Meeting with FENOC for an Annual Assessment to Discuss Nrc'S Assessment of the Safety Performance of Beaver Valley for Calendar Year 2005
ML060660509
Person / Time
Site: Beaver Valley  FirstEnergy icon.png
Issue date: 03/10/2006
From: Bellamy R
NRC/RGN-I/DRP/PB7
To:
Bellamy R Rgn-I/DRP/Br7/610-337-5200
Shared Package
ML060660502 List:
References
MN 06-006
Download: ML060660509 (5)


Text

MN No.06-006 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING March 10, 2006 Licensee: FirstEnergy Nuclear Operating Company (FENOC)

Facility: Beaver Valley Power Station, Units 1 & 2 Docket Nos.: 50-334 & 50-412 Date/Time: March 28, 2006 at 1:00 p.m.

Location: Beaver Valley Nuclear Power Station Training Building, Room 103 Shippingport Road, Shippingport, PA 15077 (Located across Shippingport Road from the Beaver Valley parking lot entrance)

Purpose:

The NRC requested an Annual Assessment Meeting with FENOC management to discuss NRCs assessment of the safety performance of the Beaver Valley Nuclear Power Station for calendar year 2005. NRCs assessment is documented in a letter dated March 2, 2006.

Attendees*:

NRC: R. Bellamy, Chief, Projects Branch 7, Region I P. Cataldo, Senior Resident Inspector G. Smith, Resident Inspector Licensee: J. Lash, Site Vice President R. Mende, Director, Beaver Valley Site Operations T. Cosgrove, Director, Maintenance L. Freeland, Acting Director, Process Improvement Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

NRCs assessment letter can be found in ADAMS with an Accession Number of ML060620158.

This meeting notice with the enclosed agenda can be located in ADAMS with an Accession Number of ML060660509. The NRC slides for the meeting can be accessed with the Accession Number ML060680441. ADAMS is accessible for the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html.

2 Additional information relative to the NRCs Annual Assessment process and the safety performance of Beaver Valley Power Station can be found on the NRCs web site at:

http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html Meeting

Contact:

Dr. Ronald Bellamy, Chief, Projects Branch 7 610-337-5200 E-mail: RRB1@nrc.gov.

C Handicapped persons requiring assistance to attend or participate in the meeting shall make their requests known to the meeting contact no later than two business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by March 28, 2006, via telephone to the NRC meeting contact.

Approved by: _____/RA/_______________

Dr. Ronald R. Bellamy, Chief Projects Branch 7 Division of Reactor Projects Distribution:

J. Lash, Site Vice President R. Mende, Director, Site Operations T. Cosgrove, Director, Maintenance P. Sena, Director, Engineering L. Freeland, Acting Director, Process Improvement M. Clancy, Mayor, Shippingport, PA R. Janati, Chief, Division of Nuclear Safety, Commonwealth of Pennsylvania C. OClaire, State Liaison to the NRC, State of Ohio D. Hill, Chief, Radiological Health Program, State of West Virginia R. Chiodo, Beaver County Emergency Management Agency Commonwealth of Pennsylvania, SLO Designee Regional Administrator Secretary, RI DRM Division Secretary, RI Region I Receptionist

Annual Assessment Meeting Agenda:

C Introduction C Review of NRC Reactor Oversight Process C National Summary of Plant Performance C Discussion of Beaver Valley Performance Results C FENOC Response and Remarks C NRC Closing Remarks C Break C NRC available to address public questions

4 Distribution: (Via E-Mail):

Executive Director for Operations, OEDO (RIDSEDOMAILCENTER)

Deputy Executive Director for Reactor Programs, OEDO (RIDSEDOMAILCENTER)

Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD)

Deputy Director, Office of Nuclear Reactor Regulation, NRR/ADPR (RIDSNRROD)

Director, Division of Regulatory Improvement Programs, NRR (RIDSNRRDRIP)

Director, Division of Inspection Program Management, NRR (RIDSNRRDIPM)

Director, Division of Licensing Project Management, NRR (RIDSNRRDLPM)

Project Directorate I-1 (PD1/2), NRR (RIDSNRRDIPMLPDI)

Asst. General Counsel Materials Litigation and Enforcement, OGC (RIDSOGCMAILCENTER)

B. Holian, DRP D. Lew, DRP R. Blough, DRS M. Gamberoni, DRS R. Bellamy, DRP R. Fuhrmeister, DRP R. Marziale, DRP Division Secretary, RI K. Gallagher, DRS Division Secretary, RI B. Sosa, RI OEDO R. Laufer, NRR T. Colburn, PM, NRR R. Guzman, NRR K. Farrar, Regional Counsel D. Screnci, Senior Public Affairs, RI N. Sheehan, Field Public Affairs Officer, RI R. Bores, ORA J. Wray, ORA P. Cataldo, SRI, Beaver Valley G. Smith, RI - Beaver Valley P. Garrett, Resident OA G. Matakas, ORA PMNS Accession Number ML060660509 SISP Review Complete: AAR (Reviewers Initials)

DOCUMENT NAME: E:\Filenet\ML060660509.wpd After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP /

NAME ARosebrook/AAR RBellamy/RRB DATE 03/07/06 03/09/06 OFFICIAL RECORD COPY

5