MONTHYEARDD-99-12, Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 9910281999-10-28028 October 1999 Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 991028 ML20217N8261999-10-25025 October 1999 Discusses Errata Re 991021 Filing of Northeast Nuclear Energy Co Answer to Request for Hearing & Petition to Intervene B17886, Requests Permission to Utilize Code Case N-623, Deferral of Insps of Shell-to-Flange & Head-to-Flange of Reactor Vessel,Section Xi,Div 1, for Millstone Unit 21999-10-18018 October 1999 Requests Permission to Utilize Code Case N-623, Deferral of Insps of Shell-to-Flange & Head-to-Flange of Reactor Vessel,Section Xi,Div 1, for Millstone Unit 2 B17901, Submits Statement of Personal Qualification (NRC Form 398) Along with Supporting Certification of Medical Exam by Facility Licensee (NRC from 396) in Support of License Renewal for PM Miner.Encls Withheld,Per 10CFR2.790(a)(6)1999-10-18018 October 1999 Submits Statement of Personal Qualification (NRC Form 398) Along with Supporting Certification of Medical Exam by Facility Licensee (NRC from 396) in Support of License Renewal for PM Miner.Encls Withheld,Per 10CFR2.790(a)(6) ML20217G9491999-10-14014 October 1999 Forwards Exemption from Requirements of 1-CFR50,App E, Section IV.F.2.c,re Conduct of full-participation Exercise in Sept 1999,at Plant,Units 1,2 & 3 B17900, Forwards Revised Assumptions Used in Fuel Handling Accident Analysis & Summary of Results.List of Regulatory Commitments Are Listed in Attachment 11999-10-14014 October 1999 Forwards Revised Assumptions Used in Fuel Handling Accident Analysis & Summary of Results.List of Regulatory Commitments Are Listed in Attachment 1 ML20217D9671999-10-12012 October 1999 Forwards Copy of Transcript of Public Meeting Held by NRC Staff & NNECO on 990825 at Waterford,Connecticut on Decommissioning Program for Millstone,Unit 1.Without Encl ML20217D3011999-10-0707 October 1999 Forwards Request for Addl Info Re Util 990118 Request for Amend to License NPF-49 to Allow full-core Offloads to Spent Fuel Pool During Core Offloads to Spent Fuel Pool During Core Offload Events ML20217F0031999-10-0606 October 1999 Forwards Original Petition to Intervene Being Filed on Behalf of Clients,Connecticut Coalition Against Millstone & Long Island Coalition Against Millstone,Iaw Provisions of 10CFR2.714 ML20217P1201999-10-0606 October 1999 Informs NRC of Proposed Acquisition of Parent Holding Company of Central Maine & Requests NRC Concurrence,Based on Threshold Review,That Proposed Acquisition Does Not,In Fact, Constitute Transfer Subject to 10CFR50.80 B17892, Requests Withdrawal of License Amend Application Re 24-month SG Tube Insp Surveillance Extensions,Submitted in Util 950726 & s to NRC1999-10-0505 October 1999 Requests Withdrawal of License Amend Application Re 24-month SG Tube Insp Surveillance Extensions,Submitted in Util 950726 & s to NRC ML20217B4711999-10-0404 October 1999 Informs That Staff Did Not Identify Any Safety Concerns Re Licensee Proposals to Modify Commitments Made for Action Items 4.2.1,4.2.2,4.5.1 & 4.5.2 of GL 83-28 by Providing Addl Justifications or Safety Bases for Changes ML20212L2081999-10-0101 October 1999 Responds to Recent Ltrs to President Wj Clinton,Chairman Jackson & Commissioners & Wd Travers,Expressing Concerns Re Millstone NPPs & Continued Lack of Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance ML20212L1971999-10-0101 October 1999 Responds to Recent Ltr to Chairman Jackson & Commissioners Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance to Ensure Public Health & Safety ML20212J2451999-10-0101 October 1999 Informs That Util 980807 & 990629 Responses to GL 98-01, Y2K Readiness of Computer Sys at NPPs Acceptable.Nrc Considers Subj GL to Be Closed for Units 2 &3 ML20212J9991999-10-0101 October 1999 Responds to Recent Ltr