MONTHYEARIR 05000338/20230052023-08-25025 August 2023 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338 2023005 and 05000339 2023005) IR 05000338/20220062023-03-0101 March 2023 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2022006 and 05000339/2022006 ML23046A1952023-02-15015 February 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000338/20220052022-08-30030 August 2022 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 Reports 05000338/2022005 and 05000339/2022005 IR 05000338/20210062022-03-0202 March 2022 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 (Reports No. 05000338/2021006 and 05000339/2021006) IR 05000338/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2021005 and 05000339/2021005) ML21165A1222021-06-14014 June 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21154A0662021-06-0202 June 2021 Notification of North Anna Power Station, Units 1 & 2 - Design Bases Assurance Inspection (Team) U.S. Nuuclear Regulatory Commission Inspection Report 05000338/2021010 and 05000339/2021010 ML21145A0052021-05-25025 May 2021 2021003 North Anna Nuclear Power Station Document Request Letter ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 IR 05000338/20200062021-03-0303 March 2021 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 NRC Inspection Reports 05000338/2020006 and 05000339/2020006 ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information IR 05000338/20200052020-08-24024 August 2020 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2020005 and 05000339/2020005) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20182A0332020-06-30030 June 2020 Notification of Inspection and Request for Information ML20175A5532020-06-23023 June 2020 Emergency Preparedness Exercise Inspection Request for Information IR 05000338/20190062020-03-0303 March 2020 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2019006 and 05000339/2019006 ML19326C9882019-11-21021 November 2019 Requalification Program Inspection North Anna Power Station IR 05000338/20190052019-08-27027 August 2019 Updated Inspection Plan for North Anna Power Station, Units 1 and 2, NRC Report 05000338/2019005 and 05000339/2019005 ML19235A1992019-08-23023 August 2019 Baseline Inservice Inspection RFI IR 05000338/20180062019-03-0404 March 2019 Annual Assessment Letter for North Anna, Units 1 and 2; NRC Inspection Report 05000338/2018006 and 05000339/2018006 ML19030A6962019-01-29029 January 2019 ISI RFI IR 05000338/20180052018-08-23023 August 2018 Updated Inspection Plan for North Anna Power Station Units 1 and 2, NRC Report 05000338/2018005 and 05000339/2018005 ML18059A0942018-02-28028 February 2018 EOC Assessment Letter IR 05000338/20170052017-08-21021 August 2017 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - Report 05000338/2017005 and 05000339/2017005 ML17156A0662017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000338/20160062017-03-0101 March 2017 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2016006 and 05000339/2016006 IR 05000338/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Report 05000338, 339/2016005 ML16222A9132016-08-0808 August 2016 Notification of Inspection and Request for Information IR 05000338/20150062016-03-0202 March 2016 Annual Assessment Letter for North Anna Power Station Units 1 and 2 - NRC Inspection Report 05000338/2015006 and 05000339/2015006 ML16013A0622016-01-12012 January 2016 North Anna Power Station, Unit 2 - Notification of Inspection and Request for Information IR 05000338/20150052015-09-0101 September 2015 Mid-Cycle Letter for North Anna Power Station, Units 1 and 2 - NRC Assessment Report 05000338/2015005 and 05000339/2015005 IR 05000338/20140012015-03-0404 March 2015 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2014001 and 05000339/2014001 ML14245A1902014-09-0202 September 2014 Mid-Cycle Ltr 2014 IR 05000338/20130012014-03-0404 March 2014 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2013001 and 05000339/2013001 ML14022A0412014-01-21021 January 2014 TI-182 Phase 2 RFI Final ML13246A1322013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000338/20120012013-03-0404 March 2013 Annual Assessment Letter North Anna, Units 1 and 2, 05000338/2012001 and 05000339/2012001 ML13032A5532013-02-0101 February 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML13037A1712013-02-0101 February 2013 Notification of Inspection and Request for Information ML12248A1102012-09-0404 September 2012 Mid Cycle Assessment Letter North Anna 2012 ML12235A2912012-08-17017 August 2012 IR 05000338-12-012, 05000339-12-012, on 10/28/2011, North Anna Power Station, Units 1 & 2 - Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML1206506412012-03-0505 March 2012 End of Cycle Assessment Report 22 ML1124400992011-09-0101 September 2011 Report 22, Inspection/Activity Plan ML1106303432011-03-0404 March 2011 Inspection/Activity Plan 03/01/2011 - 06/30/2012, EOC Report 22 ML1024402812010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan ML1006202772010-03-0303 March 2010 Inspection/Activity Plan Report 22 2010001 ML0924405332009-09-0101 September 2009 Inspection/Activity Plan 09/01/2009 - 12/31/2010 2023-08-25
