ML24177A183
| ML24177A183 | |
| Person / Time | |
|---|---|
| Site: | Calvert Cliffs |
| Issue date: | 06/25/2024 |
| From: | Laura Smith Constellation Energy Generation |
| To: | Office of Nuclear Reactor Regulation, Document Control Desk |
| References | |
| Download: ML24177A183 (1) | |
Text
Constellation*
June 25, 2024 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
Subject:
Calvert Cliffs Nuclear Power Plant, Unit No. 1 Renewed Facility Operating License No. DPR-53 NRC Docket No. 50-317 lnservice Inspection Report Larry D. Smith Manager-Regulatory Assurance Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby. MD 20657 667 313 6503 Office larry.sm1th2@constellat1on com
Reference:
- 1.
American Society of Mechanical Engineers, Boiler & Pressure Vessel Code,Section XI, Article IWA-6000
- 2.
ASME Section XI, Code Case N-532-5, Repair/Replacement Activity Documentation Requirements and lnservice Inspection Summary Report Preparation and Submission.
Pursuant to References 1 and 2, please find enclosed the Owner's Activity Report (Form OAR-1) for the Calvert Cliffs Nuclear Power Plant Unit 1 Spring 2024 refueling outage.
There are no regulatory commitments contained in this letter.
Should you have questions regarding this matter, please contact Mr. Larry D. Smith at (667) 313-6503.
Respectfully,
~~~
Larry D. Smith Manager - Regulatory Assurance LDS/aj
Enclosure:
(1) 2024 Owner's Activity Report for CC1 R27 cc:
(Without Enclosure)
NRC Project Manager, Calvert Cliffs NRC Regional Administrator, Region I NRC Resident Inspector, Calvert Cliffs S. Seaman, MD-DNR
Document Control Desk June 25, 2024 Page 2 bee:
(Without Enclosure)
D. P. Helker W. E. Para P. D. Navin P. F. Moodie D. E. Baker H. M. Crockett L. D. Smith T. Cervini T. E. Lefton M. E. Weis NRC 24-021
ENCLOSURE (1) 2024 OWNER'S ACTIVITY REPORT FOR CC1R27 Calvert Cliffs Nuclear Power Plant June 25, 2024
MANDATORY APPENDIX II ASME BPVC.XI.1-2019 FORM OAR-1 OWNER'S ACTIVITY REPORT CC1R27 Report Number ___________________________________________ _
Plant Calvert Cliffs Nuclear Power Plant Unit No. __
1 ____________ Commercial service date __
M_a~y_S~,_19_7_5 ______ Refueling outage no. _C_C_1_R2_7 __
(if applicable)
Applicable inspection interval ISi = Fifth Inspection Interval/ CISI = Third Inspection Interval (1st, 2nd, 3rd. 4th, other)
Applicable inspection period Second Inspection Period (ISi and Containment ISi}
(1st. 2nd, 3rd)
Edition and Addenda of Section XI applicable to the inspection plans __,__A,,.S,.,M,..E~S"'e"'ct...,.jo,.,n.LX,,_l...,2..
0-"13...,.E,.djwlj"'onu..... _____________ _
Date and revision of inspection plans ER-CA-330-1001 Rev 6 (1/5/2024), Rev 5 (2/25/2023), Rev 4 (8/15/2022), Rev 3 (1/5/2022)
Edition and Addenda of Section XI applicable to repair/replacement activities, if different than the inspection plans _.,S.,a""m"'e'-'a"'s'-'a,,,b..,o"'v.,,e __ _
Code Cases used for inspection and evaluation:
N-639, N-716-1, N-722-1, N-733, N-729-6, N-770-5, N-823-1, N-885 (if applicable)
CERTIFICATE OF CONFORMANCE I certify that (a) the statements made in this report are correct; (b) the examinations and tests meet the Inspection Plan as required by the ASME Code,Section XI; and (c) the repair/replacement activities and evaluations supporting the completion of ___
C_C_1_R_2_7 ________ conform to the requirements of the ASME Code,Section XI.
(refueling outage number)
Signe;i'("o.\\l~'l (. k.~f\\ u~
~~ ~o.hd;;.\\ ~r~ rO'M, ti\\~,
(Own~
s Designee, Title)
CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and employed b/he Hartford Steam Boiler Inspection and Insurance Company of ____
H_a_rlf_o_rd-'-, _Co_n_n_ecti_._cu_t _______________
have inspected the items described in this Owner's Activity Report and state that, to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of the ASME Code,Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair/replacement activities and evaluations described in this report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal Date Cbf-5/7PZ '/
I (07/15) 252
ASME BPVC.Xl.1-2019 Table 1 Mandatory Appendix II Items With Flaws or Relevant Conditions That reciuired Evaluation for Continues Servce Examination Category Item and Flaw or Relevant Condition Evaluation Description and Item Number Descriotion ECP-22-000077 Rev. 2, Evaluate Degraded E-C Supplemental Exam performed of moisture Containment Liner due to missing moisture E4.11 identifed in containment inaccessible areas barrier determined the condition is acceptable for at least another 2 refueling cycles Accepted by Evaluation ECP-18-000535, OWN 15 deg Tie Rod Condition Change; Accepted Guidelines for the Inspections of the Core RVI by Existing Analysis Shroud Tie Rods, IR 04750980, 15 deg Tie Rod Condition Change Accepted by Evaluations ECP-24-000071, B-P 11A RCP Bolting degraded due to boric acid Operating for 1 Cycle with Degraded 11A RCP Studs and Boric acid Evaluation 815.10 corrosion 20240212_04749624_CAL_A2_ 118 RCP SENSING LINES 8-P Accepted by Evaluation B15.10 12A RCP Light Boric Acid residue on bolting 20240218_04751134_CAL_A3_ 12A RCP Seal Bolting 8-P 1CKVSl-128, Boric Acid Residue Accepted by Evaluation B15.10 20240218 04751117 CAL A3 1-Sl-128 B-P 1MOV614, Boric Acid Residue Evaluation: 20240218_04751106_CAL_A3_ 1-B15.10 MOV-614 8-P 1 MOV644, Boric Acid Residue Accepted by Evaluation B15.10 20240218 04751039 CAL A3 1-MOV-644 B-P Pressurizer Manway, Boric Acid Residue Evaluation:
B15.10 20240212 04749595 CAL A3 1PZVRC11 Component Support with Obseved Gap Previously identified conditions unchanged and F-A 2-CV-1005-R-17 CCNP-1-606650 Accepted by Evaluation ESR-14-00251, F1.10B 2-CV-1005-H-14 CCNP-1-606800 lnservice Inspection identified spring can 2-CV-1005-R-13, R-14 CCNPP-1-606600 support out of tolerance Previously identified conditions unchanged and F-A Spring Can with No load scale Accepted by Evaluation ESR-24-000132, F1.40 11A-2SC CCNP-1-607950 Engineeimg Evaluation is required to evaluate 11A RCP Spring CAN.