to President Clinton,H Clinton, Chairman Jackson &/Or Wd Travers Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performance of Plant to Ensure That Public Health & Safety Adequately Protected ML20212L2171999-10-0101 October 1999 Responds to Recent Ltr to President Wj Clinton,Chairman Jackson & Commissioners,Wd Travers & Ferc,Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island ML20212L1831999-10-0101 October 1999 Responds to Recent Ltr to Wd Travers Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Performance of Millstone to Ensure Adequate Protection to Public Health ML20212J3051999-10-0101 October 1999 Discusses GL 97-06 Re Degradation of SG Internals,Dtd 971230.GL Requested Each PWR Licensee to Submit Info That Will Enable NRC Staff to Verify Whether PWR SG Internals Comply & Conform to Current Licensing Basis for Facilities ML20212K1241999-10-0101 October 1999 Responds to Recent Ltrs to Chairman Jackson,Commissioners & Wd Travers,Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performace of Millstone to Ensure That Public Health & Safety,Adequately Protected ML20212J6621999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Units 2 & 3 on 990916.Identified Several Recent Instances in Which Condition Repts Were Not Initiated,Resulting in Untimely or Inadequate C/As.Historical Listing of Plant Issues Encl ML20217A9271999-09-30030 September 1999 Discusses Investigation Conducted at Millstone Nuclear Power Station by NRC OI Region I on 980319 to Determine If Contract Training Instructor Was Terminated for Raising Concerns About Quality of Training Matls ML20217B3221999-09-30030 September 1999 Refers to Investigation Rept 1-1997-035 Conducted at Millstone Nuclear Power Station by NRC Ofc of Investigation Field Ofc,Region I on 970915 to Determine Whether Former Health Physics Technician Discriminated Against B17887, Requests Exemption from Requirements of 10CFR140.11(a)(4) Which Requires Licensees to Maintain Secondary Financial Protection Beyond Primary Layer1999-09-28028 September 1999 Requests Exemption from Requirements of 10CFR140.11(a)(4) Which Requires Licensees to Maintain Secondary Financial Protection Beyond Primary Layer ML20216J1341999-09-28028 September 1999 Ltr Contract:Task Order 49, Millstone Units 2 & 3 Employee Concerns Program Insp, Under Contract NRC-03-98-021 B17883, Forwards Mnps Unit 3 ISI Summary Rept,Cycle 6, IAW ASME Section XI,IWA-62301999-09-27027 September 1999 Forwards Mnps Unit 3 ISI Summary Rept,Cycle 6, IAW ASME Section XI,IWA-6230 B17890, Provides Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-09-27027 September 1999 Provides Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal B17888, Informs That There No Longer Exists Need to Maintain Millstone Unit 2 SRO License for CA Hines,License SOP-10741-01,effective 9909151999-09-24024 September 1999 Informs That There No Longer Exists Need to Maintain Millstone Unit 2 SRO License for CA Hines,License SOP-10741-01,effective 990915 B17884, Forwards NRC Form 536, Operator Licensing Exam Data, for Mnps,Units 2 & 3,per Administrative Ltr 99-031999-09-24024 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, for Mnps,Units 2 & 3,per Administrative Ltr 99-03 ML20212F4961999-09-20020 September 1999 Forwards Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations of NRC Requirements Occurred & Being Treated as Ncvs,Consistent with App C of Enforcement Policy B17867, Requests Relief from Requirements of 10CFR50.55a(g),IAW ASME Section XI for Millstone,Unit 3.Util Requests Relief from Performing Visual Exam of Reactor Pressure Supports to Extent Required by Code for Class 1 Supports1999-09-17017 September 1999 Requests Relief from Requirements of 10CFR50.55a(g),IAW ASME Section XI for Millstone,Unit 3.Util Requests Relief from Performing Visual Exam of Reactor Pressure