July 2003 Monthly Operating Report for Lasalle County Station, Units 1 & 2
ML032380664
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 08/14/2003
From: Kaegi G
Exelon Generation Co, Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML032380664 (7)


Text

ExeI o nsm Exelon Generation Company, LLC LaSalle County Station www.exeloncorp.conm Nudear 2601 North 21" Road Marseilles, IL 61341-9757 August 14, 2003 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-1 I and NPF-1 8 NRC Docket Nos. 50-373 and 50-374

Subject:

Monthly Operating Report for July 2003 Enclosed is the Exelon Generation Company (EGC), LLC, Monthly Operating Report for LaSalle County Station covering the period from July 1 through July 31, 2003. This report is submitted in accordance with Technical Specification 5.6.4.

Should you have any questions concerning this letter, please contact Mr. Glen T. Kaegi, Regulatory Assurance Manager, at (815) 415-2800.

Respectfully, Glen T. Kaegi Regulatory Assurance Manager LaSalle County Station Enclosure cc: Regional Administrator - NRC Region IlIl NRC Senior Resident Inspector - LaSalle County Station A_

'.3"' e43

LASALLE COUNTY STATION UNIT 1 AND UNIT 2 MONTHLY PERFORMANCE REPORT EXELON GENERATION COMPANY NRC DOCKET NO. 50-373 NRC DOCKET NO. 50-374 LICENSE NO. NPF- 1I LICENSE NO. NPF-18

TABLE OF CONTENTS Monthly Report for LaSalle Unit One A. Operating Data Summary B. Unit Shutdowns and Operating Summary C. Unique Reporting Requirements Monthly Report for LaSalle Unit Two A. Operating Data Summary B. Unit Shutdowns and Operating Summary C. Unique Reporting Requirements

Monthly Report for LaSalle County Station Unit One-July 2003 A. OPERATING DATA

SUMMARY

FOR UNIT ONE DOCKET NO.: 50-373 UNIT: LaSalle One DATE: August 6, 2003 COMPLETED BY: S. Du Pont TELEPHONE: (815) 415-2197

1. Reporting Period: July 2003 Gross Hours: 744.0
2. Currently Authorized Power Level: 3489 (MWt)

Design Electrical Rating: 1154 (MWe-net)

Max Dependable Capacity: 1111 (MWe-net)

3. Power Level To Which Restricted (If Any): None
4. Reasons For Restriction (If Any): NIA l THIS MONTH YEAR-TO-DATE CUMULATIVE
5. Reactor Critical Hours 744.0 5087.0 120732.2
6. Reactor Reserve 0.0 0.0 1641.2 Shutdown Hours
7. Hours Generator 744.0 5087.0 118503.9 On-Line
8. Unit Reserve 0.0 0.0 1.0 Shutdown Hours
9. Gross Thermal 2592762.0 17036503.1 366842674.7 Energy (MWHt) _
10. Gross Electric Energy 867524.0 5789775.0 123238807.0 (MWHe)
11. Net Electrical Energy 842684.0 5683460.0 119226621.0 (MWHe)
12. Reactor Service 100.0 100.0 70.3 Factor (%)
13. ReactorAvailability 100.0 100.0 71.3 Factor (%)
14. Unit Service Factor 100.0 100.0 69.0
15. Unit Availability 100.0 100.0 69.0 Factor__ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _
16. Unit Capacity Factor 101.9 100.6 64.8 (M DC) _ _ _ _ _ _ _ _ _ _ _ _
17. Unit Capacity Factor 98.1 96.8 62.3 (design MWe) _
18. Unit Forced Outage 0.0 0.0 10.1 Factor (%) I
19. Shutdowns Scheduled Over Next 6 Months: Refueling outage (L1 R10) scheduled to start on January 13, 2004
20. If Shutdown at End of Report Period, Date of Startup: N/A

B. UNIT SHUTDOWNS AND OPERATING

SUMMARY

REPORT MONTH JULY 2003 NO DATE TYPE (1) DURATION REASON (2) METHOD OF CORRECTIVE (HOURS)* SHUTTING ACTIONS/

DOWN COMMENTS None No n e REACTOR (3)

_ _ _ _ _ _ _ _ _ t_ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ I__

  • Year-to-date forced outage hours = 0.0 Cumulative forced outage hours = 13336.6 TABLE KEY:

(1) (3)

F: Forced Method:

S: Scheduled 1. Manual

2. Manual Scram (2) 3. Automatic Scram Reason: 4. Continuation A Equipment Failure (Explain) 5. Other (Explain)

B Maintenance or Test C Refueling D Regulatory Restriction E Operator / Licensing Exam F Administrative G Operational Error (Explain)

H Other (Explain)

SUMMARY

LaSalle Unit 1 operated at full power for the month of July 2003, with the exception of the following:

  • July 7 (2319) - Power was reduced to 1060 MWe to stabilize the electrical grid affected by the Unit 2 automatic scram. The grid was stabilized and the unit returned to full power 0937 hrs on July 8, 2003.

