MONTHYEARML23345A1662023-12-13013 December 2023 Tennessee Valley Authority - Pre-submittal Meeting for Conversion of Nuclear Quality Assurance Plan from ANSI N45.2-1971 to ASME NQA-1-2015 (EPID L-2023-LRM-0103) - Slides Project stage: Meeting ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan Project stage: Meeting 2023-12-13
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24218A2182024-08-15015 August 2024 Summary of July 16, 2024, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant LAR Related to Containment Penetrations and Fuel Handling ML24176A1252024-06-28028 June 2024 Summary of Partially Closed Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding the Hydrologic Analysis Updates ML24173A2122024-06-27027 June 2024 Summary of Public Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding Adoption of TSTF-276-A, Revision 2 to Clarify Requirements for Diesel Generator Testing ML24155A0422024-06-13013 June 2024 Meeting Summary: Public Scoping Webinars for the Environmental Review of the Subsequent License Renewal Application for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML24158A3002024-06-11011 June 2024 Summary of May 6, 2024, Public Meeting with Tennessee Valley Authority to Discuss the Potential for a License Amendment Request Regarding the Control Room Envelope and Selective Use of an Alternative Source Term ML24142A5152024-05-28028 May 2024 April 22, 2024, Summary of Public Mtg with Tennessee Valley Authority to Discuss Use of Risk-Informed Process Evaluation for a Proposed License Amendment Request Elimination of Limiting Condition for Operation Actions for the Rod Worth Mini ML24136A2242024-05-15015 May 2024 1B EDG NRC Regulatory Conference Meeting Summary May 2, 2024 ML24155A0432024-04-18018 April 2024 Meeting Summary ML24102A1212024-04-18018 April 2024 Summary of Conference Call with Tennessee Valley Authority Regarding Sequoyah Nuclear Plant, Unit 1 Spring 2024 Steam Generator Tube Inspections ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24082A2532024-03-26026 March 2024 Summary of March 18, 2024, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Fuel Handling and Fuel Decay Time ML24057A3792024-03-0808 March 2024 Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Fuel Handling and Fuel Decay Time ML24065A0262024-03-0101 March 2024 LAR Pre-Application Meeting TS 3.9.8 (Decay Time) and FHA Dose Analysis Meteorological Monitoring and Dispersion Modeling Topics ML24057A0402024-02-27027 February 2024 Summary of February 7, 2024, Public Meeting with Tennessee Valley Authority to Preliminarily Discuss the Planned Approach for the Browns Ferry Nuclear Plant Hydrologic Analysis ML24057A0582024-02-27027 February 2024 Summary of February 15, 2024, Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML24043A0462024-02-16016 February 2024 Summary of Meeting with TVA to Discuss Use of Risk-Informed Process Evaluation (RIPE) for a Proposed LAR Regarding Elimination of Limiting Condition for Operation Actions for Rod Worth Minimizers ML24044A0372024-02-15015 February 2024 February 8, 2024, Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Technical Specification Surveillance Requirement 3.1.1.8 ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23304A0682023-11-0606 November 2023 Summary of October 24, 2023, Public Mtg W/Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, and Sequoyah Nuclear Plant, Units 1 and 2 to Revise Function 5, Turbine Trip and F ML23265A1512023-09-28028 September 2023 Summary of September 12, 2023, Partially Closed Meeting with Tennessee Valley Authority to Discuss Proposed License Amendment Request ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23198A3102023-07-20020 July 2023 July 10, 2023, Summary of Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML23157A1272023-06-13013 June 2023 Meeting Summary for Environmental Pre-Submittal Meeting for Subsequent License Renewal Application on May 11, 2023 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML23068A1532023-03-16016 March 2023 Summary of February 22, 2023, Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request to Increase Allowable Number of Tritium Producing Burnable Absorber Rods at Watts Bar Nuclear Plant, Units 1 and 2 ML23055A4562023-03-0909 March 2023 Summary of February 15, 2023, Public Meeting with Tennessee Valley Authority Regarding Proposed Expedited License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML22329A1382022-12-0505 December 2022 Summary of Meeting with Tennessee Valley Authority Related to Planned Alternative Request WBN-2-ISI-01 for Watts Bar Nuclear Plant, Unit 2 ML22319A1952022-12-0202 December 2022 Summary of October 13, 2022, Meeting with Tennessee Valley Authority to Discuss Planned Alternative Requests for the Fifth 10-Year Inservice Testing Program Interval for Brown'S Ferry Nuclear Plant, Units 1, 2, and 3 ML22312A3522022-12-0101 December 2022 Revised - Summary of Regulatory Audit for Alternative