MN No.06-030 EA No.06-215 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING October 6, 2006 Licensee: First Energy Nuclear Operating Company (FENOC)

Facility: Beaver Valley Power Station, Units 1 & 2 Docket Nos.: 50-334 & 50-412 Date/Time: October 24, 2006 at 10:00 a.m.

Location: U.S. Nuclear Regulatory Commission Public Meeting Room 475 Allendale Road King of Prussia, PA 19406

Purpose:

A regulatory conference will be held to discuss an apparent violation identified during a routine inspection conducted at the Beaver Valley Nuclear Power Station on June 27, 2006. The finding concerns the performance of the Beaver Valley Power Station dose assessment team.

This finding is similar to an NRC-identified weakness during a May 2004 emergency exercise.

NRC Attendees: Samuel J. Collins, Regional Administrator A. Randolph Blough, Director, Division of Reactor Safety Raymond K. Lorson, Chief, Plant Support Branch 1, Division of Reactor Safety Ronald R. Bellamy, Chief, Projects Branch 7, Division of Reactor Projects Stephen T. Barr, Senior Emergency Preparedness Inspector Karl L. Farrar, Regional Counsel Daniel J. Holody, Team Leader, Technical Program Staff Licensee Attendees: James H. Lash, Site Vice President Larry Freeland, Director, Site Performance Improvement Susan Vicinie, Manager, Emergency Planning Brian, Tuite, Principal Consultant John Lebda, Staff Nuclear Engineer Vernon Higaki, Manager, Fleet Emergency Preparedness Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

2 NRCs inspection report can be found in ADAMS with an Accession Number of ML062620341.

This meeting notice with the enclosed agenda can be located in ADAMS with an Accession Number of ML062780341. ADAMS is accessible for the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html.

Meeting

Contact:

Ronald R. Bellamy, Chief, Projects Branch 7 Division of Reactor Projects 610-337-5200 E-mail: RRB1@nrc.gov Handicapped persons requiring assistance to attend or participate in the meeting shall make their requests known to the meeting contact no later than two business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by October 17, 2006, via telephone to the NRC meeting contact.

/RA/ Roy Fuhrmeister signed for Approved by: ____________________________

Ronald R. Bellamy, Chief Projects Branch 7 Division of Reactor Projects

3 cc w/encl:

G. Leidich, President and Chief Nuclear Officer J. Hagan, Senior Vice President of Operations and Chief Operating Officer D. Pace, Senior Vice President, Fleet Engineering J. Rinckel, Vice President, Fleet Oversight L. Myers, Executive Vice President, Special Projects R. Anderson, Vice President, FirstEnergy Nuclear Operating Company Manager, Fleet Licensing, FirstEnergy Nuclear Operating Company R. Mende, Director, Site Operations T. Cosgrove, Director, Maintenance P. Sena, Director, Engineering L. Freeland, Director, Site Performance Improvement and Manager, Regulatory Compliance D. Jenkins, Attorney, FENOC B. Sepelak, Supervisor, Nuclear Compliance M. Clancy, Mayor, Shippingport, PA D. Allard, PADEP C. OClaire, State Liaison to the NRC, State of Ohio Z. Clayton, EPA-DERR, State of Ohio Director, Utilities Department, Public Utilities Commission, State of Ohio D. Hill, Chief, Radiological Health Program, State of West Virginia J. Lewis, Commissioner, Division of Labor, State of West Virginia W. Hill, Beaver County Emergency Management Agency J. Johnsrud, National Energy Committee, Sierra Club

Distribution: (Via E-Mail):

Executive Director for Operations, OEDO M. Gamberoni, DRS (RIDSEDOMAILCENTER) R. Bellamy, DRP Director, Office of Enforcement R. Fuhrmeister, DRP (RIDSEDOMAILCENTER) B. Sosa, RI OEDO Deputy Executive Director for Reactor R. Laufer, NRR Programs, OEDO T. Colburn, PM, NRR (RIDSEDOMAILCENTER) R. Guzman, NRR RI EDO Coordinator, OEDO K. Farrar, Regional Counsel Director, Office of Nuclear Reactor D. Screnci, Senior Public Affairs, RI Regulation, NRR (RIDSNRROD) N. Sheehan, Field Public Affairs Officer, RI Deputy Director, Office of Nuclear Reactor J. Wray, ORA Regulation, NRR/ADPR (RIDSNRROD) N. McNamara, State Liaison Officer Director, Division of Regulatory M. McLaughlin, State Liaison Officer Improvement Programs, NRR P. Cataldo, SRI, Beaver Valley (RIDSNRRDRIP) D. Werkheiser, RI - Beaver Valley Director, Division of Inspection Program P. Garrett, Resident OA Management, NRR (RIDSNRRDIPM) R. Barkley, RI Technical Communications Director, Division of Licensing Project Assistant Management, NRR (RIDSNRRDLPM) G. Matakas, ORA Project Directorate I-1 (PD1/2), NRR R. Marziale, DRP Division Secretary, RI (RIDSNRRDIPMLPDI) K. Gallagher, DRS Division Secretary, RI Asst. General Counsel Materials Litigation S. Barr, Senior Emergency Preparedness and Enforcement, OGC Inspector (RIDSOGCMAILCENTER) N. Mamish, NSIR OEMAIL A. McMurtray, NSIR B. Holian, DRP R. Kahler, NSIR D. Lew, DRP PMNS R. Blough, DRS Accession Number ML062780431 SUNSI Review Complete: FMH (Reviewers Initials)

DOCUMENT NAME: E:\FileNET\ML062780341.wpd After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS RI/ORA RI/DRP NAME RLorson/FMH RSummers/JRW RBellamy/RLF DATE 10/05/06 10/05/06 10/06/06 OFFICIAL RECORD COPY