Rev 2 to Pressure/Temp Limits Rept, Dtd Feb 1999
ML20206S756
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 02/28/1999
From:
FLORIDA POWER CORP.
To:
Shared Package
ML20206S754 List:
References
NUDOCS 9905210210
Download: ML20206S756 (10)


Text

.-

FLORIDA POWER CORPORATION CRYSTAL RIVER UNIT 3 PRESSURE / TEMPERATURE LIMITS REPORT REVISION 2 February 1999 4

Referencing Improved Technical Specifications 1

i l

i i

9905210210 990512 PDR ADOCK 05000302 P PDR _a

TABLE OF CONTENTS P_ age l

S upporting I n formation ... ..... .. . ...... . .. . . . . .. .. . . . .. . . ... . . . . . . . . . . . .. . . . .. . . . . . .. . . .. . . . . .. .. . . .. . .... . . 3 References.......................................................................................................4 Allowable Pressure / Temperature Rates .................................................................. 5 Pl an t H eat up Curve . . .. . . . . . .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 Plant Cooldown Curve . . . . . .. .. .. ..... . . .. .. .. .. .. . . .. .. ... . . . . .. .. . . .. .. . . . . ... ... . . . .. . . . . .. .. . . . . . . ... . . . 7 Plant Inservice Leak and Hydrostatic Testing Curve................................. ............ 8 LTOPCurves.......................................................................................................9 Plant Compo si te Curve . . .. .. .. .. .. .. . . . .. . .. .. . . .. . . . . . . . . . . . . . ..... . . .. .. . ... . .. . .. . . . . .. . . . . . .. . .. .. ... . 10 l l

i l

i i

{

I l

1 I

P/T LIMITS REPORT, Rev. 2 Page 2 of 10 4

i

  • l

. j 1.0 Press:re/ Temperature Limits (Ref.4)

This Pressure-Temperature Limits Report for CR3 has been prepared in accordance with the requirements ofTechnical Specification Section 1.1 and 5.6.2.19. The pressure / temperature (Pff) limits have been developed using the methodology provided in the references (Ref.1, Ref.2, Ref.3). Additional limits have been included which support the LTOP Technical Specification 3.4.11.

The following pressure-temperature limits are included in this report:

1 Allowable plant heatup and cooldown rates 2 Plant heatup P/T curve 3 Plant cooldown P/T curve 4 Plant inservice leak and hydrostatic testing P/T curve 5 LTOP P/T curves 6 Composite P/T curve 2.0 Fluence and Limiting Material Information (Ref.5)

T/4 Location weld LNB to US Cire. Weld (ID 40%)

material SA-1769 fluence 4.27E+18 n/cm2 ART 213.0 F 3/4T Location weld LNB to US Cire. Weld (OD 60%)

material WF-169-1 fluence 1.55E+18 n/cm2 ART 144.5 F 3.0 PTS Evaluation Summary (Ref.6)

Inside Surface weld LNB to US Cire. Weld (ID 40%)

material SA-1769 fluence 7.08E+18 n/cm2 RTpts 239.9 F 4.0 Instrument Uncertainties The values referenced by this document do not include instrument uncertainties.

Uncertainties must be applied based on the specific instruments being used to measure the parameters ofinterest.

P/r LIMITS REPORT, Rev. 2 Page 3 of 10

5.0 Refere ces

1. B&W Owners Group, topical report BAW-1543A, Rev. 2,

" Integrated Reactor Vessel Surveillance Program," May 1985, and Addendum 1, July 1987.

2. B&W Owners Group, topical report BAW-10046A, Rev. 2, " Methods of Compliance With Fracture Toughness and Operational Requirements of 10CFR50, Appendix G," June 1986.
3. B&W Owners Group, topical report BAW-2241P, Rev. O,

" Fluence and Uncertainty Methodologies," May 1997.

4. ETI Document 32-5001746-00, "CR-3 32 EFPY PT Limits,"

August 1998.

5. FTI Document 32-5000218-00," ART for 32 EFPY for CR-3,"

June 1997.

6. FTI Document 32-5000303-00, " PTS Evaluation for CR3,"

June 1997.

