MONTHYEARIR 05000317/20240052024-08-29029 August 2024 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2024005 and 05000318/2024005) IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) IR 05000317/20220062023-03-0101 March 2023 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2022006 and 05000318/2022006) IR 05000317/20234012023-02-16016 February 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000317/2023401 and 05000318/2023401 ML23040A0102023-02-0909 February 2023 Notification of Commercial Grade Dedication Inspection (05000317/2023012 and 05000318/2023012) and Request for Information IR 05000317/20220052022-08-31031 August 2022 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2022005 and 05000318/2022005) ML22179A2112022-06-28028 June 2022 Notification of Conduct of a Fire Protection Team Inspection IR 05000317/20210062022-03-0202 March 2022 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2021006 and 05000318/2021006) IR 05000317/20210052021-09-0101 September 2021 Updated Inspection Plan for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2021005 and 05000318/2021005) ML21187A2232021-07-29029 July 2021 Temporary Instruction 2515/194 Inspection Documentation Request IR 05000317/20200062021-03-0303 March 2021 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2020006 and 05000318/2020006) IR 05000317/20210102021-02-22022 February 2021 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000317/2021010 and 05000318/2021010 IR 05000317/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000317/2020005 and 05000318/2020005) ML20154K4602020-06-0202 June 2020 Information Request to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000317/2020011 and 05000318/2020011 IR 05000317/20200112020-06-0202 June 2020 Information Request to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000317/2020011 and 05000318/2020011 IR 05000317/20190062020-03-0303 March 2020 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2019006 and 05000318/2019006) IR 05000317/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000317/2019005 and 05000318/2019005) ML19141A1242019-05-21021 May 2019 Notification of Conduct of a Triennial Fire Protection Baseline Inspection and Request for Information IR 05000317/20180062019-03-0404 March 2019 Annual Assessment Letter for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2018006 and 05000318/2018006) ML18348A4812018-12-13013 December 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000317/2019403 and 05000318/2019403 IR 05000317/20180052018-08-28028 August 2018 Updated Inspection Plan: Inspection Report 05000317/2018005 and 05000318/2018005 IR 05000317/20170062018-02-28028 February 2018 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2017006 and 05000318/2017006, Report 05000317/2017402 and 05000318/2017402, Report 05000317/2017501 and 05000318/2017501) IR 05000317/20170052017-08-28028 August 2017 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 - Inspection Report 05000317/2017005 and 05000318/2017005 IR 05000317/20160062017-03-0101 March 2017 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2016006 and 05000318/2016006) IR 05000317/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2, Report 05000317/2016005 and 05000318/2016005 IR 05000317/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2015006 and 05000318/2015006) IR 05000317/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317/2015005 and 05000318/2015005) IR 05000317/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2, (Report 05000317/2014001 and 05000318/2014001)(w/Inspection Plan) IR 05000317/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317-14-006 and 05000318-14-006) ML14206A9932014-07-25025 July 2014 Conrete Bench-Top Autoclave Experiment Test Plan for Calvert Cliffs Nuclear Power Plant. CCNPP-CHLE-010, Revision 1 IR 05000317/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317/2013001 and 05000318/2013001) (W/Inspection Plan) ML13267A0052013-09-23023 September 2013 Requal Program Inspection 60 Day Letter IR 05000317/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317-13-006 and 05000318-13-006) IR 05000317/20120012013-03-0404 March 2013 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 & 2 (Report 05000317-12-001 and 05000318-12-001) ML12244A2032012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Calvert