[Table view] Category:Letter
MONTHYEARML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 ML23214A2022023-09-0505 September 2023 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-02-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23081A5282023-04-26026 April 2023 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21322A0992021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21256A0692021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Request for Confirmation of Information ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21238A0982021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21225A5022021-08-13013 August 2021 Request for Additional Information for North Anna Power Station, Units 1 and 2, Surry Power Station, Units 1 and 2, and Millstone Power Station, Units 2 and 3, Appendix E of Fleet Report Com-Naf-2 (EPID:L02021-LLT-0000) Public Version ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21188A1652021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21174A1952021-06-23023 June 2021 Safety RAIs - Set Y - Draft - Enclosure ML21166A3512021-06-15015 June 2021 Safety RAIs - Set 4 - Draft ML21123A2972021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail ML21123A2982021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21091A0032021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure 1 - RAIs ML21091A0042021-04-0101 April 2021 SLRA Safety Review - Withdrawn Requests for Information (EPID No. L-2020-SLR-0000) - Enclosure 2 ML21076A4622021-03-17017 March 2021 NRR E-mail Capture - Draft RAI for Versatile Internals and Component Program for Reactors Vipre Code Review (L-2021-LLT-0000) ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 ML21063A5602021-03-0404 March 2021 Final Request for Additional Information Set 1 - North Anna SLRA Safety Review (EPID L-2020-SLR-0000) - Enclosure ML21049A0212021-02-17017 February 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000338/2021012 and 05000339/2021012) and Request for Information (RFI) ML21028A3902021-01-29029 January 2021 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review (EPID Number: L-2020-SLE-0000) (Docket: 50-338 and 50-339) ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21012A3412021-01-22022 January 2021 Requests for Confirmation of Information for the Environmental Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application (EPID Number: L-2020-SLE-0000) (Docket: 50-338 and 50-339) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information ML20316A0422020-11-10010 November 2020 NRR E-mail Capture - FW: Draft RAI for North Anna Unit 2 Steam Generator Tube Inspection Report (ML19179A075) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20125A0762020-05-0101 May 2020 NRR E-mail Capture - Draft RAI Related to Revised Reactor Vessel Material Surveillance Capsule Withdrawal Schedule Dominion Energy Virginia North Anna Power Station Units 1 and 2 (L-2020-LLL-0038) ML20113A5792020-04-21021 April 2020 NRR E-mail Capture - Draft RAI North Anna Fifth 10-year Interval Relief Request (L-2020-LLR-0023) ML19354B6142019-12-20020 December 2019 NRR E-mail Capture - Draft RAI for North Anna Relief Request P-9 ML19317F1042019-11-0707 November 2019 NRR E-mail Capture - Draft RAIs for SB LOCA LAR (Non Prop) ML19191A2512019-07-10010 July 2019 NRR E-mail Capture - Request for Additional Information Open Phase Condition LAR ML19169A0962019-06-17017 June 2019 NRR E-mail Capture - Request for Additional Information Emergency Action Level Scheme Change for Millstone Power Station - Units 1, 2, and 3, North Anna Power Station - Units 1 and 2, and Surry Power Station - Units 1 and 2 ML19162A0052019-06-10010 June 2019 NRR E-mail Capture - Draft RAIs for Dominion EAL Scheme Change ML19108A1902019-04-18018 April 2019 Emergency Preparedness Program Inspection Request for Information ML19060A2432019-03-0101 March 2019 Related to License Amendment Request to Address Open Phase Conditions ML18337A1312018-11-29029 November 2018 NRR E-mail Capture - North Anna SPRA (Fukushima 50.54f) Audit Follow-Up Clarification Question on Plant Modifications 2023-09-14
