ML072190047

From kanterella
Jump to navigation Jump to search

Unit 2 - Reactivation of Construction Activities
ML072190047
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 08/03/2007
From: Mccollum W
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML072190047 (138)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 August 3, 2007 U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Mail Stop:

OWFN P1-35 Washington, D.C.

20555-0001 Gentlemen:

In the Matter of

)

Docket No.

50-391 Tennessee Valley Authority WATTS BAR NUCLEAR PLANT (WBN)

UNIT 2 -

REACTIVATION OF CONSTRUCTION ACTIVITIES The purpose of this letter is to inform the Nuclear Regulatory Commission (NRC)

Staff of TVA's intention to reactivate and complete construction activities at WBN Unit 2.

As set forth in the TVA's Key Assumptions letter (Reference 1) and recognized by the Commission in the NRC Staff Requirements Memorandum (Reference 2),

TVA will complete the project under the existing construction permit and request an Operating License (OL) pursuant to 10 CFR Part 50.

As background, on October 4,

1976, TVA submitted a dual-unit WBN OL application for both WBN Unit 1 and Unit 2 (Reference 3).

WBN Unit 1 received a full power OL on February 7, 1996.

WBN Unit 2, which currently is in deferred status, would be operationally the same at startup as WBN Unit 1. Therefore, TVA believes that, from regulatory, safety and plant operational perspectives, significant benefit is gained from aligning the licensing and design bases of WBN Units 1 and 2 to the fullest extent practicable.

The Commission recognized these benefits in Reference 2.

Printed on recycled paper

U.S. Nuclear Regulatory Commission Page 2 August 3, 2007 In furtherance of this objective, TVA will complete WBN Unit 2 in compliance with applicable regulations promulgated prior to and after the issuance of the WBN Unit 1 CL.

In addition, the WBN Unit 2 licensing and design bases will incorporate modifications made to WBN Unit 1, and those modifications currently captured in the WBN Unit 1 five-year plan.

This alignment of the WBN Unit 1 and 2 licensing and design bases will ensure that there is operational fidelity between the units and at the same time demonstrate and ensure that WBN Unit 2 complies with applicable NRC regulatory requirements.

In combination, the enclosure to this letter and the accompanying attachments provide the information to be submitted by a licensee at least 120 days prior to the reactivation of construction in accordance with Generic Letter 87-15, "Commission Policy Statement on Deferred Plants" (52 FR 38077, October 14, 1987).

Some of the key points discussed in the enclosure include the following:

TVA currently plans to resume unrestricted construction activities in support of completion of WBN Unit 2 on December 3, 2007.

TVA expects to complete construction and request an operating license prior to April 1, 2012.

TVA will submit a regulatory framework document for Watts Bar Unit 2 similar to the Browns Ferry Status of Unit 1 Restart Issues letters.

This regulatory framework document will reference key correspondence, describe the open issues or commitments that need to be resolved to obtain an OL for WBN Unit 2, discuss the background of the issues or commitments, and describe their completion or status, as appropriate. This document will be periodically updated.

TVA anticipates making no changes to the Site Security Plan or the Site Emergency Plan for purposes of WBN Unit 2 construction reactivation.

Should any changes to the Site Security Plan or the Site Emergency Plan be necessary they will be evaluated and submitted to NRC as required by applicable regulations.

A Unit Separation Program will ensure that WBN Unit 2 construction activities do not adversely affect the continued safe operation of WBN Unit 1. As part of this program, unit separation isolation boundaries will be

U.S. Nuclear Regulatory Commission Page 3 August 3, 2007 administratively controlled using design output (i.e.,

engineering drawings) or the Equipment Clearance Procedure.

Feasibility studies are underway to evaluate the possible creation of construction openings into WBN Unit 2 containment (both equipment and personnel access).

The Unit Separation Program will require moving the secondary containment boundary back to the Auxiliary Building wall and removing the WBN Unit 2 Reactor Building from the Vital Area as well as the Radiological Controlled Area.

This will allow construction access to the WBN Unit 2 containment and minimize traffic in the operating unit.

Prior to resuming construction activities on quality or safety-related structures, systems or components, the Quality Assurance program and procedures will be put in place.

TVA will work with the NRC staff to review any exemptions, reliefs and other actions which were specifically granted for WBN Unit 1 to determine whether the same allowance is appropriate for WBN Unit 2.

TVA's successful operation of WBN Unit 1 provides reasonable assurance that WBN Unit 2 also can be completed successfully and then started and operated in a

safe and reliable manner.

If you have any questions, please contact me at (423) 751-6016 or Masoud Bajestani, WBN Unit 2 Vice-President, at (423) 365-2351.

Sincerely, William R. McCollum, Chief Operating Officer

References:

1. TVA letter, Watts Bar Nuclear Plant (WBN)

- Unit 2 Key Assumptions for the Possible Completion of Construction Activities, dated April 3, 2007.

2.

NRC Staff Requirements -

SECY-07-0096 -

Possible Reactivation of Construction and Licensing Activities for the Watts Bar Nuclear Plant Unit 2, dated July 25, 2007.

U.S. Nuclear Regulatory Commission Page 4 August 3, 2007

3.

TVA letter, Final Safety Analysis Report for Operating License for Watts Bar, Units 1 and 2, dated October 4, 1976.

RRB:JEM:BQP Enclosures

U.S. Nuclear Regulatory Commission Page 5 August 3, 2007 cc (Enclosures):

Catherine Haney, Director U.S. Nuclear Regulatory Commission MS 08G9 One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Lakshminarasimh Raghavan U.S. Nuclear Regulatory Commission MS 08H4A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Loren R.

Plisco, Deputy Regional Administrator for Construction U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center, Suite 23T85 61 Forsyth Street, SW, Atlanta, Georgia 30303-8931 U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Resident Inspector Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

U.S. Nuclear Regulatory Commission Page 6 August 3, 2007 cc (w/o Enclosures):

M. Bajestani, EQB IB-WBN R.

R. Baron, EQB IB-WBN A.

S.

Bhatnagar, LP 6A-C R.

H. Bryan, BR 4X-C J.

C. Fornicola, LP 6A-C M. D.

Skaggs, ADM-lV-WBN J.
Valente, EQB IB-WBN E.

J.

Vigluicci, ET IIA-K

EDMS, WT 3B-K, w/Enclosures Watts Bar Unit 2 Construction Reactivation Generic Letter 87-15, "Commission Policy Statement on Deferred Plants" establishes the NRC's position regarding quality assurance requirements, particularly the maintenance, preservation and documentation requirements for deferred plants, and establishes how new regulatory requirements will be applied to deferred plants upon reactivation. The Policy Statement calls for TVA to notify the NRC Staff of its intentions regarding the reactivation of Watts Bar Nuclear Plant (WBN) Unit 2 at least 120 days prior to the resumption of plant construction.

The information requested in the generic letter (in italics) and TVA's responses are provided as follows:

Commission Policy Statement on Deferred Plants Request 1: The proposed date for resuming construction, a schedule for completing construction, and a schedule for submittal of an operating license (OL) application, including a final safety analysis report (FSAR), if one has not already been submitted.

TVA Response: TVA plans to resume limited construction activities on selected non safety-related equipment like Raw Cooling Water piping replacement and turbine-generator-condenser work on October 1, 2007.

TVA also expects to initiate engineering walkdowns to fully determine the scope of work in late October 2007.

TVA plans to resume unrestricted construction activities in support of completion of Watts Bar Unit 2 on December 3, 2007. TVA expects to complete construction and request an operating license prior to April 1, 2012.

The construction permit for WBN Unit 2 (CPPR-92) is valid through December 31, 2010. A timely application for the extension of the construction permit will be submitted in accordance with 10 CFR 2.109 and 10 CFR 50.55(b).

On October 4, 1976, TVA submitted a dual-unit WBN OL application that included the Final Safety Analysis Report (FSAR) (Amendment 23) for both Watts Bar Units 1 and 2. The FSAR for both WBN Units 1 and 2 was periodically updated as part of the OL review process. The FSAR for WBN Unit 2 was last updated (Amendment 91) on October 24, 1995, in preparation WBN Unit 1 fuel load and issuance of the low power license. There have been no substantive design changes to WBN Unit 2 since submittal of the last FSAR revision for WBN Unit 2 in 1995. The WBN Unit 1 FSAR has been updated in accordance with 1 OCFR 50.71 e and includes the shared equipment supporting WBN Unit 1.

Approximately 18 months prior to requesting permission to load fuel, TVA plans to submit a revised OL application updating the FSAR for WBN Unit 2 and the Technical Specifications.

Commission Policy Statement on Deferred Plants Request 2: The current status of the plant site and operating equipment.

I

TVA Response: WBN Unit 1 is currently operating and WBN Unit 2 is in deferred status. Structures and systems that are shared between Unit 1 and Unit 2 are in operation supporting Unit 1. The structures important to safety that are shared are the Auxiliary Building, Control Building, Diesel Generator Building and the intake pumping station. Shared safety-related systems include the essential raw cooling water, component cooling water, fire protection, spent fuel cooling, fuel oil storage tanks, preferred and emergency electric power, chemical and volume control, radioactive waste, emergency gas treatment system, and Control and Auxiliary Building ventilation systems.

TVA anticipates making no changes to the Site Security Plan or the Site Emergency Plan for purposes of WBN Unit 2 construction reactivation. Should any changes to the Site Security Plan or the Site Emergency Plan be necessary they will be evaluated and submitted to NRC as required by applicable regulations.

Under current TVA requirements, maintenance and layup of Unit 2 equipment is controlled by TVA Procedure TI-273 "Preventive Maintenance for Non-transferred Features". In 2004, NRC approved a revision to the quality assurance plan that allowed TVA to terminate layup preventive maintenance for selected equipment. This program has been continually refined and over time the scope of equipment requiring specific maintenance activities has been reduced based on economic considerations and actual preventive maintenance results. TVA will not take credit for equipment maintained under this reduced program. TVA will confirm that structures, systems and components can perform their intended functions by testing, refurbishment or replacement.

As required, components will be refurbished to bring WBN Unit 2 equipment up to current TVA maintenance program and environmental qualification requirements. This includes, for example, the replacement of seals, gaskets, and packing necessary as a result of the extended construction and layup period for WBN Unit 2. Where operating plant preventive maintenance procedures call for specific intervals of component refurbishment or inspection, these will be implemented, as appropriate, prior to startup in order to ensure that required maintenance is within appropriate periodicity at the time of initial operation.

Commission Policy Statement on Deferred Plants Request 3: A description of how any conditions established by NRC during the deferral have been fulfilled.

TVA Response: TVA suspended construction of WBN Unit 2 in 1985, placed the unit in a construction layup status, and formally deferred WBN Unit 2 in 2000.

TVA has not identified any specific conditions established by NRC during the deferral period.

NRC has conducted periodic inspections of the Layup and Preservation Program implemented at WBN Unit 2 and documented its findings in Inspection Reports. Issues raised by NRC inspections have been acted upon 2

and resolved.

Any open issues that are identified will be addressed in the regulatory framework document.

Commission Policy Statement on Deferred Plants Request 4: A list of licensing issues that were outstanding at the time of the deferral and a description of the resolution or proposed resolution of these issues.

TVA Response:

TVA reviewed the Safety Evaluation Report (SER) and its Supplements (SSERs) (NUREG-0847) related to the operation of Watts Bar Nuclear Plant Units 1 and 2 against the 1981 version of the Standard Review Plan (NUREG 0800) to develop a list of the remaining outstanding issues open for WBN Unit 2. Attachment 1 provides the results of this review. Specifically, lists the outstanding issues, the confirmatory issues and license conditions and provides a reference to the subsequent SSER that resolved them for Unit 1 and 2, as appropriate. As a result of the review, TVA identified the following three outstanding issues for WBN Unit 2:

Preservice Inspection Program,

  • Pressure / Temperature Limits for Unit 2, and Essential Raw Cooling Water (ERCW) for two-unit operation.

Each of these issues is discussed individually below:

Preservice Inspection Program:

The WBN Unit 2 Preservice Inspection Program was last submitted to NRC on April 30, 1990. TVA will provide a revised program for NRC approval.

Pressure / Temperature Limits for Unit 2:

TVA will provide the Pressure Temperature Limits Report for WBN Unit 2 for NRC approval.

ERCW for two-unit operation:

The existing Essential Raw Cooling Water (ERCW) pumps were sized in 1974. In order to license WBN Unit 2, a two-unit preoperational flow balance test will be required. In their present conditions, the ERCW pumps do not provide adequate flow margin to meet the acceptance criteria of a two-unit flow balance test.

An engineering study was performed to determine the best alternative for meeting the design requirements of the ERCW system for two-unit operation.

The alternatives are currently being reviewed. Appropriate measures will be taken to ensure the system is fully capable of meeting design requirements for two unit operation.

3 also provides a listing of NRC Bulletins, Generic Letters and Three Mile Island Items and their status with respect to WBN Unit 2. The Watts Bar Nuclear Performance Plan Corrective Action Programs and Special Programs are listed and their status with respect to Watts Bar Unit 2. The final section of the matrix provides a listing of NRC Regulatory Guides and their applicability to WBN Unit 2.

By way of background, on September 17, 1985, the NRC sent a letter to TVA pursuant to 10 CFR 50.54(f), requesting that TVA submit information on its plans for correcting then-existing problems with the overall management of its nuclear

.program as well as plans for correcting Watts Bar specific issues. In response to that letter, TVA prepared a Corporate Nuclear Performance Plan and a site specific plan for resolution of the outstanding Corrective Action Programs (CAPs) and Special Programs (SPs) for WBN Units 1 and 2 entitled, 'WVatts Bar Nuclear Performance Plan" (WBNPP).

NRC approval of these implementing actions, primarily for WBN Unit 1, is documented in the SER on the Tennessee Valley Authority: Watts Bar Nuclear Performance Plan (NUREG-1232, Volume 4) and NUREG-0847.

TVA has evaluated the CAPs and SPs to determine their applicability to WBN Unit 2. TVA will resolve the WBN Unit 2 CAPs and SPs consistent with NUREG-1232 (Volume 4), NUREG-0847 and applicable regulations. Attachment 2 to this enclosure provides a description of the CAPs and SPs, a summary of their resolution for WBN Unit 1 and a description of their proposed resolution for WBN Unit 2. If, during this process, TVA determines that it is necessary to modify the criteria otherwise specified in NUREG-1232, then it will submit such changes to the NRC for review and concurrence. provides a listing of NRC Generic Letters, Bulletins and TMI Action Items issued before December 31, 1994 and outstanding for Watts Bar Unit 2.

TVA will resolve these in accordance with the outstanding commitments.

A listing of Open Construction Deficiencies Reports (CDRs) will be provided as part of the regulatory framework document. TVA intends to resolve these issues as part of the licensing process.

Commission Policy Statement on Deferred Plants Request 5: A listing of any new regulatory requirements applicable to the plant since construction was deferred, together with a description of proposed plans for compliance or a commitment to submit such plans by a specific date.

TVA Response: The Final Safety Analysis Report (FSAR) was updated for both units on October 24, 1995.

NRC regulatory requirements from Title 10 of the Code of Federal Regulations Part 50 that have become effective since December 31, 1994 are listed in Attachment 4 to this Enclosure. Although not specifically required by the Commission Policy Statement, Attachment 4 also lists Generic 4

Letters and Bulletins applicable to WBN Unit 2. TVA intends to address these issues, as appropriate, as part of the licensing process.

Commission Policy Statement on Deferred Plants Request 6: A description of the management and organization responsible for construction.

TVA Response:

TVA intends to rely on a contractor or contractor team to complete the engineering and construction for Watts Bar Unit 2 with oversight by TVA personnel. Contractor selection is in progress. Attachment 5 describes the TVA construction completion organization.

Commission Policy Statement on Deferred Plants Request 7: A description of all substantive changes made to the plant design or site since the CP was issued (for those plants for which an OL application has not been submitted).

TVA response: This item does not apply to WBN Unit 2, as TVA submitted the WBN Unit 2 OL application to the NRC on October 4, 1976. The application included the FSAR (Amendment 23) for WBN Units 1 and 2.

Commission Policy Statement on Deferred Plants Request 8: Identification of any additional required information that is not available at the time of reactivation and a commitment to submit this information at a specific later date.

TVA Response:

In order to further address the issues discussed under the Commission Policy Statement for Deferred Plants Requests 4 and 5 above, TVA will submit a regulatory framework document for Watts Bar Unit 2 similar to the Browns Ferry Status of Unit 1 Restart Issues letters. This regulatory framework document will reference key correspondence, describe the open issues or commitments that need to be resolved to obtain an OL for WBN Unit 2, discuss the background of the issue, and describe their completion or status, as appropriate. TVA will provide this regulatory framework submittal for WBN Unit 2 by January 31, 2008.

Subsequent to the initial submittal, TVA will provide periodic updates, as appropriate, until the WBN Unit 2 commitments related to fuel load, startup and power operation are complete. These updates will provide formal notification of the completion of each NRC Bulletin, Generic Letter, Nuclear Performance Plan CAP and SP, and TMI Action Item for the applicable WBN Unit 2 plant milestone.

5

Commission Policy Statement on Deferred Plants Request 9: As necessary, an amendment to the OL application (revised FSAR) and a discussion of the bases for all substantive site and design changes that have been made since the last FSAR revision was submitted (for those plants which were already under OL review at the time of deferral).

TVA Response: TVA submitted the OL application for WBN Unit 2 to the NRC on October 4, 1976. The application included the FSAR (Amendment 23) for WBN Unit 1 and 2. The FSAR for WBN Unit 2 was last updated (Amendment 91) on October 24, 1995, in preparation for issuance of the WBN Unit 1 fuel load and low-power OL.

It is important to recognize that WBN Unit 2 was substantially complete when TVA suspended construction in 1985. There have been no substantive design changes issued since submittal of the last FSAR revision for WBN Unit 2 in 1995.

TVA plans to provide a red-line version of the WBN Unit 1 FSAR early in the project. The schedule for submitting this markup FSAR will be provided in the regulatory framework document.

6

Attachments: - Standard Review Plan / Safety Evaluation Report and Supplements - NUREG-0847 Review Matrix. - Outstanding Corrective Action Programs and Special Programs - Listing of Generic Letters, Bulletins and TMI Action Items issued before 1995 - List of new Regulatory Requirements and Generic Communications - Construction Completion Organization - Listing of Commitments made in letter 7

- Standard Review Plan / Safety Evaluation Report and Supplements - NUREG-0847 Review Matrix

Standard Review Plan / Safety Evaluation Report and Supplements (NUREG 0847) Review Matrix Chapter 1 - Introduction and General Description of Plant Chapter 2 - Sites Characteristics Chapter 3 - Design of Structures, Components, Equipment, and Systems Chapter 4 - Reactor Chapter 5 - Reactor Coolant System and Connected Systems Chapter 6 - Engineered Safety Features Chapter 7 - Instrumentation and Controls Chapter 8 - Electric Power Chapter 9 - Auxiliary Systems Chapter 10 - Steam and Power Conversion System Chapter 11 - Radioactive Waste Management Chapter 12 - Radiation Protection Chapter 13 - Conduct of Operations Chapter 14 - Initial Test Program Chapter 15 - Accident Analysis Chapter 16 - Technical Specifications Chapter 17 - Quality Assurance Chapter 18 - Human Factors Engineering (Reviewed in the SER as Control Room Design Review)

Chapter 19 - Severe Accidents The NRC issued an OL Safety Evaluation Report (SER), NUREG-0847 for WBN1 and WBN2 in June 1982. The SER documented NRC's review of the WBN1 and WBN2 designs against Federal Regulations, construction permit criteria, and the NRC Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants ("SRP") otherwise known as NUREG-0800 (Revision 2 dated July 1981). Open issues raised by the reviewer in the SER that were not closed out when the SER was issued were classified into outstanding issues, confirmatory issues, and proposed license conditions. The staff listed 17 outstanding issues in the SER. Additional outstanding issues were added in Supplemental SERs (SSERs) for a total of 28. The SER listed 42 confirmatory actions; issue 43 was added in SSER6. There were 44 proposed Licensing conditions.

Attached is the matrix showing the NRC SRP sections (NUREG 0800) and the WBN1 and 2 SER (June 1982) and the WBN SSERs (1982-1995). The outstanding, confirmatory issues and license conditions are listed and a reference to the subsequent SSER that resolved them for Unit 1 and 2, as appropriate.

Based on TVA's review of the SER and the SSERs, the open issues (outstanding issues, confirmatory issues, and proposed license conditions) for Watts Bar Unit 2 are shown in grey.

I

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 Chapter 2 Site Characteristics 50.34(a)(1), 100.3, 2.1.1 - Site Location and 2.1.1

.10,.11 Description No open issues 50.33, 50.34(a)(1),

2.1.2 - Exclusion Area 2.1.2 100.3,.10,.11 Authority and Control No open issues 50.34(a)(1), 100.3, 2.1.3 - Population 1.70, 4.7 2.13-2.1.4

.10,.11 Distribution No open issues 50.34(a)(1)(i),

2.2.1-2.2.2 - Identification 1.78, 1.91, 2.21-2.2.3 100.10 of Potential Hazards in the No open issues 1.95 Site Vicinity 50.34(a)(1),

3.5.1.5 - Site Proximity 2.2.2 (a)(1)(ii); 100, Missiles (Except Aircraft)

No open issues Subpart A; 100.10, 3.5.1.6 - Aircraft Hazards GDC 3, 4, 5 50.34(a)(1)(i) 2.2.3 - Evaluation of 1.70R3 2.2.3 Potential Accidents No open issues 100.10(c)(2), GDC 2.3.1-Regional 1.76R1, 1.27 2.3.1 2, 4 Climatology No open issues 100.10(c)(2), GDC 2.3.2 - Local Meteorology 1.23, 1.70 2.3.2 2

No open issues 50.47(b)(4), (b)(8),

2.3.3 - Onsite 1.23 2.3.3 (b)(9), Part 50 Meteorological No open issuesSection IV.E.2 of Measurements Programs App E, App I; 100.10(c)(2),

100.11(a); GDC 19; Part 20, Subpart D 100.11(a), GDC 19 2.3.4 - Short term 1.23, 1.78, 2.3.4 Dispersion Estimates for No open issues 1.145, 1.194, 2

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 Accidental Releases 1.3, 1.4,1.5, 1.24, 1.25, 1.77, 1.98, 1.70 20, Par D 2.3.5 - Long term 1.23, 1.109, 2.3.5 Atmospheric Dispersion No open issues 1.111, Estimates for Routine 1.112,1.70 Releases 100.10(c), GDC 2 2.4.1 - Hydrologic 1.27, 1.29, 2.4.2 Description No open issues 1.59, 1.102, 1.70 50.34(a)(1), 100.3, 2.1.1 - Site Location and 1.206 2.4.3

.10,.11 Description No open issues 2.4.3 100, GDC 2 2.4.2 Floods No open issues 1.27, 1.29, 1.59, 1.102, 1.70 100.10(c), GDC 2

.2.4.3 - Probable Maximum 1.27, 1.29, 2.4.3 Flood (PMF) on Streams No open issues 1.59, 1.102, and Rivers 1.70 100.10(c), GDC 2, 2.4.4 - Potential Dam 1.27, 1.29, 2.4.3 44 Failures No open issues 1.59, 1.102, 1.70 NA 100.10 (c), GDC 2, 2.4.5 - Probable 1.27, 1.29, 44 Maximum Surge and Not addressed in SER 1.59, 1.102, Seiche Flooding 1.70 NA 100.10(c), GDC2 2.4.6 - Probable Maximum Not addressed in SER 1.27, 1.29, Tsunami Hazards 1.59, 1.102, 1.70 NA 100.10(c), GDC 2 2.4.7 - Ice Effects Not addressed in SER 1.27, 1.29, 1.59, 1.102, 3

F 1982 10CFR GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional ERNote 2

Note 1 (GL, Bulletins,

Guides Information other)

JNotes 1, 2 1.70 NA 100.10(c), GDC 1, 2.4.8 - Cooling Water Not addressed in SER 1.27, 1.29, 2, 44 Canals and Reservoirs 1.59, 1.102, 1.125,1.70 NA 100.10(c), GDC 2, 2.4.9 - Channel Not addressed in SER 1.27,1.29, 44 Diversions 1.59,1.102 100.10(c); GDC 1, 2.4.10 - Flooding 1.29,1.59, 2.4.3, 2,44 Protection Requirements No outstanding issues 1.102 2.4.10 100.10(c); GDC 2, 2.4.11 - Low Water 1.27, 1.29, 4.4 2.4.6 44 Conditions No outstanding issues 50.55(a), 100.10(c),

2.4.12 - Groundwater 1.27 2.4.7-GDC 1, 2, 5, 44 2.4.8-Confirmatory issue Resolved 2.4.8 for groundwater level for SSER3 ERCW pipeline 100.10(c), GDC 2 2.4.13 - Accidental 1.113 2.4.9 Releases of Liquid No open issues Effluents in Ground and Surface Waters 50.36, Part 100; 2.4.14 - Technical 1.29, 1.59, 2.4.2-2.4.3 100.10(c); GDC 2 & Specifications and No open issues 1.102 44 Emergency Operation Requirements 100.23, GDC 2 2.5.1 - Basic Geological 1.165, 1.208, 2.5, 2.5.1 and Seismic Information No open issues 1.132, 1.198, 4.7 100.23, GDC 2 2.5.2 - Vibratory Ground 1.165, 1.208, 2.5 Motion No open issues 1.132, 1.60, 1.138, 4.7 4

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 100.23, GDC 2 2.5.3 - Surface Faulting 1.165, 1.208, 2.5 No open issues 1.132, 1.198, 4.7 50.55a, Part 50 2.5.4 - Stability of 2.5.4-Outstanding issue Resolved 1.27, 1.28, 2.5.4 Appendix B, Subsurface Materials and on liquefaction potential.

