MONTHYEARML20192A1402020-06-30030 June 2020 Southern Nuclear Operating Co., Inc. - License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Request ML20202A0172020-07-23023 July 2020 Non-Acceptance of Requested Licensing Action License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Pos Project stage: Acceptance Review ML20224A4642020-08-11011 August 2020 Southern Nuclear Operating Co, Inc - Supplement to License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Supplement ML20217L4312020-08-13013 August 2020 Edwin I Hatch, Units 1 and 2; and Vogtle Electric Plant, Units 1, 2, 3, and 4 - Meeting Slides a License Amendment Request for the Emergency Plan (EPID Nos L-2020-LLA-0150 and L-2020-LLA-051 Project stage: Meeting ML20217L3692020-08-13013 August 2020 Summary of Meeting Joseph M. Farley Nuclear Plant, Units 1 and 2; Edwin I. Hatch, Units 1 and 2; and Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 a LAR for the Emergency Plan (EPID Nos. L-2020-LLA0150 and L-2020-LLA-015 Project stage: Meeting ML20245E2842020-09-0101 September 2020 NRR E-mail Capture - Acceptance Review - SNC Fleet EP LAR (L-2020-LLA-0150 and L-220-LLA-151) Project stage: Acceptance Review ML20293A0752020-10-14014 October 2020 NRR E-mail Capture - RAIs for SNC Fleet EP LAR (L-2020-LLA-0150 and L-2020-LLA-0151) Project stage: RAI PMNS20201237, Notice of Meeting with Southern Nuclear Operating Company, Inc. to Discuss Fleet Emergency Plan License Amendment Request2020-10-21021 October 2020 Notice of Meeting with Southern Nuclear Operating Company, Inc. to Discuss Fleet Emergency Plan License Amendment Request Project stage: Meeting ML20318A0742020-10-21021 October 2020, 12 November 2020, 16 November 2020 MTS - Meeting Summary - SNC Fleet EP LAR - November 12 2020 Project stage: Request ML20318A1032020-11-12012 November 2020 SNC ERO Staffing LAR RAI Responses Project stage: Other ML20318A0752020-11-16016 November 2020 Summary of November 12, 2020, Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a License Amendment Request for the Emergency Plan Project stage: Meeting NL-20-1273, Response to NRC Requests for Information License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for2020-11-20020 November 2020 Response to NRC Requests for Information License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Project stage: Response to RAI ML20342A0182021-02-24024 February 2021 Audit Plan for Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Other ND-21-0277, ITAAC Closure Notification on Completion of ITAAC 2.5.06.02 (Index Number 574)2021-04-26026 April 2021 ITAAC Closure Notification on Completion of ITAAC 2.5.06.02 (Index Number 574) Project stage: Request ML21117A2882021-04-27027 April 2021 ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 2.5.06.02 (Index No. 574) for Vogtle Unit 3 Combined License (VOG3) Project stage: Request ML21060B4322021-05-19019 May 2021 Audit Report for Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Other ML21217A0282021-09-17017 September 2021 Safety Evaluation for Vogtle Electric Generating Plant Units 3 and 4 Regarding Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Approval ML21217A0262021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment No. 187 Project stage: Other ML21217A0272021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment No. 185 Project stage: Other ML21217A0252021-09-17017 September 2021 Amendment No. 185 - Vogtle Electric Generating Plant Unit 4 Project stage: Other ML21217A0242021-09-17017 September 2021 Amendment No. 187 - Vogtle Electric Generating Plant Unit 3 Project stage: Other ML21217A0232021-09-17017 September 2021 Cover Letter for Vogtle Electric Generating Plant Units 3 and 4 Amendment Nos. 187 and 185 Regarding Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Other 2020-08-11
[Table View] |
Summary of Meeting Joseph M. Farley Nuclear Plant, Units 1 and 2; Edwin I. Hatch, Units 1 and 2; and Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 a LAR for the Emergency Plan (EPID Nos. L-2020-LLA0150 and L-2020-LLA-015ML20217L369 |
Person / Time |
---|
Site: |
Hatch, Vogtle, Farley, 05000365 |
---|
Issue date: |
08/13/2020 |
---|
From: |
John Lamb Plant Licensing Branch II |
---|
To: |
|
---|
Lamb J, NRR/DORL/LPLII-2, 415-3100 |
Shared Package |
---|
ML20217L458 |
List: |
---|
References |
---|
EPID L-2020-LLA-0151, EPID L-2020-LLA0150 |
Download: ML20217L369 (6) |
|
|
---|
Category:Meeting Summary
MONTHYEARML24290A1582024-10-24024 October 2024 Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed License Amendment Request to Change Table 3.3.8-1 for Vogtle Electric Generating Plant, Units 3 & 4 ML24292A0022024-10-22022 October 2024 Summary of October 16, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Increase Flexibility in Mode Restraints ML24290A0792024-10-18018 October 2024 SLR Environmental Preapplication Meeting Summary ML24270A2112024-10-0404 October 2024 September 23, 2024, Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Proposed LAR to Be Excepted from Footnote 11 Listed in Regulatory Guide 1.183, Rev. 0, for Farley 1 & 2 ML24226B2112024-08-22022 August 2024 Regulatory Audit Summary in Support of License Amendment Requests to Revise Technical Specification 3.6.5, Containment Air Temperature, Actions ML24213A2462024-08-0505 August 2024 Summary of Closed Meeting SNC Fleet - Physical Barriers Exemption ML24198A0772024-07-18018 July 2024 Summary of Observation Public Meeting Held with SNC Regarding Previous LAR to Revise TS 3.6.5 Completion Time Increase Using Risk-Informed Process for Evaluation to Increase for Farley Nuclear Plant, Units 1 and 2 ML24187A0012024-07-17017 July 2024 Summary of Observation Pre-Application Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Revise TS 3.3.8, Engineered Safety Feature Actuation System for Vogtle Electric ML24179A1592024-07-0202 July 2024 June 27, 2024, Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML24156A1772024-06-11011 June 2024 Summary of June 6, 2024, Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding the Physical Barrier Exemptions for Joseph M. Farley Nuclear Plant, Units 1 and 2, Edwin I. Hatch Nuclear Plant, Units 1 and 2, and Vogtle ML24149A0742024-06-0101 June 2024 Summary of May 29, 2024, Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding the Steam Generator Tube Inspection Report for Vogtle Electric Generating Plant, Unit 1 ML24138A0092024-05-17017 May 2024 Public Meeting Summary - 2023 Annual Assessment Meeting for Joseph M. Farley, Units 1 and 2 Docket No. 50-348, and 50-364 -Meeting Number 20240474 ML24123A0502024-05-0202 May 2024 2023 Annual Assessment Public Meeting Summary Meeting Number 20240479 ML24122C6202024-05-0101 May 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 Docket Nos.. 50-424, 50-424, 52-025, and 52-026 Meeting Number 20240471 ML24108A0832024-04-19019 April 2024 Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML24093A0612024-04-18018 April 2024 April 1, 2024, Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Proposed Alternative Requests to the Extend Examination Intervals for Joseph M. Farley Nuclear Plant and Vogtle ML24096A1832024-04-12012 April 2024 Summary of April 3, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Proposed License Amendment Request to Revise Technical Specification 3.6.5 ML24068A0962024-03-18018 March 2024 Summary of 3-7-24, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Co., Inc., Regarding a Proposed License Amendment Request for TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspection ML24025A1372024-01-31031 January 2024 Summary of Observation Pre-Submittal Meeting Held with Snc., Regarding a Proposed Alternative Request - Explosively Actuated Valves for Vogtle Electric Generating Plant, Units 3 and 4 ML24012A1592024-01-30030 January 2024 Summary of January 8, 2024, Meeting Held with Southern Nuclear Operating Company, Inc., to Discuss a RAI License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Head Bolts ML24019A1932024-01-30030 January 2024 Summary of January 8, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed LAR for Vogtle Electric Generating Plant, Units 1, 2, 3, & 4; Hatch, Units 1 & 2; Farley, Units 1 & 2 ML23356A0282023-12-27027 December 2023 December 11, 2023, Pre-Application Meeting with SNC Regarding a Proposed Fleet LAR to Revise TS 5.3.1 to Relocate Training Qualification Requirements from TS to Their Qatr/Ndqam ML23338A2592023-12-0808 December 2023 Summary of Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a License Amendment Request for the Reactor Pressure Vessel Head Closure Bolts for Hatch, Units 1 & 2 (EPID No. L-2022-LLA- 0120) ML23311A1302023-11-17017 November 2023 Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0 ML23313A0952023-11-16016 November 2023 Summary of November 7, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23303A2032023-11-0101 November 2023 October 24, 2023, Summary of Comment Gathering Public Meeting on Lessons Learned from the ITAAC Hearing Process for Vogtle Units 3 and 4 ML23275A0882023-10-12012 October 2023 Summary of Meeting with Southern Nuclear Operating Company ML23272A1822023-10-11011 October 2023 Summary of September 28, 2023, Observation Pre Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML23244A0312023-09-18018 September 2023 MTS - Meeting Summary - Pre-Submittal Meeting on August 02, 2023 - RICT 45-day Extension for TS 3.7.1 & 3.7.2 ML23230A0212023-08-30030 August 2023 LAR-22-002 Technical Specification 3.8.3 Summary of 08-17-23 Public Meeting ML23187A5742023-08-22022 August 2023 Summary of June 29, 2023, Meeting with Southern Nuclear Operating Company ML23146A1542023-06-0505 June 2023 Summary of May 25, 2023, Meeting with Southern Nuclear Operating Company ML23146A1672023-05-31031 May 2023 Public Meeting Summary2022 Annual Assessment Meeting for Joseph M. Farley, Units 1 and 2 Docket No. 50?348, and 50?364 Meeting Number 20230610 ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 ML23132A0412023-05-18018 May 2023 Summary of May 11, 2023, Meeting with Southern Nuclear Operating Company ML23121A1692023-05-12012 May 2023 Summary of Meeting with Southern Nuclear Operating Company Vogtle LAR-23-006 U/3&4 More Restrictive Action for TS 3.1.9 Cvs Isolation Valves ML23115A3282023-05-10010 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have a Pre-Submittal Discussion of Draft License Amendment Request (LAR) for Vogtle Electric Generating Plant (VEGP) Unit 3 ML23115A0662023-05-0101 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have Presubmittal Meeting for Vogtle Electric Generating Plant, Unit 4 IR 05000424/20040252023-04-28028 April 2023 Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 ML23094A1092023-04-14014 April 2023 Summary of Conference Call Held with SNC, Regarding Regulatory Issue Summary 2000-11, Supplement 2, NRC Emergency Telecommunications System, for Joseph M. Farley Nuclear Plant, Units 1 and 2, and SNC Emergency Operations Facility ML23088A3882023-04-0303 April 2023 Summary of March 28, 2023, Observation Public Meeting Held with SNC, Regarding a License Amendment Request Regarding the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plan, Units 1 and 2 ML23090A1422023-04-0303 April 2023 Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections ML23088A2362023-03-28028 March 2023 SNC Presentation - Public Meeting - 03-28-2023 - Page from ML22231B055 ML23065A0732023-03-17017 March 2023 March 2, 2023, Summary of Meeting with Southern Nuclear Operating Company - Vogtle Electric Generating Plant, Unit 4 ML23055A0902023-03-14014 March 2023 February 16, 2023, Summary of Meeting with Southern Nuclear Operating Company ML23048A0682023-03-0101 March 2023 Summary of February 13, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc. Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23037A0032023-02-0606 February 2023 Summary of February 2, 2023, Public Meeting with Southern Nuclear Operating Company ML23012A0512023-01-17017 January 2023 January 11, 2023, Summary of Public Meeting with Southern Nuclear Operating Company (SNC) Regarding Vogtle Emergency Technical Specification Amendment ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company ML22336A0812022-12-0505 December 2022 Summary of December 1, 2022, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 2024-08-05
[Table view] |
Text
August 13, 2020 LICENSEE: Southern Nuclear Operating Company, Inc.
FACILITY: Joseph M. Farley Nuclear Plant, Units 1 and 2; Edwin I. Hatch Nuclear Plant, Units 1 and 2; Vogtle Electric Generating Plant, Units 1, 2, 3, and 4
SUBJECT:
SUMMARY
OF JULY 30, 2020, PUBLIC MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY, INC., REGARDING A LICENSE AMENDMENT REQUEST FOR THE EMERGENCY PLAN FOR JOSEPH M.
FARLEY NUCLEAR PLANT, UNITS 1 AND 2; EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2; AND VOGTLE ELECTRIC GENERATING PLANT, UNITS 1, 2, 3, AND 4 (EPID NOS. L-2020-LLA-0150 AND L-2020-LLA-0151)
On July 30, 2020, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Southern Nuclear Operating Company, Inc. (SNC, the licensee) via Skype. The purpose of the meeting was to clarify the NRC letter to SNC, dated July 23, 2020 (Agencywide Documents and Access Management System (ADAMS)
Accession No. ML20202A017).
By letter dated June 30, 2020 (ADAMS Accession No. ML20192A140), SNC submitted an emergency plan (EP) license amendment request (LAR) for Joseph M. Farley Nuclear Plant, Units 1 and 2; Edwin I. Hatch Nuclear Plant, Units 1 and 2; and Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 (SNC Fleet).
The proposed LAR would revise the SNC Standard Emergency Plan, including the Site Annexes, to change the emergency response organization (ERO) staffing composition, and extend staff augmentation times from 75 to 90 minutes.
By letter dated July 23, 2020, and supporting conference call held on July 23, 2020, the NRC staff determined that the LAR did not provide technical information in sufficient detail for the NRC staff to complete its review and make an independent assessment regarding acceptability.
The subject letter and clarification call informed the licensee was needed for the submittal to be acceptable and, the licensee an opportunity to supplement its docketed submittal. Specifically, the NRC staff identified that the NRC staff needs an analysis that can be used by the NRC staff to assess the impact of the proposed changes on the relief and support functions offered by the augmenting ERO staff to implement the EP effectively. The NRC staff stated that the supplemental information needs to be sufficiently detailed to provide justification for extension of ERO response times and proposed changes to ERO on-shift and augmentation staffing.
A list of attendees is provided as an Enclosure.
On July 27, 2020 (ADAMS Accession No. ML20209A004), the meeting was noticed on the NRC public webpage.
The SNC slide presentation can be found in ADAMS Accession No. ML20217L431.
Discussion SNC presented its slide/talking points. SNC explained the formatting they plan to use in the supplement: (1) SNC response - general, (2) supplemental information on the advantages of the SNC staffing scheme, (3) supplemental information on the staffing analysis process, (4) supplemental information on enhancements, and (5) supplemental information on relief and support functions offered by augmenting staff. SNC also showed a table format that SNC plans to use.
The NRC staff explained that the NRC staff would not be consulting during the meeting and would not be making any regulatory decisions.
The SNC identified the following precedents in its LAR:
In addition, the SNC LAR cited Regulatory Issue Summary (RIS) 2016-10, License Amendment Requests for Changes to Emergency Response Organization Staffing and Augmentation (ADAMS Accession No. ML16124A002), which informed licensees of the application of guidance documents to support LARs that change augmenting ERO arrival times. It stated, in part, that:
The NRC staff has recently received multiple LARs that seek to change ERO staffing commitments by extending the augmentation time for certain positions or eliminating the staffing for positions entirely. In each case, the change has been justified primarily by referencing the on-shift staffing analysis developed in accordance with NEI [Nuclear Energy Institute] 10-05, [Assessment of On-Shift Emergency Response Organization Staffing and Capabilities,] or a similar analysis using different accident scenarios.
RIS 2016-10 further stated:
NEI 10-05 does not consider the capabilities offered by the augmenting ERO staff to relieve and support on-shift staffing for the purposes of providing justification for extension of ERO response times.
However, an evaluation performed using only the guidance of NEI 10-05 does not satisfy the requirement to identify and evaluate changes to ERO
augmentation timing or ERO augmentation staffing that reduces the capability to perform an emergency planning function. Following the guidance from RG 1.219
[Guidance on Making Changes to Emergency Plans for Nuclear Power Reactors], LARs that seek approval for changes to on-shift staffing and the augmenting ERO (e.g., staffing levels, response timing) should identify each change and evaluate them individually.
