.9 0.5 2.9 0.0 2.9 -0.5 2.9 1.5 2.9 -0,5 2.9 1.0 2.9 -1.3 2.9 0.0 2.9 1.0 2.9 -0.5 2.9 -1.1 2.9 0.0 2.9 -1.5 2:9 -1.0 2.9 -0.8 2.9 0.5 2.9 0.0 2.9 -1.0 2.9 0.0 2.9 0.0 2.9 2.0 2.9 0.1 2.9 -0.5 2.9 1.0 2.9 0.0 2.9 -0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 106 of 123 2.9 1.5 2.9 -0.5 2.9 0.0 2.9 -2.0 2.9 0.0 2.9 -1.0 2.9 -1.0 2.9 0.5 2.9 0.0 2.9 -1.0 2.9 -0.5 2.9 -1.5 2.9 -1.0 2.9 0.0 2.9 0.0 2.9 0.0 2.9 -1.0 2.9 -1.0 2.9 1.0 2.9 0.0 2.9 -1.0 2.9 0.0 2.9 0.1 2.9 -0.5 2.9 -0.5 2.9 -0.5 2.9 -0.5 2.9 -0.8 2.9 -2.0 3.0 0.5 3.0 1.5 3.0 0.0 3.0 0.0 3.0 -0.5 3.0 -1.0 3.0 0.0 3.0 -0.1 3.0 1.0 3.0 -1.0 3.0 0.2 3.0 0.0 3.0 1.5 3.0 0.0 3.0 -0.5 3.0 -0.2 3.0 0.5 3.0 -0.5 3.0 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 I Page 107 of 123 3.0 0.8 3.0 0.8 3.0 0.5 3.0 -0.5 3.0 -0.9
_ _3.0 0.0 3.0 -0.5 3.0 -0.2 3.0 1.0 3.0 0.0 3.0 1.0 3.0 0.5 3.0 0.0 3.0 0.0 3.0 0.4 3.0 0.5 3.0 0.5 3.0 -0.5 3.0 -0.5 3.0 -2.0 3.0 1.0 130 1.0 3.0 -0.5 3.0 -0.5 3.0 -0.2 3.0 -1.0 3.0 .0.0 3.0 -0.6 3.0 0.5 3.0 0.0 3.0 0.5 3.0 1.5 3.0 2.2 3.0 1.0 3.0 -0.5 3.0 -0.2 3.0 -1.1 3.0 -1.0 3.0 -0.5 3.0 -1.0 3.0 1.3 3.0 1.6 3.0 1.0 3.0 -1.5 3.0 0.5 3.0 -0.5 3.0 0.0 3.0 1.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 108 of 123 3.0 1.0 3.0 1.0 3.0 -1.0 3.0 0.0 3.0 1.0 3.0 0.0 3.0 -0.5 3.0 0.5
'3.0 -0.5 _
3.0 0.0 3.0 -1.0 3.0 0.1 3.0 0.0 3.0 0.0 3.0 -0.5 3.0 0.5 3.0 1.4 3.0 0.0 3.0 -0.5 3.0 0.4 3.0 0.1 3.0 0.0 3.0 -1.0 3.0 -0:5 3.0 0.5 3.0 1.5 3.0 1.0 3.0 1.0 3.0 -0.2 3.0 1.5 3.0 -1.0 3.0 0.0
_ 3.0 0.5 3.0 -0.7 3.0 0.0 3.0 -1.0 3.0 -0.1 3.0' -1.0 3.0 -1.0 3.0 -0.5 3.0 2.0 3.0 0.3 3.0 0.5 3.0 -1.0 3.0 0.5 3.0 0.5 3.0 0.0 3.0 0.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 109 of 123 3.0 1.0 3.0 1.0 3,0 1.0 3.0 0.5 3.0 0.4 3.0 -0.3 3.0 0.0.
