Letter Sequence Meeting |
|---|
TAC:M4546, (Open) TAC:MC4545, Changes to Section 5.0, Administrative Controls, Removal of Monthly Operating Report and Occupational Radiation Exposure Report (Open) TAC:MC6725, (Approved, Closed) |
|
MONTHYEARML0427204482004-09-20020 September 2004 Cycle 12 (U2C12) 12-Month Steam Generator Inspection Report Project stage: Request ML0427904822004-09-28028 September 2004 Duke Energy Corporation, Application for Technical Specification Improvement to Eliminate Requirements to Provide Monthly Operating Reports and Occupational Radiation Exposure Reports Project stage: Request ML0427305142004-09-28028 September 2004 Commission Meetings - FRN Project stage: Request ML0509101512005-03-31031 March 2005 Tech Spec Pages for Amendment Nos. 222 and 217, TS Revisions to Eliminate Monthly Operating and Annual Occupational Radiation Exposure Reports Project stage: Other ML0507004922005-03-31031 March 2005 License Amendment Nos. 222 and 217, TS Revisions to Eliminate Monthly Operating and Annual Occupational Radiation Exposure Reports Project stage: Other ML0507002032005-04-0606 April 2005 RAI, SG Tube IST Reports for End-of-Cycle 12 Refueling Outage (Tac No. MC4545) Project stage: RAI L-05-069, License Amendment Request 320 Re Steam Generator Replacement2005-04-13013 April 2005 License Amendment Request 320 Re Steam Generator Replacement Project stage: Request L-05-050, Units, 1 and 2, 10 CFR 50.46 (a)(3)(ii) Schedule for Reanalysis2005-04-13013 April 2005 Units, 1 and 2, 10 CFR 50.46 (a)(3)(ii) Schedule for Reanalysis Project stage: Request ML0511204592005-04-22022 April 2005 Unit 2 - Response to Request for Information Regarding Steam Generator (SG) Inspection Reports from Unit 2 Cycle 12 Project stage: Response to RAI ML0511902402005-04-22022 April 2005 Offsite Dose Calculation Manual (ODCM) Special Report Project stage: Request ML0517803942005-06-28028 June 2005 Notice of Meeting with Firstenergy Operating Company (Fenoc), ET Al., Regarding Beaver Valley Power Station, Unit No. 1 (BVPS-1) Steam Generator Replacement Project stage: Meeting L-05-112, Responses to a Request for Additional Information in Support of License Amendment Request Nos. 302 and 1732005-07-0808 July 2005 Responses to a Request for Additional Information in Support of License Amendment Request Nos. 302 and 173 Project stage: Request ML0518107112005-07-0808 July 2005 Ltr., SG ISI Reports Summary for Cycle 12 (Tac No. MC4545) Project stage: Other 05000334/LER-2005-001, Re Protection System Channel Delta Temperature Time Constant Switch Found Out of Position2005-07-28028 July 2005 Re Protection System Channel Delta Temperature Time Constant Switch Found Out of Position Project stage: Request ML0520201012005-07-28028 July 2005 Request for Additional Information (RAI) - Beaver Valley Power Station, Unit No. 1 (BVPS-1), Steam Generator Replacement, Partial Implementation of an Alternate Source Term Project stage: RAI ML0520803432005-08-11011 August 2005 Federal Register, Notice of Consideration of Issuance of Amendments to Facility Operating Licenses for Extended Power Uprate (EPU) and Opportunity for Hearing (TACs MC4545 and MC4546 Project stage: Other ML0522300542005-08-11011 August 2005 Notice of Meeting with Firstenergy Nuclear Operating Company Beaver Valley Unit 1 and 2 Extended Power Uprate Small-Break Loss-Of-Coolant Accident Analyses Project stage: Meeting L-05-137, Response to a Request for Additional Information (RAI Dated July 28, 2005) in Support of License Amendment Request No. 3202005-08-26026 August 2005 Response to a Request for Additional Information (RAI Dated July 28, 2005) in Support of License Amendment Request No. 320 Project stage: Response to RAI ML0524307372005-09-28028 September 2005 (BVPS-1), Steam Generator Replacement - Request for Additional Information (RAI) Project stage: RAI L-05-160, Discharge Monitoring Report (NPDES) Permit No. PA00256152005-09-28028 September 2005 Discharge Monitoring Report (NPDES) Permit No. PA0025615 Project stage: Request L-05-168, Supplement to License Amendment Request2005-10-28028 October 2005 Supplement to License Amendment Request Project stage: Supplement L-05-163, Supplement to License Amendment Request Nos. 327/197, 317/190, and 320, Regarding Steam Generator Level Allowable Value Setpoints, Containment Conversion & Replacement Steam Generators, Respectively2005-10-31031 October 2005 Supplement to License Amendment Request Nos. 327/197, 317/190, and 320, Regarding Steam Generator Level Allowable Value Setpoints, Containment Conversion & Replacement Steam Generators, Respectively Project stage: Supplement ML0531101892005-11-0707 November 2005 Forthcoming Meeting with Firstenergy Nuclear Operating Company (Fenoc), ET Al., Regarding Beaver Valley Power Station, Unit Nos. 1 and 2 (BVPS-1 and 2), Extended Power Uprate Project stage: Meeting ML0531201042005-11-0808 November 2005 Revised Forthcoming Meeting with Firstenergy Nuclear Operating Company, Regarding Beaver Valley Units 1 and 2 Extended Power Uprate Project stage: Meeting L-05-165, Response to a Request for Additional Information (RAI Dated September 28, 2005) in Support of License Amendment Request No. 3202005-11-18018 November 2005 Response to a Request for Additional Information (RAI Dated September 28, 2005) in Support of License Amendment Request No. 320 Project stage: Response to RAI L-05-195, Additional Information Regarding Responses to RAI Dated July 28, 