SSER3 1.132, 1.138, 100.23, GDC 1, 2, Foundations 1.198 44 2.5.4-Confirmatory issue Resolved for analysis of sheetpile SSER3 walls and material and geometric damping in soil-structure interaction analysis 2.5.4-Confirmatory issue Resolved for design differential SSER3 settlement of piping and electrical components 50.55a, Part 50 2.5.5 - Stability of Slopes 1.27, 1.28, 2.5.5 Appendix B, No open issues 1.132, 1.138, 100.23, GDC 1, 2, 1.198 44 Chapter 3 - Design of Structures, Components, Equipment, and Systems Part 50 Appendix 3.2.1 - Seismic 3.2.1-Confirmatory Issue Resolved 1.29, 1.143, 3.2.1 B, Part 100 Classification for ERCW upgrade to SSER5 1.151, 1.189 Appendix A, GDC seismic category 1 1, 2, 61 3.2.1-Confirmatory issue Resolved seismic classification of SSER5 structures, systems, and 5

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 components important to safety 50.55a, Part 50 3.2.2 - System Quality 1.26,1.84, 3.2.2 Appendix B, GDC 1 Group Classification No open issues 1.85, 1.176, 1.201 GDC 2 3.3.1 - Wind Loadings 3.3.1 No open issues 3.3.2 GDC 2 3.3.2 - Tornado Loadings

1. 76R 1 No open issues GDC 2, 4 3.4.1 - Internal Flood 1.29 3.4 Protection for Onsite No open issues Equipment Failures NA GDC 2 3.4.2 Analysis Procedures Not addressed in SER GDC 4 3.5.1.1 - Internally 1.115 3.5.1.1 Generated Missiles No open issues (Outside Containment)

GDC 4 3.5.1.2 - Internally 3.5.1.2 Generated Missiles (Inside No open issues Containment) 3.5.1.3 GDC4 3.5.1.3-1.115, 1.117 Turbine Missiles No open issues GDC 2,4 3.5.1.4 - Missiles 1.76 3.5.1.4 Generated by Tornadoes No open issues and Extreme Winds 50.34(a)(1)(ii), Part 3.5.1.5-Site Proximity 1.117,1.91 3.5.1.4 100 Subpart A, Missiles (Except Aircraft)

No open issues 100.10, GDC 4 3.5.2 100.11, GDC 2, 4 3.5.2 - Structures, 3.5.2-Confirmatory Issue Resolved 1.13, 1.27, Systems, and modifications to protect SSER2 1.115, 1.117 6

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 Components to be Diesel Generators protected from Externally Generated Missiles GDC 2 & 4 3.5.3 - Barrier Design 1.76, 1.142 3.5.3 Procedures No open issues GDC 2 & 4 3.6.1 - Plant Design for 3.6.1-Outstanding issue Resolved 3.6.1 Protection Against involving main steam line SSER14 Postulated Piping Failures break outside containment in Fluid Systems Outside Containment Part 100 Appendix 3.6.2 - Determination of 3.6.2 A, GDC 4 Rupture Locations and No open issues Dynamic Effects Associated with the Postulated Rupture of Piping NA GDC 4 3.6.3 - Leak-Before-Break New section 1.45 Evaluation Procedures Not addressed in SER SRP 1987 -

Reviewed in SSER5 - No outstanding issues 3.7.1 Part 100, Subpart A 3.7.1 - Seismic Design 3.7.1.1-Outstanding issue Resolved 1.60,1.165,

& Appendix A, GDC Parameters involving update of FSAR SSER8 1.70, 1.208 2

for site specific spectra 3.7.2 Part 100, Subpart A 3.7.2 -Seismic System 3.7.2.1.2-Outstanding Resolved 1.60, 1.70,

& GDC 2 Analysis issue involving mass SSER8 1.92, 1.122, eccentricity 1.132, 1.138 3.7.2.12-Outstanding Resolved issue involving SSER1 1 7

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 comparison of Set A vs.

Set B response 3.7.3 Part 100, Subpart A 3.7.3 - Seismic Subsystem 3.7.3-Outstanding issue Resolved 1.70

& Appendix A, Analysis involving number of peak SSER8 100.23, GDC 2 cycles to be used for OBE 3.7.3-Outstanding issue Code case use, involving use of code damping factors cases, damping factors for for conduit conduit and use of worst resolved case, critical case and SSER8, use of bounding case worst /critical /

bounding case resolved for Unit 1 only in SSER12 (CAP/SP implementation issue resolved in IR 390/93-201) 3.7.3-Outstanding issue Resolved involving 1.2 multi-mode SSER9 factor Part 20 3.7.4 - Seismic No open issues 1.12, 1.166, 3.7.4 Instrumentation 1.70 NA 50.44, 50.55(a),

3.8.1 Concrete Not addressed in SER 1.7R2, 1.35, GDC 1,2,4,16, 50, Containment 1.35.1, 1.70, Appendix J 1.90, 1.91, 1.115,1.136, 8

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 1.84, 1.147 3.8.1 50.34(o, 44, 55a; 3.8.2 - Steel Containment 3.8.1-Confirmatory issue Resolved 1.7, 1.57, GDC 1, 4, 16, 50 to verify buckling SSER3 1.70, 1.84, methodology 1.147, 1.193 3.8-Outstanding issue Resolved involving load SSER9 combinations and stress allowables 3.8.2 Part 50 Appendix 3.8.3 - Concrete and Steel No open issues 1.142, 1.199, B, 50.55a, 50.65; Internal Structures of Steel 1.57, 1.69, GDC 1,2, 4, 5, 50 or Concrete Containments 1.136,1.142, 1.143, 1.160, 1.199 3.8.3 Part 50 Appendix 3.8.4 - Other Seismic No open issues 1.142, 1.69, B, 50.55a, 50.65; Category 1 Structures 1.70, 1.91, GDC 1, 2, 4, 5, 50 1.115, 1.127, 1.143, 1.160, 1.199 3.8.4 Part 50 Appendix 3.8.5 - Foundations No open issues 1.142, 1.70, B, 50.55a, 50.65; 1.127, 1.142, GDC 1,2,4,5 1.160 3.9.1 Part 50 Appendix B 3.9.1 - Special Topics for 3.9.1-Outstanding issue Resolved Section Il, GDC 1, Mechanical Components involving assumption in SSER13 2,14, 15 piping analysis for water-hammer due to check valve slam 3.9.2.1, Part 50 Appendix 3.9.2 - Dynamic Testing No open issues 1.20, 1.29, 3.9.2.2, B, 50.55a, GDC 1, and Analysis of Systems, 1.61, 3.9.2.3 2, 4, 14 & 15 Structures and 1.68,1.92 and Components 9

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 13.9.2.4 1

[

3.9.3.1, 3.9.3.2, 3.9.3.3 and 3.9.3.4 GDC 1, 2, 4,14 &

15 3.9.3 - ASME Code Class 1, 2 and 3 Components, Component Supports, and Core Support Structures 3.9.3.4-Outstanding issue, staff was awaiting TVA concurrence on their position with respect to margin for critical buckling of Reactor Coolant Pump suooort Resolved SSER4 B 88-08, 88-11 1.124, 1.130 3.9.3. 1-Outstanding issue Resolved involving use of SSER8 experience data to qualify categr 1) piping 3.9.3.3-Outstanding issue Resolved involving operating SSER7 characteristics of main steam safety valves 3.9.3.4-Confirmatory issue Resolved involving baseplate SSER8 flexibility and its effect on anchor bolt loads 3.9.3.4-Outstanding issue Resolved involving stiffness and SSER8 deflection limits for seismic Category I pipe

___________________supports_______________________________

3.9.3.3-LC Relief and Resolved safety valve testing (ll.D.1)

SSER3 3.9.4 50.55a, GDC 1, 2, 3.9.4 - Control Rod Drive No open issues 1.26,1.29 14, 26, 27 & 29 Systems 3.9.5 50.55a, GDC 1, 2, 3.9.5 - Reactor Pressure No open issues 1.20 10

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 4 & 10 Vessel Internals 3.9.6 Part 50 Appendix B 3.9.6-Functional Design, 3.9.6-Confirmatory issue-Resolved GL 89-10, 90-09 1.192,

& J, 50.55a, GDC Qualification, and Required that Tech Spec SSER14

& 96-05 1.174R1, 1, 2, 4, 14, 15, 37, Inservice Testing of include limiting condition 1.175, 1.148 40, 43, 46 & 54 Pumps and Valves and for operation that requires Dynamic Restraints plant shutdown or system isolation when leak limits are not met. Staff had not reviewed Tech Spec.

3.9.6 LC - Inservice Resolved testing of pumps and SSER12 valves NA 3.9.7 Risk - Informed Not addressed in SER GL 89-04, 89-10 1.174, 1.175 Inservice Testing supplement 6 NA 3.9.8 Risk Informed Not addressed in SER GL 88-20, 89-1.174, 1.178 Inservice Inspection of 08, 89-13 Piping B 79-17, 88-01, 88-08, 88-11 3.10 Part 50 Appendix 3.10 - Seismic and 3.10-Generic outstanding Resolved all but 1.100R2, 1.61, B, GDC 1, 2,4,14 Dynamic Qualification of issues involving adequacy adequacy of 1.89,1.92,

& 30 Mechanical and Electrical of frequency test, peak frequency test 1.97R2,3,4 Equipment broadening of response

SSER6, spectra, reconciling actual resolved field mounting by welding adequacy of vs. testing configuration frequency test mounted by bolting and SSER9 need for surveillance and 11

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 maintenance programs to address aging 3.10-Outstanding issue Resolved involving seismic SSER8 classification of cable tray and conduits 3.11 Part 50 Appendix 3.11 - Environmental 3.11-Outstanding issue-Resolved B, 50.49, 50.67, Qualification of TVA program not SSER15 GDC 1, 2, 4, 23, Mechanical and Electrical submitted at time of SER NUREG-0737 ll.B.2 Equipment NA GDC 1, 2, 4, 14, 15 3.12 - ASME Code Class Not addressed in SER B 88-08, 88-11 1.124, 1.130, 1, 2 and 3 Piping 1.60, 1.84, Systems, Piping 1.92, 1.122, Components and their 1.207 associated supports NA 50.55(a), Part 50 3.13 Threaded Fasteners Not addressed in SER GL 91-17 1.37, 1.65, Appendix A, B and

- ASME Code Class 1, 2 1.84 G

and 3 Chapter 4 - Reactor 4.2.1, Part 50 Appendix 4.2 - Fuel System Design 4.2.2-Confirmatory issue Resolved 11.4,1.25, 4.2.2, K, 50.34, 50.46, on thermal performance SSER2 1.157, 1.126, 4.2.3, 50.67, GDC 2, 10, analysis code.

1.60,1.77, 4.2.4 27,35 1.183, 1.195, 12

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 1.196 4.2.3-Confirmatory issue Resolved on cladding-collapse SSER2 calculations 4.2.3 Confirmatory issue Resolved on Tech Spec to identify SSER2 margins and to offset reduction in DNBR due to fuel rod bowing &

incorporating residual bow penalty into the Tech Spec 4.3.1, GDC 10, 11, 12, 4.3 - Nuclear Design No open issues 1.126,1.77 4.3.2, 13, 20, 25, 26, 27, 4.3.3 28 4.4.1, GDC 10, 12 4.4 - Thermal and 4.4.4-Confirmatory issue Resolved GL 82-28, 86-1.68, 1.133R1 4.4.2, NUREG-0737 Hydraulic Design on margin reduction due SSER2 09, 88-17 4.4.3, II.F.2, to effects of rod bow on 4.4.4, DNBR 4.4.5, 4.4.3-Outstanding issue -

Resolved 4.4.6, Removal of RTD bypass SSER8 4.4.7, system 4.4.8 4.4.5-Confirmatory issue Resolved on review of Loose Parts SSER3 Monitoring System (LPMS) startup report and inclusion of limiting conditions for LPMS in Tech Spec 13

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 4.4.8 - LC Detectors for Resolved Inadequate core cooling SSER10 (II.F.2) 4.4.5 LC Loose part Resolved monitoring system SSER5 4.5.1 50.55a, GDC 1, 14, 4.5.1 - Control Rod Drive No open issues 1.44, 1.85 26 Structural Materials 4.5.2 50.55a, GDC 1 4.5.2 - Reactor Internals No open issues GL 97-01 1.31, 1.44, and Core Support 1.84 Structure Materials 4.6 GDC 4, 23, 25, 26, 4.6 - Functional Design of No open issues 27, 28, 29 Control Rod Drive System Chapter 5 - Reactor Coolant System and Connected Systems 5.2.1.1 10 CFR 50.55a 5.2.1.1 - Compliance with No open issues 1.26 GDC 1 Codes and Standards Rule, 10CFR50.55a 5.2.1.2 10 CFR 50.55a 5.2.1.2 - Applicable Code No open issues 1.84, 1.147, GDC 1 Cases 1.192 5.2.2 10 CFR 50.34 5.2.2 - Overpressure 5.2.2-Outstanding issue Resolved GL 96-03, 90-1.84, 1.26, (f)(2)(x)

Protection on staff review of SSER2 06, 82-16 1.29 10 CFR 50.34 sensitivity study of (f)(2)(xi) required safety valve flow Appendix G rate versus trip parameter GDC 15, 30, 31 5.2.3 10 CFR 50.55a 5.2.3 - Reactor Coolant No open issues GL 97-01, NRC 1.31, 1.34, GDC 1,4, 14, 30, Pressure Boundary Order EA 1.36, 1.37, 14

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 31 Materials 009 1.43,1.44, 1.50,1.71, 1.84 5.2.4 10 CFR 50.55a 5.2.4 - Reactor Coolant 5.2.4-Outstanding issue -

Resolved for GL 88-05, 1.147, 1.150 GDC 32 Pressure Boundary Unit 2 PSI program Unit 1 only B 88-09 Inservice Inspection and submitted April 30,1990 SSERs 10, 12 Testing with a partial listing of and 16 relief requests. This item (Key tracks the staff review.

Assumptions letter)

LC - Inservice inspection Resolved program SSER12 5.4.5 GDC 2, 30 5.2.5 - Reactor Coolant No open issues 1.29, 1.45 Pressure Boundary Leakage Detection LC - Installation of reactor Resolved for coolant vents (ll.B.1)

Unit 1 only SSER5 (IR 390/84-37) 5.3.1 10 CFR 50.55a, 5.3.1 - Reactor Vessel No open issues 1.31,1.34, 50.60 Materials 1.37, 1.43, Appendix G, H 1.44,1.50, GDC 1, 4, 14, 30, 1.65, 1.99, 31,32 1.161 5.3.2 10 CFR 50.55a, 5.3.2 - Pressure-5.3.2-Outstanding issue Outstanding 1.99, 1.154, 50.60, 50.61, Temperature Limits, on P-T limits for Unit 2 not issue on P-T 1.161 Appendix G Upper Shelf Energy and provided. Staff will review limits for Unit 2 15

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 GDC 1, 14, 31, 32 Pressurized Thermal as part of Unit 2 Tech (Key Shock Spec.

Assumptions letter) 5.3.3 10 CFR 50.55a, 5.3.3 - Reactor Vessel 5.3.3-Outstanding issue Outstanding 1.99R2 50.60, 50.61 Integrity that staff will complete issue on P-T GDC 1,4, 14, 30, evaluation of Unit 2 after limits for Unit 2 31,32 receipt of P-T limits (Key Assumptions letter) 5.4.1.1, 5.4 - Reactor Coolant No open issues 5.4.2.1, System Components and 5.4.2.1 Subsystem Design 5.4.1.1 10 CFR 50.55a 5.4.1.1 - Pump Flywheel No open issues 1.14 (a)(i)

Integrity (PWR)

GDC 1,4 5.4.2.1 10 CFR 50.55a (c),

5.4.2.1 - Steam Generator No open issues 1.31, 1.34, (d), e, Appendix G Materials 1.36, 1.37, GDC 1, 4, 14, 15, 1.43, 1.44, 30, 31 1.50, 1.65, 1.71, 1.84 5.4.2.2 10 CFR 50.55a (g),

5.4.2.2 - Steam Generator 5.4.2.2-Outstanding issue Resolved 1.121 50.36, 50.65 Program that staff will evaluate SSER4 GDC 32 TVAs' proposed resolution to concerns about flow induced vibrations in Model D-3 SGs pre-heat region and address in SER supplement 16

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 5.4.3 GDC 2, 4, 5,19, 34 5.4.7 - Residual Heat 5.4.3-Confirmatory issues Resolved GL 88-17, 89-1.29, 1.82 NUREG 0737 Removal (RHR) System to verify installation of an SSER5 for Unit 04, 90-06, 92-02 III.D.1.1 RHR flow alarm and 1 (IR 390/84-28) proper function of dump B 88-08, 88-04, valves when actuated 86-01 manually 5.4.3-Outstanding issue Resolved involving natural SSER10 circulation test to demonstrate ability to cool down & depressurize the plant, and that boron mixing is sufficient under such circumstances; or, if necessary, other applicable tests before startup after first refueling 5.4.4 GDC 2,4 5.4.11 - Pressurizer Relief No open issues 1.26,1.29 Tank 5.4.5 10 CFR 50.46a, (b), 5.4.12 - Reactor Coolant No open issues 1.100,1.92 50.49, 50.55a System High Point Vents GDC 14, 17, 19, 34, 36 Chapter 6 - Engineered Safety Features 6.1.1 Part 50 Appendix B 6.1.1-Engineered Safety No open issues 1.31,1.36, Criteria IX & XG I II, Features Materials 1.37, 1.44, 50.55a, GDC 1 X,

F1.50, 1.84 17

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 14,31,35,41 6.1.2 6.1.2 - Protective Coating No open issues 1.54 Systems (Paints) Organic Materials 6.2.1 Part 50 Appendix 6.2.1 - Containment No open issues GL 88-17 1.97, 1.157, contains K, 30.46, GDC Functional Design 1.4 6.2.1.1 to 4,13, 16, 38, 39, 6.2.2.5 40, 50, 64 6.2.1.1 50.34(f)(3)(v)(A)1 & 6.2.1.1.B - Ice Condenser 6.2.1.1-Confirmatory issue Resolved 1.97 (B)I, GDC 13,16, Containments involves reviewing SSER3 38, 39, 40, 50, 64 analysis that ensures that containment external pressure will not exceed design value of 2.0 psi LC - (6d) Accident Resolved for monitoring instrumentation Unit 1 only II.F.1 -containment SSER5 (IR pressure.

390/84-59)

LC - (6e) Accident Resolved for monitoring instrumentation Unit 1 only II.F.1 - containment water SSER5 (IR level 390/84-85) 6.2.1.2 GDC 4 & 50 6.2.1.2 - Subcompartment No open issues SQN Analysis 6.2.1.1.1 Part 50 Appendix 6.2.1.3 - Mass and Energy No open issues K, GDC 50 Release Analysis for Postulated Loss-of-Coolant Accidents (LOCAs) 6.2.1.1.1 GDC 50 6.2.1.4 - Mass and Energy No open issues 18

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 Release Analysis for Postulated Secondary System Pipe Ruptures 6.2.1.3 6.2.1.5 - Minimum No open issues 1.157 Part 50 Appendix K Containment Pressure I.D.2, 50.46(a)(1)(i)

Analysis for Emergency

& (a)(1)(ii)

Core Cooling System Performance Studies 6.2.2 50.46(b)(5), GDC 6.2.2 - Containment Heat No open issues 1.174R1, 1.82 38, 39, 40 Removal Systems 6.2.3 Part 50 Appendix J, 6.2.3 - Secondary No open issues SQN GDC 4, 16, 43 Containment Functional Design 6.2.4 Part 50 Appendix 6.2.4 - Containment 6.2.4-Confirmatory issue Resolved GL 83-02 & 88-1.11, 1.29 K, 50.34(0f(2)(xiv) & Isolation System to install safety-grade SSER5 17 (xv), 50.63(a)(2),

isolation valves on 1" SQN GDC 1, 2, 4, 16, chemical feed lines joining 54, 55, 56, 57 feedwater lines to main NUREG-0737 steam line I1.E.4.2 & I1.E.4.4, 6.2.4-Outstanding issue Resolved for NRC to complete SSER3 review of information provided by TVA to address Containment Purging During Normal Plant Operation 6.2.4-Outstanding issue Resolved involving containment SSER12 isolation using closed systems 19

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 LC - Modification of Resolved chemical feedlines SSER5 LC - Containment Resolved isolation dependability SSER5 6.2.5 50.44, GDC 5, 41, 6.2.5 - Combustible Gas 6.2.5-Outstanding issue Resolved SQN 1.7, 1.97, 42, 43 Control in Containment for review of TVA provided SSER4 1.155 additional information relative to discussion added to FSAR to address analysis of the production and accumulation of hydrogen within containment following onset of a LOCA LC - (6f) Accident Resolved for monitoring instrumentation Unit 1 only ll.D.1 - containment SSER5 (IR hydrogen 390/84-85)

LC - 9 Hydrogen control Resolved measures SSER8 6.2.6 Part 50 Appendix J, 6.2.6 - Containment No open issues 1.163 100.10, 100.11, Leakage Testing GDC 52, 53, 54 6.2.7 50.55a, GDC 1, 16, 6.2.7 - Fracture 6.2.7-Confirmatory issue Resolved 1.26 51 Prevention of Containment for TVA to confirm that the SSER4 Pressure Boundary lowest temperatures which will be experienced by the limiting materials of the reactor containment pressure boundary under 20

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 the conditions cited by GDC 51 will be in compliance with the temperatures identified in the staff's analysis of fracture toughness requirements for load bearing component of the containment system 6.3 Part 50 Appendix 6.3 - Emergency Core 6.3.3-Confirmatory issue Resolved B 79-24, 80-18, 1.1, 1.29, K, 50.46, 50.63, Cooling System to provide a detailed SSER2 86-03, 88-04, 1.47, 1.52, GDC 2, 4, 5, 17, survey of insulation 88-08, GL 83-1.68, 1.155, 27, 35, 36, 37 material that could 02, 88-17, 89-04 1.157, 1.82, NUREG-0737 become debris post-LOCA SQN 1.79 ll.D.3, l1.F.2, 6.3.1-Outstanding issue -

Resolved ll.K.3.17, II.D.1.1, involving removal of upper SSER7 head injection system 6.3.3-Outstanding issue Resolved involving containment SSER9 sump screen design 6.4 GDC 4, 5,19 6.4 - Control Room No open issues

1. 52R3, NUREG-0737 Habitability System 1.78R1, 1.195, Ill.D.3.4 1.196, 1.197, 1.183 6.5.1.1 to 100.11, GDC 19, 6.5.1 - ESF Atmosphere No open issues B 80-03 1.4, 1.7, 1.25, 6.5.1.4 41, 42, 43, 61, 64 Cleanup Systems 1.52, 1.140, 1.183, 1.195 6.5.2 GDC 41,42, 43 6.5.2 - Containment Spray No open issues 1.4, 1.183 as a Fission Product Cleanup System 21

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 6.5.3 Part 100, GDC 41, 6.5.3 - Fission Product No open issues 1.4, 1.52 42, 43 Control Systems and Structures 6.5.4 GDC 41, 42, 43 6.5.4 - Ice Condenser as a No open issues Fission Product Cleanup System 6.6 50.55a, GDC 36, 6.6 - Inservice Inspection 6.6-Outstanding issue on Resolved for GL 89-08 37, 39, 40, 42, 43, of Class 2 and 3 additional information Unit 1 only in 45, 46 Components required on pre-service SSER 10 (Key inspection program and Assumptions identification of plant letter) specific areas where ASME Code Section XI requirements cannot be met and supporting technical justification Chapter 7 - Instrumentation and Controls 7.1.1 50.55a(h), 50.67 7.1 - Instrumentation and 7.1.3.1-Confirmatory Resolved SQN 1.70, 1.152 Controls - Introduction issue to provide a list of all SSER4 safety related functions and a summary of the

_setpoint analysis 7.2.1 to 50.55a(a)(1),

7.2 - Reactor Trip System 7.2.5-Confirmatory issue Resolved SQN 1.22,1.47, 7.2.6 a(h)(2), GDC 1, 2, to address IEB 79-21 to SSER2 1.53R2, 4, 10, 13, 15, 19, alleviate temperature 1.75R2, 20,21,22,23,24, dependence problem

1. 105R3, 25, 29 associated with measuring 1.118, 1.152 22

1982 10 CFR/ GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 NUREG-0737 I.D.3 SG water level 7.3.1 to 50.55a(a)(1),

7.3 - Engineered Safety 7.3.2-Confirmatory issue Resolved SON 1.22, 1.47, 7.3.6 a(h)(2), GDC 1, 2, Features Systems is commitment to make a SSER2 1.53R2, 4, 10, 13, 15, 16, design change to provide 1.75R2, 19, 20, 21, 22, 23, protection that prevents

1. 105R3, 24, 29, 33, 34, 35, debris from entering level 1.118R3, 38,41,44 sensors 1.152 NUREG-0737 I.D.3, 7.3.5-Confirmatory issues Resolved II.E. 1.2, II.E.4.2 to perform confirmatory SSER3 tests to satisfy IEB 80-06 (to ensure that no device will change position solely due to reset action) and staff review of electrical schematics for modifications that ensure that valves remain in emergency mode after ESF reset 7.4.1 to 50.55a(a)(1),

7.4 - Safe Shutdown No open issues SON 1.152R2, 7.4.3 a(h)(2), a(h)(3),

Systems 1.189 GDC 1, 2, 4, 13, 19, 24, 34, 35, 38 NUREG-0737 II.G. 1 7.5.1 to 50.55a(a)(1),

7.5 - Information Systems 7.5.2-Outstanding issue Resolved 1.97R1, 2,3,4, 7.5.4 a(h)(2), a(h)(3),

Important to Safety involving RG 1.97 SSER9 1.47, 1.152R2, GDC 1, 2, 4, 13, instruments following 1.105R3, 19, 24 course of an accident 1.7R3, 1.151 NUREG-0737 I.D.3, 23

1982 10 CFR / G CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 I.D.3, II.E.1.2, ILF. 1, II.F.2, 11.F.3, ILG. 1 7.6.1 to 50.55a(a)(1),

7.6 - Interlock Systems 7.6.5-Confirmatory issue Resolved 1.47, 1.152R2 7.6.9 a(h)(2), a(h)(3),

Important to Safety to install switches on the SSER4 GDC 1, 2, 4, 10, main control board for the 13, 15, 16, 19, 24, operator to manually arm 25, 28, 33, 34, 35, this system (overpressure 38,41,44 protection provided by NUREG-0737 I.D.3 pressurizer PORVs) 7.7.1 to 50.55a(a)(1), a(h)2, 7.7 - Control Systems 7.7.2 - LC - Status Resolved 1.151, 7.7.7 a(h)(3), GDC 1, 10, monitoring system, SSER7 1.152R2 13, 15, 19, 24, 28, Bypassed and Inoperable 29, 44 Status Indication NA 50.62, 50.55a(h),

7.8 Diverse Not addressed in SER GL 85-06 1.152R2 GDC 1, 13, 19, 24 Instrumentation and Control Systems NA 50.55a(h), 50.62 7.9 Data Communication Not addressed in SER

1. 152R2, 50.34(f)(2)(v), GDC Systems 1.105R3, 1.22, 2, 4, 13, 19, 21, 22, 1.118, 1.53R1, 23, 24, 29 1.75R3, 1.180, 1.204 7.8 Appendix G 5.2.2 Overpressure 7.8.1 LC - Confirm Resolved for GL 96-03, 90-1.84, 1.26, GDC 15, 30, 31 protection installation of acoustic Unit 1 only 06, 82-16 1.29 NUREG-0737 monitoring system on Unit SSER5 (IR II.D.1, II.D.3 2

390/84-35)

Chapter 8 - Electrical Power Systems 24

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 8.1 8.1 - Electrical Power -

No open issues Introduction 8.2.1 to 50.63, 50.65(a)(4),

8.2 - Offsite Power 8.2.2.1-Confirmatory issue Resolved GL 2006-02 1.32, 1.155, 8.2.4 GDC 2, 4, 5, 17, System to document additional SSER2 1.160R2, 18, 33, 34, 35, 38, information in FSAR on 1.182, 1.204, 41,44 control power supplies NUREG-0737 I.D.3, and distribution system for the WB Hydraulic Plant Switchyard 8.2.3-Outstanding issue Resolved involving compliance of SSER13 design changes to the offsite power system with GDC 17 and 18.

8.3.1.1 to 50.55a, 50.63, 8.3.1 - AC Power Systems 8.3.1.1-Confirmatory issue Resolved GL 1996-01, 1.6, 1.9, 1.32, 8.3.1.9, 50.65(a)(4), GDC 2, (Onsite) to incorporate new design SSER2 2007-01 1,47, 1.53, 8.3.3.1 to 4, 5, 17, 18, 33, 34, that provides dedicated SQN 1.63,1.75, 8.3.3.6 35, 38, 44, 50 transformer for each 1.81, 1.106, NUREG-0737 I.D.3, preferred offsite circuit in 1.118, 1.153, I1.E.3.1, ll.G.1 FSAR 1.155, 1.160, 1.182, 1.204 8.3.1.2-Confirmatory issue Resolved to verify voltage drop SSER13 analysis and testing 8.3.1.6-Confirmatory issue Resolved to provide diesel generator SSER7 reliability qualification test report 25

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 8.3.3.1.2-Confirmatory issue to verify design for bypass of thermal overload protective device Resolved SSER2 8.3.3.2.3-Confirmatory Resolved issue for design of sharing SSER2 raceway systems between

____________________units 8.3.3.5.2-Confirmatory Resolved issue to incorporate SSER2 commitment to test only one of four power trains of he lan atone time 8.3.3.6-Confirmatory issue Resolved involving evaluation of SSER7 penetrations' ability to withstand failure of overcurrent protection device_________________

8.3.3. 1.1 -Confirmatory Resolved issue involving SSER13 submergence of electrical equipment as result of a

______________LOCA______

8.3.3.2.2-Confirmatory issue to revise FSAR to reflect requirements of shared safety systems Resolved SSER13 26

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 8.3.1.6 LC - 12 Diesel Resolved generator reliability SSER2 qualification testing at normal operating temperature 8.3.2.1 to 50.55a, 50.63, 8.3.2 - DC Power Systems 8.3.2.4-Confirmatory issue Resolved 1.6, 1.32, 8.3.2.4, 50.65(a)(4) GDC 2, (Onsite) to include diesel generator SSER2 1,47, 1.53, 8.3.3.1 to 4, 5, 17, 18, 33, 34, design analysis in FSAR 1.63, 1.75, 8.3.3.6 38,41,44, 50 1.81, 1.106, NUREG-0737 I.D.3 1.118, 1.128, 1.129, 1.153, 1.155, 1.160, 1.182, 8.3.3.2.2-Confirmatory Resolved issue to revise FSAR to SSER1 3 reflect requirements of shared safety systems 8.3.2.2 - LC - Dc Resolved monitoring and SSER13 annunciation system 8.3.3.2.4 LC - Possible Resolved sharing of dc control SSER3 power to ac switchgear 8.3.3.3 LC - Testing of Resolved associated circuits SSER3 8.3.3.3 LC - Testing of Resolved non-class 1E cables SSER3 8.3.3.4 LC - Low Resolved 27

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 temperature overpressure SSER7 protection power supplies, II.G.1 8.3.3.6 LC - Testing of Resolved reactor coolant pump SSER2 breakers NA 50.63, 50.65, GDC 8.4 Station Blackout Not addressed in SER GL 06-02 1.9, 1.155, SE for both 17, 18 1.160, 1.182 units - March 18, 1993 Chapter 9 - Auxiliary Systems 9.1.1 10 CFR 50.68 9.1.1 - Criticality Safety of No open issues

1. 13R2 GDC 62 Fresh and Spent Fuel Storage and Handling 9.1.2 10 CFR 20.1101(b), 9.1.2 - New and Spent No open issuesBulletin 84-03, 1.13,1.29, 50.68 Fuel Storage 94-01 1.115, 1.117 GDC 2, 4, 5, 61, 63 9.1.3 10 CFR 20.1101(b),

9.1.3 - Spent Fuel Pool No open issues SQN 1.13, 1.26, GDC 2, 4, 5, 61, 63 Cooling and Cleanup 1.29, 1.52, 8.8 System 9.1.4 GDC 2, 5, 61, 62 9.1.4 - Light Load No open issues 1.29 Handling System (Related to Refueling) 9.1.4 GDC 1, 2, 4, 5 9.1.5 - Overhead Heavy LC - Control of heavy Resolved SQN 1.13, 1.29 Load Handling Systems loads (NUREG-0612)

SSER13 10 CFR 100.11 15.7.5 -Spent Fuel Cask 1.25 9.1.4 GDC 61 Drop Accidents No open issues 9.2.1 GDC 2, 4, 5, 44, 9.2.1 - Station Service No open issues in SER.

Resolved for GL89-13, 89-13 1.29 45, 46 Water System SSER18 concludes Unit 1 in Supp 1, 91-13, 28

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 ERCW does not conform SSER18 (Key 96-06, 96-06 to GDC 5 for two-unit Assumptions Supp 1 operation, letter) 9.2.2 GDC 2, 4, 5, 44, 9.2.2 - Reactor Auxiliary 9.2.2-Confirmatory issue Resolved GL96-06, 96-06 1.29, 1.153, 45, 46 Cooling Water Systems to relocate component SSER5 for Unit Supp 1 1.155 cooling booster pumps 1 (IR 390/84-20) SQN above PMF level before receipt of an OL 9.2.3 GDC 2, 5 9.2.3 - Demineralized No open issues SQN 1.29 Water Makeup System 9.2.4 GDC 60 9.2.4 - Potable and No open issues SQN Sanitary Water Systems 9.2.5 GDC 2, 5, 44, 45, 9.2.5 - Ultimate Heat Sink No open issues SQN 1.27, 1.72 46 9.2.6 10 CFR 50.63 9.2.6 - Condensate No open issues SQN 1.29, 1.143, GDC 2, 5, 44, 45, Storage Facilities 1.155, 1.59, 46,60 1.102, 1.76, 1.117 9.3.1 10 CFR 50.63 9.3.1 - Compressed Air No open issues GL88-14 1.155 GDC 1, 2, 5 System SQN 9.3.2 10 CFR 20.1101(b) 9.3.2 - Process and Post-9.3.2 LC - Post-Accident Resolved 1.21, 8.8, GDC 1, 2, 13,14, Accident Sampling Sampling System SSER14 1.26,1.29, 26, 41, 60, 63, 64 Systems 1.97 NUREG 0737 IllI.D.1.1 9.3.3 GDC 2, 4, 60 9.3.3 - Equipment and No open issues Floor Drainage System 9.3.4 10 CFR 50.63(a)(2) 9.3.4 - Chemical and No open issuesBulletin 80-18, 1.26, 1.29, NUREG 0737 Volume Control System 88-04 1.155 Ill.D.1.1 (PWR) (Including Boron GL80-21, 89-04 29

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 GDC 1,2, 5,14, Recovery System) 29, 33, 35, 60, 61 9.4.1 10 CFR 50.63 9.4.1 - Control Room Area No open issues SQN 1.29, 1.78R1, GDC 2,4, 5,19,60 Ventilation System 1.52R3, 1.155 9.4.2 GDC 2, 5, 60, 61 9.4.2 - Spent Fuel Pool No open issues SQN 1.29, 1.52, Area Ventilation System 1.140, 1.13, 1.25 9.4.3 GDC 2, 5, 60 9.4.3 - Auxiliary and No open issues SQN 1.29, 1.140, Radwaste Area Ventilation 1.52 System 9.4.4 GDC 2, 5, 60 9.4.4 - Turbine Area No open issues SQN 1.29, 1.140, Ventilation System 1.52 9.4.5 10 CFR 50.63 9.4.5 - Engineered Safety No open issues SQN 1.29,1.140, GDC 2, 4, 5, 17, 60 Feature Ventilation 1.52, 1.155 System 9.5.1.1 to 10 CFR 50.48, 9.5.1 - Fire Protection 9.5.1.2-Outstanding issue Resolved SQN 1.189R1, 9.5.1.9 Appendix R Program for Fire Protection SSERs 18,19 1.174R1 GDC 3, 5, 19, 23 Program 9.5.1.3 - Confirmatory issue - Electrical penetrations documentation 9.5.1.8 LC - Fire protection program 9.5.2.1, Part 50 Appendix 9.5.2 - Communications 9.5.2 LC - Performance Resolved 1.189R1, 9.5.2.2 E, 50.47(a)(8),

Systems testing of communications SSER5 1.180 50.55a, system 73.45(e)(2)(iii),

(g)(4)(i) 73.46(o, 73.55(e) 30

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 and (f 9.5.3 None 9.5.3 - Lighting Systems No open issues 9.5.4.1, GDC 2, 4, 5,17 9.5.4 - Emergency Diesel 9.5.4.1-Outstanding issue Resolved NUREG/Cr-1.137 9.5.4.2 Engine Fuel Oil Storage for staff to complete SSER5 0660 and Transfer System review to determine if diesel generator auxiliary support systems can perform their design safety functions under all conditions, after receipt of all requested information 9.5.4.1 -Confirmatory issue Resolved to include required SSER5 language in operating instruction to ensure no-load and low-load operation is minimized and revise operating procedures to address increased diesel generator load after it has run for an extended period of time at low or no load 9.5.4.1-Outstanding issue Resolved on definition of engine SSER5 mounted piping 31

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 9.5.4.2-Outstanding issue Resolved to design skid-mounted SSER5 piping and components from the day tank to the diesel engine as seismic Category I and to ASME Section III, Class 3 9.5.4.2-Confirmatory issue Resolved to provide missile SSER5 protection for fuel oil storage tank vent lines 9.5.4.1 LC - Diesel Resolved Generator reliability SSER5 9.5.5 GDC 2, 4, 5, 17, 9.5.5 - Emergency Diesel 9.5.5-Outstanding issue to Resolved NUREG/Cr-1.115, 1.117 44, 45, 46 Engine Cooling Water design engine cooling SSER5 0660 System water system piping and components for all engines up to the engine interface, including auxiliary skid mounted piping, to ASME Section 1Il, Class 3 9.5.6 GDC 2, 4, 5, 17 9.5.6 - Emergency Diesel 9.5.6-Outstanding issue to Resolved 1.115,1.117 Engine Starting System design engine air-starting SSER5 system piping components for all engines up to the engine interface, including auxiliary skid mounted piping, to ASME Section Ill, Class 3 32

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 9.5.7 GDC 2, 4,5,17 9.5.7 - Emergency Diesel Engine Lubrication System 9.5.7-Outstanding issue to perform additional mod, or provide justification for acceptability of proposed mod, to ensure lubrication of all wearing parts of the diesel engine either on an interim or continuous basis Resolved SSER5 1.115,1.117 I-I I

9.5.7-Outstanding issue to design standby diesel engine lube oil system piping and components up to the engine interface, including skid mounted piping, to ASME Section III, Class 3 Resolved SSER5 9.5.7-Outstanding issue to provide a more detailed description of the lubricating oil system and a description of the diesel engine crankcase explosion protection features Resolved SSER5 9.5.8 GDC 2, 4, 5, 17 9.5.8 - Emergency Diesel 9.5.8-Outstanding issue to Resolved 1.115,1.117 Engine Combustion Air design standby diesel SSER5 Intake and Exhaust engine combustion air System intake and exhaust system piping and components up 33

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 to the engine interface to ASME Section III, Class 3 and recommendations of RG 1.26 Chapter 10 - Steam and Power Conversion System 10.2.1, GDC 4 10.2 - Turbine Generator No open issues 1.68 10.2.2 10.2.2 GDC 4 10.2.3 - Turbine Rotor No open issues Integrity 10.3.1 to 50.63, GDC 2, 4, 5, 10.3 - Main Steam Supply 10.3.4 LC-Secondary Resolved for GL 86-09 1.29,1.115, 10.3.4 34 System water chemistry Unit 1 only SQN 1.117, 1.155 monitoring and control SSER5 placed program in TS administration section - same resolution for WBN2 10.3.3 Part 50, Appendix 10.3.6 - Steam and No open issues GL 89-08 1.37, 1.50, B, 50.55a, GDC 1, Feedwater System SQN 1.84, 1.71 35 Materials 104.1 Part 50 Appendix!,

10.4.1 - Main Condensers No open issues GDC 60 10.4.2 Part 50 AppendixI, 10.4.2 - Main Condenser No open issues GDC 60 Evacuation System 10.4.3 GDC 60 10.4.3 - Turbine Gland No open issues Sealing System 10.4.4 GDC 4, 34 10.4.4 - Turbine Bypass No open issues 34

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 System 10.4.5 GDC 4 10.4.5 - Circulation Water No open issues SQN System 10.4.6 GDC 14 10.4.6 - Condensate No open issues Cleanup System 10.4.7 GDC 2, 4, 5, 44, 10.4.7 - Condensate and No open issues GL 89-08 1.29 45, 46 Feedwater System 10.4.8 GDC 1, 2, 13, 14 10.4.8 - Steam Generator No open issues 1.26,1.29, Blowdown System (PWR) 1.143 10.4.9 50.62, 50.63 GDC 10.4.9 - Auxiliary No open issues B 85-01, GL 88-1.29, 1.117, 2, 4, 5, 19, 34, 44, Feedwater System (PWR) 14 1.102, 1.59, 45,46 1.62, 1.76, NUREG-0737 1.155 II.E.1.1, Chapter 11 - Radioactive Waste Management 11.1 10 CFR 20, 50 11.1 - Source Terms No open issues 1,140,1.110, Appendix I 1.112 GDC 60 11.2 10 CFR 11.2 - Liquid Waste No open issues SQN 1.143, 1.110, 20.1302,20.1406, Management System 1.70, 1.11, 50.34a, Appendix I 1.33, 1.113, Sections II.A and 1.112, 1.109 IL.D GDC 60, 61 11.3 10 CFR 11.3 - Gaseous Waste No open issues SQN 1.140,1.143, 20.1302,20.1406, Management System 1.11, 1.33, 35

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 50.34a, Appendix I 1.52, 1.70, Sections II.B, II.C 1.109, 1.110, and II.D 1.111, 1.112 GDC 3, 60, 61 11.4 10 CFR 11.4 - Solid Waste No open issues GL 80-09, 81-1.143, 8.8, 20.1302,20.1301(e)

Management System 38,81-39 8.10

,20.1406, 50.34a, Appendix I Sections II.A 1iB, IIC, and II.D GDC 60, 61, 63 10 CFR 61.55 and 61.56 11.5 10 CFR 11.5 - Process and No open issues GL 80-09, 81-1.143, 1.33, 20.1302,20.1301(e)

Effluent Radiological 38, 81-39 1.70, 1.11,

,, 50.34a, 50.36(a),

Monitoring Instrumentation B 80-10, 79-19 1.110, 1.112 Appendix I, and Sampling Systems GDC 60, 63, 64 11.7 NA NUREG -0737 items LC - (6a) Accident Resolved monitoring instrumentation SSER5 II.F.1 - Noble Gas monitor LC - (6b) Accident Resolved monitoring instrumentation SSER6 II.F.1 - Iodine particulate sampling LC - Primary coolant Resolved for outside containment Unit 1 only III.D.1.1 SSER10 TS issue for waste gas disposal 36

1982 10CFR/GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 system - same resolution for WBN2 Chapter 12 - Radiation Protection 12.2 10 CFR 19.12, 12.1 - Assuring that No open issues 1.8,1.33, 20.1101 Occupational Radiation 1.70, 8.8, Exposures are As Low As 8.10, 8.27 Reasonably Achievable 12.3 10 CFR 20.1201, 12.2 - Radiation Sources No open issues 1.4,1.7,

.1202,.1203, 1.112, 1.183

.1204,.1206,

.1207,.1301,.1801 GDC 19, 61 12.4 10 CFR 1101(b),

12.3, 12.4 - Radiation No open issues SQN 1.4, 1.7, 1.52,

.1201,.1202, Protection Design 1.69,1.70,

.1203,.1004, Features 1.97, 1.183,

.1701,.1301, 8.8, 8.10,

.1302,.1406 8.19, 8.25, GDC 19,61, 63 8.38 50.68 12.5, 12.6 10 CFR 20, 19.12, 12.5 - Operational 12.6-Outstanding issue Resolved 1.8, 1.33, GDC 64 Radiation Protection involving Health Physics SSER1 0 1.97, 8.4, 8.6, 71.5 Program Program 8.7, 8.8, 8.10, 8.13,8.15, 8.20, 8.25, 8.26, 8.27, 37

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins,

Guides Information other)

Notes 1, 2 8.28, 8.29, 8.32, 8.34, 8.35, 8.36, 8.38 12.7 NA NUREG 0737 items LC - (6c) Accident Resolved for monitoring instrumentation Unit 1 only

- containment radiation SSER5 (IR monitor 390/84-23)

Chapter 13 - Conduct of Operations 13.1.1 10 CFR 50.40(b) 13.1.1 - Management and No open issues 1.8,1.68 Technical Support Organization 13.1.2, 10 CFR 50.40(b),

13.1.2, 13.1.3 - Operating 13.1.3 LC - Use of Resolved 1.8,1.33, 13.1.3 50.54 i thru m Organization experienced personnel SSER8 1.114 during startup 13.2.1 10 CFR 50.54 i thru 13.2.1 - Reactor Operator No open issues SQN 1.8, 1.149 m, 55.4, 55.31, Requalification Program, 55.41 Reactor Operator Training 13.2.2 10 CFR 19.12, 13.2.2 - Non-Licensed No open issues GL 86-04 1.8, 1.149 26.21, 26.22, Plant Staff Training 50.34(a) and (b),

50.40(b), 50.120, Appendix E II.F, IV.F 13.3 10 CFR 50.33,.34, 13.3 - Emergency 13.3 LC - Emergency Resolved Multiple GLs, 1.23, 1.97, 50.47, 100.1, Planning Preparedness III.A.1, SSER13 Bulletins and 1.70, 1.101, 38

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 100.3, 50.72(a)(3),

III.A.2, III.A.2 RISs 4.7, 5.62 (a)(4), (c)(3),

73.71(a), Appendix E

13.4 13.4 - Operational 13.4 LC - Independent Resolved for Programs Safety Engineering Group Unit 1 only I.B.1.2 SSER8TS issue - same resolution for WBN2 13.5.1 10 CFR 50.40(b),

13.5.1 - Administrative 13.5.2-Outstanding issue Resolved SQN 1.33 13.5.2 50.54(1),

Procedures involving operating, SSER9 50.34(a)(6) and maintenance and (10), 50.34(b)(6)(iv) emergency procedures and (v) 13.5.2 LC -Review of Resolved GL 82-02, 82-power ascension test SSER10 12, 83-14, 89-procedures and 23, 90-03, 91-16 emergency operating procedures by the NSSS vendor I.C.7 13.5.2 LC - Modifications Resolved to Emergency Operating SSER10 instructions 13.5.3 NA NUREG 0737 items 13.5.3 LC - Report on Resolved outage of emergency core SSER3 cooling system I1.K.3.17 13.6 10 CFR 26, 73.2, 13.6 - Physical Security 13.6-Outstanding issue to Resolved 5.12, 5.20, 73.55, 73.56, file appropriate revision to SSER15 5.44, 5.54 73.57, Part 37 the physical security plan 39

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 Chapter 14 - Initial Test Program SER 14 10 CFR 50.34(b)(6)(iii),

30.53(c), Appendix J Section III.A.4 14.2 - Initial Plant Test Program - Design Certification and new License Application 14.0-Confirmatory issues-Availability of test procedures 60 days before test.

Resolved SSER3 1.16, 1.68, 1.68.2, 1.68.3, 1.20, 1.30, 1.37, 1.52, 1.56, 1.72, 1.78, 1.116, 1.128, 1.139, 1.140 14.0-Confirmatory issue-Resolved FSAR references to SSER3 Regulatory Guides.