C. UNIQUE REPORTING REQUIREMENTS FOR UNIT ONE

1. Challenges other than routine surveillance testing to Safety/Relief Valve Operations-None
2. Major Changes to Radioactive Waste Treatment System-None

Monthly Report for LaSalle County Station Unit Two-July 2003 A. OPERATING DATA

SUMMARY

FOR UNIT TWO DOCKET NO.: 50-374 UNIT: LaSalle Two DATE: August 6, 2003 COMPLETED BY: S. Du Pont TELEPHONE: (815) 415-2197

1. Reporting Period: July 2003 Gross Hours: 744.0
2. Currently Authorized Power Level: 3489 (MWt)

Design Electrical Rating: 1154 (MWe-net)

Max Dependable Capacity: 1111 (MWe-net)

3. Power Level To Which Restricted (If Any): None
4. Reasons For Restriction (If Any): N/A THIS MONTH YEAR-TO-DATE CUMULATIVE
5. Reactor Critical Hours 647.4 4213.7 112250.3
6. Reactor Reserve 0.0 0.0 1716.9 Shutdown Hours
7. Hours Generator On- 629.6 4129.1 111158.5 Une _ _ _ _ _ _ _
8. Unit Reserve 0.0 0.0 0.0 Shutdown Hours
9. Gross Thermal 2083960.1 13797497.4 348455352.4 Energy (MWHt) ._ .
10. Gross Electric Energy 700144.0 4695783.0 117264045.0 (MWHe)
11. Net Electrical Energy 678008.0 4588675.0 112914116.0 (MWHe) .
12. Reactor Service 87.0 82.8 68.2 Factor (%) ___
13. Reactor Availability 87.0 82.8 69.2 Factor (%)
14. Unit Service Factor 84.6 81.2 67.5
15. Unit Availability 84.6 81.2 67.5 Factor _ _ _ _ _ _ _ _ _
16. Unit Capacity Factor 82.0 81.2 64.4

, MDC _ _ _ __ _ _

17. Unit Capacity Factor 79.0 78.2 61.9 (design MWe)
18. Unit Forced Outage 15.4 4.7 14.9 Factor (%) I
19. Shutdowns Scheduled Over Next 6 Months: None
20. If Shutdown at End of Report Period, Date of Startup: N/A

B. UNIT SHUTDOWNS AND OPERATING

SUMMARY

REPORT MONTH JULY 2003 NO DATE TYPE DURATION REASON (2) METHOD CORRECTIVE (1) (HOURS)* OF ACTIONS/

SHUTTING COMMENTS DOWN

- REACTOR L2F37 07/07/03 F 114.5 A - failure of the 3 Main transformer B-main transformer B- Phase disconnect Phase disconnect repaired.

  • Year-to-date forced outage hours = 202.5 Cumulative forced outage hours = 19444.7 TABLE KEY:

(1) (3)

F: Forced Method:

S: Scheduled 1. Manual

2. Manual Scram (2) 3. Automatic Scram Reason: 4. Continuation A Equipment Failure (Explain) 5. Other (Explain)

B Maintenance or Test C Refueling D Regulatory Restriction E Operator / Licensing Exam F Administrative G Operational Error (Explain)

H Other (Explain)

SUMMARY

LaSalle Unit 2 operated at full power for the month of July 2003, with the exception of the following:

  • July 7 (2319) - Shutdown due to an automatic scram caused by the failure of the main power transformer B-Phase disconnect. The affected disconnect was repaired. During the outage, a leaking safety relief valve was replaced. The unit was returned to service 1745 hrs on July 12 and returned to full power 0552 hrs on July 16, 2003.

C. UNIQUE REPORTING REQUIREMENTS FOR UNIT TWO

1. Challenges other than routine surveillance testing to Safety/Relief Valve Operations- Due to the loss of the condenser during the July 7 trip, the SRVs were challenged and operated.
2. Major Changes to Radioactive Waste Treatment Systems-None