[Table view] |
See also: IR 05000338/2021404
Text
OFFICIAL USE ONLYSECURITY-RELATED INFORMATION
January 28, 2021
Mr. Daniel G. Stoddard
Senior Vice President and Chief Nuclear Officer
Innsbrook Technical Center
5000 Dominion Blvd.
Glen Allen, VA 23060-6711
SUBJECT: NORTH ANNA UNITS 1 AND 2 - NOTIFICATION OF TARGET SET INSPECTION
AND REQUEST FOR INFORMATION (NRC INSPECTION REPORT
NO. 05000338/2021404 AND 05000339/2021404)
Dear Mr. Stoddard:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II (RII) staff will conduct an inspection of the Target Sets specified by the conditions of
your operating license at the North Anna Nuclear Power Plant Units 1 and 2 on April 27-28,
2021. The inspection team will be led by Mrs. Melana Singletary, Reactor Inspector, of the NRC
RII office. The inspection will be conducted in accordance with Inspection Procedure 71130.14,
Review of Power Reactor Target Sets, and effective Jan. 1, 2018.
On January 27, 2021, a telephone conversation with Mr. Thomas (Mitch) Hayden, confirmed
arrangements for a two-day onsite inspection. The schedule is as follows:
- Onsite inspection: April 27 - 28, 2021
Mrs. Singletary will arrive on Tuesday April 27, 2021, conduct an entrance meeting at 10 am
and exit the following Wednesday afternoon, unless there is an emergent issue which would
either delay the exit or be cause for it to take place over the phone. Due to the security related
nature of the inspection, a conference room that is SGI accessible is requested.
In order to complete the inspection in the time allotted, we will need to review your target sets
and other pertinent documents prior to the inspection. Please provide the documents below
addressed to Mrs. Melana Singletary by March 29, 2021.
OFFICIAL USE ONLYSECURITY-RELATED INFORMATION
OFFICIAL USE ONLYSECURITY-RELATED INFORMATION
D. Stoddard 2
The types of documents the team will be reviewing during conduct of the inspection are
listed below. Please contact Mrs. Singletary at (404) 997-4752 prior to preparing copies and
sending the files. The inspection team will try to minimize your administrative burden by
specifically identifying those documents required for inspection preparation.
Provide the following documents (Ideally uploaded on a file sharing server such
as Certrec):
- All non-SGI procedures that relate to the Target Set maintenance and development
- List of the Target Set Expert Panel members (names and positions)
- Response to security event operations procedure
- Any procedure listed as a credited operator action (OMA) in the target sets
- Results of the last target set expert panel review
- Corrective action program procedures and CRs associated with Target Sets and
the program
- A list of any issue/condition reports since the last target set inspection (3 years)directly
related to target sets
- Any design change packages or modification packages that affected target sets
- A summary or list of any changes that have occurred to the target sets since the
last inspection
Items needed during the Inspection Week:
- Access to all NON-SGI procedures and SGI material (which will only be reviewed on
site) related to Target Sets
- A point of contact knowledgeable in Target Sets and the defensive strategy
- We will require a meeting with Target Set knowledgeable personnel
(including operations) to discuss target set content
We will keep the requested information only as long as is necessary to complete the inspection
activity. Additionally, if you feel that any requested documents would contain proprietary or
company sensitive information, please make sure they are appropriately marked and attached
to an appropriate affidavit for withholding in accordance with 10 CFR 2.390.
This letter does not contain new or amended information collection requirements subject to
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, under control
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and
its enclosures will not be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRCs document
system (ADAMS) because of the security-related concerns contained in this letter.
OFFICIAL USE ONLYSECURITY-RELATED INFORMATION
OFFICIAL USE ONLYSECURITY-RELATED INFORMATION
D. Stoddard 3
Your cooperation and support during this inspection will be appreciated. If you have
questions concerning this inspection, or the inspection team's information or logistical needs,
please contact Mrs. Singletary, the team leader, in the Region II Office at (404) 997-4752, or me
at (404) 997-4521.
Sincerely,
/RA/
Scott M. Shaeffer, Chief
Engineering Branch 2
Division of Reactor Safety
Docket Nos.: 50-338; 50-339
License Nos.: NPF-4, NPF-7
cc: Distribution via ListServ
OFFICIAL USE ONLYSECURITY-RELATED INFORMATION
ML 21028A435
Non-Sensitive Publicly Available
X SUNSI Review
X Sensitive X Non-Publicly Available
RII/DRS RII/DRS
NAME M. Singletary S. Shaeffer