14.0-Confirmatory issue-Additional systems to be tested as part of the initial test program Resolved SSER3 40

1982 10CFR/GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 Unit 2 issue to verify capability of each common station service transformer to carry load required to supply ESF loads of 1 unit under LOCA condition in addition to power required for shutdown on non-accident unit 14.2 LC - Initial Test Resolved Program SSER7 Section 14.3 - Standard Plant deleted Designs, Initial Test Program - Final Design Approval (FDA)

Chapter 15 - Accident Analysis 15.1 Part 20, Part 50, 50.46, Part 100 GDC 2, 4, 5, 10, 13, 15, 17, 19, 20, 25, 26, 27, 28, 29, 31, 34, 35, 55, 60, 61 15 - Introduction -

Transient and Accident Analysis No open issues GDC 10, 13,15, 15.3.1-15.3.2 - Loss of 15.2 17,20,26 Forced Reactor Coolant No open issues Flow Including Trip of Pump Motor and Flow 41

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 Controller Malfunctions GDC 10, 13,15, 15.2.1 - 15.2.5 - Loss of 1.105, 1.53 15.2.1 17, 26 External Load; Turbine No open issues Trip; Loss of Condenser Vacuum; Closure of Main Steam Isolation Valve (BWR); and Steam Pressure Regulator Failure (Closed)

GDC 10, 13,15,26 15.2.6-Loss of 1.105, 1.53 15.2.1 Nonemergency AC Power No open issues to Station Auxiliaries GDC 10, 13, 15, 15.2.7 - Loss Normal 1.105, 1.53, 15.2.1 17, 26 NUREG Feedwater Flow No open issues 1.206 0737 I1.K.2.19 GDC 10, 13, 15, 15.1.1-1.105,1.53 15.2.2, 20, 26 15.1.4 - Decrease in No open issues 15.2.3 Feedwater Temperature, Increase in Feedwater Flow, Increase in Steam Flow, and Inadvertent Opening of a Steam Generator Relief or Safety Valve GDC 10, 13,15, 26 15.5.1-15.5.2 - Inadvertent RIS 2005-29 1.53, 1.105 15.2.3 Operation of ECCS and No open issues Chemical and Volume Control System Malfunction that Increases Reactor Coolant Inventory 42

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 GDC 10, 13, 17, 15.4.1 - Uncontrolled 15.2.4.1 20, 25 Control Rod Assembly No open issues Withdrawal from a Subcritical or Low Power Startup Condition GDC 10, 13, 17, 15.4.2 - Uncontrolled No open issues 15.2.4.2 20, 25 Control Rod Assembly Withdrawal at Power GDC 10, 13, 20, 25 15.4.3 - Control Rod 15.2.4.3 Maloperation (System No open issues Malfunction or Operator Error)

NA GDC 10, 13,15, 15.4.4-15.4.5 Startup of Not addressed in SER 1.105, 1.53, 20,26,28 an Inactive Loop or 1.70 Recirculation Loop at an Incorrect Temperature, and Flow Controller Malfunction Causing an Increase in BWR Core Flow Rate GDC 10, 13,15, 26 15.4.6 - Chemical and 15.2.4.4 Outstanding Resolved 15.2.4.4 Volume Control Systems issue for evaluation of SSER4 Malfunction that Results in Boron dilution and single a Decrease in Boron failure criteria Concentration in the Reactor Coolant (PWR)

Part 100 15.4.7 - Inadvertent 15.2.4.5 GDC 13 Loading and Operation of No open issues a Fuel Assembly in an Improper Position 43

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 10 CFR 100.11, 15.4.8 - Spectrum of Rod 1.77, 1.183, 15.2.6 50.67 Ejection Accidents (PWR)

No open issues 1.195 GDC 13, 28 10 CFR 50 15.6.5 - Loss-of-Coolant GL 85-12 1.157 15.3.1 Appendix K, 50.46, Accidents Resulting From No open issues SQN 100, 50.67 Spectrum of Postulated GDC 13, 35 Piping Breaks Within the NUREG 0737 Reactor Coolant Pressure II.K.3.5, II.K.3.25, Boundary II.K.3.30, I1.K.3.31 GDC 13, 17, 27, 15.1.5 - Steam System No open issues 15.3.2 28, 31, 35 Piping Failures Inside and Outside Containment (PWR) 10 CFR 100 15.2.8 - Feedwater 15.3.3 GDC 13, 17, 27, System Pipe Breaks No open issues 28, 31, 35 Inside and Outside NUREG 0737 Containment (PWR)

I1.E.1.1, II.E.1.2 15.3.4, 10 CFR 100 15.3.3-15.3.4 - Reactor 15.3.5 GDC 17, 27, 28, 31 Coolant Pump Rotor No open issues Seizure and Reactor Coolant Pump Shaft Break 10 CFR 50.62, 15.8 - Anticipated LC - Anticipated Resolved 15.3.6 50.46 Transients Without Scram Transients Without Scram SSER5 GDC 12, 14, 16, (Generic Letter 83-28, 35, 38, 50 Item 4.3) 10 CFR 100.11 15.6.5.A - Radiological 1.4 15.4.1 Consequences of a No open issues Design Basis Loss-of-44

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 Coolant Accident Including Containment Leakage Contribution 10 CFR 100.11 15.6.5.B - Radiological 1.4, 1.7, 1.52 15.4.2, Consequences of a No open issues 15.4.6 Design Basis Loss-of-Coolant Accident:

Leakage from Engineered Safety Feature Components Outside Containment 10 CFR 100.11 15.1.5.A - Radiological 1.4 15.4.2 Consequence of Main No open issues Steam Line Failures Outside Containment of a PWR 10 CFR 100.11 15.6.3 - Radiological LC - Steam Generator Resolved 1.4 15.4.3 Consequences of Steam tube rupture SSER12 and 14 Generator Tube Failure 10 CFR 100 15.4.8.A - Radiological 1.77 15.4.4 Consequences of a No open issues Control Rod Ejection Accident (PWR) 10 CFR 100.11 15.7.4 - Radiological 1.25 15.4.5 GDC 61 Consequences of Fuel No open issues Handling Accidents 10 CFR 100 15.6.2 - Radiological 1.11 15.4.6 GDC 55 Consequences of the No open issues Failure of Small Lines Carrying Primary Coolant 45

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 Outside Containment 10 CFR 20 15.7.3 - Postulated 15.4.7 GDC 60 Radioactive Releases Due No open issues to Liquid-Containing Tank Failures 15.5.1-NA NUREG 0737 items LC - Effect of high Resolved 15.5.2 pressure injection for SSER4 small beak LOCA with no auxiliary feedwater II.K.2.13 LC - Voiding in the reactor Resolved coolant system 11.K.2.17 SSER4 GDC 10, 13,15, 26 15.6.1 - Inadvertent LC - PORV isolation Resolved GL 85-12, 86-1.105, 1.53 15.5.3 NUREG 0737 Opening of a PWR system I1.K.3.1, II.K.3.2 SSER5 05, 86-06 I1.K.3.25 Pressurizer Pressure Relief Valve or a BWR Pressure Relief Valve 15.5.4 -

NA NUREG 0737 items LC - Automatic trip of Resolved 15.4.5 reactor coolant pumps SSER4 during a small break LOCA LC - Revised small break Resolved LOCA analysis SSER5 Chapter 16 - Technical Specifications 16 10 CFR 16 - Technical 50.34(b)(6)(vi),

Specifications No open issues 50.36 46

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note 1 (GL, Bulletins, Guides Information other)

Notes 1, 2 NA 10 CFR 50.36 16.1 - Risk Informed Not addressed in SER 1.177, 1.174 Decision Making:

Technical Specifications Chapter 17 - Quality Assurance 17.1, 17.2 Part 50 Appendix 17.1 - Quality Assurance 1.8,1.26, B, 50.34(a.7),

(QA) During the Design No open issues 1.28, 1.29, 50.55a, 50.55e, and Construction Phase 1.30, 1.37, GDC 1 1.38, 1.39, 1.58,1.64, 1.74, 1.88, 1.94, 1.116, 1.123, 1.144, 1.146 17.3,17.4 Part 50 Appendix 17.2 - QA During the Resolved 1.33 B, 50.34(b.6ii),

Operations Phase Outstanding issue QA

SSER2, GDC 1 program Updated
SSER5, Resolved SSER13 17.3 Part 50 Appendix B 17.3 - Quality Assurance No open issues GL 89-02 1.8, 1.26, Program Description 1.28,1.29, 1.33, 1.152, 1.143, 1.36, 1.54, 4.15 NA 10 CFR 50.65 17.6 - Maintenance Rule Not addressed in SER 1.160, 1.182 47

1982 10 CFR I GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 Chapter 18 - Control Room Design Review*

18 50.34(f)(1)(i), (f)(2),

18 - Human Factors LC - Detailed Control Resolved for 1.9,1.22, (f)(3)(i), (f)(3)(vii),

Engineering Room Design review Unit 1in 1.47,1.62, (i) to (m), 50.120 I.D.1 SSER15 with 1.81,1.97, NUREG 0737 I.D.1 onsite audit of 1.105,1.174, Unit 1 control 1.177, 1.187 room improvements -

same resolution for WBN2 LC - Make Safety Open item for Parameter Display System Unit 2-operable prior to startup resolution from the first refueling requires a outage functional system before fuel load and on-line testing after Unit 2 is operational then an operational certification (GL89-06)

  • SRP Chapter 18 was retitled to Human Factors Engineering in 1984 48

1982 10 CFR / GDC CURRENT SRP TITLE ISSUES from 1982 SER Later SSERS Guidance Regulatory Additional SER Note 2 Note I (GL, Bulletins, Guides Information other)

Notes 1, 2 Chapter 19 - Severe Accidents NA NA for Part 50 19.0 - Probabilistic Risk Not Applicable Assessment and Severe Accident Evaluation for New Reactors Part 50 19.1-Determining the Not addressed in SER 1.174, Technical Adequacy of 1.200R1 Probabilistic Risk Assessment Results for Risk-Informed Activities 50.11, 50.12, 50.90 19.2 - Review of Risk Not addressed in SER 1.174R1, Information Used to 1.200R1 Support Permanent Plant Specific Changes to the Licensing Basis: General Guidance 49

Item Title Applicabletion Status Comments Chapter 20 - Generic Communications IEB 73-01 Faulty Overcurrent Trip Delay Device in Circuit Breakers for Closed Engineered Safety Systems IEB 73-02 Malfunction of Containment Purge Supply Valve Switch 6.2.4 Closed IEB 73-03 Defective Hydraulic Snubbers and Restraints 3.9.3 Closed OL @ time IEB 73-04 Defective Bergen-Patterson Hydraulic Shock Absorbers 3.9.3 Closed IEB 73-05 Manufacturing Defect in BWR Control Rods NA BWR IEB 73-06 Inadvertent Criticality in a BWR NA BWR IEB 74-01 Valve Deficiencies 3.9.3, 3.9.6 Closed IEB 74-02 Truck Strike Possibility NA Dated issue IEB 74-03 Failure of Structural or Seismic Support Bolts on Class I 3.9.3 Closed Components IEB 74-04 Malfunction of Target Rock Safety Relief Valves Closed BWR IEB 74-05 Shipment of an Improperly Shielded Source NA Not generation IEB 74-06 Defective Westinghouse (W) Type W-2 Control Switch Component Closed IEB 74-07 Personnel Exposure - Irradiation Facility NA Not generation IEB 74-08 Deficiency in the ITE Molded Case Circuit Breakers, Type HE-3 Closed IEB 74-09 Deficiencies in GE Model 4KV Magne-Blast Circuit Breakers Closed IEB 74-10 Failures in 4 inch Bypass Pipe at Dresden NA BWR IEB 74-11 Improper Wiring of Safety Injection Logic at Zion 1 & 2 Closed IEB 74-12 Incorrect Coils in W Type SG Relays at Trojan Closed IEB 74-13 Improper Factory Wiring on GE Motor Control Centers at Fort Closed Calhoun IEB 74-14 BWR Relief Valve Discharge to Suppression Pool NA BWR IEB 74-15 Misapplication of Cutler-Hammer Three Position Maintained Switch Closed 50

Item Title Applicable Status Comments T

FSAR

______________________________________________Section Model No. 10250T IEB 74-16 Improper Machining of Pistons in Colt Industries (Fairbanks-Morse)

Closed Diesel Generators IEB 75-01 Through-Wall Cracks in Core Spray Piping at Dresden-2 NA BWR IEB 75-02 Defective Radionics Radiograph Exposure Devices and Source NA Not Changes generation IEB 75-03 Incorrect Lower Disc Spring and Clearance Dimension in Series 3.9.6 Closed 8300 and 8302 ASCO Solenoid Valves IEB 75-04 Cable Fire at BFNPP 9.5.1 Closed IEB 75-05 Operability of Category I Hydraulic Shock and Sway Suppressors 3.9.3 Closed IEB 75-06 Defective W Type OT-2 Control Switches Closed IEB 75-07 Exothermic Reaction in Radwaste Shipment NA Not generation IEB 75-08 PWR Pressure Instrumentation Closed IEB 76-01 BWR Isolation Condenser Tube Failure Closed/

By inspection NA

- BWR IEB 76-02 Relay Coil Failures Open IEB 76-03 Relay Malfunctions - GE Type STD Relays Closed IEB 76-04 Cracks in Cold Water Piping at BWRs NA BWR IEB 76-05 Relay Failures Closed IEB 76-06 Diaphragm Failures in Air Operated Auxiliary Actuators for 3.9.3, 3.9.6 Closed Safety/Relief Valves IEB 76-07 Crane Hoist Control Circuit Modifications Closed IEB 76-08 Teletherapy Units NA Not generation IEB 77-01 Pneumatic Time Delay Relay Setpoint Drift Closed IEB 77-02 Potential Failure Mechanism in Certain W AR Relays with Latch Closed Attachments IEB 77-03 On-Line Testing of the W Solid State Protection System Open IEB 77-04 Calculation Error Affecting Performance of a System for Controlling 6.2 Closed 51

Item Title Applicable Status Comments FSAR T

77-0 Eletricl Conectr Asemblesctlose pH of Containment Sump Water Following a LOCA IEB 77-05 Electrical Connector Assemblies Closed

& 77-05 A IEB 77-06 Potential Problems with Containment Electrical Penetration 3.10, 3.11 Closed Assemblies IEB 77-07 Containment Electrical Penetration Assemblies at Nuclear Power 3.10, 3.11 Closed Plants under Construction IEB 77-08 Assurance of Safety and Safeguards During an Emergency -

Closed Locking Systems IEB 78-01 Flammable Contact-Arm Retainers in GE CR120A Relays Closed IEB 78-02 Terminal Block Qualification Closed IEB 78-03 Potential Gas Mixture Accumulations Associated with BWR Offgas NA BWR System Operations IEB 78-04 Environmental Qualification of Certain Stem Mounted Limit Switches 3.11 Closed Inside Reactor Containment IEB 78-05 Malfunctioning of Circuit Breaker Auxiliary Contact Mechanism Closed IEB 78-06 Defective Cutler-Hammer Type M Relays and DC Coils Closed IEB 78-07 Protection Afforded by Air-Line Respirators and Supplied-Air Hoods NA Site IEB 78-08 Radiation Levels from Fuel Element Transfer Tubes NA Site IEB 78-09 BWR Drywell Leakage Paths Associated with Inadequate Drywell NA BWR Closures IEB 78-10 Bergen-Patterson Hydraulic Shock Suppressor Accumulator Spring 3.9.3 Closed Coils IEB 78-11 Examination of Mark I Containment Torus Welds NA BWR IEB 78-12 Atypical Weld Material in Reactor Pressure Vessel Welds 5.4 Closed IEB 78-13 Failures in Source Heads Kay Ray Gauge Models 7050, 7050B, NA Not 7051, 7051 B, 7060, 7060B, 7061 and 7061B generation IEB 78-14 Deterioration of Buna-N Components in ASCO Solenoids NA BWR IEB 79-01 Environmental Qualification of Class 1E Equipment 3.11 Closed IEB 79-02 Pipe Support Base Plate Designs Using Concrete Expansion Anchor 3.9.3 Open 52

Item Title Applicable Status Comments F 1 FSAR

______________________________________________Section Bolts IEB 79-03 Longitudinal Weld Defects in ASME SA-312 Type 304 SS Pipe 3.9.3, 6.1.1 Closed Spools Fabricated by Youngstown Welding & Engineering IEB 79-04 Incorrect Weights for Swing Check Valves Manufactured by Velan 3.7, 3.9 Closed Engineering IEB 79-05 Nuclear Incident at TMI NA B&W IEB 79-06 Review of Operational Errors and System Misalignments Identified Closed During the Three Mile Island Incident IEB 79-07 Seismic Stress Analysis of Safety-Related Piping 3.9.3 Closed IEB 79-08 Events Relevant to BWRs Identified During TMI Incident NA BWR IEB 79-09 Failure of GE Type AK-2 Circuit Breaker in Safety Related Systems Closed IEB 79-10 Requalification Training Program Statistics NA Site IEB 79-11 Faulty Overcurrent Trip Device in Circuit Breakers for Engineering Closed Safety Systems IEB 79-12 Short Period Scrams at BWR Facilities NA BWR IEB 79-13 Cracking in Feedwater Piping 3.9.3, 6.1.1 Closed OL @ time IEB 79-14 Seismic Analysis for As-Built Safety-Related Piping Systems 3.9.3 Open IEB 79-15 Deep Draft Pump Deficiencies 3.9.3, 3.9.6 Closed IEB 79-16 Vital Area Access Controls NA Site IEB 79-17 Pipe Cracks in Stagnant Borated Water Systems at PWR Plants 3.9 Closed IEB 79-18 Audibility Problems Encountered on Evacuation of Personnel from NA Site High-Noise Areas IEB 79-19 Packaging of Low-Level Radioactive Waste for Transport and Burial NA Site IEB 79-20 Packaging, Transport and Burial of Low-Level Radioactive Waste NA Site IEB 79-21 Temperature Effects on Level Measurements Open IEB 79-22 Possible Leakage of Tubes of Tritium Gas Used in Time Pieces for NA Site Luminosity IEB 79-23 Potential Failure of Emergency Diesel Generator Field Exciter Closed Transformer IEB 79-24 Frozen Lines 6.3 Open I

53

Item Title Applicable Status Comments FSAR I

Section IEB 79-25 Failures of W BFD Relays in Safety Related Systems Closed IEB 79-26 Boron Loss from BWR Control Blades NA BWR IEB 79-27 Loss of Non-Class 1 E I & C Power System Bus During Operation Open IEB 79-28 Possible Malfunction of NAMCO Model EA180 Limit Switches at Closed Elevated Temperatures IEB 80-01 Operability of ADS Valve Pneumatic Supply NA BWR IEB 80-02 Inadequate QA for Nuclear Supplied Equipment NA BWR IEB 80-03 Loss of Charcoal from Standard Type II, 2 Inch Tray Adsorber Cells 6.5 Closed IEB 80-04 Analysis of a PWR Main Steam Line Rupture with Continued 3.6, 5.5.9, Open Feedwater Addition 6.2, 10.3, 10.4 IEB 80-05 Vacuum Condition Resulting in Damage to Chemical Volume Control 9.3.4 Open System Holdup Tanks IEB 80-06 Engineered Safety Features Reset Control 6.2.2, 6.3, Open 6.5 IEB 80-07 BWR Jet Pump Assembly Failure NA BWR IEB 80-08 Examination of Containment Liner Penetration Welds 3.8 Closed IEB 80-09 Hydramotor Actuator Deficiencies Closed IEB 80-10 Contamination of Non-radioactive System and Resulting Potential for Open Unmonitored, Uncontrolled Release of Radioactivity to Environment IEB 80-11 Masonry Wall Design 3.8.4 Open IEB 80-12 Decay Heat Removal System Operability 10.4.7, Closed 10.4.8 IEB 80-13 Cracking in Core Spray Spargers NA BWR IEB 80-14 Degradation of Scram Discharge Volume Capability NA BWR IEB 80-15 Possible Loss of Emergency Notification System with Loss of Offsite NA Site Power IEB 80-16 Potential Misapplication of Rosemount Models 1151 and 1152 Closed Pressure Transmitters With Either "A" or "D" Output Codes IEB 80-17 Failure of 76 of 185 Control Rods to Fully Insert During a Scram at a NA BWR 54

Item Title Applicable Status Comments T

1 FSAR

_ I Section_

BWR IEB 80-18 Maintenance of Adequate Minimum Flow Thru Centrifugal Charging 6.3 Open Pumps Following a Secondary Side High Energy Rupture IEB 80-19 Mercury-Wetted Matrix Relay in Reactor Protective Systems Closed IEB 80-20 Failure of W Type W-2 Spring Return to Neutral Control Switches Open IEB 80-21 Valve Yokes Supplied by Malcolm Foundry Co.

3.9.3, 3.9.6 Closed IEB 80-22 Automation Industries, Model 200-520-008 Sealed-Source NA Not Connectors generation IEB 80-23 Failures of Solenoid Valves Manufactured by Valcor Eng. Corp 3.9.3, 3.9.6 Closed IEB 80-24 Prevention of Damage Due to Water Leakage Inside Containment Open IEB 80-25 Operating Problems with Target Rock SR Valves at BWRs NA BWR IEB 81-01 Surveillance of Mechanical Snubbers 3.9.3 Closed IEB 81-02 Failure of Gate Type Valves to Close Against Differential Pressure 3.9.6 Closed IEB 81-03 Flow Blockage to Cooling Water by Asiatic Clams and Mussels 9.2.1 Closed IEB 82-01 Surveillance of Mechanical Snubbers 3.9.3 Closed IEB 82-02 Degradation of Threaded Fasteners in the Reactor Coolant Pressure 3.9.3 Closed Boundary of PWR Plants IEB 82-03 Stress Corrosion Cracking in Thick-Wall, Large Diameter, Stainless NA BWR Steel, Recirculation System Piping at BWR Plants IEB 82-04 Deficiencies in Primary Containment Electrical Penetration 3.10, 3.11 Closed Assemblies IEB 83-01 Failure of Trip Breakers (Westinghouse DB-50) to Open on Closed Automatic Trip Signal IEB 83-02 Stress Corrosion Cracking in Large-Diameter Stainless Steel NA BWR Recirculation System Piping at BWR Plants IEB 83-03 Check Valve Failures in Raw Water Cooling Systems of Diesel NA Addressed Generators by IST for CP holders IEB 83-04 Failure of the Undervoltage Trip Function of Reactor Trip Breakers Closed IEB 83-05 ASME Nuclear Code Pumps and Spare Parts Manufactured by 3.9.3, 3.9.6, Closed 55

Item Title Applicable Status Comments Hayward Tyler Pump Co 17.1 IEB 83-06 Nonconforming Material Supplied by Tube-Line 3.9.3, 5.2.1, Closed 6.1.1,17.1 IEB 83-07 Apparently Fraudulent Products Sold by Ray Miller, Inc 17.1 Closed IEB 83-08 Electrical Circuit Breakers With Undervoltage Trip in Safety Related Closed Applications other than the Reactor Trip System IEB 84-01 Cracks in BWR Mark 1 Containment Vent Headers NA BWR IEB 84-02 Failure of GE Type HFA Relays In Use In Class 1 E Safety Systems Closed IEB 84-03 Refueling Cavity Water Seal 9.1.1, 9.1.2 Open IEB 85-01 Steam Binding of Auxiliary Feedwater Pumps 10.4.9 Closed IEB 85-02 Undervoltage Trip Attachment of W DB-50 Type Reactor Trip Open Breakers IEB 85-03 Motor Operated Valve Common Mode Failures During Plant 3.9.3, 3.9.6 Closed Transients due to Improper Switch Settings IEB 86-01 Minimum Flow Logic Problems That Could Disable RHR Pumps NA BWR IEB 86-02 Static "0" Ring Differential Pressure Switches Closed IEB 86-03 Potential Failure of Multiple ECCS Pumps Due to Single Failure of 6.3 Closed Air-Operated Valve in Minimum Flow Recirculation Line IEB 86-04 Defective Teletherapy Timer That May Not Terminate Treatment NA Not Dose generation IEB 87-01 Thinning of Pipe Walls in Nuclear Power Plants 3.9.3, 6.1 Closed IEB 87-02 Fastener Testing to Determine Conformance with Applicable Material 17.1 Closed Specifications IEB 88-01 Defects in W Circuit Breakers Closed IEB 88-02 Rapidly Propagating Fatigue Cracks in Steam Generator Tubes 5.5.2 Open IEB 88-03 Inadequate Latch Engagement in HFA Type Latching Relays Closed Manufactured by General Electric (GE) Company IEB 88-04 Potential Safety-Related Pump Loss 5.5.7, 6.3 Open IEB 88-05 Nonconforming Materials Supplied by Piping Supplies, Inc. and West 3.9.3, 6.1, Open Jersey Manufacturing Company 17.1 56

Item Title Applicable Status Comments I

FSAR

______________________________________________Section IEB 88-06 Actions to be Taken for the Transfer of Model No. SPEC 2-T NA Not Radiographic Exposure Device generation IEB 88-07 Power Oscillations in BWRs NA BWR IEB 88-08 Thermal Stresses in Piping Connected to Reactor Cooling Systems 3.9.3, 5.5.7, Open 6.3 IEB 88-09 Thimble Tube Thinning in Westinghouse Reactors 5.2 Open IEB 88-10 Nonconforming Molded-Case Circuit Breakers Open IEB 88-11 Pressurizer Surge Line Thermal Stratification 3.9.3 Open IEB 89-01 Failure of Westinghouse Steam Generator Tube Mechanical Plugs 5.5.2 Open IEB 89-02 Stress Corrosion Cracking of High-Hardness Type 410 Stainless 3.9.3, 3.9.6, Open Steel Preloaded Bolting in Anchor Darling Model S350W Swing 6.1 Check Valves or Valves of Similar Nature IEB 89-03 Potential Loss of Required Shutdown Margin During Refueling 9.1 Closed Operations IEB 90-01 Loss of Fill-Oil in Transmitters Manufactured by Rosemount Open IEB 94-01 Potential Fuel Pool Draindown Caused by Inadequate Maintenance NA Shutdown Practices at Dresden plants IEB 96-01 Control Rod Insertion Problems (PWR) 4.2 Open IEB 96-02 Movement of Heavy Loads over Spent Fuel, over Fuel in the 3.8.6, 9.1 Open Reactor, or over Safety-Related Equipment IEB 96-03 Potential Plugging of ECCS Suction Strainers by Debris in BWRs NA BWR IEB 96-04 Chemical, Galvanic or Other Reactions in Spent Fuel Storage and NA Not Transportation Casks generation IEB 97-01 Potential for Erroneous Calibration, Dose Rate, or Radiation NA Not Exposure Measurements with Certain Victoreen Model 530 and generation 531SI Electrometers, Dose Meters IEB 97-02 Puncture Testing of Shipping Packages Under 10 CFR Part 71 NA Not generation IEB 01-01 Circumferential Cracking of Reactor Pressure Vessel (RPV) Head 5.2.3, 5.2.4, Open Penetration Nozzles 5.2.5, 5.4 1

57

Item Title Applicable Status Comments FSAR T

_____________________________________________Section IEB 02-01 RPV Head Degradation and Reactor Coolant Pressure Boundary 5.2.3, 5.2.4, Open Integrity 5.2.5, 5.4 IEB 02-02 RPV Head and Vessel Head Penetration Nozzle Inspection Program 5.4 Open IEB 03-01 Potential Impact of Debris Blockage on Emergency Sump 6.2 Open Recirculation IEB 03-02 Leakage from RPV Lower Head Penetrations and Reactor Coolant 5.2.3 - 5.2.5, Open Pressure Boundary Integrity 5.4 IEB 03-03 Potentially Deficient 1-inch Valves for Uranium Hexaflouride NA Not Cylinders generation IEB 03-04 Rebaselining of Data in the Nuclear Management and Safeguards NA Not System generation IEB 04-01 Inspection of Alloy 82/182/600 Materials Used in the Fabrication of 3.9.3, 6.1 Open Pressurizer Penetrations and Steam Space Piping Connections at PWRs IEB 05-01 Material Control and Accounting of Reactors and Spent Fuel Storage NA Site Facilities IEB 05-02 Emergency Preparedness and Response Actions for Security Based NA Site Events GL 77-06 Questionnaire Related to Steam Generators NA OL @ time GL 77-07 Reliability of Standby Diesel Generator Units NA OL @ time GL 78-02 Asymmetric Loads Background and Revised Request for Additional 3.1, 3.9.3, Open Information 3.9.5 GL 78-03 Request for Information on Cavity Annulus Seal Ring 9.1.1, 9.1.2 Closed See IEB 84-03 GL 78-04 Steam Generator Operating History NA OL @ time GL 78-09 Multiple Subsequent Actuations of Safety Relief Valves Following an NA BWR Isolated Event GL 78-15 Request for Information on Control of Heavy Loads Near Spent Fuel NA Addressed by later BU/GLs 58

