Tenth Quarterly Update to Startup Rept
ML20247H767
Person / Time
Site: Catawba Duke Energy icon.png
Issue date: 05/15/1989
From: Tucker H
DUKE POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8905310321
Download: ML20247H767 (2)


Text

-.

' - 1,  ?

[.:!;af *-

, [. -

DUKE POWER GOMPANY  !

. * . P.O. DOX 33180  !

, i CHARLOTTE, N.O. 28242

, HAL H. TUCKER TELeenown vnos caseroset . (704) 373-4531 ~

wwa. sam emonuonon l- 1 I

L l 1

May 15,fl089  !

Document Control Desk.

Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

Catawba Nuclear Station, Unit 2 Docket No.'50-414 Tenth Quarterly Update to Startup Report Gentlemen:

In accordance with Section 6.9.1.3 of the Catawba Nuclear Station Technical ,

Specifications, please find attached the tenth quarterly update to the Unit 2 Startup Report. As indicated in my February 20, 1989 letter to NRC, one test is not complete. Additional quarterly updates to the Startup Report will be submitted as' required by Technical Specifications.-

.i Very truly yours, I

. 6 -

Hal B. Tucker

-JGT12.D1/lcs Attachment .

xc: M. L. Ernst, Regional Administrator-U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 Mr. W. T. Orders NRC Resident Inspector Catawba Nuclear Station I

8905310321 890515 Ik gDR ADOCK 0 % 4[4;{ /

., : ? .

STARTUP REPORT QUARTERLY UPDATE CATAWBA UNIT 2 CYCLE 1 May 15, 1989 TESTING COMPLETED DURING QUARTER None.

STATUS OF TESTING NOT COMPLETE i

STEADY STATE PIPING SYSTEMS OPERATIONAL VIBRATION MEASUREMENT'--TP/2/A/1200/21 This test is described in Section 10.5 and 11.5 in the Startup Report. It is complete except for retesting of piping associated with the Diesel Generator Fuel Oil and Lube Oil systems. Additional restraints were installed during the EOC-1 refueling outage. However, further modifications have been found to be necessary. These modifications involve the replacement of rigid elbows with flexible elbows. Design Engineering is currently evaluating sources of qualified parts. . It.has been determined by Design Engineer bg that a Nuclear Station Modification will be necessary to perform this piping replacement. Completion of the test is dependent on these modifications. It is expected these modifications will be completed during the Unit 2 End of Cycle 3 outage. This outage is currently scheduled to start in June, 1990, i