This table was reproduced using the OAR-1 Activity report from the 2019 Edition of ASME Section XI Approval to use IWA-6220, IWA-6230, and Mandatory Appendix II (2019 Edition) was documented in USN RC safety evaluation dated 04/28/2023 ADAMS Accession No. ML23114A252.
ASME BPVC.Xl.1-2019 Mandatory Appendix II Table2 Abstract oof Repair/Replacement Activities Required for Conintued Service Cose Case I Item Description I Description of Work IDate Completed IReoalr/Replacement Plan Number N/A I
N/A I
N/A I
NIA I
N/A This table was reproduced using the OAR-1 Activity report from the 2019 Edition of ASME Section XI Approval to use IWA-6220, IWA-6230, and Mandatory Appendix II (2019 Edition) was documented in USNRC safety evaluation dated 04/28/2023 ADAMS Accession No. ML23114A252.
TECHNICAL EVALUATION Page 1 of 7 ECP No.:
ECP-22-000077 Rev. No.:
0002 Reason for Evaluation:
As identified in IR 4477900, a general visual examination of the containment moisture barrier was performed, and it was identified that the pedestal moisture barriers are degraded. Moisture has been identified in the crevice created by some of the degraded seals. With the presence of moisture, corrosion and pitting/thinning of the containment liner is possible. The areas being evaluated are shown in attachment 2. The areas of most concern, and used for inputs to this evaluation, are the northeast side of pedestal 1, the south corner of pedestal 2, and the southwest corner of pedestal 6.
An evaluation will be performed to determine the acceptability of the containment liner. This evaluation is being performed in accordance with ASME Section XI Subsections IWE-2500(d), IWE-3512, and IWE-3122.3 and to meet the requirements of 10 CFR 50.55a(b)(2)(ix)(A)(2), specifically:
- i.
A description of the type and estimated extent of degradation, and the conditions that led to the degradation ii.
An evaluation of each area, and the result of the evaluation iii.
A description of necessary corrective actions Age related degradation of the containment pedestal moisture barriers has led to conditions that allow water intrusion into the inaccessible area which could come into contact with and result in corrosion of the underlying containment liner. Due to various leaks and spills that have resulted in water on the 10 elevation throughout the service life, signs of moisture were detected in the inaccessible areas in several locations that exhibit moisture barrier degradation. Subsequent removal of the degraded moisture barriers revealed the presence of water on the liner.
This evaluation is completed as a Technical Evaluation per CC-AA-309-101 step 1.1.1 item 1 as this evaluation is used for evaluating a degraded or non-conforming conditions to ensure that the condition is within the design basis of the plant.
This evaluation will consist of two parts. The first part will evaluate the loads on the containment liner to establish a reasonable lower-bound liner thickness which would provide margin to still be able to perform the liners safety related function as a leak tight membrane and fission product barrier during a LOCA or other accident scenario. The second part will be to determine a conservative acceptable corrosion rate and time frame; this will be compared to historical industry corrosion rates.
Rev 001 Addresses editorial comments.
Rev 002 Documents results of follow up inspection during the 2024 refueling outage and validates previous conclusion is still applicable.
Detailed Evaluation of Problem/Changes:
System description:
The reactor building consists of a concrete wall with a carbon steel liner on the inside. The concrete provides the structural function of the reactor building. The liner provides a safety related leak tight membrane. The liner is 1/4 carbon steel plate attached to the concrete by an angle grid system. Near the bottom of the reactor building the liner on the wall transitions smoothly to the floor. The transition is constructed from a 1/2 thick plate rolled to a 12 radius and welded to the wall and floor liners. The horizontal liner at the bottom of the reactor building is located at elevation 8-6 (Ref 1). A concrete slab has been placed on top of the liner, creating the reactor building floor at an elevation of 10 (Ref 1). The majority of the horizontal liner is placed directly on the outer prestressed, post tensioned concrete foundation of the reactor building and is thus not subject to bending or shear loads. The transition section is placed on a compressible material, a compressible material is also located above the transition between the transition liner and the concrete floor (Ref 3). The transition section of the liner would be subject to bending loads during a postulated accident scenario. The degraded areas of the moisture barrier are all located at
TECHNICAL EVALUATION Page 2 of 7 ECP No.:
ECP-22-000077 Rev. No.:
0002 equipment pedestals where the liner is sandwiched between the concrete shell of the reactor building and the concrete floor and thus has no freedom to move or be subjected to bending or shear loads as a result of LOCA pressure.
