Advises That in Future License Amend Applications,Util Will Request 90 Days for Implementation to Facilitate Training on New Amends During Normal Operator Requalification Schedule, in Ref to GLs 86-10 & 88-12 Re Fire Protection Requirements
ML20101D083
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 06/01/1992
From: Shelton D
CENTERIOR ENERGY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
2045, GL-86-10, GL-88-12, TAC-M82089, NUDOCS 9206110199
Download: ML20101D083 (2)


Text

._. . -. .- _- ~ _ . - . ~

s CENTEfMOR W -ENERCY

+.

Donald C. SheMon 300 Madison Amue Vee President Nuclear - Toledo, OH 436524001 De4skae (419)249 2300 Docket-Number 50-346 License Number FPF-3 Serial-Number 2045 June 1, 1992 United _ States Nuclear Regulatory Commission Document Control Desk

.Vashington, D.C. 20555

Subject:

Implementation _of License Amendment to Remove the Fire Protection Requirements per Generic Letter 86-10 and Generic Letter 88-12 Gentlemen:

By letter dated November 1, 1991 (Serial Number 1789), ToleJo Edison (TE) sunmitted an application for an amendment to the Davis-Besse Nuclear Power Station. (DBNPS), Unit Number 1, Operating License NPF-3, Appendix ~A, Technical Specifications to remove the Fire Protection ,

Requiremer's 1,er Generic Letter 86-10, " Implementation of Fire Protection Requirements", dated April 28, 1986, and Generic Letter 88-12, " Removal of Fire Protection Requirements from Technical Specifications",' dated August 2, 1988. -The NRC Staff is currently evaluating this request.

In its letter, TE requested a 60 day implementation period following-approval of the amendment by the NRC. -Toledo Edison hereby requests that this be changed to a 90 day implementation period doe to the need to allow the operating shifts sufficient time for training on the new amendment during the normal requalification cycle. Changing the implementation period does not affect any information contained in the Federal Register Notice (FR 64662, dated December 11, 1991) which provided opportunity for comment on TE's amendment application. ,

In future routine License Amendment applications, TE vill request 90 47ys for implementation in order to facilitate training on new amendments during the normal operator requalification schedule.

OSCC37 9206110199 920601

DR ADOCK 05000346 00[r, -

PDR_ i l' 0

. Operatang Comparwm {

Cleveiend Electne muminating Toleco Edison

-o Docket Number 50-346'

/  : License Number NPF-3.

Serial Number 2045-

,Page 2

'If you have a'ny-questions, please contact Mr. R. V. Schrauder, Manager - Nuclear Licensing, at (419) 249-2366.

Very t yours, KBR/dlm cci -A. B. Davis, Regional Administrator, NRC Region III J. B. Hopkins, NRC/NRR DB-1 Senior Project Manager '

V._ Levis, NRC Region III, DB-1 Senior Resident Inspector J. R. Villiams, Chief of Staff, Ohio Emergene, Management Agency, State of Ohio (NRC Liaison)

Utility Radiological S.fety Board i

-- ,.g+ , , , ,