Cliffs Nuclear Power Plant Units 1 and 2 IR 05000317/20110012012-03-0505 March 2012 Annual Assessment Letter(Report 05000317/2011001 and 05000318/2011001) ML1124208652011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Calvert Cliffs Nuclear Power Plant Units 1 and 2 IR 05000317/20100012011-03-0404 March 2011 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant-05000317/2010001 and 05000318/2010001 ML1031402312010-11-10010 November 2010 Pre-Inspection Cover Sheet and Inspection Plan (12/6/10 - 12/10/10) ML1024402082010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Calvert Cliffs Nuclear Power Plant ML1016600082010-06-15015 June 2010 Pre-Inspection Cover Sheet and Inspection Plan (6/7 - 6/11/10) ML1006208092010-03-0303 March 2010 Annual Assessment Letter ML0924402772009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant, Dated 09/01/2009 IR 05000317/20090012009-03-0404 March 2009 IR 05000317-09-001 and 05000318-09-001, on 01/01/2009 - 12/31/2008, Calvert Cliffs Nuclear Power Plant Annual Assessment Report IR 05000317/20080012008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, Calvert Cliffs, (IR 05000317-08-001 and 05000318-08-001) ML0806100132008-03-0303 March 2008 (05000317-08-001, 05000318-08-001, )Annual Assessment Letter EOC 2007 ROP8 ML0734707242007-12-13013 December 2007 ROP8 - Change to the Inspection Plan for the Calvert Cliffs Nuclear Power Plant ML0724309302007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant IR 05000317/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Calvert Cliffs Station (IR 05000317-07-001 and 05000318-07-001) ML0624304482006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 IR 05000318/20240072024-11-0606 November 2024 Assessment Follow-Up Letter for Calvert Cliffs Nuclear Power Plant, Unit 2 (Report 05000318/2024007) ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000317/20240032024-10-22022 October 2024 Integrated Inspection Report 05000317/2024003, 05000318/2024003, and Independent Spent Fuel Storage Installation Report 07200008/2024001 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24283A0012024-10-0909 October 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000317/20245012024-10-0707 October 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000317/2024501 and 05000318/2024501 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000317/20240052024-08-29029 August 2024 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2024005 and 05000318/2024005) ML24240A1112024-08-27027 August 2024 Registration of Use of Casks to Store Spent Fuel ML24240A2462024-08-27027 August 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240022024-08-0606 August 2024 Integrated Inspection Report 05000317/2024002 and 05000318/2024002 IR 05000317/20240102024-07-31031 July 2024 Age-Related Degradation Inspection Report 05000317/2024010 and 05000318/2024010 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24198A0442024-07-16016 July 2024 Inservice Inspection Report IR 05000317/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000317/2024401 and 05000318/2024401 ML24177A1832024-06-25025 June 2024 Inservice Inspection Report RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24161A0012024-06-0909 June 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML24150A0522024-05-29029 May 2024 Operator Licensing Examination Approval ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24136A1962024-05-15015 May 2024 Independent Spent Fuel Storage Installation - Annual Radiological Environmental Operating Report IR 05000317/20240012024-05-0707 May 2024 Integrated Inspection Report 05000317/2024001 and 05000318/2024001 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000317/LER-2024-002, Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus2024-04-29029 April 2024 Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus 05000318/LER-2024-001, Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip2024-04-24024 April 2024 Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip ML24101A1942024-04-22022 April 2024 Closeout Letter for GL 2004-02 ML24114A0182024-04-18018 April 2024 Electronic Reporting of Occupational Exposure Reporting ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition 05000318/LER-2023-004-01, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-04-12012 