As stated in UFSAR Section 5.5 The liner plate was designed to function only as a leak tight membrane. It does not serve as a structural member to resist the tension loads from internally applied pressure which may result from any credible accident.
Structural integrity of the containment is maintained by the prestressed, post tensioned concrete.
Since the principal applied stress to the liner plate membrane is in compression and no significant applied tension stressed were expected from internal pressure loading.
Despite the fact that the liner is not credited to resist the internal pressure as a result of a LOCA, an analysis will be performed on the liner as though it was subject to the LOCA Reactor Building pressure to evaluate its capability to function as a leak tight membrane.
The primary load on the liner would be pressure as a result of a LOCA. The Reactor building is designed to withstand an internal pressure of 50 psig during this accident scenario (ref 6). The area of concern is directly below the moisture barrier, as such there is no concrete load on top of the area.
During the 2020 refueling outage an Integrated Leak Rate Test (ILRT) was performed on unit 1 containment with satisfactory results, showing that the containment liner is capable of meeting the design basis LOCA accident peak pressure requirements of 10 CFR Appendix J Option B to Part 50. Following the ILRT there was no indication of issues with the liner.
Margin for Remaining Localized Thickness Evaluation:
When the potentially corroded areas of liner are subjected to a LOCA, the minimum thickness of the liner capable of being leak-tight during a LOCA is to be evaluated. This evaluation and methodology is not intended to replace the original liner construction analysis as described in the UFSAR. The liner itself is not the pressure vessel designed to contain the 50 psi LOCA pressure as the liner is not the containment structure. This evaluation is to verify the liner has sufficient margin to perform the leak-tight function. To be conservative, and for the purposes of this evaluation, the area of possible liner degradation will be performed by treating it as a flat plate with fixed supports on all 4 sides and no support directly beneath the area of interest. Evaluated as a flat plate fixed on 4 sides is appropriate as the plate is held rigidly in place by the concrete shell and concrete floor.
Liner material is ASTM A-36 carbon steel (Ref 6); the minimum tensile strength is 58 ksi, and the minimum yield strength is 36 ksi.
The maximum allowable tensile strength for A-36 CS is 16600 psi at 300 F per ASME Section II (Ref 8).
The value of 300F was chosen as the maximum expected concrete surface temperature during a LOCA per UFSAR section 1.2.3 is 276F.
It is assumed that the area of interest of possible liner degradation is 24 long and 1 wide. The length is a conservative value based on inspections performed of the degraded moisture barriers during the 2022 refueling outage. The results of the inspection can be viewed in the CC-AA-106-1001Attachment 2 (can be viewed in FCMS). The 1 width is conservative based on the nominal moisture barrier width of 1/2 per Ref
- 3.
of illustrates the minimum acceptable liner thickness for the potentially corroded area using code allowable stress = tmin = 0.039 inch The established margin minimum thickness of the corroded area could degrade from uniform general corrosion to 0.039 before exceeding code allowable stresses from the applied forces (LOCA pressure) when treated as a flat plate with fixed supports and no support beneath. This computation method does not demonstrate the code
TECHNICAL EVALUATION Page 3 of 7 ECP No.:
ECP-22-000077 Rev. No.:
0002 allowable stresses being satisfied as section III applied other loads and applies the pressure load using defined equations different than what is provided here. As documented in Ref 10 the 1/4 liner thickness was chosen for ease of fabrication purposes only to allow the fabricator to work with a structure that will not collapse during fabrication and concrete pouring against the liner; any thickness of liner is acceptable to perform the function of a leak tight membrane.
Although no minimum line thickness is required, UFSAR Section 5.1.4.3 lists some design cases that were applied to ensure specified leak-rate under LOCA conditions are met.
a) The liner is protected against damage by missiles b) The liner plate strains are limited to allowable values that have seen shown to result in leak-tight vessels or pressure piping c) The liner plate is prevented from development of significant distortion d) All discontinuities and openings are properly anchored to accommodate the forces exerted by the restrained liner plate, and careful attention is paid to details of corners and connection to minimize the effects of discontinuities.
In response to item a the liner is protected by missiles by way of 15-18 of reinforced concrete. The area in question is the approximately 1 wide joint surrounding the periphery pedestal(s). Per Ref 3, the area of the liner being evaluated is the liner directly under the joint. Even with the degraded moisture barriers, the barrier gap is too small to allow the entry of missiles. Corrosion of the liner does not affect the protection from missiles.
In response to item b, as stated in UFSAR section 5.1.4.3 the maximum strain in the liner is less than 0.0025in/in.
Since strain is linear to stress and stress is inversely linear to cross sectional area, the strain in the possibly corroded areas would be inversely linear to the liner thickness. A strain of 0.0025in/in in a 1/4 plate would be 0.016in/in in any areas where the liner is thinned to 0.039inches. The UFSAR states that a strain of 2% (0.02in/in) would meet the requirements of ASME BPVC, although a conservative strain of 0.5% (0.005in/in) was chosen for initial design.
If the peak strain values are located in the floor liner section, the peak strain would be higher than the maximum value used during initial design but would be less than the code allowable value. The peak strains are not likely to be located in the areas of concern for possible corrosion as these areas are located next to pedestals which contain anchoring that would restrain and fix that section of the liner, highest strains would be expected and the midpoint between anchors. The strain in the liner would not compromise the integrity of the leak-tight membrane.
In response to item c, the liner plate is restrained against significant distortion by continuous angle anchors (Per the UFSAR). Additionally, the section of liner in question is restrained by the containment shell and basement floor slab and will not be able to distort significantly. The localized areas of corrosion and liner thinning will not impact the resistance to distortion.
In response to item d, the areas of concern for possible corrosion are not near any discontinuities or openings. No additional evaluation is necessary.
