ML20148N296

From kanterella
Jump to navigation Jump to search
Responds to Violations Noted in Insp Rept 50-293/97-02. Corrective Actions:Will Revise Specification E-15A & Regulating Transformers Documentation to Reflect PDC 97-11 & Will Update Design Guide to Enhance Equipment Codes & Stds
ML20148N296
Person / Time
Site: Pilgrim
Issue date: 06/20/1997
From: Boulette E
BOSTON EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
50-293-97-02, 50-293-97-2, BECO-2.97.065, NUDOCS 9706260319
Download: ML20148N296 (7)


Text

-. - . .-. - -=._. .._. .- . . ..~ ~. . .

i .

G Boston Edison i Pilgrim Nuclear Power staton i Rocky Hill Road Plyrnouth, Massachusetts 02360 1

E. T. Boulette, PhD Senior vice President - Nuclear June 20,1997 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 License DPR-35 Docket 50-293

SUBJECT:

REPLY TO NOTICE OF VIOLATION (REFERENCE NRC INSPECTION REPORT NO. 50-293/97-02) l Enclosed is Boston Edison Company's reply to the Notice of Violation contained in the subject inspection report.

, The following commitments are made in this letter:

. Specification E-15A and regulating transformers documentation (vendor manual V-1184) will i- be revised to reflect PDC 97-11 as part of the routine modification close-out process by

] August 31,1997, 1

The electrical engineering department will update the design guide to enhance the Equipment Codes and Standards section by June 30,1997.

4 i . The specification procedure will be revised to require identification of all new component i automatic functions by July 31,1997.

1

. The human performance aspects of the cause of the deficiency in specification E15A which  !

were addressed via the corrective action process (PR 97.9245) will be discussed in the j electrical engineering department training by August 31,1997.

. The vendor interface issues associated with this violation will be addressed in our

. supplemental response due by July 11,1997.

The NRC requested inspection report (IR 97-02) that Boston Edison staff specifically address actions planned to strengthen the oversight and interface of vendor activities. This response will be included in a supplement to this violation response by July 11,1997.

4 9706260319 970620' ~

PDR ADOCK 05000293 G PDR lllfllllfllfllflflffllffllflf

          • ll

r l '

l Please do not hesitate to contact me if there are any questions regarding th enclosed reply.

. T. Boulette, PhD KRD/dmc/vio97-02 Enclosure 1: Reply to Notice of Violation cc: Mr. Alan Wang, Project Manager Project Directorate 13 Office of Nuclear Reactor Mail Stop: OWF 1482 U. S. Nuclear Regulatory Commission 1 White Flint North 11555 Rockville Pike Rockville, MD 20852 U. S. Nuclear Regulatory Commission Region 475 Allendale Road King of Prussia, PA 19406 Senior NRC Resident inspector Pilgrim Nuclear Power Station l

2

. . - _ - . -- _ .-.-.- =. .- - - . - . - - - . - . . - - - - ~ . . - . . - - . . _

( .

(,

l' l

Boston Edison Docket No. 50-293 l i; _ Pilgrim License No. DPR-35

s. -

l Enclosure 1

'I Reply to Notice of Violation I 1

i

"As a result of an inspection conue d ct d from March 3 to April 28,1997, the following violation of l l NRC requirements was identified (VIO 50-293/97-02-01). In accordance with the NRC _ l j Enforcement Policy (60 FR 34381; June 30,1995), the violation is described below:  ;

- Violation:

1 10CFR Part 50, Appendix B, Criterion Ill, Design Control, requires that applicable regulatory l - requirements and design basis for those structures, systems, and components to which this .

appendix applies are correctly translated into specifications, drawings, procedures, and 1 instructions.

1. Contrary to the abovef the function of the 480/120 voltage regulating transformers was not l 1 correctly translated into specifications which became evident during a significant storm on April 1,1997, when the running SSW and RBCCW pumps tripped and isolations of the 1 4

RWCU system and RBIS occurred with the resultant start of the SBGT system. The i transformers were procured and installed by engineering specification E-51 A and PDC 91-51A and automatically turned off due to an unknown vendor installed undervoltage design feature.

l

2. Contrary to the above, the function of MO-1301-53 (RCIC system full flow test valve) was not correctly translated into drawings when the valve functioned in the seal-in close mode i

on April 17,1997, causing an inadvertent overspeed/ trip and increased unavailability time

! of the RCIC system turbine. Electrical design drawing M1G27 did not reflect an earlier j modification made at an indeterminate date which converted MO-1301-53 to jog open/ jog i- close.

