Revised Forthcoming Meeting with Firstenergy Nuclear Operating Company, Regarding Beaver Valley Units 1 and 2 Extended Power Uprate
ML053120104
Person / Time
Site: Beaver Valley
Issue date: 11/08/2005
From: Colburn T
Plant Licensing Branch III-2
To: Richard Laufer
Plant Licensing Branch III-2
Colburn T, NRR/DLPM, 415-1402
References
TAC M4546, TAC MC4545, TAC MC6725
Download: ML053120104 (5)


Text

REVISED MEETING LOCATION November 8, 2005 MEMORANDUM TO: Richard J. Laufer, Chief Plant Licensing Branch I-1 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation (NRR)

FROM:

Timothy G. Colburn, Senior Project Manager

/RA/

Plant Licensing Branch I-1 Division of Operator Reactor Licensing, NRR

SUBJECT:

FORTHCOMING MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC), ET AL., REGARDING BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 (BVPS-1 AND 2),

EXTENDED POWER UPRATE (EPU) AND REPLACEMENT STEAM GENERATOR (RSG) ALTERNATE SOURCE TERM (AST) ACCIDENT DOSE ANALYSES (TAC NOS. MC4545, MC4546 AND MC6725)

DATE & TIME:

Tuesday and Wednesday, November 29-30, 2005 12:30 p.m. to 4:30 p.m., Tuesday, 7:30 a.m. to noon, Wednesday LOCATION:

Beaver Valley Power Station Emergency Response Facility, Conference Room A Route 168 Shippingport, PA 15077 PURPOSE:

A working-level meeting to discuss FENOCs adoption of the AST methodology for the RSG and EPU license amendment requests. The second day will consist of an audit of proprietary calculations in support of the AST analyses. The second day of the meeting will be closed to the public.

CATEGORY 1:*

This is a Category 1 meeting. The public is invited to observe this meeting (first day) and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned. The meeting agenda is enclosed.

Proprietary information will be discussed at certain times during this meeting (second day). This portion of the meeting will be closed to members of the public who have not been granted access to the information by the owner of the information.

MEETING CONTACT: Timothy G. Colburn, NRR 301-415-1402 tgc@nrc.gov

  • Commission's Policy Statement on Enhancing Public Participation in NRC Meetings,"

(67 FR 36920), May 28, 2002

R. Laufer PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC/NRR FENOC Westinghouse Stone & Webster T. Colburn J. Maracek J. DeBlasio D. Graves J. Lee M. Manoleras R. Surman S. Ferguson J. Parillo C. Keller M. Testa K. Frederick S. Sarver P. Sena H. Hegrat T. McGourty D. Adams Docket Nos. 50-334 and 50-412

Enclosure:

Meeting Agenda cc w/encl: See next page

ML053120104 NRC-001 OFFICE NRR/LPLI-1/PM NRR/LPLI-1/LA NRR/LPLI-1/BC NAME TColburn SLittle via telephone PMilano for RLaufer DATE 11/08/2005 11/08/2005 11/08/2005

MEETING AGENDA NOVEMBER 29-30, 2005, CATEGORY 1 WORKING-LEVEL MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC)

EXTENDED POWER UPRATE (EPU) AND REPLACEMENT STEAM GENERATOR (RSG)

ALTERNATE SOURCE TERM (AST) ACCIDENT DOSE ANALYSES FOR BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 DOCKET NOS. 50-334 AND 50-412 C

Introductory Remarks/Introductions Current Licensing Basis Application of AST methodology Overview of Unit 1 RSG and Units 1 and 2 EPU License Amendment Requests Overview of AST Methodology Application C

Existing Docketed Information o

EPU and RSG Licensing Reports o

Responses to Requests for Additional Information C

Previous Meetings o

December 15, 2004 Meeting (EPU Overview) o March 23, 2005 Meeting (EPU/RSG, best-estimate loss-of-cooling accident and AST) o July 11, 2005 Meeting (RSG Overview)

Questions/Comments Enclosure

Beaver Valley Power Station, Unit Nos. 1 and 2 cc:

Mary OReilly, Attorney FirstEnergy Nuclear Operating Company FirstEnergy Corporation 76 South Main Street Akron, OH 44308 Larry R. Freeland, Manager FirstEnergy Nuclear Operating Company Regulatory Affairs/Performance Improvement Beaver Valley Power Station P.O. Box 4, BV-A Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.

Harrisburg, PA 17110-9364 Ohio EPA-DERR ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149 Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 J. H. Lash, Plant Manager (BV-IPAB)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4 Shippingport, PA 15077 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 FirstEnergy Nuclear Operating Company Beaver Valley Power Station ATTN: R. G. Mende, Director Work Management (BV-IPAB)

P.O. Box 4 Shippingport, PA 15077 FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mr. B. F. Sepelak P.O. Box 4, BV-A Shippingport, PA 15077 Mr. L. William Pearce Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station P. O. Box 4 Shippingport, PA 15077