I 1

P/I' LIMITS REPORT, Rev. 2 Page 4 of 10

[- . -

ALLOWA@LE HEATUP AND COOLDOWN RATES

a. For the temperature ranges specified below, the heatup rates are:
i. T > 280'F s 70*F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period, ii. 280 F 2 T > 85'F s 50 F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period,

. iii.' 85*F 2 T > 60 F s 15'F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period

b. For the temperature ranges specified below, the cooldown rates are:
i. T > 280'F s 50*F in any 1/2 hour period, ii. - 280 F 2 T > 150 F 's 25*F in any 1/2 hour period, iii. 150 F 2 T s 25 F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period and,
c. A maximum temperature change ofless than or equal to 5 F in any one hour period during hydrostatic testing operations above system design pressure.

These limits are referred to by Technical Specification 3.4.3.

l P/T LIMITS REPORT, Rev. 2 Page 5 of 10 1

I

. REACTOR COOLANT SYSTEM PRESSURE-TEMPERATURE LIMITS FOR HEATUP FOR FIRST 32 EFPY  ;

2800 l DATA POINTS e -iic

,..i-- < , , , ,. .. 4 , ; , ,

2600, 4' Press m14

- Pojnt Temp ;i A 60 368 ,; , , , , ,

2400 _

s 120 368 _,

l c 140 383

- ~ ~ ~ 1 "~ ""

D 160 446 ~ -

E 190 497 F 220 547 - - 6 ++ e+- '

- +,e 4 r ,-e- 4 . + , , ,

2000 G 263 692 -

L -i-

_ H 300 909 . . , . , , . . < . . .,

.P 1800 -

I 325 1129

[ J 350 1448 . .

~ x 41 2772 -

TD

~ ~" ~ '

w 1600 -.

g 4., 4 i , .j,,,

, -, ..i.. ..i..i.. , , , .

g 1400-

,a:1200

.. . .... ' ' 1. . . . . ..

, , l:

  • 4 c.

~

' ~

l i I .

1000

,-.-]- 4 .-- .

, Hh, 1;- '

j a a; 7

+.

..n.>..>.

a. n4 ,

o.,.., ,, . .+> . ,,, , , ,.e.o

.s..

800 44; G: - - - -

,- F i - -

Specific Instrument Uncertainties j 600 E

~'

7- MUST be applied to this curve for -

. .T T

~

7 '

400  ; operational use (see note 2)

p. '

~ A . j l B j C -i-->< i-i-- i+!- i i--}- ++ - --i-- - ~i--

200 p q+

.r.

I '

l'4

..(

O O 50 100 150 200 250 300 350 400 450 500 550 600 RCS TEMPERATURE (degF)

NOTES:

1. The regions of acceptable operation are below and to the right of the limit curve.
2. Margins are included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve. Additional margins for instrument uncertainty are not included and must be applied to operating procedures based on the specific instruments being used to monitor the RCS conditions.

I

3. Applicable for heatup rates of:

{

T > 280*F s 70*F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period, )

280*F 2 T > 85'F s 50*F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period,  !

85'F 2 T > 60'F s 15'F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period

4. RC Pump Constraints for Heatup:

T > 263*F None, I 263'F > T 2 220*F No more than 3 RCPs running, 220*F > T 2 85'F No more than 2 RCPs running, 85'F > T No RCPs running

5. Minimum Temperature for Criticality is 2 525'F (Reference Technical Specification 3.4.2).
6. This curve referred to by Technical Specification 3.4.3 l

l l

l P/T LIMITS REPORT, Rev. 2 Page 6 of 10 i

C e

, REACTOR COOLANT SYSTEM PRESSURE-TEMPERATURE LIMITS FOR COOLDOWN FOR FIRST 32 EFPY 2800 2600, DATA POINTS <"r' "f " * * *r

'"f"* **** *' - t -" ' *- '"I" - '

Point Temp Press a t-  :., :

A- 60 313 . i. . .. ; .. i..i. , . . j . . i . .i . . . . ; ..i .. . 6.; . . j.. i .. ...4..;..

f.. 4. . i . . i . .i. . . ,

' .. . i . . ..i..

2400- B 150 313 ' '

Li. t L' L4

C 187 355 ' *

.' ,,- M~ .

y .. . . . . . .

2200- -

r. 230 543 ,

-F 240 599 -- - - * * - '

2000 -

o 263 ,71o

-H 267 725 .;., ,,, ,, ,. ,, , ,,, , , , , . , ,.s. , , ,

.9 1800 _.

I 280 865 i 32 "i '} "!" .",.

' ' ' ' ' " " " ' ~~

'i" u ' j

' 'i ' '. . $

m 1600 .

1, 3o 3666 E , . . . .