Supports to Extent Required by Code for Class 1 Supports B17876, Informs That Util Will Adopt Last Approved Northeast Util QA Program (Nuqap) Tr,Rev 21,dtd 990630,as Unit 1 Nuqap,Per Decision to Permanently Cease Operations at Subject Plant1999-09-16016 September 1999 Informs That Util Will Adopt Last Approved Northeast Util QA Program (Nuqap) Tr,Rev 21,dtd 990630,as Unit 1 Nuqap,Per Decision to Permanently Cease Operations at Subject Plant B17865, Provides NRC Staff with Updated Proposed Rev of FSAR Section 14.6.3, Radiological Consequences of SG Tube Failure. Updated Proposed Rev Will Replace Info Provided in Attachment 3 of Initial Submittal1999-09-16016 September 1999 Provides NRC Staff with Updated Proposed Rev of FSAR Section 14.6.3, Radiological Consequences of SG Tube Failure. Updated Proposed Rev Will Replace Info Provided in Attachment 3 of Initial Submittal B17859, Forwards up-to-date Distribution Lists for NRC Correspondence to NNECO & NUSCO.Side-bars Indicate Changes from Previous Lists Provided to NRC on 9801281999-09-15015 September 1999 Forwards up-to-date Distribution Lists for NRC Correspondence to NNECO & NUSCO.Side-bars Indicate Changes from Previous Lists Provided to NRC on 980128 B17882, Forwards NRC Forms 398 & 369 in Support of License Renewal for Bb Parrish,License SOP-10399-2.Encl Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Forms 398 & 369 in Support of License Renewal for Bb Parrish,License SOP-10399-2.Encl Withheld Per 10CFR2.790(a)(6) B17881, Forwards NRC Form 398 & NRC Form 396 for Le Olsen,License SOP-10398-2.Encl Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Form 398 & NRC Form 396 for Le Olsen,License SOP-10398-2.Encl Withheld Per 10CFR2.790(a)(6) B17880, Forwards NRC Form 398 & NRC Form 396 for Rf Martin,License SOP-10397-0.Encls Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Form 398 & NRC Form 396 for Rf Martin,License SOP-10397-0.Encls Withheld Per 10CFR2.790(a)(6) B17872, Informs of Election to Consolidate Previous Commitments Re Work Observation Program with Two New Programmatic Commitments Listed in Attachment 11999-09-14014 September 1999 Informs of Election to Consolidate Previous Commitments Re Work Observation Program with Two New Programmatic Commitments Listed in Attachment 1 B17838, Forwards Revs 34 & 35 to Physical Security Plan.Explanation of Changes Provided as Attachment 1.Without Encls1999-09-10010 September 1999 Forwards Revs 34 & 35 to Physical Security Plan.Explanation of Changes Provided as Attachment 1.Without Encls ML20212A7501999-09-10010 September 1999 Forwards Staff Requirements Memo Response,Dtd 990525,which Provides Actions NRC Plans for Continued Oversight of safety-conscious Work Environ & Employee Concerns Program ML20212A9011999-09-10010 September 1999 Forwards Environ Assessment & Finding of No Significant Impact Re Application for Exemption,Dtd 990803.Proposed Exemption Would Provide Relief from Requirement of 10CFR50 ML20212A3171999-09-10010 September 1999 Discusses Investigation Rept 1-1998-045 Conducted on 981112 to Determine If Former Senior Health Physics Technician Being Denied Employment at Millstone in Retaliation for Having Raised Safety Concerns in Past.Synopsis Encl ML20211J9291999-09-0303 September 1999 Forwards mark-ups & Retypes of Proposed Conforming License Changes Required in Connection with Transfers Being Sought in 990615 Application of Montaup Electric Co & New England Power Co for Transfer of Licenses & Ownership Interests ML20211K5171999-09-0202 September 1999 Expresses Appreciation for Support Provided for NRC Public Meeting on 990825 ML20216H0591999-09-0202 September 1999 Responds to Re Issues Submitted by Cullen on Behalf of Several Petitioners Concerning Offsite Emergency Prepardeness for Millstone Nuclear Power Station ML20211N9241999-09-0101 September 1999 Forwards Document Classification Form for Insertion Into Emergency Planning Services Department Procedures ML20211H0741999-08-30030 August 1999 Discusses GL 92-01,Rev 1, Rv Structural Integrity, Issued by NRC on 950519 & NNECO Responses for Millstone Unit 2 & 980715.