Advises That Rev 1 to Final Steam Generator Repair Rept Does Not Clarify Util Intent to Store Discarded Sglas Onsite. Conference Call Suggested to Provide Status of Util Steam Generator Replacement Program.Related Correspondence
ML20073D726
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 04/12/1983
From: Matthews B
HARTSVILLE GROUP
To: Hetrick D, Kline J, Margulies M
Atomic Safety and Licensing Board Panel
References
ISSUANCES-OLA, NUDOCS 8304140163
Download: ML20073D726 (1)


Text

'tELirED CC;mFEPONDENCB THE HARTSVILLE GROUP P.O. Box 1089 Hartsville, South Carolina 29550 803/332-2727 803/332-2231

p r April 12, 1983 Administrative Judge Morton B.gjarg?M P1 :06 Chairman, Atomic Safety and Licensing Toard U.S. Nuclear Regulatory Commission Washington, D.C. 20555 6

,.m

. . ; 4 x. : .

EUNCH Administrative Judge Jerry R. Kline Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Administrative Judge David L. Hetrick Department of Nuclear Engineering University of Arizona Tucson, Arizona 85721 Re: Carolina Power & Light Company (H.B. Robinson Steam Electric Plant, Unit 2)

Docket No. 50 - 261 01A

Dear Judges:

The Hartsville Group has received a copy of Revision 1 to the Final Steam Generator Ryair Report which, during the Prehearing Conference held on March 24, 1983, Counsel for the Applicant had said would be forthcoming. Counsel had informed this party previously and informed the Board at that point that Revision 1 would make clear the Applicant's intent to store the discarded SGLAs on site. This revision does not accomplish that.

However, it does address a number of other matters. Significantly, we find for the first time that sleeving of the degraded steam generator tubes "is currently a viable alternative to the repair" (FSGRR, Rev. 1, p. 97a) and that it " continues to be considered" (FSGRR, Rev. 1, p. 97).

The Hartsville Group believes that it may be an appropriate time for a conference call so that Carolina Power & Light Company can provide a status report to the Board, parties and petitioners on their steam generator replace-ment program. By this revision, does the Applicant intend to amend its License  :

Amendment Application to allow for sleeving of the steam generator tubes?

Thank you for your consideration of this matter.

Sincerely yours l

B. A. Matthews i Authorized Representative l The Hartsville Group F304140163 830412 PDR ADDCK 05000261 O PDR cc: Parties of Becord