The NRC staff clarified the use of procedure and informational technology advancements for justifying the extension in augmentation times, as well as the use of recent precedence of approvals for similar emergency plan changes.
In LIC-109, Revision 3, Acceptance Review Procedures for Licensing Basis Changes (ADAMS Accession No. ML20036C829), it states:
During the conference call, the NRC staff will identify the omitted or insufficient information to the licensee, discuss the appropriate course of action, and establish the specific date the information will be submitted. It is important that the conference call result in a clear communication to the licensee of the information needed and that the NRC staff gain an understanding of whether the licensee plans to submit the information within the NRC staffs deadline established during the call (no more than 13 working days). However, the licensee does not need to agree with the need for the information or the deadline.
SNC requested to provide the supplemental information within 13 working days from July 23, 2020. This would be August 11, 2020. The NRC staff agreed that SNC can provide the supplemental information on August 11, 2020.
Public Questions to NRC There were 14 members of the public in attendance. One member of the public asked about the functional analysis. The NRC staff responded that the functional analysis provided by SNC is also referred to as a procedure-based performance analysis (PBPA). The NRC staff further provided that the PBPA addressed procedural tasks that would be performed by the on-shift staff and did not identify any tasks that would be provided by the augmenting ERO. As such, the NRC staff could not use this PBPA, and does not justify changes to the augmenting ERO organization.
Closing SNC plans to submit the proposed supplemental information by August 11, 2020. Once received, the NRC staff will perform a thorough review of the proposed supplement and make any regulatory decisions in writing in a timely manner.
The NRC staff made no regulatory decisions during the meeting.
Public Meeting Feedback forms were available, but no comments were received.
The meeting adjourned at 11:42 am (Eastern Daylight time).
Please direct any inquiries to me at 301-415-3100.
/RA John G. Lamb, Senior Project Manager Plant Licensing Branch, II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321, 50-366, 50-348, 50-364, 50-424, 50-425,52-025, and 50-026
Enclosure:
List of Attendees cc Listserv
PKG ML20217L458 Meeting Notice ML20209A004 Meeting Summary ML20217L369 Meeting SlidesML2020217L431 OFFICE DORL/LPL2-1/PM DORL/LPL2-1/LA DORL/LPL2-1/BC DORL/LPL2-1/PM NAME JLamb KGoldstein MMarkley JLamb DATE 7/30/2020 08/11/2020 8/13/2020 8/13/2020 LIST OF ATTENDEES JULY 30, 2020, PUBLIC MEETING WITH SOUTHERN NUCLEAR COMPANY REGARDING EMERGENCY PLAN LICENSE AMENDMENT REQUEST FOR JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2; EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2; VOGTLE EECTRIC GENERATING PLANT, UNITS 1 AND 2; AND VOGTLE EECTRIC GENERATING PLANT, UNITS 3 AND 4 ATTENDEE REPRESENTING John G. Lamb NRC Mike Markley NRC Joe Anderson NRC Mike Norris NRC Ray Hoffman NRC Edward Robinson NRC Don Johnson NRC John Pelchat NRC Edwin Lea NRC Joel Munday NRC Roger Hannah NRC Ryan Joyce SNC Ken Lowery SNC Cheryl Gayheart SNC Jamie Coleman SNC Ernest Bates SNC Ricky Collings SNC Shannon Smelley SNC Justin Wheat SNC Amy Chamberlain SNC Stephanie Agee SNC Jason Weathersby SNC Barty Simonton State of Georgia Sean Hayes State of Georgia Anuradha Nair State of South Carolina David Thachik State of South Carolina Danilyn Bock State of South Carolina Michael Spradlin State of South Carolina Kevin Hicks State of Alabama Brian Hastings State of Alabama Quinton Dailey State of Alabama Monica Ray Energy Compliance Consultants John Tyndall Energy Compliance Consultants R. Brown Energy Compliance Consultants Eric White Duke Energy Neil Turner Dominion Energy Enclosure