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 Based on Response Review B17851, Forwards Semiannual fitness-for-duty Program Performance Data for 990101-990630 for Millstone Nuclear Power Station, Units 1,2 & 3,IAW 10CFR26.71(d)1999-08-27027 August 1999 Forwards Semiannual fitness-for-duty Program Performance Data for 990101-990630 for Millstone Nuclear Power Station, Units 1,2 & 3,IAW 10CFR26.71(d) ML20211H9971999-08-27027 August 1999 Forwards Insp Rept 50-423/99-07 on 990614-0715.Violations of NRC Requirements Occurred Re Adequacy of C/As for Organizational Changes & Being Treated as NCVs ML20211F5841999-08-23023 August 1999 Discusses Proposed Rev 21 to Northeast Utils Quality Assurance Program TR for NRC Review & Approval,Iaw 10CFR50.54 1999-09-30
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARDD-99-12, Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 9910281999-10-28028 October 1999 Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 991028 ML20217G9491999-10-14014 October 1999 Forwards Exemption from Requirements of 1-CFR50,App E, Section IV.F.2.c,re Conduct of full-participation Exercise in Sept 1999,at Plant,Units 1,2 & 3 ML20217D9671999-10-12012 October 1999 Forwards Copy of Transcript of Public Meeting Held by NRC Staff & NNECO on 990825 at Waterford,Connecticut on Decommissioning Program for Millstone,Unit 1.Without Encl ML20217D3011999-10-0707 October 1999 Forwards Request for Addl Info Re Util 990118 Request for Amend to License NPF-49 to Allow full-core Offloads to Spent Fuel Pool During Core Offloads to Spent Fuel Pool During Core Offload Events ML20217B4711999-10-0404 October 1999 Informs That Staff Did Not Identify Any Safety Concerns Re Licensee Proposals to Modify Commitments Made for Action Items 4.2.1,4.2.2,4.5.1 & 4.5.2 of GL 83-28 by Providing Addl Justifications or Safety Bases for Changes ML20212L1831999-10-0101 October 1999 Responds to Recent Ltr to Wd Travers Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Performance of Millstone to Ensure Adequate Protection to Public Health ML20212K1241999-10-0101 October 1999 Responds to Recent Ltrs to Chairman Jackson,Commissioners & Wd Travers,Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performace of Millstone to Ensure That Public Health & Safety,Adequately Protected ML20212J2451999-10-0101 October 1999 Informs That Util 980807 & 990629 Responses to GL 98-01, Y2K Readiness of Computer Sys at NPPs Acceptable.Nrc Considers Subj GL to Be Closed for Units 2 &3 ML20212J9991999-10-0101 October 1999 Responds to Recent Ltr to President Clinton,H Clinton, Chairman Jackson &/Or Wd Travers Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performance of Plant to Ensure That Public Health & Safety Adequately Protected ML20212L1971999-10-0101 October 1999 Responds to Recent Ltr to Chairman Jackson & Commissioners Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance to Ensure Public Health & Safety ML20212J3051999-10-0101 October 1999 Discusses GL 97-06 Re Degradation of SG Internals,Dtd 971230.GL Requested Each PWR Licensee to Submit Info That Will Enable NRC Staff to Verify Whether PWR SG Internals Comply & Conform to Current Licensing Basis for Facilities ML20212L2171999-10-0101 October 1999 Responds to Recent Ltr to President Wj Clinton,Chairman Jackson & Commissioners,Wd Travers & Ferc,Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island ML20212L2081999-10-0101 October 1999 Responds to Recent Ltrs to President Wj Clinton,Chairman Jackson & Commissioners & Wd Travers,Expressing Concerns Re Millstone