Additionally, UFSAR table 5-1 summarizes the loads in the containment structure during design accident conditions. The stresses for the interior surfaces of the containment floor are all negative indicating that they are compressive stresses. Under compressive stress the typical failure mode would be buckling; the liner in the floor of containment is between two layers of concrete which would preclude buckling.
Liner Remaining Thickness Analysis (Shear Analysis) for Pitted Area:
If a through hole developed in the liner from pitting, gross liner failure would not occur provided the surrounding base metal is at least 0.039 thick. The ability of the liner to resist LOCA pressure in pitted areas can be best evaluating by treating the area under the pit as a cylinder and determining what amount of force would be required to shear the cylinder away from the adjacent wall area beneath the pit.
TECHNICAL EVALUATION Page 4 of 7 ECP No.:
ECP-22-000077 Rev. No.:
0002 A-36 steel has a minimum yield stress of 36,000 psi and shear is conservatively assumed to occur at 40% of yield strength. Actual yield stresses are typically 60% of yield stress for carbon steels.
The following equation can be developed for the shear strength
[(LOCA pressure) * (Area expose to pressure)]/[cylindrical circumference
- wall thickness] = shear strength
[50*pi*r^2]/[2*pi*r*t] = 0.4*36000 This equation becomes r = (2*(shear strength)
- t)/50 Where r is the radius of a pit location and t is the local wall thickness in the pitted location.
Substituting various wall thickness results in the following corresponding pit radii. It can be seen that with a remaining wall thickness of 0.01 inches a 5.76 radius pit can be tolerated before the liner would fail from LOCA pressure. By definition, a pit would have a much smaller radius typically less than 1/8 diameter. It can thus be concluded that any expected pitting would not cause a failure of the liner. This is the same methodology used previously in ES200000318.
Thickness (inch)
Radii (inch)
.102 58.8
.05 28.8
.04 23.04
.03 17.28
.02 11.52
.01 5.76
.0002 1/8 Corrosion Rate:
It is not known when the moisture barrier became degraded. Construction of Calvert Cliffs Unit 1 and 2 was started in July 1969. Unit 1 went into commercial operation in May 1975 and Unit 2 in April 1977. Assume for 10 years the plant had no issue with regard to degradation of the moisture barrier or corrosion of the containment liner and the corrosion started in 1985 and continued until the next refueling outage in 2024 for Unit 1. This is conservative as moisture barrier degradation was first identified in the mid 1990s, IR 02253488 was the first IR that could be found related to moisture barriers or containment liner degradation, this IR is from 1996. When the moisture barrier around the transition between wall and floor liner was replaced as documented in ES200000318 (Ref 4), the liner below the top of the slab was found coated with a coal tar epoxy coating. The cold tar epoxy coating life expectancy is approximately 10-20 years (Ref 15).
Assuming the corrosion started in 1985 and continues up to the next outage: 2024 - 1985 = 39 years It is assumed that the liner, in the location the of the moisture barrier, has been submerged for the duration.
The maximum acceptable corrosion rate would be: (0.25- 0.039) / 39 years = 0.0054 = 0.0054*1000 =
5.4 mil / year This means if the corrosion started in 1985 and continued to the next refueling outage at a rate of 5.4 mils/year, we remain above the minimum thickness of 0.039 for the corroded area up to the time of the next refueling outage.
ES200000318 (Ref 4) has indicated that corrosion rate for Palisades (PWR - similar to Calvert Cliffs) in 2000 for 30 years was 1.3 mil/year. Reference 4 also indicated Point Beach Nuclear (PWR similar to Calvert Cliffs) had a corrosion rate of 2.5 mil/year with 1/8 to 3 of standing water. This calculation
TECHNICAL EVALUATION Page 5 of 7 ECP No.:
ECP-22-000077 Rev. No.:
0002 shows that the maximum allowable corrosion rate is 5.4 mil/year which is larger than the measured corrosion rates at similar plants. This means if moisture has made its way to the liner and resulted in 39 years of corrosion would not invalidate the liner water barrier function as it has enough remaining wall thickness available even upon imposing a LOCA pressure load during the next operating cycle.
Per ES200000318 the estimated corrosion rate is between 5 to 10 mils per year for carbon steel in salt water and is between 2 to 7 mils per year for carbon steel in borated water. Given the systems and fluids used in the reactor building it is unlikely that any moisture on the liner would be saltwater but would be borated water. EPRI guidebook MRP-058 (Ref 9) has published corrosion rates for carbon steels in various environments. For carbon steels submerged in ~100F water with 2000-2500 ppm boron corrosion rates are
<0.1 mils/year for deaerated water and 2-7 mils/year for aerated water. The water that goes into containment is CCW, SRW, and RCS; all of these water sources are chemically treated and would be closer to deaerated.
Chemistry testing was performed on the water found beneath the degraded moisture barriers; the testing showed a pH of 10 (See attachment 4). Carbon steel will corrode in high alkaline environments however the corrosion rate is much less than in acidic environments when the pH is less than 13. Reference 11 states that steel in a pH range of 12-13 forms a passive film which lowers the rate of corrosion to extremely smally values of less than 1micrometer per year (0.00004in/year) however this is based on clean, contaminant free water and concrete. Attachment 3 shows corrosion for carbon steel in alkaline water with a pH of 7 to 12 to be less than that of acidic water which are on the order of 2mil/year to 7 mil/year. At a pH value of about 12.5 the corrosion rate grows very quickly with increasing pH.
Thus, there is reasonable assurance that the corrosion rate of the liner would be less than 5 mils/year. If corrosion started in 1985, which is a conservative assumption, the thickness of the liner would be expected to remain above 0.039 until the next refueling outage. A liner thickness, in the suspect areas, of 0.039 or greater would not be challenged in performing its function as a leak-tight membrane.