The above failures adversely affected the performance of safety related equipment and ,

unnecessarily challenged the operators.

This is a Severity Level IV violation (Supplement IV)."

i 1

3 4

,-p*' 9 g 4g4,-- w ,w-y - - - ,- - , , , , * - - g -,w,- -

REASON FOR THE VIOLATION Example No. ' - no0/120 Voltaae Reaulatina Transformers The reason for the violation cited as example No.1 was that purchase specification (E15A) did not specify operation during voltage transients. A contributing cause was a vendor-installed undervoltage trip which came with the delivered transformers without the knowledge of Boston Edison. This feature in the delivered product was not captured in the equipment documentation.

Discussion-The regulating transformers were installed in 1992 via design modifications per PDC 91-59A and PDC 91-59B and associated safety evaluation nos. 2664,2685, and 2706. Transformers X55, X5E X57, and X58 were designed to regulate input voltages of 480 volts +/- 20% (i.e.,576-384 voitd) and provide regulated output voltages of 120VAC +/- 4%. Each regulating transformer ccm eins a programmable microprocessor control unit (MCU) that senses input voltage and selects the proper voltage tap to provide the regulated 120 volt output voltage. The MCUs were programmed by the manufacturer to shut down the regulating transformer if input voltage was outside the transformer's input voltage range of 576 - 384 volts. The input voltage range of +/-

20% was based on the worst case voltage dips that would be seen c' Abo design basis accidents concurrent with a loss of offsite power. Transient voltages below 384v'AC due to 345KV grid disturbances were not considered.

During a severe storm on April 1,1997, safeguard panels Y3 and Y4 lost power due to the automatic shut down of voltage regulating transformers X55 and X56. After each shut down, the operators took manual action to open and reclose the input breakers to the transformers that

, resst the transfornc and restored power to Y3 and Y4. At the same time, regulating l transformer X58, which powers the "B" train of the post accident sampling system (PASS), shut down and was reset in the same fashion. Transformer X57 was tagged out of service for maintenance during the storm.

The transforme :hui Cown due to a transient undervoltage condition. This condition was

. identified when a revir,w of the 480VAC voltage level showed a voltage drop to approximately l 350VAC during the storm.

l I The design documentation (vendor manual, etc.) provided by the manufacturer and supplier of the transformers did not identif; an automatic shut down feature if input voltage was less than 380 volts. The lack of the identification of the feature is significant because an automatic shut down due to input voltages from zero volts to 384 volts would require a manual reset of the transformer versus a designed automatic reset if input voltage was zero volts. Specification E15A did not request that the transformers continue operation er prohibit shutdown during voltages outside the design regulation range.

The cause for the automatic shut downs of the regulating transformers was a deficiency in

( specification E15A which did not address the effects of 480 voit transients of less thri 384 volts.

l The apparent cause of the deficiency was an unintentional cognitive error made by tne utility electrical engineer who prepared the specification. Nuclear engineering procedure 3.08,

" Specifications and Reports", governs the preparation and issuance of specifications. There were no unusual electrical engineering work location characteristics that contributed to the error. The 4

1 -_____ - -_-_____ - _________ _ ______- _ _ _ _ _ _ _ _ -

1 l

j human performance aspects of the cause of the deficiency in specification E15A was addressed i the corrective action process (PR 97.9245) which concluded that the problem report would be discussed in the electrical engineering department training.

Example No.2 - MO-1301-53 wirina discrepancy The reason for the v!alation cited as example No. 2 was lack of design control at a previous time in plant operation due to elementary and connection drawings not reflecting a change that made MO-1301-53 a jog close valve.