Item Title Applicable Status Comments I

~FSAR

_____________________________________________Section GL 78-34 Reactor Vessel Atypical Weld Material 5.4.2, 6.1 Open GL 79-20 Cracking in Feedwater Lines 3.9.3, 6.1 Open GL 79-24 Multiple Equipment Failures in Safety Related Systems NA OL @ time GL 79-36 Adequacy of Station Electric Distribution Systems Voltages 8.2, 8.3.1 Open GL 79-42 Potentially Unreviewed Safety Question on Interaction Between Non-NA OL @ time Safety Grade Systems and Safety Grade Systems GL 79-46 Containment Purge and Venting During Normal Operation NA OL @ time GL 79-52 Radioactive Release at No. Anna Unit 1 and Lessons Learned NA OL @ time GL 79-57 Acceptance Criteria for Mark I Long Term Program NA BWR GL 79-58 ECCS Calculations on Fuel Cladding NA OL @ time GL 80-02 QA Requirements Regarding Diesel Generator Fuel Oil NA Site GL 80-13 Qualification of Safety Related Electrical Equipment NA OL @ time GL 80-14 LWR Primary Coolant System Pressure Isolation Valves 3.9.3, 3.9.6, Open 5.5 GL 80-18 Crystal River 3 Reactor Trip From Approximately 100% Full Power NA B & W GL 80-21 Vacuum Condition Resulting in Damage to Chemical Volume Control 9.3.4 Open System Holdup Tanks GL 80-32 Information Request on Category I Masonry Walls Employed by NA Addressed Plants Under CP and OL Review by IEB 80-11 GL 80-34 Clarification of NRC Requirements for Emergency Response NA Site Facilities at Each Site GL 80-38 Summary of Certain Non-Power Reactor Physical Protection NA Not Requirements eneration GL 80-A-12, Fracture Toughness and Additional Guidance on Potential for 3.1, 3.9.3 Open 46/47 Low Fracture Toughness and Laminar Tearing on PWR Steam Generator Coolant Pump Supports GL 80-53 Decay Heat Removal Capability NA OL ( time GL 80-60 Request for Information Regarding Evaluation Times NA Site GL 80-77 Refueling Water Level - Technical Specifications Changes NA Site GL 80-84 BWR Scram System NA BWR 59

Item Title Applicable Status Comments FSAR Section GL 80-90 NUREG-0737, TMI (Prior and future GLs, with the exception of Open See NUREG certain discrete scopes, have been screened into NUREG list for list those applicable to Watts Bar 2)

GL 80-95 A-10, NUREG-0619, "BWR Feedwater Nozzle and Control Rod Drive NA BWR Return Line Cracking" GL 80-113 Control of Heavy Loads Closed See later GLs, IEBs GL 81-03 NUREG-0313, Technical Report on Material Selection and NA BWR Processing Guidelines for BWR Coolant Pressure Boundary Piping GL 81-04 Emergency Procedures and Training for Station Blackout Closed Subsumed by SB GL 81-07 Control of Heavy Loads 9.1.4 Open GL 81-12 Fire Protection Rule (and prior related GLs)

NA OLs prior to 1/1/79 GL 81-14 Seismic Qualification of Auxiliary Feedwater Systems NA OL @ time GL 81-20, Safety Concerns Associated With Pipe Breaks in the BWR Scram NA BWR

-30, -34, -

System 35 GL 81-21 Natural Circulation Cooldown 5.5 Open GL 82-28 Inadequate Core Cooling Instrumentation System 4.4 Open GL 82-33 Supplement to NUREG-0737, Requirements for Emergency 7.5.2 Open Response Capability GL 83-08 Modification of Vacuum Breakers on Mark I Containments NA BWR GL 83-10c Automatic Trip of Reactor Coolant Pumps 5.5 Closed GL 83-28 Required Actions Based on Generic Implications of Salem ATWS 15.2 Events (Prior and future GLs, with the exception of certain discrete scopes, have been screened into the following list):

1.2 - Post Trip Review Data and Information Capability Closed 2.1 - Equipment Classification and Vendor Interface (Reactor Trip Closed 60

Item Title Applicable Status Comments FSAR T

______________________________________________Section System Components) 2.2 - Equipment Classification and Vendor Interface (All SR Open Components) 3.1 - Post-Maintenance Testing (Reactor Trip System Components)

Closed 3.2 - Post-Maintenance Testing (All SR Components)

Closed 4.1 - Reactor Trip System Reliability (Vendor Related Modifications)

Open 4.3 - Reactor Trip System Reliability (Automatic Actuation of Shunt Closed Trip Attachment)

GL 84-09 Recombiner Capability Requirements of 10 CFR 50.44(c)(3)(ii)

NA BWR GL 84-11 Inspection of BWR Stainless Steel Piping NA BWR GL 84-23 Reactor Vessel Water Level Instrumentation in BWRs NA BWR GL 84-24 Certification of Compliance to 10 CFR 50.49 3.11 Closed Incorporated into license review GL 85-02 Recommended Actions Stemming From NRC Integrated Program for 5.5.2 Open the Resolution of Unresolved Safety Issues Regarding Steam Generator Tube Integrity GL 85-11 Completion of Phase II of "Control of Heavy Loads at Nuclear Power Closed See GL 81-Plants" 07 GL 85-12 Implementation of TMI Item I1.K.3.5 15.5.4 Open GL 86-05 Implementation of TMI Item I1.K.3.5 NA B&W GL 86-06 Implementation of TMI Item I1.K.3.5 NA CE GL 87-02 Verification of Seismic Adequacy of Mechanical and Electrical NA Previously

& 03 Equipment in Operating Reactors, USI A-46 operated plants GL 87-05 Request for Additional Information on Assessment of License NA BWR Measures to Mitigate and/or Identify Potential Degradation of Mark I Drywells 61

Item Title Applicable Status Comments IFSAR

_____________________________________________Section GL 87-06 Periodic Verification of Leak Tight Integrity of Pressure Isolation NA OL @ time Valves GL 87-12 Loss of Residual Heat Removal While The Reactor Coolant System 5.4.7 Closed is Partially Filled GL 88-01 NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping NA BWR GL 88-03 Resolution of GSI 93, Steam Binding of Auxiliary Feedwater Pumps 10.4.9 Closed GL 88-05 Boric Acid Corrosion of Carbon Steel Reactor Pressure Boundary 5.2 Open Components in PWR plants GL 88-07 Modified Enforcement Policy Relating to 10 CFR 50.49, EQ of 3.11 Closed To Special Electrical Equipment Important to Safety for Nuclear Power Plants Program GL 88-11 NRC Position on Radiation Embrittlement of Reactor Vessel Material 5.2.3, 5.2.4, Open and its Impact on Plant Operations 5.2.5, 5.4 GL 88-14 Instrument Air Supply System Problems Affecting Safety-Related 9.3.1 Open Equipment GL 88-17 Loss of Decay Heat Removal 4.4, 6.2,6.3 Open GL 88-20 Individual Plant Examination for Severe Accident Vulnerability Open GL 89-04 Guidelines on Developing Acceptable Inservice Testing Programs 3.9.3, 3.9.6 Open GL 89-06 TMI Action Plan Item I.D.2 - Safety Parameter Display System 7.5.2 Open GL 89-07 Power Reactor Safeguards Contingency Planning for Surface NA Site Vehicle Bombs GL 89-08 Erosion/Corrosion-Induced Pipe Wall Thinning 6.6, 10.3, Open 10.4.7 GL 89-10 Safety-Related Motor-Operated Valve Testing and Surveillance 6.9 Open GL 89-13 Service Water System Problems Affecting Safety Related Equipment 9.2.1 Open GL 89-15 Emergency Response Data System NA Site GL 89-16 Installation of a Hardened Wetwell Vent NA BWR GL 89-19 Request for Actions Related to Resolution of Unresolved Safety 7.7, 10.3 Open Issue A-47 "Safety Implication of Control Systems in LWR Nuclear Power Plants" Pursuant to 10 CFR 50.54(f)

GL 89-20 Protected Area Long Term Housekeeping NA Site 62

Item Title Applicable Status Comments FSAR Section GL 89-22 Potential For Increased Roof Load Due to Changes in Maximum 2.3 Open Precipitation GL 90-06 Resolution of Generic Issues 70, "PORV and Block Valve Reliability,"

5.2.2, 5.5.7 Open and 94, "Additional LTOP Protection for PWRs" GL 91-06 Resolution of Generic Issue A-30, "Adequacy of Safety Related DC NA OL @ time Power Supplies" GL 91-11 Resolution of Generic Issues A-48, "LCOs for Class 1 E Vital NA OL @ time Instrument Buses", and 49, "Interlocks and LCOs for 1E Tie Breakers" GL 91-13 Request for Information Related to Resolution of Generic Issue 130, NA Selected "Essential Service Water System Failures @ Multi-Unit Sites" plants GL 92-01 Reactor Vessel Structural Integrity 5.2.3, 5.2.4, Open 5.2.5, 5.4 GL 92-04 Resolution of Issues Related to Reactor Vessel Water Level NA BWR Instrumentation in BWRs GL 92-08 Thermo-Lag 330-1 Fire Barriers 9.5.1 Open GL 93-01 Emergency Response Data System Test Program NA Site GL 93-04 Rod Control System Failure and Withdrawal of Rod Control Cluster 4.4 Open Assemblies, 10 CFR 50.54(f)

GL 94-02 Long Term Solutions and Upgrade of Interim Operating NA BWR Recommendations for Thermal/Hydraulic Instabilities in BWRs GL 94-03 IGSCC of Core Shrouds in BWRs NA BWR GL 95-01 NRC Staff Technical Position on Fire Protection for Fuel Cycle NA Not Facilities generation GL 95-03 Circumferential cracking of Steam Generator (SG) Tubes 5.5.2 Open GL 95-05 Voltage Based Repair Criteria for W SG Tubes Affected by Outside 5.5.2 Open Diameter Stress Corrosion Cracking GL 95-07 Pressure Locking and Thermal Binding of Safety-Related Power-6.9 Open Operated Gate Valves GL 96-01 Testing of Safety-Related Circuits Open 63

Item Title Applicable Status Comments IFSAR

_____________________________________________Section GL 96-03 Relocation of the Pressure Temperature Limit Curves and Low 5.2.2, 5.2.4 Open Temperature Overpressure Protection System Limits GL 96-05 Periodic Verification of Design-Basis Capability of Safety-Related 6.9 Open Motor-Operated Valves GL 96-06 Assurance of Equipment Operability and Containment Integrity 9.2.1, 9.2.2 Open During Design-Basis Accident Conditions GL 97-01 Degradation of Control Rod Drive Mechanism Nozzle and Other 5.2.3, 5.2.4, Open Vessel Closure Head Penetrations 5.2.5 GL 97-04 Assurance of Sufficient Net Positive Suction Head for Emergency 6.2.2, 6.3 Open Core Cooling and Containment Heat Removal Pumps GL 97-05 SG Tube Inspection Techniques 5.5.2 Open GL 97-06 Degradation of SG Internals 5.5.2 Open GL 98-01 Year 2000 Readiness of Computer Systems at Nuclear Power Plants NA Site GL 98-02 Loss of Reactor Coolant Inventory and Associated Potential for Loss 5.5.7, 6.3 Open of Emergency Mitigation Functions While in a Shutdown Condition GL 98-04 Potential for Degradation of the ECCS and the Containment Spray 6.1.2, 6.2.2, Open System After a LOCA Because of Construction and Protective 6.3 Coating Deficiencies and Foreign Material in Containment GL 99-02 Laboratory Testing of Nuclear Grade Activated Charcoal NA Site GL 03-01 Control Room Habitability 6.4 Closed GL 04-01 Requirements for SG Tube Inspection 5.5.2 Open GL 04-02 Potential Impact of Debris Blockage on Emergency Recirculation 6.2.2 Open during Design Basis Accidents at PWRs GL 06-01 SG Tube Integrity and Associated Technical Specifications 5.5.2 Open GL 06-02 Grid Reliability and the Impact on Plant Risk and the Operability of 8.0, 8.1, 8.2, Open Offsite Power 8.3 GL 06-03 Potentially Nonconforming Hemyc and MT Fire Barrier 9.5.1 Open Configurations GL 07-01 Inaccessible or Underground Power Cable Failures that Disable 8.3.1 Open Accident Mitigation Systems or Cause Plant Transients 64

Item Title Applicable Status Comments 1

I ~~~~FSAR SttsCmes

_____________________________________________Section NUREG Control of Heavy Loads 9.1.4 Open Due to GL 0612 81-07 commitment NUREG TMI Items:

0737 I.C.1 Short term accident and procedure review 13.5 Open I.C.7 NSSS vendor revision of procedures 13.5 Open I.C.8 Pilot monitoring of selected emergency procedures for 13.5 Open NTOLs I.D.1 CRDR 6.4 Open I.D.2 Plant-safety-parameter-display console 7.5.2 Open II.B.1 Reactor-coolant-vent-system 5.5.6 Open ll.B.2 Plant shielding 3.11 Open 11.B.3 Post-accident sampling 9.3.2 Open 11.D.1 Relief and safety valve test requirements 5.2.2 Open It.D.3 Valve position indication 5.2.2, 6.3, Open 7.5 II.E.1.1 Auxiliary feedwater system evaluation, modifications 10.4.9 Open I1.E.1.2 Auxiliary feedwater system initiation and flow 7.3, 7.5 Closed I1.E.3.1 Emergency power for pressurizer heaters 8.3.1 Closed II.E.4.2 Containment isolation dependability 6.2.4, 7.3 Closed I1.F.1.2.

Accident-monitoring instrumentation A. -Noble gas 7.5 Open B. - Iodine/particulate sampling 7.5 Open C. - Containment high range monitoring 7.5 Open D. - Containment pressure 7.5 Open E. - Containment water level Open 65

Item Title ApplicableStusCmes 1

I ~~~~FSAR SttsCmes

______________________________________________Section F. - Containment Hydrogen 7.5 Open II.F.2 Instrumentation for detection of inadequate core-cooling 7.5 Open II.G.1 Power supplies for pressurizer relief valves, block valves 4.4, 6.3, 7.5 Open and level indicators 7.4, 7.5, I1.K.1.5 Review ESF valves 8.3.1 Closed I1.K.1.10 Operability status Open I1.K.1.17 Trip per low-level B/S Closed II.K.3.1 Auto PORV isolation Open II.K.3.3 Reporting SV/RV failures/challenges 15.5.3 Open I1.K.3.5 Auto trip of RCPs 5.2.2 Open I1.K.3.9 PID controller 15.5.4 Open II.K.3.10 Anticipatory trip at high power Closed II.K.3.17 ECCS outages Open I1.K.3.25 Power on pump seals 6.3 Open I1.K.3.30 SB LOCA methods 9.2.2 Closed II.K.3.31 Plant specific analysis 15.5.5 Open III.D.1.1 Primary coolant outside containment 15.5.5 Open 5.5.7, 6.3, III.D.3.3 In-plant 12 radiation monitoring 9.2 Open II1.D.3.4 Control-room habitability Closed 6.4 i

.1 __________________________

-t _______________

I ___________________________

66

Chapter 21 - Corrective Action Programs and Special Programs Description Status for Unit 2

1.

CAP - Cable Issues Open

2.

CAP - Cable Tray Supports Open

3.

CAP - Conduit Supports Open

4.

CAP - Design Baseline Verification Open Program

5.

CAP - Electrical Issues Open

6.

CAP - Equipment Seismic Open Qualification

7.

CAP - Fire Protection Open

8.

CAP - Hanger and Analysis Update Open Program

9.

CAP - Heat Code Traceability Open

10.

CAP - HVAC Duct Supports Open

11.

CAP - Instrument Sensing Lines Open

12.

CAP - Pre-start Test Program Withdrawn. TVA will perform a Regulatory Guide 1.68 Preoperational Test Program for Unit 2

13.

CAP - QA Records Open

14.

CAP - Q-List Open

15.

CAP - Piece Parts Open 67

Description Status for Unit 2

16.

CAP - Seismic Analysis Open

17.

CAP - Vendor Performance Open

18.

CAP - Welding Open

19.

SP - Concrete Quality Complete

20.

SP - Containment Cooling Open

21.

SP - Control Room Design Review Open

22.

SP - Equipment Qualification Open

23.

SP - Master Fuse List Open

24.

SP - Mechanical EQ Open

25.

SP - Micro. Induced Corrosion Open

26.

SP - MELB Flooding Open

27.

SP - Radiation Monitoring System Open

28.

SP - Soil Liquefaction Complete

29.

SP - Use-as-is CAQs Open 68

Chapter 22 - Regulatory Guide Applicability for Watts Bar Unit 2 Regulatory Guide Title i Rev Full or Partial SRP Section Compliance

1. 1 - Net Positive Suction Head for Emergency Core Cooling Full 6.3 and Containment Heat Removal System Pumps / Rev. 0 1.4 - Assumptions used for Evaluating the Potential Partial 2.3.4, 6.2.1, 6.5.1, 6.5.2, 6.5.3, 12.2, 12.3, 12.4, Radiological Consequences of a Loss of Coolant Accident for 15.6.5, 15.6.3 Pressurized Water Reactors / Rev. 2 1.6 - Independence Between Redundant Standby (onsite) Power Full 8.3.1, 8.3.2 Sources and Between Their Distribution Systems / Rev. 0 1.7 - Control of Combustible Gas Concentrations in Partial 3.8.1, 3.8.2, 6.2.5, 6.5.1, 7.5, 12.2, 12.3, 12.4, Containment Following a Loss of Cooling Accident / Rev. 2 15.6.5 1.8-Qualification and Training of Personnel for Nuclear Partial 12.1, 12.5, 13.1.1, 13.1.2, 13.1.3, 13.2.1, 13.2.2, Power Plants / Rev. 2 17.1, 17.2 1.9 - Selection, Design and Qualification of Diesel Generator Partial 8.3.1, 8.4, 18 Used as Standby (onsite) Electric Power Systems at Nuclear Power Plants / Rev. 3
1. 10 - Mechanical (Cadweld) Splices in Reinforcing Bars of Partial Category I Concrete Structures / Rev. I 1.12 - Instrumentation for Earthquakes / Rev. I Full 3.7.4 1.13 - Spent Fuel Storage Facility Design Basis / Rev. I Partial 9.1.1, 9.1.2, 9.1.3, 9.1.5, 9.4.2 1.14 - Reactor Coolant Pump Flywheel Integrity / Rev. I Partial 5.4.1.1 I. 15 - Testing of Reinforcing Bars for Category I Concrete Partial Structures / Rev I
1. 16 - Reporting of Operating Information, Appendix A Partial 14.2 Technical Specifications / Rev 4 1.20- Comprehensive Vibration Assessment Program For Partial 3.9.5, 14.2 Reactor Internals During Preoperational and Initial Startup Testing/ Rev. 2 69

Regulatory Guide Title / Rev Full or Partial SRP Section Compliance 1.21 - Measuring, Evaluating, and Reporting Radioactivity in Partial 9.3.2 Solid Wastes and Releases of Radioactive Materials in Liquid and Gaseous Effluents from Light-Water-Cooled Nuclear Power Plants / Rev. I 1.22 - Periodic Testing of Protection System Actuation Full 7.2, 7.3, 7.9, 18 Functions / Rev.0 1.23 - Onsite Meteorological Programs / Rev. 0 Partial 2.3.2, 2.3.3, 2.3.4, 2.3.5, 13.3 1.24 - Assumptions Used for Evaluating Potential Radiological Full 2.3.4 Consequences of a Pressurized Water Reactor Radioactive Gas Storage Tank Failure / Rev. 0 1.25-Assumptions Used for Evaluating Potential Radiological Partial 4.2, 6.5.1, 9.4.2, 15.7.4, 15.7.5 Consequences of a Fuel Handling Accident in the Fuel Handling and Storage Facility for Boiling and Pressurized Water Reactors / Rev. 0 1.26 - Quality Group Classifications and Standards for Water, Partial 3.2.2, 3.9.4, 5.2.1.1, 5.2.2, 5.4.11, 6.2.7, 9.1.3.

Steam, and Radioactive Waste Containing Components of 9.3.2, 9.3.4, 10.4.8, 17.1, 17.3 Nuclear Power Plants / Rev. 3 1.27 - Ultimate Heat Sink for Nuclear Power Plants / Rev. I Partial 2.4.1-2.4.9, 2.4.11, 2.4.12, 3.5.2, 9.2.5 1.28 - Quality Assurance Program Requirements - Design and Full 2.5.4, 2.5.5, 17.1, 17.3 Construction / Rev. 3 1.29 - Seismic Design Classification / Rev. I Partial 2.4.1-2.4.11, 2.4.14, 3.2.1,3.4.1, 3.9.4, 5.2.2, 5.2.5, 5.4.7, 5.4.11 6.2.4, 6.3, 9.1.2-9.1.5, 9.2.1-9.2.3, 9.2.5, 9.3.2-9.3.4, 9.4.1-9.4.5, 10.3, 10.4.7-10.4.9, 17.1, 17.3 1.30 - Quality Assurance Requirements for the Installation, Partial 14.2, 17.1 Inspection and Testing of Instrumentation and Electrical Equipment / Rev. 0 1.31 - Control of Ferrite in Stainless Steel Weld Material / Rev.

Partial 4.5.2, 5.2.3, 5.3.1, 5.4.2.1, 6.1.1 3

70

Regulatory Guide Title / Rev Full or Partial SRP Section Compliance 1.32 - Criteria for Safety-related Electric Power Systems for Full 8.2, 8.3.1, 8.3.2 Nuclear Power Plants / Rev. 2 1.33 - Quality Assurance Program Requirements - Operation /

Partial 11.2, 11.3, 11.5, 12.1, 12.5, 13.1.2, 13.1.3, 13.5.1, Rev.2 172, 17.3 1.36 - Nonmetallic Thenmal Insulation for Austenitic Stainless Partial 5.2.3, 5.4.2.1, 6.1.1, 17.3 Steel / Rev 0 1.37 - Quality Assurance Requirements for Cleaning Fluid Partial 3.13, 5.2.3, 5.3.1, 5.4.2.1, 6.1.1, 10.3.6, 14.2, 17.1 Systems and Associated Equipment of Water Cooled Nuclear Power Plants / Rev. 0 1.38 - Quality Assurance Requirements for Packaging, Partial 17.1 Shipping, Receiving, Storage and Handling of Items for Water-Cooled Nuclear Power Plants / Rev. 2 1.39 - Housekeeping Requirements for Water-cooled Nuclear Partial 17.1 Power Plants / Rev. 2 1.40- Qualification Tests of Continuous-Duty Motors Installed Full Inside the Containment of Water-Cooled Nuclear Power Plants

/ Rev. 0 1.41 - Preoperational Testing of Redundant On-site Electric Full Power Systems to Verify Proper Load Group Assignments /

Rev. 0 1.44 - Control of the use of Sensitized Stainless Steel / Rev.0 Partial 4.5.1, 4.5.2, 5.2.3, 5.3.1, 5.4.2.1,6. 1.1 1.45 - Reactor Coolant Pressure Boundary Leakage Detection Partial 3.6.3, 5.2.5 Systems / Rev.0 1.46 - Protection Against Pipe Whip Inside Containment /

Partial Rev.0 1.47 - Bypassed and Inoperable Status Indication for Nuclear Full 6.3, 7.2, 7.3, 7.4, 7.5, 18 Power Plant Safety Systems / Rev.0 1.48 - Design Limits and Loading Combinations for Seismic Partial Category I Fluid System Components / Rev.0 71

Regulatory Guide Title / Rev Full or Partial SRP Section CornplianceI 1.50 - Control of Preheat Temperature for Welding of Low-Partial 5.2.3, 5.3.1, 5.4.2.1, 6.1.1, 10.3.6 Alloy Steel / Rev. 0 1.52 -Design, Testing and Maintenance Criteria for Post-Partial 6.3, 6.4,.6.5.1. 6.5.3, 9.1.3, 9.4.1 - 9.4.5. 11.3, 12.3, Accident Engineered Safety Feature Atmospheric Cleanup 12.4, 14.2. 15.6.513 System Air Filtration and Adsorption Units of Light Water-Cooled Nuclear Powver Plants / Rev. 2 1.53 - Application of the Single Failure Criterion to Nuclear Full 8.3.1, 8.3.2, 9.2.2 Power Plants Protection Systems / Rev. 0 1.54 - Quality Assurance Requirements for Protective Coatings Partial 17.3, 6.1.2 Applied to Water-Cooled Nuclear Power Plants / Rev. 0 1.55 - Concrete Placement in Category I Structures / Rev. 0 Partial_________________________

1.58 - Qualification of Nuclear Power Plant Inspection, Partial 17.1 Examination, and Testing Personnel / Rev. I1_______________________

1.59 - Design Basis Floods for Nuclear Power Plants / Rev. 2 Partial 2.4.1 - 2.4.10, 2.4.14, 9.2.6, 10.4.9 1.60 - Design Response Spectra for Seismic Design of Nuclear Partial 2.5.2, 3.7.1, 3.7.2, 3.12, 4.2 Power Plants / Rev. I1_______________________

1.61 - Damping Values for Seismic Design of Nuclear power Partial 3.9.2 Plants / Rev. 0 1.62 - Manual Initiation of Protective Actions!/ Rev.0 Full 10.4.9, 18 1.63 - Electrical Penetration Assemblies in Containment for Full 8.3.1, 8.3.2 Nuclear Power Plants/

Rev. 3 1.64 - Quality Assurance Requirements for the Design of Partial 17.1 Nuclear Power Plants / Rev. 2 1.67 - Installation of Overpressure Protection Devices / Rev'. 0 Partial 1.68 -Initial Test Programs for Water-Cooled Nuclear Power Partial 3.9.2, 4.4. 6.3. 10.2, 14.2, 13.1.1. 14.2 Plants / Rev. 2 1.68.2 - Initial Startup Test Program to Demonstrate Remote Partial 14.2 Shutdown Capability for Water-Cooled Nuclear Power Plants/

Rev. I 72

Regulatory Guide Title / Rev Full or Partial SRP Section Compliance 1.68.3 - Preoperational Testing of Instrument and Control Air Partial 14.2 Systems / Rev. 0 1.70 - Standard Format and Content of Safety Analysis Reports Partial 2.1.3, 2.2.3, 2.3.1, 2.3.4, 2.3.5, 2.4.1 - 2.4.8, 3.7.1 -

for Nuclear Power Plants - LWR Edition / Rev. 3 3.7.4,3.8.1-3.8.5, 7.1, 11.3, 11.5, 12.1, 12.3, 12.4, 13.3, 15.4.4 1.71 - Welder Qualification for Areas of limited Accessibility /