NPPs & Continued Lack of Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance ML20217B3221999-09-30030 September 1999 Refers to Investigation Rept 1-1997-035 Conducted at Millstone Nuclear Power Station by NRC Ofc of Investigation Field Ofc,Region I on 970915 to Determine Whether Former Health Physics Technician Discriminated Against ML20217A9271999-09-30030 September 1999 Discusses Investigation Conducted at Millstone Nuclear Power Station by NRC OI Region I on 980319 to Determine If Contract Training Instructor Was Terminated for Raising Concerns About Quality of Training Matls ML20212J6621999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Units 2 & 3 on 990916.Identified Several Recent Instances in Which Condition Repts Were Not Initiated,Resulting in Untimely or Inadequate C/As.Historical Listing of Plant Issues Encl ML20216J1341999-09-28028 September 1999 Ltr Contract:Task Order 49, Millstone Units 2 & 3 Employee Concerns Program Insp, Under Contract NRC-03-98-021 ML20212F4961999-09-20020 September 1999 Forwards Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations of NRC Requirements Occurred & Being Treated as Ncvs,Consistent with App C of Enforcement Policy ML20212A9011999-09-10010 September 1999 Forwards Environ Assessment & Finding of No Significant Impact Re Application for Exemption,Dtd 990803.Proposed Exemption Would Provide Relief from Requirement of 10CFR50 ML20212A7501999-09-10010 September 1999 Forwards Staff Requirements Memo Response,Dtd 990525,which Provides Actions NRC Plans for Continued Oversight of safety-conscious Work Environ & Employee Concerns Program ML20212A3171999-09-10010 September 1999 Discusses Investigation Rept 1-1998-045 Conducted on 981112 to Determine If Former Senior Health Physics Technician Being Denied Employment at Millstone in Retaliation for Having Raised Safety Concerns in Past.Synopsis Encl ML20211K5171999-09-0202 September 1999 Expresses Appreciation for Support Provided for NRC Public Meeting on 990825 ML20211H0741999-08-30030 August 1999 Discusses GL 92-01,Rev 1, Rv Structural Integrity, Issued by NRC on 950519 & NNECO Responses for Millstone Unit 2 & 980715.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 Based on Response Review ML20211H9971999-08-27027 August 1999 Forwards Insp Rept 50-423/99-07 on 990614-0715.Violations of NRC Requirements Occurred Re Adequacy of C/As for Organizational Changes & Being Treated as NCVs ML20211F5841999-08-23023 August 1999 Discusses Proposed Rev 21 to Northeast Utils Quality Assurance Program TR for NRC Review & Approval,Iaw 10CFR50.54 ML20211D5701999-08-20020 August 1999 Informs That in May 1999,Northeast Nuclear Energy Co, Restarted Millstone Nuclear Power Station,Unit 2.Licensee Has Been Tasked Charter with Listed Specific Responsibilities ML20211C4621999-08-18018 August 1999 Discusses Rev to TS Bases Sections 3/4.5.2 & 3/4.5.3, Emergency Core Cooling Sys Subsystems ML20210S9511999-08-13013 August 1999 Responds to to Collins Expressing Concerns with Certain Terms of Proposed Merger Between New England Electric Sys & National Grid Group.Nrc Has No Authority to Interject Itself in Nees Merger with National Grid Group ML20210S9611999-08-13013 August 1999 Informs That NRC Received Encl Ltr from Pb Johnston Expressing Concern About Certain Impacts on Shareholders of New England Electric Sys with Respect to Nees Proposed Merger with Natl Grid Group ML20210N4921999-08-0909 August 1999 Ack Receipt of 990331 Electronic Transfer of $88,000 for Civil Penalty,Proposed on 990309.Corrective Actions Will Be Examined During Future Insp ML20210C0751999-07-21021 July 1999 Forwards 990721 Notice of Public Meeting Re post-shutdown Decommissioning Activities Rept ML20210A9681999-07-14014 July 1999 Responds to Re Changes to Millstone Physical Security Plan Identified as Rev 