UNITED STATES NUCLEAR REGU LATORY COMMISSION
REGION I
475 ALLENDALE ROAD KlNG OF PRUSSlA. PA 19406-1415 May 13, 2011 Mr. George H. Gellrich, Site Vice president Constellation Generation Group, LLC Calvert Cliffs Nuclear Power Plant. LLC 1650 Calvert Cliffs Parkway Lusby, Maryland 206574702 SUBJECT: CALVERT CLIFFS NUCLEAR POWER PLANT - NRc TEMPOMRY INSTRUCTION 2515/183 INSPECTTON REPORT 0500031 7 t2011 009 AND 0500031 8/201 1 009
Dear Mr. Gellrich:
On April 29,2011, the_U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Calvert Cliffs Nuclear Power Plant Units 1and2, using Tempbrary'lnstrriction 251sl1b3,
"Followup to the Fukushima Daiichi Nuclear Station Fuel Dahage Event." The enclosed inspection report documents the inspection results which were discussed on April 29, 201 1, with Mr. Draxton and other members of your staff.
The objective of this inspection was to promptly assess the capabilities of Calvert Cliffs to respond to extraordinary consequences similar to those that have recently occurred at the Japanese Fukushima Daiichi Nuclear Station. The results from this inspection, along with the from this inspection performed at other operating commercial nuclear piants in tne 19s.yttg United States will be used to evaluate the United StateJ nuclear industry's readiness to safely respond to similar events. These results will also help the NRC to deteimine if additional regulatory actions are warranted.
All of the potential issues and observations identified by this inspection are contained in this report. The NRC's Reactor Oversight Process willfurther evaluate any issues to determine if they are regulatory findings or violations. Any resulting findings or viol'ations will be documented by the NRC in a separate report. You are not required to resfond to this letter. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencyuide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.qov/readinq-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
, -/ ltn Wo^'"1-,^.-o A har^#r-^-
Lawrence T. Doerflein, Chief lf Engineering Branch 2 l Division of Reactor Safety Docket Nos.: 50-317, 50-318 License Nos.: DPR-53, DPR-69 Enclosure: Inspection Report 0500031 7 12011009 and 0500031 8/201 1 009 cc Mencl: Distribution via ListServ
SUMMARY OF FINDINGS
lR 0500031712011009 and 0500031812011009; 0412012011 -0412912011;Calvert Cliffs Nuclear
Power Plant, Units 1 and2; Temporary Instruction 25151183 - Followup to the Fukushima Daiichi Nuclear Station Fuel Damage Event.
This report covers an announced Temporary Instruction (Tl) inspection. The inspection was conducted by a resident inspector. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 4, dated December 2006.
INSPECTION SCOPE
The intent of the Tl is to provide a broad overview of the industry's preparedness for events that may exceed the current design basis for a plant. The focus of the Tl was on
- (1) assessing the licensee's capability to mitigate consequences from large fires or explosions on site,
- (2) assessing the licensee's capability to mitigate station blackout (SBO) conditions,
- (3) assessing the licensee's capability to mitigate internal and external flooding events accounted for by the station's design, and
- (4) assessing the thoroughness of the licensee's walkdowns and inspections of important equipment needed to mitigate fire and flood events to identify the potential that the equipment's function could be lost during seismic events possible for the site. lf necessary, a more specific followup inspection will be performed at a later date.
INSPECTION RESULTS
All of the potential issues and observations identified by this inspection are contained in this report. The NRC's Reactor Oversight Process will further evaluate any issues to determine if they are regulatory findings or violations. Any resulting findings or violations will be documented by the NRC in a separate report.