3.0 -0.5 3.0 -0.5 3.0 1.5 3.0 0.5 3.0 1.0 3.0 -0.5 3.0 0.1 3.0 -0.8 3.0 0.7 3.0 -0.5 3.0 0.0 3.0 0.3 3.0 0.0 3.0 0.5 3.0 0.5 3.0 -3.0 3.0- 0.5 3.0 -1.5 3.0 1.0 3.0 0.0 3.0 -1.0
_ 3.0 -0.5 3,0 1.5 3.0 -0.5 3.0 -2.0 3.0 0.0 3.0 4.0 3.0 -3.0 3.0 -1.0 3.0 -4.0 3.0 0.5 3.0 1.5 3.0 -1.0 3.0 -0.5 3.0 0.5 3.0 -0.6 3.0 0.5 3.0 -0.4 3.0 0.0 3.0 -1.1 3.0 -1.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line'High Flow Setpoint Revision I Drift Analysis Spreadsheets Attachment 3 Page 110 of 123 3.0 0.0 3.0 0.0 3.0 0,5 3.0 -1.0 3.0 0.5 3.0 0.0 3.0 1.0 310 0.0 3.0 -0.5 3.0 -1.0 3.0 0.5 3.0 -0.5 3.0 1.0 3.0 0.5 3.0 0.5 3.0 0.0 3.0 -0.5 3.0 0.5 3.0 -0.5 3.0 1.0 3.0 -0.5 3.0 -0.5 3.0 0.0 3.0 -0.8 3.0 0.0 3.0 -1.1 3.0 0.0 3.0 0.4 3.0 -0.6 3.0 0.0 3.0 1.0 3.0 0.0 3.0 -0.5 3.0 0.5 3.0 -0.5 3.0 -0.5 3.0 0.0 3.0 0.5 3.0 -1.0 3.0 0.5
- _3.0 -0,5 3.0 0.5 3.0 0.0 3.0 -1.0 3.0 0.0 3.0 0.0 3.0 0.2 3.0 -0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision I Drift Analysis Spreadsheets Page 111 of3123 Attachment 3.0 0.5 3.0 -0.5 3.0 0.0 3.0 -0.5 3.0 -0.2 3.0 0.3 3.0 -0.6 3.0 -0.1
...... _ 3 .0 1 .1 3.0 -0.1 3.0 -0.5 3.0 1.0 3.0 -0.5 3.0 -1.0 3.0 -0.5 3.0 0.0 3.0 0.0 3.0 0.5 3.0 -1.0 3.0 0.0 3.0 0.5 3.0 -0.5 3.0 0.5 3.0 -0.5 3.0- 0.0 3.0 -0.5 3.0 0.0 3.0 0.0 3.0 -0.5 3.0 -0.5 3.0 0.5 3.0 -0,5 3.0 -2.0 3.0 -0.5 3.0 0.0 3.0 0.2 3.0 -0.4 3,0 0.1 3.0 0.9
_ 3.0 0.5 3.0 0.0 3.0 0.0 3.0 0.5 3.0 -1.0 3.0 1.0 3.0 0.0
= 3.0 -0.5 1 3.0 0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Paqe 112 of 123 3.0 0.0 3.0 -0.5 3.0 -0.5 3.0 -1.0 3.0 1.0 3.0 0.5 3.0 0.0 3.0 0.5 3.0 -0.5 3.0 -1.0 3.0 -1.0 3.0 0.5 3.0 0.5 3.0 -1.0 3.0 0.5 3.0 -0.4 3.0 0.5 3.0 0.1 3.0 -1.2 3.0 1.7 3.0 -0.1 3.0 0.0 3.0 -0.5 3.0 -1.0 3.0 -0.5 3.0 0.0 3.0 0.0 3.0 0.5 3.0 0.0 3.0 0.0 3.0 -1.0 3.0 -0.5 3.0 -0.5 3.0 1.0 3.0 0.0 3.0 -1.5 3.0 1.5 3.0 0.0 3.0 -0.5 3.0 0.5 3.0 -0.5 3.0 0,5 3.0 0.0 3.0 -0.6 3.0 0.4
.3.0 -0.4 3.0 -0.2 3.0
& 0.8
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint RevisionI Drift Analysis Spreadsheets Attachment 3 Page 113 of 123 3,0 -0.3 3.0 0.5 3.0 0.0 3.0 0.0 3.0 0.0 3,0 0.4 3.0 -0.4 3.0 0.5