Conclusion/Findings:
This evaluation was performed using conservative inputs, methods, and corrosion rates to compare the projected containment liner wall thickness in 2024 to the minimum required wall thickness to perform the safety related function of the liner, which is to serve as a leak tight membrane. This evaluation assumes that corrosion of the underlying containment liner began in 1985 and projected wall loss through the next outage, 2024. This evaluation concluded that the degraded containment pedestal moisture barriers would not result in degradation sufficient to preclude the containment liner from achieving its safety related function and is therefore acceptable as is. The corrosion rates discussed in Ref 4 and utilized above were assuming material submersion, therefore it is acceptable to leave the remaining standing water in contact with the liner.
As shown above, the degraded moisture barriers would not result in containment liner damage sufficient to preclude the liner from achieving its UFSAR described function of providing a leak tight membrane. Conservative inputs and methodologies were used to show that the liner would have adequate thickness to fulfill its intended leakage barrier function upon experiencing a LOCA pressure load. It has also been shown that the liner has adequate thickness to maintain this design function until the next refueling outage in 2024, when repairs to the moisture barrier and liner, if required, can be performed. During the 2020 refueling outage an Integrated Leak Rate Test (ILRT) was performed on unit 1 containment with satisfactory results, showing that the containment liner is capable of meeting its design function per 10 CFR Appendix J Option B to Part 50. Following the ILRT there was no indication of issues with the liner.
TECHNICAL EVALUATION Page 6 of 7 ECP No.:
ECP-22-000077 Rev. No.:
0002 During, inspection of the liner following the excavation of the joint(s) discussed above, standing water was observed. Although unconfirmed, the source of the water is believed to be a result of water leaks etc from inside containment. Therefore, it is assumed the liner is still performing its leak tight function.
Following inspection of the underlying containment liner, the areas of degraded moisture barrier were repaired using an approved sealant to prevent further moisture intrusion into the inaccessible areas. Attempts were made, to the extent possible, to perform examinations of the liner for evidence of flaws and degradation. Visual examinations were performed with a borescope to identify the current health of the liner but were inconclusive. The area is inaccessible and further examinations could not be performed. Successive inspections of the containment liner beneath the moisture barrier, as required by IWE-2420(b), will be performed during the next refueling outage and beyond until the condition is determined to be relatively unchanged. More extensive repairs to the moisture barrier may be performed during future outages.
Further engineering investigation using site construction photographs dating back to 1969 indicates the presence of test channels surrounding the containment pedestals. The indications in the photographs are confirmed by Ref 15.
The test channels are size 3C4.1 arranged along the perimeter of the pedestals and tied into the test channel map that runs throughout the containment liner. Therefore, there is reasonable assurance that the standing water and corrosion observed is on top of/interacting with the 3 wide test channel and not the containment liner itself. Field depth measurements support this configuration; the depth(s) observed by the craft align with the approximate depth of the test channels.
Rev 002 A follow up inspection was performed during the 2024 RFO of the three pedestals identified above. As stated above the moisture barrier is over the leak test channels and not directly over the liner. The leak test channel is encased by concrete. Any water in the moisture barrier cavity would have to corrode through the leak test channel prior to contacting the liner. The leak test channel is 3/16 thick (ref 18); at the worst-case corrosion rates above (5 mil/year) it would take 37.5 years of continuous submergence to corrode through the leak test channel prior to the possibility of liner corrosion occurring. During the 2024 inspection it was noted that there was more debris in the cavity, the debris fell into the cavity during removal of the moisture barrier to allow the inspection to occur. The amount of water in the cavity was significantly less than the 2022 inspection; there was no standing water, only moisture present. The debris made direct comparisons to 2022 challenging, however there were sections clear of debris where the bottom of the cavity was clearly visible and those areas looked similar to that during the 2022 inspection. The inspection did not reveal the presence of corrosion or corrosion products (i.e. rust, flakes, slag) that would indicate a reduction in test channel material.
A subsequent inspection, per ASME section XI IWE-2420, is required to be performed during the next inspection period, the only opportunity will be during the 2028 refueling outage. Based on the results of the 2024 inspection the condition is acceptable for continued operation until the 2028 RFO. There is no reason to believe the liner is degraded or unable to perform its function as a fission product barrier.
Attachments:
- 1. Reasonable Plate Thickness Margin and Corrosion Rate Computation
- 2. Degraded Barrier Locations
- 3. Boiler Water Treatment Preventative Maintenance ChemREADY pdf
- 4. Chemistry Analysis Results
- 5. 2024 RFO Inspection Report
References:
- 1.
61761 Rev 5, Section at Center Line Reactor Vessel
- 2.
61756SH0001 Rev 15, Containment Interior Plan EL. 10'-0" (Concrete)
- 3.
61756SH0002 Rev 1, Containment Interior Plan @ EL 10' - 0" (Concrete)
TECHNICAL EVALUATION Page 7 of 7 ECP No.:
ECP-22-000077 Rev. No.:
0002
- 4.
ES200000318 Rev 0, Engineering Evaluation of Degraded Areas of Unit 1 Containment Steel Liner
- 5.
ASME Section XI 2013, Rules for Inservice Inspection of Nuclear Power Plant Components
- 6.
UFSAR Rev 52, Update Final Safety Analysis Report
- 7.
Roarks Formulas for Stress & Strain 6th Edition
- 8.
ASME BPVC Section II Part D, 2013 edition
- 9.