32,submitted Per Provisions of 10CFR50.54(p).No NRC Approval Is Required,Based on Util Determination That Revs Do Not Decrease Plan Effectiveness ML20209E7341999-07-12012 July 1999 Discusses Util Responses to GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity. Responses Acceptable.Info Revised in Reactor Vessel Integrity Database (Rvid) & Is Releasing as Rvid Version 2 ML20209G2921999-07-0909 July 1999 Forwards Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy DD-96-23, Informs That on 961226,NRC Issued Partial Directors Decision DD-96-23,in Response to Petition Submitted,Per 10CFR2.206,on 9508211999-07-0101 July 1999 Informs That on 961226,NRC Issued Partial Directors Decision DD-96-23,in Response to Petition Submitted,Per 10CFR2.206,on 950821 ML20196J5031999-06-30030 June 1999 Responds to 990414 Petition,Submitted Per 10CFR2.206 to Nrc. NRC Solicited Support from FEMA to Ensure That Appropriate Response to Enhancements Identified to Offsite EP in Event of Radiological Emergency at Millstone,Developed ML20196J2111999-06-30030 June 1999 Forwards SE Concluding Licensee USI A-46 Implementation Program Meets Purpose & Intent of Criteria in Generic Implementation Procedure for Seismic Verification of NPP Equipment, Rev 2 ML20196J1131999-06-29029 June 1999 Forwards Notice of Receipt & Availability for Comment of Post-Shutdown Decommissioning Activities Rept, Re .Notice Provided for Public Comments to Be Submitted within 30 Days of Notice Date ML20196G9531999-06-24024 June 1999 Discusses Changes Provided by NNECO on 990504 to TS Bases Sections 3/4.7.7 & 3/4.7.8.Returns TS Bases to NNECO to Be Inserted in TS to Ensure That NRC Staff & NNECO Have Identical TS Bases Pages ML20212H9661999-06-21021 June 1999 Confirms 990611 & 14 Telcons with M Selden,In Which Beckman & Assocs,Inc Was Advised to Stop Work Under Mod 4 to Task Order 005,under Contract NRC-03-98-021 ML20212J0751999-06-15015 June 1999 Forwards Notice of Withdrawal of Amend Request for Allowed Outage Time Extensions for Emergency Diesel Generators & Low Pressure Safety Injection Trains of Emergency Core Cooling Sys ML20212H6661999-06-15015 June 1999 Forwards RAI Re 990315 Application Request for Approval of Proposed Indirect Transfer of Seabrook Station,Unit 1 License & Proposed Indirect Transfer of Millstone,Unit 3 License to Extent Held by Nepco ML20195J3121999-06-15015 June 1999 Expresses Concern Re M Casey 990523 Column, Gaffes Turn Into Cash at NRC, & Disagrees with New London Day Earlier Editorial Criticism of NRC Investigations of Harassment & Intimidation of Employees at Millstone NPPs ML20195K0601999-06-15015 June 1999 Forwards Request for Addl Info Re fire-related IPEEE Analysis,Per GL 88-20 ML20195J0321999-06-10010 June 1999 Expresses Appreciation for Serving as Moderator for 990209 Public Meeting at Waterword,Ct.Questions Raised by Interested Members of Public & NRC Responses Encl.Staff Reply to Blanch Also Encl ML20195J4761999-06-10010 June 1999 Forwards Insp Rept 50-336/98-219 on 981214-18,990126-29 0208-19 & 0301-05.Four Violations Identified & Being Treated as Noncited Violations ML20196J5091999-06-0404 June 1999 Requests Assistance to Review Petition Submitted Under 10CFR2.206 of NRC Rules.Petition Concerns EP Issues for Millstone Nuclear Power Station ML20207G1121999-06-0303 June 1999 Forwards Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Closure of 15 Significant Items List (SIL) Issues at Unit 2 Signifies Completion of Insp for Entire Unit 2 SIL ML20207G6271999-06-0303 June 1999 Forwards Amends 105,235 & 171 to Licenses DPR-21,DPR-65 & NPF-49,respectively & Safety Evaluation.Amends Replace Specific Titles in Section 6.0 of TSs for All Three Millstone Units with Generic Titles ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) 1999-09-30
[Table view] |
Text
June 11, 1997
SUBJECT:
NOTICE OF VIOLATION AND PROPOSED IMPOSITION OF CIVIL PENALTY -
$55,000 (NRC Inspection Reports No. 50-245/97-03; 50-336/97-03; 50-423/97-03)
Dear Mr. Kenyon:
This letter refers to the NRC security inspection conducted at the Millstone facilities on February 3-7, 1997. During the inspection, three apparent violations of NRC requirements were identified, as noted in the inspection report sent to you on March 26, 1997. On April 7, 1997, a predecisional enforcement conference was conducted with Mr. Frank Rothen and other members of your staff to discuss the apparent violations identified during the i
inspection, their causes, and your corrective actions.
Based on our review of the inspection findings, and information provided during the conference, two violations are being cited and are described in Section I of the enclosed Notice of Violation and Proposed Imposition of Civil Penalty (Notice). The violations involve (1) multiple examples of the failure to control Safeguards Information (SGI) at your facility; and (2) multiple examples of failure to control vehicles in the protected area (keys were left in the ignition in unlocked / unattended vehicles).
,
Although these violations were identified by your staff, the NRC is particularly concerned with the frequency with which these two violations have occurred, as well as the fact that the violations are repetitive of violations previously cited by the NRC based on inspections conducted in October 1994 and May 1996, respectively.
For example, since February 1995 until the time of the February 1997 inspection, your staff identified 37 incidents where keys were found in unattended vehicles in the protected area, contrary to your security plan that requires vehicles to be immobilized with keys controlled (ignition locked) when not in use.
In addition, since May 1996, your staff identified seven incidents where material containing Safeguards Information was not controlled. Although these findings clearly indicated an adverse performance trend regarding adherence to security requirements, your management and staff were not effective in ensuring that prompt and aggressive corrective actions were taken to correct these problems. After each occurrence, corrective actions taken appeared to focus solely on the specific occurrence, rather than the broader problem indicated by the number of incidents which have occurred.
I t
9706120296 970611 I
PDR ADOCK 05000245 ffff f ll ff
__
a
.
Northeast Nuclear-2-
,
Energy Company
These violations represent a significant lack of attention to security responsibilities by not only your security staff and supervision, but also, and more importantly, by those site employees and contractor employees who did not follow security requirements. At the enforcement conference, your staff acknowledged that site personnel did not consistently assume appropriate individual responsibility of security requirements, and that corrective actions for previous occurrences of the same violations have been ineffective.
Given the repetitive and continuing nature of these two violations, they represent a significant regulatory concern with respect to degradation of the security program at the facility. Therefore, the violations have been categorized in the aggregate as a Severity Level III problem in accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions" (Enforcement Policy), NUREG-1600.
In accordance with the Enforcement Policy, a base civil penalty in the amount of $55,000 is considered for a Severity Level III problem or violation.
Base civil penalties for Severity Level III problems were increased from $50,000 to
$55,000 effective November 12, 1996 (61CFR 53553, October 11,1996). The higher base penalty is warranted in this case since a substantial number of the noncompliances occurred after November 12, 1996.