April 2024 Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer IR 05000317/20240402024-04-11011 April 2024 95001 Supplemental Inspection Report 05000317/2024040 and Follow-Up Assessment Letter RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24082A0082024-03-22022 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML24078A1152024-03-18018 March 2024 10 CFR 50.46 Annual Report ML24059A0632024-03-15015 March 2024 Authorization and Safety Evaluation for Alternative Request ISI-05-021 (EPID L-2023-LLR-0006) - Non-Proprietary IR 05000317/20230062024-02-28028 February 2024 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, (Reports 05000317/2023006 and 05000318/2023006 ML24052A0072024-02-14014 February 2024 Core Operating Limits Report for Unit 1, Cycle 27, Revision 0 ML24040A0962024-02-0909 February 2024 Notification of Readiness for NRC 95001 Inspection ML24040A1492024-02-0909 February 2024 Response to NRC Request for Additional Information Regarding Final Response to Generic Letter 2004-02 IR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank 2024-09-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION I
2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 March 4, 2014 Mr. George H. Gellrich, Site Vice President Calvert Cliffs Nuclear Power Plant Constellation Energy Nuclear Group, LLC 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 SUBJECT: ANNUAL ASSESSMENT LETTER FOR CALVERT CLIFFS NUCLEAR POWER PLANT UNITS 1 AND 2 (REPORT 05000317/2013001 AND 05000318/2013001)
Dear Mr. Gellrich:
On February 12, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Calvert Cliffs Nuclear Power Plant Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from January 1, 2013, through December 31, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Calvert Cliffs Nuclear Power Plant Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Calvert Cliffs Nuclear Power Plant Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all performance indicators demonstrated that your performance was within the nominal, expected range (i.e, green). Therefore, the NRC plans to conduct Reactor Oversight Process baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through June 30, 2015. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. In addition to baseline inspections, the NRC will perform Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal; Temporary Instruction (TI) 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks; TI 2515/189, Regulatory Requirements for In-service Examination and Testing of Snubbers; and IP 60855, Operation of an Independent Spent Fuel Storage Installation at Operating Plants. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence. As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year (CY) 2014 will reflect this revision to Inspection Manual Chapter (IMC) 0310. The CY 2013 end-of-cycle assessments were conducted using the IMC 0310 guidance in effect in CY 2013 (dated October 28, 2011). Cross-cutting aspects identified in 2013 using the 2013 terminology will be converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review, and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, is ongoing. This audit includes an onsite component in order for the NRC to evaluate mitigating strategies as described in licensee submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610)337-5262 with any questions you have regarding this letter.
Sincerely,
/RA/
Daniel L. Schroeder, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos: 50-317 and 50-318 License Nos: DPR-53 and DPR-69 Enclosure: Inspection Plan cc w/encl: Distribution via ListServ
ML14058A492 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP ARosebrook/AAR per NAME DSchroeder/DLS email DATE 2/27/14 3/4/14
Letter to Mr. from D. Schroeder, dated March 4, 2014 SUBJECT: ANNUAL ASSESSMENT LETTER FOR CALVERT CLIFFS NUCLEAR POWER PLANT UNITS 1 AND 2 (REPORT 05000317/2013001 AND 05000318/2013001)
Distribution w/encl: (via email)
W. Dean, RA D. Lew, DRA M. Scott, DRP E. Benner, DRP R. Lorson, DRS J. Trapp, DRS D. Schroeder, DRP A. Burritt, DRP G. Dentel, DRP F. Bower, DRP R. McKinley, DRP K. Mangan, DRP R. Powell, DRP A. Rosebrook, DRP S. Kennedy, DPR, SRI E. Torres, DRP, RI C. Fragman, DRP, AA E. Quinones, RI, OEDO RidsNrrPMCalvertCliffs Resource RidsNrrDorlLpl1-1 Resource ROPreports Resource DRS Branch Chiefs (6)