Partial 5.2.3, 5.4.2.1, 10.3.6 Rev. 0 1.73 - Qualification Tests of Electric Valve Operators Installed Full Inside Containment of Nuclear Power Plants / Rev. 0 1.74 - Quality Assurance Terms and Definitions / Rev. 0 Partial 17.1 1.75 - Physical Independence of Electrical Systems / Rev. 2 Partial 7.2, 7.3, 7.9, 8.3.1, 8.3.2 1.76 - Design Basis for Nuclear Power Plants / Rev. 0 Partial 2.3.1, 3.3.2, 3.5.1.4, 3.5.3, 9.2.6, 10.4.9 1.77 - Assumptions used for Evaluating a Control Rod Ejection Partial 2.3.4, 4.2, 4.3, 15.4.8, 15.4.8A Accident for Pressurized Water Reactors / Rev. 0 1.78 - Assumptions for Evaluating the Habitability of a Nuclear Partial 2.2.1, 2.2.2, 2.3.4, 6.4, 9.4.1, 14.2 Power Plant Control Room During a Postulated Hazardous Chemical Release / Rev. 0 1.79 - Preoperational Testing of Emergency Core Cooling Partial 6.3 Systems for Pressurized Water Reactors / Rev. 1 1.81 - Shared Emergency and Shutdown Electrical Systems for Partial 3.8.1, 3.8.2, 18 Multi-Unit Nuclear Power Plants / Rev. 1 1.82 - Water Sources for Long-Term Recirculation Cooling Partial 5.4.7, 6.2.2, 6.3 Following a Loss-of-Coolant Accident / Rev. 0 1.83 - Inservice Inspection of Pressurized Water Reactor Steam Partial Generator Tubes /

Rev. I 1.84 - Design and Fabrication Code Case Acceptability ASME Partial 3.2.2, 3.8.1,3.12, 3.13, 4.5.2, 5.2.1.2, 5.2.2, 5.2.3,Section III Division I / Rev 33 5.4.2.1, 6.1.1, 10.3.6 1.85 - Materials Code Case Acceptability ASME Section III NA 3.2.2, 4.5.1 Division I / - Withdrawn Incorporated into RG 1.84 73

Regulatory Guide Title / Rev Full or Partial SRP Section ICornpliance 1.88 - Collection, Storage, and Maintenance of Nuclear Power Partial 17.1 Plants Quality Assurance Records / Rev. 2 1.89 -Qualification of Class IlE Equipment for Nuclear power Partial 3.10 Plants / Rev. 1 1.91 - Evaluation of Explosions Postulated to Occur on Partial 2.2.1-2.2.2, 3.5.1.5, 3.8.1, 3.8.4 Transportation Routes / Rev. 1 1.92 -Combining Model Responses and Spatial Components in Partial 3.7.2, 3.12, 5.4.12 Seismic Response Analysis / Rev. 1 1.93 - Availability of Electric Power Sources / Rev'. 0 Full 1.94 - Quality Assurance Requirements for Installation, Partial 17.1 Inspection and Testing of Structural Concrete and Structural Steel During the Construction Phase of Nuclear Power Plants/

Rev. 1 1.95 -Protection of Nuclear Power Plant Control Room Partial 2.2.1-2.2.2 Operators Against an Accidental Chlorine Release / Rev. 1 1.97 - Instrumentation for Light Water Cooled Nuclear Power Partial 3.10, 6.2.1, 6.2. 1.18B, 6.2.5, 7.5, 9.3.2, 12.3, 12.4, Plants to Assess Plant and Evirons Conditions During and 12.5, 13.3. I8 Following an Accident / Rev'. 2 1.99 - Radiation Embrittlement of Reactor Vessel Materials /

Partial 5.3.2-5.3.3 Rex'. 2

1. 100 - Seismic Qualification of Electrical Equipment for Partial 3.10, 5.4.12 Nuclear Power Plants / Rev. I
1. 101 - Emergency Planning and Preparedness for Nuclear Partial 13.3 Power Plants/

Rex'. 2

1. 102 - Flood Protection for Nuclear Power Plants / Rev. I Partial 2.4.1-2.4.10, 2.4.14, 9.2.6, 10.4.9
1. 105 - Instrument Setpoints for Safety-Related Systems / Rev.

Partial 2.4.1-2.4.10, 2.4.14, 9.3.6, 10.4.9

1. 106 - Thermal Overload Protection for Electric Motors on Partial 8.3.1, 8.3.2 Motor-Operated Valves / Rev. I I________

74

Regulatory Guide Title / Rev Full or Partial SRP Section F _

ýCornpliance

1. 109 - Calculation of Annual Doses to Man from Routine Partial 2.3.5, 11.2.,11.3 Releases of Reactor Effluents for the Purpose of Evaluation Compliance with 10 CFR 50 Appendix I / Rev. I
1. 111 - Methods of Estimating Atmospheric Transport and Partial 2.3.5, 11.3 Dispersion of Gaseous Effluents in Routine Releases from Light Water Cooled Reactors / Rev. I
1. 112 - Calculation of Releases of Radioactive Materials in Partial 2.3.5, 11.1, 11.2, 11.3, 11.5, 12.2 Gaseous and Liquid Effluents from Light Water Cooled Power Reactors / Rev. 0
1. 113 - Estimating Aquatic Dispersion of Effluents from Partial 2.4.13, 11.2 Accidental and Routine Reactor Releases for the Purposes of Implementing Appendix I1! Rev. I
1. 114 - Guidance to Operators at the Controls and to Senior Partial 13.1.2, 13.1.3 Operators in the Control Room of a Nuclear Power Unit / Rev'.

2

1. 115 - Protection Against Low Trajectory Turbine Missiles!

Partial 3.5.1.1, 3.5.1.3, 3.5.2, 3.8.1, 3.8.4, 9.5.5-9.5.8, 10.3 Rev. I

1. 116 - Quality Assurance Requirements for Installation, Partial 14.2, 17.1 Inspection, and Testing of Mechanical Equipment and Systems/

Rev. 0

1. 117 - Tornado Design Classification /Partial 3.5.1.3, 3.5.1.5, 3.5.2, 9.1.2, 9.3.1, 9.5.5-9.5.8, Rev. 1 10.3, 10.4.9
1. 118 - Periodic Testing of Electric Power and Protection Partial 7.2., 7.3. 7.9, 8.3.1, 8.3.2 Systems / Rev. 2
1. 122 - Development of Floor Design Response Spectra for Partial 3.7.2, 3.12 Seismic Design of Flood-Supported Equipment or Components

/ Rev'. I

1. 123 - Quality Assurance Requirements for Control Partial 17.1 Procurement of Items and Services for Nuclear Power Plants/

Rev. I 75

Regulatory Guide Title / Rev Full or Partial SRP Section Compliance 1.124 - Service Limits and Loading Combinations for Class I Full 3.9.3, 3.12 Linear Type Component Supports / Rev. I 1.126 - An Acceptable Model and Related Statistical Methods Partial 4.2, 4.3 for Analysis of Fuel Densification / Rev. I 1.127 - Inspection of Water Control Structures Associated with Partial 3.8.4, 3.8.5 Nuclear Power Plants / Rev. I 1.128 - Installation Design and Installation of Large Lead Partial 3.8.2, 14.2 Storage Batteries for Nuclear Power Plants / Rev. 0 1.129 - Maintenance, Testing and Replacement of Large Lead Full 3.8.2 Storage Batteries for Nuclear Power Plants / Rev. I 1.130 - Service Limits and Loading Combinations for Class I Partial 3.9.3, 3.12 Plate-and-Shell Type Component Supports / Rev. I 1.133 - Loose Part Detection Program for the Primary System Partial 4.4 of Light Water Cooled Reactors / Rev. 1 1.137 - Fuel Oil Systems for Diesel Generators / Rev. I Partial 9.5.4 1.139 - Guidance for Residual Heat Removal / Rev. 0 Partial 14.2 1.140 - Design, Maintenance and Testing Criteria for Normal Partial 6.5.1, 9.4.2, 9.4.3, 9.4.4, 9.4.5, 11.3, 14.2 Ventilation Exhaust System Air Filtration and Adsorption Units of Light Water Cooled Nuclear Power Plants / Rev. I 1.141 - Containment Isolation Provisions for Fluid Systems /

Partial Rev. 0 1.143 - Design Guidance for Radioactive Waste Management Partial 3.2.1. 3.8.3, 3.8.4, 9.2.6, 10.4.8, 11.2, 11.3, 11.4, Systems, Structures and Components Installed in Light Water 11.5, 17.3 Cooled Nuclear Power Plants / Rev. I 1.144 - Auditing of Quality Assurance Programs for Nuclear Partial 17.1 Power Plants / Rev. I 1.145 - Atmospheric Dispersion Models for Potential Accident Partial 2.3.4 Consequence Assessments at Nuclear Power Plants /

Rev. I 76

Regulatory Guide Title / Rev Full or Partial SRP Section Compliance

1. 146 - Qualification of Quality Assurance Program Audit Partial 17.1 Personnel for Nuclear Power Plants / Rev. 0 1.147 - Inservice Inspection Code Case Acceptability ASME Partial 3.8.1, 3.8.2, 5.2.1.2, 5.2.4 Section XI Division I / Rev.
1. 150 - Ultrasonic Testing of Reactor Vessel Welds during Partial 5.2.4 Preservice and Inservice Examinations / Rev I 1.152 - Criteria for Programmable Digital Computer Software Partial 7.1, 7.2, 7.3, 7.4, 7.5, 7.6, 7.7, 7.8, 7.9, 17.3 in Safety-Related Systems of Nuclear Power Plants / Rev. 0 1.153 - Criteria for Power, Instnrmentation and Control Partial 8.3.1, 8.3.2, 9.2.2 Portions of Safety Systems / Rev. 0 1.155 - Station Blackout/ Rev. I Partial 6.2.5, 6.3, 8.2, 8.3.1, 8.3.2, 8.4, 9.2.2, 9.2.6, 9.3.1,.9.3.4, 9.4.1, 9.4.5, 10.3, 10.4.9 1.158 - Qualification of Safety-Related Lead Storage Batteries Partial for Nuclear Power Plants / Rev. 0 1.189 - Fire Protection for Operating Nuclear Power Plants /

Partial 3.2.1, 7.4, 9.5.1, 9.5.2 Rev. 0 Notes:

1. The requirements that must be met before a plant can be licensed are defined in NRC regulations. Over the years, the NRC staff has prepared a number of guidance documents, such as regulatory guides and the Standard Review Plan that define methods that are acceptable to the NRC staff for meeting various requirements in the regulations. Except for a few regulatory guides that are specifically referenced in a regulation, these guidance documents are not requirements. The Standard Review Plan is not a substitute for the NRC's regulations and compliance is not required. Regulatory Guides are not substitutes for regulations and compliance with them is not required.
2. 10 CFR sections, GDCs and Regulatory Guides introduced in the revised SRP are shown in italics.
3. Identification of relevant FSAR section in Chapter 20 is based on current FSAR entries, and future entries may impact other sections.
4. Technical Specification changes discussed in Generic Letters, and related to NUREG-0737, that may require license amendment are not included in this table.

77

- Outstanding Corrective Action Programs and Special Programs Outstanding Corrective Action Programs and Special Programs This Attachment provides a description of the Watts Bar Nuclear Performance Plan (NPP) Corrective Action Programs (CAPs) and Special Programs (SPs),

and a summary of their resolution for WBN Unit 1. TVA has evaluated these CAPs and SPs in order to determine their applicability to WBN Unit 2. These issues are listed in the order used in the NPP.

TVA will resolve the WBN Unit 2 CAPs and SPs consistent with NUREG-1232 (Volume 4), NUREG-0847 and applicable regulations. If, during this process, TVA determines that it is necessary to modify the criteria otherwise specified in NUREG-1232, it will submit such changes to the NRC for review and concurrence. TVA will use the procedures, databases and templates that were developed for WBN Unit 1 to the fullest extent practical for WBN Unit 2.

Corrective Action Programs:

1.

Cable Issues The Cable Issues CAP was initiated based on various employee concerns, conditions adverse to quality (CAQ) documents, and NRC findings related to cable installation and routing.

The Cable Issues CAP identified the following issues:

1. Silicone rubber insulated cables
2. Cable jamming
3. Cable support in vertical conduits
4. Cable support in vertical trays
5. Cable proximity to hot pipes
6. Cable pullbys
7. Cable bend radius
8. Cable splices
9. Cable sidewall bearing pressure
10. Pulling cables through 90-degree condulets and mid-route flexible conduits
11. Computerized Cable Routing System (CCRS) software and data base verification and validation Each of these issues is discussed individually below:

Silicone Rubber Insulated Cables The initial test program proposed by TVA for SQN in April of 1987 to address concerns with silicone rubber insulated cables, included hi-pot testing of silicone rubber insulated cables manufactured by American Insulated Wire (AIW), Rockbestos and Anaconda. The testing revealed a I

Outstanding Corrective Action Programs and Special Programs significant number of failures in AIW cables. TVA decided to replace AIW cables. Rockbestos and Anaconda cables were successfully tested at Wyle Laboratories for 40 year qualified life.

Cable Jamming NRC identified the potential for undetected cable damage since TVA-WBN documents did not address cable jam ratio. When single conductors with unacceptable jam ratios are pulled into a conduit, the cable may align in a flat configuration with resultant jamming.

For Unit 1, Class 1 E conduits were evaluated to identify those segments most likely to have experienced jamming during installation. These segments were ranked according to their calculated percent sidewall bearing pressure. A sampling of cables were removed and inspected, and no evidence of damage due to jamming was identified. The inspected cables included those with the highest calculated side wall bearing pressure and are considered to bound the lower ranked cables.

Cable Support in Vertical Conduits NRC expressed a concern that cables in long vertical conduits were inadequately supported and that random failures due to cutting of the insulation and conductor creep may occur during normal service conditions, especially for silicone rubber insulated cables.

For Unit 1, TVA identified the critical cases of silicone rubber insulated cables in vertical conduits, with cable bearing pressure occurring at the edge of the condulet the determining factor. A comparison was made of WBN critical cases with those already tested at SQN. If SQN conduits enveloped WBN, no cable testing by WBN was performed. If SQN conduits did not envelope WBN, cable was replaced or in situ cable testing was performed. If the testing option was selected, any cable found unacceptable was replaced. Additionally, TVA evaluated Class 1 E conduits containing cables of all insulation types using acceptance criteria that provided for cable supports to be added for the conduits in which the cable bearing pressure, conductor strength, or resultant loading imparted to the cable insulation, terminations or splices exceeded manufacturer's limits, as a result of the cable weight from the long vertical distance. In addition, cable installation specification and site procedures were revised to incorporate appropriate cable support requirements for cable installed in vertical conduits, and thereby prevent recurrence.

Conduits that exceeded the support requirements of General Construction Specification G-38 were analyzed and conduit support points with bearing 2

-Attachment 2 Outstanding Corrective Action Programs and Special Programs pressure greater than allowable were inspected and supports added as required.

Cable Support in Vertical Trays TVA's construction specification requires that cables in vertical trays be supported in accordance with the National Electric Code to prevent long term cable damage. The installation specification stated that this support may be provided by tie wraps. However, TVA had no basis to verify that cable ties can provide adequate support.

TVA evaluated the acceptability of various tie wrap configurations as support systems. If a configuration was found to be inadequate, it was shown by analysis, similarity to other installations, or testing that no cable damage had occurred or would occur. Cable support was added for those cables in which the cable bearing pressure, conductor and insulation strength, or the resultant loading imparted to the cable terminations or splices exceed manufacturers' limits, as a result of the cable weight. To prevent recurrence, TVA revised the cable installation specification and site procedures to identify acceptable methods for support of cables in vertical trays if the existing support system proved to be inadequate.

Cable Proximity to Hot Pipes Cables were designed for 40 year life at ambient temperatures that do not include the local effects of hot pipes which increase local temperature and can degrade the cable insulation and shorten the life of the cables. For Unit 1, criteria were developed to detail required clearances between cable/raceways and hot pipes/valves to eliminate this potential impact.

Class 1 E cables were walked down against the criteria to ensure that adequate separation existed between the cables and hot pipes/valves.

Deviations were resolved by analysis, change of pipe insulation or raceway rework.

Cable Pullbys A 1989 inspection of electrical cables found cable insulation damage. This damage resulted in exposure of five instrumentation cables in the Unit 2 Reactor Protection System. Laboratory analysis confirmed TVA's initial assessment that the damage occurred as result of cable pullby. During the scope assessment effort, additional cables were removed and additional damage was found. These deficiencies were addressed at the time.

For Unit 1, TVA identified those locations where cable pull tension and cable side wall bearing pressure had exceeded certain safe threshold 3

Outstanding Corrective Action Programs and Special Programs values, and cables that were most susceptible to this damage mechanism based on the conduit configuration. Cables that were in high risk and medium risk conduits were replaced. The threshold between low and high risk categories was validated via hi-pot testing or visual inspection and cables in the low risk category conduits were accepted-as-is based on the hi-pot tests performed on a sample of low risk category conduits.

Cable Bend Radius TVA determined that the minimum bend radius recommended by the Insulated Cable Engineers Association had been violated at WBN.

Excessive bending has the potential of damaging cables and adversely affecting their performance.

To resolve this issue on Unit 1, TVA established bend radius parameters (upper and lower bounds) for class 1 E cables and revised General Construction Specification G-38 to include the bend radius requirements for cable installation. Cable was then categorized based on 10CFR50.49 requirements, classification and voltage level. Cables were then inspected and replaced, retrained or their qualified life was reduced, based on bending or kinking relative to upper and lower bound bend radii.

Cable Splices TVA's internal review of WBN splicing details and experience at SQN indicated that the installed splices may not conform to the qualified configurations and materials tested by the vendor. To resolve this issue a list of Class 1 E cable splices in harsh and mild environments was developed. Cables and splices were identified by reviewing equipment qualification binders and construction records to determine which equipment uses pigtails for field cable connection. 1 OCFR50.49 harsh environment cable splices were replaced and some mild environment cable splices were reworked. A sampling program was implemented to verify that the splice list was complete for intermediate splices.

Cable Sidewall Bearinq Pressure At WBN, sidewall bearing pressure (SWBP) was not properly addressed in the design and installation process and installations may have exceeded the allowable value. To resolve this issue on Unit 1, TVA conducted a walk down to identify worst case conduit configurations, calculated the expected pulling tension and SWBP for those worst case conduits and performed a test to determine increased allowable SWBP values, based on actual cables used at TVA nuclear plants. These results were reviewed by a third party contractor.

4 Outstanding Corrective Action Programs and Special Programs TVA revised construction specifications to require that SWBP be limited to the values determined by the above activities. WBN site installation procedures were revised to provide explicit cable SWBP restriction to cable pulling limits.

Analysis of the severe case conduits against these limits revealed that the cable in one conduit may have exceeded these values and this cable was replaced. An additional sample of conduits, all in harsh environment, was examined and none exceeded allowable SWBP.

Pulling Cable through 900 Condulet and Flexible Conduits A concern was raised for the potential damage to cables in 900 condulets due to the small supporting surface the inside corners of condulets provide for cables under tension. Those corners can in time cut into the insulation, or the conductor can creep through the insulation, reducing the insulation level of the cables. Also, there was a concern at WBN that when cable is pulled through a flexible conduit segment in a bend, in the middle of a conduit run, it can be subjected to very high frictional forces that can tear the cable jacket and insulation.

TVA evaluated cables pulled through mid-route flexible conduits which had been tested for pullby damage, and inspected cables removed and confirmed that no damage was caused by the mid-route flexible conduits.

Computerized Cable Routing System (CCRS) Software and Database Verification and Validation CCRS was used to document information regarding cable routing. The information includes cable route in trays and conduits, cable type, cable weight, cable splices, circuit function and separation etc. There were concerns for the adequacy of CCRS. CCRS has been replaced by new software called ICRDS. The CCRS data has been transferred to ICRDS for Units 1 and 2.

2.

Cable Tray and Cable Tray Supports A combination of Employee Concerns, CAQs and NRC violations identified deficiencies with cable trays and their supports. The specific deficiencies included inadequate tray connections, inconsistencies between as-designed versus as-built tray configurations and their orientation, and failure to evaluate all loading on cable tray members.

Programmatically, these issues were categorized as a lack of documented design qualification for certain cable tray hardware, installed configuration not complying with design output documents, and a lack of documentation to verify previous re-inspection.

5 Outstanding Corrective Action Programs and Special Programs The CAP for Unit 1 assured the structural adequacy and compliance with design criteria and licensing requirements by:

Review and revision of design criteria.

Review or development of design output requirements to comply with design criteria and to adequately translate TVA design requirements.

Examples were development of generic validation calculations for typical hardware configurations and evaluation of critical cases.

" Walk down of field configurations to identify deviations from design output.

Modifications to field conditions, where necessary, to ensure that they were consistent with design output documents.

The CAP also put improvements in place to ensure the adequacy of new or modified cable trays and their supports. This was accomplished by training to revised design criteria and strengthened Nuclear Engineering (NE) procedures to allow plant configuration to be changed only on the basis of NE approved drawings, and by adding inspection requirements to verify fittings and connectors are installed consistent with Design Basis Document requirements.

3.

Design Baseline and Verification Program TVA became aware of inconsistencies in WBN licensing and design basis documentation as well as plant configuration issues as a result of several internal and external reviews that were conducted both at the plant and at the corporate level. The following conditions were identified by these reviews:

Inconsistencies between the WBN Final Safety Analysis Report and WBN design documentation 0

Incomplete and some inconsistent design input information 0

Missing, incomplete and out-of-date design calculations 0

Inconsistencies between the actual plant configuration and the as-constructed drawings.

The causes of these conditions were found to be:

Lack of effective licensing and design change control procedures and data bases to ensure that design requirements were maintained consistent with the FSAR and other commitments to NRC.

Insufficient definition of design criteria and system description information at the level of detail needed to control design changes.

6 Outstanding Corrective Action Programs and Special Programs

" Lack of a complete calculation listing to establish the full scope of calculations needed for WBN and procedures to ensure the calculations are maintained consistent with the WBN design.

" Lack of an effective definition of drawings to be maintained under configuration control and an ineffective system for keeping appropriate drawings "as-constructed" as plant changes are made.

The underlying root cause of this situation was determined to be ineffective design and configuration control measures.

TVA developed the WBN Design Baseline and Verification Program (DBVP) to correct the situation that had developed and to prevent the recurrence of such a situation by eliminating the root cause. The DBVP had four major components, each having objectives that addressed one or more of the above problems. These components and objectives of each were:

Licensing Verification Assure that commitments to NRC are captured in the appropriate highest level controlling document Establish procedures to maintain compatibility between commitments and controlling documents.

" Design Basis Establish system and topical design basis documents (DBD) that contain or reference appropriate engineering requirements including design basis commitments Establish procedures to maintain the design basis consistent with changes to the plant, technical requirements and licensing commitments.

" Calculations Assure the existence and retrievability of calculations that are technically adequate and consistent with the safety-related plant design Establish a process for statusing calculations that will maintain them current with plant design changes.

" Configuration Control Develop and implement an improved design change control system Establish a single set of configuration control drawings (CCDs)

Utilize walk downs, evaluations or testing to verify that the functional configurations of the portions of plant systems that mitigate plant design basis events are consistent between CCDs and the constructed plant.

7 Outstanding Corrective Action Programs and Special Programs

4.

Conduit Supports Employee Concerns, CAQs and the Weld Task Group identified deficiencies in the conduit support program. Subsequently, a sample of conduit supports was reviewed to gain insight into specific nonconforming attributes. A number of specific structural deficiencies were identified including inadequate conduit clamps, conduit runs supported at only one location, and excessively cantilevered conduit. While these specific discrepancies were different from those identified for cable trays and their supports, programmatically the problems were similar and fell into four major categories:

Design Basis discrepancies.

Design output not enveloping all design parameters.

Installed configurations not in compliance with design documents.

Discrepancies between as-installed configurations and inspection documentation.

The CAP for Unit 1 assured the structural adequacy and compliance with design criteria and licensing requirements by:

Revisions to design criteria Updated design output documents including specifications to factor in changes to design criteria, changes to typical support details and new support details. As with cable trays, critical case evaluations were performed for those configurations that did not meet design criteria.

Walk downs first to support critical case evaluations, then to identify configurations not enveloped by critical cases

" Modifications, as required Revisions of implementing procedures to ensure the adequacy of new or modified supports

5.

Electrical Issues The Electrical Issues CAP was initiated based on various employee concerns, conditions adverse to quality documents, and NRC findings related to electrical installation, materials and equipments. The root cause of these concerns was primarily the absence or incompleteness of specific guidelines in the development of design input or output documents and, in some instances, the lack of procedural details for the installation of electrical components.

The CAP addressed the adequacy of safety-related electrical installations in the following areas:

8 Outstanding Corrective Action Programs and Special Programs

1. Flexible Conduit Installations
2. Physical cable separation and electrical isolation
3. Contact and coil rating of electrical devices
4. Torque switch and overload relay bypass capability for active safety related valves
5. Adhesive backed cable support mounts (ABSCM)

Each of these issues is discussed individually below.

Flexible Conduit Installations The problems identified with flexible conduits were:

  • Inadequate length to account for seismic/thermal movement Lack of compliance with minimum bend radius requirements 0 Loose Fittings To resolve these issues for Unit 1, TVA revised design output documents to more specifically define flexible conduit requirements for:

Seismic/thermal movement Minimum bend radius Tightness of fittings A list of flexible conduits attached to Class 1 E pipe mounted devices was then developed to identify those flexible conduits which would experience both seismic and thermal movement. Finally, TVA walked down Class 1 E flexible conduits and reworked those found to be damaged or in noncompliance with the design output documents.

