IR 05000413/1980026

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-413/80-26 & 50-414/80-26 on 800915-19.No Noncompliance Noted.Major Areas Inspected:Rcpb Piping, safety-related Piping,Containment Structural Steel & Matl Storage
ML19339C097
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 10/10/1980
From: Blake J, Herdt A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19339C091 List:
References
50-413-80-26, 50-414-80-26, NUDOCS 8011170568
Download: ML19339C097 (3)


Text

,_

f ga rro d

UNITED STATES

'

'

[')

(

NUCLEAR REGULATORY COMMiST.ON

'

g a

REGION il i

'

'[

101 MARIETTA sT., N.W., sulTE 3100 0,

%

[

ATLANTA, G EORGIA 30303 Report Nos. 50-413/80-26 and 50-414/80-26 Licensee: Duke Power Company

-

422 South Church Street Charlotte, NC 28242 Facility Name: Catawba License Nos. CPPR-116 and CPPR-117 j

Inspection at Catawba site near Rock Hill, South Carolina Inspector:

_ /c e/#v

~

J.

.

Date Signed Approved by. M/

[///

/0 0

.

E'. Ilerdt, Section Chief, RC&ES Branch Ddte Signed SUMMARY Inspection on September 15-19, 1980 Areas Inspected This routine resident inspection involved 36_ inspector-hours onsite in the areas of reactor coolant pressure boundary piping (Units 1 and 2); safety related piping (Unit 1); containment structural steel (Unit 2); safety related concrete (Unit 2); and material storage (Units 1 and 2).

Results No items of noncompliance or deviations were identified.

t

.

_

_.

..

_.

._

.

.

__.

- __..

__._

.*

..

'

,

'

!

.:s

!

DETAILS

'I.

Persons Contacted ss Licensee Employeed

.

D. G. Beam, Project Manager

  • D. L. Freeze, Project Engineer

,

,

  • S. W. Dressler, Construction Engineer
  • L. R. Morgan, Senior QA Engineer L. R. Davison, Senior QC Engineer

,

J. C. Shropshire, QA Engineer Other licensee employees contacted included construction craftsman, QA technicians, security force members, and office personnel.

  • Attended exit interview.

2.

Exit Interview

'

The inspection scope and findings were summarized on September 19, 1980 with those persons indicated in Paragraph I above.

3.

Licensee Action on Previous Inspection Findings Not inspected.

4.

Unresolved Items i

Unresolved items were not identified during this inspection.

.5.

Independent Inspection

a.

The inspector conducted' general inspections of the reactor and auxiliary

~

buildings to observe activities such as housekeeping, material handling, material storage and protection of installed equipment and components.

'

These inspections were conducted on at at least a daily basis during -

the time of *he inspection with additional inspections on the evening shift.

,

b.

The inspector observed the sampling and testing of concrete during.

Pour No. 4543, for wall W206A. The tests witnessed were the concrete

'

temperature, slump, and air content tests for the _ pour. The' tests

!

were conducted at the location where the concrete was being discharged

)

from the trucks to the crane bucket.

'

.

c.

The inspector conducted an inspection of the piping material storage yard and warehouse.

L

.

l There were no items of noncompliance oor deviations in this area of the-inspection.

I

l

.

,.,y,

,

.-~

-,1

_,~

-. _ -, - - _ _.. -

- - - _ -.- -... -

-.. -

.

..

.

-2-O 6.

Reactor Coolant Pressure Boundary (RCPB) Piping The inspector observed work and work activities in the area of RCPB piping in both units. The observations included the following:

a.

(Unit 1) The inspector selected installed RCPB piping pieces No.

-

INC-44-EE and INC-46-EE to verify that they were installed in accor-dance with applicable design requirements.

The piping selected was between two primary loop hot legs and a "T" connector leading to the pressurizer spray piping connection. The installed piping was compared with the isometric drawings; design drawing Nos. CN-1491-NC017 and CN-1491-NC018; and flow diagram CN-1553-1.1 Rev.

4, Chg.

4., as well as the control valve specification No. 1205.06-03, b.

(Unit 2) The inspector observed preparations for the fit-up of the primary loop hot legs (between reactor vessel and steam generator).

Temporary support and protection of the hot leg piping pieces and the protection of the steam generator and reactor vessel nozzle weld preps were inspected.

There were no items of noncompliance or deviations in this area of the inspection.

7.

Safety Related Piping (Unit 1)

The inspector observed the weld repair activities on 8-inch diameter by

.322-inch nominal wall, containment spray piping weld joint No. CN-INS-114, repair 2.

The repair was to correct a lack-of-fusion, lack-of penetration reject requiring a grind-out completely through the weld joint and the use of the "open-butt" welding technique to complete the we]d repair.

While the inspector was observing the welder's repair activities he also observed the licensee's inspectors verifying wall thickness measurements adjacent to several containment spray piping welds using ultrasonic techniques.

There were no items of noncompliance or deviatrons in this area of the inspection.

8.

Containment Structural Steel (Unit 2)

The inspector observed welding of the following three welds in the Unit 2 containment dome:

Weld P-5-5-B (Horizontal)

Weld P-5-16-B (Horizontal)

Weld P-5-17-R (Vertical)

The fit up and preparation for welding of several other veld seams in the areas adjacent to the welds mentioned above were also observed.

There were no items of noncompliance or deviations in this area of the

' inspection.

..

.

-

-

-..

.. -..

.

.

.

.

-