_ 3.0 0,5 3.0 -0.5 3.0 -0.5 3.0 0.5 3.0 -1.0 3.0 0.5 3.0 0.5 3.0 -1.0 3.0 2.0 3.0 -2.0 3.0 0.0 3.0 -0.5 3.0 0.5 3,0 -1.0 3.0 1.0 3.0 -1.0 3.0 2.4 3.0 -1.1 3.0 0.2 3.0 1.7 3.0 -0.7 3.0 -0.5 3,0 2.0 3.0 -0.5 3.0 -1.0 3.0 0.5 3.0 0.5 3.0 0.5 3.0 1.5 3.0 -1.0 3.0 -0.5 3.0 1.0 3.0 -1.0 3.0 1.0 3.0 -1.5 3.0 0.5 3.0 0.5 3.0 -1.5 3.0 0.2 3.0 -1.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 114 of 123 3.0 0.5 3.0 0.0 3.0 0.5 3.0 -1.5 3.0 -0.3 3.0 -0.3 3.0 0.2 3.0 -0.1 3.0 -0.1 3.0 1.5 3.0 -0.8 3.0 0.0 3.0 0.5 3.0 0.0 3.0 -1.0 3.0 0.9 3.0 0.1 3.0 -1.0 3.0 1.0 3.0 0.0 3.0 -1.0 3.0 0.0 3.0 -0.5 3.0 0.5 3.0 0.5 3.0 -0.5 3.0 1.0 3.0 -1.0 3.0 -1.0 3.0 -1.0 3.0 1.0 3.0 0.5 3.0 -0.5 3.0 0.0 3.0 -0.2 3.0 0.8 3.0 -0.6 3.0 0.1 3.0 0.2 3.0 -0.3 3.0 0.0 3.0 0.5 3.0 -0.5 3.0 0.0 3.0 0.0 3.0 0.0 3.0 0.0 3.0 0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 115 of 123 3.0 -0.5 3.0 -1.0 3.0 0.5 3.0 -0.5 3.0 0.5 3.0 0.0 3.0 0.0 3.0 0.0 3.0 0.5
_ _ 3.0 0.5 3.0 0.0 3.0 0.5 3.0 0.0 3.0 0.0 3.0 0.0 3.0 0.0 3.0 0.5 3.0 -0.6 3.0 0.4 3.0 0.7 3.0 -0.3 3.0 0.0 3.0 0.5 3.0 0.5 3.0 -0.5 3.0 0.5 3.0 0.0 3.0 0.0 3.0 0.5 3.0 0.5.
3.0 -1.0 3.0 0.0 3.0 0.0 3.0 0.5 3.0 -0.5 3.0 -0.5 3.0 -0.3 3.0 -0.2 3.0 0.0 3.0 0.0 3.0 0.5 3.0 -0.5 3.0 -0.5 3.0 0.0 3.0 0,0 3.0 -0.9 3.0 0.2 3.0 0.7
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 116 of 123 3.0 -0.9 3.0 -0,5 3.0 1.0 3.0 0.0 3.0 -1.0 3.0 0.5 3.0 -1.0 3.0 -1.0 3.0 1.0 3.0 -0.5 3.0 -0.5 3.0 0.5 3.0 -0.5 3.0 0.5 3.0 -1.0 3.0 0.0 3.0 0.5 3.0 -1.0 3.0 0.0 3.0 -1.0 3.0 -1.0 3.0 0.5 3.0 -3.5 3.0 2.0 3.0 -0.9 3.0 0.2 3.0 0.0 3.0 -0.1 3.0 1.5 3.0 -1.4 3.0 -0.5 3.0 1.0 3.0 0.5 3.0 1.3 3.0 -0.3 3.0 0.5 3.0 0.5 3.0 0.0 3.0 -1.5 3.0 0.0 3.0 -0.5 3.0 0.5 3.0 0.0 3.0 -1.0 3.0 1.0 3.0 -0.5 3.0 0.5 3,0 -0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 117 of 123 3.0 0.5 3.0 1.0 3.0 -1.0 3.0 -1.0 3.0 -1.2 3.0 0.7 3.0 -0.8 3.0 0.4 3.0 1.1 3.0 -0.4
_ 3.0 0.0
_ 3.0 0.5
.3.0 0.0 3.0 -0.5 3.0 0.5 3.0 -0.5 3.0 3.0 3.0 4.0 3.0 0.0 3.0 -1.0.