2005 in Support of License Amendment Request No. 3202005-12-0606 December 2005 Additional Information Regarding Responses to RAI Dated July 28, 2005 in Support of License Amendment Request No. 320 Project stage: Response to RAI L-05-198, Supplemental Information for License Amendment Request2005-12-16016 December 2005 Supplemental Information for License Amendment Request Project stage: Supplement ML0603001382006-02-0606 February 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Unit No. 1 Project stage: Withholding Request Acceptance ML0602401462006-02-0909 February 2006 Issuance of License Amendment 273 Steam Generator (SG) Replacement Project stage: Approval ML0605901912006-03-0202 March 2006 Westinghouse Electric Company, LLC, Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Unit Nos. 1 and 2 (BVPS-1 and 2) Project stage: Withholding Request Acceptance ML0605902302006-03-0202 March 2006 Westinghouse Electric Company, LLC, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0606002062006-03-0202 March 2006 Westinghouse Electric Company, LLC, Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Unit Nos. 1 and 2 (BVPS-1 and 2) Project stage: Withholding Request Acceptance 2005-04-13
[Table View] |
Text
REVISED MEETING LOCATION November 8, 2005 MEMORANDUM TO: Richard J. Laufer, Chief Plant Licensing Branch I-1 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation (NRR)
FROM:
Timothy G. Colburn, Senior Project Manager
/RA/
Plant Licensing Branch I-1 Division of Operator Reactor Licensing, NRR
SUBJECT:
FORTHCOMING MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC), ET AL., REGARDING BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 (BVPS-1 AND 2),
EXTENDED POWER UPRATE (EPU) AND REPLACEMENT STEAM GENERATOR (RSG) ALTERNATE SOURCE TERM (AST) ACCIDENT DOSE ANALYSES (TAC NOS. MC4545, MC4546 AND MC6725)
DATE & TIME:
Tuesday and Wednesday, November 29-30, 2005 12:30 p.m. to 4:30 p.m., Tuesday, 7:30 a.m. to noon, Wednesday LOCATION:
Beaver Valley Power Station Emergency Response Facility, Conference Room A Route 168 Shippingport, PA 15077 PURPOSE:
A working-level meeting to discuss FENOCs adoption of the AST methodology for the RSG and EPU license amendment requests. The second day will consist of an audit of proprietary calculations in support of the AST analyses. The second day of the meeting will be closed to the public.
CATEGORY 1:*
This is a Category 1 meeting. The public is invited to observe this meeting (first day) and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned. The meeting agenda is enclosed.
Proprietary information will be discussed at certain times during this meeting (second day). This portion of the meeting will be closed to members of the public who have not been granted access to the information by the owner of the information.
MEETING CONTACT: Timothy G. Colburn, NRR 301-415-1402 tgc@nrc.gov
- Commission's Policy Statement on Enhancing Public Participation in NRC Meetings,"
(67 FR 36920), May 28, 2002
R. Laufer PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).
NRC/NRR FENOC Westinghouse Stone & Webster T. Colburn J. Maracek J. DeBlasio D. Graves J. Lee M. Manoleras R. Surman S. Ferguson J. Parillo C. Keller M. Testa K. Frederick S. Sarver P. Sena H. Hegrat T. McGourty D. Adams Docket Nos. 50-334 and 50-412
Enclosure:
Meeting Agenda cc w/encl: See next page
ML053120104 NRC-001 OFFICE NRR/LPLI-1/PM NRR/LPLI-1/LA NRR/LPLI-1/BC NAME TColburn SLittle via telephone PMilano for RLaufer DATE 11/08/2005 11/08/2005 11/08/2005
MEETING AGENDA NOVEMBER 29-30, 2005, CATEGORY 1 WORKING-LEVEL MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC)
EXTENDED POWER UPRATE (EPU) AND REPLACEMENT STEAM GENERATOR (RSG)
ALTERNATE SOURCE TERM (AST) ACCIDENT DOSE ANALYSES FOR BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 DOCKET NOS. 50-334 AND 50-412 C
Introductory Remarks/Introductions Current Licensing Basis Application of AST methodology Overview of Unit 1 RSG and Units 1 and 2 EPU License Amendment Requests Overview of AST Methodology Application C
Existing Docketed Information o
EPU and RSG Licensing Reports o
Responses to Requests for Additional Information C
Previous Meetings o
December 15, 2004 Meeting (EPU Overview) o March 23, 2005 Meeting (EPU/RSG, best-estimate loss-of-cooling accident and AST) o July 11, 2005 Meeting (RSG Overview)
Questions/Comments Enclosure
Beaver Valley Power Station, Unit Nos. 1 and 2 cc:
Mary OReilly, Attorney FirstEnergy Nuclear Operating Company FirstEnergy Corporation 76 South Main Street Akron, OH 44308 Larry R. Freeland, Manager FirstEnergy Nuclear Operating Company Regulatory Affairs/Performance Improvement Beaver Valley Power Station P.O. Box 4, BV-A Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.
Harrisburg, PA 17110-9364 Ohio EPA-DERR ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149 Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 J. H. Lash, Plant Manager (BV-IPAB)
FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4 Shippingport, PA 15077 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 FirstEnergy Nuclear Operating Company Beaver Valley Power Station ATTN: R. G. Mende, Director Work Management (BV-IPAB)
P.O. Box 4 Shippingport, PA 15077 FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mr. B. F. Sepelak P.O. Box 4, BV-A Shippingport, PA 15077 Mr. L. William Pearce Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station P. O. Box 4 Shippingport, PA 15077