Request RV-02 ML22298A1612022-11-17017 November 2022 Summary of Public Meeting on SAMA with TVA ML22266A2742022-09-28028 September 2022 Summary of September 22, 2022, Public Meeting with Tennessee Valley Authority to Discuss a Request to Use a Later Edition of the ASME OM Code ML22207B8302022-07-28028 July 2022 Summary of July 20, 2022, Observation Public Meeting with the Tennessee Valley Authority to Discuss Planned Alternative Request RP-12 to ASME OM Code Testing for the 1B-B Centrifugal Charging Pump at Sequoyah Nuclear Plant, Unit 1 ML22168A1642022-06-27027 June 2022 Summary of June 9, 2022, Meeting with TVA Regarding a Proposed License Amendment Request Related to Low Temperature Overpressure System and Cold Overpressure Mitigation System for Sequoyah and Watts Bar Nuclear Plants ML22109A0042022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Alternative Request Related to Testing of the Motor-Driven Auxiliary Feedwater Pumps at Sequoyah and Watts Bar Nuclear Plants ML22104A2252022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Exemption Request for Watts Bar Nuclear Plant, Unit 2 ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22103A2472022-04-14014 April 2022 Summary of April 12, 2022, Closed Meeting with Tennessee Valley Authority to Discuss Recently Identified Errors Potentially Affecting the Browns Ferry Revised Criticality Analysis License Amendment Request ML22094A1112022-04-0404 April 2022 Public Meeting Summary 2021 Annual Assessment Meeting Catawba Dockets Nos. 50-413 and 50-414; McGuire No. 50-369 and 50-370; Oconee. 50-269, 50-270, and 50-287 ML22083A0762022-03-24024 March 2022 Summary of March 17, 2022, Closed Meeting with Tennessee Valley Authority to Discuss Recently Identified Errors Potentially Affecting the Browns Ferry Atrium 11 License Amendment Request (EPID L-2021-LLA-0132 ML22048B7852022-03-0202 March 2022 Summary of February 16, 2022, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a Request for an Alternative to Requirements for Addressing Pressure Isolation Valve Leakage ML22042B3262022-02-14014 February 2022 Summary of February 8, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed License Amendment Request to Revise the Allowable Value for Trip of Turbine-Driven Main Feedwater Pump at Watts Bar Nuclear Plant, Unit 1 ML22025A3112022-02-0909 February 2022 Summary of January 19, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed Schedule for Development of a License Amendment Request for Increased Tritium Production ML21349A3642022-01-0404 January 2022 Summary of December 14, 2021, Teleconference with Tennessee Valley Authority Regarding a Proposed Change to the Capsule Withdrawal Schedule for Watts Bar Nuclear Plant, Unit 2 ML21313A3482021-11-18018 November 2021 Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a License Amendment Request Regarding Seismic and Fire Probabilistic Risk Assessment (PRA) Modifications to 10 CFR 50.69 ML21279A0902021-11-0303 November 2021 Summary of Conference Calls Regarding the Fall 2021, Mid-Cycle Steam Generator Tube Inspections ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21266A0532021-10-20020 October 2021 Summary of September 22, 2021, Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request to Adopt Technical Specifications Task Force (TSTF)-205 and TSTF-563 ML21265A5142021-10-12012 October 2021 Summary of September 15, 2021, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a License Amendment Request Regarding Elimination of the High Negative Flux Rate Trip ML21273A1922021-10-12012 October 2021 September 27, 2021, Summary of Meeting with Browns Ferry Nuclear Plant, Units 1 & 2 Related to a Planned Alternative Request Per American Society of Mechanical Engineers (Asmee) Code Case N-526, Alternative Requirements for Successive Sect ML21245A4252021-09-15015 September 2021 Summary of August 19, 2021, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to the Watts Bar Nuclear Plant, Units 1 and 2 2024-08-15
[Table view] |
Text
January 18, 2024 LICENSEE: Tennessee Valley Authority FACILITY: Browns Ferry Nuclear Plant, Units 1, 2, and 3 Sequoyah Nuclear Plant, Units 1 and 2 Watts Bar Nuclear Plant, Units 1 and 2 Clinch River Nuclear Site
SUBJECT:
SUMMARY
OF DECEMBER 13, 2023, MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING A PROPOSED CHANGE TO THE TENNESSEE VALLEY AUTHORITY NUCLEAR QUALITY ASSURANCE PLAN (EPID L-2023-LRM-0103)
On December 13, 2023, the U.S. Nuclear Regulatory Commission (NRC) staff conducted an observation meeting with representatives of the Tennessee Valley Authority (TVA). The purpose of the meeting was to discuss TVAs proposed conversion of its Nuclear Quality Assurance Plan (NQAP) from American National Standards Institute (ANSI) N45.2-1971, Quality Assurance Program Requirements for Nuclear Facilities, to American Society of Mechanical Engineers (ASME) NQA-1-2015, Quality Assurance Requirements for Nuclear Facility Applications.
