IR 05000317/2013001

From kanterella
Jump to navigation Jump to search
2013 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317/2013001 and 05000318/2013001) (W/Inspection Plan)
ML14058A492
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 03/04/2014
From: Daniel Schroeder
Reactor Projects Branch 1
To: George Gellrich
Constellation Energy Nuclear Group
Schroeder D
References
IR-13-001
Download: ML14058A492 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 March 4, 2014 Mr. George H. Gellrich, Site Vice President Calvert Cliffs Nuclear Power Plant Constellation Energy Nuclear Group, LLC 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 SUBJECT: ANNUAL ASSESSMENT LETTER FOR CALVERT CLIFFS NUCLEAR POWER PLANT UNITS 1 AND 2 (REPORT 05000317/2013001 AND 05000318/2013001)

Dear Mr. Gellrich:

On February 12, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Calvert Cliffs Nuclear Power Plant Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from January 1, 2013, through December 31, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Calvert Cliffs Nuclear Power Plant Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Calvert Cliffs Nuclear Power Plant Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all performance indicators demonstrated that your performance was within the nominal, expected range (i.e, green). Therefore, the NRC plans to conduct Reactor Oversight Process baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2015. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. In addition to baseline inspections, the NRC will perform Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal; Temporary Instruction (TI) 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks; TI 2515/189, Regulatory Requirements for In-service Examination and Testing of Snubbers; and IP 60855, Operation of an Independent Spent Fuel Storage Installation at Operating Plants. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence. As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year (CY) 2014 will reflect this revision to Inspection Manual Chapter (IMC) 0310. The CY 2013 end-of-cycle assessments were conducted using the IMC 0310 guidance in effect in CY 2013 (dated October 28, 2011). Cross-cutting aspects identified in 2013 using the 2013 terminology will be converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review, and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.

Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, is ongoing. This audit includes an onsite component in order for the NRC to evaluate mitigating strategies as described in licensee submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.

In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610)337-5262 with any questions you have regarding this letter.

Sincerely,

/RA/

Daniel L. Schroeder, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos: 50-317 and 50-318 License Nos: DPR-53 and DPR-69 Enclosure: Inspection Plan cc w/encl: Distribution via ListServ

ML14058A492 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP ARosebrook/AAR per NAME DSchroeder/DLS email DATE 2/27/14 3/4/14

Letter to Mr. from D. Schroeder, dated March 4, 2014 SUBJECT: ANNUAL ASSESSMENT LETTER FOR CALVERT CLIFFS NUCLEAR POWER PLANT UNITS 1 AND 2 (REPORT 05000317/2013001 AND 05000318/2013001)

Distribution w/encl: (via email)

W. Dean, RA D. Lew, DRA M. Scott, DRP E. Benner, DRP R. Lorson, DRS J. Trapp, DRS D. Schroeder, DRP A. Burritt, DRP G. Dentel, DRP F. Bower, DRP R. McKinley, DRP K. Mangan, DRP R. Powell, DRP A. Rosebrook, DRP S. Kennedy, DPR, SRI E. Torres, DRP, RI C. Fragman, DRP, AA E. Quinones, RI, OEDO RidsNrrPMCalvertCliffs Resource RidsNrrDorlLpl1-1 Resource ROPreports Resource DRS Branch Chiefs (6)

D. Screnci, PAO N. Sheehan, PAO N. McNamara, SLO D. Tifft, SLO C. ODaniell, ORA L. Pinkham, DRP K. Heater, DRS T. Haverkamp, DNMS ROPassessment Resource RidsNrrDirslpabResources