03.01 Assess the licensee's capability to mitigate conditions that result from beyond design basis events, typically bounded by security threats, committed to as part of NRC Security Order Section 8.5.b issued February 25, 2002, and severe accident management guidelines and as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.54(hh). Use Inspection Procedure (lP) 71111.05T, "Fire Protection (Triennial)," Section 02.03 and 03.03 as a guideline. lf lP 71111.05T was recently performed at the facility the inspector should review the inspection results and findings to identify any other potential areas of inspection. Particular emphasis should be placed on strategies related to the spent fuel pool. The inspection should include, but not be limited to, an assessment of any licensee actions to:
Licensee Action Describe what the licensee did to test or inspect equipment.
a. Verify through test or Licensee actions included the identification of equipment (active and passive) utilized for inspection that implementation of B.5.b actions and any additional equipment used in Severe Accident equipment is available Management Guidelines (SAMG). The scope of the equipment was defined as that equipment and functional. Active specifically designated for B.5.b or SAMG mitigation such as the portable B.5.b diesel driven equipment shall be pump, B.S.b auxiliary equipment such as adapters and hoses, and the site fire engine. The tested and passive licensee conducted walkdowns to verify the adequacy of required inventories and the functionality equipment shall be of passive equipment. Active equipment such as the B.S.b diesel driven pump, the site fire walked down and engine, and satellites radios were tested and inspected to verify readiness. 8.5.b and SAMG inspected. lt is not procedures were verified current and staged in the appropriate locations.
expected that permanently installed equipment that is tested Describe inspector actions taken to confirm equipment readiness (e.9., observed a test, reviewed under an existing test results, discussed actions, reviewed records, etc.).
regulatory testing program be retested.
The inspector assessed the licensee's capabilities by conducting a review of the licensee's This review should be walkdown activities. In addition, the inspector independently walked down and inspected major done for a reasonable B.5.b contingency response equipment staged throughout the site. The inspector reviewed sample of mitigating completed inventories and compared them with the results of field observations. In addition, the strategies/eq uipment.
inspector reviewed the test results of the 8.5.b diesel driven pump and the 8.5.b fire hoses.
Discuss general results including corrective actions by licensee.
Overall, the inspector concluded that equipment was available and functional with a few exceptions, such as some minor issues related to the proper staging of 8.5.b equipment. In addition, during a walkdown of passive fire protection equipment, the inspector identified a partially obstructed fire sprinkler associated with the Unit 2 service water pump room water curtain (issue was minor because the sprinkler on the other side of the barrier remained operable as required by station design). All equipment (active and passive) designated for 8.5.b was verified by the licensee to be in applicable procedures. The licensee identified that some dedicated equipment was not staged. The licensee issued condition reports (CR) to follow up on these deficiencies.
The associated CRs are listed in the Attachment to this report.
Describe the licensee's actions to verify that procedures are in place and can be executed (e.9.,
Licensee Action walkdowns, demonstrations, tests, etc.).
b. Verify through Licensee actions included the identification of those procedures utilized to mitigate the walkdowns or consequences of B.5.b related events and severe accidents. The licensee personnel walked demonstration that down all applicable procedures to verify the ability of the procedures to be executed.
procedures to implement the strategies associated with 8.5.b and 10 CFR 50.54(hh) are in place Describe inspector actions and the sample strategies reviewed. Assess whether procedures were and are executable.
in place and could be used as intended.
Licensees may choose not to connect or operate permanently The inspector assessed the licensee's capabilities by conducting a review of the licensee's installed equipment walkdown activities. In addition, the inspector selected several sections of a sample of the during this verification. procedures walked down by the licensee and walked those down to independently verify the licensee's conclusions. The inspector focused on mitigating strategies related to the spent fuel This review should be pool.
done for a reasonable sample of mitigating strateg ies/eq uipment.
Discuss general results including corrective actions by licensee.
The inspector concluded that procedures to implement the strategies associated with B.5.b and 10 CFR 50.54(hh) were in place and were executable. The licensee reviewed SAMG strategies and did not identify any deficiencies. Procedures used for B.S.b were reviewed by the licensee and walkdowns were performed by operators to ensure actions taken in the field in response to a 8.5.b event could be performed. Some minor enhancements were identified by the licensee and entered into the corrective action program (CAP). The associated CRs are listed in the
.
Describe the licensee's actions and conclusions regarding training and qualifications of operators Licensee Action and support staff.
Verify the training and Licensee actions included the identification of training/qualification requirements for operators for qualifications of the implementation of actions needed to mitigate B.5.b related events and for the implementation operators and the of actions needed for the SAMGS. The licensee documented that operator training requirements support staff needed to were current, and identified those operators with qualification requirements that were not current.
implement the In addition, the licensee identified the training/qualification requirements for applicable emergency procedures and work response organization (ERO) command and support staff for the implementation of actions instructions are current needed to mitigate 8.5.b related events and for the implementation of actions needed for the for activities related to SAMGS, and documented that ERO command and support staff training requirements were Security Order Section current. Gaps that were identified in the training program were entered into the CAP.
B.S.b and severe accident management guidelines as required by Describe inspector actions and the sample strategies reviewed to assess training and 10 cFR 50.54 (hh).
qualifications of operators and support staff.
The inspector assessed the licensee's training and qualification activities by conducting a review of training and qualification materials and records related to 8.5.b and SAMG event response.
Discuss general results including corrective actions by licensee.
Based on this review, the inspector concluded that training for 8.5.b and SAMGs was acceptable.
The licensee identified some minor deficiencies. This included identification that continuing training is not defined for users of SAMGs who are members of the ERO but not covered by other continuing training programs. For example, ERO positions such as Reactor Engineers and TechnicalAnalysts are not provided continuing training. However, the licensee verified that all members of the ERO were initially trained on the use of SAMGs during the qualification process.
In addition, the licensee identified three non-licensed operators who did not receive initial training on a task required for the implementation of B.S.b strategies. The licensee verified that the operators were not currently on shift and initiated actions to train the operators. The licensee issued CRs to review these deficiencies. The associated CRs are listed in the Attachment.
Describe the licensee's actions and conclusions regarding applicable agreements and contracts Licensee Action are in place.
d. Verify that any Licensee actions included the identification of all applicable contracts and agreements committed applicable agreements to be in place for the mitigation of a B.5.b related event. The licensee verified that the contracts and contracts are in and agreements were current, and documented whether or not the contracts/agreements were place and are capable of capable of meeting the mitigation strategy.
meeting the conditions needed to mitigate the consequences of these For a sample of mitigating strategies involving contracts or agreements with offsite entities, events.
describe inspector actions to confirm agreements and contracts are in place and current (e.9.,
confirm that offsite fire assistance agreement is in place and current).
This review should be done for a reasonable sample of mitigating The inspector verified that the licensee had in place current contracts and agreements with off-site agencies to provide assistance in the mitigation of the consequences of 8.5.b related events.
strateg ies/eq uipment.
Discuss general results including corrective actions by licensee.
The inspector concluded that the agreement and contracts in place were current and appropriate for the strategies evaluated.
Document the corrective action report number and briefly summarize problems noted by the Licensee Action licensee that have significant potential to prevent the success of any existing mitigating strategy.
e. Review any open l l The licensee identified minor equipment and procedural issues. The inspector reviewed the CRs corrective action l l and concluded none of the issues identified were significant and they would not preclude the documents to assess l l successful implementation of any existing mitigating strategy. Documents reviewed are listed in problems with mitigating l l the Supplemental Information.
strategy im plementation identified by the licensee. Assess the impact of the problem on the mitigating capability and the remaining capability that is not impacted.
03.02 Assess the licensee's capability to mitigate station blackout (SBO) conditions, as required by 10 CFR 50.63, "Loss of All Alternating Current Power," and station design, is functional and valid. Refer to Tl 25151120, "lnspection of lmplementation of Station Blackout Rule Multi-Plant Action ltem A-22" as a guideline. lt is not intended that Tl 25151120 be completely reinspected.
The inspection should include, but not be limited to, an assessment of any licensee actions to:
Describe the licensee's actions to verify the adequacy of equipment needed to mitigate an SBO Licensee Action event.
a. Verify through Licensee actions included the identification of equipment required for mitigation of an SBO. The walkdowns and licensee then conducted walkdowns and inspections of this equipment to ensure it was adequate inspection that al, and properly staged, tested, and maintained. Additionally, the licensee conducted a review of required materials are open CAP items for potential SBO equipment impacts.
adequate and properly staged, tested, and maintained.
Describe inspector actions to verify equipment is available and useable.
The inspector assessed the licensee's capability to mitigate SBO conditions by conducting a review of the licensee's walkdown activities. In addition, the inspector selected a sample of equipment required for mitigation of an SBO and conducted independent walkdowns of that equipment to verify that the equipment was properly aligned and staged. The sample of equipment selected by the inspector included, but was not limited to, the SBO diesel generator and its auxiliaries. Based on the licensee's activities and independent inspector walkdowns, the inspector concluded the required materials were adequate and were properly staged, tested, and maintained.
Discuss general results including corrective actions by licensee.
The inspector concluded that the licensee's reviews verified that SBO equipment was ready to respond to an SBO condition. During their reviews, the licensee identified a number of minor discrepancies including an item associated with updating the SBO coping analysis. The licensee issued CRs to review these discrepancies. The associated CRs are listed in the Attachment.
Licensee Action Describe the licensee's actions to verify the capability to mitigate an SBO event.
b. Demonstrate through Licensee actions included the identification of procedures required for response to an SBO. The walkdowns that licensee then conducted walkdowns to verify that the procedures for response to an SBO were procedures for response executable. Additionally, the licensee also conducted a review of open CAP items for potential to an SBO are impact to SBO procedures.
executable.
Describe inspector actions to assess whether procedures were in place and could be used as intended.
The inspector assessed the licensee's capabilities by conducting a review of the licensee's walkdown activities. In addition, the inspector selected several sections of a sample of the procedures walked down by the licensee and walked those down to independently verify the licensee's conclusions.
Discuss general results including corrective actions by licensee.
No significant deficiencies were identified by the licensee. The inspector identified that the acceptance criteria for the timed start of the SBO diesel was non-conservative. A timed start of the SBO is performed every 24 months to verify that the SBO diesel can be started and loaded within one hour of an SBO condition. The inspector determined that the acceptance criteria did not take into account the time for operators to complete steps in Emergency Operating Procedure (EOP)-O, "Post-Trip lmmediate Actions." In the event of an SBO, operators would perform steps in EOP-0 prior to transitioning to the EOP-7, "Station Blackout," which would be used to start and load the SBO diesel. The licensee initiated action to evaluate and correct the acceptance criteria.
The inspector determined that the issue is minor because even with the adjustment to the acceptance criteria, the licensee can still meet the SBO rule requirements to start and load the SBO diesel within one hour of an SBO condition (CR-2011-004601). Overall, the inspector concluded the SBO procedures were adequate. Documents reviewed are listed in the
.
03.03 Assess the licensee's capability to mitigate internal and external flooding events required by station design. Refer to lP 71111.01, "Adverse Weather Protection," Section 02.04, "Evaluate Readiness to Cope with External Flooding" as a guideline. The inspection should include, but not be limited to, an assessment of any licensee actions to verify through walkdowns and inspections that all required materials and equipment are adequate and properly staged. These walkdowns and inspections shall include verification that accessible doors, barriers, and penetration seals are functional.
Licensee Action Describe the licensee's actions to verify the capability to mitigate existing design basis flooding events.
Verify through Licensee actions included the identification of equipment required for mitigation of internal and walkdowns and external flooding. Equipment and material identified included rooms/walls, doors, and sump level inspection that all switches. The licensee then conducted walkdowns of this equipment to ensure it was adequate required materials are and properly staged, tested, and maintained. Where routine inspections were not performed, the adequate and properly licensee issued CRs to evaluate the deficiencies.
staged, tested, and maintained.
Describe inspector actions to verify equipment is available and useable. Assess whether procedures were in place and could be used as intended.
