Interim Deficiency Rept DER 84-27 Re Improperly Handled Instrumentation from Waldinger.Initially Reported on 840510. Due to Extensive Investigation & Evaluation Required,Final Rept Delayed Until 841207
ML20100M766
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 11/26/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-31219-TDS, DER-84-27, NUDOCS 8412120446
Download: ML20100M766 (2)


Text

.

. . . .w.

Arizona Nuclear Power Project P.O. box 52034 e PHOENIX, ARIZONA 28$07d5 ([h40E -3 M G 33 November 26, 1964 ANPP-312194DB/'IRBW U. S. Nuclear Regulatory Commissic,n Region V 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention: Mr. D. F. Kirsch, Acting Director Division of Reactor Safety and Projects

Subject:

Time Extension For Report - DER 84-27 A 50.55(e) Potentially Reportable Deficiency Relating To Improperly Handled Instrumentation from Waldinger.

File: 84-019-026; D.4.33.2

Reference:

A) Telephone Conversation between P. Narbut and T. Bradish on" May 10, 1984 B) ANPP-29648, dated June 4, 1984 (Interim Report)

C) ANPP-30317, dated August 23,1984 (Time Extension)

D) ANPP-30665, dated September 26, 1984 (Time Extension)

E) ANPP-30953, dated October 25,1984 (Time Extension)

F) ANPP-31095, dated November 12,1984 (Time Extension)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A), an Interim Report was transmitted by Reference (B),

and Time Extensions were requested by References (C), (D), (E), and (F).

At that time, it was estimated that a Final Report would be available by November 27, 1984.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by December 7, 1984, at which time a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly yours, \

")

8412120446 841126 2[.(C'i2rutcct u E. E. Van Brunt, Jr.

PDR ADOCK 05000528 APS Vice President O Nuclear Production ANPP Project Director EEVB/TRB/nj cc: See Page Two e i JE-21

, . .+..

i Mr. D. F. Kirsch DER 84-27

'Page Two cc: Richard DeYoung, Director Office of Laspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

D. B. Karner W. E. Ide D. B. Fasnacht A. C. Rogers L. A. Souza D. E. Fowler

, T. D. Shriver C. N. Russo B. S. Kaplan i

J. R. Bynum J. M. Allen A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher r H. D. Foster

! D. R. Hawkinson R. P. Zimmerman L. Clyde M. Matt T. J. Bloom Records Center Institute of Nuclear Power Operations

,e 1100 circle 75 Parkway, Suite 1500 Atlanta, GA 30339' l