EPRI Technical Report MRP-058 Rev 2, Materials Reliability Program: Boric Acid Corrosion Guidebook Managing Boric Acid Corrosion Issues at PWR Power Stations
- 10. ES199502082 rev 0, Containment Liner Thickness
- 11. SAND2010-8718, Sandia Report: Nuclear Containment Steel Liner Corrosion Workshop
- 12. 61727 Rev 2, Containment Structure Foundation Bottom Base Slab - Bottom Reinforcement
- 13. C-0016 Rev 8, Furnishing, Fabricating, Delivery and Erection of the Containment Structure Liner Plate and Accessory Steel
- 14. 2020-08 Calvert Cliffs Unit 1 2020 ILRT Report
- 15. Coal Tar Enamel & Coal Tar Epoxy Materials Analysis and Performance History - Bobbi Jo Merten 9/20/2017
- 16. NRC Information Notice No. 97-10 Liner Plate Corrosion in Concrete Containments
- 17. EPRI Technical Brief 3002021004 Deterioration and Evaluation of Steel Liners and Vessels: Operating Experience
- 18. 61744 Rev 15 Containment Liner Floor Plan & Details
- 19. IR 02253488 Provide Minimum Acceptable Containment Liner Thickness
ECP-22-000077 Page 1 of 2 Evaluate liner treating it as a rectangular flat plate, without taking credit for the concrete floor it is resting on in the area of load. The plate is supported on all 4 sides.
yield
36000 psi
a
24 in
allowable
16600 psi
b
1 in
LOCApressure
50 psi Simply supported flat plate
=
a b
24
.75
q
=
LOCApressure 50 psi
tminSimple
=
q b2 allowable 0.0475 in Flat plate with fixed edges
=
a b
24
1
.5
tminFixed
=
1 q b2 allowable 0.0388 in If we use yield stress instead of allowable stress, for plate with fixed edges
t
=
1 q b2 yield 0.0264 in
ECP-21-000077 Page 2 of 2 Evaluation of possible pitting
=
0.4 yield 14400 psi
tshear
.102 in
.05 in
.04 in
.03 in
.02 in
.01 in
.0002 in
rshear
=
2 tshear q
58.752 28.8 23.04 17.28 11.52 5.76 0.1152
in Determine maximum allowable corrosion rate. This is the corrosion rate which would result in tmin over the selected corrosion period.
yearsOfCorrosion
=
2024 1985 39
tinitial
0.250 in
allowedCorrosion
=
tinitial tminFixed 0.2112 in
allowableCorrosionRate
=
allowedCorrosion yearsOfCorrosion 0.0054 in
milsperyear
=
allowableCorrosionRate 1000 5.4152 in
2/22/22, 7:54 AM Boiler Water Treatment Preventative Maintenance l ChemREADY https://www.getchemready.com/water-facts/boiler-water-treatment-preventative-maintenance-bmps/
1/5 WATER FACTS BLOG
< View All Water Facts Articles Boiler Treatment Water Treatment Boiler Water Treatment Preventative Maintenance BMPs Why is Boiler Water Treatment Required?
No matter the type of boiler you work with, corrosion is always a risk and not everyone understands the preventative maintenance, or water treatment program, required to prevent equipment damage.
Corrosion is commonly caused by oxygen or improper pH control. This can create holes in economizers, boiler tubes or feedwater piping resulting in boiler leaks and a pricey fix (see the next section for more). There are many forms of corrosion and they are not treated equally.
It is necessary to consider the quantity of the various harmful substances that can be allowed in the boiler water without the risk of damage to the boiler. Corrosion may occur in the feed-water system as a result of low pH water and the presence of dissolved oxygen and carbon dioxide.
Corrosion can be minimized through proper design (to minimize erosion), periodic cleaning, and constant and consistent control of oxygen, pH, and dissolved solids. So when you ask yourself, why is boiler water treatment required, the best method of ensuring peak performance level is through continuous control and utilizing an automated chemical feed and monitoring system to ensure the use of high-quality feedwater (and promote passivation of metal surfaces). Deaerators are also used to heat feedwater and reduce oxygen and other dissolved gases to acceptable levels in some facilities as an additional means of preventative treatment to the automated feedwater systems and can help to reduce the amount of chemical consumed.
Learn More About ChemREADYs Boiler Water Treatment
Major monitoring parameters required for water treatment:
- 1. Dissolved solids
- 2. pH of the boiler feed water
- 3. Dissolved Oxygen in the feed water entering the boiler
- 4. Silica in boiler water
Automated feed systems provide the following benefits to any preventative maintenance water treatment program:
Little to no handling of chemicals for employees (less chance of chemical spills)
Related Articles Cooling Tower Extended Shutdown and Startup Tips What to Do If You Get a Positive Legionella Test in Your Water System?
Healthcare Facilities: How to Create a Water Treatment Plan and Why You Need One The Facts on the New 2022 Water Treatment Standard for Healthcare Facilities Six Things You Should Know About Legionella Sign Up to Receive Water Facts Emails Learn more about our Water Treatment Services and Chemical Products Contact Us CA I'm not a robot First Name
- Last Name
- Work Email
- Search
2/22/22, 7:54 AM Boiler Water Treatment Preventative Maintenance l ChemREADY https://www.getchemready.com/water-facts/boiler-water-treatment-preventative-maintenance-bmps/
2/5 No overdosing of chemicals (potentially costing more money)
No under-dosing of chemicals (allowing potential corrosion to occur)
Ability to monitor and track system consistency (both operations and cost related)
How Much Does it Cost to Maintain a Boiler System Because of a boilers vital function for any facility, their breakdown can result in safety concerns, not to mention a huge cost in order to replace or repair the system. Repair costs to boilers can be steep and can range anywhere from a few thousand dollars to over $1 million depending on size, function and accessibility. But it doesnt stop there. This price is in addition to the expense of operational down times to get the boilers repaired or replaced and up and running properly.