Page 1 of 2 Calvert Cliffs 02/26/2014 11:43:16 Inspection / Activity Plan Report 22 01/01/2014 - 06/30/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7111108P - U1 INSERVICE INSPECTION 1 1 02/18/2014 02/28/2014 IP 7111108P Inservice Inspection Activities - PWR 2515-189 - TI 2515/189 SNUBBERS 1 1, 2 02/24/2014 02/28/2014 IP 2515/189 Inspection to Determine Compliance of Dynamic Restraint (Snubber) Program with 10 CFR 50.55a 71003 - U1 LR COMMITMENTS PHASE 1 INSP - OUTAGE 1 1 02/24/2014 02/28/2014 IP 71003 Post-Approval Site Inspection for License Renewal 71124 - RADIATION SAFETY INSPECTION 1 1, 2 02/24/2014 02/28/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 02/24/2014 02/28/2014 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 02/24/2014 02/28/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation TI 182 - DEGRAD UNDERGROUND PIPING - PHASE 2 1 1, 2 03/10/2014 03/14/2014 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 8/25EXAM - CALVERT CLIFFS INITIAL EXAM 3 1 07/28/2014 08/01/2014 U01886 FY14-CALVERT CLIFFS INITIAL OPERATOR LICENSING EXAM 1 08/25/2014 09/04/2014 U01886 FY14-CALVERT CLIFFS INITIAL OPERATOR LICENSING EXAM 7111107T - TRIENNIAL HEAT SINK 1 1, 2 05/19/2014 05/23/2014 IP 7111107T Heat Sink Performance 71003 - U1 LR COMMITMENTS PHASE 2 INSPEC 4 1 05/19/2014 05/23/2014 IP 71003 Post-Approval Site Inspection for License Renewal 1 06/02/2014 06/06/2014 IP 71003 Post-Approval Site Inspection for License Renewal 71124 - RADIATION SAFETY RETS 1 1, 2 06/23/2014 06/27/2014 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 06/23/2014 06/27/2014 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment ISFSI - ISFSI LOADING INSPECTION 2 1, 2 08/04/2014 08/08/2014 IP 60855 Operation Of An ISFSI 1, 2 08/04/2014 08/08/2014 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants MODS - PERMANENT PLANT MODIFICATIONS 6 1, 2 09/22/2014 09/26/2014 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1, 2 10/06/2014 10/10/2014 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications EP PROGR - EP PROGRAM INSPECTION 1 1, 2 11/17/2014 11/21/2014 IP 7111402 Alert and Notification System Testing 1, 2 11/17/2014 11/21/2014 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 11/17/2014 11/21/2014 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Calvert Cliffs 02/26/2014 11:43:16 Inspection / Activity Plan Report 22 01/01/2014 - 06/30/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - RADIATION SAFETY RAD INSTRUMENTS 1 1, 2 12/01/2014 12/05/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 12/01/2014 12/05/2014 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 12/01/2014 12/05/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 12/01/2014 12/05/2014 IP 71124.04 Occupational Dose Assessment 71124 - RADIATION SAFETY INSPECTION 1 2 02/02/2015 02/06/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2 02/02/2015 02/06/2015 IP 71124.02 Occupational ALARA Planning and Controls 2 02/02/2015 02/06/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2 02/02/2015 02/06/2015 IP 71124.04 Occupational Dose Assessment 1, 2 02/02/2015 02/06/2015 IP 71151 Performance Indicator Verification 71124.08 - RADWASTE 1 1, 2 02/02/2015 02/06/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 7111108P - U2 INSERVISE INSPECTION 1 2 02/23/2015 03/06/2015 IP 7111108P Inservice Inspection Activities - PWR 71124 - RADIATION SAFETY INSPECTION 1 2 03/09/2015 03/13/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2 03/09/2015 03/13/2015 IP 71124.02 Occupational ALARA Planning and Controls 2 03/09/2015 03/13/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2 03/09/2015 03/13/2015 IP 71124.04 Occupational Dose Assessment 1, 2 03/09/2015 03/13/2015 IP 71151 Performance Indicator Verification 71124 - RADIATION SAFETY INSPECTION 1 1, 2 04/27/2015 05/01/2015 IP 71124.05 Radiation Monitoring Instrumentation 71124 - RADIATION SAFETY INSPECTION 1 1, 2 06/22/2015 06/26/2015 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure