|
---|
Category:Inspection Plan
MONTHYEARIR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) IR 05000263/20220062023-03-0101 March 2023 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2022006) ML23058A1522023-02-27027 February 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2023002 IR 05000263/20220052022-08-29029 August 2022 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2022005) IR 05000263/20210062022-03-0202 March 2022 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2021006) ML21322A2362021-11-18018 November 2021 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2022401 IR 05000263/20210052021-09-0101 September 2021 Updated Inspection Plan for Monticello Nuclear Generating Plant 2 (Report 05000263/2021005) ML21215A2172021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21147A5082021-06-0303 June 2021 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21099A0902021-04-0808 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000263/2021011 ML21085A8582021-03-26026 March 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000263/2021010 IR 05000263/20200062021-03-0404 March 2021 Annual Assessment Letter for the Monticello Nuclear Generating Plant (Report 05000263/2020006) ML21029A2982021-01-29029 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2021002 ML20275A3942020-10-0101 October 2020 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at the Monticello Nuclear Generating Plant IR 05000263/20200052020-09-0101 September 2020 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2020005) ML20134H9282020-05-12012 May 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000263/2020013 IR 05000263/20190062020-03-0303 March 2020 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2019006 and 07200058/2019006) ML19324F8512019-11-20020 November 2019 Long-Term Replacement Steam Dryer Inspection Plan ML19322C0512019-11-14014 November 2019 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report Number 05000263/2020011 IR 05000263/20190052019-08-28028 August 2019 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2019005) ML19136A0202019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19065A0832019-03-0505 March 2019 Ltr. 03/05/19 Monticello Nuclear Generating Plant - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2019002 (DRS-E.Fernandez) IR 05000263/20180062019-03-0404 March 2019 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2018006 and 07200058/2018006) IR 05000263/20180052018-08-28028 August 2018 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2018005) IR 05000263/20170062018-03-0202 March 2018 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2017006) ML17345A8402017-12-11011 December 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Monticello Nuclear Generating Plant IR 05000263/20170052017-08-28028 August 2017 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2017005) ML17159A6992017-06-0808 June 2017 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2017409 ML17094A4352017-04-0303 April 2017 Monticello - Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000263/20160062017-03-0101 March 2017 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2016006) ML17026A4302017-01-26026 January 2017 Notification of NRC Triennial Fire Protection Baseline Inspection and Request for Information 05000263/2017007 IR 05000263/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2016005) IR 05000263/20150062016-03-0202 March 2016 Annual Assessment Letter for Monticello Nuclear Generating Plant (Inspection Report 05000263/2015006) ML16041A0482016-02-0909 February 2016 Ltr. 02/09/16 Monticello Nuclear Generating Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000263/2016002 IR 05000263/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2015005) IR 05000263/20140012015-03-0404 March 2015 Annual Assessment Letter for the Monticello Nuclear Generating Plant, (Report 05000263/2014001) ML15027A0412015-01-26026 January 2015 ISI Request for Information ML14245A1442014-09-0202 September 2014 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant ML14216A5132014-08-0404 August 2014 Information Request to Support Upcoming Biennial Problem Identification and Resolution Inspection at the Monticello Nuclear Generating Plant IR 05000263/20130012014-03-0404 March 2014 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2013001) ML13246A2312013-09-0303 September 2013 2013 Monticello MOC Letter Combined ML13221A5712013-08-0909 August 2013 Ltr 8/9/13 Monticello MOD 50.59 Request for Information IR 05000263/20120012013-03-0404 March 2013 Annual Assessment Letter for Monticello Nuclear Generating Plant, (Report 05000263-12-001) ML12249A4222012-09-0404 September 2012 Mid-Cycle Assessment Letter for Monticello Generating Plant IR 05000263/20110072012-03-0505 March 2012 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2011007) IR 05000263/20110062011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plant for Monticello Nuclear Plant 05000263-11-006 IR 05000263/20110012011-03-0404 March 2011 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263-11-001) ML1104705722011-02-16016 February 2011 Request Notification of NRC Inspection and Request for Information ISI ML1024400642010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Monticello Nuclear Generating Plant IR 05000263/20100012010-03-0303 March 2010 Monticello Nuclear Generating Plant EOC Annual Assessment Letter (Report 05000263-10-001) 2023-08-30
[Table view] Category:Letter
MONTHYEARML24025A9362024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0055 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000263/20230042024-01-31031 January 2024 Integrated Inspection Report 05000263/2023004 ML24024A0722024-01-24024 January 2024 Independent Spent Fuel Storage Installation, Onticello, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000263/20244012024-01-22022 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2024401 L-MT-23-054, Subsequent License Renewal Application Supplement 82024-01-11011 January 2024 Subsequent License Renewal Application Supplement 8 L-MT-23-047, License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data2023-12-29029 December 2023 License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data L-MT-23-056, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 22023-12-18018 December 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 2 ML23349A0572023-12-15015 December 2023 and Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota IR 05000263/20234022023-12-13013 December 2023 Security Baseline Inspection Report 05000263/2023402 L-MT-23-042, 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462023-12-11011 December 2023 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-23-052, Subsequent License Renewal Application Supplement 72023-11-30030 November 2023 Subsequent License Renewal Application Supplement 7 L-MT-23-051, Update to the Technical Specification Bases2023-11-28028 November 2023 Update to the Technical Specification Bases L-MT-23-049, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 12023-11-21021 November 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 ML23319A3182023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000263/20230032023-11-13013 November 2023 Integrated Inspection Report 05000263/2023003 and 07200058/2023001 L-MT-23-043, 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-092023-11-13013 November 2023 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-09 L-MT-23-038, License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.62023-11-10010 November 2023 License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 L-MT-23-046, Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 12023-11-0909 November 2023 Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 ML23291A1102023-10-23023 October 2023 Environmental Audit Summary and RCIs and RAIs ML23285A3062023-10-12012 October 2023 Implementation of the Fleet Standard Emergency Plan for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant L-MT-23-041, Subsequent License Renewal Application Response to Request for Confirmation of Information Set 22023-10-0303 October 2023 Subsequent License Renewal Application Response to Request for Confirmation of Information Set 2 L-MT-23-037, Subsequent License Renewal Application Response to Request for Additional Information Set 32023-09-22022 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 3 ML23262B0372023-09-19019 September 2023 Response to NRC Request for Additional Information Regarding the 2023 Monticello and Prairie Island Plant Decommissioning Funding Status Reports ML23248A2092023-09-18018 September 2023 Proposed Alternative VR-11 to the Requirements of the ASME OM Code Associated with Periodic Verification Testing of MO-2397, Reactor Water Cleanup Inboard Isolation Valve ML23256A1682023-09-13013 September 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Voluntary Security Clearance Program 2023 Insider Threat Program Self-Inspection IR 05000263/20230102023-09-0707 September 2023 Commercial Grade Dedication Inspection Report 05000263/2023010 L-MT-23-036, Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 62023-09-0505 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 6 ML23214A2412023-08-31031 August 2023 Letter: Aging Management Audit - Monticello Unit 1 - Subsequent License Renewal Application IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) L-MT-23-035, Subsequent License Renewal Application Supplement 52023-08-28028 August 2023 Subsequent License Renewal Application Supplement 5 ML23241A9732023-08-21021 August 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application (Docket No. 50-263) L-MT-23-034, Subsequent License Renewal Application Response to Request for Additional Information Set 12023-08-15015 August 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 1 ML23222A0122023-08-10010 August 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Changes in Foreign Ownership, Control or Influence ML23215A1312023-08-0909 August 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application IR 05000263/20230022023-08-0707 August 2023 Plantintegrated Inspection Report 05000263/2023002 L-MT-23-028, 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report2023-07-31031 July 2023 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report L-MT-23-032, 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-112023-07-31031 July 2023 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-11 ML23198A0412023-07-28028 July 2023 LRA Availability Letter ML23206A2342023-07-25025 July 2023 Independent Spent Fuel Storage Installation, and Monticello Nuclear Generating Plant, Changes in Foreign Ownership, Control or Influence ML23201A0352023-07-24024 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23202A0032023-07-21021 July 2023 Independent Spent Fuel and Independent Spent Fuel Storage Installation, Monticello Nuclear Generating Plant, Submittal of Quality Assurance Topical Report (NSPM-1) L-MT-23-031, Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 12023-07-18018 July 2023 Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 1 ML23195A1732023-07-14014 July 2023 Revision of Standard Practice Procedures Plan IR 05000263/20235012023-07-13013 July 2023 Emergency Preparedness Inspection Report 05000263/2023501 2024-01-31
[Table view] |
Text
Northern States Power Company 3-May-2004 Monticello Nuclear Generating Plant Page 1 Document Control Distribution System Document Distribution Manifest Controlled Documents - Current Name: US NRC Manifest Number: 2004-321 Date Mailed:
Title:
ATTN: DOCUMENT CONTROL DESK Distribution Type: I Company: MONTI LICENSING Holder Number: 195 Location: ATTN:DOUG NEVE ID Number: YYYY09 MNGP-SAB/2ND FLOOR (1 CD)
Distribution Type: INSERVICE INSPECTION Document Type Document Number Revision Title NOTE: The documents listed below are new or revised 1991 ISI 1 INSERVICE INSPECTION EXAMINATION PLAN 4TH INTERVAL EFFECTIVE 05/01/03 9-
Nu Ce Commiffed to Nudlear Exce Ionticello Nuclear Generating Plant
,ated by Nuclear Management Company, LLC April 28, 2004 To: Holders of the Monticello 4 th Interval ISI Plan
SUBJECT:
Letter of Correction to Monticello 4 th Interval ISI Plan, Revision 1, 1117/2003 Revision 1 of the Monticello 4th Interval ISI Plan was distributed on 1/17/2003. During a self-assessment, it was discovered that an editorial error was present on page 1.2-1. This assessment finding was entered into our Corrective Action Program as Condition Report 03004203.
The noted error, located in the first paragraph (Background), referenced a non-existent paragraph of 10CFR50.55a. In addition, the same sentence was also noted as being somewhat confusing in its intent.
The sentence In error reads as follows:
The Repair/Replacement Program and Containment Inspection Program (as allowed by 10CFR55a(g)(6)(ii)(B)(5!) are maintained separately from this program and, although they are not submitted, they are available at the plant site for audit and review.
This sentence has been corrected and restructured for clarification to the following:
The Containment Inspection Program, as allowed by 10CFR55a(g)(6)(ii)(B), and the Repair/Replacement Program are maintained separately from this program, and, although they are not submitted, they are available at the plant site for audit and review.
The change is noted on the attached, corrected page with double sidebars in the right hand margin.
Please remove page 1.2-1 from your copy of the Monticello Section Xi ISI Plan, Revision 1 and replace it with the attached, corrected page.
Sincerely, Richard A. Deopere Section Xi ISI Coordinator Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 . Monticello, Minnesota 55362-9637 Telephone: 763.295.5151
ANAEMEN NUCLAR COPAN NUCLEAR MANAGEMENT COMPANY INSERVICE INSPECTION MONTICELLO 4th INTERVAL EXAMINATION PLAN INTRODUCTION
Background:
The American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (BPV) Code (hereafter referred to as ASME Section Xl, Section Xl, or the Code), Section Xl Inservice Inspection (ISI) Program is prepared and maintained by the Nuclear Management Company (NMC). The Inservice Testing Program (IST) is maintained separately from this program and is submitted under separate cover. The Containment Inspection Program, as allowed by 10CFR55a(g)(6)(ii)(B), and the Repair/Replacement Program are maintained separately from this program, and, although they are not submitted, they are available at the plant site for audit and review.
4th Ten-Year Interval: The Monticello 4th Ten-Year Inservice Inspection Interval is slightly less than 120 months due to an extension of the 3rd Interval (Letters to the NRC in May 2002 and January 2003 providing notification of 3rd Interval extension initially through March 8, 2003 (M2002057) and subsequently May 31, 2003 (no number yet assigned)). The 4th Interval will overlap the 3rd Interval as permitted by IWA-2430(d)(1),(2),(3), and (4) The 4th Interval begins May 1,2003 and ends May 31, 2012. Six refueling and maintenance outages are currently scheduled in this time frame.
Component Selection: With the exception of Class 1 and 2 piping welds, components within the examination plan were selected and scheduled using criteria in the 1995 Edition of ASME Section XI with the1996 Addenda (Inspection Program B) and 10CFR50.55a(g)(6)(ii)(A), except where relief has been requested. Per 10CFR50.55a(b)(2)(xi), the requirements of IWB-1220 in the 1989 Edition of ASME Section Xl, "Components Exempt from Examination,"
shall be used for Class 1 piping instead of the 1995 Edition of ASME Section XI with 1996 Addenda. Per 10CFR50.55a(b)(2)(xxi)(B) reused CRD Bolting must meet examination requirements for Table IWB-2500-1, Category B-G-2, Item B7.80 of ASME Section Xl 1995 Edition with 1995 Addenda.
Selection of Class 1 and Class 2 piping welds in ASME Categories B-F, B-J, C-F-1 and C-F-2 are based on EPRI Topical Report 112657 Rev. B-A. "Revised Risk Informed Inservice Inspection Evaluation Procedure." The Risk Informed Class I and Class 2 application was also conducted in a manner consistent with ASME Code Case N-578 "Risk Informed Requirements for Class 1,2, and 3 Piping, Method B." The use of the RI-ISI program was approved for use on July 27, 2002. (reference TAC MB3819 and Relief Request #1 for 4th ISI Interval)
Page 12-1 Cofreced on 41282004 1.2-1 Revision 1 See double sidebars 1/17/2003