The inspector assessed the licensee's capabilities to mitigate flooding by conducting a review of the licensee's walkdown activities. The inspector conducted independent walkdowns of selected flood mitigation equipment to independently verify the licensee's conclusions. The inspector assessed whether procedures were in place and could be used as intended.
Discuss general results including corrective actions by licensee.
The inspector concluded that all required materials are adequate and properly staged, tested, and maintained to respond to an internal or external flood within the station's design basis. While no operability or significant concerns were identified, the licensee identified that two room level switches were not in the preventive maintenance program and other minor discrepancies. The inspector identified that the licensee's review did not include some equipment required by the station design to mitigate flooding such as the service water pump room drain system check valves that are required to be functional to prevent flooding between rooms. The licensee issued CRs to review these deficiencies, which are listed in the Attachment. The inspector reviewed the associated CRs and determined that the licensee's initial responses, including their assessment and prioritization, were appropriate.
03.04 Assess the thoroughness of the licensee's walkdowns and inspections of important equipment needed to mitigate fire and flood events to identify the potential that the equipment's function could be lost during seismic events possible for the site. Assess the licensee's development of any new mitigating strategies for identified vulnerabilities (e.9., entered it in to the corrective action program and any immediate actions taken). As a minimum, the licensee should have performed walkdowns and inspections of important equipment (permanent and temporary) such as storage tanks, plant water intake structures, and fire and flood response equipment; and developed mitigating strategies to cope with the loss of that important function. Use lP 71111.21, "Component Design Basis Inspection," Appendix 3, "Component Walkdown Considerations," as a guideline to assess the thoroughness of the licensee's walkdowns and inspections.
Describe the licensee's actions to assess the potential impact of seismic events on the availability Licensee Action of equipment used in fire and flooding mitigation strategies.
a. Verify through Licensee actions included the identification of equipment required for mitigation of fire and flood walkdowns that all events. Licensee engineedng personnel determined if the equipment was seismically qualified, or required materials are assessed whether it would be possible to evaluate the equipment as being seismically rugged.
adequate and properly Seismic vulnerabilities, including storage locations, were identified, along with mitigating strategies staged, tested, and for equipment that was not seismically qualified.
maintained.
Describe inspector actions to verify equipment is available and useable. Assess whether procedures were in place and could be used as intended.
The inspector reviewed the scope of the licensee assessments and the results of their walkdowns.
The inspector also independently walked down a sample of risk significant areas of the plant to assess beyond design basis seismic and flooding vulnerabilities, including the storage tanks, the plant intake structures, and fire and flood response equipment. The inspector determined that the licensee meets the current licensing and design bases for 8.5.b, fire protection, and flooding.
Discuss general results including corrective actions by licensee. Briefly summarize any new mitigating strategies identified by the licensee as a result of their reviews.
The inspector concluded that the licensee's reviews of fire and flooding events were comprehensive. The licensee identified that additional mitigating strategies could improve the survivability of equipment to ensure its availability following a beyond design basis event. These enhancements will focus mainly on mitigating strategies to improve the survivability of the fire suppression systems and related equipment. In particular, the licensee determined that some fire suppression equipment, such as fire piping in the turbine building, the fire water storage tanks, the SBO diesel, and the fire pump house could be vulnerable during a seismic event. The licensee issued CRs to review this issue and other minor discrepancies, which are listed in the Attachment.
Meetinqs 4OAO Exit Meetinq The inspectors presented the inspection results to Mr. Draxton and other members of licensee management at the conclusion of the inspection on April 29,2011. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
A-1
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee
- G. Gellrich, Site Vice President
- E. Larson, Plant General Manager
- C. Dolbry, Fire Protection Engineer
- M. Draxton, Training Manager
- P. Furio, Principal Engineer
- J. Gaines, General Supervisor, Operations Support
- D. Lauver, Director, Licensing
- T. Shields, Supervisor, Mechanical Maintenance
- A. Simpson, Supervisor, Licensing
- M. Stanley, Site Fire Marshal
- M. Wright, Principal Engineer
Other