The cost of automating a boiler water feed system can range anywhere from a few thousand dollars up to $50K, depending on the size, demand and number of boilers any one facility may have in place.
What Are The Disadvantages Of Boiler Corrosion?
Minutes worth of imbalance in a water treatment program can cause problems, therefore, the fewer fluctuations in a water treatment program and water quality feeding the boiler the better it is for the equipment. When a system is not continuously treated and tested for accuracy, chemical imbalances can occur, allowing minutes, hours or days worth of potential corrosion and scaling to occur.
The graph below is known as theBaylis Curve. It shows the relationshipbetween pH, alkalinity, and water stability. Water above the lines isscale-forming while water below the lines is corrosive. Stable water isfound in the white area between the lines.
As you can see by the above graph, there is a fairly fine line between corrosive and not corrosive when it comes to a heated boiler water system. The pH, alkalinity, temperature of the water and various other factors will play a role in dictating whether or not there is a possibility that the water has gone corrosive and has begun to eat away at your infrastructure.
In these scenarios, we like to refer to these systems as not ifs but whens, because we know it is only a matter of WHEN the corrosion will be enough to cause a problem and not a matter of IF it will.
Keep in mind that corrosion is the only SYMPTOM and the CAUSE is inconsistent feed water.
2/22/22, 7:54 AM Boiler Water Treatment Preventative Maintenance l ChemREADY https://www.getchemready.com/water-facts/boiler-water-treatment-preventative-maintenance-bmps/
3/5 Why Is Water Quality Important?
Water contains dissolved salts, which upon evaporation of water forms scales on theheat transfersurfaces. Scales have much lower heat transfer capacity than steel: the heat transfer coefficient of the scales is 1 kcal/m/°C/hr against 15 kcal/m/°C/hr for steel. This leads to overheating and failure of the boiler tubes. Scale also reduces flow area, which increases pressure drop in boiler tubes and piping.
Low pH or dissolved oxygen in the water attacks the steel. This causes pitting or lowering the thickness of the steel tubes, leading to rupture of the boiler tubes. Contaminants like chlorides, a problem in seawater cooled power plants, also behave in a similar way.
Flow assisted corrosion occurs in the carbon steel pipes due to the continuous removal of the protective oxide layer at high flows.
Impurities carried over in the steam, causing deposits on turbine blades leading to reduced turbine efficiency, high vibrations, and blade failure. These contaminants can also cause erosion of turbine blades. Silica at higher operating pressures volatilizes and carries over to the turbine blades.
What Maintenance Does A Boiler Need?
- 1. The first step is to get the make-up water to the steam cycle as pure as possible.
- 2. The second step is to form a protective layer on the inside surface of the tubes which protects the metal surface from any further corrosion attacks.
- 3. The third step is to maintain this layer throughout the life of the plant. If the water quality goes down, this protective layer will be destroyed and corrosion starts damaging the tubes.
How Do You Maintain A Boiler System?
Even the most aggressive forms of prevention cant stop minor corrosion from eventually happening. But, with the right approach, the effects of corrosion can be minimized andextend the life of your boiler. While ChemREADY cannot reverse time and corrosion - we can certainly stop corrosion in its tracks!
2/22/22, 7:54 AM Boiler Water Treatment Preventative Maintenance l ChemREADY https://www.getchemready.com/water-facts/boiler-water-treatment-preventative-maintenance-bmps/
4/5 Heres what to do to minimize the effect of corrosion before it happens:
Use a boiler logbook. Regularly tracking the normal operation of your boiler room equipment makes it easy to spot when something critical changes.\\
Deaerator pressure or feed-tank temperature changes will give advance warning of a more expensive corrosion problem. pH changes could indicate problems with water treatment or process contamination.
Treat Feedwater.Additives can ensure that any oxygen that makes its way to the boiler in the feedwater is rapidly absorbed before it has the opportunity to form corrosive cells and blisters.
Work with a good water chemistry company (like ChemREADY!) to stay on top of your boiler water.
Implement a strict, regular service program to ensure the boiler stays clean and free of scale and corrosion problems. Train employees to ensure a complete understanding of the boiler system, how it operates and its importance If the boiler is being inspected, the root cause can be addressed early, avoiding more costly repairs.
For hydronic systems, check for leaks and monitor the quantity of make-up water.Hot water heating systems shouldnt need make-up water unless something is wrong. Call your service provider to fix the leak right away, or you may be replacing the boiler next year.
Automate boiler chemical feed and surface blowdown to maintain uniform chemical residuals and conductivity levels.
How To Treat Corrosion Damage?
Make necessary repairs to boiler and piping (such as having boiler re-tubed)
Train your crew on boiler preventative maintenance and water chemistry tests Document and report any signs of corrosion to your boiler service provider and your water chemical company so they can help prevent further damage.
Use our tips to ensure the longevity of your boiler. Need some expert advice or repair services? Contact ChemREADY todayto schedule your free consultation.
Did You Know?
What Are Different Types Of Corrosion?
Caustic Corrosion.When a concentrated caustic substance dissolves the protective magnetite layer of a boiler. This is commonly caused by boiler water pH being too high, steam blanketing (poor circulation) or local film boiling. If your boiler has a porous scale, then under deposit corrosion is also possible. Boiler water pH should be a part of yourlogbook.
Acidic Corrosion.Results from the mishandling of chemicals during acid cleaning operations or the boiler pH being run too low to passivate the carbon steel surfaces of the boiler. Boiler water pH should be a part of yourlogbook.