D. Screnci, PAO N. Sheehan, PAO N. McNamara, SLO D. Tifft, SLO C. ODaniell, ORA L. Pinkham, DRP K. Heater, DRS T. Haverkamp, DNMS ROPassessment Resource RidsNrrDirslpabResources
Page 1 of 2 Calvert Cliffs 02/26/2014 11:43:16 Inspection / Activity Plan Report 22 01/01/2014 - 06/30/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7111108P - U1 INSERVICE INSPECTION 1 1 02/18/2014 02/28/2014 IP 7111108P Inservice Inspection Activities - PWR 2515-189 - TI 2515/189 SNUBBERS 1 1, 2 02/24/2014 02/28/2014 IP 2515/189 Inspection to Determine Compliance of Dynamic Restraint (Snubber) Program with 10 CFR 50.55a 71003 - U1 LR COMMITMENTS PHASE 1 INSP - OUTAGE 1 1 02/24/2014 02/28/2014 IP 71003 Post-Approval Site Inspection for License Renewal 71124 - RADIATION SAFETY INSPECTION 1 1, 2 02/24/2014 02/28/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 02/24/2014 02/28/2014 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 02/24/2014 02/28/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation TI 182 - DEGRAD UNDERGROUND PIPING - PHASE 2 1 1, 2 03/10/2014 03/14/2014 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 8/25EXAM - CALVERT CLIFFS INITIAL EXAM 3 1 07/28/2014 08/01/2014 U01886 FY14-CALVERT CLIFFS INITIAL OPERATOR LICENSING EXAM 1 08/25/2014 09/04/2014 U01886 FY14-CALVERT CLIFFS INITIAL OPERATOR LICENSING EXAM 7111107T - TRIENNIAL HEAT SINK 1 1, 2 05/19/2014 05/23/2014 IP 7111107T Heat Sink Performance 71003 - U1 LR COMMITMENTS PHASE 2 INSPEC 4 1 05/19/2014 05/23/2014 IP 71003 Post-Approval Site Inspection for License Renewal 1 06/02/2014 06/06/2014 IP 71003 Post-Approval Site Inspection for License Renewal 71124 - RADIATION SAFETY RETS 1 1, 2 06/23/2014 06/27/2014 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 06/23/2014 06/27/2014 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment ISFSI - ISFSI LOADING INSPECTION 2 1, 2 08/04/2014 08/08/2014 IP 60855 Operation Of An ISFSI 1, 2 08/04/2014 08/08/2014 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants MODS - PERMANENT PLANT MODIFICATIONS 6 1, 2 09/22/2014 09/26/2014 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1, 2 10/06/2014 10/10/2014 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications EP PROGR - EP PROGRAM INSPECTION 1 1, 2 11/17/2014 11/21/2014 IP 7111402 Alert and Notification System Testing 1, 2 11/17/2014 11/21/2014 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 11/17/2014 11/21/2014 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures. Enclosure
Page 2 of 2 Calvert Cliffs 02/26/2014 11:43:16 Inspection / Activity Plan Report 22 01/01/2014 - 06/30/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - RADIATION SAFETY RAD INSTRUMENTS 1 1, 2 12/01/2014 12/05/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 12/01/2014 12/05/2014 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 12/01/2014 12/05/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 12/01/2014 12/05/2014 IP 71124.04 Occupational Dose Assessment 71124 - RADIATION SAFETY INSPECTION 1 2 02/02/2015 02/06/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2 02/02/2015 02/06/2015 IP 71124.02 Occupational ALARA Planning and Controls 2 02/02/2015 02/06/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2 02/02/2015 02/06/2015 IP 71124.04 Occupational Dose Assessment 1, 2 02/02/2015 02/06/2015 IP 71151 Performance Indicator Verification 71124.08 - RADWASTE 1 1, 2 02/02/2015 02/06/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 7111108P - U2 INSERVISE INSPECTION 1 2 02/23/2015 03/06/2015 IP 7111108P Inservice Inspection Activities - PWR 71124 - RADIATION SAFETY INSPECTION 1 2 03/09/2015 03/13/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2 03/09/2015 03/13/2015 IP 71124.02 Occupational ALARA Planning and Controls 2 03/09/2015 03/13/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2 03/09/2015 03/13/2015 IP 71124.04 Occupational Dose Assessment 1, 2 03/09/2015 03/13/2015 IP 71151 Performance Indicator Verification 71124 - RADIATION SAFETY INSPECTION 1 1, 2 04/27/2015 05/01/2015 IP 71124.05 Radiation Monitoring Instrumentation 71124 - RADIATION SAFETY INSPECTION 1 1, 2 06/22/2015 06/26/2015 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures. Enclosure