M .370 2297 +- ^4 *' - -

S1400 _ "K" "t" g . q. . . .. . _

..+... .. .+,

g1200 -

J-

,,,..;... 4 . , ,,,, ,,,, , ,,,, ,,,, ., ,

o 1000 --

r j E ,

, . . .j .4. .i. . ...s .j. . j . .;, . ., ,. . p .j .. , . . .[ . .p.s.j . s m.j.. ,

m . j. .

'800- _.

M

.. .. . . . . .. . . . F. . .. .

. Specific Instrument Uncertainties .

E 600 -4G MUST be applied to this curve for

. , , . .  ;.+.; - .

.7 ..+" - -

operational use (see note 2) 400  ; -D !

' f "

.C' 200 L;_Ai-R Bi
4. .t.[ ,

]... s . . ; . . ., . 4. , ..p.j.., . p. j. .; .. 4 . .i . . , m 4. . ..p.i . m. i- ~[ . . m . i. .

0 50 100 150 200 250 300 350 400 450 500 550 600 RCS TEMPERATURE (degF)

NOTES:

1, The regions of acceptable operation are below and to the right of the limit curve.

2. Margins are included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve. Additional margins for instrument uncertainty are not included and must be applied to operating procedures based on the specific instruments being used to monitor the RCS conditions.
3. Applicable for cooldown rates of:

T > 280'F s 50*F in any 1/2 hour period, 280'F 2 T > 150*F s 25'F in any 1/2 hour period, 150'F 2 T s 25'F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period

4. RC Pump Constraints for Cooldown:

T > 263*F None, 263*F 2 T > 150'F No more than 2 RCPs running, 150*F 2 T No RCPs running

5. This curve referred to by Technical Specification 3.4.3 PN' LIMITS REPORT, Rev. 2 Page 7 of 10

REACTOR COOLANT SYSTEM PRESSURE-TEMPERATURE LIMITS FOR INSERVICE LEAK HYDROSTATIC TESTS FOR FIRST 32 EFPY 3000 3600 oATA Po m s

4 ' 4 L '4"

' " " " "l ' ' *
  • Point Temp Press 3400,

. .j . , , , , , , ,

-- A 60 439 3200 -

3 c

140 439

j. - , -- .-

160 455 -

o 19 520 #

"!""' ~ " ~ ~ 4 + +"

  • 3000 _ -ro- 4 E 220 625 .;. , , ,

2800

-- F 263 956 G 300 1242 -, , . ,. , . . - . ,

_ 2600 -

u 340 1767 ,,

-f"

.9 I 370 2389 " ' i *

-M "P M " "4" "j"i" <' r '

[ 2400 J 395 3115 ,, , , , , _ , ,,

y 2200 --

g - .. . ,. 2 , -,

.pa.4.. $ NT ..;..j.. ,, , ,, ,..;..

tu ..n. ...:... . ..

[ 1600 . . . . -, , ..z.. .

o '

E 1200 T ' ~

w

^~ ~ "F ": ~ ~ ' '

1000 Specific Instrument Uncertainties 800

~! i .