Physical Cable Separation and Electrical Isolation CAQs and an employee concern identified isolated cases of less than the minimum required separation as specified by IEEE 279-1971, Standard Criteria for Protection Systems for Nuclear Generating Stations, IEEE 308-1971, Standard Criteria for Class 1 E Electrical Systems for Nuclear Power Plants and Regulatory Guide (RG) 1.6, Independence Between Redundant Standby (Onsite) Power Sources and Between Their Distribution Systems.

For Unit 1, this issue was subdivided into three issues and each was resolved separately. The issues were:

Separation between redundant divisions of Class 1 E raceways, Internal panel separation between redundant divisions of Class 1 E

cables, 9

Outstanding Corrective Action Programs and Special Programs Coil-to-contact and contact-to-contact isolation between Class 1 E and non-Class 1 E circuits.

For inadequate separation between redundant divisions of Class 1 E raceways, the raceways were reworked to meet the minimum separation requirement and site implementing procedures were revised to require specific signoffs for raceway separation attributes.

For inadequate internal panel separation between redundant divisions of Class 1 E cables design criteria were revised to include more detailed requirements for internal panel cables, an engineering output document was issued to define the requirements for internal panel cable separation and a list of panels with redundant divisions of Class 1 E cables was developed. Panels containing cables of redundant divisions were walked down to identify cables which did not comply with the revised engineering output document and these were evaluated to determine acceptability or reworked to meet required separation distances.

For coil-to-contact and contact-to-contact isolation between Class 1 E and non-Class 1 E circuits a calculation was developed to determine when coil-to-contact and contact-to contact isolation were acceptable, design criteria were revised to specify acceptable isolation methods and the existing Class 1 E coil and contact devices used as isolators were reviewed to determine that they were qualified for their intended use.

Contact and Coil Rating of Electrical Devices Problem Identification Reports were issued at WBN for deficiencies where the design and procurements of inductive devices contained in the circuits did not consider the inductive load ratings of contacts or the maximum credible voltage available at the device terminals.

To resolve this for Unit 1, TVA reviewed devices that performed inductive load switching and determined if the contacts had acceptable current ratings and reviewed inductive devices to determine if coils were qualified for the highest and lowest credible voltages. If a device could not be qualified, design output documents were issued to require replacement and qualified devices were installed.

Torque Switch and Overload Relay Bypass Capability for Active Safety Related Valves In order to meet the intent of Regulatory Guide 1.106, Thermal Overload Protection for Electric Motors on Motor Operated Valves, certain active safety related valves required to operate during a design basis event must have thermal overload and torque switches bypassed to ensure 10 Outstanding Corrective Action Programs and Special Programs operability. Employee concerns and CAQs identified that TVA did not provide thermal overload and torque switch bypass capability for certain active safety-related valves.

For Unit 1, TVA issued design criteria to provide the basis for determining which active valves were required to have their thermal overload relays and torque switches bypassed and issued a calculation to identify these values. System design criteria or system descriptions were revised to identify which valves within a system require thermal overload and torque switches bypass capability, design output documents were revised to provide the required thermal overload and torque switch bypass capability, and thermal overload and torque switch bypasses were installed where they did not already exist.

Adhesive Back Cable Support Mounts A CAQ documented that vendors and TVA used Adhesive Back Cable Support Mounts (ABSCM) inside equipment to support and restrain wire and field cables in a neat and orderly fashion. The ABSCMs sometimes separated from the inside of the equipment and, as a result, may not have properly secured the wire or cable.

For Unit 1, TVA contacted the vendors of the panels/equipment to ascertain the technical requirements for the ABSCMs for the vendor's wiring, evaluated the use of ABSCMs for field wiring and issued a calculation identifying the technical requirements for existing ABSCMs.

TVA then evaluated the as-installed conditions to determine if any corrective action was required, issued and implemented design output documents in the field and revised site implementing procedures to incorporate the necessary installation requirements and to restrict the use of ABSCMs.

6.

Equipment Seismic Qualification TVA internal reviews and employee concerns involving seismic qualification of equipment identified a number of deficiencies which were documented in CAQRs, PIRs and SCRs. These deficiencies involved configuration and document control issues and included specific technical discrepancies. Some of the more significant technical discrepancies were:

" Set B spectra accelerations (site specific with corrections) were greater than Set A (Modified Newmark, originally used) for equipment in Category I structures

  • Inadequate qualification of anchorages for tanks, pumps, heat exchangers and equipment mounted on flexible supports

" Discrepancies associated with installation of solenoid valves I1 Outstanding Corrective Action Programs and Special Programs Anchor bolt spacing/proximity violations.

To address these and other specific issues, TVA implemented the Equipment Seismic Qualification (ESQ) CAP. The objectives of the program were to provide assurance that Category I and I (L) equipment are seismically qualified, that qualification documentation is retrievable and this documentation is consistent with the design and licensing basis.

The main elements of the program were:

0 Review and revision of design bases to ensure that they were technically adequate and consistent interfaces existed between them and other design bases (e.g. for piping loads and documents that establish seismic classification)

Resolution of specific technical issues utilizing the following tasks:

Document retrieval Walk downs to identify and describe as-built vs. as-designed discrepancies and aid in the determination of the actions required to resolve them Engineering evaluations, including bounding calculations, to qualify equipment for their as-built configuration, and modifications when equipment could not be qualified in the as-built configuration Development and population of the ESQ database to maintain and control data required to qualify equipment

  • Process improvements to ensure appropriate interfaces and prevent recurrence.
7.

Fire Protection The Fire Protection (FP) CAP was initiated after the identification of a number of issues at TVAN plants to ensure that the WBN fire protection program was complete and in compliance with licensing requirements.

The specific items that were among these issues included:

In 1987, TVA identified fire-rated walls that were breached by HVAC ducts without fire dampers. The condition violated Appendix R requirements pertaining to fire rated walls that separate safety-related equipment of redundant trains.

" In 1988, several SQN Appendix R discrepancies were identified by TVA in response to employee concerns and by NRC during inspections of the SQN Fire Protection Program. TVA committed to perform a review of these issues for applicability to WBN.

" Deficiencies were identified with the Safe Shutdown Analysis (SSA) in 1989.

12 Outstanding Corrective Action Programs and Special Programs In response to the above issues and other more specific deficiencies, the Unit 1 FP Program (for Unit 1 and common areas) contained the following actions:

" TVA initiated a CAQR to document the measures taken to evaluate violation of the Appendix R requirements and DCNs were issued to correct the deficiencies.

" TVA reviewed SQN Appendix R concerns, as well as issues raised by the NRC during SQN inspections, for applicability to WBN. CAQs were initiated to address the SQN inspection report items which were deemed applicable to WBN and DCNs were issued to correct the deficiencies.

A Fire Protection Compliance Review was performed to ensure WBN conformance with NRC requirements and applicable guidelines. The following typical areas of fire protection requirements were addressed:

Safe Shutdown Analysis (SSA)

Area Heat-up Analysis Fire Hazards Analysis Lighting and Communication Post-Fire procedures Associated Circuits Modification Compliance Review Fire Protection Training/Administrative Procedures The results of the Compliance Review were used as the basis for developing the remaining scope of work (calculations/analysis, DCNs and document updates) and the consolidation of fire protection documentation into an organized package to support and substantiate the Compliance Review.

" TVA updated the SSA based on the latest as-constructed plant configuration. Also, the lessons learned from the SQN and BFN Appendix R inspections were factored into the revised SSA.

8.

Hanger and Analysis Update Program (HAAUP)

During the design and construction of WBN, NRC issued several Bulletins concerning piping analysis and pipe support design. At the same time, at Watts Bar, piping and pipe support deficiencies were being identified through employee concerns, CAQRs, NCRs, problem identification reports, significant condition reports, and internal/external audits and reviews. The identified issues are listed below with their root causes:

Control of Design Input/Output Design input was not consistently defined and controlled.

13 Outstanding Corrective Action Programs and Special Programs Design output was not clearly defined and, thus, was not consistently implemented by Construction.

" Design/Analysis Methodology Design criteria for piping analysis and pipe support design did not specify a consistent and comprehensive set of design/analysis methods. In some cases relevant industry issues were not considered.

Level of Design Documentation Requirements for closure of unverified assumptions and documentation of engineering judgments were neither fully defined nor procedurally controlled.

The scope of the HAAUP activities for Unit 1 included Seismic Category I piping, Seismic Category I (L) piping and those instrument lines that could not be decoupled from their process piping, and associated supports.

(Those instrument lines that could be decoupled were addressed in the Instrument Line CAP). The HAAUP also addressed the issue of pipe support component substitution for catalog items. The following corrective actions were taken to address the deficiencies:

Criteria and procedures governing piping system analysis and design were reviewed to ensure that they were in compliance with industry practices and were technically sound. The results of this review were incorporated into the implementing criteria and procedures utilized for the HAAUP.

As-built information for installed piping and associated pipe supports was obtained by walk downs using the updated procedures.

Pipe stress and support calculations were updated or newly generated:

To incorporate changes in the seismic response spectra input to envelope sets B and C, and to add consideration of mass participation above 33 Hz.

To qualify as-built conditions in drawings and calculations.

To ensure drawings and calculations are in compliance with current design criteria and procedures.

Resolution of open items and identified deficiencies were incorporated into the design documents.

" Design documents were updated to incorporate the as-built piping and support configurations.

" Modifications were performed, as required.

" Shop made pipe support components were evaluated using a sampling of the different types of components and a 95% confidence level that 95% of the supports satisfied design basis was used to establish acceptability.

14 Outstanding Corrective Action Programs and Special Programs

9.

Heat Code Traceability Traceability issues were identified and documented in 1985 during a review of ASME Section III N-5 data packages. Subsequently, similar issues were identified through employee concerns and CAQRs. These concerns involved ASME loose piping and fitting material and ASTM material installed as welded attachments on ASME piping systems and were categorized as:

" ASME Class 1 systems that may contain ASME Class 2, Class 3 and/or ASTM piping for which adequate NDE may not have been performed

" ASME Class 2 systems that may contain class 3 piping, and ASME Class 2 and Class 3 systems that may contain ASTM piping for which adequate NDE may not have been performed

" ASME systems that may have ASTM plate material attached (welded)

For the Unit 1 program, which included common systems, the following corrective actions were taken:

  • Accuracy of the information contained in the Heat Code Database (HCDB) was first verified by comparing it to information on CMTRs.

This information was used to flag situations where the same ASME material (same heat code) was used in systems of different classifications.

For Class 1 piping, surface NDE was performed on piping materials where the heat number was the same as for material used in a non Class 1 system. When NDE was not feasible, alternate analysis prescribed by the ASME Code was performed. Material which could not be examined or technically justified was replaced.

For Class 2 and 3 piping, required NDE was performed for piping components where classification traceability was questionable and they were installed in locations where stress ratios exceeded 0.80 for welded carbon steel and 0.85 for welded stainless steel. Additionally, for cases where ASTM, ASME Section II and ASME Section III material which may have been upgraded to ASME Section III, Class 2 or 3 materials, the items were re-verified as meeting all other requirements of Section III (material specifications, QA and design) on a sampling basis. Engineering evaluations were performed on non-complying items to provide a basis of acceptance. Material determined to be unacceptable, was replaced.

0 ASTM plate attachment material used in ASME applications was determined to be acceptable by verifying equivalence to an ASME specification, that it was supplied to an acceptable QA program and 15 Outstanding Corrective Action Programs and Special Programs that it had the necessary NDE performed. Material that could not be verified or justified as being acceptable was replaced.

Recurrence control included revising the General Construction Specification to include specific ASME requirements for reclassification of material and site implementing procedures to require CMTR traceability of materials to be installed.

10.

HVAC Duct and Duct Supports The HVAC Duct and Duct Supports CAP was implemented to address adverse conditions, which can be characterized as: incomplete design basis; inadequate design documents; as-built configurations not in conformance with existing design documents; inadequate or incomplete inspection documentation; and incomplete instructions.

For Unit 1, TVA resolved these issues via the following four tasks:

Completing the design basis by reviewing and revising the design criteria, issuing supporting calculations as necessary and updating the FSAR to be consistent with the upgraded design criteria, Updating design output documents to be consistent with the completed design basis, 0 Revising construction, maintenance and QA procedures to incorporate design output documents, and 0 Developing bounding critical cases of existing installations and evaluating their adequacy, and performing unique evaluations or modifying installations when they could not be qualified by the critical case evaluations, thereby ensuring compliance with design basis.

11.

Instrument Sensing Lines As a result of WBN employee concerns and conditions adverse to quality (CAQ) documents, an overall review of instrumentation related issues was initiated in 1985. The review determined that the technical issues associated with instrument sensing lines required a separate and independent program to evaluate the functional and structural problems on these lines. The program was labeled the WBN Instrument Line CAP.

The problems identified fell into two categories:

Functional problems related to instrument line slope.

The scope of the functional issue (slope) included sense lines associated with instruments that perform a safety-related function. It also included sense lines associated with instruments that have a particular sensitivity to the effects of entrapped air.

16 Outstanding Corrective Action Programs and Special Programs A number of the sense lines were found to not conform to the minimum slope requirements specified on design output drawings. The number of lines involved and the lack of adequate configuration control for these lines resulted in the following actions to address slope requirements:

Preparation of an Engineering Requirements (ER) Specification The identification of sense lines to be reworked to meet the ER Preparation and issuance of sense line isometric drawings, support drawings, calculations, and analysis Installation and inspection of the sense lines per design output requirements.

In addition to the development of the ER Specification, other recurrence control measures were implemented for future design, installation, and inspection activities. These included site implementing procedures to incorporate ER in the process for the installation, maintenance, and inspection.

Structural problems related to:

Thermal effects Pipe and tube bending devices Compression fittings Installation discrepancies (inadequate or loss of documentation of sense line supports).

The scope of the structural issues included Seismic Category I and I (L) instrument lines, and their associated supports, which are analytically decoupled from the process lines. Responses to these issues are described below:

Thermal Effects The review determined that instrument lines and associated supports were not designed to consider the effects of thermal expansion and operating modes for these lines indicated that portions of the sampling and radiation monitoring systems will operate at temperatures for which thermal effects could be significant. These Unit 1 lines were field sketched to identify material, line configuration and support type.

The lines were analyzed for dead weight, seismic and thermal effects.

Detailed line isometric drawings were prepared showing required line configuration, support type and material. Any deficiencies were corrected through the issuance of a design change package.

17 Outstanding Corrective Action Programs and Special Programs Recurrence control was ensured by the issuance of a procedure which identified coordination requirements between Engineering disciplines associated with the qualification of thermal instrument lines.

Pipe and Tube Bending Devices It was also determined that site implementing procedures used to qualify pipe and tube bending devices were not rigorously executed and that qualification records for the bending were not always maintained.

The corrective action consisted first of a sampling program which considered 200 randomly selected bends from an estimated total population of approximately 15,000 bends. The following attributes were evaluated: wall thickness reduction, ovality, acceptable bend contour, and surface condition. These samples were evaluated and found to be acceptable and bender qualification records were updated to incorporate the results of the sample program. Secondly, recurrence controls were established by the issuance of the Pipe and Tube Bending procedure and training requirements for personnel performing bending.

Compression Fittings Various compression fitting installations were found that were not in accordance with the fitting manufacturer's installation requirements. A sample inspection of 107 compression fittings used on instrument lines was performed and 60 discrepancies were identified. The discrepant installations were categorized as: tubing cuts that were not deburred, tubing that was not bottomed out inside the fittings, nuts that were not properly tightened, and ferrules that were either judged to be unidentifiable, missing, or reversed. Also, certain discrepant fitting installations included parts supplied by different manufacturers.

TVA performed a vibration and pressure test program for the identified discrepant compression fitting installations. This program included testing of the effects of tubing burrs on flow rate as well as testing of the integrity of fittings with various installation deficiencies by tensile pullout, vibration and seismic tests. The results of these tests demonstrated that for the instances where tube ends were not deburred, tubes were not bottomed out, or nuts were not properly tightened, fitting performance was still satisfactory. Also, normal operation vibration testing did not result in leaks in any of the samples tested and seismic testing only produced very slight leakage (undetectable on the pressure gauges) in 2 of the 47 samples. The 18 Outstanding Corrective Action Programs and Special Programs seismic tests were conservative and represented a severe test of fitting integrity.

The test program for fittings with missing, reversed, or unidentified ferrules determined that:

Missing ferrules would cause a definite leak during pressure testing.

Reversed ferrules would leak if they are "CPI" fittings.

Reversed ferrules would not leak if they are reversed "Hi-Seal" ferrules.

TVA determined that for these three particular types of questionable ferrule installations, unacceptable installations would be detected during pressure testing due to leakage. If these questionable fitting configurations are used in instrument lines that are not pressure tested, there would be no driving force to create any significant leakage.

Therefore, the corrective action consisted of the following activities:

Instrument lines designated as Seismic Category I or I(L) were pressure tested in accordance with appropriate piping code requirements Fittings seeing radioactive service in lines not pressure tested (i.e.,

drains) were re-inspected to verify installation in accordance with manufacturer's recommendations, and discrepancies found during the inspection were repaired or replaced.

In summary, for ferrule installations, since pressure testing was performed as required and leaking compression fittings were repaired or replaced, the final configurations were ultimately acceptable.

Recurrence controls consisted of revising specifications, design drawings and procedures, and requiring personnel to be trained and certified before they could perform installation and inspection activities.

Installation Discrepancies A condition was identified whereby some instrument line support documentation was determined to be lost or incorrect and it was not apparent that this condition did not apply to all Seismic Category I and I (L) instrument line supports. The corrective action consisted of a random sample of 60 instrument line supports selected for a detailed evaluation to determine the acceptability of the as-built condition. The evaluation determined that the instrument lines and supports would 19 Outstanding Corrective Action Programs and Special Programs comply with existing design basis requirements provided all attachment clamps and bolts were properly installed. The supports were then walked down to assure that the proper clamps were used and their installation was in accordance with established engineering requirements and, when necessary, the supports were reworked.

Recurrence controls consisted of updating site implementing procedures to ensure adequate installation and inspection requirements were in place.

11.

Prestart Test The Prestart Testing Program CAP for Unit 1 was withdrawn with the resubmittal of Chapter 14 of the FSAR to conform to the requirements of Regulatory Guide 1.68. The entire program is described in Chapter 14 of Amendment 91 of the FSAR.

12.

QA Records A review of WBN construction, maintenance and operations quality records required for licensing found that some records:

" Were not retrievable in a timely manner or potentially missing

" Were not maintained in proper storage Had quality problems (were incomplete, technically or administratively deficient)

To address these issues the QA Records CAP was developed. The objectives of this CAP were to:

Ensure adequate storage and retrievability of required WBN construction, maintenance and operations records.

" Resolve quality and technical problems related to WBN construction, maintenance and operations records.

Ensure programs adequate to prevent reoccurrence of records problems are established.

During the course of implementation of the CAP additional records issues were identified. Evaluation of these issues indicated a need to expand the scope to address the full extent of condition by including a broader set of records categories. This was accomplished through an Additional Systematic Records Review (ASRR) of ANSI N45.2.9 Appendix A record types, which was incorporated into the CAP. This review involved both records and hardware and was based on sampling and statistical analysis.

It provided a high level of confidence in the adequacy of QA Records.

.20 Outstanding Corrective Action Programs and Special Programs

14.

Q-List The problems associated with the WBN Q-List Program identified in the CAP included:

Multiple Q-Lists

  • Inadequate training Lack of and improper classifications Wrong component identification The objectives of the Q-List CAP were to:

0 Develop a new Q-List Compare this new Q-List to the old Q-List to identify upgraded components 0 Review maintenance and modification activities performed since 1984 to assure that those activities had the appropriate QA program controls applied.

As part of corrective action for this CAP, over 5000 component classification upgrades were identified during the comparison of the new and old Q-Lists. No field work resulted from these upgraded components.

15.

Replacement Items Replacement Items CAP was established as a result of weaknesses in TVA's policies, procedures, and practices in the area of commercial grade items purchased for installation in safety-related applications. Previous TVA policies and procedures did not adequately direct and control engineering involvement in the procurement process used to purchase replacement items. Neither did the TVA procedures incorporate industry (EPRI and NUMARC) guidance or comply with NRC Generic Letters 89-02 and 91-05.

The CAP grouped the issues into four categories:

" Current and future purchases Current warehouse inventory

" Plant installed items from previous maintenance activity

" Replacement items installed by previous construction activities To address these categories, TVA:

21 Outstanding Corrective Action Programs and Special Programs

" Created the Procurement Engineering Group, dedicated to review and evaluation of each procurement made for safety-related applications and developed a process for these activities.

" Created the Material Improvement Project to evaluate the adequacy of current inventory with respect to technical adequacy, QA receipt inspection and material storage.

" Back checked materials installed from previous maintenance activities to ensure that a proper documentation trail existed from the warehouse to maintenance history for each item.

" Reviewed the construction group's procurements of replacement items. This review indicated that the required documentation for parts traceability was available and that the materials were procured properly with engineering involvement.

16.

Seismic Analysis An independent review of the seismic analysis calculations for seismic Category I structures performed as part of the DBVP, the ECP and CAQRs identified issues and concerns that required further evaluation of the calculations, licensing requirements and design criteria.

The issues identified were consolidated into the following categories:

Integration time step used to perform time history analysis.

Soil properties and soil-structure interaction concerns

  • Torsional modeling of structures

" Seismic analysis criteria for the Additional Diesel Generator Building

  • The effect of floor and wall flexibility on design of SSC (structures, systems and components) in Category I structures The seismic design basis for WBN is the Modified Newmark design spectrum (known as Set A) anchored at 0.18 g horizontal and 0.12 g vertical for the Safe Shutdown Earthquake (SSE). The Operating Basis Earthquake (OBE) is equal to one-half the SSE. The design basis spectra were determined to be acceptable by comparison with the Site Specific Spectra developed in 1979. The seismic design basis documented in the WBN FSAR and reviewed by NRC was accepted and documented in the WBN SER. However, consideration of the above identified issues required a re-evaluation of the two spectra and this was done for Unit 1, with the appropriate determination of accelerations to apply to Unit 1 and common SCCs (Set B for site specific and Set C for the modified Newmark).

The Diesel Generator Building (DGB), Additional Diesel Generator Building (ADGB), Auxiliary-Control Building (A/CB), Condensate Demineralizer Waste Evaporator (CDWE) Building and the Intake 22 Outstanding Corrective Action Programs and Special Programs Pumping Station (IPS) are common and covered by Unit 1 scope and no additional work is required for Unit 2. However, for the Interior Concrete Structure (ICS), Shield Building (SB), Steel Containment Vessel (SCV),

Refueling Water Storage Tank (RWST), North Steam Valve Room (NSVR) and Pipe Tunnels for Unit 2, the original design basis spectra need to be compared to the site specific spectra and the comparisons documented as required.

For commodities and components, the spectra comparison between analysis using the original spectra and analysis using site specific spectra will be performed under the separate CAPs for these items (HVAC, HAAUP, Conduit, Cable Trays, Integrated Interaction Program and Equipment Seismic Qualification).

17.

Vendor Information TVA conditions adverse to quality reports, employee concerns, and TVA and NRC audit findings identified problems with vendor information at Watts Bar. Specific problems identified included:

Vendor information didn't match the plant configuration.

Vendor information was inconsistent with associated TVA-developed design input/output documents.

Vendor documents were incorrect or out of date.

Vendor manuals were lost or were uncontrolled.

The Vendor Information CAP for Unit 1 addressed these problems and their causes via the following actions:

Relevant vendor information for safety-related and quality related Unit 1, common and Unit 2 components needed for Unit 1 operation were identified, reviewed for technical adequacy and consolidated into applicable Vendor Technical Manuals and Vendor Technical Documents, which were issued as controlled documents.

Standard Procedure SSP-2.10 (which is now superseded by the current TVA procedure SPP-2.5) was issued to control vendor manual update activities.

Open Item Reports were generated, tracked, and controlled to resolve the inconsistencies found in the vendor documents.

Vendor drawings which included information necessary to support safety-related plant activities, but were not in "Approved" status, were reviewed and approved.

DCNs were issued to resolve identified design discrepancies/open items.

23 Outstanding Corrective Action Programs and Special Programs

18.

Welding NRC inspections, NCR's, CAQR's, audit findings and employee concerns identified programmatic and implementation deficiencies associated with safety related welding activities. In response to these issues, TVA established the TVA Welding Project to perform a review and determine the adequacy of the overall welding program, including that at WBN.

Subsequently, the Welding CAP was established to ensure that Unit 1 safety-related welds meet TVA licensing requirements and provide specific corrective actions to address the prior issues and those identified by the Welding Project. The Welding CAP included both installation and vendor welding deficiencies which were related to weld quality, inspections, NDE, fabrication/installation code compliance, and associated documentation.

For Unit 1, the Welding CAP consisted of three phases:

" A programmatic assessment

" An in depth review of the implementation of the welding program and corrective actions to address specific discrepancies Program enhancements to prevent recurrence The specific deficiencies that had to be addressed for Unit 1 involved structural steel, piping components, pipe supports, instrument panels, HVAC ductwork and vendor supplied component such as tanks and heat exchangers. The types of deficiencies included:

" Designs that did not satisfy design criteria for welding

" Lack of documentation of required visual inspections Indications or weld discontinuities

" Radiographs accepted with rejectable indications, inadequate radiographic techniques, and radiographic film identification discrepancies Misinterpretation of the ASME Code

" Discrepancies on vendor performed welds Errors on installation documentation These problems were addressed by a combination of techniques that included the following:

Re-inspections to validate results and support analysis

" Conservative bounding analysis

" Evaluation of as-is condition to determine acceptability

" Repairs, if necessary 24 Outstanding Corrective Action Programs and Special Programs Special Programs

1.

Concrete Quality An employee concern identified 24 issues related to concrete that subsequently resulted in the identification of three significant conditions involving concrete quality. They were:

" Some concrete mixes did not meet design compressive strength requirements,

" The use of mortar was not properly controlled, and Concrete sampling frequencies did not always comply with the requirements identified in specifications.

