IE Insp Rept 50-289/81-19 on 811013-16.Noncompliance Noted: Failure to Follow Instructions for Welding
ML20032E738
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 10/30/1981
From: Gilbert L, Randy Hall
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20032E731 List:
References
50-289-81-19, NUDOCS 8111200859
Download: ML20032E738 (4)


Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Report:

50-298/81-19 Docket:

50-298 License:

DPR-46 Licensee:

Nebraska Public Power District Post Office Box 499 Columbus, Nebraska 68601 Facility Name:

Cooper Nuclear Station Inspection at:

Cooper Nuclear Station Site, Nemaha County, Nebraska, and Nebraska Public Power District Offices, Columbus, Nebraska Inspection Conducted:

October 13-16, 1981 Inspector:

/0/.90/8/

,

L. D. Gilbirt, Reactor Inspector, Engineering and Date Materials Section Approved:

M

/0 0 f/

R. E. Hall, Acting Chief, Engineering and Materials D' ate'

Section Inspection Summary Inspection on October 13-16, 1981 (Report 50-298/81-19)

Areas Inspected:

Routine, unannounced inspection of licensee action on previously identified items and inspection of welding activities related to the Mark I Torus modifications.

The inspection involved 20 inspector-hours by one NRC inspector.

Results:

In the two areas inspected, no violations or deviations were identified in one area. One violation was identified in the other area (violation - failure to follow instructions for welding paragraph 2).

8111200859 811103'

DR ADOCK 05000

-

-

.

. _.

.

-

-

.

- -.

.-.

.

.-...._

-

-

~

-..-.

_

.

-

DETAILS 1.

Persons Contacted Nebraska Public Fower District (NPPD)

  • L. C. Lessor, Station Superintendent

P. V. Thomason, Assistant to the Station Superintendent V. Wolstenholm, QA Supervisor Chicago Bridge and Iron (CB&I)

R. Gorder, Project Manager F. Lusch, Welding /QA Superintendent W. Wagner, Corporate Welding /QA Assistant Manager Hartford Steam Boiler Inspection and Insurance Company F. Brusseau, Authorized Nuclear Inspector The NRC inspector also contacted other licensee and contractor personnel during the inspection.

  • Denotes presence at the exit interview.

2.

Licensee Action on Previous Inspection Findings (Closed) Unresolved Item (8114-04):

This item was unresolved pending review of the CB&I welding procedure qualification test report to dc vmine if a change in welding technique had been authorized.

The NRC inspector reviewed the welding procedure qualification test report, Production Test Assembly (PTA), Revision 1.

Since the PTA report is silent regarding any deviations from the contract Technical Specification requirements, the change in welding techr.ique from that required in the contract Technical Specification was not authorized.

This item is therefore upgraded to a violation.

3.

Mark I Torus Modifications a.

Review of Procedures The NRC inspector reviewed three CB&I welding procedure specifi-cations (WPSs) and supporting procedure qualification reports (PQRs)

with no discrepancies noted from the requirements of NPPD Contract I

l No. 80-28, including ASME B&PV Code, Sections III and IX, 1977 l

Edition and Summer 1977 Addendum.

The WPSs and PQRs reviewed were:

!

!

-

.

-

.

WPS-E7018 #1/05240, Revision 1, " Procedure for Shielded Metal-Arc Welding (ASME Section III NE and NF)"

PQR 4400, Revision 0, " Qualification for WPS-E7018 #1" PQR 4402, Revision 1, " Qualification for WPS-E7018 #1" WPS-E7018 #2/05240, Revision 1, " Procedure for Shielded Metal-Arc

Welding (ASME Section III NE)"

PQR 4941, Revision 0, " Qualification for WPS-E7018 #2" WPS-E705-2/E7018/05240, Revision 0, " Procedure for Gas Tungsten-Arc Welding And Shielded Metal-Arc Welding (ASME Section III NC)"

PQR 4937, Revision 0, " Qualification for WPS-E705-2/E7018" PQR 4938, Revision 0, " Qualification for WPS-E70S-2/E7018" b.

Observation of Work The NRC inspector observed activities related to the torus modifi-cations, specified in NPPD Contract No. 8-28, which included: welding of a vacuum breaker reinforcement plate, piece 12BL on Sketch SK-119; welding of a downcomer brace, piece Mark 44-4 to 44BR on Drawing 43; welding of the high pressure coolant injection (HPCI) turbine exhaust sparger pipe, weld CF on Drawing R3; final visual inspection of HPCI turbine exhaust sparger pipe, welds CA, CB, and CC on Drawing R3; and radiographic examination of sparger pipe weld CA.

In the areas of weld and inspection documentation, weld procedure compliance, welder qualification, electrode control, inspector certi-fication; no discrepancies were noted from the requirements of the following documents:

NPPD Contract No. 80-28, " Mark I Torus Modification" CB&I Nuclear Quality Assurance Manual CB&I Procedure APIN, " Alteration Procedure for Torus Modifications" CB&I Procedure WPS-E7018 #1, " Welding of Carbon Steel Supports" CB&I Procedure WPS-E705-2/E7018, " Welding of Carbon Steel Pipe" CB&I Procedure VT5X, " Visual Inspecticti" CB&I Procedure RT9X, " Radiographic Examination cf Pipe Welds" No violations or deviations were identified.

-

--

...

__

. _..

-

.

_ _ _ _

..

-

.

,.

4.

Exit Interview The NRC inspector met with Mr. L. C. Lessor, Station Superintendent, and Mr. D. DuBois, Resident Reactor Inspector, on October 16, 1981, and summarized the purpose and findings of the inspection

.