Pitting Corrosion.This is one of the most destructive types of corrosion, as it can be hard to predict before a leak forms. Pitting is a localized form of corrosion, in which either a local anodic point or more commonly a cathodic point, forms a small corrosion cell within the surrounding normal surface.Oxygen in feedwateris a common cause of boiler tube pitting. If your boiler is pitting, investigate the proper operation of your deaerator or feedwater tank and chemical treatment. If you have a hot water system, oxygen pitting can occur if the system has a leak and is bringing in fresh water.
Crevice Corrosion. This type of corrosion is also a localized form of corrosion and usually results from a crack in the boiler that does not get good circulation to rinse away caustic.
2/22/22, 7:54 AM Boiler Water Treatment Preventative Maintenance l ChemREADY https://www.getchemready.com/water-facts/boiler-water-treatment-preventative-maintenance-bmps/
5/5 Galvanic Corrosion. Galvanic corrosion is the degradation of one metal near a joint or juncture that occurs when two electrochemically dissimilar metals are in electrical contact in an electrolytic environment. So, dissimilar metals may need a special dielectric joint, sacrificial anode, or active cathodic protection system to prevent this phenomenon.
Learn More about ChemREADY's Boiler Water Treatment Services ChemREADY 1919 Case Parkway North Twinsburg, OH 44087 800-229-6801 F: 330-425-8202 sales@zinkan.com
© 2022 ChemREADY a Division of Zinkan Enterprises Inc.
APPLICATIONS Water Treatment Wastewater Treatment Solutions Equipment for Dewatering Wastewater PRODUCTS Chemical Products Matec Equipment About Contact Us Request Quote Privacy Policy
CONTACTUS Send reCAPTCHA I'm not a robot Privacy - Terms First Name Last Name Company State Phone Email Area of Interest Comments To Opt Out of Communications Do Not Email
CC1R26Unit1Pedestal6Aand2A SamplingandAnalysis ErnestThomas,SeniorChemist
ExecutiveSummary Samplesobtainedon2/23/2022fromPED6AandPED2AinU2containmentwasanalyzedviagamma spectroscopy.Noshortlivedisotopesweredetected.Noageestimatesweregeneratedthrough comparisonofisotopicratiosdetectedduetheinclusionofsolidmaterialinthesamples.Cs137,Co58 andCo60ratiosweredetectedinthesamplesbutwasunabletobequantifiedduetosample compositionandsize.Samplesconsistedofliquid,likelywaterandsolidmaterialresemblingconcrete.A pHanalysiswasperformedwithallsampleshavingapHof10S.U.whichisconsistentwithwaterthat hasbeenthathasbeenincontactwithconcreteforanextendedtime.Adissolvedoxygenanalysiswas attemptedbutthesamplecontainedtoomuchsedimenttobeperformed.
,,;;;:' Constellation Visual Examination of IWE Surface (VT-1)
Outage No.: _C_C_lR2_7 ____ _
Site/Unit: _C_C_N_P ___ / _1 ___ _
Procedure: ER-AA-335-014 Int/ Per:...;;_3_./-'2c;;.._ _____ _
Summary No.: CCNP-1-A400101 Procedure Rev.: _1_2 _________ _
Report No.: 1R27CISI*VT-017 Workscope: _IS_I __________ Work Order No.: C93886727-140 Page: 1 of ~1 __
Code: ASME Sect XI, 2013Ed Cat./Item: E-C/E4,ll Location: 10' Containment Drawing No.:
61756SH0001 and SH0002
==
Description:==
Containment Pedestal Moisture Barriers (Inaccessible Areas)
System ID:
_5_9 _______________________________________ _
Component ID: Containment Pedestal Moisture Barriers IA Limitations:
None Resolution:
..;;;o.;;..;.0;;...44;;...;;..."...;C=h=a;.;;..ra;;;;..ct;;.;;..;;.ers;..;;....________ Surface Condition:
As Excavated Visual Equipment/ Aids:
Boroscope, 3' Yard Stick Inspected From:
Inside Containment
~
Outside Containment D
Both D
Light Meter Mfg.: -'-N"'-/"'""'A'----------- Serial No.: _N_._/_A __________ Illumination: _Bo_ro_s_c_o.._p_e _____ _
Light Verification nmes:
Cal In ~ 1702
/ _N~/_A ____ / N/ A Cal Out ~ _1_7.;c..33.;;;__ __ _
Visual Examination:
Remote Coated Areas Wear / Erosion Corrosion / Pitting Mech. Damage/ Dents Cracks/ Tears Flaking / Peeling Blistering Discoloration Nicks / Gouges Missing Components Loose Components Coating Damage Comments
~
NRI RI
~
[J
~
[]
[]
~
Vent System or Containment Surfaces Non-Coated Areas N/A IO Leakage / Moisture
~
LJ Dislodged Seal / Gasket
~
lJ Dislodged Moist. Barrier
~
Dev. from Design Dwg
[]
lJ Bulges/ Deformation
~
[]
Missing Welds
~
Incomplete Welds
~
Arc Strikes
~
Missing Paint or Coating
~
~
NRI RI N/A IO
~
~
[J ~,
~
[]
~
~
~
~
[J
~
See supplemental video. VT-1 of excavation area at Pedestal 1, 2 and 6 using boroscope 6mm. The surface conditions were not condusive to perform VT-1 due to debris and in some cases murky water. VT-1 was inconclusive. Exam locations at# 1, 2 and 6 pedestals had various sections of water.
Results:
NRI 0 RI ~
IO [l Reference ECP 22-00077 and AR 4479900 Percent of Coverage Obtained > 90%:
_1_0_0_% _______ _
Reviewed Previous Data:
N/A
~----------
Examiner Level II Signature Palmer, Jacob T.
Examiner Alger, Richard L.
Other Level N/A Exam Date Reviewer Sig tur.
02/15/2024 Patrick Mahoney Lvl. III Exam Date 02/15/2024 Date Date I I Date z ia: i11