These issues were resolved and closed for Units 1 and 2 by the Concrete Quality Special Program. An NRC inspection (Inspection Report 390/90-26 and 391/90 January 8, 1991) concluded that the concrete quality concern issues were resolved. Therefore, this program is complete for Unit 2.

2.

Containment Cooling During performance of EQ activities for Unit 1, TVA documented in a CAQR that the post-accident pressure and temperature analysis for the lower compartment in containment failed to consider the long-term effects of a main steam line break inside containment for a plant going to hot standby conditions as opposed to cold shutdown. 10CFR50.49 (e).l requires that, "The time-dependent temperature and pressure at the location of electrical equipment important to safety must be established for the most severe design basis accident during or following which this equipment is required to remain functional." In order to ensure that this requirement is satisfied, TVA performed the Containment Cooling Special Program to develop time dependent temperature profiles for the lower compartment, which were then used for EQ. This was accomplished by the following tasks.

" Correcting the long-term containment temperature profile for the lower compartment considering the design basis Main Steam Line Break (MSLB) event using the Ice Condenser and Containment Spray systems as safety-grade systems for removing containment ambient (post accident) heat.

Upgrading the Lower Compartment Cooler (LCC) units and associated ducting, with the exception of the LCC coils, to safety-grade, thus ensuring a qualified means of providing air circulation to sub compartments of the lower containment to prevent hot spots from forming.

25 Outstanding Corrective Action Programs and Special Programs Evaluating containment coatings transport and replacing non qualified coatings to ensure that such coatings did not affect sump screen performance.

Using the revised calculated MSLB temperature profile to qualify components in the lower containment that are important to safety.

3.

Control Room Design Review The Control Room Design Review (CRDR) program was developed in response to the NRC requirement established following the Three Mile Island Station accident that licensees and applicants conduct a CRDR to identify and correct human factor discrepancies in their control rooms.

NUREG guidance for the conduct of the CRDR allowed licensees to perform a Preliminary Design Assessment (PDA) to identify any Human Engineering Discrepancies (HEDs) and establish a schedule for corrections with NRC staff approval and complete a full CRDR at a later date.

TVA performed a PDA and submitted the results to the NRC in January 1981. Discrepancies identified resulted in license commitments to implement corrective actions to resolve them and a CRDR Summary Report was identified as a license condition. TVA conducted a CRDR and submitted a CRDR Summary Report in October 1987. The CRDR addressed the man-machine interfaces and potential misapplication of human factor principles in the main control room, the auxiliary control room and the adjacent switch transfer rooms. Using a qualified multi-disciplined review team, TVA established a review program plan incorporating accepted human factor principles, gathered and reviewed required plant design information, surveyed the Control Room, identified and assessed HEDs, determined design improvements required and verified that the design improvements would address deficiencies and not create new ones.

Actions to ensure recurrence controls included:

0 Corporate Engineering issuing Human Factor Design Guides 0 Site Engineering issuing Human Factor Design Criteria The Design Change Process requiring human factors to be addressed The CRDR Program was the subject of a series of audits and reviews, which led to revisions and further development of HED corrective actions for Unit 1, common equipment needed for Unit 1 and Unit 2 equipment needed to support Unit 1. The Unit 1 program was completed in 1995.

26 Outstanding Corrective Action Programs and Special Programs

4.

Environmental Qualification of Electrical Equipment 10 CFR 50.49 requires that equipment used to perform a necessary safety function is capable of maintaining functional operability under all service conditions postulated to occur during their installed life under normal operating and accident conditions. It is furthermore required that the evaluation of equipment qualification (EQ) be documented and maintained in auditable files. TVA conducted a management review of the EQ programs at SQN, BFN, and WBN in July and August of 1985. This review indicated that much of the qualification documentation was not fully auditable and, in some cases, the documentation available did not demonstrate full qualification.

The Equipment Qualification Special Program was initiated to address these discrepancies. Its primary objective was to document that safety related electrical equipment installed in the plant was qualified to perform their designated function in the environment to which they will be subjected during normal plant operation as well as during postulated accidents. Further, that programs and procedures have been established to ensure that qualification is maintained as future plant modifications are made. TVA put in place the tools to accomplish these objectives and, while they have evolved to satisfy today's requirements, these tools form the basis of the processes used to implement the WBN Unit 1 EQ Program, those currently used at TVA's nuclear plants and what will be implemented for Unit 2. These processes include:

EQ program procedures which are the basis of plant procedures to maintain EQ over the operating life of the plant

  • Consistent documentation requirements for the list of electrical equipment located in harsh environments and required to function after an accident, and the EQ Documentation Package providing documented evidence of the qualification of equipment for its specific application and environment
  • Sources of information which provide the above evidence and appropriate reviews of this information Incorporation of EQ considerations into maintenance activities for equipment The activities performed to satisfy the objectives for both EQ items qualified in place and those installed during the Unit 1 completion effort included:

Analyses of the effects of pipe breaks (HELB and MELB) on temperature, humidity, dose and water level at various locations in containment and auxiliary buildings to establish the parameters for 27 Outstanding Corrective Action Programs and Special Programs areas of the plant containing equipment that must meet 1 OCFR 50.49 requirements.

Identification of 10CFR 50.49 equipment in these areas, the 50.49 list.

This list included electrical equipment located in harsh environment and required to function after an accident. It was developed through a series of steps:

A systems analysis to determine for each DBA those equipment items required to ensure completion of a safety-related function.

For each item, a review of drawings to identify those ancillary devices and cable required to operate or maintain electrical integrity to ensure completion of the item's safety related function.

This list of items is reduced by performing a failure analysis which eliminates those components whose failure would not prevent achievement of the required safety action.

Establishment of EQ binders that contain the qualification information in an auditable manner. This was accomplished using a documented process to direct completion of documented evidence of qualification of equipment for their specific application and environment. A package was developed for each Unit 1 equipment type. The package included:

Items comprising the equipment type Checklist for evaluation of qualification Analysis and justification of qualification Qualification documents Field verification data Qualification Maintenance Data Sheets Open items and deficiencies

5.

Master Fuse List Conditions adverse to quality documents and Nuclear Regulatory Commission findings identified deficiencies related to the design and configuration control of over current protection devices and the misapplication of Bussman KAZ actuators as protective devices. The programmatic issue was lack of control of these devices on the master fuse list and the lack of procedural guidance for the development of the Master Fuse List.

This Special Program was established for Unit 1 to resolve these deficiencies. The program included three primary elements:

To address configuration control deficiencies, a baseline master fuse list was developed using as-designed schematics, connection drawings and vendor drawings to establish a comprehensive list of 1 E 28 Outstanding Corrective Action Programs and Special Programs fuses for Unit 1, and Unit 2 fuses needed to support the operation of Unit 1 systems; then walk downs were performed to gather as-installed information to be included on the list.

" To resolve the Bussman KAZ actuator misapplication a review was performed of schematic and connection drawings to identify KAZ locations and then an analysis performed and a DCN developed to replace the KAZ devices with conventional fuses. Unit 2 circuits that were needed for unit 1 operation were identified and redesigned to eliminate the KAZ actuators.

  • To correct deficiencies involving redundancy provided to electrical penetration assemblies, an analysis was conducted to verify that redundant protection was provided by design and, when not the case, identified deficiencies were corrected.

While the principle focus of the program was on 1 E Safety-Related equipment subsequent efforts have resulted in the program evolving to establish similar controls and practices for fuses needed to support the operation of the station.

6.

Mechanical Equipment Qualification The Mechanical Equipment Qualification (EQ) Program was initiated in response to an NRC requirement that TVA conduct a documented evaluation of the ability of safety-related mechanical equipment located in harsh environment to perform their intended functions, as required by GDC-4 of Appendix A of 1 OCFR5O.

The Unit 1 program utilized existing temperature and dose conditions developed for electrical equipment to satisfy 1 OCFR50.49. The program then identified active safety-related mechanical equipment located in harsh environments; analyzed the non-metallic subcomponents for effect of thermal and radiation conditions; produced controlled binders to establish and maintain qualified status for life of plant; and issued DCNs to modify the plant consistent with qualification tests and analyses.

7.

Microbiologically Induced Corrosion (MIC)

Due to leakage events in several water systems including Essential Raw Cooling Water and MIC degradation at other TVAN plants, TVA committed to a corporate program to address MIC in 1987. In addition, TVA committed to specific actions to address requirements of NRC Generic Letter 89-13, "Service Water System Problems Affecting Safety-related Equipment" and the potential for existing MIC conditions in Unit 1.

The special program for Unit 1 included:

29 Outstanding Corrective Action Programs and Special Programs

" Identifying systems potentially affected by MIC via testing of water samples Performing visual inspections Reviewing design and operating documents and pre-existing NDE results to identify vulnerable locations

" Assessing MIC-infested locations identified during visual inspections

" Repairing unacceptable damage to Code requirements Installing improved biocide treatment and a long term chemical clean up system This was later augmented by the implementation of SPP-9.7, Corrosion Control Program, which specifies the programmatic and organizational requirements for management of the MIC and Macrofouling Program and delineates the program's key elements.

8.

Moderate Energy Line Break Moderate energy lines are defined as piping that during normal conditions, are either in operation, or maintained pressurized (above atmospheric pressure) at temperatures less than or equal to 200 degrees F or pressures less than or equal to 275 psi. For these lines, TVA determined that documentation was inadequate to justify that there were no unacceptable consequences as a result of flooding in a Category I structure outside of containment following a moderate energy line break (MELB).

For Unit 1, TVA evaluated whether essential equipment and structures were either unaffected by postulated flooding due to a pipe break on a moderate energy pipe, or are designed, specified, and/or qualified for the environment caused by such flooding. The evaluation involved pipe break analyses, determination of postulated break locations, determination of postulated flooding levels, and equipment qualification evaluations. In those instances where it was determined that an item was impacted and it could not be qualified, modifications were performed to make the necessary plant upgrades. Modifications providing curbs, raising junction boxes and adding or removing weather stripping were performed.

9.

Radiation Monitoring System The WBN Radiation Monitoring System (RMS) Special Program was established to address deficiencies identified by employee concerns, CAQs and internal reviews. These deficiencies involved RMS design, documentation, installation, and hardware, and are categorized in three areas of concern. These are:

30 Outstanding Corrective Action Programs and Special Programs 0 Sample line deficiencies included excessive sample line length, incomplete heat tracing, minimum bend radius violations, incorrect slope, and violation of sample line separation requirements.

0 Design and documentation deficiencies included:

Design defects on sample flow equipment Purge capability following an accident not provided in the design of some radiation monitors System interlocks with containment isolation were not provided in the containment upper and lower compartment monitor design Undocumented modifications performed on the RMS rate meters RMS rate meter cable damage due to rough, unfinished edge of the radiation monitors' cabinet.

0 Calibration issues included inadequate documentation of the traceability of the primary calibration records to support equipment testing and calibration resulting in uncertainty in the validity of the equipment calibration and the level of radioactivity indicated or alarmed.

The actions to address these deficiencies for Unit 1 were to review and update the RMS design basis, including applicable requirements of Regulatory Guide 1.97, evaluate the RMS against this design basis, and to implement modifications to correct RMS deficiencies. This also included an evaluation of the RMS design, documentation, and installations against the updated design criteria to verify the acceptability of the installation or to identify required modifications for those monitors included in the technical specifications and modifications or reworking of existing documentation to correct identified documentation.

10.

Soil Liquefaction The potential for soil to liquefy is a design consideration at Watts Bar Nuclear Plant and the Soil Liquefaction Special Program was implemented to assure that employee identified issues regarding the design and construction of soil mitigating measures on the west side of the Intake Pumping Station were addressed. The actions taken as part of this program were an evaluation of the concerns in three areas:

" Alternate material used for backfill Incomplete excavation of potentially liquefiable sand.

" Leakage between the IPS and Trench B.

To address these issues for Unit 1, TVA conducted an investigation into the concerns. In addition, an independent investigation was performed by R. L. Cloud and Associates with review by the late H. B. Seed of 31 Outstanding Corrective Action Programs and Special Programs University of California, Berkeley (a noted expert in the area of soil liquefaction). Based on the investigations, it was concluded that the areas of concern did not have a detrimental effect on liquefaction mitigation measures.

Implementation of the Soil Liquefaction Program is complete for both units. The FSAR revisions resulting from the work were submitted to NRC as part of Amendment 63. The NRC documented their review and acceptance that the WBN underground barriers provide sufficient confinement for liquefied soil in the affected area in Safety Evaluation Report Supplement No. 3. The NRC endorsed the approach for the Soil Liquefaction Special Program by NUREG-1232, subject to inspection of TVA's actions. Final inspection accepting the completion of this program was reported in NRC Inspection Report 390/92-45 and 391/92 February 17, 1993. There will be no impact on this status as a result of completion of Unit 2.

11.

Use-As-Is CAQs In 1986, Nuclear Engineering conducted an audit of the Watts Bar engineering program activities related to the handling of construction non-conformance reports. They identified that use-as-is and repair non-conformance dispositions were not reflected on drawings; there was inadequate justification for disposition of these types of non-conformances; and no project level procedural guidance was provided for use-as-is and repair dispositions. This program was initiated to address these issues.

To prevent recurrence, engineering procedures were issued to establish the requirements for handling CAQs including a specific requirement to ensure that appropriate design documents reflect the approved configuration for any use-as-is or repair disposition. These procedures also required the basis for approval of any use-as-is or repair dispositions be documented along with the disposition on the CAQ report.

For Unit 1, this was followed by the identification of CAQs that had a final disposition of either use-as-is or repair and performance of technical reviews of the latest revision of affected design documents considering the impact of the CAQ.

32

- Listing of Generic Letters, Bulletins and TMI Action Items issued before 1995 Listing of Rules, Bulletins and Generic Letters and TMI Action Items issued before 1995

1.

10CFR50.63 - Station Blackout

2.

IEB 76 Relay Coil Failures - GE Type HFA, HGA, HKA, HMA Relays

3.

IEB 77 On-Line Testing of the W Solid State Protection System

4.

IEB 79 Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts

5.

IEB 79 Seismic Analysis for As-Built Safety-Related Piping Systems

6.

IEB 79 Temperature Effects on Level Measurements

7.

IEB 79 Frozen Lines

8.

IEB 79 Loss of Non-Class lE I & C Power System Bus During Operation

9.

IEB 80 Analysis of a PWR Main Steam Line Rupture with Continued Feedwater Addition

10.

IEB 80 Vacuum Condition Resulting in Damage to Chemical Volume Control System Holdup Tanks

11.

IEB 80 Engineered Safety Features Reset Control

12.

IEB 80 Contamination of Non-radioactive System and Resulting Potential for Unmonitored, Uncontrolled Release of Radioactivity to Environment

13.

IEB 80 Masonry Wall Design

14.

IEB 80 Maintenance of Adequate Minimum Flow Thru Centrifugal Charging Pumps Following a Secondary Side High Energy Rupture

15.

IEB 80 Failure of W Type W-2 Spring Return to Neutral Control Switches

16.

IEB 80 Prevention of Damage Due to Water Leakage Inside Containment

17.

IEB 84 Refueling Cavity Water Seal I

18.

IEB 85 Undervoltage Trip Attachment of W DB-50 Type Reactor Trip Breakers

19.

IEB 88 Rapidly Propagating Fatigue Cracks in Steam Generator Tubes

20.

IEB 88 Potential Safety-Related Pump Loss

21.

IEB 88 Nonconforming Materials Supplied by Piping Supplies, Inc. and West Jersey Manufacturing Company

22.

IEB 88 Thermal Stresses in Piping Connected to Reactor Cooling Systems

23.

IEB 88 Thimble Tube Thinning in Westinghouse Reactors

24.

IEB 88 Nonconforming Molded-Case Circuit Breakers

25.

IEB 88 Pressurizer Surge Line Thermal Stratification

26.

IEB 89 Failure of Westinghouse Steam Generator Tube Mechanical Plugs

27.

IEB 89 Stress Corrosion Cracking of High-Hardness Type 410 Stainless Steel Preloaded Bolting in Anchor Darling Model S350W Swing Check Valves or Valves of Similar Nature

28.

IEB 90 Loss of Fill-Oil in Transmitters Manufactured by Rosemount

29.

GL 78-02 -Asymmetric Loads Background and Revised Request for Additional Information

30.

GL 78 Request for Information on Cavity Annulus Seal Ring

31.

GL 78 Reactor Vessel Atypical Weld Material

32.

GL 79 Cracking in Feedwater Lines

33.

GL 79 Adequacy of Station Electric Distribution System Voltages

34.

GL 80 LWR Primary Coolant System Pressure Isolation Valves

35.

GL 80 Vacuum Condition Resulting in Damage to Chemical Volume Control System Holdup Tanks

36.

GL 80 -46/47 - A-12, Fracture Toughness and Additional Guidance on Potential for Low Fracture Toughness and Laminar Tearing on PWR Steam Generator Coolant Pump Supports 2

37.

GL 81 Control of Heavy Loads (Addresses NUREG-0612)

38.

GL 81-21 -Natural Circulation Cooldown

39.

GL 82 Inadequate Core Cooling Instrumentation System (Addresses TMI Item II.F.2)

40.

GL 82 Supplement to NUREG-0737, Requirements for Emergency Response Capability

41.

GL 83 Required Actions Based on Generic Implications of Salem ATWS Events:

2.2 - Equipment Classification and Vendor Interface (All SR Components) 4.1 - Reactor Trip System Reliability (Vendor Related Modifications)

42.

GL 85 Recommended Actions Stemming From NRC Integrated Program for the Resolution of Unresolved Safety Issues Regarding Steam Generator Tube Integrity

43.

GL 85 Implementation of TMI Item II.K.3.5 - Automatic Trip of Reactor Coolant Pumps

44.

GL 88 Boric Acid Corrosion of Carbon Steel Reactor Pressure Boundary Components in PWR plants

45.

GL 88 NRC Position on Radiation Embrittlement of Reactor Vessel Material and its Impact on Plant Operations

46.

GL 88 Instrument Air Supply System Problems Affecting Safety-Related Equipment

47.

GL 88 Loss of Decay Heat Removal

48.

GL 88 Individual Plant Examination for Severe Accident Vulnerability

49.

GL 89 Guidelines on Developing Acceptable Inservice Testing Programs

50.

GL 89 TMI Action Plan Item I.D.2 - Safety Parameter Display System

51.

GL 89 Erosion/Corrosion-Induced Pipe Wall Thinning

52.

GL 89 Safety-Related Motor-Operated Valve Testing and Surveillance

53.

GL 89 Service Water System Problems Affecting Safety Related Equipment 3

54.

GL 89 Request for Actions Related to Resolution of Unresolved Safety Issue A-47 "Safety Implication of Control Systems in LWR Nuclear Power Plants" Pursuant to 10 CFR 50.54(f)

55.

GL 89 Potential for Increased Roof Load Due to Changes in Maximum Precipitation

56.

GL 90 Resolution of Generic Issues 70, "PORV and Block Valve Reliability," and 94, "Additional LTOP Protection for PWRs"

57.

GL 92 Reactor Vessel Structural Integrity

58.

GL 92 Thermo-Lag 330-1 Fire Barriers

59.

GL 93 Rod Control System Failure and Withdrawal of Rod Control Cluster Assemblies, 10 CFR 50.54(f)

60.

NUREG 0612 - Control of Heavy Loads - Response is in 7/21/93 response to GL 81-07

61.

NUREG 0737 - TMI Items:

I.C. 1 Short Term Accident and Procedure Review I.C.7 NSSS Vendor Revision of Procedures I.C.8 Pilot Monitoring of Selected Emergency Procedures for NTOLs I.D. 1 Control Room Design Review I.D.2 Plant-Safety-Parameter-Display Console II.B. 1 Reactor-Coolant-Vent-System II.B.2 Plant Shielding II.B.3 Post-Accident Sampling System II.D. 1 Relief and Safety Valve Test Requirements II.D.3 Valve Position Indication II.E. 1.1 Auxiliary Feedwater System Evaluation, Modifications II.F. 1.2.A Accident-Monitoring Instrumentation - Noble Gas II.F. 1.2.B Accident-Monitoring Instrumentation - Iodine/Particulate Sampling II.F. 1.2.C Accident-Monitoring Instrumentation - Containment High Range Monitoring 4

II.F. 1.2.D Accident-Monitoring Instrumentation - Containment Pressure II.F. 1.2.F Accident-Monitoring Instrumentation - Containment Water Level II.F. 1.2.D Accident-Monitoring Instrumentation - Containment Hydrogen II.F.2 Instrumentation for detection of inadequate core-cooling II.G. 1 Power Supplies for Pressurizer Relief Valves, Block Valves and Level Indicators II.K. 1.10 Operability Status II.K.3.1 Auto PORV Isolation II.K.3.3 Reporting SV/RV Failures/Challenges II.K.3.5 Auto Trip of RCPs II.K.3.9 PID Controller II.K.3.17 ECCS Outages II.K.3.25 Power on Pump Seals II.K.3.31 Plant Specific Analysis III.D. 1.1 Primary Coolant Outside Containment III.D.3.3 In-Plant 12 Radiation Monitoring III.D.3.4 Control-Room Habitability.

5

- List of new Regulatory Requirements and Generic Communications Listing of new Regulatory Requirements and Generic Communications

Rule, Title Associated SRP Section Bulletin or GL
1.

50.65 Maintenance Rule 3.8.3, 3.8.4, 3.8.5, 5.4.2.2, 8.2, 8.3.1, 8.3.2

2.

50.68 Criticality Accident Requirements 9.1.1, 9.1.2, 12.3, 12.4

3.

50.60 Fracture Toughness Requirements 5.3.1. 5.3.2, 5.3.3 and

-Pressurized Thermal Shock 50.61

-Thermal Annealing

4.

Bulletin Control Rod Insertion Problems (PWR) 96-01

5.

Bulletin Movement of Heavy Loads over Spent Fuel, over 96-02 Fuel in the Reactor, or over Safety-Related Equipment

6.

Bulletin Circumferential Cracking of Reactor Pressure 01-01 Vessel (RPV) Head Penetration Nozzles

7.

Bulletin RPV Head Degradation and Reactor Coolant 02-01 Pressure Boundary Integrity

8.

Bulletin RPV Head and Vessel Head Penetration Nozzle 02-02 Inspection Program

9.

Bulletin Potential Impact of Debris Blockage on Emergency 03-01 Sump Recirculation I

Rule, Title Associated SRP Section Bulletin or GL
10. Bulletin Leakage from RPV Lower Head Penetrations and 03-02 Reactor Coolant Pressure Boundary Integrity
11.

Bulletin Inspection of Alloy 82/182/600 Materials Used in 04-01 the Fabrication of Pressurizer Penetrations and Steam Space Piping Connections at PWRs

12. GL 95-03 Circumferential cracking of Steam Generator (SG)

Tubes

13. GL 95-05 Voltage Based Repair Criteria for W SG Tubes Affected by Outside Diameter Stress Corrosion Cracking
14. GL 95-07 Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves
15. GL 96-01 Testing of Safety-Related Circuits 8.3.1
16. GL 96-03 Relocation of the Pressure Temperature Limit 5.2.2 Curves and Low Temperature Overpressure Protection System Limits
17. GL 96-05 Periodic Verification of Design-Basis Capability of 3.9.6 Safety-Related Motor-Operated Valves
18. GL 96-06 Assurance of Equipment Operability and 9.2.1, 9.2.2 Containment Integrity During Design-Basis Accident Conditions 2
Rule, Title Associated SRP Section Bulletin or GL
19. GL 97-01 Degradation of Control Rod Drive Mechanism 4.5.2, 5.2.3 Nozzle and Other Vessel Closure Head Penetrations
20. GL 97-04 Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps
21. GL 97-05 SG Tube Inspection Techniques
22. GL 97-06 Degradation of SG Internals
23. GL 98-02 Loss of Reactor Coolant Inventory and Associated Potential for Loss of Emergency Mitigation Functions While in a Shutdown Condition
24. GL 98-04 Potential for Degradation of the ECCS and the Containment Spray System After a LOCA Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment
25. GL 03-01 Control Room Habitability
26. GL 04-01 Requirements for SG Tube Inspection
27. GL 04-02 Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at PWRs
28. GL 06-01 SG Tube Integrity and Associated Technical Specifications
29. GL 06-02 Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power 3
Rule, Title Associated SRP Section Bulletin or GL
30. GL 06-03 Potentially Nonconforming Hemyc and MT Fire Barrier Configurations -
31. GL 07-01 Inaccessible or Underground Power Cable Failures 8.3.1 that Disable Accident Mitigation Systems or Cause Plant Transients 4

- Construction Completion Organization

Senior Vice President I

I Nuclear Generation

__Chief Nuclear Officer WBN Site Vice President Development and Construction i

.I Licensing Nuclear Assurance Manager General Manager Vice President Nuclear Assurance

(

ChiefAdministrativeOfficer

)

Watts Bar 2 Project Manager Contracts/

Procurement Manager I

II I

I I

I~

Ep Scheduling Cost Pre-Op Startup Modification/

Construction Operations Safet Concerns Manager Manager Manager Engineering Maint. Mgr.

Manager Manager Manager Manager Updated 7/25/07

- Listing of Commitments Made in Letter

1. TVA will provide a regulatory framework submittal for WBN Unit 2 completion by January 31, 2008.
2. TVA plans to provide a red-line version of the WBN Unit 1 FSAR early in the project.

The schedule for submitting this markup FSAR will be provided in the regulatory framework document.

3. Subsequent to the initial submittal, TVA intends to provide updates, as appropriate, to the regulatory framework submittal until the WBN Unit 2 commitments related to fuel load, startup and power operation are complete.
4. The WBN Unit 2 Preservice Inspection Program was last submitted to NRC on April 30, 1990.

TVA will provide a revised program for NRC approval.

5. TVA will provide the Pressure Temperature Limits Report for WBN Unit 2 for NRC approval.