Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail
ML21123A297
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 05/03/2021
From: Lois James
NRC/NRR/DNRL/NLRP
To: Stoddard D
Dominion Energy Co, Virginia Electric & Power Co (VEPCO)
James L, NRR/DNRL/NLRP, 301-415-3306
Shared Package
ML21123A296 List:
References
L-2020-SLR-0000
Download: ML21123A297 (1)


Text

From: James, Lois To: Daniel.G.Stoddard@dominionenergy.com Cc: RidsNrrDnrl Resource; RidsNrrPMNorthAnna Resource; James, Lois; Gibson, Lauren; Tran, Tam; Elliott, Robert; Bradford, Anna; Caldwell, Bob; Miller, Ed; Markley, Michael; Fields, Leslie; Turk, Sherwin; Scro, Jennifer; Ghosh Naber, Anita; McManus, Joseph; McCoppin, Michael; Burnell, Scott; McIntyre, Dave; Hannah, Roger; Pelchat, John; Lea, Edwin; Tobin, Margaret; Downey, Steve; Bailey, Stewart; Cooper, Paula; Bloom, Steven; Desai, Binoy; Paul.Aitken@dominionenergy.com; Keith.J.Miller@dominionenergy.com; Eric.A.Blocher@dominionenergy.com; Craig.H.Heah@dominionenergy.com; Kathryn.H.Barret@dominionenergy.com; Allik, Brian; Gavula, James

Subject:

Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000)

Date: Monday, May 03, 2021 3:59:00 PM Attachments: Safety RAIs - Set 3 - Final - enclosure.pdf Mr. Stoddard:

By letter dated August 24, 2020 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML20246G703), Virginia Electric and Power Company (Dominion or the applicant) submitted an application for the subsequent license renewal of Renewed Facility Operating License Nos. NPF-4 and NPF-7 for the North Anna Power Station, Units 1 and 2 (North Anna) to the U.S. Nuclear Regulatory Commission (NRC).

Dominion submitted the application pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal.

On April 1, 2021, Dominion Energy submitted responses to request for additional information (RAI) Set 1 (ADAMS Accession No. ML21091A187). The NRC staff in the Division of New and Renewed Licenses is in the process of reviewing your application and response to RAI Set 1. Based on our review, the NRC staff has identified the attached final follow up RAIs.

Dominion Energy and NRC management held a clarification call to discuss the follow up questions and a mutually agreeable date for the response of 30 days from the date of this email.

If you have any questions, please contact me by e-mail Lois.James@nrc.gov.

Sincerely, Lois M. James, Senior Project Manger Division of New and Renewed Licenses (DNRL)