Discussion:

During RCIC testing on April 17,1997, MO-1301-53 operated as a seal-in close valve instead of t operating as a jog valve in both open/close directions. A new bucket for MO-1301-53 was installed under PDC 93-38 during RFO #11. The new bucket was wired in accordance with the existing connection and elementary drawings per the design basis. These documents referenced l MO-1301-53 as a jog open/ seal-in close valve. The wiring in the old bucket was then investigated. It was found that a wiring change made to an auxiliary relay in the bucket changed the function from a seal-in close valve to a jog close valve. This change was not captured in previous drawing revisions. A search of the maintenance request (MR) database also revealed this change was not captured on a MR. It is, therefore, concluded that the change was made at l an indeterminate date possibly dating back to pre-1972 startup testing.

l The undocumented wiring change did not result in a failure of valve MO-1301-53. '

l CORRECTIVE STEPS TAKEN AND RESULTS ACHIEVED Example No.1

The microprocessor control units (MCUs) for the four regulating transformers were modified via a design change (PDC 97-11) on April 12,1997. The modification disabled the undervoltage and overvoltage shut down functions. This allows the transformers to operate in the unregulated i

mode when the input voltage is outside the design range. Post work tests were performed to ensure the regulating transformers would continue to operate during simulated undervoltage and overvoltage conditions. During the tests, the highest and lowest transformer taps were selected  !

without a shut down of the respective regulating transformer. Based on the satisfactory results of l this testing, the regulating transformers were declared operable. j Problem report, PR 97.1658, was written to document that the safety evaluation 2664 performed

, to allow the installation of the regulating transformers did not evaluate the consequences of an i undervoltage transient shut down. The problem report evaluation concluded that the a

undervoltage shutdown was not considered because the vendor had not notified Boston Edison

?- about the transformer's undervoltage trip, and specification E15A did not ensure continued operation of the transformers during voltage transients. Tne evaluation also concluded that the procedures to write specifications and safety evaluations are adequate; however, the specification procedure will be enhanced to require identification of all new component automatic

  • functions. The electrical engineering department design guide will be also be updated to enhance the Equipment Codes and Standards section.

J 5

)

Example No. 2 An engineering design change (FRN 93-38-21) was issued on April 18,1997, to change valve MO-1301-53 to a jog open/close valve. The valve was then stroked (jogged in the open and close directions) with satisfactory results. The document changed the closing circuit from a seal-in type circuit to a jog type circuit. The affected drawings will be revised as part of the routine modification close-out procecs. With this change, the control circuitry for MO-1301-53 functions

as a jog circuit in the open and close directions. The change did not affect the automatic closing function of valve MO-1301-53.

s A review was conducted of the other breakers replaced under PDC 93-38 focusing on those that

power motor-operated valves that contain a jog control switch circuit. The review concluded the buckets were wired in accordance with design, and the undocumented wiring change was an isolated instance that could date back to initial start-up testing (circa 1972). Current procedures and wark practices require approved design changes for wiring changes and documenting wiring

, discrepancies in accordance with the problem report process.

l CORRECTIVE STEPS THAT WILL BE TAKEN TO AVOID FURTHER VIOLATIONS

Example No.1 Specification E-15A and regulating transformers documentation (vendor manual V-1184) will be revised to reflect PDC 97-11 as part of the routine modification close-out process by August 31, 2 1997.

i' j- The specification procedure will be enhanced to require identification of all new component

! automatic functions by July 31,1997.

The electrical engineering department will update the design guide to enhance the Electrical Codes and Standards and section by June 30,1997.

The human performance aspects of the cause of the deficiency in specification E15A, which were

, addressed via the corrective action process (PR 97.9245), will be discussed in the electrical engineering department training by August 31,1997.

The vendor interface issues associated with this violation will be addressed in our supplemental i response due by July 11,1997.

j Example No. 2 Our current procedures and work practices require approved design changes for wiring changes and documenting wiring discrepancies in accordance with the problem report process. No further changes are required to prevent recurrence.

1 I

6

',,.,*. i

, DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED i

Example No.1 Full compliance will be achieved by August 31,1997, following implementation of the last open I corrective action. These commitments are being tracked under RC 97.0023.

Example No. 2 I' 4

Full compliance was achieved when MO-1301-53 was rewired and tested on April 18,1997.

i I

REFERENCES 1

1) LER 97-007 " Safeguards Buses De-energized and Losses of Off-site Power during Severe Storm while Shut Down", Boston Edison Letter #2.97.050 dated May 1,1997.

i 2) LER 97-009 "RCIC System inoperable due toTurbine Overspeed Trip during Surveillance",

, Boston Edison Letter #2.97.056 dated May 19,1997.

i I

)

i 4

4 s

7