The meeting notice and agenda, dated November 28, 2023, are available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML23332A142. TVAs presentation slides for the meeting are available at ADAMS Accession No. ML23345A166. A list of participants is enclosed.
TVA stated that it plans to request NRC approval of a revision to its operating fleet NQAP by transitioning the plan to ASME NQA-1-2015, which is endorsed by Regulatory Guide (RG) 1.28, Revision 5, Quality Assurance Program Criteria (Design and Construction). The plan would also follow guidance in American National Standards Institute/American Nuclear Society (ANSI/ANS) 3.2-2012, Managerial, Administrative, and Quality Assurance Controls for the Operational Phase of Nuclear Power Plants, which is endorsed by RG 1.33, Revision 3, Quality Assurance Program Requirements (Operation).
TVA stated that the purpose of transitioning the NQAP is to support the future state of the operating fleet and new nuclear builds (e.g., at the Clinch River site). TVA previously submitted NNP-TR-001-NP, Revision 0, Quality Assurance Program Description (QAPD) For TVA New Nuclear Program (hereinafter referred to as TVA New Nuclear QAPD) to the NRC for approval.
The NRC staff has found that the TVA New Nuclear QAPD is acceptable for referencing in the Clinch River Nuclear Site construction permit license application, with the limitations and conditions (ML23254A050).
TVA stated that it plans to adopt the most recent quality-related NRC RGs with the exception of RG 1.28, Revision 6. TVA will also submit a New Nuclear Quality Assurance Plan after issuance of the safety evaluation noted above.
TVA enumerated the key updates and alternative commitments planned for the revised NQAP, notably maintaining commitments to historical design and construction standards in effect when plants were built; maintaining a commitment to alternative administrative processes versus ANSI/ANS 3.2-2012 requirement for 2-year procedure review; and maintaining a 36-month periodicity for internal audits of Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, to Part 50 of Title 10 of the Code of Federal Regulations (10 CFR Part 50, Appendix B) activities. Additionally, where ANSI/ANS 3.2-2012 references NQA-1-2008 and NQA-1-2009 addenda for requirements, TVA Nuclear will follow NQA-1-2015.
The request will be accompanied by a request to revise the TVA plants technical specifications (TS) to delete the specific revision of RG 1.33 that is cited in TS 5.4.1.a, and instead refer to the revision of RG 1.33 that is specified in the TVA NQAP. This will allow flexibility for TVA to adopt future revisions of RG 1.33 without having to submit a license amendment request.
TVA plans to submit the request by January 31, 2024, and will request approval within 1 year.
No regulatory decisions were made at this meeting.
Please direct any inquiries to me at 301-415-1627 or by e-mail to Kimberly.Green@nrc.gov.
/RA/
Kimberly J. Green, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, 50-391, and 99902056
Enclosure:
List of Participants cc: Listserv
LIST OF PARTICIPANTS DECEMBER 13, 2023, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING PROPOSED CHANGE TO TVA NUCLEAR QUALITY ASSURANCE PLAN Name Affiliation Kim Green U.S. Nuclear Regulatory Commission (NRC)
Deanna Zhang NRC Clint Ashley NRC Allen Fetter NRC Shawna Hughes Tennessee Valley Authority (TVA)
Russ Wells TVA Ronald Detwiler TVA Robert Krigelman TVA Jamie Paul TVA Stuart Rymer TVA Andy Taylor TVA Chris Rice TVA John Talbot TVA Gordon Williams TVA Adrienne Hudson TVA Jerry Bingaman State of Tennessee, Tennessee Department of Environment &
Conservation, Division of Radiological Health Enclosure
ML24008A159 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA DORL/LPL2-2/BC DORL/LPL2-2/PM NAME KGreen ABaxter DWrona KGreen DATE 01/09/24 01/10/24 01/17/24 01/18/24