+ ~

MUST be applied to this curve for

. . , s . _.; E. -. , ,,< ,., , operational use (see note 2) , ,

600 400

~~~ ~

~

- E ~ ~ ~

Al l-B

- ri C .: , ,

]-

, , ,, ,. . j .

...p ..F _

.4.. . . .

. .[

0 50 100 150 200 250 300 350 400 450 500 550 600 RCS TEMPERATURE (degF)

NOTES:

1. The regions of acceptable operation are below and to the right of the limit curve.
2. Margins are included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve. Additional margins for instrument uncertainty are not included and must be applied to operating procedures based on the specific instruments being used to monitor the RCS conditions.
3. Normal heatup and cooldown restrictions should be used with this curve as applicable.
4. This curve referred to by Technical Specification 3.4.3 Pfr LIMITS REPORT, Rev. 2 Page 8 of 10 i

r REACTOR COOLANT SYSTEM LOW-TEMPERATURE OVERPRESSURE PROTECTION L!MITS FOR FIRST 32 EFPY 1000 10 Minute Transient Analytical Limit

^ '^~"

, Poin,t Temp Press Point Temp Press " ' -

900 - A 60 300

- K 60 458

K ,

B 85 300 L 85 458  !" i * ' &

C 100 305 M 100 467

[::'

800 D 125 317 L N 125 487 ' ~

' " ___/ '. . , . .

E 150 334 o 150 517 L_

i - >

s

. I e - - . t P 180 364 P 100 567 '" * " "4" c 200 393 O 200 617 1 l 700- --

n 220 421 a 220 664 4

J R 2l"" -

j I 240 471 S 240 751 ,-'- Q g 600- -

J 263 551 i. T 263 888 i .. . .i .

-- P .;

..i..

, j;,

tu . . . . . . . .X. ,, , , . ,.

2: V.---.- '

p 500

' ^~ E ^

~ ~ ~

. a..

~

y{ ,

4 '

,  ; ..". I W.}. . ., ..O f' ? . .; . . ..i.. .....

"l 4 s ,. .y g '

K". -- .TL Q; . . 9 :: N.'"l" .

J. G,

~

-He -t +

A p 400 g - - . ~ -

p- ~

m ~~

y , , ,

. . l . . ' . . l. . ! "i" ..l.. ., ,

.4

..i..

~

E"'

' "~

300

'. -+-

. D T :f:::A': :B; .C:: ";" ~ .

Specific instrument Uncertainties . .: . .

. . - ,.4.. . ,

MUST be applied to this curve for .

200 -

. . r. .

, ..i...

4 operational use (see note 2)

' .:$:: i

..+..

' ~ ' '

.p.  ;

+

+. 4 )

7 -

q~ , 1 -t  ; , -t-

+

0 4 0 50 100 150 200 250 300 l i

RCS TEMPERATURE (degF)

NOTES:

1. The regions of acceptable operation are below and to the right of the limit curve.
2. Margins are included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve. Additional margins for instrument uncertainty are not included and must be applied to operating procedures and Technical Specification Limits based on the specific instruments being used to monitor the RCS conditions.
3. The LTOP curve applies to operation below the enable temperature of 263*F.
4. The LTOP 10 Minute Transient Curve is established based on at least 10 minutes of operation of the limiting transient without exceeding the LTOP Analytical Limits with an initial pressurizer level of 160 in.
5. The PORV setpoint is established to protect the LTOP Analytical Limit Curve. I
6. This curve referred to by Technical Specification 3.4.3.

P/T LIMITS REPORT, Rev. 2 Page 9 of 10 I

1

, REACTOR COOLANT SYSTEM COMPOSITE PRESSURE-TEMPERATURE LIMITS FOR FIRST 32 EFPY 2800 DATA POINTS - - * * - ** ** ' a -

  • 2600 .- Poirst Temp press -. "1~-

A a

60 85 300 300

. . . n . p .3 . .

^'

, .r. ' 4. . r , ,

,..... '!. .q.. ,, , ,

2400 -  ;

'O; d. .z C 100 305 . .. . ..;.. ,, ..

2200 -

g 33o 313 w F 187 355 -* -

2000 -

G 200 393  :-

H 220 421 ., , , , .. , ,

.5P 1800 __

1 240 471 E, J 263 551 K 263 692

, ..;..;.3..

.g , ,.;.

..g ,

@ 1600 -

L 300 909 M 325 1129

* ' '+ ' ' ' '

u) 1400 -

n 350 144e h o 309 2322 - - . - .

g 1200 -

M-

,o1000 E

L-}t-..

7.i . ., , ,, . ,, , , . ,

800 _

WH. . . Specific Instrument Uncertainties

' "" +

600 - - -

'T ' " + '

MUST be applied to this curve for [.

L.

t

.: G . ..

..j..

Operational use (see note 2) 400 = - - l l 3 p'~ ' ,

" ~^ "- '

A.i_. B _l cud ,E F '

200 ']

.[

l' . . . . ,.,

.. }.

0 '

0 50 100 150 200 250 300 350 400 450 500 550 600 .

RCS TEMPERATURE (degF) l NOTES:

1

1. The regions of acceptable operation are below and to the right of the limit curve.
2. Margins are included for the pressure differential between point of system pressure measurement and the pressure on the reactor vessel region controlling the limit curve. Additional margins fu j instrument uncertainty are not included and must be applied to operating procedures and Technical Specification Limits based on the specific instruments being used to monitor the RCS conditions.
3. Normal heatup, cooldown, and LTOP restrictions should be used with this curve as applicable. 1
4. The COMPOSITE curve applies to heatup, cooldown, ISLH, and LTOP.
5. . This curve envelopes the heatup, cooldown, ISLH, and LTOP curves referred to by Technical l Specification 3.4.3.

1 P/T LLMITS REPORT, Rev. 2 Page 10 of 10