_ _3.0 .1.0 3.0 1.0 3.0 2.0 3.0 -0.5 3.0 0.5 3.0 0.0 3.0 0.0 3.0 -1.0o 3.0 1.0 3.0 -0.5 3.0 1.5 3.0 -2.0 3.0 0.9 3.0 0.5 3.0 -0.3 3.0 0.0 3.0 1.0 3.0 -0.6 3.0 0.0 3.0 0.5_
3.0 0.5
ý.3.0 -0.5,
- 3.0 0.5 3.0 0.0 3.0 0.0 3.0 0.0 3.0 0.0, 3.0 -0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 118 of 123 3.0 0.5 3.0 -1.0 3.0 0.5 3.0 0.5 3.0 -0.5 3.0 0.0 3.0 -0.5 3.0 0.0 3.0 -1.0 3.0 -0.5 3.0 0.0 _
_ _3.0 0.0 3.0 -1.0 3.0 0.8 3.0 -0.9 3.0 '0.1 3.0 0.9 3.0 -0.4 3.0 -0.5 3.0 1.0 3.0 0.0 3.0 -1.0 3.0 0.5 3.0 0.0 3.0 -0.5 3.0 1.0 3.0 -0.5 3.0 -0.5 3.0 0.5 3.0 -1.0 3.0 1.0 3.0 0.5 3.0 -0.5 3.0 0.0 3.0 0.0 3.0 0.5 3.0 -0.5 3.0 0.5 3.0 0.0 3.0 0.0 3.0 -1.0 3.0 3.5 3.0 0.5 3.0 -0.5 3.0 0.0 3.0 -0.5 3.0 -0.5 I 3.0 -1.0
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 119 of 123 3.0 -0.5 3.0 0.0 3.0 0.5 3.0 0.5 3.0 -0.8 3.0 0.0 3.0 0.0 3.0 0.0 3.0 1.0 3.0 0.0 3.0 0.5 3.0 0.5 3.0 0.0 3.0 -0.5 3.0 0.5 3.0 0.5 3.0 1.0 3.0 0.0 3.0 0.0 3.0 -0.3 3.0 1.5 3.0 0.0 3.0 0.0 3.0 0.5 3.0 0.3 3.0 -1.5 3.0 1.0 3.0 0.0 3.0 1.0 3.0 -1.6 3.0 -0.5 3.0 -1.0 3.0 1.0 3.0 0.5 3.0 0.0 3.0 -1.0 3.0 0.0 3.0 0.0 3.0 1.5 3.0 1.0 3.0 0.0 3.0 1.0 3.0 0.5 3.0 0.0 3.0 0.1 130 -1.0 3.0 1.0 3.0 0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 120 of 123 3.0 1.0 3.0 -1.5 3.0 1.0 3.0 0.5 3.0 1.0 3.0 1.0 3.0 1.2 3.0 0.5 3.0 1.0 3.0 1.0 3.0 0.0 3.0 -0.3 3.0 0.5 3.0 0.5 3.0- 0.0 3.0 0.5 3.0 -0.5 3.0 0.0 3.0 2.0 3.0 0.5 3.0 1.5 3.0 -1.0 3.0 0.0 3.0 0.5 3.0 0.5 3.0 0.5 3.0 0.0 3.0 1.0 3.0 0.5 3.0 0.5 3.0 1.0 3.0 0.0 3.0 0.5 3.0 0.5 3.0 0.0 3.0 0.5 3.0 1.0 3.0 0.0 3.0 0.5 3.0 -0.5 3.0 1.0 3.0 0.0 3.0 0.5 3.0 -1.0 3.0 0.5 3.0 0.0 3.0 0.0 3.0 0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 121 of 123 3.0 -2.0 3.0 -0.5 3.0 0.0 3.0 0.5 3.0 1.0 3.0 0.0 3.0 -0.5 3.0 1.0 