NRC Bulletin 79-26, Boron Loss From BWR Control Blades

From kanterella
(Redirected from NRC Bulletin 79-26)
Jump to navigation Jump to search

text

Bulletin 79-26: Boron Loss From BWR Control Blades

SSINS: 6820

Accession No.:

7910250475

UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

WASHINGTON, D.C. 20555

November 20, 1979

IE Bulletin No. 79-26

BORON LOSS FROM BWR CONTROL BLADES

Description of Circumstances:

The General Electric Company (GE) has informed us of a failure mode for

control blades which can cause a loss of boron poison material. Hot cell

examinations of both foreign and domestic blades have revealed cracks near

the upper end of stainless steel tubing and loss of boron from the tubes.

The cracks and boron loss have so far been confined to locations in the

poison tubes with more than 50 percent Boron-10 (B10) local depletion.

Observed crack sizes range from a quarter to a half inch in length and from

one to two mils in width.

GE has postulated that the cracking is due to stress corrosion induced by

solidification of boron carbide (B4C) particles and swelling of the

compacted B4C as helium and lithium concentrations grow. Once primary

coolant penetrates the cladding (i.e., the cracking has progressed through

the cladding wall and the helium-lithium pressures are sufficient to open

the crack), boron is leached out of the tube at locations with more than 50

percent B10 local depletion (local depletion is considered to be twice the

average depletion). It was further found with similar cracking but with less

than 50 percent local depletion of B10, that leaching did not occur even

though primary coolant had penetrated the cladding.

The cracking and boron loss shorten the design life of the control blade.

According to the GE criteria the end of design life is reached when the

reactivity worth of the blade is reduced by 10 percent,, which corresponds

to 42 percent B10 depletion averaged over the top quarter of the control

blade. Because of the leaching mechanism, GE has reduced the allowance for

B10 depletion averaged over the top quarter of the control blade from the 42

percent value to 34 percent.

The safety significance of boron loss is its impact on shutdown capability

and scram reactivity. Although shutdown capability is demonstrated by

shutdown

.

IE Bulletin No. 79-26 November 20, 1979

Page 2 of 5

margin tests after refueling, the calculated control blade worths used in

the tests are based on the assumption that no boron loss has occurred.

Reduction in scram reactivity due to boron loss could increase the severity

of Critical Power Ratio (CPR) reductions during the plant transients and

could increase the consequences of control rod drop accidents.

Because the locations of limiting Linear Heat Generation Rate (LHGR), CPR,

and Average Planar LHGR (APLHGR) are not in controlled cells, local power

limit monitoring is not affected by boron loss.

GE has evaluated the potential effect of boron loss on shutdown capability,

CPR reduction and the consequences of control rod drop accidents. GE's

evaluation is based on the hot cell result that no boron loss is observed

until 50 percent local B10 depletion is attained. For each B4C tube,

complete loss of B4C was assumed when the calculated B10 depletion needed 50

percent locally. For any blade expected to reach a B10 depletion greater

than 34 percent during a cycle, GE assumed a B10 depletion distribution

typical of blades at the previously defined end of design life.

Based on these evaluations GE arrived at the following conclusions:

(a) Control rod drop accident consequences are not sufficiently sensitive

to small reductions in scram reactivity to be affected by boron loss

before the end of design life of the blades involved.

(b) If no more than 26 percent of the control blades have experienced a 10

percent reduction in projected worth taking boron loss into

consideration, there is a negligible effect on transient CPR reduction

and MCPR limits.

(c) If any control blades have experienced more than 10 percent reduction

in projected worth, taking boron loss into consideration, the shutdown

margin

.

IE Bulletin No. 79-26 November 20, 1979

Page 3 of 5

should be demonstrated to be at least the sum of the shutdown margin

required by Technical Specifications plus an increment sufficient to account

for the potential for boron loss.

We have examined the bases for GE's conclusions, including the hot cell

tests and the calculational assumptions. the preferred action is to replace

all blades expected to have greater than 34 percent B10 depletion averaged

over the upper one-fourth of the blade. However, based on our review we

believe the relation between boron loss and B10 depletion (i.e., the

observations to date show that boron loss does not occur until 50 percent

local of B10) is sufficiently understood to justify BWR operation on an

interim basis provided the following actions have been taken by licensees.

Action to be Taken by Licensees:

For all BWR power reactor facilities with an operating license:

1. The operating history of the reactor is to be reviewed to establish a

record of the current B10 depletion averaged over the upper one-fourth

of the blade for every control blade; the record is to be maintained on

a continuing basis. This action is required on all reactors whether

shutdown for refueling or operating.

2. Identify any control blades predicted to have greater than 34 percent

B10 depletion averaged over the upper one-fourth of the blade by the

next refueling outage.

a. Describe your plans for replacement of identified control blades.

b. Describe measures which you plan to take justifying continued

operations until the next refueling specifically addressing (1)

any blade with

.

IE Bulletin No. 79-26 November 20 , 1979

Page 4 of 5

greater than 42 percent depletion averaged over the upper

one-fourth of the blade; and (2) the condition where you find

greater than 26 percent of the control blades calculated to have

greater than 34 percent depletion averaged over the upper

one-fourth of the blade.

3. At the next cold shutdown or refueling outage, conduct shutdown margin

tests to verify that:

a. full withdrawal of any control blade from the cold xenon-free core

will not result in criticality; and

b. compliance with the shutdown margin requirement in a manner that

accommodates the boron loss phenomenon (i.e., by including a plant

specific increment in the shutdown margin that takes the potential

loss of boron from control blades identified from evaluation of

Item 1 into consideration).

4. Perform a destructive examination of the most highly exposed control

blade at the end of the next cycle and provide results of the

examination within one calendar year after removal of the blade. The

results to be reported should include:

a. Tube number or identification.

b. The evaluation of each crack in the tubing.

c. The calculated B10 depletion versus elevation for each tube.

d. The measured B10 loss versus elevation for each tube.

e. The maximum local depletion for -tubes having no cracks.

f. The maximum local depletion for tubes having no loss of boron.

Alternately, the results of a destructive examination of a blade of

similar fabrication and operational history may be provided within one

year of the

.

IE Bulletin No. 79-26 November 20, 1979

Page 5 of 5

date of issuance of this Bulletin. If the highest local B10 depletion

is less than 50 percent, this examination can be deferred until the

next refueling.

5. Submit within 45 days of the date of issuance of this Bulletin, a

written report of the findings as to Items (1) and (2). for facilities

in a refueling outage, and all other facilities at their next refueling

outage, submit the written report on Item (3) within 30 days after

plant startup following the outage. A written report on Item (4) is

requested within one year after removal of a control blade for

destructive examination.

Reports should be submitted to the Director of the appropriate NRC Regional

Office and a copy should be forwarded to the NRC Office of Inspection and

Enforcement, Division of Reactor Operations Inspection, Washington, D.C.

20555.

For all BWR facilities with a construction permit and all other power

reactor facilities with an operating license or construction permit, this

Bulletin is for information only no written response is required.

Approved by GAO B180225 (R0072); clearance expires 7/31/80. Approval was

given under a blanket clearance specifically for identified generic

problems.