Your facilities have been the subject of escalated enforcement actions within the last 2 years, for example, a $100,000 civil penalty was issued on June 4,1996, for a Severity Level III violation involving the discrimination against an individual who engaged in protected activities (Reference: EA 96-059). Given this enforcement history, in accordance with Section VI.B.2 of the Enforcement Policy, the NRC considered whether credit was warranted for Identification and Corrective Actfon in accordance with the civil penalty assessment process in Section VI.B.2 of the Enforcement Policy. Credit is warranted for Identification because the violations involving control of safeguards informatior and control of vehicles were identified by your staff. The NRC also considered your corrective actions as described at the enforcement conference.
These actions included, but were not limited to: (1) clearly defining expectations at the officer level regarding control of vehicles and communicating those expectations to the entire Millstone site; (2) denial of unescorted access to individuals who violate security requirements, with the requirement that prior to reinstatement, the violator's supervisor must certify that the offender understands the rules and will comply in the future; (3) posting of signs in vehicles indicating that if an individual leaves keys unattended in an unlocked vehicle, the individual will lose unescorted access; (4) incorporation of vehicle control into plant access training; (5)
publishing and discussing expectations for control of SGI at shift briefings; and (6) reduction in SGI repositories not located in security spaces with the assignment of a responsible custodian for each repository. Although these actions appear comprehensive, the NRC concluded credit is not warranted for Corrective Action because the corrective actions taken for the violations involving control of safeguards information and control of vehicles were not prompt.
In addition, corrective actions taken for earlier occurrences were not fully effective as demonstrated by the fact that multiple, subsequent violations continued to recur over an extended period of time.
,
.
.
Northeast Nuclear-3-
Energy Company
-
Therefore, to emphasize the importance of both adherence to security plan requirements and prompt and effective correction of violations, I have been
.
authorized, after consultation with the Director, Office of Enforcement, to
'
,
propose a civil penalty of $55,000 for this Severity Level III problem.
t In addition to the Severity Level III problem,Section II of the Notice describes the failure to perform a hand search of an individual granted access to the protected area after the individual caused an alarm while being checked with a hand held metal detector. This violation has been classified at Severity Level IV, in accordance with the Enforcement Policy.
You are required to respond to this letter and should follow the instructions specified in the enclosed Notice when preparing your response. The NRC will use your response, in part, to determine whether further enforcement action is
-
necessary to ensure compliance with regulatory requirements.
<
In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter, its enclosure, and your response will be placed in the NRC Public Document Room (PDR).
,
Sincerely,
!
J/L\\ m
'
dilliam D. T avers, Director Special Projects Office i
Office of Nuclear Reactor Regulation i
Docket Nos. 50-245, 50-336, 50-423 License Nos. DPR-21, DPR-65, NPF-49 Enclosure:
Notice of Violation and Proposed Imposition of Civil Penalty
,
l cc w/ encl:
See Next Page
s
1
4
_
_
-
.
.
Northeast Nuclear-4-Energy Company
l cc w/ encl:
N. Carns, Senior Vice President and Chief Nuclear Officer i
P. Loftus, Director - Regulatory Affairs for Millstone Station M. Brothers, Vice President - Millstone, Unit 3 J. McElwain, Unit 1 Recovery Officer i
M. Bowling, Jr., Unit 2 Recovery Officer D. Goebel, Vice President, Nuclear Oversight J. Thayer, Recovery Officer, Nuclear Engineering and Support P. Hinnenkamp, Director, Unit Operations F. Rothen, Vice President, Work Services
{
J. Stankiewicz, Training Recovery Manager i
R. Johannes, Director - Nuclear Training L. Cuoco, Esquire J. Egan, Esquire V. Juliano, Waterford Library Department of Public Utility Control S. Comley, We The People
State of Connecticut SLO Designee D. Katz, Citizens Awareness Network (CAN)
R. Bassilakis, CAN
'
J. Block, Attorney, CAN S. Luxton, Citizens Regulatory Commission (CRC)
Representative T. Concannon E. Woollacott, Co-Chairman, NEAC I
-,