3.0 1.0 3.1 1.0 3.1 1.1 3.1 0.8 3.1 1.3 3.1 0.2 3.1 3.2 3.1 0.8 3.1 0.3 3.1 1.2 3.1 0.7 3.1 0.4 3.1 0.0 3.1 0.6 3.1 0.8 3.1 0.7 3.1 0.3 3.1 -0.5 3.1 -1.0 3.1 -1.0 3.1 -1.0 3.1 0.0 3.1 -1.0 3.1 -0.5 3.1 -1.0 3.1 0.0 3.1 -1.0 3.1 -0.5 3.1 -0.5 3.1 0.0 3.1 0.5 3.1 0.0 3,1 -0.5 3.2 -0.5 3.2 -0.4 3.2 1.0 3.2 -0.6 3.2 -0.9 3.2 -0.2 3.2 -0.1
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3 Page 122 of 123 3.2 -0.7 3.2 -0.4 3.2 -0.1 3.2 -0.2 3.2 -0.5 3.2 -0.8 3.2 -0.5 3.2 -0.4 3.2 -0.2 3.3 1.0 3.3 3.0 3.3 1.1 3.3 1.0 3.3 -0.2 3.3 1.5 3.3 1.0 3.3 1.0 3.3 0.6 3.3 1.0 3.3 0.8 3.3 1.0 3.3 0.5 3.3 0.5 3.3 1.4 3.3 1.5 3.3 1.1 3.3 1.5 3.3 0.2 3.3 0.5 3.3 0.3 3.3 0.5 3.3 0.0 3.3 0.0 3.3 0.8 3.3 1.0 3.3 1.1 3.3 1.0 3.3 0.7 3.3 1.5 3.3 0.3 3.3 1.5 3.4 0.5 3.4 -0.5 3.4 0.0 3.4 0.5 3.4 -0.5 3.4 0.5 3.4 -0.5
MONTICELLO NUCLEAR GENERATING PLANT CA-95-075 TITLE: Main Steam Line High Flow Setpoint Revision 1 Drift Analysis Spreadsheets Attachment 3
.Page 123 of 123 3.4 -1.0 3.4 0.0 3.4 0.0 3.4 -0.5 3.4 1.0 3.4 0.2
,3.4 0.5 3.4 0.0 3.4 0.0 Bin Range %of Valid?
Bin # (months) Count Total YESINO Data 1 0 to 1.25 21 1.9 NO 2 > 1.25 to 3.75 1057 96.6 YES 3 > 3.75 to 7.5 16 1.5 NO Drift Bin # ADrift e a e St Standard Average C Data o n Average Deviation Cl Count 1 -0.4 0.82 0.7 21 2 0.0 0.88 2.8 1057 3 0.0 1.35 4.6 16 ESM-03.02-APP-III sets forth criteria to perform the binning analysis. One of the requirements is that there are multiple valid bins. A bin is considered valid if it contains at least 5 data points and 10% of the total data. Only the middle bin (> 1.25 to 3.75) meets the criteria. Therefore, the complete binning analysis cannot be.performed on this data. Per the instruction in ESM-03.02-APP-Ill, the data is considered moderately time dependent.